CN109083442A - The construction method of dynamic load bearing structure when existing building is docked with newly-built basis - Google Patents

The construction method of dynamic load bearing structure when existing building is docked with newly-built basis Download PDF

Info

Publication number
CN109083442A
CN109083442A CN201811195854.4A CN201811195854A CN109083442A CN 109083442 A CN109083442 A CN 109083442A CN 201811195854 A CN201811195854 A CN 201811195854A CN 109083442 A CN109083442 A CN 109083442A
Authority
CN
China
Prior art keywords
existing building
basis
trailer
dynamic load
newly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811195854.4A
Other languages
Chinese (zh)
Other versions
CN109083442B (en
Inventor
赵建红
张明
李东华
苏晨
年永林
张莉莉
李素霞
李晓欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Fourth Construction & Engineering Co Ltd
Original Assignee
Beijing Fourth Construction & Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Fourth Construction & Engineering Co Ltd filed Critical Beijing Fourth Construction & Engineering Co Ltd
Priority to CN201811195854.4A priority Critical patent/CN109083442B/en
Publication of CN109083442A publication Critical patent/CN109083442A/en
Application granted granted Critical
Publication of CN109083442B publication Critical patent/CN109083442B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure

Abstract

The construction method of dynamic load bearing structure when a kind of existing building and newly-built basis are docked, step 1 in the structural column work progress for creating box basis while being supported the construction of column;Step 2 chooses the material of backfill;Step 3 clears up basement bottom board, and checks and accepts substrate absolute altitude;Step 4 inserts backfilling material in basement, rams method using water and vibrating head is added to tamp the material of backfill;Step 5 is laid with steel plate in backfilling material top surface, the trailer for carrying existing building is migrated in place along steel plate;Step 6 installs interim steel drum support at the top of support column;Step 7 is jacked trailer using jack after trailer migration is in place, and the existing building on trailer is ridden upon to the top of interim steel drum support;Trailer is landed and is removed by step 8;Backfilling material is excavated carry out secondary use by step 9.The technical issues of present invention solves when being migrated using traditional migration pattern, and migration work cannot smoothly complete.

Description

The construction method of dynamic load bearing structure when existing building is docked with newly-built basis
Technical field
Dynamic load carrying when being docked the invention belongs to the realm of building construction more particularly to a kind of existing building with newly-built basis The construction method of structure.
Background technique
Since the last century 90's, in the process of urbanization transformation, ancient building frequently encounters the wind for needing to remove Danger, in order to protect historical relic to take the scheme of ancient building integral translation to new address, had not only protected historical relic in this way but also had met city The planning requirement of transformation.China is in the process of urbanization accelerated development in recent years, existing civilian, public build often occurs The problem of building with planned land use contradiction, the construction technology of building integrated translation is just widely adopted.But since building is whole The moving method used during translation is different, the dynamic load bearing mode used in existing building and newly-built basis docking Also different, currently used is the migration pattern using trailer mobile device, but since trailer is heavier, creates foundation structure Overall stability and safety it is lower, migration when certain damage can be usually caused to newly-built basis so that migration Work cannot be completed smoothly.
Summary of the invention
The construction party of dynamic load bearing structure when being docked the object of the present invention is to provide a kind of existing building with newly-built basis Method, when solving to be migrated using traditional migration pattern, overall stability and the safety for creating foundation structure are lower, Certain damage can be usually caused when migration to newly-built basis, so that the technical issues of migration work cannot smoothly complete.
To achieve the above object, the present invention adopts the following technical scheme that.
A kind of construction method of existing building and dynamic load bearing structure when creating basic dock, the newly-built basis is case Formula basis;The construction method includes that steps are as follows.
Step 1 in the structural column work progress for creating box basis while being supported the construction of column.
Step 2 chooses the material backfilled to the basement for creating box basis.
Step 3 clears up the basement bottom board for creating box basis, and checks and accepts substrate absolute altitude.
Step 4 inserts backfilling material in basement, carries out back-filling in layers, and ram method using water and add vibrating head to backfill Material tamped, so that backfilling material is reached the compactness of requirement.
Step 5 after the completion of backfill, is laid with steel plate in backfilling material top surface, will carry the trailer of existing building along laying Steel plate migration it is in place, dynamic load when using backfilling material carrying trailer and existing building in place.
Step 6 installs interim steel drum support at the top for creating the support column in box basis.
Step 7 is jacked trailer using jack, and the existing building on trailer is set up after trailer migration is in place At the top of interim steel drum support.
Trailer is landed and is removed using jack by step 8.
Backfilling material is excavated carry out secondary use by step 9.
Preferably, it creating in box basis, be respectively provided with structure along the cross wall for creating box basic two sides Column, and the structural column of two sides is correspondingly arranged;Support column is respectively arranged with inside and outside every structural column;The support column Capital be higher than the capital of structural column and identical as the elevation of top of backfilling material after the completion of engineered fill;It is supported at every Connection short beam is connected between column and structural column.
Preferably, the material backfilled in step 2 is using the medium coarse sand for meeting design requirement.
Preferably, in step 4, backfill is carried out according to construction line segmentation and regionalization, backfilling material hanging wire void paving, and will be empty Thickness control is spread in the range of 1000mm~2000mm, the spacing between vibrating head is not more than 1m.
Preferably, in step 4, water rams method and vibrating head water rammer is added to tamp backfilling material method particularly includes: is returning It when filling out, after one layer of backfilling material of every making, is filled the water, so that water filling height is more than the top surface of material, then given a violent shake to and smash with vibrating head It is real;Wherein, the spacing range that water rams is 5m~10m.
Preferably, the compactness required in step 4 is not less than 0.94.
Preferably, in step 6, the interim corresponding top for being mounted on support column of steel drum support, and use chemical anchors Bolt is connect with support column.
Compared with prior art the invention has the characteristics that and beneficial effect.
1, the migration pattern of traditional trailer mobile device creates the overall stability of foundation structure since trailer is heavier It is lower with safety, certain damage can be usually caused to newly-built basis in migration, so that migration work cannot be smooth Completion;And the present invention uses the Cast-in-situ Piles in Sand-filling on newly-built sole plate, and rams method+vibrating head compacting backfill technology using water, The overall stability and safety that ensure that newly-built foundation structure and existing building, smoothly complete existing building and newly-built base The Linking with foundation of plinth.
2, the present invention is spaced setting structure column in creating box basis, and support is respectively set in the two sides of structural column Column, when existing building is supported on interim steel drum support top, the load of existing building passes through two support columns and a structure Column is dispersed on foundation structure bottom plate, be ensure that the overall stability of existing building and is created the safety on basis.
3, the construction method in the present invention uses river sand easy to drawing materials, is transported using dumper truck to construction site, and Backfilling material is inserted using forklift and is convenient for construction organization in basement, the construction method is simple and easy, and whole stress is closed safely Reason.
4, the backfilling material in the present invention can realize 100% secondary use, and human and material resources and financial resources are greatly saved.
Detailed description of the invention
The present invention will be further described in detail with reference to the accompanying drawing.
Fig. 1 is the planar structure schematic diagram of structural column and support column arrangement of the invention.
Fig. 2 is the floor map of structural column and support column connection structure in the present invention.
Fig. 3 is that the schematic view of facade structure at the top of support column is arranged in interim steel drum support in the present invention.
Appended drawing reference: the interim steel drum support of 1- structural column, 2- support column, 3-, 4- connection short beam.
Specific embodiment
Method+vibrating head puddled backfill sand is rammed using water when existing building in the present embodiment connect in place with newly-built basis Mode undertakes delivery existing building trailer dynamic load.
The construction method of dynamic load bearing structure when this existing building is docked with newly-built basis, the newly-built basis is case Formula basis;The construction method includes that steps are as follows.
Step 1 in 1 work progress of structural column for creating box basis while being supported the construction of column 2.
Step 2 chooses the material backfilled to the basement for creating box basis.
Step 3 clears up the basement bottom board for creating box basis, remove the rubbish of basement bottom board, tree root, The foreign organic matters such as template, weeds extract hole ponding and mud out, and check and accept substrate absolute altitude, and basement bottom board is cleaned out, and take out Ponding, mud are the prerequisites that the construction method is smoothly implemented to substrate absolute altitude is checked and accepted out.
Step 4, backfilling material are transported using dumper truck to construction site, insert ground for backfilling material using forklift In lower room, back-filling in layers, the jolt ramming of marginal not waterside is carried out, and method is rammed using water, vibrating head is added to tamp the material of backfill, made Backfilling material reaches the compactness of requirement;Every one layer of backfill, water backfill one layer after ramming a laminated lattice;Rationalization's self-unloading tipping bucket Vehicle and forklift march into the arena and appearance route, guarantee construction speed.
Step 5 after the completion of backfill, is laid with steel plate in backfilling material top surface, will carry the trailer of existing building along laying Steel plate migration it is in place, dynamic load when using backfilling material carrying trailer and existing building in place.
Step 6 installs interim steel drum support 3 at the top for creating the support column 2 in box basis.
Step 7 is jacked trailer using jack, and the existing building on trailer is set up after trailer migration is in place At the top of interim steel drum support 3.
Trailer is landed and is removed using jack by step 8.
Backfilling material is excavated carry out secondary use by step 9, and backfilling material can carry out 100% recycling after digging out.
As shown in Figure 1-3, being created in box basis, along the cross wall point for creating box basic two sides in the present embodiment It is not arranged at intervals with structural column 1, and the structural column 1 of two sides is correspondingly arranged;It is respectively set inside and outside every structural column 1 There is support column 2;The capital of the support column 2 is higher than the capital of structural column 1 and the top with backfilling material after the completion of engineered fill Portion's absolute altitude is identical;Connection short beam 4 is connected between every support column 2 and structural column 1.
In the present embodiment, the material backfilled in step 2 is using the medium coarse sand for meeting design requirement, because medium coarse sand can be whole Recycling is used for secondary structure and Decorating Project;If backfill element, rain frequency high place big in areal rainfall depth is being returned Heavy rainfall is met during filling out and seriously affects backfill quality, and differential settlement is easy to happen when trailer drives into place;If backfilling broken Stone, porosity is higher, when the weight that trailer is loaded with more than 4500 tons drives into place, squeezes between rubble and is more prone to produce uneven liter Drop or bulk settling;The middle sand of backfill uses river sand.
In the present embodiment, in step 4, backfill is carried out according to construction line segmentation and regionalization, backfilling material hanging wire void paving, and By virtual resurfacing thickness control in the range of 1000mm~2000mm, the spacing between vibrating head is not more than 1m;In order to guarantee to tamp Quality, the spacing that each operator is responsible for water rammer is unsuitable too long, is advisable with 5m~10m;The empty paving of layering is filled with enough moisture, layering Whether compacting, audit-in-depth guarantee that water rams four keys of quality;When carrying out water rammer, according to field condition reasonable Arrangement water pump, The waste water of generation is excluded in time, avoids impacting structure.
In the present embodiment, in step 4, water rams method and vibrating head water rammer is added to tamp backfilling material method particularly includes: It in backfill, after one layer of backfilling material of every making, is filled the water, so that water filling height is more than the top surface of material, then shaken with vibrating head Shake tamping.
In the present embodiment, which is characterized in that the compactness required in step 4 is not less than 0.94.
In the present embodiment, in step 6, the corresponding top for being mounted on support column 2 of the interim steel drum support 3, and use Chemical anchor bolts are connect with support column 2, as shown in Figure 3.
Above-described embodiment is not the exhaustion of specific embodiment, can also there is other embodiments, and above-described embodiment purpose exists In illustrating the present invention, the protection scope being not intended to limit the present invention, all applications from simple change of the present invention all fall within this In the protection scope of invention.

Claims (7)

  1. The construction method of dynamic load bearing structure when 1. a kind of existing building is docked with newly-built basis, it is characterised in that: described new Building basis is box basis;The construction method comprises the following steps that
    Step 1 in structural column (1) work progress for creating box basis while being supported the constructions of column (2);
    Step 2 chooses the material backfilled to the basement for creating box basis;
    Step 3 clears up the basement bottom board for creating box basis, and checks and accepts substrate absolute altitude;
    Step 4 inserts backfilling material in basement, carries out back-filling in layers, and ram method using water and add vibrating head to the material of backfill Material is tamped, and backfilling material is made to reach the compactness of requirement;
    Step 5 after the completion of backfill, is laid with steel plate in backfilling material top surface, will carry the trailer of existing building along the steel of laying Plate migration is in place, dynamic load when using backfilling material carrying trailer and existing building in place;
    Step 6 installs interim steel drum support (3) at the top for creating the support column (2) in box basis;
    Step 7 is jacked trailer using jack, and the existing building on trailer is ridden upon and is faced after trailer migration is in place When steel drum support (3) top;
    Trailer is landed and is removed using jack by step 8;
    Backfilling material is excavated carry out secondary use by step 9.
  2. 2. existing building according to claim 1 and the construction party for creating dynamic load bearing structure when box basis is docked Method, it is characterised in that: creating in box basis, be respectively provided with structural column along the cross wall for creating box basic two sides (1), and the structural column of two sides (1) is correspondingly arranged;Support column (2) are respectively arranged with inside and outside every structural column (1); The capital of the support column (2) is higher than the capital of structural column (1) and the elevation of top with backfilling material after the completion of engineered fill It is identical;It is connected between every support column (2) and structural column (1) and connect short beam (4).
  3. The construction method of dynamic load bearing structure when 3. existing building according to claim 1 is docked with newly-built basis, It is characterized in that, the material backfilled in step 2 is using the medium coarse sand for meeting design requirement.
  4. The construction method of dynamic load bearing structure when 4. existing building according to claim 1 is docked with newly-built basis, It is characterized in that, in step 4, backfill is carried out according to construction line segmentation and regionalization, backfilling material hanging wire void paving, and by virtual resurfacing thickness In the range of 1000mm~2000mm, the spacing between vibrating head is not more than 1m for control.
  5. The construction method of dynamic load bearing structure when 5. existing building according to claim 1 is docked with newly-built basis, It is characterized in that, in step 4, water rams method and vibrating head water rammer is added to tamp backfilling material method particularly includes: in backfill, It after one layer of backfilling material of every making, is filled the water, so that water filling height is more than the top surface of material, then give a violent shake to tamping with vibrating head;Its In, the spacing range that water rams is 5m~10m.
  6. The construction method of dynamic load bearing structure when 6. existing building according to claim 1 is docked with newly-built basis, It is characterized in that, the compactness required in step 4 is not less than 0.94.
  7. The construction method of dynamic load bearing structure when 7. existing building according to claim 1 is docked with newly-built basis, It is characterized in that, in step 6, the interim corresponding top for being mounted on support column (2) of steel drum support (3), and use chemical anchors Bolt is connect with support column (2).
CN201811195854.4A 2018-10-15 2018-10-15 Construction method of dynamic load bearing structure during butt joint of existing building and newly-built foundation Active CN109083442B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811195854.4A CN109083442B (en) 2018-10-15 2018-10-15 Construction method of dynamic load bearing structure during butt joint of existing building and newly-built foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811195854.4A CN109083442B (en) 2018-10-15 2018-10-15 Construction method of dynamic load bearing structure during butt joint of existing building and newly-built foundation

Publications (2)

Publication Number Publication Date
CN109083442A true CN109083442A (en) 2018-12-25
CN109083442B CN109083442B (en) 2020-10-23

Family

ID=64843375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811195854.4A Active CN109083442B (en) 2018-10-15 2018-10-15 Construction method of dynamic load bearing structure during butt joint of existing building and newly-built foundation

Country Status (1)

Country Link
CN (1) CN109083442B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610882A (en) * 2018-12-26 2019-04-12 北京建工四建工程建设有限公司 A kind of support construction and its construction method for building translation
CN113802879A (en) * 2021-09-23 2021-12-17 山东建筑大学 Trailer jacking building displacement method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1208103A (en) * 1998-07-16 1999-02-17 赵启 Integral building-translating equipment and method
JP2000008623A (en) * 1998-06-26 2000-01-11 Kajima Corp Restoration method of structure
JP2014040703A (en) * 2012-08-21 2014-03-06 Leafair Co Ltd Existent construction ground improvement structure
CN105133856A (en) * 2015-08-14 2015-12-09 山东建筑大学 Method for integrally displacing building by utilizing assembly trailer
CN205088982U (en) * 2015-11-10 2016-03-16 上海先为土木工程有限公司 Whole on -vehicle system of underpining that shifts of building
CN107227862A (en) * 2017-07-12 2017-10-03 叶长青 The gliding construction method of building

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000008623A (en) * 1998-06-26 2000-01-11 Kajima Corp Restoration method of structure
CN1208103A (en) * 1998-07-16 1999-02-17 赵启 Integral building-translating equipment and method
JP2014040703A (en) * 2012-08-21 2014-03-06 Leafair Co Ltd Existent construction ground improvement structure
CN105133856A (en) * 2015-08-14 2015-12-09 山东建筑大学 Method for integrally displacing building by utilizing assembly trailer
CN205088982U (en) * 2015-11-10 2016-03-16 上海先为土木工程有限公司 Whole on -vehicle system of underpining that shifts of building
CN107227862A (en) * 2017-07-12 2017-10-03 叶长青 The gliding construction method of building

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610882A (en) * 2018-12-26 2019-04-12 北京建工四建工程建设有限公司 A kind of support construction and its construction method for building translation
CN109610882B (en) * 2018-12-26 2020-09-29 北京建工四建工程建设有限公司 Support structure for building translation and construction method thereof
CN113802879A (en) * 2021-09-23 2021-12-17 山东建筑大学 Trailer jacking building displacement method

Also Published As

Publication number Publication date
CN109083442B (en) 2020-10-23

Similar Documents

Publication Publication Date Title
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
CN107447778A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN105953078A (en) Protection device and protection method of high-pressure gas pipeline
CN207331740U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN107489164A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN112064751A (en) Deep groove construction method for drainage pipeline
CN109680671A (en) A kind of liquefaction foundation treatment method based on building waste
CN111894023A (en) Construction method of steep-slope bridge foundation
CN214993554U (en) Hydraulic engineering's side slope reinforced structure
CN109083442A (en) The construction method of dynamic load bearing structure when existing building is docked with newly-built basis
CN207331739U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN106869153B (en) A kind of method of the quick soft soil foundation treatment of well-points dewatering
CN206385525U (en) A kind of timber structure for preventing the high backfill earthwork from sinking
CN115506382A (en) Construction method for pile plate wall of island building platform
CN102635044B (en) Treating method of dynamic compacter for excavation roadbed
CN114991165A (en) Construction method for subway deep foundation pit adjacent to railway business line
CN114525808A (en) Construction method for ground beam of edge portal crane of deep foundation pit
CN205223874U (en) Emergent bridge with novel interim abutment
CN109098205B (en) Civil air defense underground passage and construction method thereof
CN105568871A (en) Method for building temporary abutment of emergency bridge by using containers
CN206941614U (en) A kind of slope reinforcement structure
CN215829168U (en) Barricade type roadbed device for controlling settlement of adjacent existing lines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant