CN109056738A - Excavation method below high-speed railway - Google Patents

Excavation method below high-speed railway Download PDF

Info

Publication number
CN109056738A
CN109056738A CN201810947981.9A CN201810947981A CN109056738A CN 109056738 A CN109056738 A CN 109056738A CN 201810947981 A CN201810947981 A CN 201810947981A CN 109056738 A CN109056738 A CN 109056738A
Authority
CN
China
Prior art keywords
foundation pit
speed railway
excavation
foundation
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810947981.9A
Other languages
Chinese (zh)
Inventor
王佳武
黄剑
鲜炳林
张继培
周志伟
徐文豪
张晓声
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201810947981.9A priority Critical patent/CN109056738A/en
Publication of CN109056738A publication Critical patent/CN109056738A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of high-speed railway lower section excavation method.It includes constituting foundation pit support system;Foundation pit inside is segmented, is excavated paragraph by paragraph, every section uses from top to bottom, the stage excavation mode of two sides behind first middle part;The foundation soil heap excavated out is loaded on the ground between foundation pit and two high-speed railway bridge pier cushion caps adjacent with foundation pit;After required heap carrying capacity to be achieved, no longer preloading;Digging process monitors the deformation real-time perfoming of high-speed railway bridge pier and foundation pit;Main body construction is carried out rapidly, gradually decreases heap carrying capacity;After the completion of construction, the foundation soil of remaining preloading on the ground is all removed and etc..The invention has the advantages that the deflection that can be effectively controlled high-speed railway bridge pier in permissible range, ensure that the safety of high-speed railway.It ensure that the stability of foundation pit, it is ensured that construction safety.Important construction procedure has all carried out the calculating of science, and in conjunction with real-time monitoring, work progress substantially reduces risk factors, has very strong dissemination.

Description

Excavation method below high-speed railway
Technical field
The invention belongs to rail facility construction method technical fields, more particularly to excavation of foundation pit below a kind of high-speed railway Construction method.
Background technique
With the rapid development of China's Urbanization Construction and the complication of traffic route, base is excavated below high-speed railway The case where hole, is more and more, and how to guarantee to be located at the stability of foundation pit and the safety of high-speed railway below high-speed railway becomes hardly possible Point.When foundation pit is in below high-speed railway, foundation pit two sides are adjacent with high-speed railway bridge pier, after excavating foundation soil in foundation pit, It is influenced by foundation pit distant place building and other loads, entire foundation pit position and surrounding soil will be emerged in large numbers in presentation as i.e. foundation pit Surrounding soil floats.In addition, will drive pier footing when foundation pit surrounding soil is sprung up upwards and also move together, to make height Floating trend is also presented in fast Railway Bridges And Piers, causes the bridge pier relative settlement of closing foundation ditch two sides is opposite to increase, causes high-speed railway Roadbed deforms, once deflection exceeds warning value, will seriously affect traffic safety.Excavation of foundation pit is mainly pressed at this stage It is carried out according to normal construction method and code requirement, but for sedimentation, the higher high-speed railway of deformation requirements, thereunder Excavation pit, it is necessary to use scientific and rational construction method, construction safety be ensured in conjunction with Precision measurement, and then guarantee high speed Railway security.But at present it is not yet found that the construction method of effect.
Summary of the invention
To solve the above-mentioned problems, the purpose of the present invention is to provide excavation sides below a kind of high-speed railway Method.
In order to achieve the above object, below high-speed railway provided by the invention excavation method include in order into Capable the following steps:
1) foundation pit enclosure stake, anti-shifting stake are set in foundation pit surrounding position to be excavated by construction personnel first, and in base It cheats in the ground in outside and sets subgrade protection stake;Then it is arranged more between the foundation pit enclosure stake top portion for being located at foundation pit two sides Reinforced concrete support and bracing members, thus constitute foundation pit support system;
2) inside of entire foundation pit is divided at least two excavation sections along its length, then from close to high-speed railway bridge pier One end carry out the excavation of foundation pit paragraph by paragraph to the other end, and every section using from top to bottom, first behind middle part two sides stage excavation Mode;
3) when just being excavated, the foundation soil heap excavated out is loaded in foundation pit and two High-speed Railway Bridges adjacent with foundation pit On ground between pier cushion cap, heap carrying capacity must first pass through calculating in advance and determine;
4) after required heap carrying capacity to be achieved, other foundation soils are transported to the designated place outside construction site by no longer preloading;
5) in digging process, the deformation real-time perfoming of high-speed railway bridge pier and foundation pit is monitored, once discovery high-speed iron The deflection of road and bridge pier and/or foundation pit exceeds respective deflection early warning value, or encounters and be mutated larger situation, stops applying immediately Work analyzes reason, and takes corresponding corrective action;
6) after the completion of the excavation of foundation pit, main body construction is carried out rapidly;With the progress of main body construction process, gradually decrease Heap carrying capacity, while monitoring data are paid close attention to, forbid disposably all to remove the foundation soil of preloading on the ground, to prevent height There is jumping phenomenon in fast Railway Bridges And Piers, to influence traffic safety;
7) after the completion of constructing, the foundation soil of remaining preloading on the ground is all removed.
In step 2), the length of the excavation section is 40 ± 10m;When stage excavation every layer with a thickness of 1m.
In step 5), the deflection early warning value of the high-speed railway bridge pier is 2.75mm;The deflection early warning of foundation pit 1 Value is 6.4mm.
Excavation method has the advantages that below high-speed railway provided by the invention
First, the deflection of high-speed railway bridge pier can be efficiently controlled in permissible range, ensure that the peace of high-speed railway Entirely.
Second, it ensure that the stability of foundation pit, it is ensured that construction safety.
Third, important construction procedure have all carried out the calculating of science, and in conjunction with real-time monitoring, work progress substantially reduces wind Dangerous factor has very strong dissemination.
Detailed description of the invention
Fig. 1 is to utilize base when excavation method makes foundation pit support system below high-speed railway provided by the invention Cheat structural plan figure.
Fig. 2 is to utilize foundation pit structure plane when excavation method is excavated below high-speed railway provided by the invention Figure.
Fig. 3 is to be shown using foundation pit longitudinal direction section when excavation method is excavated below high-speed railway provided by the invention It is intended to.
Fig. 4 is to be shown using foundation pit transverse direction section when excavation method is excavated below high-speed railway provided by the invention It is intended to.
Specific embodiment
In the following with reference to the drawings and specific embodiments to excavation method below high-speed railway provided by the invention into Row is described in detail.
As shown in Fig. 1-Fig. 4, excavation method includes carrying out in order below high-speed railway provided by the invention The following steps:
1) foundation pit enclosure stake 2, anti-shifting stake 3 are set in 1 surrounding position of foundation pit to be excavated by construction personnel first, and Subgrade protection stake 4 is set in the ground in 1 outside of foundation pit;Then it is set between 2 top of foundation pit enclosure stake for being located at 1 two sides of foundation pit More reinforced concrete supports 5 and bracing members 6 are set, foundation pit support system is thus constituted;
2) inside of entire foundation pit 1 is divided at least two excavation sections along its length, then from close to High-speed Railway Bridges One end of pier carries out the excavation of foundation pit 1 to the other end paragraph by paragraph, and every section uses from top to bottom, and first the layering of two sides is opened behind middle part Excavation formula, for example when excavation first segment first layer, first excavate the foundation soil at the intermediate position of this layer, then symmetrically excavate the layer two again The foundation soil of side, excavates the second layer again later, and so on, the digging process until being fully completed this section;Then this is pressed Method excavates next section;In the present embodiment, the length of the excavation section is 40 ± 10m;Every layer of thickness when stage excavation For 1m;
3) when just being excavated, the foundation soil heap excavated out is loaded in foundation pit 1 and two high-speed railways adjacent with foundation pit 1 On ground between pier cap 7, as shown in Figure 2,3, heap carrying capacity must first pass through calculating in advance and determine in preloading region 8, calculate first Preloading extent of injury caused by foundation pit supporting system, it is ensured that preloading does not influence foundation pit 1 or in foundation pit supporting system institute In the coverage that can be born;Secondly the size of high-speed railway bridge pier Float upward function power can be offset by calculating preloading;
4) after required heap carrying capacity to be achieved, other foundation soils are transported to the designated place outside construction site by no longer preloading;
5) in digging process, the deformation real-time perfoming of high-speed railway bridge pier and foundation pit 1 is monitored, once discovery high-speed iron The deflection of road and bridge pier and/or foundation pit 1 exceeds respective deflection early warning value, or encounters and be mutated larger situation, stops immediately Construction analyzes reason, and takes corresponding corrective action;In the present embodiment, the deflection of the high-speed railway bridge pier is pre- Alert value is 2.75mm;The deflection early warning value of foundation pit 1 is 6.4mm;
6) after the completion of the excavation of foundation pit 1, main body construction is carried out rapidly;With the progress of main body construction process, gradually subtract Few heap carrying capacity, while monitoring data are paid close attention to, forbid disposably all to remove the foundation soil of preloading on the ground, to prevent There is jumping phenomenon in high-speed railway bridge pier, to influence traffic safety;
7) after the completion of constructing, the foundation soil of remaining preloading on the ground is all removed.

Claims (3)

1. a kind of excavation method below high-speed railway, it is characterised in that: the construction method include in order into Capable the following steps:
1) foundation pit enclosure stake (2), anti-shifting stake (3) are set in foundation pit (1) surrounding position to be excavated by construction personnel first, and Subgrade protection stake (4) are set in the ground on the outside of foundation pit (1);Then in the foundation pit enclosure stake (2) for being located at foundation pit (1) two sides More reinforced concrete supports (5) and bracing members (6) are set between top, thus constitute foundation pit support system;
2) inside of entire foundation pit (1) is divided at least two excavation sections along its length, then from close to high-speed railway bridge pier One end carry out the excavation of foundation pit (1) paragraph by paragraph to the other end, and every section using from top to bottom, and first the layering of two sides is opened behind middle part Excavation formula;
3) when just being excavated, the foundation soil heap excavated out is loaded in foundation pit (1) and two high-speed railways adjacent with foundation pit (1) On ground between pier cap (7), heap carrying capacity must first pass through calculating in advance and determine;
4) after required heap carrying capacity to be achieved, other foundation soils are transported to the designated place outside construction site by no longer preloading;
5) in digging process, the deformation real-time perfoming of high-speed railway bridge pier and foundation pit (1) is monitored, once discovery high-speed railway The deflection of bridge pier and/or foundation pit (1) exceeds respective deflection early warning value, or encounters and be mutated larger situation, stops immediately Construction analyzes reason, and takes corresponding corrective action;
6) after the completion of the excavation of foundation pit (1), main body construction is carried out rapidly;With the progress of main body construction process, gradually decrease Heap carrying capacity, while monitoring data are paid close attention to, forbid disposably all to remove the foundation soil of preloading on the ground, to prevent height There is jumping phenomenon in fast Railway Bridges And Piers, to influence traffic safety;
7) after the completion of constructing, the foundation soil of remaining preloading on the ground is all removed.
2. excavation method below high-speed railway according to claim 1, it is characterised in that: in step 2), The length of the excavation section is 40 ± 10m;When stage excavation every layer with a thickness of 1m.
3. excavation method below high-speed railway according to claim 1, it is characterised in that: in step 5), The deflection early warning value of the high-speed railway bridge pier is 2.75mm;The deflection early warning value of foundation pit (1) is 6.4mm.
CN201810947981.9A 2018-08-20 2018-08-20 Excavation method below high-speed railway Withdrawn CN109056738A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810947981.9A CN109056738A (en) 2018-08-20 2018-08-20 Excavation method below high-speed railway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810947981.9A CN109056738A (en) 2018-08-20 2018-08-20 Excavation method below high-speed railway

Publications (1)

Publication Number Publication Date
CN109056738A true CN109056738A (en) 2018-12-21

Family

ID=64687494

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810947981.9A Withdrawn CN109056738A (en) 2018-08-20 2018-08-20 Excavation method below high-speed railway

Country Status (1)

Country Link
CN (1) CN109056738A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778599A (en) * 2019-01-29 2019-05-21 兰州交通大学 Infiltration coefficient in-situ intelligent measuring method under a kind of high-speed rail ground mud stone overlying burden
CN110067216A (en) * 2019-05-15 2019-07-30 中国电建集团中南勘测设计研究院有限公司 A kind of construction method of weak soil section culvert

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101761068A (en) * 2009-11-10 2010-06-30 同济大学 Box-raft pressure-bearing type foundation underpinning and construction reinforcing method for tunnel across pile foundation of bridge above river
CN102505697A (en) * 2011-11-10 2012-06-20 中铁十七局集团有限公司 Method for excavating deep foundation pits under temporary bridge of main line railway
CN107142948A (en) * 2017-05-18 2017-09-08 河北省高速公路廊坊北三县管理处 A kind of highway wears high ferro viaduct system and construction method without pre- leave

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101761068A (en) * 2009-11-10 2010-06-30 同济大学 Box-raft pressure-bearing type foundation underpinning and construction reinforcing method for tunnel across pile foundation of bridge above river
CN102505697A (en) * 2011-11-10 2012-06-20 中铁十七局集团有限公司 Method for excavating deep foundation pits under temporary bridge of main line railway
CN107142948A (en) * 2017-05-18 2017-09-08 河北省高速公路廊坊北三县管理处 A kind of highway wears high ferro viaduct system and construction method without pre- leave

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
唐业清等: "《特种工程新技术2009》", 31 October 2009, 中国建材工业出版社 *
郭全元: "基坑开挖对临近城际铁路高架桥墩的影响分析", 《铁道施工技术》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778599A (en) * 2019-01-29 2019-05-21 兰州交通大学 Infiltration coefficient in-situ intelligent measuring method under a kind of high-speed rail ground mud stone overlying burden
CN109778599B (en) * 2019-01-29 2023-08-22 兰州交通大学 In-situ intelligent determination method for permeability coefficient of high-speed railway foundation mudstone under overburden load
CN110067216A (en) * 2019-05-15 2019-07-30 中国电建集团中南勘测设计研究院有限公司 A kind of construction method of weak soil section culvert

Similar Documents

Publication Publication Date Title
CN101831873B (en) Temporary bridge covered excavation method for constructing box culvert below traffic ground line of operating track
CN102352590B (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN111396095B (en) Tunnel simple arch open cut tunnel structure penetrating through huge karst cave and construction method thereof
CN105804119A (en) Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure
CN111139721A (en) Frame bridge penetrating existing railway bridge downwards and construction method thereof
CN111172833A (en) Construction method of steep slope high embankment structure
CN109056738A (en) Excavation method below high-speed railway
CN111411992A (en) Integrated structure system penetrating through giant karst cave and construction method thereof
CN108708290B (en) Box bridge frame hollow structure of small-radius railway curve unit and cast-in-place construction method
CN111501451B (en) Construction method for jacking municipal frame bridge
CN107152281A (en) The construction method of fractured rock tunnel Xia Chuan abrupt slopes high pier
CN209669718U (en) A kind of existing hangar tunnel combination stone cut off wall structure of rockfall protection
CN104652299B (en) Construction method is shifted out in the whole hole of a kind of existing bridges and culverts of electric railway
CN111041995B (en) Construction method for U-shaped frame structure to penetrate high-speed rail bridge obliquely downwards
CN212154795U (en) Integral structure system for passing through giant karst cave
CN105625184A (en) Subway station building method using bridge and station combined building mode
CN114790748A (en) Construction method for deep foundation pit near existing line
CN204151662U (en) A kind of one across the temporary trestle bridge crossing over river valley
CN109555173A (en) A kind of separate type bridge integrally lifts stake reinforcement means
CN113389218A (en) Retaining wall structure for entrance and exit of road bridge and construction method thereof
RU180833U1 (en) DEVICE FOR PROTECTING THE RAILWAY
CN106555379A (en) Pass through both wired elevated formation level Combined temporary bridge construction methods
CN220888347U (en) Newly-built shield tunnel is worn existing river course railway bridge under and is reformed transform structure
CN211872560U (en) Frame bridge of existing railway bridge is worn down
CN211898526U (en) Pile foundation underpinning protection device based on limited space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Qi Pengyu

Inventor after: Wang Jiawu

Inventor after: Huang Jian

Inventor after: Xian Binglin

Inventor after: Zhang Jipei

Inventor after: Zhou Zhiwei

Inventor after: Xu Wenhao

Inventor after: Zhang Xiaosheng

Inventor before: Wang Jiawu

Inventor before: Huang Jian

Inventor before: Xian Binglin

Inventor before: Zhang Jipei

Inventor before: Zhou Zhiwei

Inventor before: Xu Wenhao

Inventor before: Zhang Xiaosheng

WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20181221