CN108914781A - A kind of connection construction technique for welding nail connector combination beam with assembled - Google Patents

A kind of connection construction technique for welding nail connector combination beam with assembled Download PDF

Info

Publication number
CN108914781A
CN108914781A CN201810882881.2A CN201810882881A CN108914781A CN 108914781 A CN108914781 A CN 108914781A CN 201810882881 A CN201810882881 A CN 201810882881A CN 108914781 A CN108914781 A CN 108914781A
Authority
CN
China
Prior art keywords
assembled
pedestal
nail connector
combination beam
connector
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810882881.2A
Other languages
Chinese (zh)
Other versions
CN108914781B (en
Inventor
苏庆田
王思哲
贺欣怡
戴昌源
吴玲琳
雷东阳
惠术
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201810882881.2A priority Critical patent/CN108914781B/en
Publication of CN108914781A publication Critical patent/CN108914781A/en
Application granted granted Critical
Publication of CN108914781B publication Critical patent/CN108914781B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The present invention discloses a kind of connection construction technique that nail connector combination beam is welded with assembled, includes the following steps:Step 1:Girder steel is made, the pedestal of weldering nail connector is welded on girder steel;Step 2:Girder steel with welding pedestal is transported, is installed to specified Bridge position;Step 3:Precast concrete floorings are lifted on girder steel, so that the reserving hole in concrete is corresponding with the weldering nail base position of connector;Step 4:The screw portion of each weldering nail connector is screwed on the pedestal of weldering nail connector;Step 5:Cement injection sill inside to concrete slab reserving hole;Step 6:Cement-based material in hole is conserved, until reaching design strength requirement.The connection construction technique provided by the invention that nail connector combination beam is welded with assembled can effectively avoid drawback of traditional weldering nail connector in concrete slab construction, improve construction efficiency, increase the bearing capacity of weldering nail connector.

Description

A kind of connection construction technique for welding nail connector combination beam with assembled
Technical field
The present invention relates to the interconnection technique field in steel performance between steel and concrete, more particularly to A kind of connection construction technique for welding nail connector combination beam with assembled.
Background technique
Concrete slab is combined with girder steel by weldering nail connector in combination beam, traditional weldering nail connector is in girder steel There are serious drawbacks when transport and the installation of precast concrete floorings.Weldering nail connector is welded to girder steel and protrudes above one first An a slender member, in steel beam lifting transport, the collision meeting of beam body takes off even from girder steel so that welding and following closely to deform It falls, seriously affects the safety of structure.Followed by, the installation of precast slab is played in the elongated weldering nail that girder steel protrudes above It is extremely difficult that displacement fine tuning is carried out when obstructive action, especially prefabricated bridge are using crane lifting, so that concrete slab is frequent It is blocked by elongated weldering nail, live construction efficiency is very low.Finally, due to which the factors such as construction error influence, can make prefabricated Reinforcing bar conflicts with weldering nail enlarged footing generation position during concrete slab is placed into girder steel, it has to weldering nail be cut off, cause to weld Nail connection bearing capacity substantially reduces.
Summary of the invention
The object of the present invention is to provide a kind of connection construction techniques that nail connector combination beam is welded with assembled, on solving Problem of the existing technology is stated, drawback of traditional weldering nail connector in concrete slab construction can be effectively avoided, Construction efficiency is improved, the bearing capacity of weldering nail connector is increased.
To achieve the above object, the present invention provides following schemes:
The present invention provides a kind of connection construction technique that nail connector combination beam is welded with assembled, includes the following steps:
Step 1:Girder steel is made, the pedestal that assembled welds nail connector is welded on girder steel according to design code position;
Step 2:Girder steel with welding pedestal is transported, is installed to the specified Bridge position of design;
Step 3:Precast concrete floorings are lifted on girder steel, so that the reserving hole in concrete and weldering nail connect The base position of fitting is corresponding;
Step 4:The screw portion of each weldering nail connector is screwed on the pedestal of weldering nail connector, is formed complete Weldering nail connector;
Step 5:Cement injection sill inside to concrete slab reserving hole, it is ensured that cement-based material wraps completely Wrap up in weldering nail;
Step 6:Cement-based material in hole is conserved, until reaching design strength requirement, completes band assembled The connection construction of weldering nail connector combination beam.
Optionally, the cement-based material good fluidity, intensity is high, and the coefficient of expansion is small.
Optionally, the connector of weldering nail described in step three and four includes pedestal and screw rod, offers indent on the pedestal Circular groove, be provided with internal screw thread on the inner wall of the circular groove;External screw thread, the outer spiral shell are offered on the side wall of described screw rod one end Line and the internal screw thread can be cooperatively connected.
Optionally, the base bottom is provided with metal striking point.
Optionally, the metal striking point is the smooth hemispherical configuration in surface.
Optionally, the screw rod is connected with enlarged footing far from described externally threaded one end, and the enlarged footing is greater than for diameter The cylindrical-shaped structure of the screw diameter.
Optionally, the pedestal is cylindrical-shaped structure, and the circular groove is opened in the pedestal middle and upper part.
The present invention achieves following technical effect compared with the existing technology:
The connection construction technique provided by the invention that nail connector combination beam is welded with assembled, it is easy to operate, it is easy for construction, It improves work efficiency.Screw and pedestal use detachable screw connection structure, and installation is simple, easy to adjust.The cross of pedestal Section is big compared with conventional weldering nail section, can effectively improve the shear strength and rigidity of connector, and screw portion is transversal Face is small compared with conventional weldering nail section, can effectively save material.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without any creative labor, can also be according to these attached drawings Obtain other attached drawings.
Fig. 1 is that connecting-piece structure schematic diagram is followed closely in present invention weldering;
Wherein, 1 it is pedestal, 2 be screw rod, 3 be metal striking point, 4 is enlarged footing.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The object of the present invention is to provide a kind of connection construction techniques that nail connector combination beam is welded with assembled, on solving Problem of the existing technology is stated, drawback of traditional weldering nail connector in concrete slab construction can be effectively avoided, Construction efficiency is improved, the bearing capacity of weldering nail connector is increased.
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
The present invention provides a kind of connection construction technique that nail connector combination beam is welded with assembled, includes the following steps:
Step 1:Girder steel is made, the pedestal that assembled welds nail connector is welded on girder steel according to design code position, Welding method is identical as conventional weldering nail connector;
Step 2:Girder steel with welding pedestal is transported, is installed to the specified Bridge position of design;
Step 3:Precast concrete floorings are lifted on girder steel, so that the reserving hole in concrete and weldering nail connect The base position of fitting is corresponding;
Step 4:The screw portion of each weldering nail connector is screwed on the pedestal of weldering nail connector, is formed complete Weldering nail connector;
Step 5:Cement injection sill inside to concrete slab reserving hole, it is ensured that cement-based material wraps completely Weldering nail is wrapped up in, the intensity of cement-based material is greater than the intensity of concrete slab;
Step 6:Cement-based material in hole is conserved, until reaching design strength requirement, completes band assembled The connection construction of weldering nail connector combination beam.
Specifically, cement-based material uses good fluidity, intensity is high, the small material of the coefficient of expansion.As shown in Figure 1, step Weldering nail connector includes pedestal 1 and screw rod 2 in three and four, and the circular groove of indent is offered on pedestal 1, is provided on the inner wall of circular groove Internal screw thread;External screw thread is offered on the side wall of screw rod one end, external screw thread and internal screw thread can be cooperatively connected;The setting of 1 bottom of pedestal There is the hemispherical metal striking point 3 that surface is smooth.
It is further preferred that screw rod 2 is connected with enlarged footing 4 far from externally threaded one end, enlarged footing 4 is that diameter is greater than screw rod The cylindrical-shaped structure of 2 diameters.Pedestal 1 is cylindrical-shaped structure, and circular groove is opened in 1 middle and upper part of pedestal.
The invention avoids prior welding weldering nails and steel mesh position collision problem in bridge floor plate holes.Conventional weldering nail connection Part failure by shear usually occurs in root, and the cross section of assembled weldering nail root pedestal 1 of the present invention is big compared with conventional weldering nail section, The shear strength and rigidity of connector can be effectively improved, and the cross section of 2 part of screw rod is small compared with conventional weldering nail section, it can Effectively to save material.
Specific examples are applied in the present invention, and principle and implementation of the present invention are described, above embodiments Illustrate to be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, according to According to thought of the invention, there will be changes in the specific implementation manner and application range.In conclusion the content of the present specification It should not be construed as limiting the invention.

Claims (7)

1. a kind of connection construction technique for welding nail connector combination beam with assembled, it is characterised in that:Include the following steps:
Step 1:Girder steel is made, the pedestal that assembled welds nail connector is welded on girder steel according to design code position;
Step 2:Girder steel with welding pedestal is transported, is installed to the specified Bridge position of design;
Step 3:Precast concrete floorings are lifted on girder steel, so that the reserving hole in concrete and weldering nail connector Base position it is corresponding;
Step 4:The screw portion of each weldering nail connector is screwed on the pedestal of weldering nail connector, complete weldering nail is formed Connector;
Step 5:Cement injection sill inside to concrete slab reserving hole, it is ensured that the fully wrapped around weldering of cement-based material Nail;
Step 6:Cement-based material in hole is conserved, until reaching design strength requirement, completes band assembled weldering nail The connection construction of connector combination beam.
2. the connection construction technique according to claim 1 for welding nail connector combination beam with assembled, it is characterised in that:Institute Cement-based material good fluidity is stated, intensity is high, and the coefficient of expansion is small.
3. the connection construction technique according to claim 1 for welding nail connector combination beam with assembled, it is characterised in that:Step The connector of weldering nail described in rapid three and four includes pedestal and screw rod, and the circular groove of indent is offered on the pedestal, the circular groove Internal screw thread is provided on inner wall;External screw thread, the external screw thread and the internal screw thread energy are offered on the side wall of described screw rod one end It is enough to be cooperatively connected.
4. the connection construction technique according to claim 3 for welding nail connector combination beam with assembled, it is characterised in that:Institute It states base bottom and is provided with metal striking point.
5. the connection construction technique according to claim 4 for welding nail connector combination beam with assembled, it is characterised in that:Institute Stating metal striking point is the smooth hemispherical configuration in surface.
6. the connection construction technique according to claim 5 for welding nail connector combination beam with assembled, it is characterised in that:Institute It states screw rod and is connected with enlarged footing far from described externally threaded one end, the enlarged footing is the cylinder that diameter is greater than the screw diameter Shape structure.
7. the connection construction technique according to claim 6 for welding nail connector combination beam with assembled, it is characterised in that:Institute Stating pedestal is cylindrical-shaped structure, and the circular groove is opened in the pedestal middle and upper part.
CN201810882881.2A 2018-08-06 2018-08-06 Connection construction process of combined beam with assembled welding nail connecting piece Active CN108914781B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810882881.2A CN108914781B (en) 2018-08-06 2018-08-06 Connection construction process of combined beam with assembled welding nail connecting piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810882881.2A CN108914781B (en) 2018-08-06 2018-08-06 Connection construction process of combined beam with assembled welding nail connecting piece

Publications (2)

Publication Number Publication Date
CN108914781A true CN108914781A (en) 2018-11-30
CN108914781B CN108914781B (en) 2020-02-14

Family

ID=64394339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810882881.2A Active CN108914781B (en) 2018-08-06 2018-08-06 Connection construction process of combined beam with assembled welding nail connecting piece

Country Status (1)

Country Link
CN (1) CN108914781B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468708A (en) * 2019-07-31 2019-11-19 中铁大桥科学研究院有限公司 A kind of combined bridge deck structure and its construction method of steel-UHPC prefabricated board

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2627526A1 (en) * 1988-02-19 1989-08-25 Roret Jean Method for making mixed concrete metal structure - has metal I=beam supporting tensioning members and concrete slab supporting compression member with top covered in at least two zones
CN203320417U (en) * 2013-04-07 2013-12-04 同济大学 Composite beam bridge deck structure with replaceable bridge deck slab
CN104100004A (en) * 2013-04-07 2014-10-15 同济大学 Steel and concrete combined connecting piece with changeable dual column caps
CN205329851U (en) * 2015-12-22 2016-06-22 山东科技大学 Novel bolt collar shear connector
CN106088469A (en) * 2016-07-21 2016-11-09 曹华 Confined concrete splitting and the peg shear connector of splitting development
CN106835951A (en) * 2017-03-28 2017-06-13 宁波金蛟龙重工钢构有限公司 A kind of replaceable prefabricated assembled combined beam structure and manufacturing process

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2627526A1 (en) * 1988-02-19 1989-08-25 Roret Jean Method for making mixed concrete metal structure - has metal I=beam supporting tensioning members and concrete slab supporting compression member with top covered in at least two zones
CN203320417U (en) * 2013-04-07 2013-12-04 同济大学 Composite beam bridge deck structure with replaceable bridge deck slab
CN104100004A (en) * 2013-04-07 2014-10-15 同济大学 Steel and concrete combined connecting piece with changeable dual column caps
CN205329851U (en) * 2015-12-22 2016-06-22 山东科技大学 Novel bolt collar shear connector
CN106088469A (en) * 2016-07-21 2016-11-09 曹华 Confined concrete splitting and the peg shear connector of splitting development
CN106835951A (en) * 2017-03-28 2017-06-13 宁波金蛟龙重工钢构有限公司 A kind of replaceable prefabricated assembled combined beam structure and manufacturing process

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468708A (en) * 2019-07-31 2019-11-19 中铁大桥科学研究院有限公司 A kind of combined bridge deck structure and its construction method of steel-UHPC prefabricated board

Also Published As

Publication number Publication date
CN108914781B (en) 2020-02-14

Similar Documents

Publication Publication Date Title
CN209722702U (en) Pipe pier and cushion cap connection structure
CN109853363A (en) Pipe pier and cushion cap connection structure and construction method
CN105781010B (en) A kind of combined wall board and its cast in place and precast construction
CN105569266B (en) A kind of Combined concrete coupling beam
CN103388408A (en) External pre-stressed tendon reinforcing steering block for building structure
CN106284655A (en) Precast concrete beam stud connects node and method of attachment in succession
CN105971827A (en) Transfer ring beam for concrete cylinder and steel cylinder combined tower and construction method thereof
CN109138221B (en) Precast concrete-steel plate combined shear wall splicing joint and construction method
CN107355010A (en) A kind of precast concrete shear wall profile steel joint attachment structure
CN108914781A (en) A kind of connection construction technique for welding nail connector combination beam with assembled
JP2021017738A (en) Reinforcement structure and reinforcement method of masonry construction structure
CN204826196U (en) Take prefabricated concrete structure of cage connecting elements
CN108412134A (en) A kind of mixed type grout sleeve and its precast shear wall
CN107700841A (en) Prefabricated exterior wall Cast-in-Situ Segment internal lobe Formwork Installation Method
WO2020098452A1 (en) Anti-seismic and energy-consuming fabricated beam-column joint structure located in plastic zone
CN208168421U (en) A kind of plate masonry wall combination beam underpinning structure
CN108677716B (en) Group nail connecting device with corrugated sleeve
RU172472U1 (en) OVERLAP JOINT CONNECTION OF PIPE CONCRETE COLUMN
CN110485631A (en) There is the pretensioned prestressing precast beam of anchor head in a kind of end
CN206457996U (en) Reinforcing bar is with half grout sleeve joint
CN115772848A (en) Single-layer reinforcement hollow prefabricated pier with built-in metal corrugated pipe
CN205677128U (en) A kind of assembled cavity laminated floor slab
CN204898944U (en) Steel plate concrete that cracks combination power consumption shear force wall
CN108517759A (en) The Sarasota crossbeam connection system and construction method of Wavelike steel webplate combination beam form
CN210562989U (en) Assembled steel structure post is connected grout anchor joint with post

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant