CN108867651A - A kind of pervious concrete well casing mounting device for base pit dewatering - Google Patents

A kind of pervious concrete well casing mounting device for base pit dewatering Download PDF

Info

Publication number
CN108867651A
CN108867651A CN201810834327.7A CN201810834327A CN108867651A CN 108867651 A CN108867651 A CN 108867651A CN 201810834327 A CN201810834327 A CN 201810834327A CN 108867651 A CN108867651 A CN 108867651A
Authority
CN
China
Prior art keywords
dewatering
well
guide pipe
pipe
mounting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810834327.7A
Other languages
Chinese (zh)
Other versions
CN108867651B (en
Inventor
赵卫政
郁邦永
潘书才
钱冬冬
王学海
王国祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhou Vocational Institute of Engineering
Original Assignee
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201810834327.7A priority Critical patent/CN108867651B/en
Publication of CN108867651A publication Critical patent/CN108867651A/en
Application granted granted Critical
Publication of CN108867651B publication Critical patent/CN108867651B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

本发明提供一种适用于基坑降水的透水混凝土井管安装装置,包括:起重机,吊装装置,导向装置和定位装置;所述定位装置包括密封圈及底座,所述底座大小与降水井截面大小相适配,并使底座沿着降水井内壁同轴上下移动;所述密封圈与底座同轴安装固定;所述导向装置包括导向管、定位柱,吊装时所述导向管下端通过密封圈与底座可拆卸同轴安装;所述导向管露出降水井部分通过定位柱定位使导向管上端保持与底座同轴;所述起重机通过吊装装置与透水混凝土井管连接,吊装时,所述起重机挂钩承重点、透水混凝土井管与降水井同轴线。该发明可以实现降水井管的快速精准安装,保证各段井管间的密封,具有广泛的实用性。

The invention provides a permeable concrete well pipe installation device suitable for foundation pit dewatering, comprising: a crane, a hoisting device, a guiding device and a positioning device; and make the base move up and down coaxially along the inner wall of the dewatering well; the sealing ring is coaxially installed and fixed with the base; the guide device includes a guide tube and a positioning column, and the lower end of the guide tube passes through the seal ring and the positioning column during hoisting. The base is detachable and installed coaxially; the part of the guide pipe exposed to the dewatering well is positioned by the positioning column so that the upper end of the guide pipe remains coaxial with the base; the crane is connected to the permeable concrete well pipe through a hoisting device. The key point is the coaxial line between the permeable concrete well pipe and the dewatering well. The invention can realize fast and accurate installation of the downwater well pipes, ensure the sealing between each section of the well pipes, and has wide practicability.

Description

一种用于基坑降水的透水混凝土井管安装装置A permeable concrete well pipe installation device for foundation pit dewatering

技术领域technical field

本发明涉及建筑工程中吊装装置技术领域,尤其是涉及一种用于基坑降水的透水混凝土井管安装装置。The invention relates to the technical field of hoisting devices in construction engineering, in particular to a permeable concrete well pipe installation device for foundation pit dewatering.

技术背景technical background

近年来,随着高层建筑的逐渐增多,建筑物地基基础的埋置越来越深,工程建设常常需要在含水层中进行施工,因而大多都涉及到基坑降水。为了提高降水效率,在基坑内布置多处降水井降低地下水位,提高施工安全性。目前降水井井管大量使用了透水材料,主要包括无砂管和透水混凝土。传统的降水井管安装方法主要依赖于人工,工具主要包括溜绳器和钢丝绳,施工流程:埋设圆木溜绳器、搭设工作平台和下管作业。施工过程中钢丝绳穿过最下面一节降水井管底部,其余井管叠放在其上,钢丝绳承受载荷较大,其收放均难以控制;未设置降水井管定位和导向装置,容易出现降水井管的倾斜、贴壁、滤料不均匀等问题;工序繁琐,施工效率低,用时长,容易导致井孔的变形和坍塌。本发明设计一种降水井管安装装置,配置定位和导向装置,保证降水井管安装于井孔中心位置,且利用电动葫芦进行降水井管的下放,极大提高了施工效率,具有重要的实用意义。In recent years, with the gradual increase of high-rise buildings, the foundations of buildings are buried deeper and deeper, and engineering construction often requires construction in aquifers, so most of them involve foundation pit precipitation. In order to improve the dewatering efficiency, multiple dewatering wells are arranged in the foundation pit to reduce the groundwater level and improve the construction safety. At present, a large number of permeable materials are used in the well pipes of precipitation wells, mainly including sand-free pipes and permeable concrete. The traditional installation method of dewatering well pipe mainly relies on labor, and the tools mainly include rope slides and wire ropes. The construction process: burying log rope slides, erecting working platforms and lowering pipes. During the construction process, the steel wire rope passes through the bottom of the bottom section of the dewatering well pipe, and the rest of the well pipes are stacked on top of it. The steel wire rope bears a large load, and its retraction is difficult to control; the positioning and guiding device for the dewatering well pipe is not installed, and precipitation is prone to occur Problems such as the inclination of the well pipe, sticking to the wall, and uneven filter material; the process is cumbersome, the construction efficiency is low, and the construction time is long, which may easily lead to deformation and collapse of the well hole. The invention designs a dewatering well pipe installation device, which is equipped with positioning and guiding devices to ensure that the dewatering well pipe is installed in the center of the well hole, and uses an electric hoist to lower the dewatering well pipe, which greatly improves the construction efficiency and has important practical significance.

发明内容Contents of the invention

本发明的目的是针对现有技术中存在的问题,提供一种结构简单、操作方便、定位精准,安全高效的用于基坑降水的透水混凝土井管安装装置。The purpose of the present invention is to solve the problems existing in the prior art, and provide a simple structure, convenient operation, accurate positioning, safe and efficient permeable concrete well pipe installation device for foundation pit dewatering.

为了实现上述目的,本发明的技术方案为:In order to achieve the above object, the technical solution of the present invention is:

一种用于基坑降水的透水混凝土井管安装装置,包括:起重机,吊装装置,导向装置和定位装置;A permeable concrete well pipe installation device for foundation pit dewatering, comprising: a crane, a hoisting device, a guiding device and a positioning device;

所述定位装置包括密封圈及底座,所述底座大小与降水井截面大小相适配,并使底座沿着降水井内壁同轴上下移动;所述密封圈与底座同轴安装固定;The positioning device includes a sealing ring and a base, the size of the base is adapted to the size of the section of the dewatering well, and the base moves up and down coaxially along the inner wall of the dewatering well; the sealing ring and the base are coaxially installed and fixed;

所述导向装置包括导向管、定位柱,吊装时所述导向管下端通过密封圈与底座可拆卸同轴安装;所述导向管露出降水井部分通过定位柱定位使导向管上端保持与底座同轴;所述定位柱为可收缩结构,当吊装的透水混凝土井管顺着导向管外壁下降时定位柱收缩;The guide device includes a guide tube and a positioning column. When hoisting, the lower end of the guide tube is detachably installed coaxially with the base through a sealing ring; the part of the guide tube exposed to the dewatering well is positioned by the positioning column so that the upper end of the guide tube remains coaxial with the base The positioning column is a shrinkable structure, and the positioning column shrinks when the hoisted permeable concrete well pipe descends along the outer wall of the guide pipe;

所述起重机安装在降水井旁,所述起重机通过吊装装置与透水混凝土井管连接,吊装时,所述起重机挂钩承重点、透水混凝土井管与降水井同轴线。The crane is installed next to the dewatering well, and the crane is connected with the permeable concrete well pipe through a hoisting device. When hoisting, the crane hooks the bearing point, the permeable concrete well pipe and the dewatering well are coaxial.

作为本发明的优选实施例,为了实现透水混凝土井管的平稳、快捷、方便吊装:所述吊装装置包括安装板、电动葫芦以及吊环,所述安装板通过吊绳悬挂在起重机挂钩上;所述电动葫芦设置在安装板两侧并呈对称分布,电动葫芦的卷筒上设有钢丝绳;所述吊环与电动葫芦位置垂直对应安装在透水混凝土井管上端口外沿上;吊装时,所述钢丝绳一端穿过降水井管上的吊环后回转并可拆卸安装在安装板上。As a preferred embodiment of the present invention, in order to achieve stable, fast and convenient hoisting of the permeable concrete well pipe: the hoisting device includes a mounting plate, an electric hoist and a lifting ring, and the mounting plate is suspended on a crane hook through a sling; The electric hoist is arranged on both sides of the installation plate and distributed symmetrically. The reel of the electric hoist is provided with a steel wire rope; One end passes through the suspension ring on the downwater well pipe and then turns and is detachably installed on the mounting plate.

为了防止外部泥沙进入管内,本发明的进一步改进在于:设有土工布,所述密封圈分为上密封圈和下密封圈,所述土工布四周固定于上密封圈和下密封圈之间。In order to prevent external silt from entering the pipe, the further improvement of the present invention is that a geotextile is provided, the sealing ring is divided into an upper sealing ring and a lower sealing ring, and the geotextile is fixed around the upper sealing ring and the lower sealing ring .

作为本发明的进一步改进在于:所述上密封圈为中空的圆锥台结构,下密封圈为圆环结构,从而保证了导向管的安装。As a further improvement of the present invention, the upper sealing ring is a hollow truncated cone structure, and the lower sealing ring is a ring structure, thereby ensuring the installation of the guide tube.

作为本发明的进一步改进在于:所述导向管下端与上密封圈之间为过盈配合安装。As a further improvement of the present invention, the lower end of the guide tube and the upper sealing ring are installed with an interference fit.

为了实现对导向管的快速且准确的定位,所述定位柱数量至少有三根,且均匀分布在导向管四周,随时根据需要调节偏离方位。In order to realize fast and accurate positioning of the guide tube, there are at least three positioning columns, which are evenly distributed around the guide tube, and the deviation orientation can be adjusted at any time as needed.

作为本发明的进一步改进在于:所述导向管截面大小与透水混凝土井管截面大小相适配,使透水混凝土井管套接在导向管上并沿着导向管外壁同轴上下移动。As a further improvement of the present invention, the size of the section of the guide pipe is adapted to the section size of the permeable concrete well pipe, so that the permeable concrete well pipe is sleeved on the guide pipe and moves up and down coaxially along the outer wall of the guide pipe.

作为本发明的进一步改进在于:所述定位装置的底座下面设有砂层。As a further improvement of the present invention, a sand layer is provided under the base of the positioning device.

为了保证吊装装置的平稳联接,作为本发明的进一步改进在于:所述安装板上设有至少四个呈中心对称分布的挂环,所述安装板通过吊绳与挂环的连接实现吊装装置的吊装。In order to ensure the smooth connection of the hoisting device, as a further improvement of the present invention, the mounting plate is provided with at least four center-symmetrically distributed hanging rings, and the mounting board realizes the connection of the hoisting device through the connection of the hanging rope and the hanging rings. Hoisting.

本发明的有益效果在于:本发明不仅可以减少降水井管吊装程序,提高施工效率,同时利用定位管预先对降水井管进行定位,有效减少降水井管倾斜造成的贴壁、滤料不均匀等问题,同时在降水井管顶部设置密封垫圈,实现井管间的密封,防止外部泥沙进入井管内部,从而保证降水井管的排水效果。其结构简单,吊装效率高,故障率低,投资少,具有广泛的实用性。The beneficial effect of the present invention is that: the present invention can not only reduce the hoisting procedure of the dewatering well pipe, improve the construction efficiency, but also use the positioning pipe to pre-position the dewatering well pipe, effectively reducing the sticking of the dewatering well pipe and uneven filter material, etc. At the same time, a sealing gasket is set on the top of the dewatering well pipe to realize the sealing between the well pipes and prevent external sediment from entering the inside of the well pipe, thereby ensuring the drainage effect of the dewatering well pipe. The utility model has the advantages of simple structure, high hoisting efficiency, low failure rate, low investment and wide practicability.

附图说明Description of drawings

图1为本发明的基坑降水用透水混凝土井管安装装置结构示意图。Fig. 1 is a structural schematic diagram of a permeable concrete well pipe installation device for foundation pit dewatering according to the present invention.

图2为本发明中定位装置的结构示意图。Fig. 2 is a schematic structural diagram of the positioning device in the present invention.

图中:起重机-1,降水井-2,安装板-3,电动葫芦-4,钢丝绳-5,密封垫圈-6,吊环-7,透水混凝土降水井管-8,定位柱-9,导向管-10,吊绳-11,上密封圈-12,下密封圈-13,螺丝钉-14,土工布-15,底座-16,粗砂层-17。In the figure: crane-1, dewatering well-2, mounting plate-3, electric hoist-4, wire rope-5, sealing washer-6, lifting ring-7, permeable concrete dewatering well pipe-8, positioning column-9, guide pipe -10, sling-11, upper sealing ring-12, lower sealing ring-13, screw-14, geotextile-15, base-16, coarse sand layer-17.

具体实施方式Detailed ways

下面将结合附图对本发明的一个实施例作进一步的说明:An embodiment of the present invention will be further described below in conjunction with accompanying drawing:

如图1所示,基坑降水用透水混凝土井管安装装置主要由安装板3,电动葫芦4,钢丝绳5,吊环7,定位柱9,导向管10,吊绳11,上密封圈12,下密封圈13,土工布15,底座16构成。As shown in Figure 1, the permeable concrete well pipe installation device for foundation pit dewatering is mainly composed of a mounting plate 3, an electric hoist 4, a steel wire rope 5, a lifting ring 7, a positioning column 9, a guide pipe 10, a lifting rope 11, an upper sealing ring 12, a lower Sealing ring 13, geotextile 15, base 16 constitute.

如图1所示,吊装装置设置在降水井2上方,包括安装板3、两个电动葫芦4、钢丝绳5以及两个吊环7,其中安装板3上对称设置四个挂环,并通过吊绳11悬挂在起重机1挂钩上,电动葫芦4固定在安装板3两侧,吊环7与电动葫芦4位置垂直对应,钢丝绳5一端绕过电葫芦卷筒,另一端穿过透水混凝土降水井管8上的吊环7后通过销轴固定在安装板3下面,透水混凝土降水井管8吊装到位后取下销轴,实现钢丝绳5的回收,吊环7通过钢丝安装在透水混凝土降水井管8上口附近,实现钢丝绳5的滑动,透水混凝土降水井管8上口内侧安装密封垫圈6,实现相邻两节井管的密封。As shown in Figure 1, the hoisting device is arranged above the dewatering well 2, including a mounting plate 3, two electric hoists 4, a wire rope 5 and two lifting rings 7, wherein four hanging rings are symmetrically arranged on the mounting plate 3, and are 11 is suspended on the hook of the crane 1, the electric hoist 4 is fixed on both sides of the installation plate 3, the suspension ring 7 is vertically corresponding to the position of the electric hoist 4, one end of the steel wire rope 5 bypasses the electric hoist drum, and the other end passes through the permeable concrete dewatering well pipe 8 After the lifting ring 7 is fixed below the mounting plate 3 by the pin shaft, the pin shaft is removed after the permeable concrete dewatering well pipe 8 is hoisted in place to realize the recovery of the steel wire rope 5. The sliding of the steel wire rope 5 is realized, and the sealing washer 6 is installed on the inner side of the upper mouth of the permeable concrete dewatering well pipe 8, so as to realize the sealing of two adjacent joints of the well pipe.

如图2所示,定位装置包括上密封圈12、下密封圈13、螺丝钉14、土工布15以及底座16,上密封圈12与下密封圈13通过螺丝钉14固定于底座16上,土工布15通过螺丝钉14固定在上密封圈12与下密封圈13之间,保证透水混凝土降水井管8外部大颗粒泥沙不会进入降水井管内部。其中,底座16截面大小与降水井截面大小相适配,并使底座16沿着降水井2内壁同轴上下移动,从而实现底座中心的定位。本实施例中上密封圈12为中空的圆锥台结构,下密封圈13为圆环结构。As shown in Figure 2, the positioning device includes an upper sealing ring 12, a lower sealing ring 13, a screw 14, a geotextile 15 and a base 16, the upper sealing ring 12 and the lower sealing ring 13 are fixed on the base 16 by screws 14, and the geotextile 15 The screw 14 is fixed between the upper sealing ring 12 and the lower sealing ring 13 to ensure that the large particles of silt outside the permeable concrete downwater well pipe 8 will not enter the inside of the downwater well pipe. Wherein, the cross-sectional size of the base 16 is adapted to the cross-sectional size of the dewatering well, and the base 16 is moved up and down coaxially along the inner wall of the dewatering well 2, thereby realizing the positioning of the center of the base. In this embodiment, the upper sealing ring 12 is a hollow truncated cone structure, and the lower sealing ring 13 is a ring structure.

如图1所示,导向装置包括导向管10、定位柱9,其中导向管10上端即露出降水井部分通过定位柱9定位在与降水井同轴中心位置,导向管10下端与上密封圈12过盈配合连接,实现导向管10在降水井底部的中心定位;同时在透水混凝土降水井管8全部吊装后,利用透水混凝土降水井管8的自重实现两者分离。本实施例中,三根定位柱均匀分别在导向管10四周,其可采用油缸或气缸或螺杆等结构,定位柱9一端铰接在地面上,伸缩端通过活动销轴铰接在导向管10上,当透水混凝土降水井管8向下吊装时,活动销轴取下,实现定位柱9与导向管10的分离,保证透水混凝土降水井管8通过降水井口。As shown in Figure 1, the guide device includes a guide tube 10 and a positioning column 9, wherein the upper end of the guide tube 10 is exposed to the part of the dewatering well and is positioned at the coaxial center position with the dewatering well through the positioning column 9, and the lower end of the guide tube 10 is connected to the upper sealing ring 12 The interference fit connection realizes the central positioning of the guide pipe 10 at the bottom of the dewatering well; at the same time, after all the permeable concrete dewatering well pipes 8 are hoisted, the self-weight of the permeable concrete dewatering well pipe 8 is used to realize the separation of the two. In this embodiment, the three positioning columns are evenly arranged around the guide tube 10 respectively, which can adopt structures such as oil cylinders, air cylinders or screw rods. One end of the positioning column 9 is hinged on the ground, and the telescopic end is hinged on the guide tube 10 through a movable pin. When the permeable concrete dewatering well pipe 8 is hoisted downward, the movable pin shaft is taken off to realize the separation of the positioning column 9 and the guide pipe 10, ensuring that the permeable concrete dewatering well pipe 8 passes through the dewatering wellhead.

如图1所示,基坑降水用透水混凝土井管安装装置工作过程:在钻井完成后,向井底填砂层,本实施例采用粗砂形成粗砂层17,作为滤层;在导向管10下口与定位装置的上密封圈12连接后,将导向管10沿井壁下放,到达井底后,轻微上提后向下振捣,重复3-5次,实现井底的找平,通过底座16与井壁的贴合,实现导向管10在井底中心的定位;As shown in Figure 1, the working process of the permeable concrete well pipe installation device for foundation pit dewatering: after the drilling is completed, the sand layer is filled to the bottom of the well. In this embodiment, coarse sand is used to form a coarse sand layer 17 as a filter layer; After the lower port is connected with the upper sealing ring 12 of the positioning device, lower the guide pipe 10 along the well wall. 16 fits with the well wall to realize the positioning of the guide pipe 10 at the center of the well bottom;

将导向管10下端定位连接后,在导向管10上口放置水平尺,通过定位柱9的伸缩调整导向管10的位置,实现导向管10在降水井轴心的定位;在透水混凝土降水井管8上口内侧安装密封垫圈6,利用钢丝将吊环7安装在透水混凝土降水井管8上口外侧,钢丝绳5一端穿过吊环7,利用活动销轴将钢丝绳5固定在安装板3下面;利用起重机1将透水混凝土降水井管8提升至导向管10上方,调整透水混凝土降水井管8位置,实现透水混凝土降水井管8与导向管10的同轴,起重机1上挂钩下放实现透水混凝土降水井管8下端部分套在导向管10上,保持起重机1上挂钩的位置;After the lower end of the guide pipe 10 is positioned and connected, a level is placed on the upper mouth of the guide pipe 10, and the position of the guide pipe 10 is adjusted through the expansion and contraction of the positioning column 9, so as to realize the positioning of the guide pipe 10 at the axis of the dewatering well; Install sealing gasket 6 on the inner side of the upper opening of 8, install the lifting ring 7 on the outer side of the upper opening of the permeable concrete dewatering well pipe 8 by using steel wire, one end of the steel wire rope 5 passes through the lifting ring 7, and use the movable pin to fix the steel wire rope 5 under the mounting plate 3; 1 Lift the permeable concrete dewatering well pipe 8 above the guide pipe 10, adjust the position of the permeable concrete dewatering well pipe 8, realize the coaxiality between the permeable concrete dewatering well pipe 8 and the guide pipe 10, and lower the hook on the crane 1 to realize the permeable concrete dewatering well pipe 8. The lower end part is set on the guide pipe 10 to keep the position of the hook on the crane 1;

将定位柱9收起,启动电动葫芦4,实现透水混凝土降水井管8的下放,待透水混凝土降水井管8全部进入降水井后,将定位柱9复位;待透水混凝土降水井管8吊装到位后,关闭电动葫芦4,取出安装板3下面活动销轴,反转电动葫芦4,实现钢丝绳5的回收;待全部透水混凝土降水井管8吊装完毕后,向透水混凝土降水井管8与井壁间隙间填充滤料和黏土,井口外再用黏土拍实;最后,正反转动导向管10各3次,向上拔出导向管10。Put away the positioning column 9, start the electric hoist 4, realize the lowering of the permeable concrete dewatering well pipe 8, and reset the positioning column 9 after all the permeable concrete dewatering well pipes 8 enter the dewatering well; wait for the permeable concrete dewatering well pipe 8 to be hoisted in place Finally, close the electric hoist 4, take out the movable pin shaft below the mounting plate 3, reverse the electric hoist 4, and realize the recovery of the wire rope 5; The gaps are filled with filter material and clay, and the outside of the wellhead is tapped with clay; finally, the guide tube 10 is rotated forward and reverse three times each, and the guide tube 10 is pulled out upward.

显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例,附图中给出了本发明的较佳实施例。本发明可以以许多不同的形式来实现,并不限于本文所描述的实施例,相反地,提供这些实施例的目的是使对本发明的公开内容的理解更加透彻全面。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。Apparently, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments, and the preferred embodiments of the present invention are shown in the accompanying drawings. The present invention can be implemented in many different forms and is not limited to the embodiments described herein, on the contrary, these embodiments are provided for the purpose of making the disclosure of the present invention more thorough and comprehensive. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

Claims (9)

1. a kind of pervious concrete well casing mounting device for base pit dewatering, which is characterized in that including:Crane, lifting dress It sets, guiding device and positioning device;The positioning device includes sealing ring and pedestal, and the pedestal size and dewatering well section are big It is small to be adapted, and move up and down pedestal coaxially along dewatering well inner wall;The sealing ring and pedestal are co-axially mounted fixation;It is described Guiding device includes guide pipe, positioning column, and when lifting, the guide pipe lower end was detachably co-axially mounted by sealing ring with pedestal; The guide pipe exposes dewatering well part makes guide pipe upper end keep coaxial with pedestal by positioning column positioning;The positioning column is Retractable structure, when the pervious concrete well casing of lifting is along guiding pipe outer wall decline, positioning column is shunk;The crane peace By dewatering well, the crane is connect by hanging apparatus with pervious concrete well casing, and when lifting, the crane is linked up with Supporting point, pervious concrete well casing and dewatering well coaxial line.
2. mounting device according to claim 1, which is characterized in that the hanging apparatus includes mounting plate, electric block And hanging ring, the mounting plate are suspended on crane hook by lifting rope;Electric block setting mounting plate two sides simultaneously It is symmetric, the reel of electric block is equipped with wirerope;The hanging ring and electric block position are vertical corresponding to be mounted on On water coagulation soil well casing upper port outer;When lifting, described wirerope one end is turned round after passing through the hanging ring on downcast well pipe and can Disassembly installation is on a mounting board.
3. mounting device according to claim 1, which is characterized in that be equipped with geotextiles, the sealing ring is divided into sealing Circle and lower seal, the geotextiles surrounding are fixed between upper seal and lower seal.
4. mounting device according to claim 3, which is characterized in that the upper seal is hollow circular cone structure, Lower seal is circular ring structure.
5. mounting device according to claim 4, which is characterized in that be between the guide pipe lower end and upper seal It is full of and is coupled.
6. mounting device according to claim 1, which is characterized in that the positioning column quantity at least three, and uniformly It is distributed in guide pipe surrounding.
7. mounting device according to claim 1, which is characterized in that the guide pipe cross-sectional sizes and pervious concrete well Tube section size is adapted, and pervious concrete well casing is made to be socketed on guide pipe and move up and down along guide pipe wall coaxial.
8. mounting device according to claim 1, which is characterized in that layer of sand is arranged below in the pedestal of the positioning device.
9. mounting device according to claim 2, which is characterized in that it is in center pair that the mounting plate, which is equipped at least four, Claim the link of distribution, the mounting plate realizes the lifting of hanging apparatus by the connection of lifting rope and link.
CN201810834327.7A 2018-07-26 2018-07-26 Water permeable concrete well pipe installation device for foundation pit dewatering Active CN108867651B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810834327.7A CN108867651B (en) 2018-07-26 2018-07-26 Water permeable concrete well pipe installation device for foundation pit dewatering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810834327.7A CN108867651B (en) 2018-07-26 2018-07-26 Water permeable concrete well pipe installation device for foundation pit dewatering

Publications (2)

Publication Number Publication Date
CN108867651A true CN108867651A (en) 2018-11-23
CN108867651B CN108867651B (en) 2024-07-05

Family

ID=64305347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810834327.7A Active CN108867651B (en) 2018-07-26 2018-07-26 Water permeable concrete well pipe installation device for foundation pit dewatering

Country Status (1)

Country Link
CN (1) CN108867651B (en)

Citations (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3321916A1 (en) * 1983-06-16 1985-01-17 Ulrich Dr.Ing. e.h. Dr.Ing. 8000 München Finsterwalder Well for passing through non-load-bearing soil layers
CN2071701U (en) * 1990-09-11 1991-02-20 辽河石油勘探局钻采工艺研究院 Casing centralizer for directional well
CN2312969Y (en) * 1997-10-15 1999-04-07 上海港务工程公司 Implement for laying-out building cloth
JP2007285090A (en) * 2006-04-20 2007-11-01 Takenaka Komuten Co Ltd Underground water level lowering method for excavated ground, and filling/pumping well for use in the method
CN101363228A (en) * 2008-05-23 2009-02-11 上海广联建设发展有限公司 Tube well for simultaneously dewatering and decompressing and technology thereof
JP2009121063A (en) * 2007-11-12 2009-06-04 Ohbayashi Corp Service well, method of constructing service well, and structure of service well
CN201943608U (en) * 2010-12-17 2011-08-24 中国石油天然气集团公司 Excessively-moved pipe centering device
CN102518133A (en) * 2011-12-15 2012-06-27 昆明理工大学 Pile sinking method for prestress hollow pipe piles by aid of follow-up sleeve
CN203160245U (en) * 2013-04-03 2013-08-28 中铁十局集团第二工程有限公司 Positioning device for temporary steel-pipe column pile
CN103601089A (en) * 2013-11-22 2014-02-26 山东矿业管理技术服务集团有限公司 Shaft construction air duct suspension method
CN203569575U (en) * 2013-09-18 2014-04-30 上海岩土工程勘察设计研究院有限公司 Plastic blind ditch pipe sandless precipitation well
CN204849792U (en) * 2015-05-14 2015-12-09 中国建筑第八工程局有限公司 Precipitation well well casing underpins support
CN105350555A (en) * 2015-11-27 2016-02-24 上海长凯岩土工程有限公司 Fast construction method of precipitation well
CN205152969U (en) * 2015-11-19 2016-04-13 中国建筑第七工程局有限公司 A precipitation tubular well structure for foundation ditch precipitation
CN105696611A (en) * 2014-11-25 2016-06-22 中冶天工上海十三冶建设有限公司 Foundation pit dewatering device for sand layer with high water permeability
CN206266082U (en) * 2016-12-15 2017-06-20 中建筑港集团有限公司 A kind of hanging apparatus for being available for polytypic caisson to lift
CN106968263A (en) * 2017-04-25 2017-07-21 中国二十冶集团有限公司 A kind of sunk safely without sand precipitation pipe well sets construction method
CN107460885A (en) * 2017-09-22 2017-12-12 中国路桥工程有限责任公司 A kind of relief well of deep foundation pit and its construction method
CN107476337A (en) * 2017-08-21 2017-12-15 中铁六局集团有限公司 The prefabricated side wall assembling and construction method in open cut subway assembled station
US20180044907A1 (en) * 2016-08-12 2018-02-15 Wuhan Zhihe Geotechnical Engineering Co., Ltd Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
CN207073140U (en) * 2017-08-22 2018-03-06 中国建筑第七工程局有限公司 A kind of well casing dewatering well dewatering device
CN207079569U (en) * 2017-07-26 2018-03-09 浙江省工程勘察院 A kind of side slope slopes automate dewatering device
CN208618415U (en) * 2018-07-26 2019-03-19 江苏兴厦建设工程集团有限公司 A kind of pervious concrete well casing mounting device for base pit dewatering

Patent Citations (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3321916A1 (en) * 1983-06-16 1985-01-17 Ulrich Dr.Ing. e.h. Dr.Ing. 8000 München Finsterwalder Well for passing through non-load-bearing soil layers
CN2071701U (en) * 1990-09-11 1991-02-20 辽河石油勘探局钻采工艺研究院 Casing centralizer for directional well
CN2312969Y (en) * 1997-10-15 1999-04-07 上海港务工程公司 Implement for laying-out building cloth
JP2007285090A (en) * 2006-04-20 2007-11-01 Takenaka Komuten Co Ltd Underground water level lowering method for excavated ground, and filling/pumping well for use in the method
JP2009121063A (en) * 2007-11-12 2009-06-04 Ohbayashi Corp Service well, method of constructing service well, and structure of service well
CN101363228A (en) * 2008-05-23 2009-02-11 上海广联建设发展有限公司 Tube well for simultaneously dewatering and decompressing and technology thereof
CN201943608U (en) * 2010-12-17 2011-08-24 中国石油天然气集团公司 Excessively-moved pipe centering device
CN102518133A (en) * 2011-12-15 2012-06-27 昆明理工大学 Pile sinking method for prestress hollow pipe piles by aid of follow-up sleeve
CN203160245U (en) * 2013-04-03 2013-08-28 中铁十局集团第二工程有限公司 Positioning device for temporary steel-pipe column pile
CN203569575U (en) * 2013-09-18 2014-04-30 上海岩土工程勘察设计研究院有限公司 Plastic blind ditch pipe sandless precipitation well
CN103601089A (en) * 2013-11-22 2014-02-26 山东矿业管理技术服务集团有限公司 Shaft construction air duct suspension method
CN105696611A (en) * 2014-11-25 2016-06-22 中冶天工上海十三冶建设有限公司 Foundation pit dewatering device for sand layer with high water permeability
CN204849792U (en) * 2015-05-14 2015-12-09 中国建筑第八工程局有限公司 Precipitation well well casing underpins support
CN205152969U (en) * 2015-11-19 2016-04-13 中国建筑第七工程局有限公司 A precipitation tubular well structure for foundation ditch precipitation
CN105350555A (en) * 2015-11-27 2016-02-24 上海长凯岩土工程有限公司 Fast construction method of precipitation well
US20180044907A1 (en) * 2016-08-12 2018-02-15 Wuhan Zhihe Geotechnical Engineering Co., Ltd Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
CN206266082U (en) * 2016-12-15 2017-06-20 中建筑港集团有限公司 A kind of hanging apparatus for being available for polytypic caisson to lift
CN106968263A (en) * 2017-04-25 2017-07-21 中国二十冶集团有限公司 A kind of sunk safely without sand precipitation pipe well sets construction method
CN207079569U (en) * 2017-07-26 2018-03-09 浙江省工程勘察院 A kind of side slope slopes automate dewatering device
CN107476337A (en) * 2017-08-21 2017-12-15 中铁六局集团有限公司 The prefabricated side wall assembling and construction method in open cut subway assembled station
CN207073140U (en) * 2017-08-22 2018-03-06 中国建筑第七工程局有限公司 A kind of well casing dewatering well dewatering device
CN107460885A (en) * 2017-09-22 2017-12-12 中国路桥工程有限责任公司 A kind of relief well of deep foundation pit and its construction method
CN208618415U (en) * 2018-07-26 2019-03-19 江苏兴厦建设工程集团有限公司 A kind of pervious concrete well casing mounting device for base pit dewatering

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘红;: "深井井点降水在高层建筑工程中的应用", 山西建筑, no. 27, pages 124 - 125 *
李棉巧;: "大基坑深井降水系统施工技术研究", 价值工程, no. 08, pages 97 - 100 *

Also Published As

Publication number Publication date
CN108867651B (en) 2024-07-05

Similar Documents

Publication Publication Date Title
CN210767786U (en) A self-elevating operating platform for construction in elevator shafts
CN103806654A (en) Hydraulic support system for elevator shaft mold and operating method thereof
CN109098178A (en) A kind of concrete-spouting plant
CN113833027A (en) Construction method of manhole cover
CN115492403A (en) Combined type precise positioning construction device for tower footing steel latticed column
CN204753628U (en) Guider that hangs down is transferred to contrary way of doing things steel -pipe column that can have enough to meet need
CN205224050U (en) Steel reinforcement cage is hung and is put device
CN209482359U (en) Urban road cast-in-place concrete well curb construction equipment
CN103924653B (en) A kind of frame type catch pit and construction method thereof
CN211171941U (en) Manual hole digging operation frame based on full-sleeve full-slewing drilling machine
CN211712490U (en) Pipe well pipe hoisting device
CN108867651A (en) A kind of pervious concrete well casing mounting device for base pit dewatering
CN208618415U (en) A kind of pervious concrete well casing mounting device for base pit dewatering
CN120139193A (en) A construction method for artificial bored piles on an operating line
CN204510221U (en) Rotary marine piling saddle
CN203782863U (en) Frame type draining well
CN221956719U (en) Drilling bored concrete pile integration rapid prototyping construction equipment
CN209760761U (en) A construction platform in the core tube and the construction structure of the elevator core tube
CN111749244A (en) Construction device and construction method for safe construction of underground structure
CN104878775A (en) Turnable top-down method steel pipe column verticality adjusting guide device and construction method thereof
CN217780552U (en) A door crane type lifting slag discharge device
CN207760881U (en) Piping lane internal model lift adjustment support device
CN216866017U (en) A concrete pouring device in a concrete-filled steel tube column
CN217000110U (en) Municipal administration is cleaning device for sewage well
CN212641456U (en) Construction system of vibrating rod fast-assembling shaft steel reinforcement cage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Pan Shucai

Inventor after: Zhao Weizheng

Inventor after: Wang Xuehai

Inventor after: Yu Bangyong

Inventor after: Qian Dongdong

Inventor after: Wang Guoxiang

Inventor before: Zhao Weizheng

Inventor before: Yu Bangyong

Inventor before: Pan Shucai

Inventor before: Qian Dongdong

Inventor before: Wang Xuehai

Inventor before: Wang Guoxiang

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20240607

Address after: 213164 No. 33 Gehuzhong Road, Wujin District, Changzhou City, Jiangsu Province

Applicant after: CHANGZHOU VOCATIONAL INSTITUTE OF ENGINEERING

Country or region after: China

Address before: 225600 No. 8, Wu'an East Road, Gaoyou City, Yangzhou City, Jiangsu Province

Applicant before: JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Country or region before: China

GR01 Patent grant
GR01 Patent grant