CN109184259B - Sliding construction technology for building - Google Patents

Sliding construction technology for building Download PDF

Info

Publication number
CN109184259B
CN109184259B CN201811322904.0A CN201811322904A CN109184259B CN 109184259 B CN109184259 B CN 109184259B CN 201811322904 A CN201811322904 A CN 201811322904A CN 109184259 B CN109184259 B CN 109184259B
Authority
CN
China
Prior art keywords
sliding
sliding beam
traction
frame column
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811322904.0A
Other languages
Chinese (zh)
Other versions
CN109184259A (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia Kunsheng Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811322904.0A priority Critical patent/CN109184259B/en
Publication of CN109184259A publication Critical patent/CN109184259A/en
Application granted granted Critical
Publication of CN109184259B publication Critical patent/CN109184259B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

本发明公开了一种建筑物的滑移施工方法,其特征是施工步骤包括:(1)凿除框架柱1/5截面作为与滑移梁的连接部分;(2)将滑移梁部位的砖墙凿除,支设模板;(3)支设滑移梁钢筋;(4)浇筑滑移梁混凝土;(5)用风割机割除框架柱与筏板的联接钢筋及破除联接部分的混凝土;(6)将木拉梁与滑移梁的预埋螺钉联接;(7)浇筑滑移梁就位部位的新基础;(8)在筏板朝向牵拉方向埋设牵引钢吊环,施工反力桩,安装反力设施和千斤顶;(9)在滑移方向铺设滑移铁轨,新基础上面也铺设滑移铁轨;(10)采用牵引设施进行牵引;(11)将滑移梁与新基础进行联接、框架柱与新基础进行联接。

Figure 201811322904

The invention discloses a sliding construction method for a building, which is characterized in that the construction steps include: (1) cutting out 1/5 of the cross-section of a frame column as a connection part with the sliding beam; (2) cutting the part of the sliding beam part Chisel out the brick wall and set up the formwork; (3) Support the sliding beam steel bar; (4) Pour the sliding beam concrete; (5) Use the wind cutter to cut off the connecting steel bar between the frame column and the raft and break the concrete of the connecting part ; (6) Connect the pre-embedded screws of the wooden tension beam and the sliding beam; (7) Pouring a new foundation for the position of the sliding beam; (8) Embed the traction steel lifting ring on the raft towards the pulling direction, and the construction reaction force Pile, install reaction force facilities and jacks; (9) Lay sliding rails in the sliding direction, and also lay sliding rails on the new foundation; (10) Use traction facilities for traction; (11) Connect the sliding beams to the new foundation Connections, frame columns and new foundations are connected.

Figure 201811322904

Description

Sliding construction technology for building
Technical Field
The invention relates to sliding construction, in particular to a sliding construction method of a building.
Background
As city construction is being conducted vigorously, since urban planning and town road construction require removal of buildings, demolition of buildings directly causes a large amount of construction waste, and causes pollution. Especially the historical protection of buildings in normal use, it would be a significant loss to remove them. For some buildings with complete structures and still having use values, secondary repeated design and construction are avoided by adopting a building sliding technology, the buildings can be immediately put into use after sliding in place, and obvious economic and social benefits are obviously achieved. However, how to ensure the safety of the building in the sliding process, how to make the connection between the building and a new foundation, and how to reduce the cost on the premise of ensuring the safety.
Disclosure of Invention
The invention provides a sliding construction method of a building, which solves the problems of unsafe sliding construction and high cost of the building.
The upper surface of the raft is provided with the sliding beams, the distance between every two adjacent sliding beams is 3-3.6 m, the distance between the bottom of each sliding beam and the top of the raft is 60-80 mm, the height of each sliding beam is determined according to the upper load, and when the number of building layers is 5, the height of each sliding beam is 800 mm; when the number of the building layers is 4, the height of the sliding beam is 750 mm; when the number of the building layers is 3, the height of the sliding beam is 700 mm; when the number of the building layers is 2, the height of the sliding beam is 650 mm; when the number of the building layers is 1, the height of the sliding beam is 600 mm.
The width of the sliding beam is 300 mm. And a steel ball is arranged below the sliding beam, and the diameter of the steel ball is 60-80 mm.
In order to avoid local damage of the sliding beams in the sliding process, a wood tie beam is arranged between every two adjacent sliding beams to increase the overall rigidity, the diameter of each wood tie beam is 150-180 mm, and the included angle between each wood tie beam and each sliding beam is 45-60 degrees.
The right side of the position where the traction building is in place is provided with a reaction pile as a reaction facility, the distance between the reaction pile and the position where the traction building is in place is 0.6-0.8 m so as to provide an operation space, the reaction pile adopts a precast tubular pile, and the diameter of the precast tubular pile is 500-600 mm. The initial friction force of the counter-force pile is much larger than that of the counter-force pile during traction movement when the building is dragged, according to a large number of detection results, the initial friction force coefficient of the counter-force pile during traction movement is 0.15-0.2, the dynamic friction coefficient of the counter-force pile during traction movement is 0.017-0.025, in order to save cost, the counter-force pile and the engineering pile are jointly used as a counter-force support during initial traction movement, and only the counter-force pile is used as the counter-force support during traction movement.
The building can vibrate to a certain extent in the walking process, and if the surrounding environment has high requirements on vibration reduction, the purpose of vibration reduction can be achieved by taking technical measures. The damping steel blocks are arranged at intervals of 2-3 m at the lower part of the sliding rail, springs are installed in the damping steel blocks, the sliding rail is enabled to be the same as a spring body, when steel balls located in the range of the sliding rail body meet advancing resistance, impact force can be relieved under the action of the springs in the damping steel blocks, vibration energy is directly attracted by the springs in the damping steel blocks, and the steel balls meeting the resistance are prevented from bearing overlarge pressure and impact force.
The construction steps comprise:
(1) in order to integrate the sliding beam with the frame column, the section of the frame column 1/5 is chiseled out as a connecting part with the sliding beam; temporary supports are provided adjacent the frame posts.
(2) Chiseling off the brick wall at the position of the sliding beam, erecting a template, arranging a pouring hole and a tamping hole at the upper part of the lateral template, wherein the diameter of the pouring hole is 40-50 mm, and the arrangement interval of the pouring holes is 1.2-1.5 m; the diameter of each vibrating hole is 20-30 mm, and the distance between every two vibrating holes is 0.7-0.9 m; placing the steel ball bottom the template when setting up the template, steel ball embedding lower bolster, steel ball top is the same with lower bolster top elevation, has the bearing in the middle of the steel ball, and the bearing stretches into the template, and the bearing stretches into length and is 120 ~ 150 mm.
(3) And erecting a sliding beam reinforcing steel bar, wherein a main rib of the sliding beam extends into the chiseling part of the frame column and is bent upwards or downwards to increase the anchoring length, and the anchoring length is 500-700 mm.
(4) And pouring concrete of the sliding beam, then pouring concrete at chiseling-out parts of the frame columns, and pouring the concrete by adopting a high-pressure pump.
(5) And after the concrete strength of the sliding beam reaches the designed strength, cutting off the connecting reinforcing steel bars of the frame column and the raft and breaking off the concrete of the connecting part by using a wind cutting machine, so that the elevation of the bottom of the frame column is the same as the elevation of the bottom of the sliding beam.
(6) And connecting the wood tie beam with the embedded screws of the sliding beam.
(7) And pouring a new foundation of the in-place part of the sliding beam.
(8) And embedding a traction steel hanging ring in the raft towards the traction direction, constructing a counter-force pile, and installing a counter-force facility and a jack.
(9) And laying a slipping rail in the slipping direction, and laying the slipping rail on the new foundation.
(10) Traction is carried out by adopting a traction facility.
The traction facility adopts an automatic control hydraulic synchronous system, the automatic control hydraulic synchronous system consists of a hydraulic system, a detection sensor and a computer control system, wherein the hydraulic system comprises an oil pump and a hydraulic jack. The hydraulic system is controlled by a computer, fully automatically completes synchronous displacement, and realizes the functions of force and displacement control, operation locking and process display. The working pressure of the hydraulic system is 30-32 MPa, and the peak pressure is 35 MPa. The pushing stroke of the pushing cylinders is 1200mm, the pushing control speed is 0-60 mm/min, the pushing cylinders in the group are communicated in pressure, the positions of the groups are synchronously controlled, and the synchronous precision is +/-lmm.
(11) And connecting the sliding beam with the new foundation and connecting the frame column with the new foundation.
After the sliding beam is in place, two treatment modes can be provided, namely, the steel ball is cut by wind after the sliding beam is jacked, the sliding rail is removed, and then the sliding beam is lowered to connect the sliding beam with a new foundation. The risk of this process is that local structural damage is likely to occur due to uneven handling during the jacking of the skidding beam.
If the building structure performance is not good, the sliding rail is welded with the new foundation steel bar, and the steel ball is firmly welded with the sliding rail after the sliding rail slides in place, so that the steel ball cannot roll and translate under the action of external load later. And (3) pouring and compacting the gap between the sliding rail and the steel ball by using high-strength micro-expansion fine stone concrete, and pouring the steel ball into the high-strength micro-expansion fine stone concrete. By adopting the measures, the reliable connection of the upper structure and the new foundation is ensured, and when the sliding rail is subjected to the action of strong earthquake load, the post-cast filling fine aggregate concrete of the sliding rail and the steel ball are subjected to mutual friction extrusion deformation, so that partial earthquake energy can be absorbed, the action of the earthquake on the upper structure is reduced, and a certain earthquake isolation effect can be realized.
The frame column is connected with the new foundation by adopting fine aggregate concrete grouting, and the grouting process ensures that the vertical displacement of the column is zero after the column is in place and connected. The pulp squeezing adopts dry and hard fine stone concrete, and the dry and hard degree is qualified by being kneaded into a ball by hand and scattered when falling to the ground. And during the squeezing, two opposite side surfaces of the frame column are clamped tightly by a mold clamp, and the hard concrete is squeezed into the frame column from the other two surfaces.
The invention has good safety performance and low construction cost.
Drawings
Fig. 1, a schematic diagram of a sliding structure, fig. 2, a schematic diagram of a template support, fig. 3, a schematic diagram of a sliding plane, and fig. 4, a schematic diagram of a vibration reduction steel block.
In the drawings: 1. the device comprises a sliding beam, 2 frame columns, 3 raft plates, 4 steel balls, 5 sliding beam main ribs, 6 templates, 7 wood tie beams, 8 damping steel blocks, 9 springs.
Detailed Description
Example one
In the embodiment, the sliding beams 1 are arranged on the raft 3, the distance between every two adjacent sliding beams 1 is 3.2m, the distance between the bottom of each sliding beam 1 and the top of the raft 3 is 70mm, and the height of each sliding beam 1 is 750 mm. The width of the sliding beam 1 is 300 mm. And a steel ball 4 is arranged below the sliding beam 1, and the diameter of the steel ball 4 is 70 mm.
And a wood tie beam 7 is arranged between the adjacent sliding beams 1, the diameter of the wood tie beam 7 is 160mm, and the included angle between the wood tie beam 7 and the sliding beam 1 is 60 degrees.
The right side of the position of the traction building in place is provided with a reaction pile as a reaction facility, the distance between the reaction pile and the position of the traction building in place is 0.7m, the reaction pile is a prefabricated pipe pile, and the diameter of the prefabricated pipe pile is 500 mm. The combined reaction pile and engineering pile are used as reaction support during initial traction, and the reaction pile is only used as reaction support during traction movement.
Damping steel blocks 8 are arranged at intervals of 2-3 m at the lower part of the sliding rail, springs 9 are arranged in the damping steel blocks 8, the sliding rail is made to be like a spring body, and when the steel balls 4 located in the range of the sliding rail body meet advancing resistance, impact force can be relieved under the action of the springs 9 in the damping steel blocks 8.
The construction steps comprise:
(1) chiseling the section of the frame column 1/5 to be used as a connecting part with the sliding beam 1; temporary supports are provided near the frame posts 2.
(2) Chiseling off the brick wall at the position of the sliding beam 1, supporting a template 6, arranging pouring holes and vibrating holes at the upper part of the lateral template 6, wherein the diameter of each pouring hole is 40mm, and the arrangement interval of the pouring holes is 1.3 m; the diameter of each vibrating hole is 25mm, and the distance between every two vibrating holes is 0.8 m; when erecting template 6, place steel ball 4 in 6 bottoms of template, steel ball 4 embedding lower bolster 6, steel ball 4 tops are the same with 6 top elevations of lower bolster, have the bearing in the middle of the steel ball 4, and the bearing stretches into template 6, and the bearing stretches into length and is 130 mm.
(3) The steel bar of the sliding beam 1 is erected, the main steel bar 5 of the sliding beam extends into the chiseled part of the frame column 2 and is bent upwards or downwards to increase the anchoring length, and the anchoring length is 600 mm.
(4) And pouring concrete of the sliding beam 1, then pouring concrete of chiseling parts of the frame columns 2, and pouring the concrete by adopting a high-pressure pump.
(5) And after the concrete strength of the sliding beam 1 reaches the designed strength, cutting off the connecting reinforcing steel bars of the frame column 2 and the raft 3 and the concrete of the connecting part by using a wind cutting machine, so that the bottom elevation of the frame column 2 is the same as the bottom elevation of the sliding beam 1.
(6) And connecting the wood tie beam 7 with the embedded screws of the sliding beam 1.
(7) And pouring a new foundation of the in-place part of the sliding beam 1.
(8) And embedding a traction steel hanging ring in the raft 3 towards the traction direction, constructing a counter-force pile, and installing a counter-force facility and a jack.
(9) And laying a slipping rail in the slipping direction, and laying the slipping rail on the new foundation.
(10) Traction is carried out by adopting a traction facility.
The traction facility adopts an automatic control hydraulic synchronous system, the automatic control hydraulic synchronous system consists of a hydraulic system, a detection sensor and a computer control system, wherein the hydraulic system comprises an oil pump and a hydraulic jack. The hydraulic system is controlled by a computer, fully automatically completes synchronous displacement, and realizes the functions of force and displacement control, operation locking and process display. The working pressure of the hydraulic system is 30-32 MPa, and the peak pressure is 35 MPa. The pushing stroke of the pushing cylinders is 1200mm, the pushing control speed is 0-60 mm/min, the pushing cylinders in the group are communicated in pressure, the positions of the groups are synchronously controlled, and the synchronous precision is +/-lmm.
(11) And connecting the sliding beam 1 with the new foundation, and connecting the frame column 2 with the new foundation.
And after the sliding beam 1 is slid in place, the sliding beam 1 is jacked, the steel ball 4 is cut by wind after the sliding beam 1 is jacked, the sliding rail is removed, and then the sliding beam 1 is lowered to connect the sliding beam 1 with a new foundation.
The frame column 2 is connected with the new foundation by adopting fine aggregate concrete pulp extrusion, and the pulp extrusion process ensures that the vertical displacement of the column is zero after the column is in place and connected. The pulp squeezing adopts dry and hard fine stone concrete, and the dry and hard degree is qualified by being kneaded into a ball by hand and scattered when falling to the ground. When in pulp extrusion, two opposite side surfaces of the frame column 2 are clamped tightly by a mould clamp, and hard concrete is extruded from the other two surfaces.
Example two
In the embodiment, the sliding beams 1 are arranged on the raft 3, the distance between every two adjacent sliding beams 1 is 3.2m, the distance between the bottom of each sliding beam 1 and the top of the raft 3 is 70mm, and the height of each sliding beam 1 is 700 mm; the width of the sliding beam 1 is 300 mm. And a steel ball 4 is arranged below the sliding beam 1, and the diameter of the steel ball 4 is 70 mm.
A wood tie beam 7 is arranged between the adjacent sliding beams 1, the diameter of the wood tie beam 7 is 150-180 mm, and the included angle between the wood tie beam 7 and the sliding beam 1 is 50 degrees.
The right side of the position of taking one's place of the traction building is provided with a counterforce pile as a counterforce facility, the distance between the counterforce pile and the position of taking one's place of the building is 0.7m, the counterforce pile is a prefabricated tubular pile, and the diameter of the prefabricated tubular pile is 500-600 mm. The combined reaction pile and engineering pile are used as reaction support during initial traction, and the reaction pile is only used as reaction support during traction movement.
Damping steel blocks 8 are arranged at intervals of 2-3 m at the lower part of the sliding rail, springs 9 are arranged in the damping steel blocks 8, the sliding rail is made to be like a spring body, and when the steel balls 4 located in the range of the sliding rail body meet advancing resistance, impact force can be relieved under the action of the springs 9 in the damping steel blocks 8.
The construction steps comprise:
(1) chiseling the section of the frame column 1/5 to be used as a connecting part with the sliding beam 1; temporary supports are provided near the frame posts 2.
(2) Chiseling off the brick wall at the position of the sliding beam 1, supporting a template 6, arranging pouring holes and vibrating holes at the upper part of the lateral template 6, wherein the diameter of each pouring hole is 45mm, and the arrangement interval of the pouring holes is 1.3 m; the diameter of each vibrating hole is 25mm, and the distance between every two vibrating holes is 0.8 m; when erecting template 6, place steel ball 4 in 6 bottoms of template, steel ball 4 embedding lower bolster 6, steel ball 4 tops are the same with 6 top elevations of lower bolster, have the bearing in the middle of the steel ball 4, and the bearing stretches into template 6, and the bearing stretches into length and is 130 mm.
(3) The steel bars of the sliding beam 1 are erected, the main steel bars 5 of the sliding beam extend into the chiseling part of the frame column 2 and are bent upwards or downwards to increase the anchoring length, and the anchoring length is 500 mm.
(4) And pouring concrete of the sliding beam 1, then pouring concrete of chiseling parts of the frame columns 2, and pouring the concrete by adopting a high-pressure pump.
(5) And after the concrete strength of the sliding beam 1 reaches the designed strength, cutting off the connecting reinforcing steel bars of the frame column 2 and the raft 3 and the concrete of the connecting part by using a wind cutting machine, so that the bottom elevation of the frame column 2 is the same as the bottom elevation of the sliding beam 1.
(6) And connecting the wood tie beam 7 with the embedded screws of the sliding beam 1.
(7) And pouring a new foundation of the in-place part of the sliding beam 1.
(8) And embedding a traction steel hanging ring in the raft 3 towards the traction direction, constructing a counter-force pile, and installing a counter-force facility and a jack.
(9) And laying a slipping rail in the slipping direction, and laying the slipping rail on the new foundation.
(10) Traction is carried out by adopting a traction facility.
The traction facility adopts an automatic control hydraulic synchronous system, the automatic control hydraulic synchronous system consists of a hydraulic system, a detection sensor and a computer control system, wherein the hydraulic system comprises an oil pump and a hydraulic jack. The hydraulic system is controlled by a computer, fully automatically completes synchronous displacement, and realizes the functions of force and displacement control, operation locking and process display. The working pressure of the hydraulic system is 30-32 MPa, and the peak pressure is 35 MPa. The pushing stroke of the pushing cylinders is 1200mm, the pushing control speed is 0-60 mm/min, the pushing cylinders in the group are communicated in pressure, the positions of the groups are synchronously controlled, and the synchronous precision is +/-lmm.
(11) And connecting the sliding beam 1 with the new foundation, and connecting the frame column 2 with the new foundation.
And (3) welding the sliding rail with the new foundation steel bar, and firmly welding the steel ball 4 with the sliding rail after the sliding rail slides in place, so that the steel ball 4 cannot roll and translate under the action of an external load later. And (3) pouring and compacting the gap between the sliding rail and the steel ball 4 by using high-strength micro-expansion fine stone concrete, and pouring the steel ball 4 into the high-strength micro-expansion fine stone concrete.
The frame column 2 is connected with the new foundation by adopting fine aggregate concrete pulp extrusion, and the pulp extrusion process ensures that the vertical displacement of the column is zero after the column is in place and connected. The pulp squeezing adopts dry and hard fine stone concrete, and the dry and hard degree is qualified by being kneaded into a ball by hand and scattered when falling to the ground. When in pulp extrusion, two opposite side surfaces of the frame column 2 are clamped tightly by a mould clamp, and hard concrete is extruded from the other two surfaces.

Claims (1)

1.一种建筑物的滑移施工方法,其特征是在筏板上面设置滑移梁,相邻滑移梁距离为3~3.6m,滑移梁底部与筏板顶部距离为60~80mm,滑移梁宽度为300mm;滑移梁下面设置钢滚珠,钢滚珠直径为60~80mm;1. the sliding construction method of a building, it is characterized in that sliding beam is arranged on the raft, the adjacent sliding beam distance is 3~3.6m, and the distance at the bottom of the sliding beam and the top of the raft is 60~80mm, The width of the sliding beam is 300mm; steel balls are arranged under the sliding beam, and the diameter of the steel balls is 60-80mm; 相邻滑移梁之间设置木拉梁,木拉梁直径为150~180mm,木拉梁与滑移梁夹角为45~60度;A wooden tie beam is arranged between adjacent sliding beams, the diameter of the wooden tie beam is 150-180mm, and the angle between the wooden tie beam and the sliding beam is 45-60 degrees; 施工步骤包括:Construction steps include: (1)凿除框架柱1/5截面作为与滑移梁的连接部分;在框架柱附近设置临时支撑;(1) Cut out 1/5 of the section of the frame column as the connection part with the sliding beam; set up temporary support near the frame column; (2)将滑移梁部位的砖墙凿除,支设模板,侧向模板上部设置灌注孔和震捣孔,灌注孔直径为40~50mm,灌注孔设置间距为1.2~1.5m;震捣孔直径为20~30mm,震捣孔设置间距为0.7~0.9m;在支设模板时在下模板放置钢滚珠,钢滚珠嵌入下模板,钢滚珠顶部与下模板顶部标高相同,钢滚珠中间有轴承,轴承伸入模板,轴承伸入长度为120~150mm;(2) Chisel away the brick wall at the position of the sliding beam, set up a formwork, and set a perfusion hole and a vibration hole on the upper part of the lateral formwork. The diameter of the perfusion hole is 40-50mm, and the spacing between the perfusion holes is 1.2-1.5m; The diameter of the holes is 20-30mm, and the spacing of the vibration holes is 0.7-0.9m; when the formwork is supported, place steel balls on the lower formwork, the steel balls are embedded in the lower formwork, the top of the steel balls is the same as the top of the lower formwork, and there are bearings in the middle of the steel ball , the bearing extends into the template, and the bearing length is 120 ~ 150mm; (3)支设滑移梁钢筋,滑移梁主筋伸入框架柱的凿开部分向上或向下弯折以增加锚固长度,锚固长度为500~700mm;(3) The sliding beam reinforcement is supported, and the chiseled part of the sliding beam main reinforcement extending into the frame column is bent upwards or downwards to increase the anchorage length, and the anchorage length is 500-700mm; (4)浇筑滑移梁混凝土,然后浇筑框架柱凿除部位混凝土,混凝土采用高压泵进行灌注;(4) pouring the slip beam concrete, and then pouring the frame column chiseled concrete, and the concrete is poured with a high-pressure pump; (5)待滑移梁混凝土强度达到设计强度后用风割机割除框架柱与筏板的联接钢筋及破除联接部分的混凝土,使框架柱底部标高与滑移梁底部标高相同;(5) After the concrete strength of the sliding beam reaches the design strength, use the wind cutting machine to cut off the connecting steel bars of the frame column and the raft and break the concrete of the connecting part, so that the bottom elevation of the frame column is the same as that of the bottom of the sliding beam; (6)将木拉梁与滑移梁的预埋螺钉联接;(6) Connect the pre-embedded screws of the wooden tension beam and the sliding beam; (7)浇筑滑移梁就位部位的新基础;(7) Pouring a new foundation for the position of the slip beam; (8)在筏板朝向牵拉方向埋设牵引钢吊环,施工反力桩,安装反力设施和千斤顶;(8) Bury traction steel rings on the raft towards the pulling direction, construct reaction force piles, install reaction force facilities and jacks; (9)在滑移方向铺设滑移铁轨,新基础上面也铺设滑移铁轨;(9) The sliding rails are laid in the sliding direction, and the sliding rails are also laid on the new foundation; (10)采用牵引设施进行牵引;(10) Use traction facilities for traction; 牵引设施采用自动控制液压同步系统,自动控制液压同步系统由液压系统、检测传感器和计算机控制系统组成,其中液压系统包括油泵、液压千斤顶;液压系统由计算机控制,全自动完成同步位移,实现力和位移控制、操作闭锁、过程显示功能;液压系统工作压力30~32MPa,尖峰压力为35MPa;顶推缸推力行程为1200mm,顶推控制速度为0~60mm/min,组内各顶推缸压力连通,组与组之间位置同步控制,同步精度为±lmm;The traction facility adopts an automatic control hydraulic synchronization system. The automatic control hydraulic synchronization system consists of a hydraulic system, a detection sensor and a computer control system. The hydraulic system includes an oil pump and a hydraulic jack; Displacement control, operation locking, and process display functions; the working pressure of the hydraulic system is 30-32MPa, and the peak pressure is 35MPa; the thrust stroke of the jacking cylinder is 1200mm, the jacking control speed is 0-60mm/min, and the pressure of each jacking cylinder in the group is connected , the position synchronization control between groups, the synchronization accuracy is ±lmm; (11)将滑移梁与新基础进行联接、框架柱与新基础进行联接;(11) Connect the sliding beam with the new foundation, and connect the frame column with the new foundation; 在牵引建筑物就位位置的右侧设置反力桩作为反力设施,反力桩离建筑物就位位置距离有0.6~0.8m,反力桩采用预制管桩,预制管桩直径为500~600mm;初始牵引时采用反力桩和工程桩联合作为反力支座,牵引运动时仅采用反力桩作为反力支座;A reaction force pile is set on the right side of the in-position position of the traction building as a reaction force facility. The distance between the reaction force pile and the in-position position of the building is 0.6~0.8m. The reaction force pile adopts a prefabricated pipe pile with a diameter of 500~ 600mm; in the initial traction, the combination of the reaction pile and the engineering pile is used as the reaction support, and only the reaction pile is used as the reaction support during the traction movement; 在滑移铁轨下部每隔2~3m设置减振钢块,减振钢块内安装弹簧。Vibration-damping steel blocks are installed at intervals of 2 to 3m at the lower part of the sliding rail, and springs are installed in the vibration-damping steel blocks.
CN201811322904.0A 2017-07-12 2017-07-12 Sliding construction technology for building Active CN109184259B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811322904.0A CN109184259B (en) 2017-07-12 2017-07-12 Sliding construction technology for building

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710563525.XA CN107227862B (en) 2017-07-12 2017-07-12 Sliding construction method of buildings
CN201811322904.0A CN109184259B (en) 2017-07-12 2017-07-12 Sliding construction technology for building

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201710563525.XA Division CN107227862B (en) 2017-07-12 2017-07-12 Sliding construction method of buildings

Publications (2)

Publication Number Publication Date
CN109184259A CN109184259A (en) 2019-01-11
CN109184259B true CN109184259B (en) 2021-06-29

Family

ID=59956289

Family Applications (7)

Application Number Title Priority Date Filing Date
CN201811322768.5A Active CN109184256B (en) 2017-07-12 2017-07-12 Displacement construction method for building
CN201811328587.3A Active CN109184260B (en) 2017-07-12 2017-07-12 Sliding construction technology for buildings with rafts
CN201811337134.7A Active CN109184261B (en) 2017-07-12 2017-07-12 Slippage construction method for building with raft
CN201811322904.0A Active CN109184259B (en) 2017-07-12 2017-07-12 Sliding construction technology for building
CN201811322818.XA Pending CN109184257A (en) 2017-07-12 2017-07-12 The displacement construction technology of building
CN201710563525.XA Active CN107227862B (en) 2017-07-12 2017-07-12 Sliding construction method of buildings
CN201811322858.4A Withdrawn CN109184258A (en) 2017-07-12 2017-07-12 Displacement construction method with raft plate building

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201811322768.5A Active CN109184256B (en) 2017-07-12 2017-07-12 Displacement construction method for building
CN201811328587.3A Active CN109184260B (en) 2017-07-12 2017-07-12 Sliding construction technology for buildings with rafts
CN201811337134.7A Active CN109184261B (en) 2017-07-12 2017-07-12 Slippage construction method for building with raft

Family Applications After (3)

Application Number Title Priority Date Filing Date
CN201811322818.XA Pending CN109184257A (en) 2017-07-12 2017-07-12 The displacement construction technology of building
CN201710563525.XA Active CN107227862B (en) 2017-07-12 2017-07-12 Sliding construction method of buildings
CN201811322858.4A Withdrawn CN109184258A (en) 2017-07-12 2017-07-12 Displacement construction method with raft plate building

Country Status (1)

Country Link
CN (7) CN109184256B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107816125B (en) * 2017-10-26 2024-06-07 临沂锋立建筑劳务有限公司 Structure for synchronous construction of basement and superstructure
CN109083442B (en) * 2018-10-15 2020-10-23 北京建工四建工程建设有限公司 Construction method of dynamic load bearing structure during butt joint of existing building and newly-built foundation
CN109281255B (en) * 2018-10-26 2023-10-20 中交路桥华南工程有限公司 Steel beam sliding support and system
CN114969889B (en) * 2022-04-18 2024-06-04 朱胜祥 Pile-raft foundation overhanging raft stress calculation method
CN115522572B (en) * 2022-10-28 2025-08-26 上海宝冶建筑装饰有限公司 Concrete structure and pouring method of basement wall column node
CN116516838A (en) * 2023-03-15 2023-08-01 上海公路桥梁(集团)有限公司 Prefabricated bridge deck installation system and installation method
CN116716819B (en) * 2023-07-14 2025-08-01 中铁十七局集团第一工程有限公司 Device for pouring template of reinforced concrete approach bridge and main bridge end beam to slide relatively

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1077512A (en) * 1992-09-25 1993-10-20 高继良 The method and apparatus of building translation
CN2440893Y (en) * 2000-08-16 2001-08-01 广州市鲁班建筑防水补强专业公司 Apparatus for unitary horizontal movement of construction
JP2003056186A (en) * 2001-08-17 2003-02-26 Hikiya Kenchikubutsu Furiku Chosei Shuei Tonosaki An H-shaped steel frame mounting method for lifting and pulling wooden buildings using H-shaped steel, special anchor fittings, and specially-made fine adjustment fittings, adapted to the structural characteristics of wooden buildings.
CN204738556U (en) * 2015-05-29 2015-11-04 中国建筑第六工程局有限公司 A device for landmark is whole to shift
CN106285040A (en) * 2016-08-19 2017-01-04 山东建筑大学 The track discrepancy in elevation is utilized to realize the method that building moving turns to
CN106760619A (en) * 2016-12-23 2017-05-31 河北省建筑科学研究院 A kind of building translation apparatus and its construction method

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1562430A (en) * 1925-01-08 1925-11-24 Alexander Orion Means for and method of moving buildings
CN1034881C (en) * 1993-10-09 1997-05-14 阮蔚文 Building Relocation Method
CN1132302A (en) * 1995-09-29 1996-10-02 哈尔滨市道里区房屋土地开发公司 Structure displacement method of building
JP2002013299A (en) * 2000-06-30 2002-01-18 Yutaka Kouen Structure transferring device
JP5415243B2 (en) * 2009-12-07 2014-02-12 大成建設株式会社 Structure transfer method
JP5320499B1 (en) * 2012-10-04 2013-10-23 株式会社北日本重量 Heavy goods transfer device and heavy goods transfer device
CN103233588B (en) * 2013-04-18 2015-07-29 叶长青 With the shift method of raft foundation building
JP6341705B2 (en) * 2014-03-14 2018-06-13 大成建設株式会社 Moving method
CN105089292A (en) * 2015-08-21 2015-11-25 顾雍舟 Monolithic movement construction method for house with soil foundation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1077512A (en) * 1992-09-25 1993-10-20 高继良 The method and apparatus of building translation
CN2440893Y (en) * 2000-08-16 2001-08-01 广州市鲁班建筑防水补强专业公司 Apparatus for unitary horizontal movement of construction
JP2003056186A (en) * 2001-08-17 2003-02-26 Hikiya Kenchikubutsu Furiku Chosei Shuei Tonosaki An H-shaped steel frame mounting method for lifting and pulling wooden buildings using H-shaped steel, special anchor fittings, and specially-made fine adjustment fittings, adapted to the structural characteristics of wooden buildings.
CN204738556U (en) * 2015-05-29 2015-11-04 中国建筑第六工程局有限公司 A device for landmark is whole to shift
CN106285040A (en) * 2016-08-19 2017-01-04 山东建筑大学 The track discrepancy in elevation is utilized to realize the method that building moving turns to
CN106760619A (en) * 2016-12-23 2017-05-31 河北省建筑科学研究院 A kind of building translation apparatus and its construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
建筑物整体平移施工技术;庄延清;《福建建筑》;20070831(第8期);第73-74、85页 *
某文物建筑的平移改造工程;韩继云等;《特种结构》;20010430;第28卷(第2期);第109-113页 *

Also Published As

Publication number Publication date
CN109184261A (en) 2019-01-11
CN109184256B (en) 2021-06-29
CN109184259A (en) 2019-01-11
CN109184261B (en) 2021-06-29
CN109184260B (en) 2021-06-29
CN109184256A (en) 2019-01-11
CN109184257A (en) 2019-01-11
CN107227862A (en) 2017-10-03
CN107227862B (en) 2019-04-02
CN109184258A (en) 2019-01-11
CN109184260A (en) 2019-01-11

Similar Documents

Publication Publication Date Title
CN109184259B (en) Sliding construction technology for building
CN106065577B (en) A kind of structure and method of new pile foundation underpinning
CN110259184A (en) Column construction method is pulled out based on Removing Columns combined support jack-up system
CN102839601A (en) Consolidated structure of steel piers and caps of portal-type rigid frame overpass and its construction method
CN105002834A (en) Deviation rectifying and strengthening method for piers
CN103603359A (en) Deep foundation pit diagonal bracing support structure demolition method
CN103774674B (en) A kind of steel pipe underpinned pile and anchor pole deep foundation pit supporting structure and construction method thereof
CN104988915B (en) A kind of prefabricated installation method of detachable steel casing and under water connection beam
CN103541735A (en) Tunnel boring machine stepping push support device and construction method
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN110565449A (en) Anti-uplift and anti-separation type pile plate structure of high-speed railway
CN104612120A (en) Integrated construction method related to in-water steel pipe pile establishing platform
CN205223976U (en) Irrigation gallery concrete slipform device
CN114992382B (en) Open caisson method construction muddy water balance pipe jacking working well opening construction method
CN106894420B (en) Basement construction method for supporting
CN103790176B (en) A construction method of pre-embedded short-leg column structure
CN106013783A (en) Formwork support and erecting method thereof
CN113279334B (en) Construction method of one-step pouring molding system of double-column type vase pier steel template
CN105133575A (en) Suspended formwork supporting device for casting lining on surface of underground continuous wall and construction method
CN103266899A (en) Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN203238950U (en) Concrete beam formwork supported by trusses suspended in air
CN106480826B (en) The cast-in-place traversing construction engineering method of single line box beam pier top
CN109024288A (en) A method of using precast concrete pad erecting steel truss girder
CN116657510A (en) A construction method for underpinning damaged bridge piers on restricted height and narrow terrain
CN111535355A (en) Industrial building shock attenuation basis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 325000 No. 48 Xinghai Road, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province

Applicant after: Ye Changqing

Address before: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, 4

Applicant before: Ye Changqing

GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, 4

Patentee after: Ye Changqing

Address before: 325000 No. 48 Xinghai Road, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province

Patentee before: Ye Changqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250325

Address after: No. 3 Ronghua Community, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region, 750000

Patentee after: Ni Yanshou

Country or region after: China

Address before: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, 4

Patentee before: Ye Changqing

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250509

Address after: 750000 4th floor, No. 306 Funing street, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region

Patentee after: Ningxia Kunsheng Construction Engineering Co.,Ltd.

Country or region after: China

Address before: No. 3 Ronghua Community, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region, 750000

Patentee before: Ni Yanshou

Country or region before: China