CN109162738A - Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window - Google Patents

Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window Download PDF

Info

Publication number
CN109162738A
CN109162738A CN201811334438.8A CN201811334438A CN109162738A CN 109162738 A CN109162738 A CN 109162738A CN 201811334438 A CN201811334438 A CN 201811334438A CN 109162738 A CN109162738 A CN 109162738A
Authority
CN
China
Prior art keywords
window
chute
concrete
tunnel
shunt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811334438.8A
Other languages
Chinese (zh)
Inventor
邓历振
吴力斌
张宏闽
范德全
陈济熙
陈博极
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 24th Bureau Group Co Ltd
Fujian Railway Construction Co Ltd of China Railway 24th Bureau Group Co Ltd
Original Assignee
China Railway 24th Bureau Group Co Ltd
Fujian Railway Construction Co Ltd of China Railway 24th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 24th Bureau Group Co Ltd, Fujian Railway Construction Co Ltd of China Railway 24th Bureau Group Co Ltd filed Critical China Railway 24th Bureau Group Co Ltd
Priority to CN201811334438.8A priority Critical patent/CN109162738A/en
Publication of CN109162738A publication Critical patent/CN109162738A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明涉及一种实现混凝土分层逐窗入模浇筑的机构及其浇筑工艺,其特征在于:实现混凝土分层逐窗入模浇筑的机构包括隧道和设在隧道内壁面的模板,所述模板上沿隧道长度方向和纵向设有若干个用于通入混凝土料的开窗,所述开窗包括上窗口、中窗口和下窗口,所述隧道的一定长度内自上而下依次设有主料斗、两个三通分流槽、四个分流串筒和溜槽,在隧道的同一纵面内三通分流槽位于主料斗的两下侧,三通分流槽与主料斗通过第一溜槽连接,在隧道的立面内分流串筒位于分流槽的两下侧,分流串筒与分流槽通过第二溜槽连接,本发明实现混凝土分层逐窗入模浇筑的机构结构简单、设计合理,有利于提高隧道浇筑施工效率。

The invention relates to a mechanism for realizing layer-by-window-by-window pouring of concrete and a pouring process thereof. There are several windows for passing the concrete material along the length direction and longitudinal direction of the tunnel. Hopper, two three-way distribution troughs, four distribution cylinders and chute, the three-way distribution tank is located on the two lower sides of the main hopper in the same longitudinal plane of the tunnel, and the three-way distribution tank is connected with the main hopper through the first chute, In the facade of the tunnel, the diverting cylinders are located on the two lower sides of the diverting trough, and the diverting cylinders and the diverting trough are connected by the second chute. Tunnel pouring construction efficiency.

Description

Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window
Technical field:
Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window the present invention relates to a kind of.
Background technique:
With increasing for the construction such as highway, railway, the case where highway or railway crossing tunnel, is more and more, carries out in the past to tunnel When pouring construction, it is required to be poured in tunnel height and length direction segmentation, construction efficiency is low, and the mistake after pouring occurs Layer woollen is more, and cleaning task afterwards are huge.
Summary of the invention:
Realize that concrete delamination enters the mechanism and its casting craft that mould pours, the reality by window the purpose of the present invention is to provide a kind of Existing concrete delamination by window enter the mechanism structure that mould pours is simple, design rationally, be conducive to improve tunnel pouring construction efficiency.
To achieve the above object, the present invention adopts the following technical scheme:
The present invention realizes that concrete delamination enters the mechanism that mould pours by window, it is characterised in that: including tunnel and is located at tunnel inner wall The template in face, in the template along length of tunnel direction and it is longitudinal be equipped with several windowings for being used to be passed through concrete material, it is described Windowing includes upper window, middle window and lower window, is successively arranged main hopper, two from top to bottom in the certain length in the tunnel Distributing T-pipe slot, four shunting tumbling barrels and chute, in the same vertical face in tunnel distributing T-pipe slot position in main hopper two downside, Distributing T-pipe slot is connect with main hopper by the first chute, and two downsides that tumbling barrel is located at diversion channel are shunted in the facade in tunnel, It shunts tumbling barrel to connect with diversion channel by the second chute, the chute towards upper window is third chute, and third chute is slipped with second The lower end connection of slot connection, the chute towards middle window are the 4th chute, and the 4th chute shunts the bypass pipe of tumbling barrel with connecting Connection;Chute towards lower window is the 5th chute, and the 5th chute is connected with the lower through-tube for shunting tumbling barrel is connect.
Further, above-mentioned first, second, third and fourth and five chute feed end and discharge end difference in height be less than 2.0m.
Further, in same longitudinal orientation, middle window is located at upper window and lower window for above-mentioned upper window and lower window Perpendicular bisector position on.
Further, said one main hopper, two distributing T-pipe slots, four shunting tumbling barrels and chute constitute a component layers Enter mould by window and pour component, is equipped with two groups along length of tunnel direction or three component layers enter mould by window and pour component, adjacent major ingredient Bucket by with pour the upper siphunculus connection that trolley connect.
Further, above-mentioned main hopper is rectangular opening shape cone bucket: 50 × 45cm of size suitable for reading, 47 × 23cm of bottom size, High 50cm;Distributing T-pipe slot is rectangular opening shape cone bucket: 40 × 25cm of size suitable for reading, bottom size 35 × 18cm, high 25cm;It shunts Tumbling barrel is that Upper rectangular mouth lower part is circular cone bucket: top 50 × 50cm of size suitable for reading, lower openings caliber 27cm, wall thickness 3mm, high 40cm;Chute is arc panel: its width 34cm, deep 10cm.
The present invention realizes that concrete delamination enters the casting craft of mould by window, it is characterised in that: the realization concrete delamination Entering mould to pour mechanism by window includes tunnel and the template for being located at tunnel inner wall face, along length of tunnel direction and longitudinal direction in the template It is used to be passed through the windowing of concrete material equipped with several, the windowing includes upper window, middle window and lower window, the tunnel Main hopper, two distributing T-pipe slots, four shunting tumbling barrels and chute are successively arranged in certain length from top to bottom, in the same of tunnel Distributing T-pipe slot position is in two downsides of main hopper in one vertical face, and distributing T-pipe slot is connect with main hopper by the first chute, in tunnel Two downsides that tumbling barrel is located at diversion channel are shunted in the facade in road, are shunted tumbling barrel and are connect with diversion channel by the second chute, are led to upper The chute of window is third chute, and lower end that third chute connect with the second chute connects, and the chute towards middle window is the Four chutes, the 4th chute are connected with the bypass pipe for shunting tumbling barrel is connect;Chute towards lower window is the 5th chute, the 5th chute It is connected with the lower through-tube for shunting tumbling barrel is connect;When construction, concrete is pumped into main hopper by delivery pump pump line, by distributing T-pipe Slot, shunting tumbling barrel and each chute are guided to each corresponding operation window, and it is symmetrical to realize that concrete enters mould layering by window from the bottom to top It pours.
Further, when above-mentioned casting concrete, concrete maximum height of drop is no more than 2m, trolley front and back concrete Height difference forbids unilateral one-time-concreting 1m or more no more than 0.5m no more than 0.6m, left and right concrete height.
Further, in casting process, it should be noted that the case where observing template, reinforcing bar, when discovery has deformation, displacement, Should take reinforcement measure in time, when in construction such as discovery pumping concrete slump deficiency, self-watering must not be arrogated to oneself, when triple window layering by After the completion of window pours, trolley delivery pump connecting leg to vault carries out concrete and rushes to summit operation.
Further, concreting should be carried out continuously, and concrete is made firm by ramming closely knit using artificial and attached vibrator;When For some reason when interval, the time that the intermittent time should be less than the presetting period of bottom concrete or can remold, when more than permission interval When the time, by treatment of construction joints, lining cutting concrete seam crossing must carry out dabbing processing.
Further, the secondary lining concrete strength applied after Support Deformation is basicly stable in the early stage reaches 8MPa or more Demoulding;100% side that the unstable secondary lining concrete strength applied in advance of preliminary bracing should reach design strength can demould; When demoulding, the temperature difference between inside concrete and surface layer, surface layer and environment is not greater than 20 DEG C, and the outer surface temperature difference is not in structure It obtains and is greater than 15 DEG C;Inside concrete must not demoulding before starting cooling;After secondary lining demoulding, spray maintenance is carried out, curing time: To the concrete using portland cement, ordinary portland cement mixing, 7d must not be less than;To Mixed With Admixture or have impervious etc. It is required that concrete, 14d must not be less than.
The present invention realize concrete delamination by window enter mechanism structure that mould pours is simple, design rationally, be conducive to improve tunnel Road pouring construction efficiency.
Detailed description of the invention:
Fig. 1 is that two component layers of the invention by window enter the organigram that mould pours component;
Fig. 2 is organigram of the invention;
Fig. 3 is the expanded view along tunnel direction certain length template;
Fig. 4 is the organigram that distributing T-pipe slot is connect with shunting tumbling barrel.
Specific embodiment:
It includes tunnel 1 and the template 2 for being located at tunnel inner wall face, institute that the present invention, which realizes that concrete delamination enters the mechanism that mould pours by window, It states along length of tunnel direction and longitudinal windowing 3 for being used to be passed through concrete material equipped with several in template 2, the windowing includes upper Window 301, middle window 302 and lower window 303 are successively arranged main hopper 4, two in the certain length in the tunnel from top to bottom 5, four shunting tumbling barrels 6 of distributing T-pipe slot and chute 7, the interior distributing T-pipe of same vertical face (plane as where Fig. 2) in tunnel Slot 5 is located at two downsides of main hopper 4, and distributing T-pipe slot 5 is connect with main hopper 5 by the first chute 701, the facade in tunnel Two downsides that tumbling barrel 6 is located at diversion channel 5 are shunted in (plane as where Fig. 4), are shunted tumbling barrel 6 and are slipped with diversion channel 5 by second Slot 702 connects, and the chute towards upper window 301 is third chute 703, the lower end that third chute 703 is connect with the second chute 702 Portion's connection, the chute towards middle window 302 are the 4th chute 704, and the 4th chute 704 shunts the bypass pipe 601 of tumbling barrel 6 with connecting Connection;Chute towards lower window is the 5th chute 705, and the 5th chute 705 is connected with the lower through-tube 602 for shunting tumbling barrel 6 is connect.
One of embodiment, in order to which feeding is reliable and stable, above-mentioned first, second, third and fourth and five chute feed end with go out Expect that the difference in height at end is less than 2.0m.
One of embodiment, as shown in figure 3, good in order to make to pour effect, above-mentioned upper window 301 exists with lower window 303 In same longitudinal direction orientation, middle window 302 is located on the perpendicular bisector position of upper window and lower window.
Further, it in order to design rationally, said one main hopper, two distributing T-pipe slots, four shunting tumbling barrels and slips Slot one component layers of composition enter mould by window and pour component A, are equipped with two groups along length of tunnel direction or three component layers enter mould by window and pour Component, adjacent main hopper by with pour the upper siphunculus 8 that trolley connect and connect.
Further, in order to design rationally, above-mentioned main hopper 4 is rectangular opening shape cone bucket: 50 × 45cm of size suitable for reading, lower mouth Size 47 × 23cm, high 50cm;Distributing T-pipe slot 5 be rectangular opening shape cone bucket: 40 × 25cm of size suitable for reading, bottom size 35 × 18cm, high 25cm;It is circular cone bucket that shunting tumbling barrel 6, which is Upper rectangular mouth lower part: top 50 × 50cm of size suitable for reading, lower part is opened Mouth caliber 27cm, wall thickness 3mm, high 40cm;Chute is arc panel: its width 34cm, deep 10cm.
Fig. 3 is the expanded view along tunnel direction certain length template, and arrow direction is length of tunnel direction, wherein 201 are Top template, the construction scope not poured in the application, 202 be the mould for offering window 301, middle window 302 and lower window 303 Plate is also to have windowing on 201, is to be poured with other mode, does not illustrate here.
The present invention realizes that concrete delamination enters the casting craft of mould by window, and the realization concrete delamination enters mould by window and pours Mechanism includes tunnel and the template for being located at tunnel inner wall face, is equipped with several along length of tunnel direction and longitudinal direction in the template and uses In the windowing for being passed through concrete material, the windowing includes upper window, middle window and lower window, and the certain length in the tunnel is interior certainly It is successively arranged main hopper, two distributing T-pipe slots, four shunting tumbling barrels and chute under above, the threeway in the same vertical face in tunnel Diversion channel is located at two downsides of main hopper, and distributing T-pipe slot is connect by the first chute with main hopper, divided in the facade in tunnel Stream tumbling barrel is located at two downsides of diversion channel, shunts tumbling barrel and is connect with diversion channel by the second chute, the chute towards upper window is Third chute, the lower end connection that third chute is connect with the second chute, the chute towards middle window is the 4th chute, and the 4th slips Slot is connected with the bypass pipe for shunting tumbling barrel is connect;Chute towards lower window is the 5th chute, and the 5th chute is gone here and there with shunting is connect The lower through-tube connection of cylinder;When construction, concrete is pumped into main hopper by delivery pump pump line, by distributing T-pipe slot, shunts tumbling barrel It is guided to each corresponding operation window with each chute, realizes that concrete enters mould layering by window from the bottom to top and symmetrically pours.
Further, when above-mentioned casting concrete, concrete maximum height of drop is no more than 2m, trolley front and back concrete Height difference forbids unilateral one-time-concreting 1m or more no more than 0.5m no more than 0.6m, left and right concrete height.
Further, in casting process, it should be noted that the case where observing template, reinforcing bar, when discovery has deformation, displacement, Should take reinforcement measure in time, when in construction such as discovery pumping concrete slump deficiency, self-watering must not be arrogated to oneself, when triple window layering by After the completion of window pours, trolley delivery pump connecting leg to vault carries out concrete and rushes to summit operation.
Further, concreting should be carried out continuously, and concrete is made firm by ramming closely knit using artificial and attached vibrator;When For some reason when interval, the time that the intermittent time should be less than the presetting period of bottom concrete or can remold, when more than permission interval When the time, by treatment of construction joints, lining cutting concrete seam crossing must carry out dabbing processing.
Further, the secondary lining concrete strength applied after Support Deformation is basicly stable in the early stage reaches 8MPa or more Demoulding;100% side that the unstable secondary lining concrete strength applied in advance of preliminary bracing should reach design strength can demould; When demoulding, the temperature difference between inside concrete and surface layer, surface layer and environment is not greater than 20 DEG C, and the outer surface temperature difference is not in structure It obtains and is greater than 15 DEG C;Inside concrete must not demoulding before starting cooling;After secondary lining demoulding, spray maintenance is carried out, curing time: To the concrete using portland cement, ordinary portland cement mixing, 7d must not be less than;To Mixed With Admixture or have impervious etc. It is required that concrete, 14d must not be less than.
The present invention realize concrete delamination by window enter mechanism structure that mould pours is simple, design rationally, be conducive to improve tunnel Road pouring construction efficiency.
The foregoing is merely presently preferred embodiments of the present invention, all equivalent changes done according to scope of the present invention patent with Modification, is all covered by the present invention.

Claims (10)

1.一种实现混凝土分层逐窗入模浇筑的机构,其特征在于:包括隧道和设在隧道内壁面的模板,所述模板上沿隧道长度方向和纵向设有若干个用于通入混凝土料的开窗,所述开窗包括上窗口、中窗口和下窗口,所述隧道的一定长度内自上而下依次设有主料斗、两个三通分流槽、四个分流串筒和溜槽,在隧道的同一纵面内三通分流槽位于主料斗的两下侧,三通分流槽与主料斗通过第一溜槽连接,在隧道的立面内分流串筒位于分流槽的两下侧,分流串筒与分流槽通过第二溜槽连接,通往上窗口的溜槽为第三溜槽,第三溜槽与第二溜槽连接的下端部连接,通往中窗口的溜槽为第四溜槽,第四溜槽与连接分流串筒的旁通管连接;通往下窗口的溜槽为第五溜槽,第五溜槽与连接分流串筒的下通管连接。1. a mechanism that realizes concrete layer-by-window pouring into mould, it is characterized in that: comprise tunnel and the formwork that is arranged on the inner wall of tunnel, described formwork is provided with several along the tunnel length direction and longitudinal direction for feeding concrete The opening of the material, the opening includes an upper window, a middle window and a lower window, and a main hopper, two three-way distribution troughs, four distribution cylinders and a chute are arranged in sequence from top to bottom within a certain length of the tunnel. , in the same longitudinal plane of the tunnel, the three-way distribution trough is located on the two lower sides of the main hopper, the three-way distribution trough is connected with the main hopper through the first chute, and the shunt cylinders are located on the two lower sides of the distribution tank in the vertical surface of the tunnel. The shunt string and the shunt are connected through the second chute, the chute leading to the upper window is the third chute, the third chute is connected to the lower end of the second chute, the chute leading to the middle window is the fourth chute, the fourth chute It is connected with the bypass pipe connecting the shunt serial cylinder; the chute leading to the lower window is the fifth chute, and the fifth chute is connected with the down pipe connecting the shunt serial cylinder. 2.根据权利要求1所述的实现混凝土分层逐窗入模浇筑的机构,其特征在于:所述第一、二、三、四和五溜槽的进料端与出料端的高度差少于2.0m。2. The mechanism for realizing layer-by-window pouring of concrete layer by window according to claim 1, wherein the height difference between the feeding end and the discharging end of the first, second, third, fourth and fifth chutes is less than 2.0m. 3.根据权利要求1所述的实现混凝土分层逐窗入模浇筑的机构,其特征在于:所述上窗口与下窗口在同一纵向方位上,中窗口位于上窗口与下窗口的中垂线位置上。3. The mechanism for realizing layer-by-window pouring of concrete layer by window according to claim 1, characterized in that: the upper window and the lower window are in the same longitudinal orientation, and the middle window is located on the mid-perpendicular line of the upper window and the lower window position. 4.根据权利要求1所述的实现混凝土分层逐窗入模浇筑的机构,其特征在于:所述一个主料斗、两个三通分流槽、四个分流串筒和溜槽构成一组分层逐窗入模浇筑构件,沿隧道长度方向设有两组或三组分层逐窗入模浇筑构件,相邻的主料斗通过与浇筑台车连接的上通管连接。4. The mechanism for realizing layer-by-window pouring of concrete layer-by-window according to claim 1, characterized in that: the one main hopper, two three-way distribution troughs, four distribution cylinders and chute constitute a set of layers For the window-by-window casting components, there are two or three groups of layer-by-window casting components along the length of the tunnel, and the adjacent main hoppers are connected by an upper pipe connected to the casting trolley. 5.根据权利要求1所述的实现混凝土分层逐窗入模浇筑的机构,其特征在于:所述主料斗为矩形口状锥斗:上口尺寸50×45cm,下口尺寸47×23cm,高50cm;三通分流槽为矩形口状锥斗:上口尺寸40×25cm,下口尺寸35×18cm,高25cm;分流串筒为上部矩形口下部为圆形的锥斗:上部上口尺寸50×50cm,下部开口管径27cm ,壁厚3mm,高40cm;溜槽为弧形板:其宽34cm ,深10cm。5. The mechanism for realizing layer-by-window pouring of concrete layer by window according to claim 1, characterized in that: the main hopper is a rectangular mouth-shaped cone: the upper mouth size is 50×45cm, and the lower mouth size is 47×23cm, The height is 50cm; the three-way shunt is a rectangular mouth-shaped cone: the size of the upper port is 40×25cm, the size of the lower port is 35×18cm, and the height is 25cm. 50×50cm, the lower opening diameter is 27cm, the wall thickness is 3mm, and the height is 40cm; the chute is a curved plate: its width is 34cm and its depth is 10cm. 6.一种实现混凝土分层逐窗入模的浇筑工艺,其特征在于:所述实现混凝土分层逐窗入模浇筑机构包括隧道和设在隧道内壁面的模板,所述模板上沿隧道长度方向和纵向设有若干个用于通入混凝土料的开窗,所述开窗包括上窗口、中窗口和下窗口,所述隧道的一定长度内自上而下依次设有主料斗、两个三通分流槽、四个分流串筒和溜槽,在隧道的同一纵面内三通分流槽位于主料斗的两下侧,三通分流槽与主料斗通过第一溜槽连接,在隧道的立面内分流串筒位于分流槽的两下侧,分流串筒与分流槽通过第二溜槽连接,通往上窗口的溜槽为第三溜槽,第三溜槽与第二溜槽连接的下端部连接,通往中窗口的溜槽为第四溜槽,第四溜槽与连接分流串筒的旁通管连接;通往下窗口的溜槽为第五溜槽,第五溜槽与连接分流串筒的下通管连接;施工时,混凝土通过输送泵泵管泵入主料斗,经过三通分流槽、分流串筒和各溜槽导流至各相应的工作窗口,实现混凝土由下至上逐窗入模分层对称浇筑。6. A pouring technique for realizing layer-by-window moulding of concrete, characterized in that: the mechanism for realizing layer-by-window moulding of concrete comprises a tunnel and a template arranged on the inner wall of the tunnel, and the template is along the length of the tunnel. There are several windows for passing concrete in the direction and longitudinal direction. The windows include an upper window, a middle window and a lower window. Within a certain length of the tunnel, there are a main hopper, two The three-way shunt, four shunt cylinders and the chute are located on the two lower sides of the main hopper in the same longitudinal plane of the tunnel. The inner shunt barrel is located on the two lower sides of the shunt tank, the shunt string and the shunt tank are connected through the second chute, the chute leading to the upper window is the third chute, the third chute is connected with the lower end of the second chute, leading to the The chute in the middle window is the fourth chute, and the fourth chute is connected with the bypass pipe connecting the shunt string; the chute leading to the lower window is the fifth chute, and the fifth chute is connected with the down pipe connecting the shunt string; during construction , Concrete is pumped into the main hopper through the pump pipe of the conveying pump, and is diverted to the corresponding working windows through the three-way shunt, the shunt and the chutes, and the concrete is poured into the mold layer by layer and symmetrically from the bottom to the top. 7.根据权利要求6所述的实现混凝土分层逐窗入模的浇筑工艺,其特征在于:所述浇筑混凝土时,混凝土最大下落高度不能超过2m,台车前后混凝土高差不能超过0.6m,左右混凝土高度不能超过0.5m,严禁单侧一次浇筑1m以上。7. the pouring technique that realizes layer-by-window moulding of concrete according to claim 6, is characterized in that: when concrete is poured, the maximum drop height of concrete cannot exceed 2m, and the height difference of concrete before and after the trolley cannot exceed 0.6m, The height of the left and right concrete cannot exceed 0.5m, and it is strictly forbidden to pour more than 1m at a time on one side. 8.根据权利要求6所述的实现混凝土分层逐窗入模的浇筑工艺,其特征在于:在浇筑过程中,应注意观察模板、钢筋的情况,当发现有变形、移位时,应及时采取加固措施,施工中如发现泵送砼坍落度不足时,不得擅自加水,当三层窗分层逐窗浇筑完成后,台车输送泵连管至拱顶进行混凝土冲顶作业。8. The pouring technique for realizing the layer-by-window moulding of concrete according to claim 6, is characterized in that: in the pouring process, attention should be paid to the observation of the conditions of the formwork and the steel bars, and when deformation and displacement are found, it should be timely Reinforcement measures shall be taken. If it is found that the slump of the pumped concrete is insufficient during the construction, water shall not be added without authorization. 9.根据权利要求6所述的实现混凝土分层逐窗入模的浇筑工艺,其特征在于:混凝土浇筑应连续进行,混凝土采用人工和附着式振捣器捣固密实;当因故间歇时,其间歇时间应小于底层混凝土的初凝时间或能重塑的时间,当超过允许间歇时间时,按施工缝处理,衬砌砼接缝处必须进行凿毛处理。9. the pouring technique that realizes concrete layer-by-window moulding according to claim 6, is characterized in that: concrete pouring should be carried out continuously, and concrete adopts artificial and attached vibrator to tamping and compact; The interval time should be less than the initial setting time of the bottom concrete or the time it can be reshaped. When the allowable interval time is exceeded, it should be treated as a construction joint, and the lining concrete joint must be chiseled. 10.根据权利要求6所述的实现混凝土分层逐窗入模的浇筑工艺,其特征在于:在初期支护变形基本稳定后施作的二次衬砌混凝土强度达到8MPa以上脱模;初期支护未稳定提前施作的二次衬砌混凝土强度应达到设计强度的100%方可脱模;拆模时,混凝土内部与表层、表层与环境之间的温差不得大于20℃,结构内外侧表面温差不得大于15℃;混凝土内部开始降温前不得拆模;二次衬砌脱模后,进行喷淋养护,养护时间:对采用硅酸盐水泥、普通硅酸盐水泥拌制的混凝土,不得少于7d;对掺加外加剂或有抗渗等要求的混凝土,不得少于14d。10. The pouring process for realizing concrete layer-by-window moulding according to claim 6, characterized in that: the secondary lining concrete strength applied after the initial support deformation is basically stable reaches more than 8MPa and demoulding; the initial support The strength of the secondary lining concrete that is not stabilized and applied in advance should reach 100% of the design strength before demoulding; when demoulding, the temperature difference between the inside of the concrete and the surface, the surface and the environment should not be greater than 20 °C, and the temperature difference between the inner and outer surfaces of the structure should not be greater than 20°C. The temperature is higher than 15℃; the formwork shall not be removed before the concrete starts to cool down; after the secondary lining is demolded, spray curing shall be carried out. For concrete mixed with admixtures or with impermeability and other requirements, it shall not be less than 14d.
CN201811334438.8A 2018-11-09 2018-11-09 Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window Pending CN109162738A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811334438.8A CN109162738A (en) 2018-11-09 2018-11-09 Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811334438.8A CN109162738A (en) 2018-11-09 2018-11-09 Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window

Publications (1)

Publication Number Publication Date
CN109162738A true CN109162738A (en) 2019-01-08

Family

ID=64876982

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811334438.8A Pending CN109162738A (en) 2018-11-09 2018-11-09 Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window

Country Status (1)

Country Link
CN (1) CN109162738A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485463A (en) * 2019-08-30 2019-11-22 中建五局土木工程有限公司 Vertically to wall pouring construction method and pouring construction device
CN111119945A (en) * 2020-02-24 2020-05-08 中铁十七局集团第四工程有限公司 Tunnel secondary lining concrete pumping extrusion type pouring construction method
CN111749714A (en) * 2020-07-30 2020-10-09 四川港航建设工程有限公司 Window-by-window layered pouring system for circular water delivery tunnel wall and construction method
CN113931657A (en) * 2021-09-27 2022-01-14 中铁八局集团第七工程有限公司 Large-volume super-thick concrete pouring structure and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB791625A (en) * 1955-02-15 1958-03-05 Welding Ind Ltd Improvements in apparatus for moulding concrete and like blocks
JPH0791192A (en) * 1993-09-21 1995-04-04 Gifu Kogyo Kk Tunnel concrete placing method, test window opener, concrete flow divider and concrete placing device
JP2008088696A (en) * 2006-10-02 2008-04-17 Maeda Corp Tunnel lining construction method
CN106499410A (en) * 2016-11-13 2017-03-15 中铁十局集团第工程有限公司 Layer-by-layer pouring method of concrete for side wall of tunnel lining
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method
CN209261597U (en) * 2018-11-09 2019-08-16 中铁二十四局集团福建铁路建设有限公司 Realize that concrete delamination enters the mechanism that mould pours by window

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB791625A (en) * 1955-02-15 1958-03-05 Welding Ind Ltd Improvements in apparatus for moulding concrete and like blocks
JPH0791192A (en) * 1993-09-21 1995-04-04 Gifu Kogyo Kk Tunnel concrete placing method, test window opener, concrete flow divider and concrete placing device
JP2008088696A (en) * 2006-10-02 2008-04-17 Maeda Corp Tunnel lining construction method
CN106499410A (en) * 2016-11-13 2017-03-15 中铁十局集团第工程有限公司 Layer-by-layer pouring method of concrete for side wall of tunnel lining
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method
CN209261597U (en) * 2018-11-09 2019-08-16 中铁二十四局集团福建铁路建设有限公司 Realize that concrete delamination enters the mechanism that mould pours by window

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485463A (en) * 2019-08-30 2019-11-22 中建五局土木工程有限公司 Vertically to wall pouring construction method and pouring construction device
CN110485463B (en) * 2019-08-30 2024-03-26 中建五局土木工程有限公司 Vertical wall pouring construction method and pouring construction device
CN111119945A (en) * 2020-02-24 2020-05-08 中铁十七局集团第四工程有限公司 Tunnel secondary lining concrete pumping extrusion type pouring construction method
CN111119945B (en) * 2020-02-24 2021-10-15 中铁十七局集团第四工程有限公司 Tunnel secondary lining concrete pumping extrusion type pouring construction method
CN111749714A (en) * 2020-07-30 2020-10-09 四川港航建设工程有限公司 Window-by-window layered pouring system for circular water delivery tunnel wall and construction method
CN111749714B (en) * 2020-07-30 2021-11-09 四川港航建设工程有限公司 Window-by-window layered pouring system for circular water delivery tunnel wall and construction method
CN113931657A (en) * 2021-09-27 2022-01-14 中铁八局集团第七工程有限公司 Large-volume super-thick concrete pouring structure and method

Similar Documents

Publication Publication Date Title
CN109162738A (en) Realize that concrete delamination enters the mechanism and its casting craft that mould pours by window
CN106499410B (en) Tunnel-liner side wall concrete is by window placement layer by layer method
SA519400994B1 (en) Continuous Mixer and Method of Mixing Reinforcing Fibers with Cementitious Materials
CN102108787B (en) Construction method of ultra-high strength steel fiber concrete
CN106869503A (en) A kind of concreting method of concrete heat-insulating curtain wall
CN100547193C (en) Construction method of cast-in-place concrete floor with thin-wall box formwork
CN103304213A (en) Method for making cored building material block by using solidified soda residue soil
CN106378857A (en) Molding device for directional steel fiber reinforced ultrahigh-performance concrete and application method of molding device
WO2015111860A1 (en) Method for constructing continuously reinforced concrete pavement using foam shotcrete
CN106758840B (en) gradient concrete pouring method
CN109779262A (en) A kind of building concrete pours device
CN106868958B (en) Self-compacting concrete construction system and its construction method
CN104499498A (en) Construction method of mass concrete construction
CN208441867U (en) Concrete mold-entering distributor for lining trolley
CN209261597U (en) Realize that concrete delamination enters the mechanism that mould pours by window
CN208005975U (en) A kind of construction concrete grout material conveying device
CN112096415B (en) Construction Technology of Concrete Lining Buried Pipe Method at Bottom of Circular Tunnel
JP2022124859A (en) Extrusion lamination method for fiber-reinforced mortar
CN1579722A (en) Steel-containing fiber pouring material construction method and equipment
CN112982467A (en) Concrete pouring device and raft foundation pouring method
CN111484295A (en) Construction method for preventing pier wall concrete temperature cracks
CN117306872A (en) A kind of mass concrete construction method
JP2001152404A (en) Concrete block for water permeable pavement, manufacturing method therefor and water permeable paving slab
CN208122867U (en) A kind of tunnel double-lining divides storehouse cloth system
CN113565205A (en) One-time pouring forming method for interlayer beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190108