CN108643381A - 装配式剪力墙结构无支撑底部搭接方法 - Google Patents
装配式剪力墙结构无支撑底部搭接方法 Download PDFInfo
- Publication number
- CN108643381A CN108643381A CN201810477826.5A CN201810477826A CN108643381A CN 108643381 A CN108643381 A CN 108643381A CN 201810477826 A CN201810477826 A CN 201810477826A CN 108643381 A CN108643381 A CN 108643381A
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- support
- concrete
- poured
- shear
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 230000003014 reinforcing Effects 0.000 claims abstract description 13
- 238000009434 installation Methods 0.000 claims abstract description 5
- 230000002787 reinforcement Effects 0.000 claims abstract description 5
- 238000005266 casting Methods 0.000 claims abstract description 4
- 238000009415 formwork Methods 0.000 claims abstract description 4
- 238000010276 construction Methods 0.000 abstract description 11
- 238000009435 building construction Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
Abstract
本发明涉及建筑施工技术领域,具体是一种装配式剪力墙结构无支撑底部搭接方法。包括将预制的由混凝土和钢筋组成的墙体吊装到安装位置,同时用千斤顶将墙体支撑起来,通过斜支撑将墙体固定好,在墙体底部钢筋搭接处绑扎后浇钢筋,钢筋绑扎后将墙体底部后浇段进行支模并浇筑混凝土,待混凝土达到强度后,即可拆除模板。本发明减少了制作底部后浇段的模具及后期拆除工作,减少了后期的修补工作,节省了人工和材料费用,缩短了施工工期,提高了施工效率。
Description
装配式剪力墙结构无支撑底部搭接方法
技术领域
[0001]本发明涉及建筑施工技术领域,具体是一种装配式剪力墙结构无支撑底部搭接方 法。
背景技术
[0002]在装配式剪力墙安装施工过程中,节点及接缝处的纵向钢筋连接多采用套筒灌浆 连接、机械连接、焊接连接及间接锚固连接等连接方式,但是上述方式在施工过程中技术要 求高、施工难度大、施工成本高。
发明内容
[0003]本发明旨在解决上述问题,从而提供一种能够节省人工及材料费用、缩短施工工 期、提高施工效率的装配式剪力墙结构无支撑底部搭接方法。
[0004]本发明解决所述问题,采用的技术方案是: 一种装配式剪力墙结构无支撑底部搭接方法,按照如下步骤进行: (一) 将预制的由混凝土和钢筋组成的墙体吊装到安装位置,同时用千斤顶将墙体支撑 起来,通过斜支撑将墙体固定好; (二) 在墙体底部钢筋搭接处绑扎后浇钢筋; (三) 钢筋绑扎后将墙体底部后浇段进行支模并浇筑混凝土; (四) 待混凝土达到强度后,即可拆除模板。
[0005]采用上述技术方案的本发明,与现有技术相比,其突出的特点是: ①减少了制作底部后浇段的模具及后期拆除工作。
[0006] ②减少了后期的修补工作。
[0007]③节省了人工和材料费用,缩短了施工工期,提高了施工效率。
附图说明
[0008]图1是本发明实施例墙体的结构示意图; 图2是图1的侧视结构示意图; 图3是图1的俯视结构示意图; 图中:墙体1;钢筋2;混凝土3。
[0009]具体实施方式: 下面结合实施例对本发明作进一步说明,目的仅在于更好地理解本发明内容,因此,所 举之例并不限制本发明的保护范围。 CM10]参见图u图2、图3,一种装配式剪力墙结构无支撑底部搭接方法,按照如下步骤进 行: (一)将预制的由混凝土3和钢筋2组成的墙体1吊装到安装位置,同时用千斤顶将墙体丄 支撑起来,通过斜支撑将墙体1固定好。 LUUMJ 、二”土㊆佯1胲邰钢筋2的搭接处绑扎后浇筑的钢筋2。
[0012](二)钢筋2绑扎后将墙体1底部后浇段进行支模并浇筑混凝土 3。
[0013](四)待混凝土 3达到强度后,即可拆除模板。
[00M]本发明减少了制作底部后浇段的模具及后期拆除工作,减少了后期的修补工作, 节省了人工和材料费用,缩短了施工工期,提高了施工效率。
[0015]以上所述仅为本发明较佳可行的实施例而己,并非因此局限本发明的权利范围, 凡运用本发明说明书及其附图内容所作的等效变化,均包含于本发明的权利范围之内。
Claims (1)
1. 一种装配式剪力墙结构无支撑底部搭接方法,其特征在于,按照如下步骤进行: (一) 将预制的由混凝土和钢筋组成的墙体吊装到安装位置,同时用千斤顶将墙体支撑 起来,通过斜支撑将墙体固定好; (二) 在墙体底部钢筋搭接处绑扎后浇钢筋; (三) 钢筋绑扎后将墙体底部后浇段进行支模并浇筑混凝土; (四) 待混凝土达到强度后,即可拆除模板。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810477826.5A CN108643381A (zh) | 2018-05-18 | 2018-05-18 | 装配式剪力墙结构无支撑底部搭接方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810477826.5A CN108643381A (zh) | 2018-05-18 | 2018-05-18 | 装配式剪力墙结构无支撑底部搭接方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108643381A true CN108643381A (zh) | 2018-10-12 |
Family
ID=63756684
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810477826.5A Withdrawn CN108643381A (zh) | 2018-05-18 | 2018-05-18 | 装配式剪力墙结构无支撑底部搭接方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108643381A (zh) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102425310A (zh) * | 2011-12-15 | 2012-04-25 | 中国二十二冶集团有限公司 | 装配式住宅剪力墙结构墙体竖向连接施工方法 |
CN202273335U (zh) * | 2011-08-30 | 2012-06-13 | 东南大学 | 装配剪力墙结构预制内墙板竖向混合连接结构 |
CN102808465A (zh) * | 2012-08-08 | 2012-12-05 | 沈阳建筑大学 | 装配式混凝土框架-剪力墙拼装连接结构及拼装连接方法 |
CN107299695A (zh) * | 2017-07-12 | 2017-10-27 | 湖北宇辉中工建筑产业化有限公司 | 预制墙体混凝土门窗框及施工方法 |
CN206902987U (zh) * | 2017-07-24 | 2018-01-19 | 李聪 | 一种带顶柱的t型剪力墙 |
CN206956979U (zh) * | 2017-07-20 | 2018-02-02 | 李聪 | 一种带顶柱的一字型剪力墙 |
CN207003713U (zh) * | 2017-08-04 | 2018-02-13 | 李聪 | 一种部分现浇剪力墙 |
-
2018
- 2018-05-18 CN CN201810477826.5A patent/CN108643381A/zh not_active Withdrawn
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202273335U (zh) * | 2011-08-30 | 2012-06-13 | 东南大学 | 装配剪力墙结构预制内墙板竖向混合连接结构 |
CN102425310A (zh) * | 2011-12-15 | 2012-04-25 | 中国二十二冶集团有限公司 | 装配式住宅剪力墙结构墙体竖向连接施工方法 |
CN102808465A (zh) * | 2012-08-08 | 2012-12-05 | 沈阳建筑大学 | 装配式混凝土框架-剪力墙拼装连接结构及拼装连接方法 |
CN107299695A (zh) * | 2017-07-12 | 2017-10-27 | 湖北宇辉中工建筑产业化有限公司 | 预制墙体混凝土门窗框及施工方法 |
CN206956979U (zh) * | 2017-07-20 | 2018-02-02 | 李聪 | 一种带顶柱的一字型剪力墙 |
CN206902987U (zh) * | 2017-07-24 | 2018-01-19 | 李聪 | 一种带顶柱的t型剪力墙 |
CN207003713U (zh) * | 2017-08-04 | 2018-02-13 | 李聪 | 一种部分现浇剪力墙 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108643382A (zh) | 装配式剪力墙板竖向连接的施工方法 | |
CN107254884A (zh) | 一种可拆卸预制装配式方钢管混凝土柱脚节点 | |
CN107143034A (zh) | 一种装配式混凝土框架结构梁柱刚性连接节点 | |
CN105569224A (zh) | 钢管混凝土边缘约束叠合整体式剪力墙及制备和安装方法 | |
CN107100069A (zh) | 一种混凝土圆柱墩盖梁和系梁逆序施工方法 | |
CN108661221A (zh) | 一种预制楼板及其连接结构及其施工方法 | |
CN105133791A (zh) | 装配式厚板钢骨混凝土柱变截面转换节点结构的施工方法 | |
CN208430661U (zh) | 一种“一”字型自保温叠合剪力墙竖向拼缝构造 | |
CN106088326B (zh) | 基于3d打印的装配式框架柱结构 | |
CN208618627U (zh) | 一种预制楼板及其连接结构 | |
CN201753530U (zh) | 简支箱梁钢筋整体绑扎台座及其吊架和支架 | |
CN107090908B (zh) | 一种竖向预制构件节点连接方法 | |
CN108643381A (zh) | 装配式剪力墙结构无支撑底部搭接方法 | |
CN206503164U (zh) | 逆作法取土口快速封闭施工连接节点 | |
CN111396079B (zh) | 一种叠合装配式隧道二次衬砌结构及其施工方法 | |
CN104314105A (zh) | 地下室外墙板与现浇扶壁柱的连接竖向拼缝结构及施工方法 | |
CN205382595U (zh) | 钢管混凝土边缘约束叠合整体式剪力墙 | |
CN103866866A (zh) | 超高层核心筒与外框架梁后浇节点 | |
CN103397720A (zh) | 建筑用钢管剪力墙 | |
CN111502123A (zh) | 倒插灌浆式预制混凝土柱结构及其施工方法 | |
CN205369709U (zh) | 双面叠合梁 | |
CN207032474U (zh) | 一种装配式混凝土框架结构梁柱刚性连接节点 | |
CN205917992U (zh) | 一种灌浆套筒 | |
CN108589970A (zh) | 预制窗框剪力墙的施工方法 | |
CN108756038A (zh) | 装配式混凝土剪力墙与楼承板刚性连接节点及施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20181012 |