CN108951424A - The formwork support structure and construction method that bridge suspension type pours - Google Patents

The formwork support structure and construction method that bridge suspension type pours Download PDF

Info

Publication number
CN108951424A
CN108951424A CN201810746091.1A CN201810746091A CN108951424A CN 108951424 A CN108951424 A CN 108951424A CN 201810746091 A CN201810746091 A CN 201810746091A CN 108951424 A CN108951424 A CN 108951424A
Authority
CN
China
Prior art keywords
supporting beam
pours
end template
beam body
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810746091.1A
Other languages
Chinese (zh)
Inventor
罗利
王侨
刘建亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201810746091.1A priority Critical patent/CN108951424A/en
Publication of CN108951424A publication Critical patent/CN108951424A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of formwork support structure that bridge suspension type pours and construction methods, supplement pouring for the gap between two parallel existing beam bodies and newly pours beam body, including end template and support group frame, the evenly spaced support group frame of several groups is provided between two existing beam bodies;Every group of support group frame includes the upper supporting beam being parallel to each other and lower supporting beam, and the both ends of upper supporting beam are respectively supported in two existing beam bodies, and lower supporting beam is located at bridge lower part, and is fixed in upper supporting beam by pull rod suspension;What end template integrally closed was intended pouring newly pours the lower part of beam body, and is supported jointly by the lower supporting beam of all support group framves.So that supplement pour that beam body is no longer limited by existing full hall support frame set up condition, have that occupied area is small, at low cost, short time limit, periphery natural conditions required with low, the advantages that security risk is easier to control.

Description

The formwork support structure and construction method that bridge suspension type pours
Technical field
The invention belongs to technical field of building construction, in particular to a kind of formwork support structure that bridge suspension type pours and Construction method.
Background technique
With the expansion and development in city, many existing some bridge needs are transformed or consolidation process, to adapt to The vehicle flowrate of ever-increasing super Design cooling load.For example, largely there is the Urban Bridge in such use in practice: bridge Two sides are driveway, and centre is relatively wide greenbelt, still, with being significantly increased for city vehicle, existing left and right vehicle Trade has been unable to meet current requirement, and then, intermediate greenbelt can be transformed by many city managers, to increase two sides Driveway.But transformation can face many stubborn problems, because not setting under the intermediate greenbelt of bridge in original construction The beam body being equipped with as driveway lower part, but the prefabricated board being supported in the driveway beam body of two sides is only devised, it is certainly pre- Making sheet has been enough to support original greening weight, also meets relevant standard, still, is transformed into driveway if necessary, but Meet demand and correlation are not sufficient to definitely, so must carry out supplement in corresponding position pours beam body, to reach corresponding Requirement.
If using traditional Cast-in-situ Beam body construction, it is necessary to which the mode for setting up full hall support frame carries out, but full hall support frame must Must have corresponding bridge bottom supporting condition, frame body is very high to the foundation requirement of lower part, and there are construction cost height, and it is long in time limit, The disadvantages of all kinds of security risks are prominent, and security management and control difficulty is big.
Summary of the invention
It is an object of the invention to: it is directed to the above-mentioned problems of the prior art and difficulty, provides a kind of bridge The formwork support structure and construction method that suspension type pours, so that supplement pours beam body and is no longer limited by existing full hall support frame Condition is set up, there is extensive adaptability.
The technical scheme of the present invention is realized as follows: a kind of formwork support structure that bridge suspension type pours, is used for Gap between two parallel existing beam bodies carries out supplementing to pour newly pouring beam body, including end template and support group frame, described The evenly spaced support group frame of several groups is provided between two existing beam bodies;Every group of support group frame include be parallel to each other it is upper Supporting beam and lower supporting beam, the both ends of upper supporting beam are respectively supported in two existing beam bodies, and lower supporting beam is located at bridge lower part, And it is fixed in upper supporting beam by pull rod suspension;The quasi- lower part for newly pouring beam body poured of end template integrally closed, and by owning The lower supporting beam of support group frame supports jointly.
The formwork support structure that bridge suspension type of the present invention pours, the upper supporting beam of every group of support group frame and 2 or more pull rods are provided between lower supporting beam.
The formwork support structure that bridge suspension type of the present invention pours also is set between the end template and lower supporting beam Several assistant longitudinal beams are equipped with, for directly carrying the weight bearing on end template.
The formwork support structure that bridge suspension type of the present invention pours, the pull rod pass through preset on end template Hole is pierced by end template, and every pull rod is arranged with indwelling tube, and the length of indwelling tube is not less than the thickness for newly pouring beam body, uses After completing to pour, pull rod takes out from indwelling tube.
The formwork support structure that bridge suspension type of the present invention pours divides along longitudinal direction in the existing beam body of the two sides It is not provided with carrying stringer, the both ends of the upper supporting beam of the support group frame are supported directly upon on carrying stringer.
The formwork support structure that bridge suspension type of the present invention pours, the upper supporting beam two of every group of support group frame End is supported in the existing beam body of two sides by a jacking respectively.
The formwork support structure that bridge suspension type of the present invention pours, unilateral all jackings pass through longitudinally arranged Longitudinally connected steel pipe and pipe clamp be fixed.The longitudinally connected steel pipe of two sides passes through evenly spaced several lateral connection steel pipes It is attached with pipe clamp.
The formwork support structure that bridge suspension type of the present invention pours is set along longitudinal direction at the center for newly pouring beam body It is equipped with a heavy caliber pvc pipe, the receiving opening of heavy caliber pvc pipe has been reserved in longitudinal steel reinforcement cage.
The formwork support structure that bridge suspension type of the present invention pours, the upper supporting beam of the support group frame and lower branch Corresponding upper hole and lower opening are provided on support beam, the both ends of the pull rod are provided with screw thread, and pull rod will by matched nut Upper supporting beam and lower supporting beam are attached.
A kind of construction method that bridge suspension type pours, the specific steps of the construction method are as follows:
S1: removing status bridge floor and afforest dividing strip, abolishes to newly pouring beam body position and carrying out the prefabricated cover board of status, and to newly pouring The surface of the existing beam body of beam body two sides is cleared up;
S2: along the longitudinally mounted carrying stringer of bridge in the existing beam body of two sides;
S3: the assembly of support group frame intercepts upper supporting beam and lower supporting beam using H profile steel, and respectively in upper supporting beam Two upper holes are opened up, two lower opening for corresponding to upper hole are opened up in lower supporting beam, then penetrate two threaded pull rods Indwelling tube respectively penetrates pull rod both ends in the upper hole of upper supporting beam and the lower opening of lower supporting beam, screws in nut at pull rod both ends, Complete the assembling of support group valence;
S4: support group frame after the assembly for completing several groups support group frame in S3, is newly being poured beam by the installation of support group frame It is put between the existing beam body of two sides above body along the longitudinal direction for newly pouring beam body, when beam to be supported is lower than existing beam body, rotation branch Support group frame, so that the both ends vertical support of upper supporting beam is on carrying stringer;And it is uniform according to said method to complete all support group framves The installation at interval;
S5: assistant longitudinal beam is installed in the lower supporting beam of all support group framves;
S6: the installation of end template, each section is newly poured at beam body, is horizontally spliced at least through 3 pieces of end templates, and total Body width is greater than the base width for newly pouring beam body, is provided with opening corresponding with pull rod, the width of opening on the outside of the end template of two sides Degree is equal with the diameter of pull rod, and the spacing of adjacent apertures is equal with the spacing of adjacent supports group frame;By the opening of two sides end template It snaps onto corresponding pull rod, after completing the installation of two sides end template, then intermediate end template is mounted between the end template of two sides, with Complete the installation of all end templates;
S7: after the installation for completing end template, adjustment pull rod is located at the bolt on upper support bar, to adjust the level of end template Highly, so that the existing beam body bottom of end template and two sides is in close contact;
S8: it after the binding for completing steel reinforcement cage on end template, carries out newly pouring pouring for beam body;
S9: newly pouring the maintenance of beam body, demoulding, and construction is completed.
The beneficial effects of the present invention are: being made by introducing the formwork support structure and construction method that bridge suspension type pours Must supplement the condition of setting up that beam body is no longer limited by existing full hall support frame that pours, especially no longer under by bridge foundation condition limit The advantages that system, small, the at low cost, short time limit with occupied area is low to the requirement of periphery natural conditions, and security risk is easier to control, Therefore, it for small-scale Cast-in-situ Beam body construction, is constructed using formwork support structure, is necessary, and had very wide Promotion prospect.
Detailed description of the invention
Fig. 1 is the transverse sectional view of embodiment 1;
Fig. 2 is the transverse sectional view of embodiment 2;
Fig. 3 is the working state figure of jacking in embodiment 2;
Fig. 4 is the connection schematic diagram of jacking and longitudinally connected steel pipe and lateral connection steel pipe in embodiment 2.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The technology of the present invention is further elaborated.It should be appreciated that specific embodiment described herein is only used to explain this hair It is bright, it is not intended to limit the present invention.
Embodiment 1
As shown in Figure 1, the formwork support structure that bridge suspension type pours, between two parallel existing beam bodies 1 Gap carry out supplement and pour and newly pour beam body 2, the formwork support structure includes end template 3 and support group frame 4, at described two The evenly spaced support group frame 4 of several groups is provided between existing beam body 1;Every group of support group frame 4 is upper including being parallel to each other Supporting beam 41 and lower supporting beam 42, the both ends of upper supporting beam 41 are respectively supported in two existing beam bodies 1, and lower supporting beam 42 is located at Bridge lower part, and be fixed in supporting beam 41 by the suspension of pull rod 43;What 3 integrally closed of end template was intended pouring newly pours beam body 2 Lower part, and by the lower supporting beam 42 of all support group framves 4 jointly support.
2 or more pull rods 43 are provided between the upper supporting beam 41 and lower supporting beam 42 of every group of support group frame 4, this Embodiment is provided with two pull rods 43, and the arrangement of the two sides by newly pouring beam body 2, if spacing between the existing beam body 1 in two sides compared with When big, then need to encrypt arrangement pull rod 43.It is provided in the upper supporting beam 41 and lower supporting beam 42 of the support group frame 4 corresponding Upper hole 411 and lower opening 421, the both ends of the pull rod 43 are provided with screw thread, and pull rod 43 is by matched upper end nut 431 under Upper supporting beam 41 and lower supporting beam 42 are attached by end nut 432, and upper end nut 431 is located at the top of upper supporting beam 41, under End nut 432 is located at the lower part of lower supporting beam 42, to realize suspention connection.
Several assistant longitudinal beams 5 are additionally provided between the end template 3 and lower supporting beam 42, for directly carrying end template Weight bearing on 3.The pull rod 43 is pierced by end template 3 by hole preset on end template 3, and every pull rod 43 is arranged Have an indwelling tube 433, the length of indwelling tube 433 is not less than the thickness for newly pouring beam body 2, for completing after pouring, facilitate pull rod 43 from It is taken out in indwelling tube 433.
Carrying stringer 6, the upper support of the support group frame 4 are respectively arranged in the existing beam body 1 of the two sides along longitudinal direction The both ends of beam 41 are supported directly upon on carrying stringer 6.The carrying stringer 6 of every side can be not limited to one, can pour beam body 2 according to new Prediction weights increase the quantity of carrying stringer 6, in the present embodiment, unilateral side sets the carrying stringers 6 of two parallel arrangements, i.e., It can reach corresponding bearing requirements.In the present embodiment more specifically, the carrying stringer 6 is using I-steel.
It is vertically arranged with a heavy caliber pvc pipe 7 at the center for newly pouring beam body 2, it is pre- in longitudinal steel reinforcement cage The receiving opening of heavy caliber pvc pipe 7 has been stayed, the weight for newly pouring beam body 2 can be mitigated in this way, has reduced materials, support strength does not have yet It is substantially reduced.
Embodiment 2
As in Figure 2-4, the present embodiment the difference from embodiment 1 is that, the upper supporting beam 41 of every group of support group frame 4 Both ends pass through a jacking 8 respectively and are supported in the existing beam body 1 of two sides;Unilateral all jackings 8 pass through longitudinally arranged Longitudinally connected steel pipe 9 and pipe clamp are fixed;The joint steel pipe 9 of two sides passes through evenly spaced several 91 Hes of lateral connection steel pipe Pipe clamp is attached.Jacking 8 can carry out height adjustment in vertical direction, avoid and existed using the carrying stringer 6 of I-steel shape Existing 1 out-of-flatness of beam body, or when having fluctuating, setting carrying stringer 6 will have an impact support effect.Jacking 8 includes lower part Jacking main body 81 and telescopic screw rod 82, top plate 83 and the adjusting bolt 84 being supported in existing beam body 1, telescopic screw rod 82 can It is freely lifted in jacking main body 81, top plate 83, upper branch of the top plate 83 directly with H profile steel production is fixed at the top of telescopic screw rod 82 The web contact of strut 41 adjusts 84 sets of bolt on telescopic screw rod 82 to form support, to facilitate adjustment telescopic screw rod 82 Adjustable height.
Embodiment 3
The concrete construction method that the present embodiment is poured mainly for bridge suspension type, and work is implemented with status at applicant one For journey, the general 12m of this engineering bridge depth of beam.This time the range of construction is that the right width of bridge road afforests dividing strip, and status is right It is a concrete slab under width greenbelt, no hollow slab girder, this engineering main purpose is to remove concrete slab, carries out cast-in-place sky Core beam, and status greening dividing strip is changed to driveway, add road center greenbelt.This, which is constructed, amounts to 7 cored slabs Beam, monolithic length are 20m or so, and deck-molding 0.9m, suitable for reading is 1.12m, and lower mouth is 1.06m.
The specific steps of the construction method are as follows:
S1: removing status bridge floor and afforest dividing strip, abolishes to newly pouring beam body position and carrying out the prefabricated cover board of status, and to newly pouring The surface of the existing beam body of beam body two sides is cleared up;
S2: along the longitudinally mounted carrying stringer of bridge in the existing beam body of two sides;
S3: the assembly of support group frame intercepts upper supporting beam and lower supporting beam using H profile steel, and respectively in upper supporting beam Two upper holes are opened up, two lower opening for corresponding to upper hole are opened up in lower supporting beam, then penetrate two threaded pull rods Indwelling tube respectively penetrates pull rod both ends in the upper hole of upper supporting beam and the lower opening of lower supporting beam, screws in nut at pull rod both ends, Complete the assembling of support group valence;
S4: support group frame after the assembly for completing several groups support group frame in S3, is newly being poured beam by the installation of support group frame It is put between the existing beam body of two sides above body along the longitudinal direction for newly pouring beam body, when beam to be supported is lower than existing beam body, rotation branch Support group frame, so that the both ends vertical support of upper supporting beam is on carrying stringer;And it is uniform according to said method to complete all support group framves The installation at interval;
S5: assistant longitudinal beam is installed in the lower supporting beam of all support group framves;
S6: the installation of end template, each section is newly poured at beam body, is horizontally spliced at least through 3 pieces of end templates, and total Body width is greater than the base width for newly pouring beam body, is provided with opening corresponding with pull rod, the width of opening on the outside of the end template of two sides Degree is equal with the diameter of pull rod, and the spacing of adjacent apertures is equal with the spacing of adjacent supports group frame;By the opening of two sides end template It snaps onto corresponding pull rod, after completing the installation of two sides end template, then intermediate end template is mounted between the end template of two sides, with Complete the installation of all end templates;
S7: after the installation for completing end template, adjustment pull rod is located at the bolt on upper support bar, to adjust the level of end template Highly, so that the existing beam body bottom of end template and two sides is in close contact;
S8: it after the binding for completing steel reinforcement cage on end template, carries out newly pouring pouring for beam body;
S9: newly pouring the maintenance of beam body, demoulding, and construction is completed.
Bed die plate surface answers smooth bright and clean, no dirt, and is mortar leakage prevention, template connects in template surface brushing release agent Should paste adhesive tape at seam, and along bridge to present beam body week cheek board patch sponge strip suitable for reading.
After end template is installed, rotating nut adjusting template absolute altitude makes it meet floor level requirement, formwork elevation measuring 5mm or so, and portion's arch camber in a template, springing height about 10mm should be higher by than designed elevation.
The long 1.5m of pull rod, along bridge to spacing 0.5m, direction across bridge spacing is 0.96m, corresponding upper support bar and lower support bar Nut respectively uses 300 double nut+220mm*220mm*20mm double steel plate gaskets to connect.The nut of lower support bar bottom must pacify in advance It is attached to position, to avoid subsequent construction difficulty, the nut on upper support bar subsequent can carry out unified adjustment.
After the completion of end template construction, carries out existing beam body construction joint and pick chisel, it is desirable that construction joint picks into " V " font, and reduction is applied The suffered shearing of reinforcing bar at work seam.It is stitched before concrete placings with clear water chemical cleaning project.
To existing beam body concrete joint face dabbing before reinforcing bar binding, laitance is cut, is worked well with ensuring that new and old concrete connects stubble.
When bar diameter d≤20mm, binding overlap joint or welding point can be used, mechanical connection also can be used;When reinforcing bar is straight Preferentially using mechanical connection when diameter d >=22mm.Because of construction error, using binding or weldering when individual connector straight threads can not connect It connects, binding welding need to meet design and code requirement.
It is 1.4 times of LaE (anchorage length that LaE is tension reinforcement), reinforcement welding joint length that reinforcing bar, which binds the lap of splice, Are as follows: single welding 10d, welding by both sides 5d, throat depth are no less than 0.4d, and width is no less than 0.8d, and (d is that connected reinforcing bar is straight Diameter takes larger bar diameter when being connected bar diameter difference);(same jointing is inscribed using II grade of connector for mechanical connection The area percentage of head is no more than 50%).When reinforcing bar must should use I grade of mechanical splice when same section connects;It is various to connect Head must satisfy the requirement such as related specifications, regulation and technical stipulation, it is ensured that quality.
Hollow shape is built up if necessary to newly pour beam body and pour, method for binding reinforcing steel bars are as follows: draw in the existing beam body in two sides empty Heart beam body stirrup spacing → by top main reinforcement is fixed on upper supporting beam lower part by spacing with iron wire, while stirrup is penetrated top master Muscle → binding stirrup and top main reinforcement by spacing → wear layer indulge muscle and with stirrup bind → hang concrete protective layer pad → It is put into 50 bellowss and does internal model → beam framework is put into template.
Generally poker vibrator is used manually to vibrate when concrete placings, vibrate and made firm by ramming by person skilled in the art, guaranteed Make equilibrium firm by ramming in each position.It is inserted with immersion vibrator and is pulled out slowly fastly, slotting point is evenly distributed, and it is point-by-point mobile, it carries out in order, it must not It omits, accomplishes uniform jolt ramming, every is vibrated 20~30 seconds, and mobile spacing is not more than 1.5 times of vibrating head operating radius (generally 300~400mm), vibrate upper one layer when be inserted into lower layer's concrete face 50mm, with eliminate two interlayers seam, it is no longer significant with concrete surface , no longer there is bubble, surface glows subject to mortar in decline.Insertion vibrator avoids collision reinforcing bar, must not more be placed on reinforcing bar, shakes Stamper head could be inserted into concrete after starting turning, and after having shaken, be proposed slowly, cannot be pulled out again, be vibrated after too fast or stalling When close to template, poker vibrator head must keep 5~10cm distance with template.
It pours, every layer of 45cm point two layers, in work progress, controls speed of perfusion, after the completion of first layer pours, stop 4 hours, It pours upper layer again after template stability under loading, guarantees that material supply is continuous in casting process, cannot there is the phenomenon that fracture, reduce It constructs the appearance of cold seam, guarantees concrete globality and density.
Simultaneously moisture-keeping maintaining is covered to concrete within 12h after pouring;The time of concrete water seasoning: to using silicon The concrete of acid salt cement, ordinary portland cement or portland slag cement mixing must not be less than 7d;To mixing retarding additive Or have the concrete of seepage resistance demand, 14d must not be less than;Irrigation times should be able to keep concrete to be in moisture state;Concrete strength reaches 1.2N/ mm2Before, it must not trample on it or installation template and bracket.
Isothermal holding is carried out after the completion of concrete placings in time, is laid with+two layers geotextiles of one layer of heat preservation film pouring finished surface It is kept the temperature.
Winter construction and concrete curing measure:
If temperature is not less than zero degree (pouring the above period in latter week), concrete heat-insulating is carried out.If negative (minimum temperature be lower than subzero 5 DEG C) environment casting concrete under temperature, it should be noted that mainly early concrete it is antifreeze.Antifreeze need To operate in terms of two: 1) use antifreezing agent: the freezing point of mixing water can be greatly lowered in antifreezing agent, prevent in mecystasis With early concrete internal moisture freezing and expansion, frostbite concrete.Antifreezing agent does not obviously endanger concrete strength performance, but Some antifreezing agents contain urea, and concrete can discharge ammonia taste for a long time, pay particular attention to.2) it keeps the temperature: using glued board, wood as far as possible Plate etc. has the template of certain insulation effect, with the thermal insulation material such as coverings such as cotton-wadded quilt, straw screen or mat or foam heat-insulating board exposure concrete Surface and package steel form, develop concrete strength comparatively fast.Winter construction, it is preferred to use early-strength silicate or common silicic acid Salt cement, because strength development is fast, the heat of hydration is relatively high.But, as long as carrying out heat preservation, any cement can be used, by force Degree development is slow, more preferable to thermal stress cracking is prevented.In 2 DEG C of environment of minimum temperature, casting concrete can not use antifreezing agent, But heat preservation must be carried out, and keeps a close eye on Calculating Temperature Variation.If temperature can also reduce, need to reinforce concrete heat-insulating every And keep a close eye on Calculating Temperature Variation.If temperature can also reduce, need to reinforce concrete heat-insulating every cold.
The coagulation local product of winter construction selects portland cement or ordinary portland cement, and cement grade is not preferably less than 32.5, the cement consumption in every cubic meter of concrete should not be less than 300kg, and the ratio of mud should not exceed 0.6, and early strength agent is added By antifreezing agent (determining according to temperature situation) should be added when necessary.
To reduce freeze injury, the water consumption in match ratio should be minimized method is: the control slump, addition subtract Aqua preferentially selects high efficiency water reducing agent.
Template and insulating layer should be greater than 20 DEG C when concrete and the extraneous temperature difference in concrete cooling to 5 DEG C of dismountable in rear When, the concrete surface after demoulding should be covered temporarily, make its Slow cooling.
Uncooled concrete has higher brittleness, so structure must not be subjected to impact load or dynamic load before cooling Effect.
The aggregate of mixing concrete must clean, must not containing ice and snow and freeze block, and easily bursting by freezing substance mixed with Containing potassium, when the additive of sodium ion, it must not use active aggregates. when conditional, sandstone, which is sieved and washed, should get the jump on temperature above freezing When do, and with plastic paper, oilcloth is covered.
When mixing mixes the concrete of additive, if additive be pulvis, can as required volume be directly sprinkling upon above cement and It is liquid that cement puts into such as additive simultaneously, and when use should first be configured to normal concentration solution, then according to requirements, is used Normal concentration solution, which is configured to construction each solution of solution, to be respectively placed in the container of distinguishing mark, and must not obscure per tour makes Additional agent solution should be once made into.
When the construction time being in 0 DEG C or so, early strength agent can be added in concrete, volume should meet requirement and specification Regulation, and it should be noted that simulation test should be carried out, before addition to verify related technical measures;Limited period demoulding is required mixed Solidifying soil, should also properly increase Concrete Design grade
When adding antifreezing agent in concrete, forbid using high alumina cement.
Strict control concrete water-cement ratio, the moisture in moisture and additional agent solution brought by aggregate should all be from mixing water Middle deduction.
When stirring the concrete mixed with additive, mixing time should take 1.5 times of (7) concrete of stirring at normal temperature time to mix Not preferably less than 10 DEG C of out-of-machine temperature for closing object, molding temperature must not be lower than 5 DEG C.
The concrete that winter pours, before being transferred to negative temperature conservation by positive temperature, the compression strength of concrete not lower than designs strong The 40% of degree.
After being poured, cotton wool felt, straw bag, the thermal insulation materials such as gunnysack, thermal insulation material are covered in first plastic covering film, top again Laying depth are as follows: 0 DEG C under normal circumstances with one layer of upper berth;0 DEG C with two layers or three layers of lower berth;It must not sprinkling maintenance, it is ensured that hair The drying of felt.
Concrete after demoulding also answers timely covering insulation material, to prevent surface temperature of concrete rapid drawdown and generate and split Stitch
After beam body concrete strength reaches code requirement, first loosening upper nut, beat pull rod with hand hammer, make pull rod and End template and concrete loosen, it is then made to fall by self gravity.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. a kind of formwork support structure that bridge suspension type pours is carried out for the gap between two parallel existing beam bodies Supplement, which pours, newly pours beam body, it is characterised in that: including end template and support group frame, is provided between two existing beam bodies The evenly spaced support group frame of several groups;Every group of support group frame includes the upper supporting beam being parallel to each other and lower supporting beam, upper branch The both ends of support beam are respectively supported in two existing beam bodies, and lower supporting beam is located at bridge lower part, and is fixed on by pull rod suspension In upper supporting beam;What end template integrally closed was intended pouring newly pours the lower part of beam body, and is total to by the lower supporting beam of all support group framves With support.
2. the formwork support structure that bridge suspension type according to claim 1 pours, it is characterised in that: every group of support 2 or more pull rods are provided between the upper supporting beam and lower supporting beam of group frame.
3. the formwork support structure that bridge suspension type according to claim 2 pours, it is characterised in that: the end template and Several assistant longitudinal beams are additionally provided between lower supporting beam, for directly carrying the weight bearing on end template.
4. the formwork support structure that bridge suspension type according to claim 2 pours, it is characterised in that: the pull rod passes through Preset hole is pierced by end template on end template, and every pull rod is arranged with indwelling tube, and the length of indwelling tube is not less than The thickness for newly pouring beam body, for completing after pouring, pull rod takes out from indwelling tube.
5. the formwork support structure that bridge suspension type according to claim 2 pours, it is characterised in that: the two sides show Have and be respectively arranged with carrying stringer in beam body along longitudinal direction, it is vertical that the both ends of the upper supporting beam of the support group frame are supported directly upon carrying Liang Shang.
6. the formwork support structure that bridge suspension type according to claim 2 pours, it is characterised in that: every group of support The upper supporting beam both ends of group frame pass through a jacking respectively and are supported in the existing beam body of two sides.
7. the formwork support structure that bridge suspension type according to claim 6 pours, it is characterised in that: unilateral all tops Support is fixed by longitudinally arranged longitudinally connected steel pipe and pipe clamp;The longitudinally connected steel pipe of two sides passes through evenly spaced Several lateral connection steel pipes and pipe clamp are attached.
8. the formwork support structure that bridge suspension type according to claim 1 pours, it is characterised in that: newly pour beam described The center of body is vertically arranged with a heavy caliber pvc pipe, and the receiving that heavy caliber pvc pipe has been reserved in longitudinal steel reinforcement cage is logical Hole.
9. the formwork support structure that bridge suspension type according to claim 1 pours, it is characterised in that: the support group frame Upper supporting beam and lower supporting beam on be provided with corresponding upper hole and lower opening, the both ends of the pull rod are provided with screw thread, pull rod Upper supporting beam and lower supporting beam are attached by matched nut.
10. a kind of construction method that bridge suspension type pours, which is characterized in that the specific steps of the construction method are as follows:
S1: removing status bridge floor and afforest dividing strip, abolishes to the beam body position progress prefabricated cover board of status is newly poured, and pour beam body to new The surface of the existing beam body of two sides is cleared up;
S2: along the longitudinally mounted carrying stringer of bridge in the existing beam body of two sides;
S3: the assembly of support group frame intercepts upper supporting beam and lower supporting beam using H profile steel, and opens up in upper supporting beam respectively Two upper holes, two lower opening for corresponding to upper hole are opened up in lower supporting beam, two threaded pull rods are then penetrated indwelling Pipe, pull rod both ends is respectively penetrated in the upper hole of upper supporting beam and the lower opening of lower supporting beam, is screwed in nut at pull rod both ends, is completed The assembling of support group valence;
S4: the installation of support group frame pours support group frame in beam body newly after the assembly for completing several groups support group frame in S3 Side is put between the existing beam body of two sides along the longitudinal direction for newly pouring beam body, when beam to be supported is lower than existing beam body, rotates support group Frame, so that the both ends vertical support of upper supporting beam is on carrying stringer;And according to said method complete all support group frame uniform intervals Installation;
S5: assistant longitudinal beam is installed in the lower supporting beam of all support group framves;
S6: the installation of end template, each section is newly poured at beam body, is horizontally spliced at least through 3 pieces of end templates, and overall wide Degree, which is greater than, newly pours the base width of beam body, is provided with opening corresponding with pull rod on the outside of the end template of two sides, the width of opening with The diameter of pull rod is equal, and the spacing of adjacent apertures is equal with the spacing of adjacent supports group frame;The opening of two sides end template is caught in Into corresponding pull rod, after completing the installation of two sides end template, then intermediate end template is mounted between the end template of two sides, to complete The installation of all end templates;
S7: after the installation for completing end template, adjustment pull rod is located at the bolt on upper support bar, high with the level for adjusting end template Degree, so that the existing beam body bottom of end template and two sides is in close contact;
S8: it after the binding for completing steel reinforcement cage on end template, carries out newly pouring pouring for beam body;
S9: newly pouring the maintenance of beam body, demoulding, and construction is completed.
CN201810746091.1A 2018-07-09 2018-07-09 The formwork support structure and construction method that bridge suspension type pours Pending CN108951424A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810746091.1A CN108951424A (en) 2018-07-09 2018-07-09 The formwork support structure and construction method that bridge suspension type pours

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810746091.1A CN108951424A (en) 2018-07-09 2018-07-09 The formwork support structure and construction method that bridge suspension type pours

Publications (1)

Publication Number Publication Date
CN108951424A true CN108951424A (en) 2018-12-07

Family

ID=64483487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810746091.1A Pending CN108951424A (en) 2018-07-09 2018-07-09 The formwork support structure and construction method that bridge suspension type pours

Country Status (1)

Country Link
CN (1) CN108951424A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680706A (en) * 2018-12-11 2019-04-26 中交一公局土木工程建筑研究院有限公司 Assembled bearing platform pier pile full scale model and crack pouring construction process using same
CN110331667A (en) * 2019-07-02 2019-10-15 中交二公局东萌工程有限公司 When being open to traffic under execution conditions bridge joining method
CN110629655A (en) * 2019-10-09 2019-12-31 广西大学 Local replaceable plate steel concrete composite beam adopting suspended formwork system
CN112095874A (en) * 2020-09-16 2020-12-18 江苏万年达杭萧钢构有限公司 Detachable steel construction building carrier plate structure
CN112411568A (en) * 2020-11-11 2021-02-26 中天建设集团有限公司 Foundation pit concrete support beam bottom form removal device and form removal method
CN114481857A (en) * 2022-03-17 2022-05-13 中铁大桥局集团第二工程有限公司 Post-cast section hanging template system for middle flange of highway and railway dual-purpose bridge and highway beam

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1696431A (en) * 2004-05-10 2005-11-16 邱则有 Hollow slab made from concrete reinforced by steel bar cast in-site
CN202017346U (en) * 2011-04-13 2011-10-26 中建七局第二建筑有限公司 Late poured band hanging formwork structure
CN202416184U (en) * 2011-12-29 2012-09-05 中建七局第一建筑有限公司 Construction device for formwork for longitudinal wet joint of box girder
CN103452052A (en) * 2013-08-26 2013-12-18 中铁六局集团有限公司 Movable mold hanging equipment for closing swivel bridges and closure section construction method
CN204098486U (en) * 2014-10-13 2015-01-14 中建七局(上海)有限公司 The concrete of building basement roof ater-casting hangs mould
CN104631512A (en) * 2014-12-22 2015-05-20 山东万鑫建设有限公司 Post-cast strip beam and slab construction method adopting formwork hanging method
CN105525569A (en) * 2014-10-22 2016-04-27 五冶集团上海有限公司 Bridge flange plate wet joint suspended formwork construction method
KR101645469B1 (en) * 2015-12-31 2016-08-08 브릿지테크놀러지(주) Molding system for through bridge and through bridge construction method therewith
CN106013781A (en) * 2016-07-18 2016-10-12 广州建筑股份有限公司 Slab supporting construction method and construction device by reversely suspending template
CN206562761U (en) * 2017-01-13 2017-10-17 中国建筑第五工程局有限公司 Floor post-cast strip boatswain chair mould
CN207406036U (en) * 2017-10-17 2018-05-25 云南建投第二建设有限公司 A kind of adjustable beam bottom support jacking device
CN208430443U (en) * 2018-07-09 2019-01-25 中国五冶集团有限公司 A kind of formwork support structure that bridge suspension type pours

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1696431A (en) * 2004-05-10 2005-11-16 邱则有 Hollow slab made from concrete reinforced by steel bar cast in-site
CN202017346U (en) * 2011-04-13 2011-10-26 中建七局第二建筑有限公司 Late poured band hanging formwork structure
CN202416184U (en) * 2011-12-29 2012-09-05 中建七局第一建筑有限公司 Construction device for formwork for longitudinal wet joint of box girder
CN103452052A (en) * 2013-08-26 2013-12-18 中铁六局集团有限公司 Movable mold hanging equipment for closing swivel bridges and closure section construction method
CN204098486U (en) * 2014-10-13 2015-01-14 中建七局(上海)有限公司 The concrete of building basement roof ater-casting hangs mould
CN105525569A (en) * 2014-10-22 2016-04-27 五冶集团上海有限公司 Bridge flange plate wet joint suspended formwork construction method
CN104631512A (en) * 2014-12-22 2015-05-20 山东万鑫建设有限公司 Post-cast strip beam and slab construction method adopting formwork hanging method
KR101645469B1 (en) * 2015-12-31 2016-08-08 브릿지테크놀러지(주) Molding system for through bridge and through bridge construction method therewith
CN106013781A (en) * 2016-07-18 2016-10-12 广州建筑股份有限公司 Slab supporting construction method and construction device by reversely suspending template
CN206562761U (en) * 2017-01-13 2017-10-17 中国建筑第五工程局有限公司 Floor post-cast strip boatswain chair mould
CN207406036U (en) * 2017-10-17 2018-05-25 云南建投第二建设有限公司 A kind of adjustable beam bottom support jacking device
CN208430443U (en) * 2018-07-09 2019-01-25 中国五冶集团有限公司 A kind of formwork support structure that bridge suspension type pours

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐建军;: "地下室顶板后浇带吊支模施工技术", 浙江建筑, no. 01 *
陈典华;: "地铁车站预留洞口现浇顶板吊模施工技术", 隧道建设, no. 12, pages 872 - 876 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680706A (en) * 2018-12-11 2019-04-26 中交一公局土木工程建筑研究院有限公司 Assembled bearing platform pier pile full scale model and crack pouring construction process using same
CN110331667A (en) * 2019-07-02 2019-10-15 中交二公局东萌工程有限公司 When being open to traffic under execution conditions bridge joining method
CN110629655A (en) * 2019-10-09 2019-12-31 广西大学 Local replaceable plate steel concrete composite beam adopting suspended formwork system
CN112095874A (en) * 2020-09-16 2020-12-18 江苏万年达杭萧钢构有限公司 Detachable steel construction building carrier plate structure
CN112095874B (en) * 2020-09-16 2021-12-17 江苏万年达杭萧钢构有限公司 Detachable steel construction building carrier plate structure
CN112411568A (en) * 2020-11-11 2021-02-26 中天建设集团有限公司 Foundation pit concrete support beam bottom form removal device and form removal method
CN114481857A (en) * 2022-03-17 2022-05-13 中铁大桥局集团第二工程有限公司 Post-cast section hanging template system for middle flange of highway and railway dual-purpose bridge and highway beam

Similar Documents

Publication Publication Date Title
CN108951424A (en) The formwork support structure and construction method that bridge suspension type pours
CN108951425A (en) Cast-in-situ prestressed concrete continuous box girder primary concreting molding construction method
CN101338595B (en) Construction method of haydite dry concrete wall
CN207987983U (en) A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip
CN201738600U (en) Assembled integrated type building
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN107905254A (en) Construction method of comprehensive pipe gallery formwork supporting integrated hydraulic internal formwork trolley
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN102677898A (en) Sequence construction method for large area reinforced concrete floors
CN106284080A (en) Continuous rigid frame aqueduct closure segment construction method
CN106988164A (en) Platy ballastless track structure and its construction method
CN103774561B (en) The job execution of speedway prefabricated small box girder frock method streamlined
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN105666687A (en) Construction process for pre-stress reactive powder concrete box girder
CN208430443U (en) A kind of formwork support structure that bridge suspension type pours
CN103276916A (en) Constructing method and infill board for solidly sealed lightweight concrete board wall hole
CN110230242A (en) Construction method of pavement base
CN107090777A (en) A kind of T beam manufacture methods for reducing blibbing
CN106120855A (en) A kind of subway open-cut station arch is without rod structure and construction thereof
CN104631680B (en) A kind of construction method of thin-walled square chest superstructure
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN108609955A (en) T-type beam concrete and its construction method
CN106088436A (en) BRT Lightweight core mould construction technology
CN107313532A (en) Assembled heat insulation concrete walls structural connection and connection structure and method
CN110528524A (en) Volume of concrete foundation unit cellular-type construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181207