Steel girder bridge assembling support system and construction method
Technical field
The present invention relates to construction engineering technical fields, in particular to steel girder bridge assembling support system and construction method.
Background technique
Steel girder bridge is a kind of a kind of structural system between beam and arch, it be by by curved top girder construction with hold
The structure that the lower post of pressure is integrally joined together.Since truss bridge is compared with conventional concrete bridge, the design of structure is more
To be simple, faster, bridge simple installation, truss adapts to the bigger advantage of span scope to the manufacturing speed of component, therefore in engineering
It obtains very extensive.At present steel girder bridge in the construction process, using raft support method come erect bracket, and in this, as top
The support of bridge.But the working rack template consumption of raft support method is big, long in time limit, has very to Bridges in Mountainous Areas and Gao Dun
Big limitation;Secondly steel girder bridge, place the material on the dilatory slideway of one end, is then being constructed using dilatory method construction
In the process, material is run along scheduled slideway route, is finally transported to and is formulated position.But dilatory method needs large-scale traction
Mechanical equipment, and in heave, it is injury-free not can guarantee material, and potential hazard is caused to entire construction.In addition it passes
The construction method of system needs to occupy a large amount of place, to be used to heap putting material and for being parked to transporting equipment, but it is traditional
Construction method is limited place in narrow field or place and can not effectively construct.
Therefore, it needs to seek one kind at present can to construct on small place, and can be to avoid raft support method bring mould
The steel truss assembling support system and construction method of plate consumption and disadvantage long in time limit seem particularly significant.
Summary of the invention
The object of the invention is to overcome drawbacks described above, a kind of steel truss assembling support system and construction method are provided.This
The purpose of invention is achieved through the following technical solutions:
The steel girder bridge assembling support system, it is characterised in that including bottom door opening strutting system and bridge top spliceosome
System;
The bottom door opening strutting system, including two groups of parallel temporary rest piers, cooperation is equipped with U-shaped at the top of each temporary rest pier
Steel, lateral arrangement Bailey bracket forms rack beam in corresponding U-shaped steel in two groups, and Bailey bracket is equipped with backing plate at bottom, in every group
Bridging is set between adjacent temporary rest pier, and temporary rest pier bottom is embedded to underground, and embedment region concrete grouting is closely knit, structure
At concrete foundation;
System is spliced on the bridge top, including the rectangle bridge floor frame surrounded by two side lower booms and two radicle I-steel
Frame, rectangle bridge floor frame are equipped with bridge floor, and side top boom is arranged in parallel in above the lower boom of side, and side top boom and side
Staggeredly one group of abnormity connecting plate of interval setting, side diagonal web member and side erect web member and pass through special-shaped connecting plate setting on the lower boom of face
Between side top boom and side lower boom, installation top diagonal web member and the elongated straight-bar in top, two sides on the top boom of side
Face top boom end is connected by positive side top boom respectively, and the setting top parallel with positive side top boom is logical between the perpendicular web member in two sides
Long straight-bar, positive side top boom lower section are arranged parallel positive side lower boom, positive side are equipped between positive side top boom and positive side lower boom
Web member;Between the elongated straight-bar of positive side top boom and top, top diagonal web member is equipped between the elongated straight-bar of adjacent top.
The steel girder bridge assembling support system, it is characterised in that bridge floor is by bottom transverse direction I-steel and bottom longitudinal direction work
Word steel is connected and composed by bolt and I-shaped steel fastener.
The steel girder bridge assembling support system, it is characterised in that side top boom and difference on the outside of the lower boom of side are equal
The even special-shaped connecting plate of interval setting, and the special-shaped connecting plate of the special-shaped connecting plate of side top boom and side lower boom divides in interlocking
Cloth, side diagonal web member both ends are fixed on special-shaped connecting plate adjacent on side top boom and side lower boom, and web member is erected in side
One end connects special-shaped connecting plate, and the other end connects trapezoidal connecting plate, connects side by special-shaped connecting plate, trapezoidal connecting plate and winds up
Bar and side lower boom.
The steel girder bridge assembling support system, it is characterised in that erect web member inside, the elongated straight-bar in top, positive side in side
Several trapezoidal connecting plates, and the ladder on positive side top boom and positive side lower boom is arranged in uniform intervals on top boom, positive side lower boom
Shape connecting plate position is staggered, and the elongated straight-bar in top is identical as the trapezoidal connecting plate position on positive side top boom, and top is elongated
It is equipped with top diagonal web member between straight-bar and positive side top boom, positive side web member, position are equipped between positive side top boom and positive side lower boom
It is connected on the top boom of side in outermost top diagonal web member, positive side web member end.
The steel girder bridge assembling support system, it is characterised in that web member, the oblique abdomen in side are erected in side top boom, side
Bar, top diagonal web member, the elongated straight-bar in top, positive side top boom, positive side web member, positive side lower boom are I-steel, side lower edge
Bar 9 is U-shaped steel.
The steel girder bridge assembling support system, it is characterised in that end cross I-shaped steel dimensions are greater than bottom longitudinal direction work
Word steel dimensions, bottom longitudinal direction I-shaped steel dimensions are greater than bottom transverse direction I-steel size.
The steel girder bridge assembling support system, it is characterised in that the elongated straight-bar in top passes through bolt and rectangular connecting panels
Riveting is fixed on the perpendicular web member in side and side top boom intersection, adjacent side are erected at the center of web member.
The construction method of the steel girder bridge assembling support system, it is characterised in that include the following steps:
1) temporary rest pier sets up temporary rest pier using steel-pipe pile, composition integrated poured to steel-pipe pile lower position progress concrete
Concrete foundation pours completion to steel-pipe pile lower part, using U-shaped steel to banding is drawn, then arranges that Bailey bracket is formed in U-shaped steel
Crossbeam, and backing plate at bottom is laid on crossbeam, bridging is set with channel steel between adjacent steel-pipe pile;
2) lower boom installation in two sides requires surveying and locating according to detail design, determines the position of side lower boom, and by side
Lower boom is mounted on Bailey bracket top;
3) bottom transverse direction I-steel and bottom longitudinal direction I-steel are installed to side lower boom after the installation is completed, utilize bolt and I-shaped
Two end cross I-steel are connected to the both ends of two sides lower boom by steel fastener, using assembling clamp by bottom longitudinal direction work
Word steel is mounted on end cross I-steel, then bottom transverse direction I-steel is mounted on the I-steel of bottom longitudinal direction, forms bridge floor;
4) side diagonal web member, side erect web member, side top boom outside the venue first will side diagonal web member, side erect web member and side on
Chord member is installed to obtain assembly, it is to be installed it is good after, assembly is hung to suitable position using crane, and using bolt with it is different
Shape connecting plate 5 is riveted on the lower boom of side;
5) top diagonal web member, the elongated straight-bar in top are mounted on side and erect web member and side top boom intersection and the perpendicular abdomen of adjacent side
At the center of bar, the elongated straight-bar of bolt and rectangular connecting panels riveting top is utilized;After after top, elongated straight-bar is installed, by top
Diagonal web member is riveted on the elongated straight-bar in top and side top boom;
6) positive side top boom, positive side web member, positive side lower boom are mounted on the top that web member and side top boom intersection are erected in side
Positive side lower boom is arranged in parallel immediately below elongated straight-bar, positive side lower boom both ends are fixed on side and erect on web member, then by positive flank
Bar is inclined between positive side top boom and positive side lower boom, and positive side top boom is arranged in parallel in same with the elongated straight-bar in top
In plane;
7) floorings construction and installation;
8) temporary rest pier and bottom door opening strutting system are removed.
The construction method of the steel girder bridge assembling support system, it is characterised in that the assembling clamp in step 3) includes
Chassis, chassis middle part are equipped with slide slot, and the round bar of two rod failures cone is movably arranged on slide slot by bar cone, on every round bar
Equipped with matched strap and ambulatory splint, wherein the ambulatory splint upper surface on a round bar is equipped with solid button, Ling Yigen
Ambulatory splint upper surface on round bar is set there are two fixed ring, and motion bar is movably arranged between two fixed rings, on motion bar
Equipped with fixed ring, fixed ring can match snapping with solid button, two ambulatory splints be fixed, it is convex that strap side is equipped with fixation
Platform, ambulatory splint side are equipped with movable boss, and fixing lug boss and the overall length of movable boss are equal to strap length, two work
It moves the width of boss and is matched with the upper surface width of bottom longitudinal direction to be installed I-steel.
The construction method of the steel girder bridge assembling support system, it is characterised in that the installation of bottom longitudinal direction I-steel
Journey is as follows: successively chassis being placed on backing plate at bottom, two straps are placed on end cross I-steel corresponding position, bottom
Portion longitudinal direction I-steel, which is placed on, needs position to be mounted, adjusts position of the round bar on slide slot, makes two straps the bottom of by
Portion longitudinal direction I-steel clamps, then adjusts ambulatory splint, it is made to be close together with end cross I-steel, rotates motion bar, will
Button hole is buckled on solid mouth;Using I-shaped steel fastener, bolt, bottom longitudinal direction I-steel is mounted on end cross I-steel
On;Bottom transverse direction I-steel is mounted on the I-steel of bottom longitudinal direction using identical method.
By using above-mentioned technology, compared with prior art, beneficial effects of the present invention are as follows:
1) present invention is integrated poured using concrete is carried out to steel-pipe pile lower position, completely can be in this, as temporary rest pier
Meet the load requirement of steel truss construction, and small to the demand of template, avoids raft support method because needing using a large amount of moulds
Economic waste caused by plate;In addition the temporary rest pier construction period is shorter compared with raft support method;
2) vertically and horizontally I-steel etc. component is all made of high-strength bolt connection for web member of the invention, top boom, lower boom, bottom.
Its opposite conventional method using welding, speed of application is faster, easy for construction, and small to being influenced by weather;
3) speed of application of the invention is fast, using over-the-counter prefabricated steel member, after element precast is good, then transport to construct now into
Row splices between scene, solves the problems, such as the accumulation in place, and the large-scale traction without using in dilatory method to a certain extent
Equipment.
Detailed description of the invention
Fig. 1 is the main view of steel girder bridge splicing support system;
Fig. 2 is the side view of steel girder bridge splicing support system;
Fig. 3 is the sectional view in Fig. 1;
Fig. 4 is the vertically and horizontally I-steel layout drawing on bridge floor;
Fig. 5 is bolt connection node schematic diagram in Fig. 1;
Fig. 6 is vertically and horizontally I-steel connection schematic diagram in Fig. 4;
Fig. 7 is assembling clamp schematic diagram;
Fig. 8 is that schematic diagram is completed in assembling clamp assembly.
In figure: 1-rectangular connecting panels;Erect web member in 2-sides;3-side top booms;4-bolts hole;5-abnormity connections
Plate;6-side diagonal web members;7-bridgings;8-concrete foundations;9-side lower booms;10-bottom longitudinal direction I-steel;
11-bottom transverse direction I-steel;12-top diagonal web members;The elongated straight-bar in 13-tops;14-positive side top booms;15-positive flanks
Bar;16-trapezoidal connecting plates;17-positive side lower booms;18-backing plate at bottom;19-temporary rest piers;20-I-shaped steel fasteners;
21-bolts;22-bridge floors;23-end cross I-steel;24-U-shaped steels;25-solid buttons;26-ambulatory splints;Gu 27-
Clamp plate;28-fixed rings;29-motion bars;30-button holes;31-Bailey brackets;32-round bars;33-chassis;34-slide
Slot;35-bars cone.
Specific embodiment
Below in conjunction with Figure of description, the invention will be further described, but protection scope of the present invention is not limited in
This:
As shown in figures 1-8, steel girder bridge assembling support system of the invention, including bottom door opening strutting system and bridge top are spelled
Junctor system;
The bottom door opening strutting system, including two groups of parallel temporary rest piers 19, cooperation is equipped with U at the top of each temporary rest pier 19
Fashioned iron 24, lateral arrangement Bailey bracket 31 forms rack beam in corresponding U-shaped steel 24 in two groups, and Bailey bracket 31 is equipped with bottom pad
Bridging 7 is arranged in every group for plate 18 between adjacent temporary rest pier 19,19 bottom of temporary rest pier is embedded to underground, and is embedded to region and uses
Concrete grouting is closely knit, constitutes concrete foundation 8;
System is spliced on the bridge top, including the rectangle bridge surrounded by two side lower booms 9 and two radicle I-steel 23
Surface frame frame, rectangle bridge floor frame are equipped with bridge floor 22, and bridge floor 22 is led to by bottom transverse direction I-steel 11 and bottom longitudinal direction I-steel 10
Bolt 21 is crossed to connect and compose with I-shaped steel fastener 20;Side top boom 3 is arranged in parallel in 9 top of side lower boom, and side
Staggeredly one group of abnormity connecting plate 5 of interval setting, side diagonal web member 6 and side are erected web member 2 and are led on top boom 3 and side lower boom 9
It crosses special-shaped connecting plate 5 to be arranged between side top boom 3 and side lower boom 9, installation top diagonal web member 12 on side top boom 3
With the elongated straight-bar 13 in top, two 3 ends of side top boom are connected by positive side top boom 14 respectively, and two sides are erected between web member 2
The elongated straight-bar 13 in the top parallel with positive side top boom 14 is set, parallel positive side lower boom is set below positive side top boom 14
17, positive side web member 15 is equipped between positive side top boom 14 and positive side lower boom 17;Positive side top boom 14 and the elongated straight-bar 13 in top
Between, between the elongated straight-bar 13 of adjacent top be equipped with top diagonal web member 12.
As shown in Figs. 1-5, the special-shaped connecting plate 5 of uniform intervals setting is distinguished on the outside of side top boom 3 and side lower boom 9,
And the special-shaped connecting plate 5 of side top boom 3 and the special-shaped connecting plate 5 of side lower boom 9 are interspersed, 6 liang of side diagonal web member
End is fixed on special-shaped connecting plate 5 adjacent on side top boom 3 and side lower boom 9, and 2 one end of web member connection abnormity is erected in side
Connecting plate 5, the other end connect trapezoidal connecting plate 16, by special-shaped connecting plate 5, trapezoidal connecting plate 16 connect side top boom 3 with
Side lower boom 9;Side erect 2 inside of web member, on the elongated straight-bar 13 in top, positive side top boom 14, positive side lower boom 17 uniformly between
Every several trapezoidal connecting plates 16 of setting, and positive side top boom 14 is staggeredly set with 16 position of trapezoidal connecting plate on positive side lower boom 17
It sets, the elongated straight-bar 13 in top is identical as 16 position of trapezoidal connecting plate on positive side top boom 14, the elongated straight-bar 13 in top and positive side
It is equipped with top diagonal web member 12 between top boom 14, positive side web member 15, position are equipped between positive side top boom 14 and positive side lower boom 17
It is connected on side top boom 3 in outermost top diagonal web member 12,15 end of positive side web member.
Web member 2, side diagonal web member 6, top diagonal web member 12, the elongated straight-bar in top are erected in side top boom 3 of the invention, side
13, positive side top boom 14, positive side web member 15, positive side lower boom 17 are I-steel, and side lower boom 9 is U-shaped steel;End cross
23 size of I-steel is greater than 10 size of bottom longitudinal direction I-steel, and I-steel 10 size in bottom longitudinal direction is greater than bottom transverse direction I-steel 11
Size;The elongated straight-bar 13 in top is fixed on the perpendicular web member 2 in side by bolt and the riveting of rectangular connecting panels 1 and hands over side top boom 3
At remittance, at the center of the perpendicular web member 2 of adjacent side.
As shown in Figure 7 and Figure 8, the assembling clamp includes chassis 33, is equipped with slide slot 34, two rod failures in the middle part of chassis 33
The round bar 32 of cone 35 is movably arranged on slide slot 34 by bar cone 35, and every round bar 32 is equipped with matched 27 He of strap
Ambulatory splint 26, wherein 26 upper surface of ambulatory splint on a round bar 32 is equipped with solid button 25, the work on another round bar 32
Dynamic 26 upper surface of clamping plate sets that there are two fixed rings 28, and motion bar 29 is movably arranged between two fixed rings 28, on motion bar 29
Equipped with fixed ring 28, fixed ring 28 can match snapping with solid button 25, two ambulatory splints 26 are fixed, 27 side of strap
Equipped with fixing lug boss 27a, 26 side of ambulatory splint is equipped with the overall length of activity boss 26a, fixing lug boss 27a and movable boss 26a
Equal to 27 length of strap, the width of two movable boss 26a and the upper surface width with bottom longitudinal direction to be installed I-steel 10
Matching.
As shown, the construction method of the steel girder bridge assembling support system, includes the following steps:
1) temporary rest pier 19 sets up temporary rest pier 19 and uses steel-pipe pile, integrated poured to steel-pipe pile lower position progress concrete,
Concrete foundation 8 is constituted, completion is poured to steel-pipe pile lower part, using 24 pairs of drawing bandings of U-shaped steel, is then arranged in U-shaped steel 24
Bailey bracket 31 forms crossbeam, and backing plate at bottom 18 is laid on crossbeam, and bridging 7 is arranged with channel steel between adjacent steel-pipe pile;
2) installation of two sides lower boom 9 requires surveying and locating according to detail design, determines the position of side lower boom 9, and by side
Face lower boom 9 is mounted on 31 top of Bailey bracket;
3) bottom transverse direction I-steel 11 and bottom longitudinal direction I-steel 10 are installed to side lower boom 9 after the installation is completed, utilize bolt
Two end cross I-steel 23 are connected to the both ends of two sides lower boom 9 with I-shaped steel fastener 20, utilize assembling clamp
Bottom longitudinal direction I-steel 10 is mounted on end cross I-steel 23, the installation process of bottom longitudinal direction I-steel 10 is as follows: according to
It is secondary chassis 33 is placed on backing plate at bottom 18, two straps 27 are placed on 23 corresponding position of end cross I-steel, bottom
Portion longitudinal direction I-steel 10, which is placed on, needs position to be mounted, adjusts position of the round bar 32 on slide slot 34, makes two fixing clamps
Plate 27 clamps bottom longitudinal direction I-steel 10, then adjusts ambulatory splint 26, it is made to be close together with end cross I-steel 23,
Motion bar 29 is rotated, button hole 30 is buckled on solid mouth 25;Using I-shaped steel fastener 20, bolt 21, by bottom longitudinal direction I-shaped
Steel 10 is mounted on end cross I-steel 23;Bottom transverse direction I-steel 11 is mounted on bottom longitudinal direction work using identical method
On word steel 10, bridge floor 22 is formed;
4) side diagonal web member 6, side erect web member 2, side top boom 3 outside the venue first by side diagonal web member 6, side erect web member 2 with
Side top boom 3 is installed to obtain assembly, it is to be installed it is good after, assembly is hung to suitable position using crane, and utilize
Bolt and special-shaped connecting plate 5 are riveted on side lower boom 9;
5) top diagonal web member 12, the elongated straight-bar 13 in top are mounted on side and erect web member 2 and 3 intersection of side top boom and sides adjacent
Face is erected at the center of web member 2, and the elongated straight-bar 13 of bolt and the riveting of rectangular connecting panels 1 top is utilized;Pacify to the elongated straight-bar 13 in top
After installing, top diagonal web member 12 is riveted on the elongated straight-bar 13 in top and side top boom 3;
6) positive side top boom 14, positive side web member 15, positive side lower boom 17 are mounted on the perpendicular web member 2 in side and cross with side top boom 3
Positive side lower boom 17 is arranged in parallel immediately below the elongated straight-bar 13 in the top at place, 17 both ends of positive side lower boom are fixed on side and erect web member
On 2, then positive side web member 15 is inclined between positive side top boom 14 and positive side lower boom 17, positive side top boom 14 and top
Elongated straight-bar 13 is arranged in parallel in the same plane;
7) floorings construction and installation;
8) temporary rest pier 19 and bottom door opening strutting system are removed.
The above-mentioned specific embodiment technical solution that the invention is not limited in any way, it is all to use equivalent replacement or wait
The mode technical solution obtained of effect transformation all falls within protection scope of the present invention.