CN108867978A - Large space furred ceiling and installation method - Google Patents
Large space furred ceiling and installation method Download PDFInfo
- Publication number
- CN108867978A CN108867978A CN201810833518.1A CN201810833518A CN108867978A CN 108867978 A CN108867978 A CN 108867978A CN 201810833518 A CN201810833518 A CN 201810833518A CN 108867978 A CN108867978 A CN 108867978A
- Authority
- CN
- China
- Prior art keywords
- plate
- furred ceiling
- splice
- top plate
- suspender member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009434 installation Methods 0.000 title claims abstract description 59
- 238000000034 method Methods 0.000 title claims abstract description 26
- 239000002344 surface layer Substances 0.000 claims abstract description 32
- 229910000831 Steel Inorganic materials 0.000 claims description 11
- 239000010959 steel Substances 0.000 claims description 11
- 238000010276 construction Methods 0.000 abstract description 38
- 230000006378 damage Effects 0.000 abstract description 11
- 238000010586 diagram Methods 0.000 description 8
- 230000000694 effects Effects 0.000 description 6
- 230000000392 somatic effect Effects 0.000 description 4
- 229910001220 stainless steel Inorganic materials 0.000 description 4
- 239000010935 stainless steel Substances 0.000 description 4
- 238000005034 decoration Methods 0.000 description 3
- 238000011065 in-situ storage Methods 0.000 description 3
- 238000010422 painting Methods 0.000 description 3
- 230000001105 regulatory effect Effects 0.000 description 3
- 238000005507 spraying Methods 0.000 description 3
- 239000002131 composite material Substances 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 238000004080 punching Methods 0.000 description 2
- 235000008227 Illicium verum Nutrition 0.000 description 1
- 240000007232 Illicium verum Species 0.000 description 1
- 210000000988 bone and bone Anatomy 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 230000000241 respiratory effect Effects 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
- E04B9/20—Means for suspending the supporting construction adjustable
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/22—Connection of slabs, panels, sheets or the like to the supporting construction
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Finishing Walls (AREA)
Abstract
The invention discloses a kind of large space furred ceiling and installation methods.Large space furred ceiling includes the top surface of interior architecture, furred ceiling base and two furred ceiling surface layers for being located at furred ceiling base two sides;Furred ceiling base includes locating piece, suspender member and support plate;Locating piece is jointly mounted to top surface;Suspender member is installed on the positioning element;Support plate is mounted on one end on suspender member far from top surface, and the first faying surface and the second faying surface are located at the two sides of suspender member;Furred ceiling surface layer includes the first top plate being connected to each other and the second top plate and splice;Splice is connected with the first top plate, and splice is connected with the second top plate, and one end of two splices is overlapped on respectively on the first faying surface and the second faying surface.Installation method is for installing large space furred ceiling.Large space furred ceiling and installation method provided by the invention reduce the destruction to concrete original on top surface, and the stability after improving furred ceiling mounting simplifies construction process without live processing component.
Description
Technical field
The present invention relates to building decoration technology field more particularly to a kind of large space furred ceilings and installation method.
Background technique
Furred ceiling is that interior decoration is indispensable to decoration, illumination or wind action out is played at the top of interior architecture
Part.
In the prior art, the laying for generally completing top surface in public space using plasterboard, by top surface
If drilling installation sunpender, hanging keel on sunpender, then by plasterboard hanging on keel.Inventor is in the process for realizing invention
The middle above-mentioned paving mode of discovery has the following disadvantages:The weight of plasterboard is larger, and the contact area of sunpender and plasterboard is small, uses
It is larger to the destruction of the original concrete on top surface that sunpender hangs plasterboard;The stability of plasterboard mounting is reduced, matter of constructing
Amount not can guarantee;Second, it needs at the construction field (site) to drill to top surface according to the position of hanging rod, reduces the whole of construction environment
Clean property, extends construction period;Third, the length of sunpender needs to be processed according to the height scene of plasterboard, time-consuming and laborious;The
Four, plasterboard generally requires back and hangs keel, hangs keel installation on hanging keel by back, back hangs keel and hanging keel needs
Proper alignment installation, installation procedure is complicated, and difficulty of construction is big;5th, for the top surface that plasterboard is completed, the powder of Puttying mopping
Dirt is more and smell is all bigger, not only bad for the respiratory health of construction personnel, and needs the curing period of long period, prolongs
Construction period is grown.
Therefore, it is necessary to solve above-mentioned technical problem.
Summary of the invention
The present invention provides a kind of large space furred ceiling and installation method, to solve problems of the prior art, reduces pair
The destruction of original concrete on top surface, the stability after improving furred ceiling mounting simplify construction process without live processing component,
Shorten construction period, reduces difficulty of construction and reduce somatic damage of the surface construction to operating personnel, lifting construction effect.
The present invention provides a kind of large space furred ceiling, the top surfaces including interior architecture, which is characterized in that further include:
Furred ceiling base and two furred ceiling surface layers for being located at furred ceiling base two sides;
The furred ceiling base includes locating piece, suspender member and support plate;The locating piece is jointly mounted to the top
Surface;The suspender member is mounted on the locating piece;The support plate is mounted on the suspender member far from the top table
The one end in face, the distance between the support plate and the locating piece are adjustable;The support plate is towards the surface of the suspender member
Including the first faying surface and the second faying surface, first faying surface and second faying surface are located at the suspender member
Two sides;The furred ceiling surface layer includes the first top plate being connected to each other and the second top plate and splice;The splice and described the
One top plate, the splice and second top plate are oppositely arranged;The splice is connected with first top plate, described
Splice is connected with second top plate, and one end of two splices is overlapped on first faying surface and described respectively
On second faying surface.
Optionally, the furred ceiling surface layer further includes the first keel and the second keel, the splice and first top plate
It is connected by first keel, the splice is connected with second top plate by second keel.
Optionally, it is equal to institute backwards to the distance between the surface of the splice and the splice on first top plate
It states on the second top plate backwards to the distance between the surface of the splice and the splice.
Optionally, the surface in the support plate backwards to the suspender member is parallel to the top surface.
Optionally, the suspender member is that top hangs angle steel.
Optionally, the locating piece includes the first corner brace and the second corner brace, and first corner brace includes connected vertically the
One gusset and the second gusset, second corner brace include third gusset and fourth angle plate connected vertically;First gusset and
The third gusset is mounted on the top surface, and second gusset is arranged in parallel with the fourth angle plate, and the top is hung
One end on angle steel close to the locating piece is fixed between second gusset and the fourth angle plate.
Optionally, the furred ceiling base further includes closing in parts and mounting plate;The closing in parts include sequentially connected first
Shrinking plate, the second shrinking plate, third shrinking plate, first shrinking plate and the third shrinking plate are arranged in parallel and are respectively positioned on institute
State the same side of the second shrinking plate;The mounting plate is mounted on the side in the support plate backwards to the locating piece, the peace
Loading board includes the first installation end and the second installation end being oppositely arranged;First installation end and second installation end are all connected with
There are the closing in parts, two closing in parts are respectively positioned on the front of the mounting plate;The end of two first shrinking plates
End is connected to first installation end and second installation end, and two first shrinking plates are oppositely arranged, any one
A third shrinking plate is respectively positioned on connected first shrinking plate backwards to the one of another first shrinking plate
Side.
Optionally, the splice is the square tube of bar shaped.
Optionally, the square tube is zinc-plated square tube.
Based on the same inventive concept, the present invention also provides a kind of installation method of large space furred ceiling, include the following steps:
Setting needs the interior architecture in top surface setting large space furred ceiling;Furred ceiling base is set on the top surface, makes institute
Stating furred ceiling base includes locating piece, suspender member and support plate;The locating piece is jointly mounted to the top surface;It is described
Suspender member is mounted on the locating piece;The support plate is mounted on one end on the suspender member far from the top surface,
The distance between the support plate and the locating piece are adjustable;The support plate is taken towards the surface of the suspender member including first
Junction and the second faying surface, first faying surface and second faying surface are located at the two sides of the suspender member;Splicing
Two furred ceiling surface layers, making each furred ceiling surface layer includes the first top plate being connected to each other and the second top plate and splice;It is described
Splice is oppositely arranged with first top plate, the splice and second top plate;Two furred ceiling surface layers are hung
It hangs in the furred ceiling base, so that one end of two splices is overlapped on first faying surface and described second respectively and take
In junction.
Large space furred ceiling and installation method provided by the invention, the locating piece, which uses, to be bonded or is spirally connected etc. without punching
Mode be jointly mounted to the top surface, reduce the destruction to concrete original on top surface;The length of the suspender member
It is adjustable, and the length of suspender member can be fixed at the position regulated, be wanted with adapting to the height of the first top plate and the second top plate
It asks, without scene processing, simplifies construction process, shorten construction period;The splice is connected with first top plate,
The splice is connected with second top plate;Realize that the first top plate and the second top plate mutually splice by splice, without existing
Field cutting, reduces the difficulty of construction, and one end of two splices is overlapped on respectively on the first faying surface and the second faying surface, the
One top plate and the second top plate are overlapped on respectively on two third shrinking plates, and it is difficult to reduce the first top plate and the second top plate overlapped
Degree.In the process, the weight of the first top plate and the second top plate is transferred on locating piece by suspender member, due to locating piece and top
The contact area on portion surface is larger, can reduce the stress of top surface unit area, improves the spliced stability of top plate, rises
The high quality of construction;And first top plate and the second top plate be not necessarily to in-situ spraying and painting, shorten curing cycle, improve and apply
Work efficiency rate, reduces somatic damage of the surface construction to operating personnel, on first top plate backwards to the surface of the splice with
The distance between described splice is equal on second top plate between the surface and the splice of the splice
Distance ensure that the planarization of the first top plate after being connected to each other and the second top plate, improve the spliced flatness of surface layer, be promoted
Construction effect.
Detailed description of the invention
It below will be by preferred embodiment in attached drawing the present invention is described in detail, to help the purpose of the present invention and excellent is understood
Point, wherein:
Fig. 1 is the structural schematic diagram for the big surface layer furred ceiling that alternative embodiment of the present invention provides.
Fig. 2 is the structural schematic diagram for the furred ceiling base that alternative embodiment of the present invention provides.
Fig. 3 is the structural schematic diagram for the furred ceiling surface layer that alternative embodiment of the present invention provides.
Fig. 4 is the structural schematic diagram that the closing in parts that alternative embodiment of the present invention provides are connected with mounting plate.
Fig. 5 is the flow chart of the installation method for the big surface layer furred ceiling that alternative embodiment of the present invention provides.
Specific embodiment
It mentions in the present specification or up, down, left, right, before and after, front, the back side, top, the bottom that may mention etc.
Positional terms are defined relative to each construction shown in the drawings, and word "inner" and "outside" refer respectively to direction or remote
From the direction of geometric center of specific component, they are opposite concepts, and it is therefore possible to can different location, difference according to locating for it
Use state and correspondingly changed.So also these or other positional terms should not be construed to restricted use
Language.
Fig. 1 is the structural schematic diagram for the big surface layer furred ceiling that alternative embodiment of the present invention provides, and Fig. 2 is the optional implementation of the present invention
The structural schematic diagram for the furred ceiling base that example provides, Fig. 3 are the structural schematic diagram for the furred ceiling surface layer that alternative embodiment of the present invention provides.
Please refer to Fig. 1 to Fig. 3, the present invention provides a kind of large space furred ceilings, top surface 30, furred ceiling base including interior architecture and
It is located at two furred ceiling surface layers of furred ceiling base two sides.
Referring to Fig. 1 to Fig. 3, the furred ceiling base includes locating piece, suspender member 4 and support plate 5;It is described fixed
Position part using bonding or can be spirally connected etc. without being jointly mounted to the top surface 30 by the way of punching, and reduce to top surface
The destruction of original concrete on surface 30, the suspender member 4 are mounted on the locating piece;The support plate 5 is mounted on described
Far from one end of the top surface 30 on suspender member 4, the support plate 5 and the distance between the locating piece are adjustable;Wherein
The length that can be the suspender member 4 is adjustable, and the length of suspender member 4 can be fixed at the position regulated, to adapt to
A variety of requirement for height of one top plate 61 and the second top plate 62 simplify construction process without scene processing, shorten construction week
Phase, support plate 5 include the first faying surface and the second faying surface towards the surface of the suspender member 4, and one end of two splices 7 can
Be overlapped on the first faying surface and the second faying surface respectively, to realize the first top plate 61 and the second effectively splicing of top plate 62.The
The type of one top plate 61 and the second top plate 62 can be a variety of, and the first top plate 61 mutually splices with the second top plate 62, splice 7 and spell
The first top plate 61 and the second top plate 62 after connecing are oppositely arranged, i.e., splice 7 is fed through first top plate 61 and described simultaneously
Second top plate 62.The splice 7 is connected with first top plate 61, and the splice 7 is connected with second top plate 62
It connects;It realizes that the first top plate 61 mutually splices with the second top plate 62 by splice 7, is not necessarily to on-site cutting, reduces the difficulty of construction,
And first top plate 61 and the second top plate 62 be not necessarily to in-situ spraying and painting, shorten curing cycle, improve construction efficiency, reduce
Somatic damage of the surface construction to operating personnel.
First faying surface and second faying surface can be located at two be oppositely arranged on the suspender member 4
Side, can also be located at two sides except being oppositely arranged in addition on the suspender member 4, practical with two splices, 7 place that needs that overlapped
Position subject to, the weight of the first top plate 61 and the second top plate 62 is transferred on locating piece by suspender member 4, due to locating piece with
The contact area of top surface 30 is larger, can reduce the stress of 30 unit area of top surface, improves the first top plate 61 and the
The spliced stability of two top plate 62, increases the quality of construction.
Optionally, the furred ceiling surface layer further includes the first keel 82 and the second keel 82, the splice 7 and described first
Top plate 61 is connected by first keel 81, and the splice 7 passes through second keel 82 with second top plate 62
It is connected;
Preferably, backwards to the distance between surface of the splice 7 and the splice 7 etc. on first top plate 61
In, backwards to the surface of the splice 7 and the distance between the splice 7, ensure that after being connected to each other on second top plate 62
The first top plate 61 and the second top plate 62 planarization, improve the spliced flatness of surface layer, lifting construction effect.Construction
When, splice 7 then can be mounted on the first top plate 61 and second by the first top plate 61 and the second top plate 62 ground spliced
On top plate 62, finally furred ceiling surface layer is integrally hung in top surface 30, further simplifies construction process.Preferably, described
Surface in support plate 5 backwards to the suspender member 4 is parallel to the top surface 30, has by setting support plate 5 preferably flat
Whole degree, to guarantee the stationarity for two splices 7 being overlapped on the first faying surface and the second faying surface respectively.
Optionally, the suspender member 4 is that top hangs angle steel, and on the basis of guaranteeing the intensity of suspender member 4, reduction is constructed into
This.
Preferably, the locating piece includes the first corner brace 31 and the second corner brace 32, first corner brace 31 includes vertically connecting
The first gusset 33 and the second gusset 34 connect, second corner brace 32 include third gusset 35 connected vertically and fourth angle plate
36;First gusset 33 and the third gusset 35 can be by being fixedly mounted on the top table using metal expansion pipe
On face 30, the contact area between locating piece and top surface 30 is increased, is further reduced to former on top surface 30
The destruction of beginning concrete;Second gusset 34 is arranged in parallel with the fourth angle plate 36, and the top is hung on angle steel close to described
One end of locating piece is fixed between second gusset 34 and the fourth angle plate 36;Similarly, the second gusset 34 and the 4th
Gusset 36 and the contact area that top hangs angle steel are larger, can increase the stability that top hangs angle steel installation.
Preferably, offering the hanging hole for penetrating through the suspender member 4 on the suspender member 4, opened on second gusset 34
Equipped with the first mounting hole, offer the second mounting hole on the fourth angle plate 36, first mounting hole, the hanging hole, with
And it is bolted after the second mounting hole alignment.Hanging hole be bolted to the second gusset 34 and fourth angle plate 36 it
Between, it is easy for removal and installation.
On the basis of the above embodiments, first mounting hole is multiple, and second mounting hole is multiple, Duo Gesuo
It states the first mounting hole and is arranged on second gusset 34 along the direction perpendicular to the top surface 30, it is multiple described
Second mounting hole is arranged on the fourth angle plate 36 along the direction perpendicular to the top surface 30.It is hung by adjusting
Hanging hole on pendant 4 is bolted after being aligned from different the first mounting hole and the second mounting hole, can be to suspender member 4
Height carry out flexible modulation, to adapt to the requirement of more than 62 kinds of height of the first top plate 61 and the second top plate.
Preferably, being provided with third corner brace 51 and fourth angle code 52 in the support plate 5, the third corner brace 51 includes hanging down
Direct-connected the 5th gusset 53 and hexagonal plate 54 connect, the fourth angle code 52 include heptangle plate 55 connected vertically and illiciumverum
Plate 56, the 5th gusset 53 are mounted on first faying surface, and the heptangle plate 55 is mounted on second faying surface, institute
It states hexagonal plate 54 to be arranged in parallel with the octagonal plate 56, one end that the top is hung on angle steel far from the locating piece is fixed on
Between the hexagonal plate 54 and the octagonal plate 56.Similarly, hexagonal plate 54 and octagonal plate 56 can hang angle to top
Steel effectively limits, and increases the structural stability that top hangs angle steel.
Fig. 4 is the structural schematic diagram that the closing in parts that alternative embodiment of the present invention provides are connected with mounting plate.
Referring to figure 4., the furred ceiling base further includes closing in parts and mounting plate 1;The closing in parts include sequentially connected
First shrinking plate 21, the second shrinking plate 22, third shrinking plate 23, first shrinking plate 21 are parallel with the third shrinking plate 23
It is arranged and is respectively positioned on the same side of second shrinking plate 22, in the present embodiment, closing in parts are the structure of similar " u "-shaped.Institute
It states mounting plate 1 and is mounted on the first top plate 61 and the second top plate 62 for being used to support in support plate 5 and mutually splicing.The mounting plate 1 wraps
Include the first installation end 11 and the second installation end 12 being oppositely arranged;First installation end 11 and second installation end 12 connect
The closing in parts are connected to, two closing in parts are respectively positioned on the front of the mounting plate 1.Two first shrinking plates 21
End be connected to first installation end 11 and second installation end 12, two first shrinking plates 21 are opposite to be set
It sets, any one of third shrinking plate 23 is respectively positioned on connected first shrinking plate 21 backwards to another described the
The side of one shrinking plate 21.Installation passes through mounting plate 1 and support plate there are two the structure that the mounting plate 1 of closing in parts is similar to " π "
5 are connected, and overlap the first top plate 61 and the second top plate 62 mutually spliced respectively by two third shrinking plates 23, and two at this time
It is located at the part between two the second shrinking plates 22 on two shrinking plates 22 and mounting plate 1 to the first top plate 61 and second mutually spliced
Top plate 62 closes up, and without joint filling, the flaw of the corner of the first top plate 61 and the second top plate 62 is by two the second shrinking plates 22
And the part being located between two the second shrinking plates 22 on mounting plate 1 is directly blocked, and furred ceiling surface layer mounting process, time saving province are simplified
Power improves the efficiency of construction.
Optionally, the side in the support plate 5 backwards to the locating piece is equipped with the first limit plate 57 being oppositely arranged
With the second limit plate 58, first installation end 11 is connected on first limit plate 57, and second installation end 12 abuts
On second limit plate 58.First limit plate 57 and the second limit plate 58 play positioning to mounting plate in the horizontal direction
Effect guarantees that mounting plate 1 is connected to the stability in support plate 5.
Optionally, the closing in parts further include the 4th shrinking plate 25, and the 4th shrinking plate 25 is mounted on the third and receives
One end on oralia 23 far from second shrinking plate 22 and the direction extension towards close first shrinking plate 21, the 4th closes up
Plate 25 can increase the overlapping area between the first top plate 61 and the second top plate 62 and closing in parts, be conducive to improve the first top plate 61
Stability with the second top plate 62 in stitching portion.
Preferably, first installation end 11 is provided with the first abutting plate 13, second installation end 12 is provided with second
Plate 14 is abutted, the first abutting plate 13 and the second abutting plate 14 are each perpendicular to the mounting plate 1 and are located at the installation
The back side of plate 1.The first abutting plate 13 and the second abutting plate 14 can increase the structural strength of mounting plate 1.
Further, the first abutting plate 13 is aligned setting with the edge of first installation end 11, and described second supports
Fishplate bar 14 is aligned setting with the edge of second installation end 12, can be in the first installation end 11 and the second installation end 12 setting first
When limit plate 57 and the second limit plate 58, increase the contact area and the second peace between the first installation end 11 and the first limit plate 57
The contact area between end 12 and the second limit plate is filled, the stability of mounting plate 1 is increased.
On the basis of the above embodiments, positioning plate 24 is installed, each closing in parts pass through in the closing in parts
The fitting of positioning plate 24 is arranged on the mounting plate 1.Positioning plate 24 can increase between the first shrinking plate 21 and mounting plate 1
Contact area, improve the stability connected between closing in parts and mounting plate 1.
Preferably, extending respectively to described first on one side far from first shrinking plate 21 on two positioning plates 24
The edge of installation end 11 and second installation end 12 can increase the base surface between the first installation end 11 and the first limit plate 57
The long-pending and contact area between the second installation end 12 and the second limit plate 58 increases structure between mounting plate 1 and closing in parts
Stability.
Optionally, two first shrinking plates 21 are each perpendicular to the mounting plate 1, and two the first shrinking plates 21 are set in parallel
It sets, can increase by the first top plate 61 and the second top plate 62 is overlapped on stability on third shrinking plate 23.
Further, the mounting plate 1 is stainless steel plate, and the closing in parts are stainless steel part.Stainless steel plate and stainless steel
Part has good anti-corrosion effect, can effectively extend the service life of mounting plate 1 and closing in parts.
Preferably, being located at the third shrinking plate 23 of first installation end 11 and being located at first installation end 11
The distance between described first shrinking plate 21 is greater than the edge of first installation end 11 and is located at first installation end 11
The distance between described first shrinking plate 21 can increase the stress torque of third shrinking plate 23, improve overlap joint third shrinking plate
Stability after 23 is for furred ceiling surface layer, and optionally, first keel 81 are located at the splice 7 and first top plate 61
Between, the both ends being oppositely arranged on first keel 81 are connected with first top plate 61 and the splice 7 respectively;Institute
The second keel 82 are stated between the splice 7 and second top plate 62, two be oppositely arranged on second keel 82
End is connected with the splice 7 and second top plate 62 respectively, and the first keel 81 can increase splice 7 and the first top plate
Bonding strength between 61, the second keel 82 can increase the bonding strength between splice 7 and the second top plate 62, improve furred ceiling
The stability of surface layer.
Preferably, first keel 81 include the first keel plate 83, the second keel plate 84 and the third dragon being connected
Bone plate 85, first keel plate 83 are oppositely arranged with the third keel plate 85, and the fitting of the first keel plate 83 setting exists
On the splice 7, the fitting of third keel plate 85 is arranged on first top plate 61.First keel 81 can make splice
7 and first there are certain gaps between top plate 61, convenient for the ventilation of the first top plate 61.Optionally, the second keel 82 and second
It can also be attached using aforesaid way between top plate 62, be convenient for unified construction.
As an optional implementation process, the splice 7 is the square tube of bar shaped, and square tube has high excellent of flatness
Gesture, convenient for improving the uniformity between spliced first top plate 61 and the second top plate 62.
Further, the square tube is zinc-plated square tube, and construction environment is complex, and zinc-plated square tube has corrosion-resistant characteristic,
The service life of square tube can be extended.
Further, the hollow setting of the zinc-plated square tube, can mitigate the weight of zinc-plated square tube, and zinc-plated square tube is mounted on
After on top surface 30, the stress of top surface 30 can be mitigated, improve the stability of system.
On the basis of the above embodiments, the distance between the zinc-plated square tube and first top plate 61 are equal to the side
Pipe is conducive on spliced first top plate 61 the distance between with described second top plate 62 backwards to the face of top surface 30 and the
Face on two top plates 62 backwards to top surface 30 is in the same plane.
Preferably, the quantity of the zinc-plated square tube is two, and two zinc-plated square tubes are arranged in parallel, and two described zinc-plated
Square tube is fed through spliced first top plate 61 and second top plate 62.After two zinc-plated square tubes can increase splicing
The first top plate 61 and the second top plate 62 stability.
Preferably, at least one is composite plate in first top plate 61 and second top plate 62.Composite plate has
Biggish intensity, hardness and antiwear characteristic can effectively extend the service life of the first top plate 61 and the second top plate 62.
Preferably, the first top plate 61 and the second top plate 62 can also be that NP plate, NP plate are generally 600 wide cuts, Design of length is in 2700-
3300 are advisable, and are large-scale plate, and adjacent NP plate can directly be hung after ground spliced in top surface 30, convenient for applying
Work.
Fig. 5 is the flow chart of the installation method for the big surface layer furred ceiling that alternative embodiment of the present invention provides.
As shown in figure 5, based on the same inventive concept, the present invention also provides a kind of installation method of large space furred ceiling, packets
Include following steps:S1, setting need that the interior architecture of large space furred ceiling is arranged in top surface 30;S2, in the top surface
Furred ceiling base is set on 30, and making the furred ceiling base includes locating piece, suspender member 4 and support plate 5;The locating piece fitting
It is mounted on the top surface 30;The suspender member 4 is mounted on the locating piece;The support plate 5 is mounted on the hanging
Far from one end of the top surface 30 on part 4, the support plate 5 and the distance between the locating piece are adjustable;The support
Plate 5 includes the first faying surface and the second faying surface towards the surface of the suspender member 4, and first faying surface and described second is taken
Junction is located at the two sides of the suspender member 4;S3 splices two furred ceiling surface layers, and it includes opposite for making each furred ceiling surface layer
The first top plate 61 and the second top plate 62 and splice 7 connect;The splice 7 and first top plate 61, the splice
7 are oppositely arranged with second top plate 62;S4 makes two by two furred ceiling surface layer hangings in the furred ceiling base
One end of the splice 7 is overlapped on respectively on first faying surface and second faying surface.
Large space furred ceiling and installation method provided in an embodiment of the present invention, the locating piece use the nothings such as be bonded or be spirally connected
The mode that need to be punched is jointly mounted to the top surface 30, reduces the destruction to concrete original on top surface;The hanging
The length of part 4 is adjustable, and the length of suspender member 4 can be fixed at the position regulated, to adapt to the first top plate 61 and second
The requirement for height of top plate 62 simplifies construction process, shortens construction period without scene processing;The splice 7 with it is described
First top plate 61 is connected, and the splice 7 is connected with second top plate 62;The first top plate 61 is realized by splice 7
Mutually splice with the second top plate 62, is not necessarily to on-site cutting, reduces the difficulty of construction, one end of two splices 7 is overlapped on respectively
On first faying surface and the second faying surface, the first top plate 61 and the second top plate 62 are overlapped on respectively on two third shrinking plates 23,
Reduce the first top plate 61 and the second top plate 62 overlapped difficulty.In the process, the weight of the first top plate 61 and the second top plate 62
Amount is transferred on locating piece by suspender member 4, since the contact area of locating piece and top surface 30 is larger, can reduce top
The stress of 30 unit area of surface improves the spliced stability of top plate, increases the quality of construction;And first top plate 61 and
Two top plates 62 are not necessarily to in-situ spraying and painting, shorten curing cycle, improve construction efficiency, reduce surface construction to operation people
The somatic damage of member is equal on first top plate 61 backwards to the distance between the surface of the splice 7 and the splice 7
Backwards to the distance between the surface of the splice 7 and the splice 7 on second top plate 62, ensure that after being connected to each other
The planarization of first top plate 61 and the second top plate 62 improves the spliced flatness of surface layer, lifting construction effect.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although
Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that:It still may be used
To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features;
And these are modified or replaceed, the range for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution.
Claims (10)
1. a kind of large space furred ceiling, the top surface including interior architecture, which is characterized in that further include:Furred ceiling base and difference
Two furred ceiling surface layers positioned at furred ceiling base two sides;
The furred ceiling base includes locating piece, suspender member and support plate;The locating piece is jointly mounted to the top table
Face;The suspender member is mounted on the locating piece;The support plate is mounted on the suspender member far from the top surface
One end, the distance between the support plate and the locating piece are adjustable;The support plate is wrapped towards the surface of the suspender member
The first faying surface and the second faying surface are included, first faying surface and second faying surface are located at the two of the suspender member
Side;
The furred ceiling surface layer includes the first top plate being connected to each other and the second top plate and splice;The splice and described the
One top plate, the splice and second top plate are oppositely arranged;The splice is connected with first top plate, described
Splice is connected with second top plate,
One end of two splices is overlapped on respectively on first faying surface and second faying surface.
2. large space furred ceiling according to claim 1, which is characterized in that the furred ceiling surface layer further includes the first keel and
Two keel, the splice are connected with first top plate by first keel, the splice and second top
Plate is connected by second keel.
3. large space furred ceiling according to claim 1, which is characterized in that backwards to the splice on first top plate
The distance between surface and the splice are equal on second top plate backwards to the surface of the splice and the splice
The distance between.
4. large space furred ceiling according to claim 1, which is characterized in that backwards to the table of the suspender member in the support plate
Face is parallel to the top surface.
5. large space furred ceiling according to claim 1, which is characterized in that the suspender member is that top hangs angle steel.
6. large space furred ceiling according to claim 5, which is characterized in that the locating piece includes the first corner brace and second jiao
Code, first corner brace include the first gusset and the second gusset connected vertically, and second corner brace includes connected vertically the
Set square and fourth angle plate;First gusset and the third gusset are mounted on the top surface, second gusset
Be arranged in parallel with the fourth angle plate, it is described top hang angle steel on close to the locating piece one end be fixed on second gusset and
Between the fourth angle plate.
7. large space furred ceiling according to claim 1, which is characterized in that the furred ceiling base further includes closing in parts and installation
Plate;
The closing in parts include sequentially connected first shrinking plate, the second shrinking plate, third shrinking plate, first shrinking plate with
The third shrinking plate is arranged in parallel and is respectively positioned on the same side of second shrinking plate;
The mounting plate is mounted on the side in the support plate backwards to the locating piece, and the mounting plate includes being oppositely arranged
First installation end and the second installation end;First installation end and second installation end are respectively connected with the closing in parts,
Two closing in parts are respectively positioned on the front of the mounting plate;The end of two first shrinking plates is connected to described
One installation end and second installation end, two first shrinking plates are oppositely arranged, and any one of third shrinking plate is equal
Backwards to the side of another first shrinking plate on connected first shrinking plate.
8. large space furred ceiling described in -7 any one according to claim 1, which is characterized in that the splice is the side of bar shaped
Pipe.
9. large space furred ceiling according to claim 8, which is characterized in that the square tube is zinc-plated square tube.
10. a kind of installation method of large space furred ceiling, which is characterized in that include the following steps:
Setting needs the interior architecture in top surface setting large space furred ceiling;
Furred ceiling base is set on the top surface, and making the furred ceiling base includes locating piece, suspender member and support plate;
The locating piece is jointly mounted to the top surface;The suspender member is mounted on the locating piece;The support plate installation
Far from one end of the top surface on the suspender member, the distance between the support plate and the locating piece are adjustable;Institute
State support plate towards the surface of the suspender member include the first faying surface and the second faying surface, first faying surface and described the
Two faying surfaces are located at the two sides of the suspender member;
Splice two furred ceiling surface layers, each furred ceiling surface layer is made to include the first top plate being connected to each other and the second top plate and spell
Fitting;The splice is oppositely arranged with first top plate, the splice and second top plate;
By two furred ceiling surface layer hangings in the furred ceiling base, one end of two splices is made to be overlapped on institute respectively
It states on the first faying surface and second faying surface.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810833518.1A CN108867978B (en) | 2018-07-26 | 2018-07-26 | Large-space suspended ceiling and installation method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810833518.1A CN108867978B (en) | 2018-07-26 | 2018-07-26 | Large-space suspended ceiling and installation method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108867978A true CN108867978A (en) | 2018-11-23 |
| CN108867978B CN108867978B (en) | 2024-04-16 |
Family
ID=64305285
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810833518.1A Active CN108867978B (en) | 2018-07-26 | 2018-07-26 | Large-space suspended ceiling and installation method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108867978B (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109852942A (en) * | 2019-01-09 | 2019-06-07 | 苏州求是真空电子有限公司 | A kind of anti-pollution Combined-type sheet-type baffle |
| CN113356458A (en) * | 2021-06-21 | 2021-09-07 | 北新集团建材股份有限公司 | Ceiling member and ceiling board mounting method |
| CN113356461A (en) * | 2021-06-21 | 2021-09-07 | 北新集团建材股份有限公司 | Combined ceiling mounting structure, ceiling assembly and mounting method thereof |
| CN114293699A (en) * | 2022-01-12 | 2022-04-08 | 浙江亚厦装饰股份有限公司 | Assembled overlap joint cavity furred ceiling |
| CN117071807A (en) * | 2023-08-25 | 2023-11-17 | 浙江亚厦装饰股份有限公司 | A kind of ceiling panel installation structure and installation method |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201391034Y (en) * | 2009-03-26 | 2010-01-27 | 徐蕴慧 | Main keel with the hanging function |
| CN202055389U (en) * | 2011-04-07 | 2011-11-30 | 深圳市洪涛装饰股份有限公司 | Modularized suspended ceiling structure |
| US20150027075A1 (en) * | 2012-02-23 | 2015-01-29 | Saint-Gobain Ecophon Ab | Suspended ceiling, a ceiling tile and an associated installation method |
| CN204626738U (en) * | 2015-04-30 | 2015-09-09 | 山东万得福装饰工程有限公司 | A kind of ceiling structure |
| CN206546099U (en) * | 2017-03-14 | 2017-10-10 | 石家庄钢铁有限责任公司 | Erecting by overhang at the top of a kind of furnace flue |
| CN107304598A (en) * | 2016-04-20 | 2017-10-31 | 北新集团建材股份有限公司 | A kind of dark frame ceiling system and its installation method |
| CN206667565U (en) * | 2017-04-20 | 2017-11-24 | 北京广佳建筑装饰股份有限公司 | A kind of ceiling structure |
| CN211341371U (en) * | 2018-07-26 | 2020-08-25 | 浙江亚厦装饰股份有限公司 | Large-space suspended ceiling |
-
2018
- 2018-07-26 CN CN201810833518.1A patent/CN108867978B/en active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201391034Y (en) * | 2009-03-26 | 2010-01-27 | 徐蕴慧 | Main keel with the hanging function |
| CN202055389U (en) * | 2011-04-07 | 2011-11-30 | 深圳市洪涛装饰股份有限公司 | Modularized suspended ceiling structure |
| US20150027075A1 (en) * | 2012-02-23 | 2015-01-29 | Saint-Gobain Ecophon Ab | Suspended ceiling, a ceiling tile and an associated installation method |
| CN204626738U (en) * | 2015-04-30 | 2015-09-09 | 山东万得福装饰工程有限公司 | A kind of ceiling structure |
| CN107304598A (en) * | 2016-04-20 | 2017-10-31 | 北新集团建材股份有限公司 | A kind of dark frame ceiling system and its installation method |
| CN206546099U (en) * | 2017-03-14 | 2017-10-10 | 石家庄钢铁有限责任公司 | Erecting by overhang at the top of a kind of furnace flue |
| CN206667565U (en) * | 2017-04-20 | 2017-11-24 | 北京广佳建筑装饰股份有限公司 | A kind of ceiling structure |
| CN211341371U (en) * | 2018-07-26 | 2020-08-25 | 浙江亚厦装饰股份有限公司 | Large-space suspended ceiling |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109852942A (en) * | 2019-01-09 | 2019-06-07 | 苏州求是真空电子有限公司 | A kind of anti-pollution Combined-type sheet-type baffle |
| CN109852942B (en) * | 2019-01-09 | 2024-05-07 | 杭州比凡科电子科技有限公司 | Anti-pollution sheet type combined baffle |
| CN113356458A (en) * | 2021-06-21 | 2021-09-07 | 北新集团建材股份有限公司 | Ceiling member and ceiling board mounting method |
| CN113356461A (en) * | 2021-06-21 | 2021-09-07 | 北新集团建材股份有限公司 | Combined ceiling mounting structure, ceiling assembly and mounting method thereof |
| CN114293699A (en) * | 2022-01-12 | 2022-04-08 | 浙江亚厦装饰股份有限公司 | Assembled overlap joint cavity furred ceiling |
| CN114293699B (en) * | 2022-01-12 | 2024-10-25 | 浙江亚厦装饰股份有限公司 | Assembled overlap joint cavity furred ceiling |
| CN117071807A (en) * | 2023-08-25 | 2023-11-17 | 浙江亚厦装饰股份有限公司 | A kind of ceiling panel installation structure and installation method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108867978B (en) | 2024-04-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108867978A (en) | Large space furred ceiling and installation method | |
| CN108049552B (en) | Top-mounted drop-grade ceiling and installation method | |
| CN106013585B (en) | Furred ceiling falls stage arrangement and installation method | |
| CN103031964B (en) | Modularized clean operating room and installation technology thereof | |
| WO2007131387A1 (en) | Assembly type wall structure | |
| CN205917957U (en) | Modularization furred ceiling falls a grade device | |
| CN108049554A (en) | Double-deck drop level furred ceiling and installation method | |
| CN207998973U (en) | Pendant and ceiling joist component | |
| CN107587643B (en) | Suspended ceiling structure capable of being assembled in quick plugging manner | |
| CN1392314A (en) | Building assembling method using thin plate light steel | |
| US9482000B2 (en) | Hanger devices for interstital seismic resistant support for an acoustic ceiling grid | |
| CN115030362B (en) | A composite wall for modular substation and its construction process | |
| CN203878746U (en) | Assembled lightweight house | |
| CN108518008B (en) | Rigid roof structure on flexible inhaul cable structure and mounting method thereof | |
| CN211114323U (en) | Suspended ceiling basic unit | |
| CN211341371U (en) | Large-space suspended ceiling | |
| CN210947361U (en) | A multi-point hanging prefabricated ceiling installation structure | |
| CN204311792U (en) | A kind of fire wall | |
| CN208518081U (en) | A kind of folded grade type sets of brackets on top of the columns aluminium sheet connector system | |
| CN208122075U (en) | Top hangs drop level furred ceiling | |
| CN211690983U (en) | Floor board frame and floor board structure | |
| CN204113300U (en) | Municipal tunnel | |
| CN209723240U (en) | Prefabricated single bevel tubular truss tubular joint | |
| CN116065780A (en) | Seamless and safe connection structure for decorative surface layer and application method thereof | |
| CN207974326U (en) | Toilet furred ceiling component |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |