CN108999195B - It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula - Google Patents

It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula Download PDF

Info

Publication number
CN108999195B
CN108999195B CN201810960618.0A CN201810960618A CN108999195B CN 108999195 B CN108999195 B CN 108999195B CN 201810960618 A CN201810960618 A CN 201810960618A CN 108999195 B CN108999195 B CN 108999195B
Authority
CN
China
Prior art keywords
grouting
drilling
water
side wall
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810960618.0A
Other languages
Chinese (zh)
Other versions
CN108999195A (en
Inventor
林春金
张猛
戴文杰
王孝特
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201810960618.0A priority Critical patent/CN108999195B/en
Publication of CN108999195A publication Critical patent/CN108999195A/en
Application granted granted Critical
Publication of CN108999195B publication Critical patent/CN108999195B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention discloses formula safe grouting construction process in step heap weir in a kind of stratum of closure larger water burst of deep-foundation side wall.It include: to be observed the water yield and quantity of sand and mud of foundation pit deep side wall, calculated;Tapping pipe is arranged in issue to sluice;Back-pressure body is set around issue, back-pressure is formed to the foundation pit side-wall around issue;It is drilling on the ground of side wall where issue, is drilling and be at least divided into two rows, it is the first row hole drilling by proximal wall prop that the depth of the first row hole drilling and the second row hole drilling, which is in up/down steps formula, is successively reduced according to sequence, drilling depth outward;Slip casting blocks.The vertical drilling of rapid construction on the ground of the side-wall outer side locating for the issue of foundation pit deep, aggregate is injected into the cavity of conduit pipe or formation and with the anti-slurries for dispersing early strong rapid hardening by drilling, the curtain that blocks water quickly is formed in water burst stratum, block underground water gushing channelway, reach and quickly administer water burst, the purpose of grouting and reinforcing is carried out to the stratum destroyed by water burst.

Description

一种封堵深基坑侧壁较大涌水的地层内台阶堆堰式安全注浆 施工工艺A kind of safety grouting of step and weir type in the formation to block the large water gushing from the side wall of deep foundation pit construction technology

技术领域technical field

本发明属于城市地铁隧道、建筑等深基坑侧壁深部较大涌水的注浆封堵领域,特别是涉及一种封堵深基坑侧壁较大涌水的地层内台阶堆堰式安全注浆施工工艺。The invention belongs to the field of grouting plugging of relatively large water gushing deep in the side walls of deep foundation pits such as urban subway tunnels and buildings, and in particular relates to a step stacking weir type safety grouting in strata for sealing large water gushing in the side walls of deep foundation pits construction process.

背景技术Background technique

在修建城市地铁隧道车站、高层建筑开挖深基坑时,经常会遇到基坑深部侧壁出现水量不低于10m3/h的较大涌水现象。涌水后,给工程带来很大安全威胁。经分析深基坑深部遇到的涌水来源主要为地下潜水、地表河流侧向补给或地下管线(污水、雨水等)的严重泄漏。涌水点一般位于杂填土,砂砾、粉沙、粉土等松散地层或土岩结合面处。这类地层孔隙率高,含导水能力强。因为基坑深处涌水带有一定的压力,故呈现集中的较大流量的股状涌水,呈喷射状。涌水口被临时封堵后,水位会迅速升高,并在基坑侧壁其他位置出现多处涌水现象,对侧壁的稳定性危害较大。当深基坑出现较大涌水后,涌水会呈股状急速涌出,并携带出大量泥沙。若涌水得不到有效处理,大量泥沙溃出后,在涌水点处的周围地层内形成空洞,引起上覆地层沉降,甚至引发地面的沉陷;基坑侧壁在地层沉陷的动载荷作用下,出现严重失稳现象,出现基坑侧壁及其支护体的垮塌,严重时出现较为严重的突水突泥事故。When constructing urban subway tunnel stations and excavating deep foundation pits for high-rise buildings, it is often encountered that there is a large water gushing phenomenon with a water volume of not less than 10m 3 /h on the deep side walls of the foundation pit. After the flooding, it brought a great security threat to the project. After analysis, the sources of water gushing in the deep part of the deep foundation pit are mainly underground diving, lateral recharge of surface rivers, or serious leakage of underground pipelines (sewage, rainwater, etc.). Water gushing points are generally located in loose strata such as miscellaneous fill, gravel, silt, silt, or soil-rock joints. This type of formation has high porosity and strong water conductivity. Because the water gushing deep in the foundation pit has a certain pressure, it presents a concentrated stream of relatively large flow of water gushing in the form of a jet. After the water gushing outlet is temporarily blocked, the water level will rise rapidly, and there will be many water gushing phenomena at other positions on the side wall of the foundation pit, which will greatly harm the stability of the side wall. When a large water gushing occurs in a deep foundation pit, the gushing water will rush out in strands and carry a large amount of sediment. If the gushing water cannot be effectively treated, a large amount of sand will burst out, forming cavities in the surrounding strata at the gushing point, causing the overlying strata to subside, and even causing ground subsidence; the side wall of the foundation pit is under the dynamic load of stratum subsidence , there will be serious instability, the collapse of the side wall of the foundation pit and its supporting body, and serious water and mud inrush accidents will occur.

当基坑出现较小的涌水(比如侧壁荫水,较大较大面积的分散的点状渗水或较小的股状涌水等)后,当分析后认为不会出现较大险情时,一般常用的处治方法是在涌水点处的侧壁上施工注浆锚杆,注浆锚杆注浆后起到锚注双重作用。利用注浆锚杆对基坑侧壁支护体后的空隙内注入水泥浆或化学浆液,起到封堵较小涌水的现象。因这种荫水渗水情况下水量较小,携带泥沙的能力弱,短时间内不会引起基坑壁后地层的较为严重的沉降,因此也不会出现较严重的地层沉陷失稳的灾害。但一旦出现较大量的持续时间较长的股状涌水后,说明涌水具有较强的水源补给能力和较为畅通的导水通道。因为具有一定的压力,水流流速较大,对导水通道围岩的冲刷破坏能力较强,携带泥沙能力较强,会迅速把导水通道周围的地层搬空,就会出现地表沉陷,基坑侧壁垮塌甚至突水突泥等严重事故。在这种情况下,利用侧壁锚杆注浆的方法因为注浆量小、难以达到持续大量注浆的要求,而且锚杆注浆深度浅,为与水流方向相逆的顶水注浆,浆液扩散范围小,注入的浆液大部分被水流冲出,堵水效果较差,施工工期较长,有可能在没有来的及达到治理效果,就会出现严重垮塌沉陷事故。而且施工人员要靠近涌水侧壁,人身安全风险较高。When there is a small water gushing in the foundation pit (such as shady water on the side wall, scattered point-like water seepage in a large and large area, or small strand-like water gushing, etc.), when it is considered that there will be no major danger after analysis, generally A common treatment method is to construct a grouting anchor rod on the side wall at the water gushing point, and the grouting anchor rod plays a dual role of anchoring and grouting after grouting. Use the grouting bolt to inject cement slurry or chemical slurry into the gap behind the support body of the side wall of the foundation pit to block the phenomenon of small water gushing. Due to the small amount of water and the weak ability to carry sediment under the condition of shady water seepage, it will not cause serious subsidence of the strata behind the foundation pit wall in a short period of time, so there will be no serious stratum subsidence and instability disasters . However, once a large amount of long-lasting strand-shaped water gushing occurs, it shows that the gushing water has a strong water supply capacity and a relatively smooth water-conducting channel. Due to the certain pressure, the water flow velocity is relatively high, the ability to scour and destroy the surrounding rock of the aqueduct is strong, and the ability to carry sediment is strong, and the strata around the aqueduct will be evacuated quickly, and the surface subsidence will occur. Serious accidents such as pit side wall collapse or even water and mud inrush. In this case, the grouting method using side wall bolts is difficult to meet the requirements of continuous large-scale grouting due to the small amount of grouting, and the grouting depth of the bolts is shallow, which is top water grouting opposite to the direction of water flow. The grout diffusion range is small, most of the injected grout is washed out by the water flow, the water blocking effect is poor, and the construction period is long. It is possible that serious collapse and subsidence accidents will occur before the treatment effect is achieved. Moreover, construction workers have to be close to the side wall of the gushing water, which poses a high risk to personal safety.

专利CN201710977510.8公开了一种基坑涌水快速抢险注浆封堵方法,包括以下步骤:险情发生后进行及时反压及泄压管的放置;确定基坑出水点位置,在基坑侧壁距离灌注桩一定位置即旋喷桩轴线位置处进行地表钻孔施工,当钻孔施工至导水通道位置处,下一定长度套管并下PVC管至导水通道位置处;将注浆泵管路与PVC管连接,打开注浆泵泵送水泥浆单液;当从泄压管处观察到有水泥浆流出,开始注速凝类浆液,浆液在导水通道内迅速凝结硬化,直至泄压管不再有水流出,至此实现对导水通道的完全封堵。该方法可实现基坑侧壁涌水的快速封堵,对基坑侧壁涌水灾害应急性处理具有重要作用。Patent CN201710977510.8 discloses a rapid emergency grouting plugging method for foundation pit water gushing, which includes the following steps: timely back pressure and pressure relief pipe placement after the danger occurs; determine the position of the water outlet point of the foundation pit, and the distance between The surface drilling construction is carried out at a certain position of the cast-in-place pile, that is, the axial position of the rotary grouting pile. When the drilling construction reaches the position of the water guide channel, a certain length of casing is lowered and the PVC pipe is lowered to the position of the water guide channel; the grouting pump pipeline Connect with the PVC pipe, turn on the grouting pump to pump the single liquid of cement slurry; when the cement slurry is observed to flow out from the pressure relief pipe, start injecting quick-setting grout, and the slurry will harden rapidly in the water guide channel until the pressure relief pipe No more water flows out, so far the complete blocking of the water guide channel is realized. This method can realize rapid sealing of water inrush on the side wall of the foundation pit, and plays an important role in emergency treatment of water inrush disasters on the side wall of the foundation pit.

发明内容Contents of the invention

针对上述现有技术存在的不足,本发明提供了一种封堵深基坑侧壁较大涌水的地层内台阶堆堰式安全注浆施工工艺。即在基坑深部涌水点所处的侧壁外侧的地面上快速施工垂向钻孔,通过钻孔向导水通道或形成的空洞内注入骨料和具有抗分散早强速凝的特殊浆液,在涌水地层内快速形成阻水帷幕,封堵地下涌水通道,达到快速治理涌水,并对被涌水破坏的地层进行注浆加固的目的。In view of the deficiencies in the above-mentioned prior art, the present invention provides a safety grouting construction technology of step and weir type in the formation to block relatively large water gushing from the side wall of a deep foundation pit. That is, vertical drilling is rapidly constructed on the ground outside the side wall where the deep water gushing point of the foundation pit is located, and aggregate and special slurry with anti-dispersion, early strength and quick-setting are injected into the water guide channel or the formed cavity through the drilling hole. A water-blocking curtain is quickly formed in the water gushing formation to block the underground water gushing channel, so as to quickly control the water gushing and to perform grouting reinforcement on the stratum damaged by the gushing water.

为了实现上述目的,本发明采用如下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

一种封堵深基坑侧壁较大涌水的地层内台阶堆堰式安全注浆施工方法,包括:A safety grouting construction method of step-stack weir type in strata for blocking relatively large water gushing from the side wall of a deep foundation pit, comprising:

对基坑深部侧壁的涌水量和泥沙量进行观察、计算;Observe and calculate the amount of water inflow and sediment on the deep side wall of the foundation pit;

在涌水点内设置泄水管进行泄水;Set up a drainpipe in the water gushing point for water discharge;

在涌水点周围设置反压体,对涌水点周围的基坑侧壁形成反压;Set up a back pressure body around the water gushing point to form a back pressure on the side wall of the foundation pit around the water gushing point;

在涌水点所在侧壁的地面上钻孔,钻孔至少分为两排,第一排钻孔和第二排钻孔的深度呈上下台阶式,靠近侧壁支护体的为第一排钻孔,向外按照排序、钻孔深度依次减少;Drill holes on the ground of the side wall where the water gushing point is located. The holes are divided into at least two rows. The depths of the first row of holes and the second row of holes are stepped up and down. Holes, outward according to sorting, drilling depth decreases in turn;

注浆封堵。Grouting plugging.

与两排注浆孔的钻孔深度一致的施工方式相比,本申请通过注浆形成台阶堆堰式浆液扩散阻水加固体可以更有效地降低涌水点水流速度,较其它前进式或后退式注浆方式更具有针对性,能快速针对涌水点注浆封堵,更加节省注浆浆液,更能兼顾到常年潜水位以下的含导水地层,还解决了在地面有效空间内施工不同性质钻孔的需要。采用注浆堵水钻孔和注浆加固钻孔不同的设计位置和施工顺序,达到了快速堵水和系统加固的双重目的。Compared with the construction method in which the drilling depths of the two rows of grouting holes are the same, this application can more effectively reduce the water flow velocity at the water gushing point by forming the stepped weir type grout diffusion water blocking reinforcement body through grouting, and compared with other forward or backward types The grouting method is more targeted, it can quickly grout the water gushing point, save more grouting grout, and take into account the water-conducting formation below the perennial phreatic level. It also solves the problem of drilling with different properties in the effective space on the ground. hole needs. Different design positions and construction sequences of grouting water blocking drilling and grouting reinforcement drilling are used to achieve the dual purpose of rapid water blocking and system reinforcement.

在一些实施例中,所述钻孔分为注浆堵水钻孔和注浆加固钻孔两种。In some embodiments, the boreholes are classified into two types: grouting water blocking boreholes and grouting reinforcement boreholes.

在一些实施例中,所述注浆堵水钻孔是最靠近涌水点的第一排的1~3个钻孔,其中第一个关键钻孔要正对涌水点处施工。In some embodiments, the grouting and water plugging holes are the first row of 1-3 holes closest to the water influx point, and the first key hole should be constructed directly facing the water influx point.

在一些实施例中,所述注浆堵水钻孔分上下两部分施工,第一部分为粗径钻孔,第二部分为注浆管自进式施工钻孔。In some embodiments, the grouting and water blocking drilling is constructed in two parts, the first part is a large-diameter drilling, and the second part is a grouting pipe self-advancing construction drilling.

本申请采用粗径钻孔向空洞内注入石子、沙硬骨料的方式对空洞进行充填,可以有效降低涌水点水流速度,同时采用这种方式与注浆泵泵送水泥单液相比,可更好地对空洞起到支撑作用,同时节省封堵材料。利用粗径钻孔和自进式钻进相结合进行注浆,可以兼顾钻孔揭露地层空洞后的骨料充填阻水,同时兼顾注浆堵水和注浆加固的需要。This application adopts the method of injecting stones and hard sand aggregates into the cavity to fill the cavity by drilling with a large diameter, which can effectively reduce the water flow velocity at the water gushing point. It can better support the cavity and save plugging materials at the same time. Combining large-diameter drilling and self-propelled drilling for grouting can take into account the needs of aggregate filling and water blocking after drilling to expose stratum cavities, and at the same time meet the needs of grouting water blocking and grouting reinforcement.

在一些实施例中,所述第一排钻孔的孔位线距离侧壁的距离不超过1.5m。In some embodiments, the distance between the position line of the first row of boreholes and the sidewall is no more than 1.5m.

在一些实施例中,所述第一排钻孔注浆深度最深,其浆液扩散加固区域处于最低位置并完全覆盖涌水点。In some embodiments, the first row of boreholes has the deepest grouting depth, and its grout diffusion reinforcement area is at the lowest position and completely covers the water influx point.

在一些实施例中,所述第二排钻孔浆液扩散加固区域位置要高于第一排浆液扩散加固区域。In some embodiments, the position of the second row of drilling slurry diffusion reinforcement areas is higher than that of the first row of grout diffusion reinforcement areas.

在一些实施例中,最后一排钻孔浆液扩散阻水加固体的上缘标高要超过或接近该处的常年潜水位。In some embodiments, the elevation of the upper edge of the last row of drilling slurry diffusion water blocking reinforcement is higher than or close to the perennial phreatic level there.

在一些实施例中,在注浆堵水钻孔内注入早强抗分散速凝浆液时,要缓慢关闭泄水管阀门;一旦发现阀门关闭到一定程度,泄水管有被顶出的趋势或基坑侧壁涌水点上方出现渗水现象时,停止关闭阀门,仍保留泄水状态;此时要缩短早强抗分散速凝浆液的初凝时间,保持低压持续注浆;注浆持续一段时间后,仍可以试着继续关闭阀门,直到阀门被安全关闭为止。In some embodiments, when injecting early-strength, anti-dispersion and quick-setting grout into the grouting water blocking borehole, the valve of the drain pipe should be closed slowly; once the valve is found to be closed to a certain extent, the drain pipe has a tendency to be pushed out or the foundation pit When water seepage occurs above the water gushing point on the side wall, stop closing the valve and keep the draining state; at this time, shorten the initial setting time of the early-strength anti-dispersion quick-setting grout, keep low pressure and continue grouting; after grouting lasts for a period of time, still You can try to keep closing the valve until it is safely closed.

在一些实施例中,关闭阀门后,要持续注浆,直到注浆压力达到设计终压为止;设计终压为不引起基坑侧壁支护体出现开裂、膨出的最大安全压力。In some embodiments, after the valve is closed, the grouting is continued until the grouting pressure reaches the design final pressure; the design final pressure is the maximum safe pressure that does not cause cracking and swelling of the side wall support of the foundation pit.

本发明的有益效果Beneficial effects of the present invention

(1)利用不同排别的钻孔在地层内注浆,形成台阶堆堰式浆液扩散注浆阻水加固体,能有效解决以往在钻孔内大段距注浆中,较深部位注浆质量差于较浅部位注浆质量的技术难题。在单个钻孔内缩小了注浆段距,并用另一排钻孔注浆形成的浆液扩散注浆加固体相搭接来弥补,形成台阶堆堰式浆液扩散注浆阻水加固体。(1) Grouting in the formation by using different rows of boreholes to form a stepped weir grout diffusion grouting water-blocking reinforcement, which can effectively solve the problem of grouting at deeper parts in the past in large-span grouting in boreholes The technical problem that the quality is worse than the grouting quality in the shallower part. The grouting interval is reduced in a single borehole, and it is compensated by the overlap of the grouting grouting reinforced body formed by grouting in another row of boreholes to form a stepped weir-type grouted grouting water-blocking reinforced body.

(2)利用42mm钢管作为钻杆在地层深部自进式钻进,减少了较大口径钻孔施工中孔壁坍塌的风险;利用该钢管作为注浆管,可以实现在钢管上花眼范围内的地层段距内的同时均匀进浆,浆液扩散均匀,整体加固效果好。(2) Using the 42mm steel pipe as the drill pipe for self-propelled drilling in deep formations reduces the risk of hole wall collapse during drilling with larger diameters; using the steel pipe as the grouting pipe can realize drilling within the range of the eye on the steel pipe. Slurry is fed uniformly within the formation interval at the same time, the slurry spreads evenly, and the overall reinforcement effect is good.

(3)利用粗径钻孔和自进式钻进相结合,既兼顾了钻孔揭露地层空洞后的骨料充填阻水,也兼顾了注浆堵水和注浆加固的需要。(3) The combination of large-diameter drilling and self-propelled drilling not only takes into account the water blocking of aggregate filling after the drilling exposes the stratum cavity, but also takes into account the needs of grouting water blocking and grouting reinforcement.

(4)通过注浆形成台阶堆堰式浆液扩散阻水加固体,可以较其它前进式或后退式注浆方式更具有针对性,能快速针对涌水点注浆封堵,更加节省注浆浆液,更能兼顾到常年潜水位以下的含导水地层,还解决了在地面有效空间内施工不同性质钻孔的需要。采用注浆堵水钻孔和注浆加固钻孔不同的设计位置和施工顺序,达到了快速堵水和系统加固的双重目的。(4) The formation of step-stacked weir-type grout diffusion water-blocking reinforcement by grouting can be more targeted than other forward or backward grouting methods, and can quickly grout and block water gushing points, saving more grouting grout. It can better take into account the water-conducting stratum below the perennial phreatic level, and also solves the need to construct different types of boreholes in the effective space on the ground. Different design positions and construction sequences of grouting water blocking drilling and grouting reinforcement drilling are used to achieve the dual purpose of rapid water blocking and system reinforcement.

附图说明Description of drawings

构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。The accompanying drawings constituting a part of the present application are used to provide further understanding of the present application, and the schematic embodiments and descriptions of the present application are used to explain the present application, and do not constitute improper limitations to the present application.

图1:地层内台阶堆堰式浆液扩散注浆堵水加固体钻孔布置平面图;Figure 1: Plane layout of stepped weir grout diffusion grouting water plugging plus solid drilling in the formation;

图2:A-A断面垂向剖面示意图;Figure 2: Schematic diagram of the vertical section of the A-A section;

图3:B-B断面处钻孔浆液扩散剖面示意图。Figure 3: Schematic diagram of the drilling slurry diffusion profile at the B-B section.

其中:1第一排注浆加固钻孔,2第二排注浆加固钻孔,3孔位线,4涌水点,5基坑侧壁,6注浆堵水钻孔,7反压堆积体,8泄水管,9基坑底,10地面,11河流,12常年潜水水位线,13第一排钻孔浆液扩散注浆堵水加固体,14、第二排钻孔浆液扩散注浆加固体,15、台阶堆堰式浆液扩散注浆堵水加固体。Among them: 1 the first row of grouting reinforced drilling, 2 the second row of grouting reinforced drilling, 3 hole position line, 4 water gushing point, 5 foundation pit side wall, 6 grouting water blocking drilling, 7 back pressure accumulation , 8 drainage pipe, 9 bottom of foundation pit, 10 ground, 11 river, 12 perennial submerged water level line, 13 first row of drilling slurry diffusion grouting water blocking reinforcement, 14, second row of drilling slurry diffusion grouting reinforcement , 15. Step-stacked weir grout diffusion grouting water plugging reinforcement.

具体实施方式Detailed ways

应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed description is exemplary and intended to provide further explanation to the present application. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used here is only for describing specific implementations, and is not intended to limit the exemplary implementations according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural, and it should also be understood that when the terms "comprising" and/or "comprising" are used in this specification, they mean There are features, steps, operations, means, components and/or combinations thereof.

1、涌水量及携带的泥沙量的观测计算。当基坑深部侧壁出现股状涌水后,要尽快设立观测系统。观测并计算涌水量是否变化,尤其是是否增加,涌水中是否携带有大量泥沙。若携带大量泥沙,则要计算涌水中单位时间内携带的泥沙的量,根据携带出的泥沙的体积,推算出一定时间内地层形成的空洞的大小。通过对可能形成的空洞体积的计算,预测是否出现较大险情。若可能出现较大险情时,必须尽快采取注浆封堵和加固措施进行处治。1. Observation and calculation of water gushing volume and carried sediment volume. When strand-shaped water gushing occurs on the deep side wall of the foundation pit, an observation system should be established as soon as possible. Observe and calculate whether the gushing water changes, especially if it increases, and whether the gushing water carries a lot of sediment. If a large amount of sediment is carried, it is necessary to calculate the amount of sediment carried in the gushing water per unit time, and calculate the size of the cavity formed in the formation within a certain period of time according to the volume of the carried sediment. Through the calculation of the volume of the void that may be formed, it is predicted whether there will be a major danger. If a serious danger may occur, grouting plugging and reinforcement measures must be taken as soon as possible to deal with it.

2、埋设泄水管集中泄水。尽快把一端带有阀门的一条或多条钢管插进基坑侧壁内的涌水点内,保持阀门开启,使涌水尽量都从泄水管内泄出,泄水管外端连接塑料水管,把水引到积水坑,并用泵把积水排出。钢管外和坑壁之间的间隙用沙袋以及速凝混凝土封闭。并把泄水管固定在基坑侧壁内,防止泄水管被涌水顶出。2. Buried drain pipes for centralized drainage. Insert one or more steel pipes with a valve at one end into the water gushing point in the side wall of the foundation pit as soon as possible, keep the valve open, so that the gushing water can leak out of the drain pipe as much as possible, and the outer end of the drain pipe is connected to a plastic water pipe to lead the water to Puddles of accumulated water and drained with a pump. The gap between the outside of the steel pipe and the pit wall is closed with sandbags and quick-setting concrete. And fix the drain pipe in the side wall of the foundation pit to prevent the drain pipe from being pushed out by gushing water.

3、堆积沙袋形成反压体。尽快在涌水点周围堆积沙袋,沙袋堆积面积要宽厚,沙袋堆积起来后,对涌水点周围的基坑侧壁产生反压作用,目的是用沙袋堆压住侧壁,防止侧壁倾斜鼓出甚至垮塌。沙袋反压体的形成,也可减小注浆时注浆压力对基坑侧壁的破坏影响。3. Pile up sandbags to form a counter pressure body. Sandbags should be piled up around the water inflow point as soon as possible. The sandbag accumulation area should be wide and thick. After the sandbags are piled up, it will have a back pressure effect on the side wall of the foundation pit around the water influx point. collapse. The formation of the sandbag anti-pressure body can also reduce the damage effect of the grouting pressure on the side wall of the foundation pit during grouting.

4、迅速设计施工注浆钻孔。尽快在涌水点所处一侧侧壁的地面上形成钻孔施工条件,并设计注浆钻孔。一般情况下围绕涌水点周围设计两排注浆钻孔。第一排钻孔尽量靠近侧壁,孔位线距离侧壁的距离不超过1.5m;两排钻孔深度呈上下台阶式,靠近侧壁支护体的为第一排钻孔,向外按照排序依次类推。第一排钻孔注浆深度最深,其浆液扩散加固区域处于最低位置并完全覆盖涌水点。第二排钻孔浆液扩散加固区域位置要高于第一排浆液扩散加固区域。向外逐排依次类推,形成台阶堆堰式浆液扩散注浆阻水加固体。台阶堆堰式浆液扩散注浆阻水加固体的上缘标高要超过或接近该处的常年潜水位。当两排钻孔形成的阻水加固体标高达不到常年潜水位标高时,可增加钻孔的排数。4. Quickly design and construct grouting drilling. Form the drilling construction conditions on the ground of the side wall where the water gushing point is located as soon as possible, and design the grouting drilling. Generally, two rows of grouting boreholes are designed around the water gushing point. The first row of drilling holes should be as close to the side wall as possible, and the distance between the hole position line and the side wall should not exceed 1.5m; the depth of the two rows of drilling holes is stepped up and down. Sort by analogy. The grouting depth of the first row of boreholes is the deepest, and its grout diffusion reinforcement area is at the lowest position and completely covers the water gushing point. The position of the second row of drill holes for the reinforcement of the grout diffusion is higher than that of the first row of the grout for the reinforcement of the diffusion. Row by row outward and so on, a stepped weir type grout diffusion grouting water blocking reinforcement is formed. The elevation of the upper edge of the stepped weir grout diffusion grouting water blocking reinforcement should exceed or be close to the perennial phreatic level there. When the level of the water-blocking reinforcement formed by the two rows of boreholes is less than the perennial phreatic level, the number of rows of boreholes can be increased.

采用台阶堆堰式加固体在满足注浆加固强度的前提下,可以有效节约注浆材料的使用,大大节省了深基坑侧壁突涌水注浆治理的成本。同时,台阶式堆堰加固体将注浆加固体设计成台阶形式,可以增加水流通过加固体时的能耗。其基本原理是利用台阶对水流的阻力,使水流在台阶之间形成水平旋滚,并与台阶堆堰式加固体主流发生强烈的混掺作用,迫使水流产生强烈紊动而掺入空气,从而达到消散水体能量的目的,进而有效降低水流对深基坑的破坏作用。Under the premise of satisfying the strength of grouting reinforcement, the use of step pile weir type reinforcement can effectively save the use of grouting materials, and greatly save the cost of grouting treatment of water inrush on the side wall of deep foundation pit. At the same time, the grouting reinforcement is designed in the form of steps in the stepped weir reinforcement, which can increase the energy consumption when water flows through the reinforcement. The basic principle is to use the resistance of the steps to the water flow to make the water flow form a horizontal roll between the steps, and have a strong mixing effect with the mainstream of the stepped weir reinforcement, forcing the water flow to generate strong turbulence and mixed with air, thus The purpose of dissipating the energy of the water body is achieved, thereby effectively reducing the destructive effect of the water flow on the deep foundation pit.

两个注浆孔浆液扩散交汇处的加固体强度最高,即在两个注浆孔圆心的连接线上,采用本申请中的钻孔排布方式,浆液凝固后形成稳固的三角形注浆加固网络,相比其他的钻孔排布方式形成的注浆加固体更加稳固。The strength of the reinforced body at the junction of the two grouting holes where the grout spreads is the highest, that is, on the connecting line between the centers of the two grouting holes, the drilling arrangement in this application is adopted, and a stable triangular grouting reinforcement network is formed after the grout is solidified , the grouting reinforcement formed by other drilling arrangements is more stable.

注浆钻孔分为注浆堵水钻孔和注浆加固钻孔两种。Grouting drilling is divided into two types: grouting water blocking drilling and grouting reinforcement drilling.

5、注浆堵水钻孔施工。注浆堵水钻孔为关键孔,是最靠近涌水点的第一排的1~3个钻孔,其中第一个关键钻孔要正对涌水点处施工。每个关键注浆钻孔分上下两部分施工。第一部分为粗径钻孔,第二部分为注浆管自进式施工钻孔。粗径钻孔深度一般比钢管自进式施工钻孔深度浅2-3m。5. Grouting and water blocking drilling construction. The grouting water plugging holes are the key holes, which are the first row of 1 to 3 holes closest to the water inflow point, and the first key hole should be constructed directly at the water inflow point. Each key grouting drilling is divided into upper and lower parts for construction. The first part is the large-diameter drilling, and the second part is the self-advancing construction drilling of the grouting pipe. The depth of large-diameter drilling is generally 2-3m shallower than that of self-advancing construction of steel pipes.

(1)粗径钻孔施工。粗径钻孔施工深度一般为涌水点深度左右处。钻孔直径在110-150mm之间。当粗径钻孔施工深度接近涌水点处时,要密切观察是否出现掉钻(即钻杆突然下落)现象,有掉钻现象时,说明导水通道已被涌水冲刷成了空洞。立即提钻,在钻孔内快速下入直径不小于108mm的粗径钢管。把粗径钢管下到空洞以上2m处。通过粗径钢管向空洞内注入石子、沙等硬骨料或海带等软骨料,对空洞进行充填。对空洞进行充填时,要下入钻杆钻头到空洞内不断回转搅拌。充填过程中通过钻杆注入初凝时间不短于3min的早强抗分散速凝浆液,对注入的骨料进行胶结,或注入密度不小于1.7g/cm3的浓稠的单液浆。(1) Large-diameter drilling construction. The construction depth of thick-diameter drilling is generally around the depth of the water gushing point. The drilling diameter is between 110-150mm. When the construction depth of the thick-diameter drilling is close to the water inflow point, it is necessary to closely observe whether there is a drill drop (that is, the drill pipe suddenly drops). Immediately lift the drill, and quickly lower a thick steel pipe with a diameter of not less than 108mm in the drill hole. Lower the thick-diameter steel pipe to 2m above the cavity. Fill the cavity by injecting hard aggregates such as stones and sand or soft aggregates such as kelp into the cavity through thick-diameter steel pipes. When filling the cavity, the drill bit should be lowered into the cavity and continuously rotated and stirred. During the filling process, the early-strength anti-dispersion quick-setting slurry with an initial setting time of not less than 3 minutes is injected through the drill pipe to cement the injected aggregate, or a thick single-liquid slurry with a density of not less than 1.7g/ cm3 is injected.

若粗径钻孔在涌水点深度左右没有揭露到空洞,也要提钻,停止施工粗径钻孔,若粗径钻孔孔壁稳定无掉块无坍塌现象,粗径钻孔内可以不下钢管。If the large-diameter borehole does not expose a cavity at the depth of the water inflow point, the drill should also be raised and the construction of the large-diameter borehole should be stopped. If the wall of the thick-diameter borehole is stable and there is no block or collapse, the steel pipe may not be lowered in the thick-diameter borehole .

在粗径钻孔施工中,因为要经过松散地层,施工速度要快,并使用带有锯末的浓稠水泥浆作为冲洗液进行护壁。当遇到坍塌地层时,要注入双液浆进行固结。骨料把空洞充填满并注入浆液后,涌水点处的涌水流速就会减弱,水量会减少。In the construction of large-diameter drilling, the construction speed should be fast because of the loose ground, and thick cement slurry with sawdust should be used as flushing fluid for wall protection. When a collapsed formation is encountered, double liquid slurry should be injected for consolidation. After the aggregate fills the cavity and injects the slurry, the water gushing velocity at the water gushing point will be weakened and the water volume will be reduced.

(2)注浆管自进式钻进施工。在42mm钢管上安装钻头,利用42mm钢管作为钻杆,向粗径钻孔以下的地层内钻进,钻进深度为涌水点深度以下2m。42mm钢管在被下入粗径钻孔作为钻杆使用前,要割花眼和安装膨胀止浆塞。在其底口端以上的4m长度范围内的侧壁上割花眼(因设计在地层内的注浆段距为4m),花眼直径6mm,花眼要均匀分布,花眼的数量由花眼的总面积确定,花眼的总面积与注浆管内径的总面积接近;在42mm钢管上安装膨胀止浆塞,止浆塞下边缘位于粗径钻孔内或位于钢管底端口以上4.5m处。利用42mm钢管作为钻杆钻进到设计深度后,该钢管不再提出,作为注浆管使用。利用该注浆管向地层内注入早强抗分散速凝浆液的浆液,浆液初凝时间一般不长于50s。(2) Self-advancing drilling construction of grouting pipe. Install the drill bit on the 42mm steel pipe, use the 42mm steel pipe as the drill pipe, and drill into the stratum below the large-diameter borehole, and the drilling depth is 2m below the depth of the water gushing point. Before the 42mm steel pipe is lowered into a large-diameter drill hole and used as a drill pipe, it needs to cut the eyelet and install the expansion plug. Cut eyelets on the side wall within the length range of 4m above the bottom end (because the grouting interval in the stratum is designed to be 4m), the eyelet diameter is 6mm, and the eyelets should be evenly distributed, and the number of eyelets is determined by the total area of the eyelets , the total area of the flower eye is close to the total area of the inner diameter of the grouting pipe; the expansion stopper is installed on the 42mm steel pipe, and the lower edge of the stopper is located in the large-diameter borehole or 4.5m above the bottom port of the steel pipe. After the 42mm steel pipe is used as the drill pipe to drill to the design depth, the steel pipe is no longer proposed and used as a grouting pipe. The grouting pipe is used to inject early-strength anti-dispersion quick-setting grout into the formation, and the initial setting time of the grout is generally not longer than 50s.

本申请采用42mm钢管作为钻杆在地层深部自进式钻进,相比一般钻孔铺设套管的方式共有三个优点:一是钻进与铺设套管的过程同时进行,大大节省了施工时间,可以更加快速高效地应对深基坑突涌水这种重大的突发性灾害;二是减少了较大口径钻孔施工中孔壁坍塌的风险,发生突涌水的地层因为有水的存在自稳能力相对较弱,采用自进式钻进的方式打孔可以避免一般作业方式在提钻杆和铺设套管的间隙钻孔坍塌,减少其对抢险作业带来的影响;三是在钢管上花眼,可以实现在钢管花眼范围内的地层同时均匀进浆,浆液扩散均匀,整体加固效果更好。This application uses 42mm steel pipe as the drill pipe for self-propelled drilling in deep formations. Compared with the general method of drilling and laying casing, there are three advantages: First, the process of drilling and laying casing is carried out at the same time, which greatly saves construction time , which can deal with the major sudden disasters of deep foundation pit water inrush more quickly and efficiently; second, it reduces the risk of hole wall collapse in the construction of large-diameter drilling, and the stratum where water inrush occurs is self-stabilizing due to the presence of water. The ability is relatively weak, and self-propelled drilling can avoid drilling holes in the gap between lifting drill pipes and laying casings in general operations, and reducing its impact on emergency operations; , it can achieve uniform grouting in the strata within the range of steel pipe eyes, the grout spreads evenly, and the overall reinforcement effect is better.

快速施工涌水点两侧的其它两个注浆堵水钻孔,其技术要求同上,作用是对第一个关键注浆钻孔的补充。The other two grouting water plugging holes on both sides of the rapid construction water gushing point have the same technical requirements as above, and their function is to supplement the first key grouting hole.

6、施工注浆加固钻孔。除注浆堵水钻孔外,其他钻孔均为注浆加固钻孔。注浆加固钻孔的孔径结构与施工工艺与注浆堵水钻孔一致。所不同的是注入的浆液为高浓度的单液水泥浆和初凝时间不长于50s的早强速凝浆液。两种浆液交替连续注入。注入单液水泥浆的目的是利用其较强的固结强度注浆加固地层,提高被加固地层的整体强度;交替注入早强速凝浆液的目的是不仅控制该浆液本身的扩散范围,使其在设计的扩散范围内留存。还可以利用其迅速固结后形成的固结体,拦截阻挡随后注入的单液浆向远端的扩散,使其在钻孔近端留存。这样达到控制注浆的目的。6. Construction grouting reinforcement drilling. Except for the grouting water blocking drilling, the other drillings are all grouting reinforcement drillings. The aperture structure and construction technology of the grouting reinforced boreholes are consistent with those of the grouted water blocking boreholes. The difference is that the injected slurry is high-concentration single-liquid cement slurry and early-strength quick-setting slurry whose initial setting time is not longer than 50s. The two slurries are alternately and continuously injected. The purpose of injecting single-liquid cement slurry is to use its strong consolidation strength to strengthen the formation and improve the overall strength of the strengthened formation; the purpose of alternately injecting early-strength quick-setting grout is not only to control the diffusion range of the slurry itself, but also to make it Remain within the designed diffusion range. The consolidated body formed after rapid solidification can also be used to intercept and block the diffusion of the subsequently injected single liquid slurry to the distal end, so that it remains at the proximal end of the borehole. This achieves the purpose of controlling grouting.

7、注浆要求。注浆前通过注浆管注入单液水泥浆,进行注浆试验,通过注浆试验观察单液浆从泄水管内的跑浆程度以及注浆初始压力,依此确定水中抗分散的早强速凝浆液的注浆初凝时间和注浆终压。7. Grouting requirements. Before grouting, inject single-liquid cement slurry through the grouting pipe, and conduct a grouting test. Through the grouting test, observe the degree of single-liquid grout running out of the drain pipe and the initial pressure of grouting, and determine the early strength rate of anti-dispersion in water. The grouting initial setting time and grouting final pressure of the grouting liquid.

在注浆堵水钻孔内注入早强抗分散速凝浆液时,要缓慢关闭泄水管阀门。给速凝浆液在地层内的留存创造条件。一旦发现阀门关闭到一定程度,泄水管有被顶出的趋势或基坑侧壁涌水点上方出现渗水现象时,停止关闭阀门,仍保留泄水状态。此时要缩短早强抗分散速凝浆液的初凝时间,保持低压持续注浆。注浆持续一段时间后,仍可以试着继续关闭阀门,直到阀门被安全关闭为止。关闭阀门后,要持续注浆,直到注浆压力达到设计终压为止。设计终压一般以不引起基坑侧壁支护体出现开裂、膨出的最大安全压力。When injecting early-strength anti-dispersion quick-setting grout into the grouting water plugging hole, slowly close the valve of the drain pipe. Create conditions for the retention of quick-setting slurry in the formation. Once it is found that the valve is closed to a certain extent, the drain pipe tends to be pushed out or water seepage occurs above the water gushing point on the side wall of the foundation pit, stop closing the valve and keep the draining state. At this time, the initial setting time of the early-strength anti-dispersion quick-setting grout should be shortened, and the low pressure should be kept for continuous grouting. After grouting continues for a period of time, you can still try to continue closing the valve until the valve is safely closed. After closing the valve, continue grouting until the grouting pressure reaches the design final pressure. The design final pressure is generally the maximum safe pressure that does not cause cracking and swelling of the side wall support of the foundation pit.

所有钻孔达到设计要求,注浆堵水和地层加固结束。All boreholes meet the design requirements, and the grouting water plugging and formation reinforcement are completed.

实施例1Example 1

1、涌水量及携带的泥沙量的观测计算。当基坑深部侧壁出现股状涌水后,在基坑底部设置了积水坑,通过潜水泵抽水量进行了测算。经测算,侧壁涌水量约为16.7m3/h,在观测的5小时内水量稳定不减。且水质较混,泥沙含量约为13%(体积含量)。涌水点位于粉沙层,粉砂层底部为粘土层。分析认为涌水水源为地下潜水,但也不排除有200米外河流补充的可能。导水通道在粉砂层内,不会出现向下转移的可能,粉砂层上覆岩层分别为砂砾层、粉土层和杂填土层,若涌水持续冲刷,涌水地层有被逐渐冲垮上覆松散层由引发沉陷的安全危险。必须尽快采取注浆封堵和加固措施进行处治。1. Observation and calculation of water gushing volume and carried sediment volume. When strand-shaped water gushing appeared on the deep side wall of the foundation pit, a water accumulation pit was set up at the bottom of the foundation pit, and the pumping volume of the submersible pump was used to measure and calculate. According to calculations, the water inflow from the side wall is about 16.7m 3 /h, and the water flow remained stable within 5 hours of observation. And the water quality is mixed, the sediment content is about 13% (volume content). The water gushing point is located in the silt layer, and the bottom of the silt layer is clay layer. According to the analysis, the source of the gushing water is underground diving, but the possibility of replenishment by a river 200 meters away is not ruled out. The aqueduct is in the silt layer, and there is no possibility of downward transfer. The overlying rock layers on the silt layer are gravel layer, silt layer and miscellaneous filling layer. The overlying loose layer causes the safety hazard of subsidence. Grouting plugging and reinforcement measures must be taken as soon as possible for treatment.

2、埋设带阀门的泄水管8集中泄水。尽快把一端带有阀门的一条或多条钢管插进基坑侧壁内的涌水点内,保持阀门开启,使涌水尽量都从泄水管8内泄出,泄水管8外端连接塑料水管,把水引到积水坑,并用泵把积水排出。泄水管8外和基坑侧壁5之间的间隙用沙袋以及速凝混凝土封闭。并把泄水管8固定在基坑侧壁5内,防止泄水管8被涌水顶出。2. Embed 8 discharge pipes with valves for centralized discharge. Insert one or more steel pipes with a valve at one end into the water gushing point in the side wall of the foundation pit as soon as possible, keep the valve open, and make the gushing water leak out from the drain pipe 8 as much as possible. The outer end of the drain pipe 8 is connected to the plastic water pipe. The water is led to a sump and pumped out. The gap between the outside of the drain pipe 8 and the side wall of the foundation pit 5 is closed with sandbags and quick-setting concrete. And the drain pipe 8 is fixed in the side wall 5 of the foundation pit to prevent the drain pipe 8 from being ejected by gushing water.

3、堆积沙袋形成反压堆积体7。尽快在涌水点4周围堆积沙袋,沙袋堆积面积要宽厚,沙袋堆积起来后,对涌水点4周围的基坑侧壁5产生反压作用,目的是用沙袋堆压住侧壁,防止基坑侧壁5倾斜鼓出甚至垮塌。反压堆积体7的形成,也可减小注浆时注浆压力对基坑侧壁5的破坏影响。3. Accumulate sandbags to form a back pressure accumulation body 7. Sandbags should be piled up around the water inflow point 4 as soon as possible. The sandbag accumulation area should be wide and thick. After the sandbags are piled up, they will have a backpressure effect on the side wall 5 of the foundation pit around the water inflow point 4. The wall 5 bulges obliquely or even collapses. The formation of the back pressure accumulation body 7 can also reduce the damage effect of the grouting pressure on the side wall 5 of the foundation pit during grouting.

4、迅速设计施工注浆钻孔。尽快在涌水点4所处一侧侧壁的地面上形成钻孔施工条件,并设计注浆钻孔。一般情况下围绕涌水点4周围设计两排注浆钻孔。第一排钻孔尽量靠近基坑侧壁5,孔位线3距离基坑侧壁5的距离b 1不超过1.5m;两排钻孔深度呈上下台阶式,靠近基坑侧壁5的为第一排钻孔,向外按照排序依次类推。第一排钻孔注浆深度最深,其第一排钻孔浆液扩散注浆堵水加固体13处于最低位置并完全覆盖涌水点4。第二排钻孔浆液扩散加固体14位置要高于第一排钻孔浆液扩散注浆堵水加固体13。向外逐排依次类推,形成台阶堆堰式浆液扩散注浆堵水加固体15。台阶堆堰式浆液扩散注浆堵水加固体15的上缘标高要超过或接近该处的常年潜水水位线12标高。当两排钻孔形成的台阶堆堰式浆液扩散注浆堵水加固体15标高达不到常年潜水水位线12标高时,可增加钻孔的排数。4. Quickly design and construct grouting drilling. Form the drilling construction conditions on the ground of the side wall where the water gushing point 4 is located as soon as possible, and design the grouting drilling. Generally, two rows of grouting boreholes are designed around the gushing point 4 . The first row of drilling holes should be as close as possible to the side wall 5 of the foundation pit, and the distance b1 between the hole position line 3 and the side wall 5 of the foundation pit should not exceed 1.5m; Drill holes in the first row, outwards according to the order and so on. The depth of grouting in the first row of boreholes is the deepest, and the grouting grouting in the first row of drillholes is at the lowest position and covers the water gushing point 4 completely. The position of the second row of drilling slurry diffusion and reinforcement bodies 14 is higher than that of the first row of drilling slurry diffusion grouting and water blocking reinforcement bodies 13 . Row by row outward and so on, a stepped weir type grout diffusion grouting water blocking reinforcement body 15 is formed. The elevation of the upper edge of the stepped weir type grout diffusion grouting water blocking reinforced body 15 will exceed or be close to the elevation of the perennial diving water level line 12 at this place. When the level 15 of the stepped weir-type grout diffusion grouting grouting reinforcement body formed by two rows of boreholes is less than the level 12 of the perennial diving water level, the number of rows of boreholes can be increased.

注浆钻孔分为注浆堵水钻孔和注浆加固钻孔两种。Grouting drilling is divided into two types: grouting water blocking drilling and grouting reinforcement drilling.

5、注浆堵水钻孔施工。注浆堵水钻孔6为关键孔,是最靠近涌水点4的第一排的1~3个钻孔,其中第一个注浆堵水钻孔6要正对涌水点4处施工。每个注浆堵水钻孔6分上下两部分施工。上部分为粗径钻孔,下部分为注浆管自进式施工钻孔。粗径钻孔深度一般比注浆管自进式施工钻孔深度浅3m左右。5. Grouting and water blocking drilling construction. The grouting water blocking borehole 6 is a key hole, which is 1 to 3 boreholes of the first row closest to the water gushing point 4, wherein the first grouting water blocking borehole 6 will be constructed at 4 places of the water gushing point. Each grouting water plugging drilling hole is constructed in 6 parts, upper and lower parts. The upper part is the large-diameter drilling, and the lower part is the self-advancing construction drilling of the grouting pipe. The depth of the large-diameter drilling is generally about 3m shallower than that of the self-advancing construction of the grouting pipe.

(1)粗径钻孔施工。粗径钻孔施工深度一般为涌水点4的深度位置附近。钻孔直径在110-150mm之间。当粗径钻孔施工深度接近涌水点4处时,要密切观察是否出现掉钻(即钻杆突然下落)现象,当有掉钻现象时,说明导水通道已被涌水冲刷成了空洞。应立即提钻,在粗径钻孔内快速下入直径不小于108mm的粗径钢管。把粗径钢管下到空洞以上2m处。通过粗径钢管向空洞内注入石子、沙等硬骨料或海带等软骨料,对空洞进行充填。对空洞进行充填时,要下入钻杆钻头到空洞内不停回转搅拌。在骨料充填和钻杆的不停回转搅拌过程中,通过钻杆内通眼注入初凝时间不短于3min的早强抗分散速凝浆液,对注入的骨料进行胶结,或注入密度不小于1.7g/cm3的浓稠的单液水泥浆。(1) Large-diameter drilling construction. The construction depth of the thick-diameter borehole is generally near the depth of the water gushing point 4 . The drilling diameter is between 110-150mm. When the construction depth of the thick-diameter drilling is close to the water gushing point 4, it is necessary to closely observe whether there is a phenomenon of drill drop (that is, the sudden drop of the drill pipe). The drill should be raised immediately, and a thick-diameter steel pipe with a diameter of not less than 108mm should be quickly lowered into the thick-diameter borehole. Lower the thick-diameter steel pipe to 2m above the cavity. Fill the cavity by injecting hard aggregates such as stones and sand or soft aggregates such as kelp into the cavity through thick-diameter steel pipes. When filling the cavity, the drill bit should be lowered into the cavity and rotated continuously to stir. In the process of aggregate filling and non-stop rotation and stirring of the drill pipe, the early-strength, anti-dispersion and quick-setting slurry with an initial setting time of not less than 3 minutes is injected through the hole in the drill pipe to cement the injected aggregate, or the injection density is different. Thick one-fluid cement slurry less than 1.7g/cm 3 .

若粗径钻孔在涌水点4的深度左右没有揭露到空洞,也要提钻,停止施工粗径钻孔,若粗径钻孔孔壁稳定无掉块无坍塌现象,粗径钻孔内可以不下粗径钢管。If the thick-diameter borehole does not reveal a cavity at the depth of the water gushing point 4, the drill should also be lifted, and the construction of the thick-diameter borehole should be stopped. Not under thick diameter steel pipe.

在粗径钻孔施工中,因为要经过松散地层,施工速度要快,并使用带有锯末的密度不小于1.60g/cm3的浓稠水泥浆作为冲洗液进行护壁。当遇到坍塌地层时,要注入双液浆进行固结。骨料把空洞充填满并注入浆液后,涌水点处的涌水流速就会减弱,水量会减少。In the construction of large-diameter drilling, the construction speed should be fast because it needs to go through the loose ground, and thick cement slurry with a density of not less than 1.60g/cm 3 with sawdust should be used as the flushing fluid to protect the wall. When a collapsed formation is encountered, double liquid slurry should be injected for consolidation. After the aggregate fills the cavity and injects the slurry, the water gushing velocity at the water gushing point will be weakened and the water volume will be reduced.

(2)注浆管自进式钻进施工。在42mm钢管上安装钻头,利用42mm钢管作为钻杆,向粗径钻孔以下的地层内钻进,钻进深度为涌水点4深度以下2m左右。42mm钢管在被下入粗径钻孔作为钻杆使用前,要割花眼和安装膨胀止浆塞。在底口端以上的4m长度范围内的42mm钢管侧壁上割花眼(因设计在地层内的注浆段距为4m),花眼直径6mm,花眼要均匀分布,花眼的数量由花眼的总面积确定,花眼的总面积与注浆管内径的总面积接近;在42mm钢管上安装膨胀止浆塞,止浆塞下边缘应位于粗径钻孔内或位于钢管底端口以上4.5m处。利用42mm钢管作为钻杆钻进到设计深度后,该钢管不再提出,作为注浆管使用。利用该注浆管向地层内注入早强抗分散速凝浆液,浆液初凝时间一般不长于50s。(2) Self-advancing drilling construction of grouting pipe. A drill bit is installed on the 42mm steel pipe, and the 42mm steel pipe is used as the drill rod to drill into the formation below the large-diameter borehole, and the drilling depth is about 2m below the water gushing point 4 depth. Before the 42mm steel pipe is lowered into a large-diameter drill hole and used as a drill pipe, it needs to cut the eyelet and install the expansion plug. Cut eyelets on the side wall of the 42mm steel pipe within a length of 4m above the bottom end (because the grouting interval in the stratum is designed to be 4m), the diameter of the eyelets is 6mm, and the eyelets should be evenly distributed. The number of eyelets is determined by the total area of the eyelets It is determined that the total area of the flower eye is close to the total area of the inner diameter of the grouting pipe; the expansion stopper is installed on the 42mm steel pipe, and the lower edge of the stopper should be located in the large-diameter borehole or 4.5m above the bottom port of the steel pipe. After the 42mm steel pipe is used as the drill pipe to drill to the design depth, the steel pipe is no longer proposed and used as a grouting pipe. The grouting pipe is used to inject early-strength anti-dispersion quick-setting grout into the formation, and the initial setting time of the grout is generally not longer than 50s.

快速施工涌水点两侧的其它两个注浆堵水钻孔,其技术要求同上,作用是对第一个注浆堵水钻孔的补充。三孔之间的间距a 1为2m。三孔距离基坑侧壁5的距离b 1为1.5m。The other two grouting water blocking boreholes on both sides of the rapid construction water gushing point have the same technical requirements as above, and the effect is to supplement the first grouting water blocking borehole. The spacing a1 between the three holes is 2m. The distance b1 between the three holes and the side wall 5 of the foundation pit is 1.5m.

6、施工注浆加固钻孔。除注浆堵水钻孔6外,其他钻孔均为注浆加固钻孔。注浆加固钻孔的孔径结构与施工工艺与注浆堵水钻孔6一致。所不同的是注入的浆液为高浓度的单液水泥浆和初凝时间不长于50s的早强速凝浆液。两种浆液交替连续注入。注入单液水泥浆的目的是利用其较强的固结强度注浆加固地层,提高被加固地层的整体强度;交替注入早强速凝浆液的目的是不仅控制该浆液本身的扩散范围,使其在设计的扩散范围内留存。还可以利用其迅速固结后形成的固结体,拦截阻挡随后注入的单液浆向远端的扩散,使其在钻孔近端留存。这样达到控制注浆的目的。6. Construction grouting reinforcement drilling. Except the grouting water plugging borehole 6, other boreholes are all grouting reinforcement boreholes. The aperture structure and the construction technology of the grouting reinforcement borehole are consistent with the grouting water blocking borehole 6 . The difference is that the injected slurry is high-concentration single-liquid cement slurry and early-strength quick-setting slurry whose initial setting time is not longer than 50s. The two slurries are alternately and continuously injected. The purpose of injecting single-liquid cement slurry is to use its strong consolidation strength to strengthen the formation and improve the overall strength of the strengthened formation; the purpose of alternately injecting early-strength quick-setting grout is not only to control the diffusion range of the slurry itself, but also to make it Remain within the designed diffusion range. The consolidated body formed after rapid solidification can also be used to intercept and block the diffusion of the subsequently injected single liquid slurry to the distal end, so that it remains at the proximal end of the borehole. This achieves the purpose of controlling grouting.

第一排注浆加固钻孔和第二排注浆加固钻孔的排间距b 2为1.2m;同排间相邻钻孔的间距a 1为2m;两排钻孔浆液扩散注浆加固段长度h 2相同,均为4m;第一排钻孔浆液扩散注浆堵水加固体13、第二排钻孔浆液扩散注浆加固体14重叠高度h 3为0.5-1m;设计单孔浆液扩散直径d 1为1.5m。相邻加固体水平面上重叠宽度d 2为1m。The row spacing b 2 of the first row of grouting reinforcement drilling holes and the second row of grouting reinforcement drilling holes is 1.2m; the spacing a 1 of adjacent drilling holes in the same row is 2m; the grouting reinforcement section of the two rows of drilling holes The length h 2 is the same, both are 4m; the first row of drilling grout diffusion grouting reinforcement body 13, the second row of drilling grout diffusion grouting reinforcement body 14, the overlapping height h 3 is 0.5-1m; the designed single hole grouting diffusion The diameter d 1 is 1.5m. The overlapping width d2 on the horizontal plane of adjacent reinforcements is 1m.

7、注浆要求。注浆前要通过注浆管注入单液水泥浆,进行注浆试验,通过注浆试验观察单液浆从泄水管8的跑浆程度以及注浆初始压力,依此确定注入的早强抗分散速凝浆液的初凝时间和注浆终压。7. Grouting requirements. Before grouting, a single-liquid cement slurry should be injected through the grouting pipe, and a grouting test should be carried out. Through the grouting test, the degree of grouting of the single-liquid grout from the drain pipe 8 and the initial pressure of grouting should be observed, and the early strength and anti-dispersion of the injection should be determined accordingly. Initial setting time and final grouting pressure of quick-setting grout.

在注浆堵水钻孔6内注入早强抗分散速凝浆液时,要缓慢关闭泄水管8阀门。给速凝浆液在地层内的留存创造条件。一旦发现阀门关闭到一定程度,泄水管8有被顶出的趋势或涌水点4上方的基坑侧壁5上方出现渗水现象时,停止关闭阀门,仍保留泄水状态。此时要缩短早强抗分散速凝浆液的初凝时间,保持低压持续注浆。注浆持续一段时间后,仍可以试着继续关闭阀门,直到阀门被安全关闭为止。关闭阀门后,仍保持持续注浆,直到注浆压力达到设计终压为止。设计终压一般以不引起基坑侧壁5支护体出现开裂、膨出的最大安全压力,实例注浆中注浆堵水钻孔控制的终压为0.5MPa,注浆加固钻孔控制的最大终压为1.5MPa。When injecting the early-strength anti-dispersion quick-setting grout in the grouting water blocking borehole 6, slowly close the valve of the drain pipe 8. Create conditions for the retention of quick-setting slurry in the formation. Once it is found that the valve is closed to a certain degree, when the drain pipe 8 has a tendency to be ejected or water seepage occurs above the foundation pit side wall 5 above the water gushing point 4, stop closing the valve and still retain the draining state. At this time, the initial setting time of the early-strength anti-dispersion quick-setting grout should be shortened, and the low pressure should be kept for continuous grouting. After grouting continues for a period of time, you can still try to continue closing the valve until the valve is safely closed. After the valve is closed, the grouting continues until the grouting pressure reaches the design final pressure. The design final pressure is generally the maximum safe pressure that does not cause cracking and swelling of the 5 supports on the side wall of the foundation pit. In the example, the final pressure controlled by grouting water blocking drilling is 0.5MPa, and the control of grouting reinforcement drilling is 0.5 MPa. The maximum final pressure is 1.5MPa.

实施例2:Example 2:

2017年4月5日在修建济南地铁R3号线恒大城站的基坑时,基坑南侧侧壁距地表深度13m处突然出现涌水,目测涌水量约为50-70m3/h,后经测量,水量为37m3/h,水量在观测6小时后无变化。水质发黑含泥沙,含沙泥量约10-15%左右。经从勘查资料分析,排除了水源为地表下17m深处的砾石层内承压水的可能。经对水质化验,水质与地下潜水水质相同,也排除了管道漏水的可能。后经调查,水源为埋藏于地下的古河道的水,不排除补充水源为基坑西侧300m左右处的河道内水的可能。On April 5, 2017, during the construction of the foundation pit of Hengdacheng Station of Jinan Metro Line R3 , water gushed out suddenly at a depth of 13m from the ground surface on the south side wall of the foundation pit. According to the measurement, the water volume is 37m 3 /h, and the water volume has not changed after 6 hours of observation. The water quality is black and contains silt, and the silt content is about 10-15%. Based on the analysis of the survey data, the possibility that the water source is the confined water in the gravel layer at a depth of 17m below the surface has been ruled out. After testing the water quality, the water quality was the same as that of the underground diving water, and the possibility of pipeline leakage was also ruled out. After investigation, it was found that the water source was the water in the ancient river channel buried underground, and the possibility that the supplementary water source was the water in the channel about 300m to the west of the foundation pit could not be ruled out.

采用的处治方案是在涌水点处插入2根108mm钢管,用钢管把水引出。钢管端头安装阀门。钢管外侧与坑壁之间用沙袋塞住,外面用标号为C20的早强素混凝土封闭。试着关闭阀门后,2分钟水位抬升到2.5m高,从基坑初支的喷护体上呈多点股状涌出。说明基坑侧壁抗水压的能力较小,同样抗注浆压力的能力也较小。若采用常规的在基坑侧壁上涌水点周围,利用注浆锚杆注浆的话,难以控制水位的抬升或扩散,会影响涌水点上部基坑侧壁的安全,给基坑侧壁的安全构成威胁。The treatment plan adopted is to insert two 108mm steel pipes at the water gushing point, and use the steel pipes to draw the water out. A valve is installed at the end of the steel pipe. The outer side of the steel pipe and the pit wall are plugged with sandbags, and the outer side is closed with C20 early-strength concrete. After trying to close the valve, the water level rose to a height of 2.5m in 2 minutes, gushing out from the sprayed protection body of the initial support of the foundation pit in the form of multiple strands. It shows that the ability of the side wall of the foundation pit to resist water pressure is small, and the ability to resist grouting pressure is also small. If the conventional grouting anchor is used to grout around the water gushing point on the side wall of the foundation pit, it will be difficult to control the rise or spread of the water level, which will affect the safety of the side wall of the foundation pit above the water gushing point and affect the safety of the side wall of the foundation pit. threatening.

后在涌水点周围堆积沙袋进行反压。在涌水点上方基坑边缘外地面上施工垂向钻孔,钻孔内下模袋隔离上部岩土,模袋位置在10m左右,先对着涌水点施工3个钻孔,注入具有早强抗分散的速凝浆液(C-GT浆液)。注浆开始后跑浆严重并减水,后涌水水量又恢复到原水量,出现水量反复现象。注浆过程中,通过调节浆液配比参数,减小浆液初凝时间,控制浆液跑浆,并配合逐步关闭阀门的措施。通过3个钻孔,成功把涌水堵住。后施工了6个钻孔对涌水点周围地层进行了注浆加固,注浆加固浆液为C-S浆液和单液水泥浆,注浆终压为1.5MPa。Finally, sandbags are piled up around the water gushing point for back pressure. A vertical borehole is constructed on the ground outside the edge of the foundation pit above the water gushing point. The lower mold pocket in the borehole isolates the upper rock and soil. The position of the mold pocket is about 10m. Dispersed quick-setting slurry (C-GT slurry). After the grouting started, the grout ran seriously and the water was reduced, and the water inflow returned to the original water volume, and the water volume repeated. During the grouting process, by adjusting the grout ratio parameters, the initial setting time of the grout can be reduced, the grout running out can be controlled, and the valves can be gradually closed. Through 3 drill holes, the gushing water was successfully blocked. Afterwards, 6 boreholes were constructed to strengthen the strata around the water gushing point by grouting. The grouting reinforcement grout was C-S grout and single liquid cement grout, and the final grouting pressure was 1.5MPa.

最后应该说明的是,以上所述仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照前述实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分进行等同替换。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。上述虽然对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。Finally, it should be noted that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, it is still The technical solutions described in the foregoing embodiments may be modified, or part of them may be equivalently replaced. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included within the protection scope of the present invention. Although the specific implementation of the present invention has been described above, it is not a limitation to the protection scope of the present invention. Those skilled in the art should understand that on the basis of the technical solution of the present invention, those skilled in the art can do it without creative work. Various modifications or deformations are still within the protection scope of the present invention.

Claims (7)

1. formula safe grouting construction method in step heap weir in a kind of stratum for blocking the larger water burst of deep-foundation side wall, feature exist In, comprising:
Water yield and quantity of sand and mud to foundation pit deep side wall are observed, are calculated;
Tapping pipe is arranged in issue to sluice;
Back-pressure body is set around issue, back-pressure is formed to the foundation pit side-wall around issue;
It is drilling on the ground of side wall where issue, drilling is at least divided into two rows, the depth of the first row hole drilling and the second row hole drilling Degree is in up/down steps formula, is the first row hole drilling by proximal wall prop, is successively reduced according to sequence, drilling depth outward;
Slip casting blocks;
The first row bored grouting depth is most deep, and slurries diffusion reinforcing area is in extreme lower position and water burst is completely covered Point;
Second row hole drilling slurries diffusion reinforcing area position is higher than first row slurries diffusion reinforcing area;
The block water upper limb absolute altitude of reinforcing body of last row hole drilling slurries diffusion will be more than or close to the long-term phreatic table at this.
2. the method as described in claim 1, which is characterized in that the drilling is divided into grouting for water blocking drilling and grouting and reinforcing drilling Two kinds.
3. method according to claim 2, which is characterized in that the grouting for water blocking drilling is the first row near issue 1~3 drilling, wherein first crucial drilling is wanted to construct at face issue.
4. method according to claim 2, which is characterized in that the grouting for water blocking drilling, which is divided into the top part and the bottom part, gives work, and first Part is that particle size drills, and second part is Grouting Pipe self-advancing type construction drill.
5. the method as described in claim 1, which is characterized in that the distance of the hole location linear distance side wall of first row hole drilling is not More than 1.5m.
6. the method as described in claim 2-4 any one, which is characterized in that inject morning Qiang Kangfen in grouting for water blocking drills When dissipating rapid hardening slurries, slowly closing sluicing tube valve;Once tapping pipe, which has, to be ejected it was found that valve is closed to a certain extent When occurring infiltration phenomenon above trend or foundation pit side-wall issue, phase down valve still retains sluicing state;To shorten at this time In the presetting period of early strong anti-dispersion rapid hardening slurries, low pressure is kept to continue slip casting;After slip casting continues for some time, can still try after It is continuous to close valve, until valve is by safety shutdown.
7. the method as described in claim 1, which is characterized in that after closing sluicing tube valve, Yao Chixu slip casting, until slip casting pressure Until power reaches design final pressure;Design final pressure is the Maximum safe pressure for not causing foundation pit side-wall prop cracking, bulging occur.
CN201810960618.0A 2018-08-22 2018-08-22 It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula Active CN108999195B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810960618.0A CN108999195B (en) 2018-08-22 2018-08-22 It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810960618.0A CN108999195B (en) 2018-08-22 2018-08-22 It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula

Publications (2)

Publication Number Publication Date
CN108999195A CN108999195A (en) 2018-12-14
CN108999195B true CN108999195B (en) 2019-10-29

Family

ID=64593565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810960618.0A Active CN108999195B (en) 2018-08-22 2018-08-22 It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula

Country Status (1)

Country Link
CN (1) CN108999195B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611098A (en) * 2019-01-18 2019-04-12 马钢集团矿业有限公司 A kind of shaft of vertical well quick freezing method under the conditions of deep layer runoff water is larger
CN111379267A (en) * 2020-04-09 2020-07-07 太原理工大学 A water blocking method for solving water gushing at the bottom of foundation pit
CN113309109B (en) * 2021-05-26 2022-07-15 广西壮族自治区地质环境监测站 Construction method for quickly blocking water and reinforcing near pit wall of deep foundation pit in loose soil layer
CN114704322B (en) * 2022-03-16 2023-04-28 中国矿业大学 A water catchment prevention and control method in goaf without coal pillars
CN114775630A (en) * 2022-04-12 2022-07-22 中建八局天津建设工程有限公司 Plugging method for deep foundation pit support structure
CN114934518B (en) * 2022-05-23 2024-04-26 甘肃建投建设有限公司 A deep foundation pit reinforcement method combining backfilling, decompression and grouting
CN115030755A (en) * 2022-06-25 2022-09-09 中电建十一局工程有限公司 Construction method for quickly blocking water and sand gushes of tunnel portal

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101624910A (en) * 2009-07-31 2010-01-13 广州市建筑机械施工有限公司 Method for reinforcing concealed tunnel
CN102041810A (en) * 2010-12-22 2011-05-04 中国水电顾问集团华东勘测设计研究院 Construction method for pouring dam foundation concrete in zone with centralized water gushing
CN203238649U (en) * 2013-04-22 2013-10-16 中铁十三局集团第三工程有限公司 Combined type waterproof curtain
KR20150108204A (en) * 2014-03-17 2015-09-25 (주)진성토건이엔씨 Waterproof method and system of earth retaining wall using jacket barrier wall packer preventing ground subsidence
CN107761753A (en) * 2017-10-17 2018-03-06 山东大学 A kind of foundation ditch water burst rapid rescue slip casting method for blocking

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101624910A (en) * 2009-07-31 2010-01-13 广州市建筑机械施工有限公司 Method for reinforcing concealed tunnel
CN102041810A (en) * 2010-12-22 2011-05-04 中国水电顾问集团华东勘测设计研究院 Construction method for pouring dam foundation concrete in zone with centralized water gushing
CN203238649U (en) * 2013-04-22 2013-10-16 中铁十三局集团第三工程有限公司 Combined type waterproof curtain
KR20150108204A (en) * 2014-03-17 2015-09-25 (주)진성토건이엔씨 Waterproof method and system of earth retaining wall using jacket barrier wall packer preventing ground subsidence
CN107761753A (en) * 2017-10-17 2018-03-06 山东大学 A kind of foundation ditch water burst rapid rescue slip casting method for blocking

Also Published As

Publication number Publication date
CN108999195A (en) 2018-12-14

Similar Documents

Publication Publication Date Title
CN108999195B (en) It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula
CN100591866C (en) Water plugging construction method of moving water double-fluid high-pressure grouting in quicksand layer and gravel layer
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
CN111119940B (en) Grouting construction treatment method
CN101560764B (en) Method for calking exploratory hole by intermittent high-pressure rotary jet grouting
CN108999181A (en) Molten, soil cave injecting treatment construction method and its application
CN106761835A (en) A kind of Karst Tunnel leak segmenting slip casting construction method
CN115787693B (en) Water stopping method for water gushing in deep foundation pit under river-like gentle dip mutually-inclined layer
CN107339108A (en) The layer of sand location subway pipe shed construction method of underground water enrichment
CN102995647B (en) A Groundwater Control Method for Pile Hole Grouting and Seepage Isolation
CN107740434A (en) It is a kind of to be used for sandy gravel, the construction method of dolomite crushed zone dam foundation ditch water protecting curtain
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN205369234U (en) Freeze high pressure jet grouting pile
CN111894103A (en) Pipe jacking connection guide row structure and pipe jacking connection method
CN112081158A (en) A construction technology for forming a reinforced composite pile foundation by forward grouting for high-rise buildings
CN201031380Y (en) Seepage prevention and plugging grouting injection device for cofferdam
CN102979105A (en) Underground water control method of wellhole grouting and seepage insulation
CN106638606B (en) A kind of quick grouting method of deep covering layer
CN212506349U (en) A device for water sealing well in the dewatering zone of ultra-deep foundation pit tube well
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method
CN117404106A (en) Tunnel sand layer segmented double-membrane bag telescopic penetration-compaction synergistic grouting device and technology
CN207109745U (en) Contain high water head plugging structure in a kind of dam foundation water delivery bottom
CN207080242U (en) Cup-type horizontal reinforcement structure of bamboo reinforcement grouting anchor rod at the end of shield tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant