CN108708541A - A kind of suspension platform and its construction method for skybridge construction - Google Patents

A kind of suspension platform and its construction method for skybridge construction Download PDF

Info

Publication number
CN108708541A
CN108708541A CN201810646099.0A CN201810646099A CN108708541A CN 108708541 A CN108708541 A CN 108708541A CN 201810646099 A CN201810646099 A CN 201810646099A CN 108708541 A CN108708541 A CN 108708541A
Authority
CN
China
Prior art keywords
vestibule
hanger
construction
layer
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810646099.0A
Other languages
Chinese (zh)
Other versions
CN108708541B (en
Inventor
吴昊
张锐
潘孝金
吴航
吴庆超
时伟敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huashi Enterprises Co Ltd
Original Assignee
China Huashi Enterprises Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huashi Enterprises Co Ltd filed Critical China Huashi Enterprises Co Ltd
Priority to CN201810646099.0A priority Critical patent/CN108708541B/en
Publication of CN108708541A publication Critical patent/CN108708541A/en
Application granted granted Critical
Publication of CN108708541B publication Critical patent/CN108708541B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • E04G3/243Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the outside contour of a building

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of suspension platforms and its construction method for skybridge construction, belong to construction engineering technical field, the suspension platform for being used for skybridge construction includes suspension scaffold and hanger, the suspension scaffold is set to the both sides of vestibule, the hanger is set to the bottom of the vestibule, the hanger includes transverse horizontal layer, vertical equity layer and be connected to the vestibule bottom sunpender group, the transverse horizontal layer and the vertical equity layer are both provided with multilayer, and the transverse horizontal layer is arranged alternately with the vertical equity layer, adjacent transverse horizontal layer segment overlapping, the sunpender group is sequentially connected to transverse horizontal layer described in multilayer.When the outside to vestibule is decorated, operation platform structure and construction method provided by the invention can effectively ensure the personal safety of operating personnel, and easy for construction, be effectively guaranteed operating efficiency.

Description

A kind of suspension platform and its construction method for skybridge construction
Technical field
The present invention relates to construction engineering technical field more particularly to it is a kind of for skybridge construction suspension platform and its Construction method.
Background technology
Skybridge, due to uniqueness and the diversity functionally of its appearance, is got in recent years for being connected to two high buildings It is applied in skyscraper come more.According to design feature, Steel corridor main structural framework mostly uses whole promoted and applies Work.After promotion, steel vestibule extraneous adornment becomes a technology difficulty because of its height, the limitation in space, the selection of construction operation platform Topic.On the one hand the personal safety of guarantee operating personnel is not only needed, but also needs to avoid operating platform that from cannot interfering applying for operating personnel Work.In addition, in actual work progress, if building for operating platform can be easy for construction, it can effectively ensure operating efficiency.
Invention content
It is an object of the invention to propose a kind of suspension platform and its construction method for skybridge construction, to even When the outside of corridor is decorated, it can effectively ensure the personal safety of operating personnel, and easy for construction, be effectively guaranteed work Industry efficiency.
For this purpose, the present invention uses following technical scheme:
A kind of suspension platform for skybridge construction, including suspension scaffold and hanger, the suspension scaffold are set to vestibule Both sides, the hanger is set to the bottom of the vestibule, and the hanger includes transverse horizontal layer, vertical equity layer and is connected to The sunpender group of the bottom of the vestibule, the transverse horizontal layer and the vertical equity layer are both provided with multilayer, and the transverse direction Level course is arranged alternately with the vertical equity layer, and adjacent transverse horizontal layer segment overlapping, the sunpender group is sequentially connected to Transverse horizontal layer described in multilayer.
As optimal technical scheme, the hanger includes the first hanger and the second hanger, and first hanger is set to institute The underface of vestibule is stated, second hanger is set to the both sides of first hanger and the underface positioned at the suspension scaffold.
Further include multiple supporting racks, support frame as described above is distributed in the both sides of the vestibule, described as optimal technical scheme Second hanger is connected to support frame as described above and the lower section positioned at support frame as described above, and the suspension scaffold is connected to support frame as described above and position In the top of support frame as described above.
As optimal technical scheme, support frame as described above includes horizontally-supported and is connected to the horizontally-supported oblique branch Support, the skewed horizontal load relative to it is described it is horizontally-supported be arranged diagonally downward, the described horizontally-supported and described skewed horizontal load is divided equally It is not connected to the steel construction of vestibule;Second hanger and the suspension scaffold are all connected to described horizontally-supported.
As optimal technical scheme, the transverse horizontal layer includes more horizontal rods, and the horizontal rod is along horizontal Extend to direction, the sunpender group includes multiple row sunpender, each horizontal rod and several sunpenders in each column sunpender Connection.
As optimal technical scheme, the both ends of the sunpender are both provided with anti-skid fastener.
As optimal technical scheme, the vertical equity layer includes more longitudinal horizontal rods, and the longitudinal horizontal rod is along vertical Extend to direction, the longitudinal horizontal rod is connected to the horizontal rod.
As optimal technical scheme, template is equipped between the transverse horizontal layer and the vertical equity layer.
As optimal technical scheme, the suspension scaffold includes two row vertical bars and multilayer link, and the link includes Two transverse bars and the more longitudinal rods being connected between two transverse bars, it is vertical that every transverse bar is sequentially connected to each column Bar, the vertical bar are connected to support frame as described above.
The present invention also provides a kind of construction methods of the suspension platform for skybridge construction, include the following steps:
Suspension scaffold is set up in the both sides of vestibule;
Vestibule and suspension scaffold are overall increased into the first mounting distance, and hanger is set up in the bottom of vestibule;
Vestibule, suspension scaffold and hanger are overall increased into the second mounting distance, vestibule is made to be docked simultaneously with the high building of its both sides It is fixed, meanwhile, suspension scaffold docks fixation with outrigger;
The both sides of vestibule are decorated on suspension scaffold, after decoration, both sides suspension scaffold is removed after the completion of the decoration of both sides;
Remove sunpender group by column and successively remove transverse horizontal layer and vertical equity layer, meanwhile, the bottom of vestibule by column It is laid with decorative panel.
Beneficial effects of the present invention:
The present invention on corridor construction suspension platform by being arranged suspension scaffold and hanger, to realize both sides and bottom to vestibule Portion is decorated.Transverse horizontal layer and vertical equity layer are replaced, and lateral water described in multilayer is sequentially connected to by sunpender group Flat bed sets up hanger to realize.Further, since the decoration board size of decoration vestibule bottom is larger, the present invention will be adjacent Transverse horizontal layer gradual laying is carried out using partly overlapping mode, keep hanger domed, when operating personnel is in vestibule When bottom is decorated, the bottom of vestibule can be decorated by way of decorative panel is installed when removing hanger, to A kind of new operation platform structure is provided for the construction of the appearance of vestibule.
Description of the drawings
Fig. 1 is the side view for the suspension platform constructed provided by the present invention for skybridge;
Fig. 2 is the front view for the suspension platform constructed provided by the present invention for skybridge;
Fig. 3 is the partial schematic diagram of the hanger for the suspension platform constructed provided by the present invention for skybridge;
Fig. 4 is the exploded view of supporting rack provided by the invention and vestibule steel construction;
Fig. 5 is the schematic diagram that suspension scaffold provided by the invention is installed on supporting rack;
Fig. 6 is the schematic diagram of the work progress for the suspension platform constructed provided by the present invention for skybridge.
In figure:
10, vestibule;20, high building;30, steel construction;40, outrigger;
1, suspension scaffold;11, vertical bar;12, link;121, transverse bar;122, longitudinal rod;
2, hanger;201, the first hanger;202, the second hanger;
21, transverse horizontal layer;211, horizontal rod;22, vertical equity layer;221, longitudinal horizontal rod;23, sunpender group; 231, sunpender;24, template;
3, supporting rack;31, horizontally-supported;32, skewed horizontal load;
4, anti-skid fastener;
5, support is thrown.
Specific implementation mode
In order to make those skilled in the art more fully understand technical scheme of the present invention, below in conjunction with the accompanying drawings and by specific Embodiment is come the technical solution that further illustrates the present invention.
A kind of suspension platform for skybridge construction is present embodiments provided, as shown in Figure 1-Figure 3, this is used for high-altitude The suspension platform of corridor construction includes suspension scaffold 1 and hanger 2, and the suspension scaffold 1 is set to the both sides of vestibule 10, the hanger 2 It is set to the bottom of the vestibule 10, the hanger 2 is including transverse horizontal layer 21, vertical equity layer 22 and is connected to the vestibule The sunpender group 23 of 10 bottom, the transverse horizontal layer 21 and the vertical equity layer 22 are both provided with multilayer, and the transverse direction Level course 21 is arranged alternately with the vertical equity layer 22, and adjacent transverse horizontal layer 21 partly overlaps, the sunpender group 23 according to It is secondary to be connected to transverse horizontal layer 21 described in multilayer.Preferably, the sunpender group 23 is sequentially connected to transverse horizontal described in multilayer Layer 21 makes the hanger 2 form domes.Wherein, it laterally refers to the X-direction in figure, longitudinally refers to the Z-direction in figure, It is wherein laterally and longitudinally vertical.
The present embodiment on corridor construction suspension platform by being arranged suspension scaffold 1 and hanger 2, to realize to the two of vestibule 10 Side and bottom are decorated.The present embodiment replaces transverse horizontal layer 21 and vertical equity layer 22, and successively by sunpender group 23 It is connected to transverse horizontal layer 21 described in multilayer, to realize setting up to hanger 2.Further, since the dress of 10 bottom of decoration vestibule Plaque size is larger, and adjacent transverse horizontal layer 21 is carried out gradual laying by the present embodiment using partly overlapping mode, is made Hanger 2 is domed, can be by installing decoration when removing hanger 2 when operating personnel is when the bottom of vestibule 10 is decorated The mode of plate decorates the bottom of vestibule 10, to which the construction of the appearance for vestibule 10 provides a kind of new operation platform Structure.
Above-mentioned hanger 2 includes the first hanger 201 and the second hanger 202, and first hanger 201 is set to the vestibule 10 Underface, second hanger 202 be set to the both sides of first hanger 201 and positioned at the suspension scaffold 1 underface. The present embodiment in the underface of suspension scaffold 1 by being arranged the second hanger 202, when operating personnel constructs on suspension scaffold 1, if applying It after work tool is accidentally fallen, can fall on the second hanger 202, on the one hand ensure that 10 lower section personnel safety of vestibule, separately On the one hand so that operating personnel conveniently fetches construction tool.
As shown in figure 3, the transverse horizontal layer 21 includes more horizontal rods 211, the horizontal rod 211 is along cross Extend to direction, the sunpender group 23 includes multiple row sunpender 231, in each horizontal rod 211 and each column sunpender 231 Several sunpenders 231 connect.Preferably, each horizontal rod 211 is connect with four sunpenders 231 in each column sunpender 231, So that when operating personnel is when decorative panel is installed in the bottom of vestibule 10, after removing a sunpender 231, also three sunpenders 231 connect Connect transverse horizontal layer 21.Due to having overlapping region between adjacent transverse horizontal layer 21 so that adjacent 21 energy of transverse horizontal layer Enough public several sunpenders 231, to ensure that the safety of hanger 2 dismounts.
The both ends of above-mentioned sunpender 231 are both provided with anti-skid fastener 4, and the present embodiment is anti-by being arranged at the both ends of sunpender 231 On the one hand slide fastener part 4 is fastened and is positioned to transverse horizontal layer 21 and vertical equity layer 22, transverse horizontal layer is effectively prevented 21 and vertical equity layer 22 along sunpender 231 glide;On the other hand sunpender 231 is effectively fixed in the bottom of vestibule 10 Portion.Wherein, the bottom of vestibule 10 is welded with hanging ring, and the upper end of sunpender 231 is connect with hanging ring.
The vertical equity layer 22 includes more longitudinal horizontal rods 221, and the longitudinal horizontal rod 221 is prolonged along the longitudinal direction It stretches, the longitudinal horizontal rod 221 is connected to the horizontal rod 211.Specifically, every layer of transverse horizontal layer 21 is connected with more Longitudinal horizontal rod 221, the more longitudinal horizontal rods 221 are sequentially connected to more horizontal rods of every layer of transverse horizontal layer 21 211。
It is equipped with template 24 between above-mentioned transverse horizontal layer 21 and the vertical equity layer 22, by the way that template 24 is arranged, is made The suspension platform that must construct is more steady, convenient working personnel construction.
As shown in Fig. 2, Fig. 4 and Fig. 5, which further includes multiple supporting racks 3, described Supporting rack 3 is distributed in the both sides of the vestibule 10, and second hanger 202 is connected to support frame as described above 3 and is located at the support The lower section of frame 3, the suspension scaffold 1 are connected to support frame as described above 3 and the top positioned at support frame as described above 3.Specifically, the support Frame 3 includes horizontally-supported 31 and is connected to horizontally-supported 31 skewed horizontal load 32, and the skewed horizontal load 32 is relative to described Horizontally-supported 31 are arranged diagonally downward, described horizontally-supported 31 and the skewed horizontal load 32 be respectively connected to the steel knot of vestibule 10 Structure 30.Second hanger 202 and the suspension scaffold 1 are all connected to described horizontally-supported 31.
Above-mentioned suspension scaffold 1 includes two row vertical bars 11 and multilayer link 12, and the link 12 includes two transverse bars 121 and the more longitudinal rods 122 being connected between two transverse bars 121, every transverse bar 121 be sequentially connected to respectively often Row vertical bar 11, the vertical bar 11 are connected to support frame as described above 3.
In addition, in the present embodiment, suspension scaffold 1 is wrapped with safety net, and the both sides of hanger 2 are set to skirting board, to right The side of vestibule 10 carries out facade protection and foot guard, it is ensured that completely enclosed.
Connection in the present embodiment between rod piece is attached by fastener, and the structure of the present embodiment contacting piece does not limit It is fixed.
The present embodiment additionally provides a kind of construction method of the suspension platform for skybridge construction, and the construction method is excellent Choosing is implemented using above-mentioned suspension platform.The construction method includes the following steps:
Step 1:Preparation of construction.In this step, outrigger 40 is set up in the side of two high buildings 20.
Step 2:Suspension scaffold 1 is set up in the both sides of vestibule 10.It should be noted that between step 1 and step 2, need Will on installation on ground moulding bed assembled vestibule 10, after the completion of 10 assembly of vestibule, suspension scaffold 1 is set up in the both sides of vestibule 10.This reality Example is applied by carrying out assembly to vestibule 10 on installation on ground moulding bed, is effectively guaranteed the levelness of platform for lining, Jin Eryou It ensure that effect the assembled quality of vestibule 10.
Specifically, multilayer link 12 is installed in two row vertical bars 11, to complete the installation of suspension scaffold 1, suspension scaffold 1 After installation is complete, montant is connect with horizontally-supported 31.Finally, suspension scaffold 1 is connect with vestibule 10, with ensure suspension scaffold 1 with The stability that vestibule 10 connects.It should be noted that throwing support 5 can also be installed between suspension scaffold 1 and bearing diagonal, further to protect Demonstrate,prove the stability that suspension scaffold 1 is installed.It should be noted that as shown in Figure 4 and Figure 5, before montant is connect with horizontally-supported 31, needing To do upright bar telltale mark on horizontally-supported 31, when montant being made to be connect with horizontally-supported 31, facilitate positioning, wherein Fig. 4 be The schematic diagram after upright bar telltale mark is made on horizontally-supported 31, Fig. 5 is that suspension scaffold 1 is installed on the schematic diagram after horizontally-supported 31.
Process when being fitted into one layer of link 12 in two row vertical bars 11 is:First two transverse bars 121 it Between connect more longitudinal rods 122, to complete installation to link 12, secondly, by two horizontal rods 211 respectively with two Row vertical bar 11 is connected and fixed.
Step 3:Vestibule 10 and suspension scaffold 1 are promoted to the first mounting distance, and hanger 2 is set up in the bottom of vestibule 10. Preferably, the first mounting distance is 2.5m, the first mounting distance of the present embodiment pair is not construed as limiting, can be according to practice of construction need It asks and is adjusted.The present embodiment promotes vestibule 10 and suspension scaffold 1 by the hydraulic lifting apparatus on high building 20, can also use it He promotes vestibule 10 and suspension scaffold 1 mode, is not construed as limiting to this.
The present embodiment includes the following steps when hanger 2 is set up in the bottom of vestibule 10:First, sunpender 231 is fixed on company Then the bottom of corridor 10 is successively laid with transverse horizontal layer 21 and vertical equity layer 22, makes 2 domed structure of hanger.Thus with even The bottom structure of corridor 10 is adapted, to facilitate the bottom to vestibule 10 to decorate.
Step 4:Vestibule 10, suspension scaffold 1 and hanger 2 are overall increased into the second mounting distance, make vestibule 10 and its both sides High building 20 be butted against and fixed, meanwhile, suspension scaffold 1 docks fixation with outrigger 40.After suspension scaffold 1 docks fixed with outrigger 40, Suspension scaffold 1 is connected to outrigger 40, and operating personnel can enter suspension scaffold 1 by outrigger 40.Preferably, the second mounting distance is 42m, the second mounting distance of the present embodiment pair are not construed as limiting, and are determined according to the design of vestibule.
Step 5:Make high-altitude protection.Suspension scaffold 1 is wrapped with safety net, and the both sides of hanger 2 are set to skirting board, to Facade protection and foot guard are carried out to the side of vestibule 10, it is ensured that it is completely enclosed, to ensure the personal safety of operating personnel.
Step 6:The both sides of vestibule 10 are decorated on suspension scaffold 1, after decoration, two are removed after the completion of the decoration of both sides Side suspension scaffold.After the completion of the decoration of the both sides of vestibule 10, link 12 is successively removed.As shown in fig. 6, Fig. 6 is the two of vestibule 10 After the completion of the decoration of side, the structural schematic diagram after suspension scaffold 1 is removed.
Step 7:Sunpender group 23 is removed by column and successively removes transverse horizontal layer 21 and vertical equity layer 22, meanwhile, even The bottom of corridor 10 is laid with decorative panel by column.When installing decorative panel to the bottom of vestibule 10, due to the limitation of the size of decorative panel, It,, will be positioned at the installation of decorative panel when decorative panel is installed in the present embodiment if the installation of decorative panel can be interfered by not removing sunpender 231 The sunpender 231 and transverse horizontal layer 21 and vertical equity layer 22 in region carry out gradual dismounting, after installation is complete for decorative panel, hang Frame 2 is also removed and is finished, and construction is convenient.
Note that the above shows and describes the basic principles and main features of the present invention and the advantages of the present invention.The industry Technical staff it should be appreciated that the present invention is not limited to the embodiments described above, described in the above embodiment and specification Merely illustrate the principles of the invention, without departing from the spirit and scope of the present invention, the present invention also have various change and It improves, these changes and improvements all fall within the protetion scope of the claimed invention, and claimed range of the invention is by appended Claims and its equivalent thereof.

Claims (10)

1. a kind of suspension platform for skybridge construction, which is characterized in that described outstanding including suspension scaffold (1) and hanger (2) Builder's jack (1) is set to the both sides of vestibule (10), and the hanger (2) is set to the bottom of the vestibule (10), hanger (2) packet Include transverse horizontal layer (21), vertical equity layer (22) and be connected to the vestibule (10) bottom sunpender group (23), the cross It is both provided with multilayer, and the transverse horizontal layer (21) and longitudinal water to level course (21) and the vertical equity layer (22) Flat bed (22) is arranged alternately, and adjacent transverse horizontal layer (21) partly overlaps, and the sunpender group (23) is sequentially connected to multilayer institute State transverse horizontal layer (21).
2. the suspension platform according to claim 1 for skybridge construction, which is characterized in that hanger (2) packet The first hanger (201) and the second hanger (202) are included, first hanger (201) is set to the underface of the vestibule (10), institute It states the second hanger (202) and is set to the both sides of first hanger (201) and the underface positioned at the suspension scaffold (1).
3. the suspension platform according to claim 2 for skybridge construction, which is characterized in that further include multiple supports Frame (3), support frame as described above (3) are distributed in the both sides of the vestibule (10), and second hanger (202) is connected to support frame as described above (3) and positioned at the lower section of support frame as described above (3), the suspension scaffold (1) is connected to support frame as described above (3) and is located at support frame as described above (3) top.
4. the suspension platform according to claim 3 for skybridge construction, which is characterized in that support frame as described above (3) Including horizontally-supported (31) and be connected to the skewed horizontal load (32) of horizontally-supported (31), the skewed horizontal load (32) relative to Horizontally-supported (31) are arranged diagonally downward, and horizontally-supported (31) and the skewed horizontal load (32) are respectively connected to The steel construction of corridor (10);
Second hanger (202) and the suspension scaffold (1) are all connected to horizontally-supported (31).
5. the suspension platform according to claim 1 for skybridge construction, which is characterized in that the transverse horizontal layer (21) include more horizontal rods (211), the horizontal rod (211) extends in transverse direction, the sunpender group (23) Including multiple row sunpender (231), each horizontal rod (211) connects with several sunpenders (231) in each column sunpender (231) It connects.
6. the suspension platform according to claim 5 for skybridge construction, which is characterized in that the sunpender (231) Both ends be both provided with anti-skid fastener (4).
7. the suspension platform according to claim 5 for skybridge construction, which is characterized in that the vertical equity layer (22) include more longitudinal horizontal rods (221), the longitudinal horizontal rod (221) is extendable in the longitudinal direction, the longitudinal horizontal rod (221) it is connected to the horizontal rod (211).
8. the suspension platform according to claim 1 for skybridge construction, which is characterized in that the transverse horizontal layer (21) template (24) is equipped between the vertical equity layer (22).
9. the suspension platform according to claim 3 for skybridge construction, which is characterized in that the suspension scaffold (1) Including two row vertical bars (11) and multilayer link (12), the link (12) includes two transverse bars (121) and more companies The longitudinal rod (122) being connected between two transverse bars (121), every transverse bar (121) are sequentially connected to each column vertical bar (11), the vertical bar (11) is connected to support frame as described above (3).
10. a kind of construction method of suspension platform for skybridge construction, which is characterized in that include the following steps:
Suspension scaffold is set up in the both sides of vestibule;
The vestibule and the suspension scaffold are overall increased into the first mounting distance, and hanger is set up in the bottom of the vestibule;
The vestibule, the suspension scaffold and the hanger are overall increased into the second mounting distance, make the vestibule and its both sides High building be butted against and fixed, meanwhile, the suspension scaffold docks fixation with outrigger;
The both sides of the vestibule are decorated on the suspension scaffold, after decoration, both sides overhanging is removed after the completion of the decoration of both sides Frame;
Remove sunpender group by column and successively remove transverse horizontal layer and vertical equity layer, meanwhile, the bottom of the vestibule by column It is laid with decorative panel.
CN201810646099.0A 2018-06-21 2018-06-21 Suspension platform for high-altitude corridor construction and construction method thereof Active CN108708541B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810646099.0A CN108708541B (en) 2018-06-21 2018-06-21 Suspension platform for high-altitude corridor construction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810646099.0A CN108708541B (en) 2018-06-21 2018-06-21 Suspension platform for high-altitude corridor construction and construction method thereof

Publications (2)

Publication Number Publication Date
CN108708541A true CN108708541A (en) 2018-10-26
CN108708541B CN108708541B (en) 2023-12-12

Family

ID=63872890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810646099.0A Active CN108708541B (en) 2018-06-21 2018-06-21 Suspension platform for high-altitude corridor construction and construction method thereof

Country Status (1)

Country Link
CN (1) CN108708541B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116201342A (en) * 2023-02-27 2023-06-02 中铁九局集团有限公司 Method for dismantling and reinforcing suspension operation platform after super high-rise fire disaster
CN116856534A (en) * 2023-07-18 2023-10-10 中国建筑第七工程局有限公司 Inter-building lifting corridor and use method thereof
CN118545612A (en) * 2024-07-29 2024-08-27 杭萧钢构(洛阳)有限公司 High-precision intelligent hoisting equipment for steel structure corridor and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101845849A (en) * 2010-06-22 2010-09-29 中国建筑第二工程局有限公司 Large-span steel structure corridor erected between new and old buildings and construction method thereof
CN107642225A (en) * 2017-09-21 2018-01-30 广西壮族自治区冶金建设公司 A kind of hanging scaffold and its assembly and method for dismounting
CN208363560U (en) * 2018-06-21 2019-01-11 中国华西企业有限公司 A kind of suspension platform for skybridge construction

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101845849A (en) * 2010-06-22 2010-09-29 中国建筑第二工程局有限公司 Large-span steel structure corridor erected between new and old buildings and construction method thereof
CN107642225A (en) * 2017-09-21 2018-01-30 广西壮族自治区冶金建设公司 A kind of hanging scaffold and its assembly and method for dismounting
CN208363560U (en) * 2018-06-21 2019-01-11 中国华西企业有限公司 A kind of suspension platform for skybridge construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
任光勇等: ""下沙东部国际商务中心钢连廊结构的设计与施工"", 《浙江建筑》, vol. 29, no. 8, pages 19 - 23 *
王辉: ""高空大跨度钢连廊现浇楼面的 模板吊架施工工艺"", 《建筑施工》, vol. 27, no. 11, pages 47 - 48 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116201342A (en) * 2023-02-27 2023-06-02 中铁九局集团有限公司 Method for dismantling and reinforcing suspension operation platform after super high-rise fire disaster
CN116201342B (en) * 2023-02-27 2025-04-25 中铁九局集团有限公司 A method for dismantling and reinforcing a suspended work platform for a super high-rise fire corridor
CN116856534A (en) * 2023-07-18 2023-10-10 中国建筑第七工程局有限公司 Inter-building lifting corridor and use method thereof
CN116856534B (en) * 2023-07-18 2025-09-09 中国建筑第七工程局有限公司 Inter-building lifting corridor and use method thereof
CN118545612A (en) * 2024-07-29 2024-08-27 杭萧钢构(洛阳)有限公司 High-precision intelligent hoisting equipment for steel structure corridor and construction method

Also Published As

Publication number Publication date
CN108708541B (en) 2023-12-12

Similar Documents

Publication Publication Date Title
CN211899558U (en) A cantilever operating stand
CN209011528U (en) An all-steel attached lifting scaffold
CN108708541A (en) A kind of suspension platform and its construction method for skybridge construction
CN105484502A (en) Combination installation method for steel structure roofing purlins and support bars of industrial factory building
CN110284598A (en) The installation method and device of spherical net brace roof structure
CN208363560U (en) A kind of suspension platform for skybridge construction
CN218175600U (en) Suspension frame for welding arch rib segments
CN115306137A (en) Operation platform structure for mounting suspended ceiling at bottom of overhead corridor and construction method thereof
CN105839907A (en) Suspension type steel platform scaffold foundation and method for mounting same
CN205777428U (en) Elevator is from climbing platforms
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN205777438U (en) A kind of suspension type steel platform legs hand cradle basis
CN205758443U (en) The low concealed window cleaning equipment of high flexion-extension
CN209260569U (en) A kind of sliding lifting device of steel structure bridge arc-shape decorative plate
CN107916772A (en) A kind of hanging-type construction platform and installation method for curved surface ceiling construction
CN209040527U (en) A kind of scaffold cradle structure
CN206722372U (en) Across a plurality of business circuit elevated station room curtain wall decoration bilateral vertical transport erecting device
CN210685328U (en) All-steel Attached Lifting Scaffolding
CN203878962U (en) Independent supporting device for high-place operation hanging basket cantilever
CN203394008U (en) Suspension type hanging bracket used on plane truss
CN204826727U (en) Reinforcing bar processing protection canopy that can dismantle, has enough to meet need
CN107035037A (en) High building top layer curtain wall frame and its installation method
CN107313586A (en) A kind of special-shaped cornice decorative curtain wall mounting platform of building and construction method
CN215055177U (en) Protection dress is built to irregular facade building scaffold
CN212983624U (en) Movable hanging basket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant