CN108915248A - The continuous construction method of fiber is realized in concrete structure seam crossing using mold - Google Patents
The continuous construction method of fiber is realized in concrete structure seam crossing using mold Download PDFInfo
- Publication number
- CN108915248A CN108915248A CN201810821092.8A CN201810821092A CN108915248A CN 108915248 A CN108915248 A CN 108915248A CN 201810821092 A CN201810821092 A CN 201810821092A CN 108915248 A CN108915248 A CN 108915248A
- Authority
- CN
- China
- Prior art keywords
- fiber
- concrete
- connecting plate
- mold
- seam crossing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses realize the continuous construction method of fiber in concrete structure seam crossing using mold, by being bridged in concrete seam using fiber, without improving seam mechanical property by the joint form for changing seam shape, the encryption complexity such as arrangement of reinforcement or deformed steel flats, fundamentally solve the problems, such as that concrete structure is discontinuous in seam crossing fiber;By making pore mold, the work of fiber insertion connecting plate can be made easy to accomplish, and construct quickly, precisely, for pore spacing by the fiber spacing production of design, mold is reusable, greatlys save construction cost for position of fibers insertion;The mold of production is contemplated that insertion variety classes fiber, is suitable for various concrete structure seams;In addition, the method for the present invention quick construction, can reduce project cost, there is preferable promotion prospect, in addition, the method for the present invention quick construction, can reduce project cost, there is preferable promotion prospect.
Description
Technical field
The invention belongs to technical field of civil engineering, fine more particularly, to being realized using mold in concrete structure seam crossing
Tie up continuous construction method.
Background technique
Concrete with fiber(Such as common fiber concrete, ultra-high performance concrete)Due to its excellent every power
Performance is learned, civil construction field is widely used in.Fiber in concrete substrate can block the development of distress in concrete, thus
Improve its tension, bending resistance, shearing strength, shock resistance, it is antifatigue, split rear toughness and durability also and have larger improvement.However
Presently, there are technical problem be that either precast construction or gradation pouring structure is all difficult to avoid that seam(Including construction
Seam, boundary seam etc.)Presence, this also related to new-old concrete interface connection the problem of, especially for band fiber
Concrete structure, it is discontinuous that the presence of seam will lead to fiber, thus make seam become its weak part.
Common joint form has carvel joint, sawtooth seam, step-lap laminated, T and G joint etc. in engineering.Carvel joint due to
Its construction is simple, application is wider, but its seam crack-resisting intensity is insufficient, is easily damaged;Sawtooth seam and step-lap laminated are in carvel joint
On the basis of increase the contact area at seam interface, to increase the breaking resistance of seam crossing, but reinforcing effect it is not obvious enough and
Construction formwork is complicated;T and G joint makes seam further through the interlock action that tongue and groove constructs on the basis of increasing seam contact area
The tensile stress of receiving is partially converted into shear stress, further improves the breaking resistance of seam, but equally increases the difficulty of construction
Degree, and the quality of seam is also difficult to ensure.
Though these above-mentioned seam construction measures can partially improve joint strength, fail fundamentally to solve due to seam crossing
The seam crack-resisting strength reduction problem that fiber is caused by artificial " truncation ", and the advantage of structure and material itself is not played.
Summary of the invention
The case where for the prior art, implements reliable, convenient, fast for construction, effect the purpose of the present invention is to provide a kind of
Rate is high and can guarantee construction quality and concrete is made to realize that seam crossing keeps continuous in gradation casting process, in addition, can also
It enough improves the anti-crack ability of seam crossing and what structure is reasonable realizes that fiber is continuous in concrete structure seam crossing using mold
Construction method.
In order to realize that above-mentioned technical purpose, the technical solution adopted by the present invention be:
It is a kind of to realize the continuous construction method of fiber in concrete structure seam crossing using mold, in a plate-like mold side
Face is drilled with several pores, and fiber is then inserted into pore, and it is exposed outside to make fiber partial-length, then takes a connecting plate and mould
Tool cooperation in the fiber partial insertion connecting plate for keeping mold exposed, forms the connecting plate for being inserted with fiber, then by mold with connect
Plate separation, then connecting plate is matched to merge with concrete-pouring template, connecting plate is fixedly mounted on default concrete seam, make
The exposed one end outside connecting plate of fiber is located at the default concrete side poured for the first time, then through first time concreting and
After maintenance, connecting plate and concrete-pouring template are removed, the other end of fiber is made to be exposed at the default coagulation poured for the second time
Then native side carries out second of concreting and maintenance again, poured in adjacent different batches to realize by fiber is continuously coupled
In the concrete built.
Further comprising following steps:
(1)Mold Making:According to preset fibers content, required fiber number is calculated, takes plate-like mold, according to
The fiber distributing position of default concrete structure seam crossing connection is drilled with several pores in mold one side correspondence;
(2)Mold is inserted into fiber:By fiber correspond insertion mold on pore in, and keep fiber partial-length exposed
Outside;
(3)The production of fibre-bearing connecting plate:A specification is taken to be adapted with it according to the connection facial contour of concrete structure seam crossing
Connecting plate, then the exposed fiber partial insertion connecting plate of mold combs fiber, makes when being inserted into connecting plate
It is uniformly inserted into connecting plate, then separates mold with connecting plate, and being formed has the connecting plate for being inserted with fiber;
(4)Step will be passed through(3)Treated connecting plate and concrete-pouring template with merge connecting plate is fixedly mounted on it is pre-
If concrete seam, one end that fiber is exposed on connecting plate is made to be located at the default concrete side poured for the first time;
(5)It pours and conserves for the first time:The concrete side that default first time pours is poured and maintenance is handled, is made outside fiber
One end of dew is embedded in concrete;
(6)Demoulding:Connecting plate is slowly removed, then dismantling concrete formwork for placing again along fibre length direction, makes fiber
The other end is exposed at the default concrete side poured for the second time;
(7)Seam surface treatment:Surface laitance and unconsolidated formation are removed to the joint face of the concrete side poured for the first time, so
Blow down the dust near joint face again afterwards;
(8)It pours and conserves for the second time:The default concrete side poured for the second time is poured and maintenance is handled, makes fiber
The other end is embedded in concrete, is realized fiber is continuously coupled in the concrete that adjacent different batches pour.
It preferably, further include step(9), the step(9)To repeat step(1)Extremely(8), realize that multiple concrete pour
The seam crossing fiber for building face is continuously constructed.
Preferably, step(1)Described in mold can be rectangular plate-like structure.
Preferably, step(1)Described in mold be timber, steel or plastic material molding, the pore aperture being drilled with
It is 1.2~1.5 times of fibre diameter, the depth of pore is 0.4~0.6 times of fibre length, and the pore is blind hole.
Preferably, step(2)Described in fiber shape contour be flat shape, arch or waveform, the diameter of the fiber
For 0.2~2 mm, length is not less than 13 mm.
It is furthermore preferred that the fiber can be steel fibre.
Preferably, step(3)In by way of manually or mechanically pressing will expose outside mold fiber partial insertion connect
Fishplate bar.
More preferably, step(3)After middle fiber insertion connecting plate, the method on fibre length direction surface corresponding with connecting plate
Line direction is parallel to each other or is formed the angle less than 20 °.
Preferably, step(3)Fiber in middle insertion connecting plate is not pierced by from the other side of connecting plate, the connecting plate
Material is foamed plastics, cork sheet, high-density sponge, pitch, rubber, plasticine or clay.
Preferably, step(5)And step(8)The seam crossing of middle concreting using normal concrete, fiber concrete,
High performance concrete or ultra-high performance concrete pour.
A kind of application for above-mentioned construction method comprising above-mentioned construction method is used for continuous cast-in-place engineering and prefabricated
Assembled engineering.
Using above-mentioned technical solution, the device have the advantages that being:The present invention program passes through in concrete joint
Place is connect in succession using Fiber Bridge, without the joint form by changing seam shape, encrypting the complexity such as arrangement of reinforcement or deformed steel flats
Improve seam crossing mechanical property, fundamentally solves the problems, such as that concrete structure is discontinuous in seam crossing fiber.Also pass through
Pore mold is made, the work of fiber insertion connecting plate can be made easy to accomplish, and construct quickly, position of fibers insertion is accurate.Carefully
Pitch of holes, so that mold is reusable, greatlys save construction cost by the fiber spacing production of design.In addition, the mould of production
Tool is suitable for various concrete structure seams, due in long-term work progress, ability it is contemplated that insertion variety classes fiber
The associated construction in domain designs or Field Force has formd certain inertial thinking, i.e. site operation mostly uses greatly assembled in situ
Cast in situs or other do used mode now to construct, and use prefabricated component form it is also more rare, especially
It lays in the fiber of the concrete seam of different batches very rare on prefabrication solutions, when site operation, is carried out in seam crossing
The mode of fiber not only inefficiency is adlibed, but also the difficulty for laying uniformity is big and often can not be done over again or be done over again
It is with high costs, it is time-consuming and laborious, and the solution of the present invention connecting plate and formwork for placing cooperation before can pass through mold transfer
The form of fiber is by the uniformly distributed one side in connecting plate of fiber, which is not necessarily to execute-in-place and can be prefabricated, so that live
When pouring, only needs after quickly being cooperated connecting plate and formwork for placing, the work for pouring link can be carried out, substantially increased
Site operation efficiency and the risk of doing over again for reducing the link.In addition, the method for the present invention quick construction, can reduce project cost, have
Preferable promotion prospect.
Detailed description of the invention
The solution of the present invention is further elaborated with reference to the accompanying drawings and detailed description:
Fig. 1 is the brief configuration schematic diagram of mold in the present invention program;
Fig. 2 is the connecting plate schematic diagram inserted with fiber in the present invention program;
Fig. 3 is the implementation diagram after pouring and conserve for the first time in the present invention program;
Fig. 4 is the scheme of installation for pouring front template in the present invention program for the second time;
Fig. 5 is the implementation diagram after pouring and conserve for the second time in the present invention program;
Fig. 6 is the present invention after two-step pouring and maintenance, and the continuous seam of fiber pours the simplified diagram of completion;.
Each label corresponds in figure:1- mold;2- pore;3- concrete-pouring template;4- connecting plate;5- is poured for the first time
Concrete;Second of casting concrete of 6-.
Specific embodiment
To make features described above and advantage of the invention more obvious understandable, example is cited below particularly, and cooperate attached drawing, does in detail
It is described as follows.
Embodiment 1
It is a kind of to realize the continuous construction method of fiber in concrete structure seam crossing using mold as shown in Fig. 1 to one of 6,
Substantially:Several pores 2 are drilled in 1 one side of mold of rectangular plate-like one, then fiber is inserted into pore 2, makes fibre
It is exposed outside to tie up partial-length, then a connecting plate 4 is taken to cooperate with mold 1, makes the fiber partial insertion connecting plate 4 that mold is exposed
In, the connecting plate 4 for being inserted with fiber is formed, is then separated mold 1 with connecting plate 4, then connecting plate 4 and concrete-pouring template
Connecting plate 4 is fixedly mounted on default concrete seam with merging by 3, and the one end for keeping fiber exposed outside connecting plate 4 is located at pre-
If the concrete side poured for the first time, then after first time concreting and maintenance, by connecting plate 4 and concreting mould
Plate 3 is removed, and so that the other end of fiber is exposed at the default concrete side poured for the second time, is then carried out second of concrete again and pour
It builds and conserves, to realize fiber is continuously coupled in the concrete that adjacent different batches pour.
It specifically comprises the following steps:
(1)Mold Making:According to preset fibers content, carries out calculating required fiber number, take the mould in rectangular plate-like
Tool 1 is drilled with several pores in mold one side correspondence according to the fiber distributing position of default concrete structure seam crossing connection
2, wherein mold 1 can for timber, steel or plastic material molding, 2 aperture of pore being drilled be fibre diameter 1.2~
1.5 times, the depth of pore 2 is 0.4~0.6 times of fibre length, in addition, pore 2 is blind hole.;
(2)Mold is inserted into fiber:By fiber correspond insertion mold 1 on pore 2 in, and keep fiber partial-length exposed
Outside, wherein the fiber is steel fibre, and shape contour can be flat shape, arch or waveform, and the diameter of fiber is 0.2
~2 mm, length are not less than 13 mm;
(3)The production of fibre-bearing connecting plate:A specification is taken to be adapted with it according to the connection facial contour of concrete structure seam crossing
Connecting plate 4, then connecting plate 4 is inserted into the exposed fiber part of mold 1 by way of manually or mechanically pressing, is being inserted into
When connecting plate 4, fiber is combed, it is made uniformly to be inserted into connecting plate 4, after fiber is inserted into connecting plate 4, fibre length direction with
The corresponding normal to a surface direction of connecting plate 4 is parallel to each other or is formed the angle less than 20 °, and the fiber of insertion connecting plate 4 not from
The connecting plate other side is pierced by, and then separates mold 1 with connecting plate 4, and being formed has the connecting plate for being inserted with fiber, in addition, connection
The material of plate 4 can be foamed plastics, cork sheet, high-density sponge, pitch, rubber, plasticine or clay;
(4)Step will be passed through(3)Connecting plate 4 is fixedly mounted on merging by treated connecting plate 4 and concrete-pouring template 3
Default concrete seam makes one end that fiber is exposed on connecting plate 4 be located at the default concrete side poured for the first time;
(5)It pours and conserves for the first time:The concrete side that default first time pours is poured and maintenance is handled, is made outside fiber
One end of dew is embedded in concrete, wherein the seam crossing of concreting can using normal concrete, fiber concrete,
High performance concrete or ultra-high performance concrete pour;
(6)Demoulding:Connecting plate 4 is slowly removed, then dismantling concrete formwork for placing again along fibre length direction, makes fiber
The other end be exposed at the default concrete side poured for the second time;
(7)Seam surface treatment:Surface laitance and unconsolidated formation are removed to the joint face of the concrete side poured for the first time, then
The dust near joint face is blown down again;
(8)It pours and conserves for the second time:The default concrete side poured for the second time is poured and maintenance is handled, makes fiber
The other end is embedded in concrete, to realize fiber is continuously coupled in the concrete that adjacent different batches pour, wherein
The seam crossing of concreting can use normal concrete, fiber concrete, high performance concrete or ultra-high performance concrete
It pours.
(9)If needing continuously to construct to the seam crossing fiber in multiple concreting faces, then step need to be only repeated
(1)~(8).
Embodiment 2
The present embodiment is roughly the same with the step method of embodiment 1, the difference is that the concrete poured is concrete
Native plate, the good fiber of cloth is inserted in each side of precast concrete in advance in the way of described in above-described embodiment 1, then is transported to scene, installs
In place, the then cast in situs cast-in-site stripe between each prefabricated board seam, is linked to be entirety for each prefabricated board, so that precast slab
Between steel fibre it is continuous.
By using above-mentioned technical solution, advantages of the present invention further includes:It is easy for construction, it can be by changing different batches
Fiber shape, content and slenderness ratio on secondary concrete structure seam crossing increase the switching performance at seam interface, avoid passing through
Change interface shape, setting connector or setting deformed steel flats etc. and facilitate enhancing interface mechanics behavior, finally reduces engineering cost,
And preferably guarantee the performance of seam crossing structure.
Above-described embodiment is only preferable form of implementation of the invention, and the solution of the present invention is not limited to above-mentioned implementation
Mode, anyone can obtain other various forms of concrete structure seams being used in turn under the inspiration of the present invention
Locate the continuous structure of fiber and construction method.And according to equivalent changes and modifications within the scope of the patent application of the present invention, should all it belong to
Covering scope of the invention.
Claims (10)
1. a kind of realize the continuous construction method of fiber in concrete structure seam crossing using mold, it is characterised in that:It is in one
The mold one side of plate is drilled with several pores, and fiber is then inserted into pore, keeps fiber partial-length exposed outside, then
It takes a connecting plate and mold to cooperate, in the fiber partial insertion connecting plate for keeping mold exposed, forms the connecting plate for being inserted with fiber, so
Mold is separated with connecting plate afterwards, then connecting plate is matched to merge with concrete-pouring template, connecting plate is fixedly mounted on default mix
Solidifying soil seam crossing, makes the exposed one end outside connecting plate of fiber be located at the default concrete side poured for the first time, then through first
After secondary concreting and maintenance, connecting plate and concrete-pouring template are removed, the other end of fiber is made to be exposed at default the
The secondary concrete side poured, then carries out second of concreting and maintenance again, thus realize by fiber it is continuously coupled in
In the concrete that adjacent different batches pour.
2. a kind of utilization mold according to claim 1 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:It includes the following steps:
(1)Mold Making:According to preset fibers content, required fiber number is calculated, plate-like mold is taken, according to pre-
If the fiber distributing position of concrete structure seam crossing connection is drilled with several pores in mold one side correspondence;
(2)Mold is inserted into fiber:By fiber correspond insertion mold on pore in, and keep fiber partial-length exposed
Outside;
(3)The production of fibre-bearing connecting plate:A specification is taken to be adapted with it according to the connection facial contour of concrete structure seam crossing
Connecting plate, then the exposed fiber partial insertion connecting plate of mold combs fiber, makes when being inserted into connecting plate
It is uniformly inserted into connecting plate, then separates mold with connecting plate, and being formed has the connecting plate for being inserted with fiber;
(4)Step will be passed through(3)Treated connecting plate and concrete-pouring template with merge connecting plate is fixedly mounted on it is pre-
If concrete seam, one end that fiber is exposed on connecting plate is made to be located at the default concrete side poured for the first time;
(5)It pours and conserves for the first time:The concrete side that default first time pours is poured and maintenance is handled, is made outside fiber
One end of dew is embedded in concrete;
(6)Demoulding:Connecting plate is slowly removed, then dismantling concrete formwork for placing again along fibre length direction, makes fiber
The other end is exposed at the default concrete side poured for the second time;
(7)Seam surface treatment:Surface laitance and unconsolidated formation are removed to the joint face of the concrete side poured for the first time, so
Blow down the dust near joint face again afterwards;
(8)It pours and conserves for the second time:The default concrete side poured for the second time is poured and maintenance is handled, makes fiber
The other end is embedded in concrete, is realized fiber is continuously coupled in the concrete that adjacent different batches pour.
3. a kind of utilization mold according to claim 2 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:It further includes step(9), the step(9)To repeat step(1)Extremely(8), realize that multiple concrete pour
The seam crossing fiber for building face is continuously constructed.
4. a kind of utilization mold according to claim 2 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:Step(1)Described in mold be timber, steel or plastic material molding, the pore aperture being drilled with is
1.2~1.5 times of fibre diameter, the depth of pore are 0.4~0.6 times of fibre length, and the pore is blind hole.
5. a kind of utilization mold according to claim 2 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:Step(2)Described in fiber shape profile be flat shape, arch or waveform, the diameter of the fiber is
0.2~2 mm, length are not less than 13 mm.
6. a kind of utilization mold according to claim 2 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:Step(3)In by way of manually or mechanically pressing will expose outside mold fiber partial insertion connection
Plate.
7. a kind of utilization mold according to claim 6 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:Step(3)After middle fiber insertion connecting plate, fibre length direction normal to a surface side corresponding with connecting plate
To the angle for being parallel to each other or being formed less than 20 °.
8. a kind of utilization mold according to claim 2 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:Step(3)Fiber in middle insertion connecting plate is not pierced by from the other side of connecting plate, the connecting plate
Material is foamed plastics, cork sheet, high-density sponge, pitch, rubber, plasticine or clay.
9. a kind of utilization mold according to claim 2 realizes the continuous construction party of fiber in concrete structure seam crossing
Method, it is characterised in that:Step(5)And step(8)The seam crossing of middle concreting using normal concrete, fiber concrete,
High performance concrete or ultra-high performance concrete pour.
10. according to claim 1 to the application of construction method described in 9, it is characterised in that:Be used for continuous cast-in-place engineering and
Precast assembly engineering.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810821092.8A CN108915248A (en) | 2018-07-24 | 2018-07-24 | The continuous construction method of fiber is realized in concrete structure seam crossing using mold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810821092.8A CN108915248A (en) | 2018-07-24 | 2018-07-24 | The continuous construction method of fiber is realized in concrete structure seam crossing using mold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108915248A true CN108915248A (en) | 2018-11-30 |
Family
ID=64417695
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810821092.8A Pending CN108915248A (en) | 2018-07-24 | 2018-07-24 | The continuous construction method of fiber is realized in concrete structure seam crossing using mold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108915248A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109881795A (en) * | 2019-02-21 | 2019-06-14 | 福州大学 | One kind making the continuous construction method of concrete structure seam crossing fiber by different setting times |
CN113942097A (en) * | 2021-09-23 | 2022-01-18 | 重庆建工建材物流有限公司 | Preparation method of ultra-high performance concrete decorative plate |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002061296A (en) * | 2000-08-15 | 2002-02-28 | Taisei Corp | Structure of joint and construction method therefor |
CN103669417A (en) * | 2013-12-17 | 2014-03-26 | 中国建筑第八工程局有限公司 | Epoxy resin cement concrete used at position of prefabricated basement exterior wall joint and construction method thereof |
CN103866670A (en) * | 2014-02-28 | 2014-06-18 | 中国建筑股份有限公司 | Novel fabricated vehicle bearing pavement and construction method thereof |
CN104669643A (en) * | 2013-11-26 | 2015-06-03 | 比亚迪股份有限公司 | Apparatus and method for producing fiber composite shell |
CN107060117A (en) * | 2017-04-25 | 2017-08-18 | 福州大学 | The continuous construction method of seam crossing fiber is realized in concrete gradation casting process |
CN107780590A (en) * | 2017-10-18 | 2018-03-09 | 山西华通蓝天环保有限公司 | A kind of superfined flyash lightweight Self-insulation wall plate and preparation method thereof |
-
2018
- 2018-07-24 CN CN201810821092.8A patent/CN108915248A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002061296A (en) * | 2000-08-15 | 2002-02-28 | Taisei Corp | Structure of joint and construction method therefor |
CN104669643A (en) * | 2013-11-26 | 2015-06-03 | 比亚迪股份有限公司 | Apparatus and method for producing fiber composite shell |
CN103669417A (en) * | 2013-12-17 | 2014-03-26 | 中国建筑第八工程局有限公司 | Epoxy resin cement concrete used at position of prefabricated basement exterior wall joint and construction method thereof |
CN103866670A (en) * | 2014-02-28 | 2014-06-18 | 中国建筑股份有限公司 | Novel fabricated vehicle bearing pavement and construction method thereof |
CN107060117A (en) * | 2017-04-25 | 2017-08-18 | 福州大学 | The continuous construction method of seam crossing fiber is realized in concrete gradation casting process |
CN107780590A (en) * | 2017-10-18 | 2018-03-09 | 山西华通蓝天环保有限公司 | A kind of superfined flyash lightweight Self-insulation wall plate and preparation method thereof |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109881795A (en) * | 2019-02-21 | 2019-06-14 | 福州大学 | One kind making the continuous construction method of concrete structure seam crossing fiber by different setting times |
CN113942097A (en) * | 2021-09-23 | 2022-01-18 | 重庆建工建材物流有限公司 | Preparation method of ultra-high performance concrete decorative plate |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060117A (en) | The continuous construction method of seam crossing fiber is realized in concrete gradation casting process | |
CN106013529B (en) | The arrangement of reinforcement method of concrete shear force wall based on 3D printing | |
CN104532985B (en) | Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof | |
CN208533764U (en) | A kind of panel structure | |
CN207616844U (en) | Foundation platform precast concrete side form and molding machine | |
CN108915248A (en) | The continuous construction method of fiber is realized in concrete structure seam crossing using mold | |
CN106113230B (en) | The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need | |
CN108301425A (en) | Prefabricated fast-assembling lattice beam system and construction method thereof | |
CN110409283A (en) | It is a kind of based on retarded adhesive prestressed UHPC permanent template without the rib prestressed Self-curing combination beam of abdomen and construction method | |
CN108411751A (en) | Asphalt road surface local repairs structure and restorative procedure | |
CN209227556U (en) | Prefabricated fast-assembling type lattice beam system | |
CN205474843U (en) | Prefabricated T beam -ends head mould board | |
CN108625531A (en) | A kind of construction method pouring constructional column concrete non-dismantling formwork | |
CN106337530B (en) | A kind of construction of frame beam seams stifled construction method | |
CN210507502U (en) | Prefabricated assembled concrete slab bed structure | |
CN101327614A (en) | Method for manufacturing pre-fabricated reinforced concrete plate with rib | |
CN102303351B (en) | Method for manufacturing once pouring-molded T-shaped beam | |
CN105369981B (en) | A kind of arrangement of reinforcement formula buckle connection permanent beam template, concrete structure member and manufacture method | |
CN106968366A (en) | A kind of construction method for pouring constructional column free removal template | |
CN204282229U (en) | Hole injecting glue reinforced structure is drawn in a kind of prestressing force prefabricated case beam crack | |
CN108589939A (en) | The continuous construction method of concrete structure seam crossing fiber | |
CN212352375U (en) | Interface concrete mould of implantable reinforcing bar | |
CN201068619Y (en) | Dedicated collar beam, trim joist building blocks with heat-insulating layer | |
CN115748623A (en) | Prefabricated no muscle assembled irrigation canals and ditches | |
CN209868976U (en) | Device for injecting retarder to enable fibers at joint of concrete structure to be continuous |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181130 |
|
RJ01 | Rejection of invention patent application after publication |