CN108675106A CN201810543780.2A CN201810543780A CN108675106A CN 108675106 A CN108675106 A CN 108675106A CN 201810543780 A CN201810543780 A CN 201810543780A CN 108675106 A CN108675106 A CN 108675106A
Authority
CN
China
Prior art keywords
steel wire
balance
wire rope
pipe
drop tee
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810543780.2A
Other languages
Chinese (zh)
Inventor
李子长
李春杰
张文清
刘鹏
闫丽文
孟维波
李治
贾永斌
朱伟正
高鑫
耿彦方
王鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SNANXI HONGSHA 1ST CONSTRUCTION CO Ltd
Original Assignee
SNANXI HONGSHA 1ST CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SNANXI HONGSHA 1ST CONSTRUCTION CO Ltd filed Critical SNANXI HONGSHA 1ST CONSTRUCTION CO Ltd
Priority to CN201810543780.2A priority Critical patent/CN108675106A/en
Publication of CN108675106A publication Critical patent/CN108675106A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/122Sling or load protectors
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C15/00Safety gear

Abstract

A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe, it is therefore an objective to prevent round umbellate form blast cap from being deformed during lifting;The present invention first makes a set of lifting apparatus;Lifting apparatus includes balance pipe, connection lifting lug and steel wire rope;Balance length of tube is longer than the diameter of suspended object part cowl;Balance drop tee T is mounted in balance pipe both ends;Emptying drop tee T is attached separately to blow-down pipe both sides;Hypomere steel wire rope is connected between emptying drop tee T and homonymy balance drop tee T;Epimere steel wire rope is connected between two balance drop tee Ts;There are certain intervals between hypomere steel wire rope and suspended object part cowl edge;Epimere steel wire rope midpoint is triggered with crane hook, crane hook is slightly lifted, upper and lower two sections of steel wire ropes are all tightened, and after suspended object part balance, draw high crane hook again, and suspended object part is sling and is put to installation at required position and is fixed.

Description

A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe
Technical field
The present invention relates to a kind of methods of lifting Large Diameter Pipeline blow-down pipe and umbellate form blast cap.
Background technology
In gas pumping equipment of pumping station installing engineering, the specification of Large Diameter Pipeline blow-down pipe is typically that diameter phi is more than or equal to The steel pipe of 800mm installs umbellate form blast cap at the top of blow-down pipe.Made of the steel plate that umbellate form blast cap is rolls, size is big, structure It is soft.Umbellate form blast cap, need to be fixed at the top of blow-down pipe by previous construction before lifting by crane blow-down pipe.Then recycle crane that will be vented Pipe lifts installation, and previous hoisting method is to weld lifting lug directly on blow-down pipe and hang up properly steel wire rope and buckle to hang.But such umbrella Type blast cap easily deforms after being squeezed by steel wire rope Le, needs to remake blast cap after damage, extends installing engineering progress, increase work Journey expense.
Invention content
Purpose of the present invention is to overcome the shortcomings of above-mentioned prior art, providing one kind can prevent round umbellate form blast cap in lifting process It is middle to deform, to avoid the lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe done over again.
The method of the present invention is:
(1)According to the blow-down pipe and umbellate form blast cap appearance and size lifted, a set of lifting apparatus is made;It includes balance to lift by crane apparatus Pipe, connection lifting lug and steel wire rope;It includes two balance drop tee Ts and two emptying drop tee Ts to connect lifting lug;Balance pipe is using seamless Steel pipe, length will be longer than the diameter of suspended object part cowl, if seamless steel pipe insufficient strength, in place can add Reinforcing rib is to ensure its intensity.
(2)Two balance drop tee Ts are attached separately to balance pipe both ends;Two emptying drop tee Ts are attached separately to blow-down pipe two Side;Steel wire rope is divided into upper and lower two sections;There are two hypomere steel wire ropes, length is identical, is connected to emptying drop tee T and homonymy Between balance drop tee T;Epimere steel wire rope is connected between two balance drop tee Ts;The length of epimere steel wire rope is more than balance pipe Length;
(3)Selection balance length of tube and emptying drop tee T installation site and hypomere rope capacity so that emptying drop tee T with Hypomere steel wire rope between homonymy balance drop tee T stretches tension, is stayed between hypomere steel wire rope and suspended object part cowl edge There is certain interval, to prevent suspended object part cowl from deforming or breaking lifting steel wire rope;
To prevent steel wire rope to be broken at lifting lug, steel wire rope protection ring and load clamp are had additional at lifting lug.Load clamp is One U-shaped part is attached separately to balance drop tee T by fixed pin shaft and is vented on drop tee T;Steel wire rope protection ring is water-drop-shaped Shape is sleeved on load clamp;Steel wire rope both ends are connected to by steel wire rope protection ring on load clamp;Connect the thick steel of lifting lug selection Plate makes, and effect is to connect upper and lower hoisting wirerope, it is desirable that has comparable intensity.
(4)Epimere steel wire rope midpoint is triggered with crane hook, crane hook is slightly lifted, upper and lower two sections of steel wire ropes It all tightens, after suspended object part balance, draws high crane hook again, suspended object part is sling and is put to required position Installation is fixed.
The method of the present invention suitable for gas pumping equipment of pumping station installing engineering to Large Diameter Pipeline(In general, caliber is equal to Or it is more than 800mm)It is vented the lifting installation of steel pipe.Advantage be it is possible to prevente effectively from deformation of umbellate form blast cap during lifting, Artificial material is saved, efficiency is improved, overcomes original common hoisting method to easily cause the deformation of umbellate form blast cap, in turn results in wind Cap do over again again fabrication and installation, take a lot of work material a series of problems, such as.
Description of the drawings
Fig. 1 is hoisting structure schematic diagram of the present invention;
Fig. 2 is connection structure diagram between hypomere steel wire rope and emptying drop tee T;
Fig. 3 is connection structure diagram between epimere steel wire rope and balance drop tee T.
In figure:1, crane hook, 2, epimere steel wire rope, 3, balance pipe, 4, balance drop tee T, 5, cowl, 6, under Section steel wire rope, 7, blow-down pipe, 8, emptying drop tee T, 9, steel wire rope protection ring, 10, load clamp.
Specific implementation mode
Singapore dollar company of Yang Mei groups gas pumping pumping plant installs gas blow-down pipe, and the specification of installed gas blow-down pipe is: φ1020mm(Diameter)×22mm(Skin depth), it is 18 meters long, it is vertically-mounted, umbellate form blast cap is installed at the top of blow-down pipe.Umbellate form blast cap It is to be rolled using the steel plate of 6mm thickness, a diameter of 2000mm of blast cap.Using the method for the present invention lifting gas blow-down pipe once at Any deformation does not occur for work(, umbellate form blast cap, efficiently completes lifting task.Installation process is lifted by crane in specific allocation and transportation:
(1)Make a set of lifting apparatus, including balance pipe 3, connection lifting lug and steel wire rope;Connection lifting lug is hung including two balance pipes Ear 4 and two emptying drop tee Ts 8;3 length of balance pipe is longer than suspended object part cowl diameter;
(2)Two balance drop tee Ts 4 are attached separately to 3 both ends of balance pipe;Two emptying drop tee Ts 8 are attached separately to 7 liang of blow-down pipe Side;Steel wire rope is divided into upper and lower two sections;There are two hypomere steel wire ropes 6, and length is identical, is connected to emptying drop tee T 8 and homonymy Balance drop tee T 4 between;Epimere steel wire rope 2 is connected between two balance drop tee Ts 4;
(3)Being vented the installation site of drop tee T 8 will determine according to 3 length of balance pipe and the diameter calculation of cowl, under guarantee There are certain interval between section steel wire rope 6 and 5 edge of suspended object part cowl, 6 angle with horizontal plane of hypomere steel wire rope is not small In 60 °.Cowl 5 and blow-down pipe 7 are connected and fixed by the modes such as welding, riveting.
Steel wire rope protection ring 9 and load clamp 10 are had additional at lifting lug.Load clamp 10 is U-shaped part, passes through fixed pin Axis is attached separately to balance drop tee T 4 and is vented on drop tee T 8;Steel wire rope protection ring 9 is drop shape, is sleeved on load clamp 10 On;Steel wire rope both ends are connected to by steel wire rope protection ring 9 on load clamp 10;Lifting lug selection steel plate is connected to make.Hypomere It is connected by load clamp 10 between steel wire rope 6 and emptying drop tee T 8, between hypomere steel wire rope 6 and balance drop tee T 4, on It is connected by load clamp 10 between section steel wire rope 2 and balance pipe connection lifting lug 4.
(4)2 midpoint of epimere steel wire rope is triggered with crane hook 1, crane hook 1 is slightly lifted, upper and lower two sections of steel wires Rope 2,6 is all tightened, and after suspended object part balance, draws high crane hook 1 again, suspended object part is sling and is put to required It installs and fixes at position.
Steel wire rope protection ring 9 is also commonly called as " steel wire rope lantern ring ", is the attachment that is fixedly connected of steel wire rope, and protection steel wire rope is curved Bent portions uniform force, is not easily broken.

Claims (4)

1. a kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe, it is characterized in that:
(1)According to the blow-down pipe and umbellate form blast cap shape and size lifted, a set of lifting apparatus is made;It includes flat to lift by crane apparatus Weighing apparatus pipe, connection lifting lug and steel wire rope;It includes two balance drop tee Ts and two emptying drop tee Ts to connect lifting lug;It is long to balance length of tube In the diameter of suspended object part cowl;
(2)Two balance drop tee Ts are attached separately to balance pipe both ends;Two emptying drop tee Ts are attached separately to blow-down pipe both sides;Steel Cord is divided into upper and lower two sections;There are two hypomere steel wire ropes, and length is identical, is connected to the balance of emptying drop tee T and homonymy Between drop tee T;Epimere steel wire rope is connected between two balance drop tee Ts;The length of epimere steel wire rope is more than balance length of tube;
(3)Selection balance length of tube and emptying drop tee T installation site and hypomere rope capacity so that emptying drop tee T with Hypomere steel wire rope between homonymy balance drop tee T stretches tension, is stayed between hypomere steel wire rope and suspended object part cowl edge There is certain interval, to prevent suspended object part cowl from deforming or breaking lifting steel wire rope;
(4)Epimere steel wire rope midpoint is triggered with crane hook, crane hook is slightly lifted, upper and lower two sections of steel wire ropes are all It tightens, after suspended object part balance, draws high crane hook again, suspended object part is sling and put to installation at required position It is fixed.
2. the lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe as described in claim 1, it is characterized in that in lifting lug Place is equipped with the steel wire rope protection ring and load clamp for preventing wire cable rupture;Load clamp is a U-shaped part, passes through fixed pin shaft It is attached separately to balance drop tee T and is vented on drop tee T;Steel wire rope protection ring is drop shape, is sleeved on load clamp;Steel wire rope It is connected on load clamp by steel wire rope protection ring.
3. the lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe as claimed in claim 1 or 2, it is characterized in that according to The diameter of balance length of tube and cowl is vented the installation site of drop tee T to determine, reconnection tightens hypomere steel wire rope, protects Card hypomere steel wire rope is in tensioned state and angle with horizontal plane is not less than 60 °.
4. the lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe as claimed in claim 1 or 2, it is characterized in that described Balance pipe is using seamless steel pipe, steel pipe sizes and intensity according to balance length of tube and cowl diameter, Large Diameter Pipeline blow-down pipe weight It measures to determine.
CN201810543780.2A 2018-05-31 2018-05-31 A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe Pending CN108675106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810543780.2A CN108675106A (en) 2018-05-31 2018-05-31 A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810543780.2A CN108675106A (en) 2018-05-31 2018-05-31 A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe

Publications (1)

Publication Number Publication Date
CN108675106A true CN108675106A (en) 2018-10-19

Family

ID=63809125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810543780.2A Pending CN108675106A (en) 2018-05-31 2018-05-31 A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe

Country Status (1)

Country Link
CN (1) CN108675106A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202214130U (en) * 2011-08-01 2012-05-09 中国石油化工股份有限公司 Balance beam for hoisting
CN202609768U (en) * 2012-04-13 2012-12-19 天津二十冶建设有限公司 Special lifting device for crane beam brake plate
CN203451047U (en) * 2013-08-01 2014-02-26 中船澄西船舶修造有限公司 Balance weight lifting and mounting structure
CN203513079U (en) * 2013-10-16 2014-04-02 中国化学工程第七建设有限公司 Multi-segment lifting device for large tower device
CN204607377U (en) * 2015-05-21 2015-09-02 中国化学工程第三建设有限公司 Equalizing bar

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202214130U (en) * 2011-08-01 2012-05-09 中国石油化工股份有限公司 Balance beam for hoisting
CN202609768U (en) * 2012-04-13 2012-12-19 天津二十冶建设有限公司 Special lifting device for crane beam brake plate
CN203451047U (en) * 2013-08-01 2014-02-26 中船澄西船舶修造有限公司 Balance weight lifting and mounting structure
CN203513079U (en) * 2013-10-16 2014-04-02 中国化学工程第七建设有限公司 Multi-segment lifting device for large tower device
CN204607377U (en) * 2015-05-21 2015-09-02 中国化学工程第三建设有限公司 Equalizing bar

Similar Documents

Publication Publication Date Title
CN102444086A (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN108190723A (en) A kind of hanging method with the segmentation of the topside of outside plate bulwark and hatch coaming
CN105621280B (en) The apparatus and method for mounting and dismounting crane arm
CN108675106A (en) A kind of lifting installation method with umbellate form blast cap Large Diameter Pipeline blow-down pipe
CN201703776U (en) Inverted lifting device of storage tank
CN205527435U (en) Installation and device of dismantling jib loading boom
CN208716671U (en) A kind of umbellate form blast cap Large Diameter Pipeline blow-down pipe lifting apparatus
CN105735641B (en) A kind of scaffold with reel drawknot adjusting means, which is encorbelmented, expects platform
CN207986492U (en) A kind of heat exchanger integral hoisting tooling
CN205590168U (en) Overturning lifting device
CN206693031U (en) A kind of large-span suspension bridge cable crane load bearing system of head-rope parallel structure
CN108946475A (en) A kind of overturning Lift-on/Lift-off System and hanging method for horizontal equipment
CN101734549A (en) Lifting sling
CN201605579U (en) Tubular pile industrial steel cage suspending device
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN203959697U (en) The equalizing bar of hoisting platform truss
CN102756988A (en) Movable sling for mounting expansion joint of comb plate
CN206693063U (en) A kind of galvanized wire for suspension bridge of head-rope series-mode frame hangs load bearing system
CN207312913U (en) A kind of high-power blower jacket central tube turns over fixture
CN206857957U (en) A kind of crane steel reinforcement cage lifting device of convenient dismounting
CN104627814A (en) Rigging for hoisting waste hopper
CN107777538B (en) Roughing mill frame hoisting device and using method thereof
CN210505201U (en) Equipment for hoisting reinforcing steel bars in batches
CN212077646U (en) Pin-connected arch rib buckling and hanging system of steel pipe arch bridge
CN208869199U (en) A kind of overturning Lift-on/Lift-off System for horizontal equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181019

RJ01 Rejection of invention patent application after publication