CN108800174A - The deashing device and method of novel low low-level (stack-gas) economizer - Google Patents

The deashing device and method of novel low low-level (stack-gas) economizer Download PDF

Info

Publication number
CN108800174A
CN108800174A CN201810637675.5A CN201810637675A CN108800174A CN 108800174 A CN108800174 A CN 108800174A CN 201810637675 A CN201810637675 A CN 201810637675A CN 108800174 A CN108800174 A CN 108800174A
Authority
CN
China
Prior art keywords
deashing
gas
low
branch pipe
stack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810637675.5A
Other languages
Chinese (zh)
Inventor
张锡乾
肖隽
吴冲
杨彭飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huadian Engineering Group Co Ltd
Huadian Environmental Protection Engineering and Technology Co Ltd
Original Assignee
China Huadian Engineering Group Co Ltd
Huadian Environmental Protection Engineering and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huadian Engineering Group Co Ltd, Huadian Environmental Protection Engineering and Technology Co Ltd filed Critical China Huadian Engineering Group Co Ltd
Priority to CN201810637675.5A priority Critical patent/CN108800174A/en
Publication of CN108800174A publication Critical patent/CN108800174A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J3/00Removing solid residues from passages or chambers beyond the fire, e.g. from flues by soot blowers
    • F23J3/02Cleaning furnace tubes; Cleaning flues or chimneys
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22DPREHEATING, OR ACCUMULATING PREHEATED, FEED-WATER FOR STEAM GENERATION; FEED-WATER SUPPLY FOR STEAM GENERATION; CONTROLLING WATER LEVEL FOR STEAM GENERATION; AUXILIARY DEVICES FOR PROMOTING WATER CIRCULATION WITHIN STEAM BOILERS
    • F22D1/00Feed-water heaters, i.e. economisers or like preheaters
    • F22D1/02Feed-water heaters, i.e. economisers or like preheaters with water tubes arranged in the boiler furnace, fire tubes or flue ways
    • F22D1/04Feed-water heaters, i.e. economisers or like preheaters with water tubes arranged in the boiler furnace, fire tubes or flue ways the tubes having plain outer surfaces, e.g. in vertical arrangement
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F28HEAT EXCHANGE IN GENERAL
    • F28GCLEANING OF INTERNAL OR EXTERNAL SURFACES OF HEAT-EXCHANGE OR HEAT-TRANSFER CONDUITS, e.g. WATER TUBES OR BOILERS
    • F28G1/00Non-rotary, e.g. reciprocated, appliances
    • F28G1/16Non-rotary, e.g. reciprocated, appliances using jets of fluid for removing debris
    • F28G1/166Non-rotary, e.g. reciprocated, appliances using jets of fluid for removing debris from external surfaces of heat exchange conduits
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F28HEAT EXCHANGE IN GENERAL
    • F28GCLEANING OF INTERNAL OR EXTERNAL SURFACES OF HEAT-EXCHANGE OR HEAT-TRANSFER CONDUITS, e.g. WATER TUBES OR BOILERS
    • F28G15/00Details
    • F28G15/003Control arrangements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J2700/00Ash removal, handling and treatment means; Ash and slag handling in pulverulent fuel furnaces; Ash removal means for incinerators
    • F23J2700/001Ash removal, handling and treatment means

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Incineration Of Waste (AREA)

Abstract

The present invention relates to a kind of deashing devices and method of novel low low-level (stack-gas) economizer, belong to the industrial flue gas cleanings such as coal-fired power station boiler, Industrial Boiler and waste heat recovery field.Deashing device includes deashing main pipe, ash cleaning jet nozzle, deashing branch pipe, branch pipe valve and main pipe valve, one end of several deashing branch pipes is connected with deashing main pipe, main pipe valve is provided in deashing main pipe, several opening up ash cleaning jet nozzles are additionally provided on each deashing branch pipe, branch pipe valve is both provided on each deashing branch pipe.The system adjusts the flow-disturbing of flue gas by way of opening and closing branch pipe valve and main pipe valve, so that flue gas is in the state to suspend by air quantity and wind pressure, dust will not fall on flue bottom plate, improve the uniformity of low low-level (stack-gas) economizer section flue gas duct.The ash removal method of novel low low-level (stack-gas) economizer is additionally provided, the drag losses of boiler controller system can be effectively reduced, reduces the energy loss of flue gas, enhanced heat exchange effect.

Description

The deashing device and method of novel low low-level (stack-gas) economizer
Technical field
The present invention relates to a kind of deashing devices and method of novel low low-level (stack-gas) economizer, belong to coal-fired power station boiler, industry The industrial flue gas cleanings such as boiler and waste heat recovery field.
Background technology
Heat loss due to exhaust gas proportion is larger in operation for coal-fired plant boiler, accounts for 50% or more total heat loss of boiler, Some thermal power plants operation exhaust gas temperature is usually above design value.Therefore, the exhaust gas temperature of station boiler is reduced for energy saving Emission reduction has important practical significance, and low low-level (stack-gas) economizer is widely used in this context.At present frequently with low Warm economizer carries out waste heat recovery recycling to the high-temperature flue gas of discharge, and the heat of low low-level (stack-gas) economizer recycling is currently used primarily in The following aspects:1. heating steam turbine side condensed water;2. heating desulfurization outlet tail flue gas;3. heating boiler Secondary Air.It is low Warm economizer be mostly installed at after boiler of power plant air preheater and before electric precipitator between on flue, as coal-fired plant boiler sky Heat transmission equipment in pre- device outlet, electric precipitator gas approach, its main function are:1. reducing exhaust gas temperature, recycling Flue gas heat improves boiler efficiency;2. reducing dust specific resistance and practical exhaust gas volumn, efficiency of dust collection is improved;3. reducing desulfurization to mend Water;4. reducing desulfuration absorbing tower exports dust concentration, power plant's minimum discharge is realized.Current low low-level (stack-gas) economizer is arranged in sky mostly On horizontal flue between pre- device outlet and electric precipitator entrance, according to《Thermal power plant cigarette wind pulverized coal channel designing technique rule Journey》And engineering experience, to prevent horizontal segment dust deposit in flue here, while to prevent low low-level (stack-gas) economizer heat exchanger tube serious wear;Cause This, when designing flue, the flue gas flow rate of this section of flue is designed by 9m/s or so.China's major part boiler of power plant machine at present Group operating load is relatively low, and therefore, flue gas in flue flow velocity is less than design value (9m/s), and flue gas carries flying dust reduced capability, causes This horizontal segment dust stratification is serious, directly affects economy and the safety of boiler.Up to the present, for low low-level (stack-gas) economizer system Underload dust stratification serious problems never have relatively reasonable solution.
In view of the above-mentioned problems, previous way is mainly:Ash bucket and defeated is installed in low low-level (stack-gas) economizer horizontal flue bottom Ash system;I.e. in underrun, since flue gas flow rate is relatively low, flue gas carries flying dust ability to be weakened significantly;When flue gas passes through When low low-level (stack-gas) economizer, flying dust falls into ash bucket, low to solve through ancillary equipments such as storehouse pumps by fly ash carry to designated position Dust stratification problem caused by when at warm economizer due to boiler controller system underrun.The system capital equipment has:Storehouse pump, pneumatics The compositions such as machine, air compression tank, gasification wind turbine, ash discharging system, ash bucket heater, vapour system;System is relative complex, cost compared with High and floor space is larger.
Invention content
The object of the present invention is to provide the deashing device of novel low low-level (stack-gas) economizer, which leads to It crosses and opens and closes the mode of branch pipe valve and main pipe valve to adjust the flow-disturbing of flue gas, so that flue gas is in suspension by air quantity and wind pressure State, dust will not fall on flue bottom plate, can effectively reduce low low-level (stack-gas) economizer section flue when boiler controller system underrun Dust stratification, improve the uniformity of low low-level (stack-gas) economizer section flue gas duct;The ash removal method of novel low low-level (stack-gas) economizer is additionally provided, The drag losses that boiler controller system can effectively be reduced reduce the energy loss of flue gas, enhanced heat exchange effect.
In order to solve the above technical problems, the present invention adopts the following technical scheme that:
The deashing device of novel low low-level (stack-gas) economizer, wherein heat exchanger group is provided in low low-level (stack-gas) economizer flue, it is described Heat exchanger group includes the heat exchange module of m longitudinal arrangement (i.e. the direction setting of flue cross section from top to bottom) setting, n lateral row The heat exchange module of row (i.e. flue gas circulating direction is arranged) setting, m and n are the natural number more than 1.One group of deashing device is mounted on In low low-level (stack-gas) economizer entrance flue before deduster, another group of deashing device is mounted between heat exchanger group, the deashing Device include deashing main pipe, ash cleaning jet nozzle, deashing branch pipe, branch pipe valve and main pipe valve, several deashing branch pipes One end is connected with deashing main pipe, and main pipe valve is provided in the deashing main pipe, and being additionally provided with several on each deashing branch pipe opens Mouth ash cleaning jet nozzle upward is both provided with branch pipe valve on each deashing branch pipe.The branch pipe on deashing branch pipe is opened when underload Valve and main pipe valve purge flue upwards, so that flue gas is in the state to suspend by air quantity and wind pressure, dust will not be fallen on Flue bottom plate, and then reduce dust deposit in flue.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned, the deashing device further includes control system, the branch pipe Valve and the equal signal of main pipe valve are connected to control system.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned further includes discharge outlet, and the discharge outlet is set to the bottom of flue Portion.Since flying dust has abrasion, the setting of discharge outlet that can prevent from generating ponding inside heat exchanger tube leakage rear pass, influence in pipeline The safety of boiler and economy.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned, the ash cleaning jet nozzle are sprayed using non-return nozzle or blast cap Mouth.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned, ash cleaning jet nozzle are from the horizontal by certain angle a, a 45 °~135 °.The distance between ash cleaning jet nozzle is 200mm~500mm on each deashing branch pipe.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned, the deashing branch pipe is through supporting I-steel to be supported in flue Portion, the support I-steel are welded in flue inner wall.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned, the quantity of the branch pipe valve and the quantity phase of deashing branch pipe Deng the quantity of the main pipe valve is equal with deashing main pipe.
The deashing device of novel low low-level (stack-gas) economizer above-mentioned, the blowing medium in the deashing main pipe are that power plant is primary Wind, power plant's Secondary Air or compressed air.
The ash removal method of novel low low-level (stack-gas) economizer, using the deashing device of novel low low-level (stack-gas) economizer above-mentioned, including Following methods:Control system adjusts the unlatching quantity and open frequency of branch pipe valve according to the load signal of boiler, also adjusts female The open frequency of tube valve, to boiler load is relatively low, flue gas take grey ability it is weaker when, to prevent dust stratification from needing to open branch pipe Valve and main pipe valve make the blowing medium in deashing main pipe enter flue through deashing branch pipe and ash cleaning jet nozzle and purge upwards, Flue gas is set to be in the state to suspend by air quantity and wind pressure, dust will not fall on flue bottom plate, reduce the dust load of flue, The flying dust of deposition is taken away under the action of flue gas.
The ash removal method of novel low low-level (stack-gas) economizer above-mentioned, control system changes according to boiler load adjusts deashing branch pipe It is the start-stop time of upper branch pipe valve, primary every two hours purgings when underload.
Compared with prior art, the invention has the beneficial effects that:
1, the present invention in deashing device structure and it is simple for process, improvement project amount is smaller, cost is relatively low, pass through open and close branch The mode of tube valve and main pipe valve, to adjust the flow-disturbing of flue gas, and then that improves flue gas takes grey ability, can effectively reduce pot The dust stratification of low low-level (stack-gas) economizer section flue when stove performing low-load running of machine set;
2, flue gas can be made to be in the state to suspend by air quantity and wind pressure by using the present invention, dust will not fall on flue Bottom plate, and then dust deposit in flue is reduced, avoid the harm of the unit chaser caused by dust deposit in flue;When boiler controller system is transported at full capacity When row, since the influence of dust stratification changes the flow field of original flue, after the present invention, so that former flow field is not destroyed, make The drag losses of boiler controller system greatly reduce, and improve the economy of boiler operatiopn;
3, it is provided with control system, signal connects the branch pipe valve therewith with main pipe valve, and control system can utilize The Signal Regulation of boiler load variation feedback purges start-stop time and the frequency of various valves, and then reduces the dust stratification of flue, makes The heat exchange area of low low-level (stack-gas) economizer increases, and reduces the energy loss of flue gas, enhanced heat exchange effect;
4, the ash removal method in the present invention, control system therein changes according to boiler load adjusts each valve on deashing branch pipe It is the start-stop time of door, about primary every two hours purgings when underload;When boiler load is relatively low, due to flue gas flow rate compared with Low, flue gas carries the reduced capability of flying dust, and leading to low low-level (stack-gas) economizer entrance flue, there are serious fouling phenomenons, therefore, when When underrun, to prevent dust stratification from needing Open valve, blowing medium is set through deashing branch pipe and nozzle to enter flue upward Purging is enhanced the disturbance ability of deposition flying dust, is raised again, under the action of flue gas by the perturbation action of blowing medium The flying dust of deposition is taken away;
5, the present invention and " a kind of soot cleaning system and operation method for the thermal power plant's low-level (stack-gas) economizer " phase submitted on the same day Than ash cleaning jet nozzle blows the purging that will not make causative agent and worn caused by flue bottom plate from the bottom up;It simultaneously can be by suitable Air quantity and wind pressure so that flue gas is in the state to suspend, dust will not fall on flue bottom plate, reduce the dust load of flue, reduce The quantities of civil engineering reduces project cost;Provided with a set of control system, can more adjust in real time each valve start-stop time and Frequency;Be also provided with discharge outlet, can effectively and in time be discharged due to flying dust exchange heat pipe abrasion cause heat exchanger tube to leak when The ponding of flue effectively prevents influence of the water accumulation of pipeline to boiler economics and safety.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
Fig. 2 is also the structural schematic diagram of the present invention;
Fig. 3 is the part connection relationship diagram of the present invention.
The meaning of reference numeral:1- deashing main pipes, 2- heat exchange modules, the low low-level (stack-gas) economizer entrances of 3-, 4- ash cleaning jet nozzles, 5- Deashing branch pipe, 6- support I-steel, 7- branch pipe valves, 8- main pipe valves, 9- discharge outlet, 10- control systems.
The present invention is further illustrated with reference to the accompanying drawings and detailed description.
Specific implementation mode
The embodiment of the present invention 1:As shown in Figure 1-Figure 3, the deashing device of novel low low-level (stack-gas) economizer, wherein low temperature saves Heat exchanger group is provided in coal device flue, the heat exchanger group includes m longitudinal arrangement (the i.e. direction of flue cross section from top to bottom It is arranged) heat exchange module 2 that heat exchange module 2, the n transversely arranged (i.e. flue gas circulating direction is arranged) of setting are arranged, m and n are Natural number more than 1.For one group of deashing device in 3 sections of flues of low low-level (stack-gas) economizer entrance before deduster, another group clear Apparatus for ash is mounted between heat exchanger group, and the deashing device includes deashing main pipe 1, ash cleaning jet nozzle 4, deashing branch pipe 5, branch pipe One end of valve 7 and main pipe valve 8, several deashing branch pipes 5 is connected with deashing main pipe 1, is arranged in the deashing main pipe 1 There is main pipe valve 8, be additionally provided with several opening up ash cleaning jet nozzles 4 on each deashing branch pipe 5, on each deashing branch pipe 5 It is provided with branch pipe valve 7.The branch pipe valve 7 and main pipe valve 8 opened when underload on deashing branch pipe are upward to being carried out in flue Purging makes flue gas be in the state to suspend by air quantity and wind pressure, and dust will not fall on flue bottom plate, and then reduce flue product Ash.The deashing device further includes control system 10, and the branch pipe valve 7 and 8 equal signal of main pipe valve are connected to control system 10。
Embodiment 2:As shown in Figure 1-Figure 3, the deashing device of novel low low-level (stack-gas) economizer, wherein low low-level (stack-gas) economizer flue It is inside provided with heat exchanger group, the heat exchanger group includes that m longitudinal arrangement (i.e. the direction setting of flue cross section from top to bottom) is set The heat exchange module 2 for a transversely arranged (the i.e. flue gas circulating direction is arranged) setting of heat exchange module 2, n set, m and n are more than 1 Natural number, specifically, m is 4, n 2.One group of deashing device is mounted on 3 sections of flues of low low-level (stack-gas) economizer entrance before deduster Interior, another group of deashing device is mounted between heat exchanger group, and the deashing device includes deashing main pipe 1, ash cleaning jet nozzle 4, clear One end of grey branch pipe 5, branch pipe valve 7 and main pipe valve 8, several deashing branch pipes 5 is connected with deashing main pipe 1, described clear It is provided with main pipe valve 8 in grey main pipe 1, several opening up ash cleaning jet nozzles 4 are additionally provided on each deashing branch pipe 5, each Branch pipe valve 7 is both provided on deashing branch pipe 5.Branch pipe valve 7 and main pipe valve 8 when underload on unlatching deashing branch pipe is to cigarette It is purged upwards in road, so that flue gas is in the state to suspend by air quantity and wind pressure, dust will not fall on flue bottom plate, in turn Reduce dust deposit in flue.The deashing device further includes control system 10, and the branch pipe valve 7 is connected with 8 equal signal of main pipe valve In control system 10.
Further, the deashing device further includes discharge outlet 9, and the discharge outlet 9 is set to the bottom of flue.Due to flying dust There are abrasion, the setting of discharge outlet 9 that can prevent from generating ponding inside heat exchanger tube leakage rear pass in pipeline, influences the safety of boiler Property and economy.The ash cleaning jet nozzle 4 uses non-return nozzle or blast cap nozzle.Ash cleaning jet nozzle 4 is from the horizontal by certain Angle a, a are 45 °~135 °.The distance between ash cleaning jet nozzle 4 is 200mm~500mm on each deashing branch pipe 5.The deashing Through supporting I-steel 6 to be supported in inside flue, the support I-steel 6 is welded in flue inner wall branch pipe 5.The branch pipe valve 7 quantity is equal with the quantity of deashing branch pipe 5, and the quantity of the main pipe valve 8 is equal with deashing main pipe 1.The deashing main pipe 1 In blowing medium be power plant's First air, power plant's Secondary Air or compressed air.
Embodiment 3:As Figure 1-Figure 2, the ash removal method of novel low low-level (stack-gas) economizer, using novel low temperature above-mentioned The deashing device of economizer, including following methods:Control system 10 adjusts the unlatching of branch pipe valve 7 according to the load signal of boiler Quantity and open frequency also adjust the open frequency of main pipe valve 8, to that boiler load is relatively low, flue gas takes grey ability is weaker When, to prevent dust stratification from needing to open branch pipe valve 7 and main pipe valve 8, make the blowing medium in deashing main pipe 1 through deashing branch pipe 5 Flue is entered with ash cleaning jet nozzle 4 to purge upwards, so that flue gas is in the state to suspend by air quantity and wind pressure, dust will not be fallen on Flue bottom plate reduces the dust load of flue, takes away the flying dust of deposition under the action of flue gas.Control system 10 is according to boiler Load variations adjust the start-stop time of branch pipe valve 7 on deashing branch pipe 5, and when underload is primary every two hours purgings.
Embodiment 4:As Figure 1-Figure 2, the deashing device of novel low low-level (stack-gas) economizer, wherein low low-level (stack-gas) economizer flue It is inside provided with heat exchanger group, the heat exchanger group includes that m longitudinal arrangement (i.e. the direction setting of flue cross section from top to bottom) is set The heat exchange module 2 for a transversely arranged (the i.e. flue gas circulating direction is arranged) setting of heat exchange module 2, n set, m and n are more than 1 Natural number.One group of deashing device is in 3 sections of flues of low low-level (stack-gas) economizer entrance before deduster, another group of deashing device peace Between heat exchanger group, the deashing device includes deashing main pipe 1, ash cleaning jet nozzle 4, deashing branch pipe 5,7 and of branch pipe valve One end of main pipe valve 8, several deashing branch pipes 5 is connected with deashing main pipe 1, and main pipe is provided in the deashing main pipe 1 Valve 8 is additionally provided with several opening up ash cleaning jet nozzles 4 on each deashing branch pipe 5, is both provided on each deashing branch pipe 5 Branch pipe valve 7.The branch pipe valve 7 and main pipe valve 8 on deashing branch pipe are opened when underload to being purged upwards in flue, are led to Crossing air quantity and wind pressure makes flue gas be in the state to suspend, and dust will not fall on flue bottom plate, and then reduce dust deposit in flue.It is described clear Grey nozzle 4 uses non-return nozzle or blast cap nozzle.
A kind of operation principle of embodiment in the present invention:Fig. 1-Fig. 3 indicates the deashing device of the low low-level (stack-gas) economizer of the present invention Mounting structure schematic diagram when for existing low low-level (stack-gas) economizer system.Low low-level (stack-gas) economizer is by m × n heat exchange module 2 in product Die model formula forms.After high-temperature flue gas as shown in Figure 1 leaves air preheater, enter horizontal flue by 90 ° of elbows of flue.Control System 10 processed opens the branch pipe valve 7 on deashing branch pipe 5 in underload by ash cleaning jet nozzle 4 to being blown upwards in flue It sweeps, ash cleaning jet nozzle 4 blows the purging that will not make causative agent and worn caused by flue bottom plate from the bottom up, while by suitable Air quantity and wind pressure make flue gas be in the state to suspend, and dust will not fall on flue bottom plate, reduce the dust load of flue, reduce soil The quantities built.Apparatus of the present invention can effectively reduce the product of low low-level (stack-gas) economizer section flue when boiler controller system underrun Ash improves the uniformity of low low-level (stack-gas) economizer section flue gas duct.The present invention also provides a kind of ash removal method, this method can be effective The drag losses for reducing boiler controller system, reduce the energy loss of flue gas, enhanced heat exchange effect.

Claims (10)

1. the deashing device of novel low low-level (stack-gas) economizer, wherein heat exchanger group is provided in low low-level (stack-gas) economizer flue, it is described to change Hot device group includes the heat exchange module (2) for a transversely arranged setting of heat exchange module (2), n that m longitudinal arrangement is arranged, and m and n are Natural number more than 1, which is characterized in that one group of deashing device is mounted on low low-level (stack-gas) economizer entrance (3) the section cigarette before deduster In road, another group of deashing device is mounted between heat exchanger group, and the deashing device includes deashing main pipe (1), ash cleaning jet nozzle (4), one end of deashing branch pipe (5), branch pipe valve (7) and main pipe valve (8), several deashing branch pipes (5) is connected with clearly Grey main pipe (1) is provided with main pipe valve (8) on the deashing main pipe (1), and being additionally provided with several on each deashing branch pipe (5) opens Mouth ash cleaning jet nozzle (4) upward is both provided with branch pipe valve (7) on each deashing branch pipe (5).
2. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that the deashing device is also Including control system (10), the branch pipe valve (7) and main pipe valve (8) signal are connected to control system (10).
3. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that further include discharge outlet (9), the discharge outlet (9) is set to the bottom of flue.
4. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that the ash cleaning jet nozzle (4) non-return nozzle or blast cap nozzle are used.
5. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that ash cleaning jet nozzle (4) with Horizontal direction has a certain degree a, and a is 45 °~135 °;The distance between ash cleaning jet nozzle (4) is on each deashing branch pipe (5) 200mm~500mm.
6. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that the deashing branch pipe (5) through supporting I-steel (6) to be supported in inside flue, the support I-steel (6) is welded in flue inner wall.
7. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that the branch pipe valve (7) quantity is equal with the quantity of deashing branch pipe (5), and the quantity of the main pipe valve (8) is equal with deashing main pipe (1).
8. the deashing device of novel low low-level (stack-gas) economizer according to claim 1, which is characterized in that the deashing main pipe (1) blowing medium in is power plant's First air, power plant's Secondary Air or compressed air.
9. the ash removal method of novel low low-level (stack-gas) economizer, using any novel low low-level (stack-gas) economizers of claim 1-8 Deashing device, which is characterized in that including following methods:Control system (10) adjusts branch pipe valve according to the load signal of boiler (7) unlatching quantity and open frequency also adjust the open frequency of main pipe valve (8), to boiler load is relatively low, flue gas is taken When grey ability is weaker, to prevent dust stratification from needing to open branch pipe valve (7) and main pipe valve (8), make the purging in deashing main pipe (1) Medium is entered in flue and is purged upwards through deashing branch pipe (5) and ash cleaning jet nozzle (4), so that flue gas is in outstanding by air quantity and wind pressure Floating state, dust will not fall on flue bottom plate, reduce the dust load of flue, by the flying dust band of deposition under the action of flue gas It walks.
10. the ash removal method of novel low low-level (stack-gas) economizer according to claim 8, which is characterized in that control system (10) Changed according to boiler load the start-stop time for adjusting branch pipe valve (7) on deashing branch pipe (5), when underload every two hours to Upper purging is primary.
CN201810637675.5A 2018-06-20 2018-06-20 The deashing device and method of novel low low-level (stack-gas) economizer Pending CN108800174A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810637675.5A CN108800174A (en) 2018-06-20 2018-06-20 The deashing device and method of novel low low-level (stack-gas) economizer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810637675.5A CN108800174A (en) 2018-06-20 2018-06-20 The deashing device and method of novel low low-level (stack-gas) economizer

Publications (1)

Publication Number Publication Date
CN108800174A true CN108800174A (en) 2018-11-13

Family

ID=64083894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810637675.5A Pending CN108800174A (en) 2018-06-20 2018-06-20 The deashing device and method of novel low low-level (stack-gas) economizer

Country Status (1)

Country Link
CN (1) CN108800174A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109442377A (en) * 2018-12-13 2019-03-08 中国华能集团清洁能源技术研究院有限公司 A kind of low low-level (stack-gas) economizer system and application method of efficient anti-gray
CN110173706A (en) * 2019-06-17 2019-08-27 中国华电科工集团有限公司 Deashing device and operation method for coal steam-electric plant smoke afterheat utilizing system
CN110743301A (en) * 2019-10-18 2020-02-04 华电电力科学研究院有限公司 Coal-fired power plant electric bag dust removal system and method
CN112856787A (en) * 2021-03-03 2021-05-28 北京瀚江新材料科技有限公司 Environment-friendly air conditioner tuber pipe accuse wind valve part
CN113086652A (en) * 2021-04-21 2021-07-09 西安热工研究院有限公司 Prevent stifled grey system suitable for coal fired power plant malleation dense phase pneumatic conveying ash system storehouse pump

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202590629U (en) * 2011-12-21 2012-12-12 浙江蓝天求是环保集团有限公司 Selective catalytic reduction (SCR) inlet flue soot blower
CN205227269U (en) * 2015-11-20 2016-05-11 西安华江环保科技股份有限公司 Take dry coke quenching boiler of soot blower
CN206582827U (en) * 2017-03-01 2017-10-24 许昌天健热电有限公司 A kind of anti-blocking grey economizer
CN107525088A (en) * 2017-10-18 2017-12-29 中国华电科工集团有限公司 A kind of deashing device and operation method for the low low-level (stack-gas) economizer of thermal power plant
CN207035169U (en) * 2017-06-01 2018-02-23 华电电力科学研究院 Improve the soot blower of SCR inlet flow field uniformity
CN208536019U (en) * 2018-06-20 2019-02-22 中国华电科工集团有限公司 The deashing device of novel low low-level (stack-gas) economizer

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202590629U (en) * 2011-12-21 2012-12-12 浙江蓝天求是环保集团有限公司 Selective catalytic reduction (SCR) inlet flue soot blower
CN205227269U (en) * 2015-11-20 2016-05-11 西安华江环保科技股份有限公司 Take dry coke quenching boiler of soot blower
CN206582827U (en) * 2017-03-01 2017-10-24 许昌天健热电有限公司 A kind of anti-blocking grey economizer
CN207035169U (en) * 2017-06-01 2018-02-23 华电电力科学研究院 Improve the soot blower of SCR inlet flow field uniformity
CN107525088A (en) * 2017-10-18 2017-12-29 中国华电科工集团有限公司 A kind of deashing device and operation method for the low low-level (stack-gas) economizer of thermal power plant
CN208536019U (en) * 2018-06-20 2019-02-22 中国华电科工集团有限公司 The deashing device of novel low low-level (stack-gas) economizer

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109442377A (en) * 2018-12-13 2019-03-08 中国华能集团清洁能源技术研究院有限公司 A kind of low low-level (stack-gas) economizer system and application method of efficient anti-gray
CN110173706A (en) * 2019-06-17 2019-08-27 中国华电科工集团有限公司 Deashing device and operation method for coal steam-electric plant smoke afterheat utilizing system
CN110743301A (en) * 2019-10-18 2020-02-04 华电电力科学研究院有限公司 Coal-fired power plant electric bag dust removal system and method
CN112856787A (en) * 2021-03-03 2021-05-28 北京瀚江新材料科技有限公司 Environment-friendly air conditioner tuber pipe accuse wind valve part
CN113086652A (en) * 2021-04-21 2021-07-09 西安热工研究院有限公司 Prevent stifled grey system suitable for coal fired power plant malleation dense phase pneumatic conveying ash system storehouse pump

Similar Documents

Publication Publication Date Title
CN108800174A (en) The deashing device and method of novel low low-level (stack-gas) economizer
CN105972632B (en) Air preheater hot wind adverse current in coal-burning power plant is anti-blocking and the system and its technique of corrosion
CN106197045B (en) Afterheat boiler system, rotary hearth furnace high-temperature dust-containing flue gas processing system and method
CN107883388A (en) A kind of soot blower system and ash-blowing method for π type boiler furnace arch, furnace noses
CN107525088A (en) A kind of deashing device and operation method for the low low-level (stack-gas) economizer of thermal power plant
CN208536019U (en) The deashing device of novel low low-level (stack-gas) economizer
CN101672479B (en) Sweeping device for dust deposit in flue
CN204513372U (en) Coal feeder for circular fluidized bed boiler
CN208536020U (en) A kind of soot cleaning system for thermal power plant's low-level (stack-gas) economizer
CN209193888U (en) A kind of deashing device of coke dry quenching boiler bottom
CN207907273U (en) It is a kind of prevent coal-burning boiler denitration be transformed after tail portion dust deposit in flue device
CN207584795U (en) A kind of deashing device for the low low-level (stack-gas) economizer of thermal power plant
CN108679636A (en) A kind of soot cleaning system and operation method for thermal power plant's low-level (stack-gas) economizer
CN205919305U (en) High cloud of dust gas disposal of smoke treatment device and rotary hearth furnace high temperature and waste heat utilization system
CN204513422U (en) Steam blast cap soot blower system
CN210373503U (en) Ash removal device for flue gas waste heat utilization system of thermal power plant
CN202350556U (en) Air-draft system for generating power by utilizing air-exhausted smoke waste heat of cement kiln bypass
CN102401573B (en) Air intake system for generating power by using cement kiln bypass flue gas waste heat
CN214551913U (en) Flue gas tar trapping device
CN109092059A (en) A kind of denitration of glass furnace fume ammonia-spraying grid online ash removal device and its ash removal method
CN213746815U (en) Smoke bypass arrangement system for preventing dust deposition and jamming
CN106195968A (en) Flue gas processing device and rotary hearth furnace high-temperature high dust smoke processing system
CN104399321B (en) Shell and tube air cooler and closed submerged kiln gas purification method ash removal method interior with pipe
CN113339780A (en) Operation optimization method of 660MW unit smoke cooler
CN203533582U (en) Fly ash separating and conveying system for coal economizer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181113