CN108590169A - A kind of urea prilling tower is without derrick hydraulic sliding mould construction method - Google Patents

A kind of urea prilling tower is without derrick hydraulic sliding mould construction method Download PDF

Info

Publication number
CN108590169A
CN108590169A CN201810235025.8A CN201810235025A CN108590169A CN 108590169 A CN108590169 A CN 108590169A CN 201810235025 A CN201810235025 A CN 201810235025A CN 108590169 A CN108590169 A CN 108590169A
Authority
CN
China
Prior art keywords
construction method
template
prilling tower
derrick
urea prilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810235025.8A
Other languages
Chinese (zh)
Inventor
王群伟
鲁礼刚
刘金剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
13th Construction Co Ltdof China National Chemical Engineering
Original Assignee
13th Construction Co Ltdof China National Chemical Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 13th Construction Co Ltdof China National Chemical Engineering filed Critical 13th Construction Co Ltdof China National Chemical Engineering
Priority to CN201810235025.8A priority Critical patent/CN108590169A/en
Publication of CN108590169A publication Critical patent/CN108590169A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • E04G11/24Construction of lifting jacks or climbing rods for sliding forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention provides a kind of urea prilling towers without derrick hydraulic sliding mould construction method, belong to towering cross-section or the reinforced concrete Cylinder wall structure of variable cross-section and the construction method of wall panel structure, the most of operating process of construction all carries out on a continuous upward sliding operating platform, without setting up scaffold, it need to only be prepared by standard flat and rigging can be sliding to top, substantially increase the turnover rate and utilization rate of template, reduce cost, simultaneously instead of the repeated multiple times dismounting of the template of common reassembling type template and reverse mould method, finishing, it carries upwards and assembles the operating process removed again again, reduce the process of cumbersome repetition, mitigate the labor intensity of engineering, accelerate the duration.

Description

A kind of urea prilling tower is without derrick hydraulic sliding mould construction method
Technical field
The invention belongs to towering cross-section or the reinforced concrete Cylinder wall structure of variable cross-section and the construction methods of wall panel structure, more It says to body, is to be related to a kind of urea prilling tower without derrick hydraulic sliding mould construction method.
Background technology
Urea prilling tower has become modular in design in chemical fertilizer industry, and urea prilling tower is adopted extensively in chemical fertilizer production One of tall and big reinforced concrete cylinder shape structures, the bodily form is tall and big, and the method for traditional construction urea prilling tower is led to Frequently with reassembling type template or reverse mould template, and reassembling type template and reverse mould template need repeated multiple times tear open when in use It removes, modify, carrying the operating process for assembling remove again again upwards, working procedure is more, and labor intensity is big;And in building course In, it needs to establish derrick, to increase material consumption, increases construction cost, extend the duration.
Invention content
The purpose of the present invention is to provide a kind of urea prilling towers without derrick hydraulic sliding mould construction method, it is intended to solve tradition Build big, the of high cost and long in time limit problem of urea prilling tower construction labor intensity.
To achieve the above object, the technical solution adopted by the present invention is:A kind of urea prilling tower is applied without derrick hydraulic slip-form Work method, includes the following steps:
S1:Assembly operation platform and template are prepared by construction standard layer plane;
S2:Hydraulic climbing machinery and vertical transportation machinery are installed;
S3:Reinforcing bar is installed;
S4:Pour concrete;
S5:Sliding operating platform and template;
S6:Step S3, S4, S5 are repeated, predetermined altitude is reached.
Further, the operating platform in the step S1 is constituted using radiation beam and steel ring, using diagonal brace and with gug Frame connects, and lower part pull rod is connect with center drum circle.
Further, the template in the step S1 includes the inner and outer template of main cylinder, the inner and outer template of elevator, elevator The profiled template of junction and the typified form of edge.
Further, the hydraulic climbing machinery in the step S2 is hydraulic jack.
Further, the vertical transportation machinery in the step S2 is that the vertical buoyancy lift type derrick of setting on the operational platform is hung Cage hoist engine.
Further, the reinforcing bar in the step S3 is machined molding in advance using ground, transports to operating platform installation Weld spreading.
Further, the concrete in the step S4 is transported to using ground machine stirring and cage on operating platform, after entering mould Machinery vibrates.
Further, the concrete in the step S4 selectes concrete proportioning according to the temperature at that time in concrete engineering location.
Further, operating platform and the sliding of template use hydraulic jack promotion and leveling in the step S5.
Further, the number of repetition of step S3, S4, S5 in the step S6, is equal to design height and single is sliding The ratio of height subtracts once, and the integer into one is taken when ratio is not integer.
A kind of advantageous effect of the urea prilling tower provided by the invention without derrick hydraulic sliding mould construction method is:With it is existing Technology is compared, and a kind of urea prilling tower provided by the invention is without derrick hydraulic sliding mould construction method, most of operating process of constructing It is all carried out on a continuous upward sliding operating platform, without setting up scaffold, only need to be prepared and be assembled by standard flat Template sliding can substantially increase the turnover rate and utilization rate of template to top, reduce cost, while instead of common dismounting The repeated multiple times dismounting of the template of formula template and reverse mould method, finishing, carrying assembles the operating process removed again again upwards, reduces The process of cumbersome repetition mitigates the labor intensity of engineering, accelerates the duration.
Description of the drawings
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art Needed in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description be only the present invention some Embodiment for those of ordinary skill in the art without having to pay creative labor, can also be according to these Attached drawing obtains other attached drawings.
Fig. 1 is a kind of flow chart of the urea prilling tower without derrick hydraulic sliding mould construction method provided in an embodiment of the present invention.
Specific implementation mode
In being described below, for illustration and not for limitation, it is proposed that such as tool of particular system structure, technology etc Body details, to understand thoroughly the embodiment of the present invention.However, it will be clear to one skilled in the art that there is no these specific The present invention can also be realized in the other embodiments of details.In other situations, it omits to well-known system, device, electricity The detailed description of road and method, in case unnecessary details interferes description of the invention.
It should be appreciated that ought use in this specification and in the appended claims, term " comprising " and "comprising" instruction Described feature, entirety, step, operation, the presence of element and/or component, but one or more of the other feature, whole is not precluded Body, step, operation, element, component and/or its presence or addition gathered.
It is also understood that the term used in this description of the invention is merely for the sake of the mesh for describing specific embodiment And be not intended to limit the present invention.As description of the invention and it is used in the attached claims, unless on Other situations are hereafter clearly indicated, otherwise " one " of singulative, "one" and "the" are intended to include plural form.
It will be further appreciated that the term "and/or" used in description of the invention and the appended claims is Refer to any combinations and all possible combinations of one or more of associated item listed, and includes these combinations.
As used in this specification and in the appended claims, term " if " can be according to context quilt Be construed to " when ... " or " once " or " in response to determination " or " in response to detecting ".Similarly, phrase " if it is determined that " or " if detecting [described condition or event] " can be interpreted to mean according to context " once it is determined that " or " in response to true It is fixed " or " once detecting [described condition or event] " or " in response to detecting [described condition or event] ".
With reference to figure 1, Fig. 1 is a kind of urea prilling tower provided in an embodiment of the present invention without derrick hydraulic sliding mould construction method Flow chart now illustrates a kind of urea prilling tower provided by the invention without derrick hydraulic sliding mould construction method, including following Step:
S1:Assembly operation platform and template are prepared by construction standard layer plane;
S2:Hydraulic climbing machinery and vertical transportation machinery are installed;
S3:Reinforcing bar is installed;
S4:Pour concrete;
S5:Sliding operating platform and template;
S6:Step S3, S4, S5 are repeated, preset height is reached.
A kind of advantageous effect of the urea prilling tower provided by the invention without derrick hydraulic sliding mould construction method is:With it is existing Technology is compared, and a kind of urea prilling tower that patent of the present invention provides is without derrick hydraulic sliding mould construction method, most of operation of constructing Process all carries out on a continuous sliding operating platform upwards, without setting up scaffold, need to only be prepared by standard flat and Rigging can be sliding to top, substantially increases the turnover rate and utilization rate of template, reduces cost, while instead of common The repeated multiple times dismounting of the template of reassembling type template and reverse mould method, finishing, the operation carried to assemble again upwards and removed again ... Journey reduces the process of cumbersome repetition, mitigates the labor intensity of engineering.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the operating platform in step S1 are constituted using radiation beam and steel ring, are connect with gug frame using diagonal brace, lower part It is connect with center drum circle with pull rod, to constitute the rigid platfor of an entirety, the present embodiment is using 60 radiation Liang Ji tri- Steel ring constitutes platform, is connect with gug frame using 8 diagonal braces, and lower part is connect with 120 pull rods with center drum circle, and diagonal brace is selected The steel pipe of Φ 108mm, pull rod use I grade of reinforcing bar of diameter of phi 20mm, according to the size and stressing conditions of platform, can adjust each connection The parameters such as quantity, diameter and its model of component, to ensure the stability of operating platform.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the template in step S1 include the inner and outer template of main cylinder, the inner and outer template of elevator, elevator junction it is different The typified form of shape template and edge, various forms of templates need to carry out stringent assembling, and template assemblies will be according to mould Plate matching board figure size assembly is integral, when template is assembled at the scene, to control piece between adjacent plate face, two plate connectors are wanted Clamp is added, with mortar leakage prevention, template and vertical steel pipe are bound securely, to keep the globality of template with steel wire after the completion of assembled Template assemblies are integral in strict accordance with formwork collocation figure size assembly, when template is assembled at the scene, to control adjacent plate face Between piece, two plate connectors will add clamp, and with mortar leakage prevention, with steel wire template and vertical steel pipe jail is bound after the completion of assembled Gu to keep the globality of template.
Assembled required precision is as follows:
1, piece≤1 between two pieces of templates;
2, difference of height≤1 between adjacent forms;
3, template flatness≤2;
4, stencil plane dimensional discrepancy ± 3.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the hydraulic climbing machinery in step S2 are hydraulic jack, and hydraulic jack is provided with number of units and regards actual conditions Depending on, include additionally the high pressure steel wire spiral rubber hose of connection hydraulic control panel and more hydraulic jacks, and be arranged in high pressure The valve for controlling the opening and closing of high pressure steel wire spiral rubber hose on wire spirally-wound hose, hydraulic control panel control valve are opened High pressure steel wire spiral rubber hose is opened and closed, and then controls the working condition of hydraulic jack.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the vertical transportation machinery in step S2 are that the vertical buoyancy lift type derrick of setting on the operational platform hangs cage elevator Machine, including bitubular double-speed winch, slow-motion hoist and fast winch etc., according to different device to promoted speed standard and Safety requirements is realized by bitubular double-speed winch collocation slow-motion hoist or fast winch.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the reinforcing bar in step S3 are machined molding in advance using ground, according to design requirement by reinforcing bar on the ground Machine-shaping is completed, the reinforcing bar for completing machine-shaping needs to transport on operating platform, but longer reinforcing bar handling is cumbersome, especially When it is higher for operating platform position, the difficulty of handling reinforcing bar will be more big, therefore need to be segmented reinforcing bar on the ground And be marked, then handling, after the reinforcing bar after segmentation is hoisted to operating platform, mark the reinforcing bar that matches by connecting tube with Reinforcing bar is welded, so that reinforcing bar meets design requirement.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the concrete in step S4 are transported to using ground machine stirring and cage on operating platform, and machinery vibrates after entering mould, machine Tool vibrates using plug-in type vibrating, and immersion vibrator is inserted perpendicularly into the concrete after the completion of stirring, it is not yet pre-hardening to be inserted into lower layer Concrete in 50-100mm insert determinant (it is rectangular to insert the neat arrangement of point) is distributed with and handing over for point to promote levels to combine Wrong two kinds of formula (it is rectangular to insert dot interlace arrangement) inserts point spacing to ordinary concrete and is not more than 1.5R (R is vibrator operating radius), right Light aggregate concrete is then not more than 1.0R.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the concrete in step S4 needs the temperature at that time according to concrete engineering location, and rationally correctly selected concrete is matched Than so that concrete setting time be adapted with sliding speed, avoid because concrete condensation is too fast or it is excessively slow due to cause concrete to bond template, concrete quilt Drawing crack or the accident that concrete slump occurs want the levelness of frequent close inspection and the sliding platform of control and central axis degree inclined Difference accomplishes that regular check is corrected in time, when it is sliding during mold plate verticality it is moderate in by state of a control.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, when meeting the cross members such as crossbeam, bracket, floor during template sliding lifting in step S5, using preformed hole Hole, embedded iron parts, pre- doweling, after depanning with the construction of aerial suspension formwork method meet during template sliding lifting crossbeam, bracket, When the cross members such as floor, using reserving hole, embedded iron parts, pre- doweling, constructed with aerial suspension formwork method after depanning, behaviour Make platform and the sliding of template wants real-time monitoring center's perpendicularity deviation simultaneously using hydraulic jack promotion and leveling, operating platform Central perpendicularity deviation is corrected at any time, the sliding central perpendicularity deviation of operating platform is monitored using big plumb bob and the quasi- instrument of light, The sliding central perpendicularity bias correction of operating platform pours the method that starting point is combined using platform inclination method and change concrete and carries out It corrects.
Further, as a kind of a kind of tool of the urea prilling tower without derrick hydraulic sliding mould construction method provided by the invention Body embodiment, the number of repetition of step S3, S4, S5 in step S6 determine according to the sliding height of single and design height, if Meter height is H, and the sliding height of single is h, and sliding frequency n is H/h-1, that is, the number for needing to repeat step S3, S4, S5 is H/h- 1 time.
For the urea prilling tower without derrick hydraulic sliding mould construction method, most of operating process of constructing is all continuous upward at one It is carried out on sliding operating platform, the whole load of operating platform is born by the reinforcing bar in structure, so how high no matter construct Reinforced concrete structure need not set up scaffold, realize High-rise Reinforced Concrete engineering construction without scaffold operation;The carbamide granulation Tower without derrick hydraulic sliding mould construction method, on sliding power using operate steadily, it is noiseless and vibration hydraulic elevator Tool realizes reinforced concrete engineering construction serialization and high mechanization;The urea prilling tower without derrick hydraulic sliding mould construction method, No matter construct how high structure, only need to by standard flat prepare and assemble one section of (normally only 1M~1.5M high) template can slide It is raised to top, thus substantially increases the turnover rate and utilization rate of template, due to sliding instead of common reassembling type upwards with template The repeated multiple times dismounting of the template of template and reverse mould method, finishing, the operating process carried to assemble again upwards and removed again ..., to The labor intensity for significantly reducing form work engineering, has been greatly reduced form work engineering labour expenditure, and work efficiency increases substantially;The urine Plain granulation tower without derrick hydraulic sliding mould construction method materials in construction horizontal transport, vertical transport, concrete pour, operating platform and Template sliding equal mechanization upwards, thus the high short time limit of work efficiency, according to statistics, under normal temperature per round the clock averagely can sliding 3M~ 4M high, if temperature is higher, labour rationalization is even every round the clock can sliding 4M~5M high;The urea prilling tower is without derrick liquid It presses slding form operation method generally suitable in towering cross-section or the reinforced concrete Cylinder wall structure and wall panel structure of variable cross-section, is one fast Speed, efficient construction method.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement etc., should all be included in the protection scope of the present invention made by within refreshing and principle.

Claims (10)

1. a kind of urea prilling tower is without derrick hydraulic sliding mould construction method, which is characterized in that include the following steps:
S1:Assembly operation platform and template are prepared by construction standard layer plane;
S2:Hydraulic climbing machinery and vertical transportation machinery are installed;
S3:Reinforcing bar is installed;
S4:Pour concrete;
S5:Sliding operating platform and template;
S6:Step S3, S4, S5 are repeated, preset height is reached.
2. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Operating platform in rapid S1 is constituted using radiation beam and steel ring, is connect with gug frame using diagonal brace, lower part pull rod and center Drum circle connects.
3. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Template in rapid S1 includes the inner and outer template of main cylinder, the inner and outer template of elevator, the profiled template of elevator junction and side Typified form at angle.
4. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Hydraulic climbing machinery in rapid S2 is hydraulic jack.
5. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Vertical transportation machinery in rapid S2 is that the vertical buoyancy lift type derrick of setting on the operational platform hangs cage hoist engine.
6. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Reinforcing bar in rapid S3 is machined molding in advance using ground, transports to operating platform erecting and welding spreading.
7. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Concrete in rapid S4 is transported to using ground machine stirring and cage on operating platform, and machinery vibrates after entering mould.
8. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Concrete in rapid S4 selectes concrete proportioning according to the temperature at that time in concrete engineering location.
9. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:The step Operating platform and the sliding of template use hydraulic jack promotion and leveling in rapid S5.
10. a kind of urea prilling tower as described in claim 1 is without derrick hydraulic sliding mould construction method, it is characterised in that:It is described The ratio that the number of repetition of step S3, S4, S5 in step S6 are equal to design height and the sliding height of single subtracts once, when than Value takes the integer into one when not being integer.
CN201810235025.8A 2018-03-21 2018-03-21 A kind of urea prilling tower is without derrick hydraulic sliding mould construction method Pending CN108590169A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810235025.8A CN108590169A (en) 2018-03-21 2018-03-21 A kind of urea prilling tower is without derrick hydraulic sliding mould construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810235025.8A CN108590169A (en) 2018-03-21 2018-03-21 A kind of urea prilling tower is without derrick hydraulic sliding mould construction method

Publications (1)

Publication Number Publication Date
CN108590169A true CN108590169A (en) 2018-09-28

Family

ID=63627135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810235025.8A Pending CN108590169A (en) 2018-03-21 2018-03-21 A kind of urea prilling tower is without derrick hydraulic sliding mould construction method

Country Status (1)

Country Link
CN (1) CN108590169A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088582A (en) * 2016-07-08 2016-11-09 广州市第四建筑工程有限公司 Slip form platform and be applied to armored concrete cylinder slding form operation method
CN206128607U (en) * 2016-08-22 2017-04-26 中国化学工程第十三建设有限公司 Lifting platform device of chimney derrick
CN107687254A (en) * 2017-09-30 2018-02-13 五冶集团上海有限公司 A kind of concrete disjunctor group storehouse slip form construction device and construction method
CN207048306U (en) * 2017-07-14 2018-02-27 陕西煤业化工建设(集团)有限公司 Sliding formwork flexibility platform
CN107795122A (en) * 2017-11-21 2018-03-13 中国十九冶集团有限公司南京分公司 Concrete stack shell constructing device and construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088582A (en) * 2016-07-08 2016-11-09 广州市第四建筑工程有限公司 Slip form platform and be applied to armored concrete cylinder slding form operation method
CN206128607U (en) * 2016-08-22 2017-04-26 中国化学工程第十三建设有限公司 Lifting platform device of chimney derrick
CN207048306U (en) * 2017-07-14 2018-02-27 陕西煤业化工建设(集团)有限公司 Sliding formwork flexibility platform
CN107687254A (en) * 2017-09-30 2018-02-13 五冶集团上海有限公司 A kind of concrete disjunctor group storehouse slip form construction device and construction method
CN107795122A (en) * 2017-11-21 2018-03-13 中国十九冶集团有限公司南京分公司 Concrete stack shell constructing device and construction method

Similar Documents

Publication Publication Date Title
CN100557168C (en) A kind of method for high altitude installation of large span steel truss
CN105464244A (en) Prefabricated integrated shear wall construction method
CN103510702B (en) Steel core concrete column pin type concrete pouring construction method
CN103104091B (en) Sliding mold whole lifting platform and construction method
CN105863275A (en) Construction method for assembly type annular reinforcement buckling concrete shear wall system
CN110761402B (en) Concrete pouring construction method for hysteresis synchronization construction of same floor of building floor slab
CN107313506A (en) Building frame construction and its construction method provided with side bar
CN208965714U (en) A kind of prefabricated piping lane main frame structure of assembly concrete
CN107795122A (en) Concrete stack shell constructing device and construction method
CN112627387A (en) Rib-free type side connection method for prefabricated external wall panel
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN210685444U (en) Quick leveling, mounting and supporting device for prefabricated external wall panel
CN109252656B (en) High-rise building climbing template and assembling, pouring and lifting method
CN108000690A (en) Precast prestressed concrete composite beam production mould, production equipment and production technology
CN103485574A (en) Method for constructing reinforced concrete structure of tower top of prilling tower
CN103061508A (en) Triangular slip form device and construction method for the same triangular slip form
CN110616706B (en) Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole
CN109487827B (en) Modular processing and binding method for comprehensive pipe gallery steel reinforcement framework
CN217758964U (en) Basement outer wall post-cast strip closed structure
CN108590169A (en) A kind of urea prilling tower is without derrick hydraulic sliding mould construction method
CN207160217U (en) Building frame construction provided with side bar
CN110512776B (en) Construction method of assembled steel structure multi-cavity steel plate composite shear wall
CN210947710U (en) Synchronous sliding mode system for multiple special-shaped cabin bodies of underground shaft
CN210152143U (en) A connection structure for concrete cladding panel hoist and mount construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928