CN108675132A - A kind of steel construction purlin and Accessory Members method for rapidly mounting - Google Patents
A kind of steel construction purlin and Accessory Members method for rapidly mounting Download PDFInfo
- Publication number
- CN108675132A CN108675132A CN201810338215.2A CN201810338215A CN108675132A CN 108675132 A CN108675132 A CN 108675132A CN 201810338215 A CN201810338215 A CN 201810338215A CN 108675132 A CN108675132 A CN 108675132A
- Authority
- CN
- China
- Prior art keywords
- steel construction
- purlin
- rope
- accessory
- accessory members
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention provides a kind of steel construction purlin and Accessory Members method for rapidly mounting, including, step a:At least two purlins are placed on the ground according to default spacing;Step b:Accessory structure is installed to purlin;Step c:Assembled good at least two purlins and accessory structure are connected into an entirety by lifting rope;Step d:Lifting rope installation site is hoisted to by boom hoisting to install.Compared with prior art, the beneficial effects of the present invention are steel construction purlin and Accessory Members method for rapidly mounting provided by the invention by least two purlins and accessory structure Integral lifting by, to home, greatly shortening working hour, crane machine-team and labour are saved, cost is reduced.
Description
Technical field
The present invention relates to metallurgy industry Steel Structure Installation engineering technical fields, in particular to a kind of steel construction purlin
And Accessory Members method for rapidly mounting.
Background technology
Currently, when steel construction purlin and Accessory Members lift, traditional method be by purlin one one lift one by one just
Then position arranges construction personnel to install the Accessory Members such as tie rod and even support in high-altitude again.Due to steel-structure factory building purlin and tie rod,
The Accessory Members quantity such as even support are more, and installation is multi-point and wide-ranging, and using conventional method installation, not only effect is low, but also duty cycle is long,
Setting increases, and security risk is big.
Invention content
In consideration of it, the present invention proposes a kind of steel construction purlin and Accessory Members method for rapidly mounting, it is intended to solve existing
Since purlin and Accessory Members transport lead to the technical problem that purlin and Accessory Members installation period are grown slowly in technology.
A kind of steel construction purlin and Accessory Members method for rapidly mounting proposed by the present invention, including:
Step a:At least two purlins are placed on the ground according to default spacing;
Step b:Accessory structure is installed to the purlin;
Step c:Assembled good at least two purlins and accessory structure are connected into an entirety by lifting rope;
Step d:The lifting rope installation site is hoisted to by boom hoisting to install.
Further, the accessory structure includes pull rod, even support.
Further, the pull rod and even support are bolted on the purlin.
Further, the top of the lifting rope is provided with suspension hook.
Further, the lifting rope includes main rope, secondary rope, buckle;
The buckle is fixed on the pair to be restricted on the main rope.
Further, the diameter of the main rope is more than the diameter of the secondary rope.
Further, the buckle is at least arranged three, to ensure the secured of locking.
Compared with prior art, the beneficial effects of the present invention are steel construction purlins and Accessory Members provided by the invention
Method for rapidly mounting is saved by the way that at least two purlins and accessory structure Integral lifting to home, are greatly shortened working hour
About crane machine-team and labour, reduce cost.
Further, by the present invention in that pair rope is fixed on main rope at least three buckles, it is ensured that pair rope will not
It is fallen from main rope, increases working security.
Description of the drawings
By reading the detailed description of hereafter preferred embodiment, various other advantages and benefit are common for this field
Technical staff will become clear.Attached drawing only for the purpose of illustrating preferred embodiments, and is not considered as to the present invention
Limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is the flow chart of steel construction purlin provided in an embodiment of the present invention and Accessory Members method for rapidly mounting;
Fig. 2 is the overall structure signal of steel construction purlin provided in an embodiment of the present invention and Accessory Members method for rapidly mounting
Figure;
Fig. 3 is lifting rope structural schematic diagram provided in an embodiment of the present invention.
Specific implementation mode
The exemplary embodiment of the disclosure is more fully described below with reference to accompanying drawings.Although showing the disclosure in attached drawing
Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here
It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure
Completely it is communicated to those skilled in the art.It needs to illustrate
Further, the lifting rope includes main rope, secondary rope, buckle;
The buckle is fixed on the pair to be restricted on the main rope.
Further, the diameter of the main rope is more than the diameter of the secondary rope.
Further, the buckle is at least arranged three, to ensure the secured of locking.
Compared with prior art, the beneficial effects of the present invention are steel construction purlins and Accessory Members provided by the invention
Method for rapidly mounting is saved by the way that at least two purlins and accessory structure Integral lifting to home, are greatly shortened working hour
About crane machine-team and labour, reduce cost.
Further, by the present invention in that pair rope is fixed on main rope at least three buckles, it is ensured that pair rope will not
It is fallen from main rope, increases working security.
Description of the drawings
By reading the detailed description of hereafter preferred embodiment, various other advantages and benefit are common for this field
Technical staff will become clear.Attached drawing only for the purpose of illustrating preferred embodiments, and is not considered as to the present invention
Limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is the flow chart of steel construction purlin provided in an embodiment of the present invention and Accessory Members method for rapidly mounting;
Fig. 2 is the overall structure signal of steel construction purlin provided in an embodiment of the present invention and Accessory Members method for rapidly mounting
Figure;
Fig. 3 is lifting rope structural schematic diagram provided in an embodiment of the present invention.
Specific implementation mode
The exemplary embodiment of the disclosure is more fully described below with reference to accompanying drawings.Although showing the disclosure in attached drawing
Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here
It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure
Completely it is communicated to those skilled in the art.It should be noted that in the absence of conflict, embodiment in the present invention and
Feature in embodiment can be combined with each other.The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
Refering to fig. 1, it is the flow of steel construction purlin provided in an embodiment of the present invention and Accessory Members method for rapidly mounting
Figure, including, at least two purlins 2 are placed on the ground first, in accordance with default spacing;Secondly accessory structure is installed to purlin 2
On;Then assembled good at least two purlins 2 and accessory structure are connected into an entirety by lifting rope 5;Finally by lifting
Lifting rope 5 is hoisted to installation site and installed by device.In the present embodiment, by the advance mounting purlines in ground and attached knot
Structure, it is possible to reduce the working at height time reduces the risk of working at height, by by the purlin 2 and attached after at least two assemblings
Structure Integral lifting is to installation site, it is possible to reduce the number of handling improves construction efficiency to save construction cost.
Referring to Fig.2, its entirety for steel construction purlin provided in an embodiment of the present invention and Accessory Members method for rapidly mounting
Structural schematic diagram, in the present embodiment, purlin 2 and Accessory Members are arranged three groups, are connected on lifting rope 5, and Accessory Members include drawing
Wherein one end of bar 3, even support 4, pull rod 3 and even support 4 is bolted on the side wall of purlin 2, and the other end is free end.It hangs
The top of rope 5 is provided with suspension hook 1, to be connected with boom hoisting, handling lifting rope 5.
It is lifting rope structural schematic diagram provided in an embodiment of the present invention, including main rope 51, secondary rope 52, buckle refering to Fig. 3
53, pair rope 52 is fixed on main rope 51 by buckle 53, and in the present embodiment, main rope 51, secondary rope 52 are steel wire rope, and due to master
Rope 51 undertakes the weight of all hanging objects, therefore main rope 51 uses thicker steel wire rope, pair rope 52 to use thinner steel wire rope with side
Just the binding of purlin 2.Buckle 53 is annular buckle, and 52 setting two of pair rope is separately positioned on 51 both sides of main rope, it is secondary restrict 52 its
Middle one end is fixed on by buckle 53 on the side wall of main rope 51, and the other end of pair rope 52 is connected with the both ends of purlin 2 respectively.In order to
Ensure that secondary rope will not be fallen from main rope, 53 setting three of buckle avoids purlin 2 in transportational process to reinforce connection
It is fallen from main rope 51, increases the safety of construction.It will be understood by those skilled in the art that secondary rope 52 can by
End set snap ring sets purlin 2 by snap ring card, can also be directly by pair 52 setting fastenings of rope in the both sides of purlin 2, and the present embodiment exists
This is not limited.
Specifically, steel construction purlin proposed by the present invention and Accessory Members method for rapidly mounting include the following steps:
Step S1:At least two purlins 2 are placed on the ground according to default spacing;
Step S2:It will be on pull rod 3,4 installation to purlin 2 of even support;
Step S3:Assembled at least two good purlins 2 are connected into an entirety by lifting rope 5;
Step S4:Lifting rope 5 installation site is hoisted to by boom hoisting to install.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art
God and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies
Within, then the present invention is also intended to include these modifications and variations.
Claims (7)
1. a kind of steel construction purlin and Accessory Members method for rapidly mounting, which is characterized in that including:
Step a:At least two purlins (2) are placed on the ground according to default spacing;
Step b:Accessory structure is installed to the purlin (2);
Step c:Assembled good at least two purlins (2) and accessory structure are connected into an entirety by lifting rope (5);
Step d:The lifting rope (5) installation site is hoisted to by boom hoisting to install.
2. steel construction purlin according to claim 1 and Accessory Members method for rapidly mounting, which is characterized in that described attached
Structure includes pull rod (3), even support (4).
3. steel construction purlin according to claim 2 and Accessory Members method for rapidly mounting, which is characterized in that the pull rod
(3) it is bolted on the purlin (2) with even support (4).
4. steel construction purlin according to claim 1 and Accessory Members method for rapidly mounting, which is characterized in that the lifting rope
(5) top is provided with suspension hook (1).
5. steel construction purlin according to claim 1 and Accessory Members method for rapidly mounting, which is characterized in that the lifting rope
(5) include main rope (51), secondary rope (52), buckle (53);
Secondary restrict (52) being fixed on the main rope (51) by the buckle (53).
6. steel construction purlin according to claim 5 and Accessory Members method for rapidly mounting, which is characterized in that the main rope
(51) diameter is more than the diameter of the secondary rope (52).
7. steel construction purlin according to claim 6 and Accessory Members method for rapidly mounting, which is characterized in that the buckle
(53) at least it is arranged three, to ensure the secured of locking.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810338215.2A CN108675132A (en) | 2018-04-16 | 2018-04-16 | A kind of steel construction purlin and Accessory Members method for rapidly mounting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810338215.2A CN108675132A (en) | 2018-04-16 | 2018-04-16 | A kind of steel construction purlin and Accessory Members method for rapidly mounting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108675132A true CN108675132A (en) | 2018-10-19 |
Family
ID=63800000
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810338215.2A Pending CN108675132A (en) | 2018-04-16 | 2018-04-16 | A kind of steel construction purlin and Accessory Members method for rapidly mounting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108675132A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110386546A (en) * | 2019-08-05 | 2019-10-29 | 中冶天工(天津)装备制造有限公司 | A kind of hanging method for the installation of more steel structure wall purlins |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4671724A (en) * | 1985-12-13 | 1987-06-09 | Bolton Gary R | Multi-beam structure clip |
JPH08128206A (en) * | 1994-10-31 | 1996-05-21 | Penta Ocean Constr Co Ltd | Conveyance of beam member in one lump, and construction-and device therefor |
CN201746220U (en) * | 2010-07-27 | 2011-02-16 | 广东省第二建筑工程公司 | Strip-type element hanging device |
CN203173681U (en) * | 2012-12-17 | 2013-09-04 | 中国一冶集团有限公司 | Device for lifting whole ultra-long reinforcing cage of underground continuous wall |
CN203513086U (en) * | 2013-09-14 | 2014-04-02 | 唐山港集团股份有限公司 | Special lifting appliance for long-bundle-shaped material |
CN104098018A (en) * | 2014-05-25 | 2014-10-15 | 中石化南京工程有限公司 | Reusable multistage balance beam combination system |
CN204609324U (en) * | 2015-03-30 | 2015-09-02 | 山东达驰电气有限公司 | A kind of lifting device used in steel work purlin is installed |
CN205045698U (en) * | 2015-10-27 | 2016-02-24 | 中铁上海工程局集团有限公司 | Reinforcement cage hoisting utensil |
CN105484502A (en) * | 2014-10-10 | 2016-04-13 | 五冶集团上海有限公司 | Combination installation method for steel structure roofing purlins and support bars of industrial factory building |
CN106429791A (en) * | 2016-11-10 | 2017-02-22 | 大连益利亚工程机械有限公司 | Special hoisting sling and hoisting method for nuclear power station CR10 and reinforcing steel bar composite module |
-
2018
- 2018-04-16 CN CN201810338215.2A patent/CN108675132A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4671724A (en) * | 1985-12-13 | 1987-06-09 | Bolton Gary R | Multi-beam structure clip |
JPH08128206A (en) * | 1994-10-31 | 1996-05-21 | Penta Ocean Constr Co Ltd | Conveyance of beam member in one lump, and construction-and device therefor |
CN201746220U (en) * | 2010-07-27 | 2011-02-16 | 广东省第二建筑工程公司 | Strip-type element hanging device |
CN203173681U (en) * | 2012-12-17 | 2013-09-04 | 中国一冶集团有限公司 | Device for lifting whole ultra-long reinforcing cage of underground continuous wall |
CN203513086U (en) * | 2013-09-14 | 2014-04-02 | 唐山港集团股份有限公司 | Special lifting appliance for long-bundle-shaped material |
CN104098018A (en) * | 2014-05-25 | 2014-10-15 | 中石化南京工程有限公司 | Reusable multistage balance beam combination system |
CN105484502A (en) * | 2014-10-10 | 2016-04-13 | 五冶集团上海有限公司 | Combination installation method for steel structure roofing purlins and support bars of industrial factory building |
CN204609324U (en) * | 2015-03-30 | 2015-09-02 | 山东达驰电气有限公司 | A kind of lifting device used in steel work purlin is installed |
CN205045698U (en) * | 2015-10-27 | 2016-02-24 | 中铁上海工程局集团有限公司 | Reinforcement cage hoisting utensil |
CN106429791A (en) * | 2016-11-10 | 2017-02-22 | 大连益利亚工程机械有限公司 | Special hoisting sling and hoisting method for nuclear power station CR10 and reinforcing steel bar composite module |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110386546A (en) * | 2019-08-05 | 2019-10-29 | 中冶天工(天津)装备制造有限公司 | A kind of hanging method for the installation of more steel structure wall purlins |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109095343A (en) | Assembled hanger | |
CN202465025U (en) | Sling special for prefabricated panel | |
CN201598100U (en) | Anti-curl device for steel plate clamp suspension system | |
CN201746220U (en) | Strip-type element hanging device | |
CN203173684U (en) | Component for hoisting reinforcement cage | |
CN108675132A (en) | A kind of steel construction purlin and Accessory Members method for rapidly mounting | |
CN205637622U (en) | Perpendicular unit glass curtain wall hoist and mount system | |
CN106315426A (en) | Block form tower crane mounting and jacking method for assembled building | |
CN114180456A (en) | Hoisting posture adjusting method for giant laterally inclined truss structure | |
CN105858437A (en) | Automatic lifting appliance for balancing weight | |
CN202717497U (en) | Lifting device of prefabricated composite floor slab | |
CN205132903U (en) | Steel wire slings | |
CN215828220U (en) | Double-winch lifting system | |
CN208948679U (en) | Assembled hanger | |
CN103669887A (en) | Temporary supporting frame for annular steel structure installation | |
CN205170161U (en) | Precast beam board framework of steel reinforcement hoist | |
CN210457158U (en) | Curtain type mounting structure for quickly hoisting square concrete pier column hooping | |
CN216997258U (en) | A hoisting structure for hoist and mount of roofing purlin | |
CN204778496U (en) | Platform sling structure of tower crane | |
CN202575684U (en) | Prefabricated-slab hoisting tool | |
CN103669886A (en) | Installation method for annular steel structure | |
CN207108259U (en) | Special lifting appliance for lifting steel structure module system | |
CN220845070U (en) | Prefabricated assembled concrete member hoist device and crane | |
CN216889678U (en) | Rectangular steel reinforcement cage hoisting system | |
CN205953321U (en) | A gallows for hoist and mount of arc roof boarding |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181019 |
|
RJ01 | Rejection of invention patent application after publication |