CN108645997A - A kind of controlling groundwater level monitoring subgrade settlement rule test model and test method - Google Patents
A kind of controlling groundwater level monitoring subgrade settlement rule test model and test method Download PDFInfo
- Publication number
- CN108645997A CN108645997A CN201810452844.8A CN201810452844A CN108645997A CN 108645997 A CN108645997 A CN 108645997A CN 201810452844 A CN201810452844 A CN 201810452844A CN 108645997 A CN108645997 A CN 108645997A
- Authority
- CN
- China
- Prior art keywords
- roadbed
- level
- reading
- model
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N33/00—Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
- G01N33/24—Earth materials
Abstract
The present invention relates to a kind of controlling groundwater levels to monitor subgrade settlement rule test model, including model, it is cavity structure in the model, the cavity structure is divided into two parts by a vertical partition panel, a part is vertical well, another part bottom is equipped with one layer of blotter, is equipped with above blotter and constructs identical red clay roadbed with half range highway subgrade, has water level control system outside vertical water well section mould walls.The present invention also discloses the test methods of the model.The present invention can analyze the settlement law of red clay under different levels of ground water, and rational technological borrowing and theoretical direction are provided for roadbed filling and repair.
Description
Technical field
The present invention relates to a kind of brick or concrete duct, especially a kind of strength retrogression's subgrade deformation and variation of stress test mould
Type and test method.
Background technology
China is that a monsoon climate is significantly national, and the season distribution of precipitation differs greatly, and precipitation in rain season accounts for about year
70% or so of total amount, general Used in Rainy Seasons of Southern Cities are the 4-9 months, and the north is the 6-9 months.In contrast dry season then drought, to make
Decline at level of ground water, the soil body is caused to generate dry shrinkage and cracking, red clay is opened as a kind of its generation of the apparent soil body of shrinkage
It splits destruction to become apparent from than general clay, destructive also bigger.It is carried out by early-stage study and to red clay area highway
Live disease and geological condition investigation after find, moisture source is abundant, moisture changes place greatly and is susceptible to subgrade settlement
Disease.This project is mainly carried out seasonal underground water and is analyzed the settlement influence of red clay roadbed.It is quick with high-speed railway
Development and highway are continuously increased, and subgrade settlement caused by rainwater in the urgent need to address deforms disaster.
Invention content
The purpose of the present invention is to overcome above-mentioned the deficiencies in the prior art, provide red clay under a kind of different levels of ground water
Settlement law test model and test method.
To achieve the above object, the present invention uses following technical proposals:
A kind of controlling groundwater level monitoring subgrade settlement rule test model, which is characterized in that including model, the mould
It is cavity structure in type body, which is divided into two parts by a vertical partition panel, and a part is vertical well, another portion
Point bottom is equipped with one layer of blotter, is equipped with above blotter and constructs identical red clay roadbed with half range highway subgrade,
There is water level control system outside vertical water well section mould walls.
The slope gradient of the red clay roadbed is 1:1.5.
A kind of controlling groundwater level monitoring subgrade settlement rule test model test method, steps are as follows:
1) experiment roadbed fill and the installation of equipment and instrument with it is embedded;
2) acquisition of water level control and data is experimental field descended;
3) Data Management Analysis is carried out.
Experiment roadbed fills points 5 layers and fills in the step 1), includes the following steps:
A. first layer is blotter, filling-up thickness 10cm, smooth, one layer of upper berth geotextiles after having filled;
B. the second layer to layer 5 fills red clay, using electric shocking rammer compaction in layers, and detect every layer banket contain
Water, density and compactness physical index;
C. simultaneously during roadbed filling, the different compacting passes to be banketed according to each layer pass through soil stiffness modulus test
Instrument measures the elasticity modulus of compacted soil, establishes red clay compactness and the relationship of elasticity modulus.
The installation of equipment and instrument in the step 1) with it is embedded, be included in during roadbed filling and existed according to actual design
The different location of roadbed buries detecting instrument, passes through the specific depth of measurement of the level Accurate Calibration instrument during detecting instrument is embedded
Degree simultaneously, after the completion of roadbed filling, is arranged several displacement observation points in roadbed side slope middle section, is examined by steel ruler and spirit level
Survey level and the vertical displacement of side slope.
Level of ground water control in the step 2) uses water level control system, specific level of ground water control and data to adopt
Collection includes the following contents:
A. roadbed is created, after roadbed reaches final settlement after construction with controlling vertical well using level of ground water control system
Lower water level is kept for the 20cm15 days time of level of ground water, then open discharge outlet and drained at distance model body bottom 20cm, is arranged
7 day time is kept after clean water, this is recycled for first time groundwater level, and during which acquisition, roadbed top surface and slope displacement are seen
It is the elevation of measuring point, the horizontal displacement of slope displacement observation point to experimental tank, the reading of soil pressure cell, the reading of soil moisture meter, single
The reading of horizontal displacement dial gauge, whole numbers in the reading of point sedimentometer, the reading of roadbed top surface dial gauge and monitoring side slope
It is acquired according to computer reading mode is all made of;
B. the vertical well level of ground water of level of ground water control system control is reused after first time groundwater level cycle to exist
At distance model body bottom 30cm, kept for the 30cm15 days time of level of ground water, then open discharge outlet and drained, drain water purification it
7 day time is kept afterwards, this is recycled for second of groundwater level, during which the height of acquisition, roadbed top surface and slope displacement observation point
Journey, the horizontal displacement of slope displacement observation point to experimental tank, the reading of soil pressure cell, the reading of soil moisture meter, single-point sedimentometer
Reading, the reading of roadbed top surface dial gauge and the reading of horizontal displacement dial gauge in monitoring side slope, total data is all made of
Computer reading mode acquires;
Until off-test when groundwater level is recycled to distance model body bottom 80cm.
The cast material and size of the present invention
By consulting amount of literature data, due to the elasticity modulus very little of banketing of road engineering, it is difficult to according to elasticity modulus
The similar material for finding replacement is often tried using undisturbed soil so in the large-scale relevant model test of road engineering
It tests, so this experimental model is using the filler used in entity project.
Roadbed is banded structure object, and stress belongs to plane strain problems simultaneously, and common embankment is symmetric form, therefore
Half range roadbed can be selected and carry out experimental study.This experimental model selects common road structure form and size (roadbed length 10m;
Half range roadbed top surface width:8m;The depth of fill:8m;Slope gradient:1:1.5), according to 1:10 ratios, therefore, test model ruler
It is very little to be:Roadbed length 1m;Half range roadbed top surface width:0.8m;The depth of fill:0.8m;Slope gradient:1:1.5.
Model roadbed is using red clay placement in layers and tamps;For simulated groundwater rise phenomenon, the ground of model roadbed
The blotter of 10cm is filled in beginning first, passes through the SEA LEVEL VARIATION of vertical well, the fluctuation of simulated groundwater position, to realize
The variation of model roadbed different height water content.
Compared with prior art, the beneficial effects of the invention are as follows,
According to test model, scheme and technique, the sedimentation rule of red clay roadbed under the influence of different levels of ground water can be analyzed
Rule, and level of ground water height can be precisely controlled by water level control system, reinforcing repair for roadbed filling provides rational skill
Art is used for reference and theoretical direction.
Description of the drawings
Fig. 1 is model road structure schematic diagram of the present invention;
Fig. 2 (a) is test equipment plane of arrangement figure;
Fig. 2 (b) is test equipment arrangement sectional view;
Wherein 1. models, 2. vertical baffles, 3. vertical wells, 4. blotters, 5. red clay roadbeds, 6. water level controls
System.
Specific implementation mode
Present invention will be further explained below with reference to the attached drawings and examples.
As shown in Figure 1, a kind of controlling groundwater level monitors subgrade settlement rule test model, including model 1, the mould
1 inside of type body is cavity structure, which is divided into two parts by a vertical baffle 2, and a part is vertical well 3, separately
A part of bottom is equipped with one layer of blotter 4, and blotter 4 is equipped with red clay roadbed identical with half range subgrade structure above
5, model is equipped with water level control system 6 outside.The slope gradient of red clay roadbed 5 is 1:1.5.
By consulting amount of literature data, due to the elasticity modulus very little of banketing of road engineering, it is difficult to according to elasticity modulus
The similar material for finding replacement is often tried using undisturbed soil so in the large-scale relevant model test of road engineering
It tests, so this experimental model is using the filler used in entity project.
Roadbed is banded structure object, and stress belongs to plane strain problems simultaneously, and common embankment is symmetric form, therefore
Half range roadbed can be selected and carry out experimental study.This experimental model selects common road structure form and size (roadbed length 10m;
Half range roadbed top surface width:8m;The depth of fill:8m;Slope gradient:1:1.5), according to 1:10 ratios, therefore, test model ruler
It is very little to be:Roadbed length 1m;Half range roadbed top surface width:0.8m;The depth of fill:0.8m;Slope gradient:1:1.5.
Model roadbed is using red clay placement in layers and tamps;For simulated groundwater rise phenomenon, the ground of model roadbed
The blotter of 10cm is filled in beginning first, passes through the SEA LEVEL VARIATION of vertical well, the fluctuation of simulated groundwater position, to realize
The variation of model roadbed different height water content.
Test apparatus is arranged and test content
Test apparatus arrangement is as shown in Fig. 2 (a), Fig. 2 (b).
Testing content includes:The distribution of roadbed vertical pressure, the variation of the vertical moisture content of roadbed, roadbed vertical displacement change
Change, the vertical pore water pressure distribution of roadbed.
The distribution of roadbed vertical pressure is measured by ZLK-YLH soil pressure cells, and the variation of the vertical moisture content of roadbed passes through
NHSF48AR soil moisture sensors measure, and the variation of roadbed vertical displacement is measured by dial gauge, the vertical pore water pressure of roadbed
The distribution of power is measured by ZLK.KXYL pore pressure gauges.
It is as follows that controlling groundwater level monitors subgrade settlement rule test model test method:
One, experiment roadbed fill and the installation of equipment and instrument with it is embedded:
Filling points 5 layers and filling for experiment roadbed, includes the following steps:
A. first layer is blotter, filling-up thickness 10cm, smooth, one layer of upper berth geotextiles after having filled;
B. the second layer to layer 5 fills red clay, using electric shocking rammer compaction in layers, and detect every layer banket contain
Water, density and compactness physical index;
C. simultaneously during roadbed filling, the different compacting passes to be banketed according to each layer pass through soil stiffness modulus test
Instrument measures the elasticity modulus of compacted soil, establishes red clay compactness and the relationship of elasticity modulus.
The installation of equipment and instrument with it is embedded, be included in during roadbed filling according to actual design roadbed different location
Embedded detecting instrument, during detecting instrument is embedded simultaneously by the specific depth of measurement of the level Accurate Calibration instrument, roadbed is filled out
After the completion of building, several displacement observation points are set in roadbed side slope middle section, the level of side slope is detected by steel ruler and spirit level
And vertical displacement.
Two, the acquisition of water level control and data is experimental field descended;
Level of ground water control uses water level control system, and specific level of ground water control and data acquisition include in following
Hold:
A. roadbed is created, after roadbed reaches final settlement after construction with controlling vertical well using level of ground water control system
Lower water level is kept for the 20cm15 days time of level of ground water, then open discharge outlet and drained at distance model body bottom 20cm, is arranged
7 day time is kept after clean water, this is recycled for first time groundwater level, and during which acquisition, roadbed top surface and slope displacement are seen
It is the elevation of measuring point, the horizontal displacement of slope displacement observation point to experimental tank, the reading of soil pressure cell, the reading of soil moisture meter, single
The reading of horizontal displacement dial gauge, whole numbers in the reading of point sedimentometer, the reading of roadbed top surface dial gauge and monitoring side slope
It is acquired according to computer reading mode is all made of;
B. the vertical well level of ground water of level of ground water control system control is reused after first time groundwater level cycle to exist
At distance model body bottom 30cm, kept for the 30cm15 days time of level of ground water, then open discharge outlet and drained, drain water purification it
7 day time is kept afterwards, this is recycled for second of groundwater level, during which the height of acquisition, roadbed top surface and slope displacement observation point
Journey, the horizontal displacement of slope displacement observation point to experimental tank, the reading of soil pressure cell, the reading of soil moisture meter, single-point sedimentometer
Reading, the reading of roadbed top surface dial gauge and the reading of horizontal displacement dial gauge in monitoring side slope, total data is all made of
Computer reading mode acquires;Until off-test when groundwater level is recycled to distance model body bottom 80cm.
Three, Data Management Analysis is carried out.
Claims (6)
1. a kind of controlling groundwater level monitors subgrade settlement rule test model, which is characterized in that including model, the model
It is cavity structure in vivo, which is divided into two parts by a vertical partition panel, and a part is vertical well, another part
Bottom is equipped with one layer of blotter, is equipped with above blotter and constructs identical red clay roadbed with half range highway subgrade, erected
There is water level control system to outside water well section mould walls.
2. model according to claim 1, which is characterized in that the slope gradient of the red clay roadbed is 1:1.5.
3. a kind of controlling groundwater level monitors subgrade settlement rule test model test method, which is characterized in that steps are as follows:
1) experiment roadbed fill and the installation of equipment and instrument with it is embedded;
2) acquisition of water level control and data is experimental field descended;
3) Data Management Analysis is carried out.
4. according to the method described in claim 3, it is characterized in that, experiment roadbed fills points 5 layers and fills in the step 1),
Include the following steps:
A. first layer is blotter, filling-up thickness 10cm, smooth, one layer of upper berth geotextiles after having filled;
B. the second layer to layer 5 fills red clay, using electric shocking rammer compaction in layers, and detect every layer of water content banketed,
Density and compactness physical index;
C. simultaneously during roadbed filling, the different compacting passes to be banketed according to each layer are surveyed by soil stiffness modulus test instrument
The elasticity modulus for measuring compacted soil, establishes silt compactness and the relationship of elasticity modulus.
5. according to the method described in claim, which is characterized in that the installation of the equipment and instrument in the step 1) and embedded, packet
It includes and detecting instrument is buried in the different location of roadbed according to actual design during roadbed filling, during detecting instrument is embedded
Pass through the specific depth of measurement of the level Accurate Calibration instrument.Meanwhile after the completion of roadbed filling, it is arranged in roadbed side slope middle section
Several displacement observation points detect level and the vertical displacement of side slope by steel ruler and spirit level.
6. according to the method described in claim 3, it is characterized in that, the level of ground water control in the step 2) uses water level control
System processed, specific level of ground water control and data acquisition include content:
A. roadbed is created, vertical well underground water is controlled using level of ground water control system after roadbed reaches final settlement after construction
Position is kept for the 20cm15 days time of level of ground water, then open discharge outlet and drained, is discharged at distance model body bottom 20cm
7 day time is kept after water, this is recycled for first time groundwater level, during which acquisition, roadbed top surface and slope displacement observation point
Elevation, the horizontal displacement of slope displacement observation point to experimental tank, the reading of soil pressure cell, the reading of soil moisture meter, single-point it is heavy
The reading of instrument, the reading of roadbed top surface dial gauge and the reading for monitoring horizontal displacement dial gauge in side slope drop, and total data is equal
It is acquired using computer reading mode;
B. level of ground water control system is reused after first time groundwater level cycle controls vertical well level of ground water in distance
It at the 30cm of model bottom, is kept for the 30cm15 days time of level of ground water, then open discharge outlet and drained, drains guarantor after water purification
7 day time is held, this is recycled for second of groundwater level, during which elevation, the side of acquisition, roadbed top surface and slope displacement observation point
Slope displacement observation point to the horizontal displacement of experimental tank, the reading of soil pressure cell, soil moisture meter reading, single-point sedimentometer reading
The reading of horizontal displacement dial gauge, total data are all made of calculating in number, the reading of roadbed top surface dial gauge and monitoring side slope
Machine reading mode acquires;Until off-test when groundwater level is recycled to distance model body bottom 80cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810452844.8A CN108645997A (en) | 2018-05-13 | 2018-05-13 | A kind of controlling groundwater level monitoring subgrade settlement rule test model and test method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810452844.8A CN108645997A (en) | 2018-05-13 | 2018-05-13 | A kind of controlling groundwater level monitoring subgrade settlement rule test model and test method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108645997A true CN108645997A (en) | 2018-10-12 |
Family
ID=63754959
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810452844.8A Pending CN108645997A (en) | 2018-05-13 | 2018-05-13 | A kind of controlling groundwater level monitoring subgrade settlement rule test model and test method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108645997A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111896717A (en) * | 2020-09-22 | 2020-11-06 | 兰州理工大学 | Soil seepage-settlement testing method |
CN112433042A (en) * | 2020-11-12 | 2021-03-02 | 山东省交通科学研究院 | Visual large-scale filling roadbed model test platform and application thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102519811A (en) * | 2011-12-16 | 2012-06-27 | 山东大学 | Model and method for testing deformation and stress variation law of intensity attenuation roadbed |
CN202421181U (en) * | 2012-01-13 | 2012-09-05 | 山东大学 | Salinity aggregation regulation test model for salinized soil roadbed |
CN103233486A (en) * | 2013-05-10 | 2013-08-07 | 山东大学 | Testing device and testing method of anchor-tension type retaining wall model |
CN205483956U (en) * | 2016-03-07 | 2016-08-17 | 盐城工学院 | Test device that simulation weak soil embankment soaks stability repeatedly and warp |
CN105974088A (en) * | 2016-05-04 | 2016-09-28 | 同济大学 | Water level cycle rising and falling induced ground settlement test apparatus and test method thereof |
-
2018
- 2018-05-13 CN CN201810452844.8A patent/CN108645997A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102519811A (en) * | 2011-12-16 | 2012-06-27 | 山东大学 | Model and method for testing deformation and stress variation law of intensity attenuation roadbed |
CN202421181U (en) * | 2012-01-13 | 2012-09-05 | 山东大学 | Salinity aggregation regulation test model for salinized soil roadbed |
CN103233486A (en) * | 2013-05-10 | 2013-08-07 | 山东大学 | Testing device and testing method of anchor-tension type retaining wall model |
CN205483956U (en) * | 2016-03-07 | 2016-08-17 | 盐城工学院 | Test device that simulation weak soil embankment soaks stability repeatedly and warp |
CN105974088A (en) * | 2016-05-04 | 2016-09-28 | 同济大学 | Water level cycle rising and falling induced ground settlement test apparatus and test method thereof |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111896717A (en) * | 2020-09-22 | 2020-11-06 | 兰州理工大学 | Soil seepage-settlement testing method |
CN111896717B (en) * | 2020-09-22 | 2021-04-30 | 兰州理工大学 | Soil seepage-settlement testing method |
CN112433042A (en) * | 2020-11-12 | 2021-03-02 | 山东省交通科学研究院 | Visual large-scale filling roadbed model test platform and application thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108061687B (en) | Geotechnical engineering simulation test platform for researching potential failure surface | |
CN103882894B (en) | Prestressed concrete pipe pile horizontal bearing characteristic test model and test method | |
CN102519811B (en) | Model and method for testing deformation and stress variation law of intensity attenuation roadbed | |
CN107037195A (en) | Water-level fluctuation influences experimental rig and method to lower sleeping ice sheet talus slope stability | |
CN108845108A (en) | The simulator and measuring method of a kind of Compacted Loess seepage flow and settlement after construction | |
CN105136638A (en) | Tailing dam seepage filed similarity simulation test system and tailing dam seepage filed similarity simulation test method | |
CN104865371A (en) | Experiment device and method for consolidation of soft foundation under vacuum condition | |
CN213875269U (en) | Multifunctional tunnel model test device | |
CN105986582A (en) | Indoor model device for reinforcing foundations at different underground water levels by means of dynamic compaction and test method | |
CN109781773A (en) | A kind of frost heave device and its detection method being layered telescopic detection soil | |
CN110967252A (en) | Device for simulating influence of shield tunnel construction on existing tunnel and using method thereof | |
CN105332394A (en) | Testing device for researching resistance of uplift piles on abrupt gush damage mechanism of foundation pits | |
CN108645997A (en) | A kind of controlling groundwater level monitoring subgrade settlement rule test model and test method | |
CN110245426B (en) | Finite element refined simulation method for pipe gallery structure pipe jacking construction | |
CN103898929A (en) | Horizontal bearing characteristics test model for prestressed concrete pipe piles and data testing method | |
CN103898930B (en) | Prestressed concrete pipe pile horizontal bearing attribute testing model and modeling method | |
CN109797729A (en) | A kind of roadbed brick slag changes packing course compactness and refers to object detection method | |
CN202372418U (en) | Testing model for strength weakening roadbed deformation and stress change law | |
CN106759220A (en) | The method that coefficient of static earth pressure is quickly determined using static cone penetration resistance | |
CN208902713U (en) | Ground preloading influences the indoor model test device of existing subway tunnel | |
CN109826175A (en) | A kind of detection method of reinforced soil with geosynthetics filled soils | |
CN101819105B (en) | Drainage test system by low-path embankment and method thereof | |
CN116446470A (en) | Pile-supporting embankment model test device and method under rainfall and dry-wet circulation effects | |
CN201707328U (en) | Low-path-embankment waterproof and drainage test device | |
CN114518292B (en) | Model test device and test method for high-speed railway roadbed of inclined-span campaigns |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181012 |
|
RJ01 | Rejection of invention patent application after publication |