CN108560701A - Fabricated construction system - Google Patents

Fabricated construction system Download PDF

Info

Publication number
CN108560701A
CN108560701A CN201810738891.9A CN201810738891A CN108560701A CN 108560701 A CN108560701 A CN 108560701A CN 201810738891 A CN201810738891 A CN 201810738891A CN 108560701 A CN108560701 A CN 108560701A
Authority
CN
China
Prior art keywords
column
prefabricated
reinforcement
reinforcement cage
primary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810738891.9A
Other languages
Chinese (zh)
Inventor
陈�光
马云飞
杨逸
李青山
司建超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang 31 Architectural Design Research Co Ltd
Original Assignee
Shenyang 31 Architectural Design Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang 31 Architectural Design Research Co Ltd filed Critical Shenyang 31 Architectural Design Research Co Ltd
Priority to CN201810738891.9A priority Critical patent/CN108560701A/en
Publication of CN108560701A publication Critical patent/CN108560701A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional [3D] framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to fabricated construction system technical field, more particularly to a kind of fabricated construction system.In the fabricated construction system, prefabricated post, precast main beam and prefabricated secondary beam are including steel reinforcement cage and the shell being wrapped in outside steel reinforcement cage, after each prefabricated components lift positioning as requested, formwork at steel reinforcement cage can be connected in the column between the fraction region of needs such as upper layer prefabricated post and lower layer's prefabricated post, then complete whole live pouring construction concrete.Shell may act as template, without being respectively provided with a large amount of templates at prefabricated post, precast main beam and prefabricated secondary beam, then can greatly reduce branch modulus, to make construction is simple, construction efficiency is high, and integrality performance of the structure is good.Live reinforcing bar binding work amount greatly reduces, and working procedure is simple, so as to improve construction efficiency, saves duration and construction cost.

Description

装配式结构体系Assembled structure system

技术领域technical field

本发明涉及装配式结构体系技术领域,特别涉及一种装配式结构体系。The invention relates to the technical field of assembled structural systems, in particular to an assembled structural system.

背景技术Background technique

国家推进建筑工业化发展和建筑行业转型升级的重要措施之一是推动建筑结构体系、建筑设计、部品构配件等方面的关键技术研究与应用。装配式建筑是指用预制的构件在工地装配而成的建筑。这种建筑的优点是建造速度快,受气候条件制约小,节约劳动力并可提高建筑质量。One of the important measures for the country to promote the development of construction industrialization and the transformation and upgrading of the construction industry is to promote the research and application of key technologies in the construction structural system, architectural design, parts and accessories. Prefabricated buildings refer to buildings assembled on site with prefabricated components. The advantage of this kind of building is that the construction speed is fast, it is less restricted by climatic conditions, it saves labor and can improve the construction quality.

目前行业内装配式框架结构存在很多问题:构件质量大,给构件生产、运输、吊装造成很大压力;现场支模量较大;柱节点采用灌浆套筒连接,对构件精度要求高,施工困难,且灌浆质量难以检验;梁柱连接节点处整体性较差、抗震性能差等。At present, there are many problems in the prefabricated frame structure in the industry: the mass of the components is large, which causes great pressure on the production, transportation and hoisting of the components; the on-site modulus is large; the column nodes are connected by grouting sleeves, which requires high precision of the components and difficult construction , and the grouting quality is difficult to inspect; the integrity of the beam-column joints is poor, and the seismic performance is poor.

发明内容Contents of the invention

本发明的目的在于提供一种装配式结构体系,以解决现有技术中的现场支模量大、结构整体性能差、施工效率低的技术问题。The purpose of the present invention is to provide a prefabricated structural system to solve the technical problems in the prior art of large amount of on-site modulus support, poor overall performance of the structure, and low construction efficiency.

本发明提供一种装配式结构体系,包括基础、预制柱以及预制主梁;基础包括基础本体以及设置在基础本体内且伸出基础本体的上端面的基础钢筋;预制柱包括柱钢筋笼以及两端开口的柱外壳,柱外壳包裹在柱钢筋笼的外侧;预制主梁包括主梁钢筋笼以及至少两端开口的主梁外壳,主梁外壳包裹在主梁钢筋笼的外侧;还包括基础连接钢筋;基础连接钢筋的一端与基础钢筋连接,另一端与柱钢筋笼的下端连接;还包括柱连接钢筋笼以及梁柱连接钢筋;梁柱连接钢筋的延伸方向与预制主梁的延伸方向一致,柱连接钢筋笼的一端与柱钢筋笼的上端连接,两个预制主梁一一位于预制柱的上端的两侧,梁柱钢筋穿过柱连接钢筋笼,且一端与一个梁钢筋笼连接,另一端与另一个梁钢筋笼连接;预制柱竖直设置,预制梁水平设置;预制柱的内腔、预制主梁的内腔、基础连接钢筋处以及柱连接钢筋笼均现场浇筑有施工混凝土。The invention provides an assembled structure system, which includes a foundation, a prefabricated column and a prefabricated main beam; the foundation includes a foundation body and foundation steel bars arranged in the foundation body and protruding from the upper end surface of the foundation body; the prefabricated column includes a column reinforcement cage and two The column casing with open ends, the column casing is wrapped on the outside of the column reinforcement cage; the prefabricated main beam includes the main beam reinforcement cage and the main beam casing with openings at least at both ends, and the main beam casing is wrapped on the outside of the main beam reinforcement cage; it also includes the foundation connection Steel bars; one end of the foundation connection reinforcement is connected to the foundation reinforcement, and the other end is connected to the lower end of the column reinforcement cage; it also includes the column connection reinforcement cage and the beam-column connection reinforcement; the extension direction of the beam-column connection reinforcement is consistent with the extension direction of the prefabricated main beam, One end of the column connection reinforcement cage is connected to the upper end of the column reinforcement cage. Two prefabricated main beams are located on both sides of the upper end of the prefabricated column. One end is connected to another beam reinforcement cage; the prefabricated column is set vertically, and the prefabricated beam is installed horizontally; the inner cavity of the prefabricated column, the inner cavity of the prefabricated main beam, the foundation connection reinforcement and the column connection reinforcement cage are all poured with construction concrete on site.

进一步地,装配式结构体系还包括延伸方向与预制柱的延伸方向一致的柱连接纵筋;预制柱为多个,多个预制柱由上而下依次设置,处于最底层的预制柱通过基础连接钢筋与基础连接;相邻两个预制柱中,位于上方的为上层预制柱,位于下方的为下层预制柱;每相邻两个预制柱之间均设置有柱连接钢筋笼以及柱连接纵筋,其中,柱连接钢筋笼与下层预制柱的钢筋笼连接,柱连接纵筋的一端与上层预制柱的纵筋连接,另一端插入柱连接钢筋笼并固定;上层预制柱、下层预制柱以及柱连接钢筋笼同时现场浇筑有施工混凝土。Further, the prefabricated structural system also includes column connecting longitudinal reinforcements whose extension direction is consistent with that of the prefabricated columns; there are multiple prefabricated columns, and the prefabricated columns are arranged sequentially from top to bottom, and the prefabricated columns at the bottom are connected through the foundation The reinforcement is connected to the foundation; among the two adjacent prefabricated columns, the upper one is the upper prefabricated column, and the lower one is the lower prefabricated column; between each two adjacent prefabricated columns, there is a column connecting reinforcement cage and column connecting longitudinal reinforcement , wherein, the column connection reinforcement cage is connected with the reinforcement cage of the lower prefabricated column, one end of the column connection longitudinal reinforcement is connected with the longitudinal reinforcement of the upper prefabricated column, and the other end is inserted into the column connection reinforcement cage and fixed; the upper prefabricated column, the lower prefabricated column and the column The reinforcement cage is connected and construction concrete is poured on site at the same time.

进一步地,装配式结构体系还包括第一预制次梁,第一预制次梁包括第一次梁钢筋笼以及至少两端开口的第一次梁外壳,第一次梁外壳包裹在第一次梁钢筋笼的外侧;还包括第一主次梁连接口以及第一主次梁连接纵筋;第一主次梁连接口设置在主梁外壳上的指定位置,第一主次梁连接纵筋的一端插设在第一主次梁连接口内,另一端与第一次梁钢筋笼连接;第一主次梁连接口以及第一预制次梁的内腔同时现场浇筑有施工混凝土。Further, the prefabricated structural system also includes a first prefabricated secondary beam, the first prefabricated secondary beam includes a reinforcement cage of the primary beam and a shell of the primary beam with openings at least at both ends, the shell of the first beam is wrapped around the primary beam The outer side of the reinforcement cage; it also includes the first primary and secondary beam connection port and the first primary and secondary beam connection longitudinal reinforcement; the first primary and secondary beam connection port is set at the specified position on the main beam shell, and the first primary and secondary beam connection longitudinal reinforcement One end is inserted in the connection port of the first primary and secondary beams, and the other end is connected with the reinforcement cage of the primary beam; the connection port of the first primary and secondary beams and the inner cavity of the first prefabricated secondary beam are simultaneously poured with construction concrete on site.

进一步地,装配式结构体系还包括两个第二预制次梁,两个第二预制次梁相对设置在预制主梁的两侧;每个第二预制次梁包括第二次梁钢筋笼以及至少两端开口的第二次梁外壳,第二次梁外壳包裹在第二次梁钢筋笼的外侧;还包括第二主次梁连接口以及第二主次梁连接钢筋;第二主次梁连接口设置在主梁外壳上的指定位置,第二主次梁连接钢筋穿设在第二主次梁连接口内,第二主次梁连接贯通纵筋的一端与一个第二次梁钢筋笼连接,另一端与另一个第二次梁钢筋笼连接;第二主次梁连接口以及预制次梁的内腔同时浇筑有施工混凝土。Further, the prefabricated structural system also includes two second prefabricated secondary beams, and the two second prefabricated secondary beams are oppositely arranged on both sides of the prefabricated main beam; each second prefabricated secondary beam includes a reinforcement cage of the second secondary beam and at least The shell of the second beam with openings at both ends, the shell of the second beam is wrapped on the outside of the steel cage of the second beam; it also includes the connection port of the second primary and secondary beams and the connecting reinforcement of the second primary and secondary beams; the connection of the second primary and secondary beams The mouth is set at the designated position on the shell of the main beam, the connecting reinforcement of the second primary and secondary beams is passed through the connecting opening of the second primary and secondary beams, and one end of the connecting longitudinal reinforcement of the second primary and secondary beams is connected with a reinforcement cage of the second beam, The other end is connected with another second beam reinforcement cage; the second primary beam connection port and the inner cavity of the prefabricated secondary beam are poured with construction concrete at the same time.

进一步地,柱连接钢筋笼与柱钢筋笼一体设置;柱钢筋笼包括柱钢筋网片组以及柱外壳的延伸方向延伸的柱纵筋,柱外壳包裹在钢筋网片组外,柱纵筋设置在钢筋网片组内;柱连接纵筋与柱纵筋一体设置。Further, the column connection reinforcement cage and the column reinforcement cage are integrated; the column reinforcement cage includes a column reinforcement mesh group and column longitudinal reinforcement extending in the extension direction of the column casing, the column casing is wrapped outside the reinforcement mesh group, and the column longitudinal reinforcement is arranged on In the reinforcement mesh group; the longitudinal reinforcement of the column connection and the longitudinal reinforcement of the column are integrated.

进一步地,梁柱连接钢筋包括梁柱连接腰筋;梁柱连接腰筋穿设在柱连接钢筋笼内,且梁柱连接腰筋的一端搭接在一个梁钢筋笼上,另一端搭接在另一个梁钢筋笼上;和/或,梁柱连接钢筋还包括梁柱贯通纵筋;梁柱贯通纵筋穿过柱连接钢筋笼,梁柱贯通纵筋的一端搭接在一个梁钢筋笼的远离柱连接钢筋笼的一端,另一端搭接在另一个梁钢筋笼远离柱连接钢筋笼的一端。Further, the beam-column connection reinforcement includes beam-column connection waist reinforcement; the beam-column connection waist reinforcement is penetrated in the column connection reinforcement cage, and one end of the beam-column connection waist reinforcement is lapped on a beam reinforcement cage, and the other end is lapped on the on another beam reinforcement cage; and/or, the beam-column connecting reinforcement also includes beam-column through longitudinal reinforcement; the beam-column through-through longitudinal reinforcement passes through the column connection reinforcement cage, and one end of the beam-column through-through longitudinal reinforcement is lapped at the end of a beam reinforcement cage One end of the reinforcement cage away from the column connection is lapped at the other end of the beam reinforcement cage away from the column connection reinforcement cage.

进一步地,柱钢筋网片组包括多个沿柱纵筋的延伸方向依次间隔设置的多个柱钢筋网片;每个柱钢筋网片均包括多个柱第一筋以及多个柱第二筋;多个柱第一筋与多个柱第二筋一一交错设置,以形成网格结构;多个柱第一筋的两端均伸出所有柱第二筋外,多个柱第二筋的两端均伸出所有柱第一筋外;柱外壳包括首尾依次连接的柱第一侧板,柱第三侧板,柱第二侧板以及柱第四侧板,多个柱第一筋的第一端均柱第一侧板连接,多个柱第一筋的第二端均与柱第二侧板连接,多个柱第二筋的第一端与柱第三侧板连接,多个柱第二筋的第二端均与柱第四侧板连接。Further, the column reinforcement mesh group includes a plurality of column reinforcement mesh sheets arranged at intervals along the extending direction of the column longitudinal reinforcement; each column reinforcement mesh sheet includes a plurality of column first bars and a plurality of column second bars ; The first ribs of multiple columns and the second ribs of multiple columns are arranged alternately one by one to form a grid structure; both ends of the first ribs of multiple columns extend outside the second ribs of all columns, and the second ribs of multiple columns Both ends of the column protrude from the first ribs of all columns; the column shell includes the first side plate of the column, the third side plate of the column, the second side plate of the column and the fourth side plate of the column, and the first ribs of multiple columns The first end of each column is connected to the first side plate of the column, the second ends of the first ribs of multiple columns are all connected to the second side plate of the column, the first ends of the second ribs of multiple columns are connected to the third side plate of the column, and more The second ends of the second ribs of each column are connected with the fourth side plate of the column.

进一步地,柱第一筋的两端均设置有柱第一凸起,柱第一凸起的截面尺寸大于柱第一筋的截面尺寸;多个柱第二筋的两端均设置有柱第二凸起,柱第二凸起的截面尺寸大于柱第二筋的截面尺寸。Further, both ends of the first rib of the column are provided with a first protrusion of the column, and the cross-sectional size of the first protrusion of the column is larger than the cross-sectional size of the first rib of the column; The second protrusion, the cross-sectional dimension of the second protrusion of the column is larger than the cross-sectional dimension of the second rib of the column.

进一步地,主梁外壳包括依次连接的主梁左侧板、主梁底板以及主梁右侧板;主梁钢筋笼包括主梁钢筋网片组以及连接在主梁钢筋网片组内的主梁纵筋,主梁左侧板连接在主梁钢筋网片组的左外侧,主梁右侧板连接在主梁钢筋网片组的右外侧,主梁底板连接在主梁钢筋网片组的底外侧。Further, the main girder shell includes the left side plate of the main girder, the bottom plate of the main girder and the right side plate of the main girder connected in sequence; For longitudinal reinforcement, the left plate of the main beam is connected to the left outer side of the main beam steel mesh group, the right side plate of the main beam is connected to the right outer side of the main beam steel mesh group, and the main beam bottom plate is connected to the bottom of the main beam steel mesh group outside.

进一步地,主梁钢筋网片包括相对设置的主梁第一筋,以及沿主梁第一筋的延伸方向依次间隔设置的多个主梁第二筋;多个主梁第二筋的左端均伸出一个主梁第一筋,多个主梁第二筋的右端均伸出另一个主梁第一筋;主梁第一筋的下端均伸出所有主梁第二筋;Further, the steel mesh sheet of the main beam includes the first rib of the main beam arranged oppositely, and a plurality of second ribs of the main beam arranged at intervals along the extending direction of the first rib of the main beam; the left ends of the second ribs of the multiple main beam are all The first rib of a main beam protrudes, and the right ends of the second ribs of multiple main beams protrude from the first rib of another main beam; the lower ends of the first ribs of the main beam protrude all the second ribs of the main beam;

多个主梁第二筋的左端均与主梁左侧板连接,多个主梁第二筋的右端均与主梁右侧板连接,两个主梁第一筋的下端均与主梁底板连接;主梁第一筋的下端设置有主梁第一凸起,主梁第一凸起的截面尺寸大于主梁第一筋的截面尺寸。The left ends of the second ribs of multiple main beams are connected with the left side plate of the main beam, the right ends of the second ribs of multiple main beams are connected with the right side plate of the main beam, and the lower ends of the first ribs of the two main beams are connected with the bottom plate of the main beam Connection; the lower end of the first rib of the main beam is provided with a first protrusion of the main beam, and the cross-sectional size of the first protrusion of the main beam is larger than that of the first rib of the main beam.

本发明提供的装配式结构体系中,当各个预制构件按照要求吊装定位后,可在需要的小部分区域例如上层预制柱与下层预制柱之间的柱连接钢筋笼处支模,然后完成整体的现场灌浇施工混凝土。构件外壳即可充当模板,无需预制柱、预制主梁以及预制次梁处均设置大量模板,则能够极大减少支模量,从而使施工简单,施工效率高。预制梁、预制柱及其他预制构件现场整体浇筑,受力合理,综合性能与普通现浇混凝土结构相当,具有安全可靠、简化施工、节约耗材、减少扬尘和建筑垃圾等特点,具有较强的市场竞争力。In the prefabricated structure system provided by the present invention, after each prefabricated component is hoisted and positioned according to the requirements, the formwork can be set up in a small part of the required area, such as the column connection reinforcement cage between the upper prefabricated column and the lower prefabricated column, and then complete the whole Pouring construction concrete on site. The shell of the component can be used as a template, and there is no need to set a large number of templates at the prefabricated columns, prefabricated main beams and prefabricated secondary beams, which can greatly reduce the modulus of support, so that the construction is simple and the construction efficiency is high. Prefabricated beams, prefabricated columns and other prefabricated components are integrally poured on site, with reasonable force, and the comprehensive performance is equivalent to that of ordinary cast-in-place concrete structures. It has the characteristics of safety and reliability, simplified construction, saving consumables, reducing dust and construction waste, and has a strong market Competitiveness.

附图说明Description of drawings

构成本发明的一部分的附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:The drawings constituting a part of the present invention are used to provide a further understanding of the present invention, and the schematic embodiments and descriptions of the present invention are used to explain the present invention, and do not constitute an improper limitation of the present invention. In the attached picture:

图1是根据本发明实施例的装配式结构体系的结构示意图;Fig. 1 is a structural schematic diagram of an assembled structural system according to an embodiment of the present invention;

图2是图1所示的装配式结构体系中预制柱现场浇筑后的结构示意图;Fig. 2 is a structural schematic diagram of the prefabricated column in the prefabricated structural system shown in Fig. 1 after on-site pouring;

图3是图1所示的装配式结构体系中预制主梁现场浇筑后的结构示意图;Fig. 3 is a structural schematic diagram of the prefabricated main girder in the prefabricated structural system shown in Fig. 1 after on-site pouring;

图4是图1所示的装配式结构体系中预制次梁现场浇筑后的结构示意图;Fig. 4 is a structural schematic diagram of the prefabricated secondary beam in the prefabricated structural system shown in Fig. 1 after on-site pouring;

图5是图1所示的装配式结构体系中预制柱与基础的连接节点的结构示意图;Fig. 5 is a structural schematic diagram of the connection node between the prefabricated column and the foundation in the prefabricated structural system shown in Fig. 1;

图6是图1所示的装配式结构体系中上层预制柱与下层预制柱的连接节点的结构示意图;Fig. 6 is a structural schematic diagram of the connection node between the upper prefabricated column and the lower prefabricated column in the prefabricated structural system shown in Fig. 1;

图7a是图1所示的装配式结构体系中预制主梁与第一预制次梁的连接节点的一种结构示意图;Fig. 7a is a structural schematic diagram of the connection node between the prefabricated main girder and the first prefabricated secondary girder in the prefabricated structural system shown in Fig. 1;

图7b是图7a所示的装配式结构体系中预制主梁与第一预制次梁的连接节点的A-A剖面图;Fig. 7b is an A-A sectional view of the connection node between the prefabricated main beam and the first prefabricated secondary beam in the prefabricated structural system shown in Fig. 7a;

图8a是图1所示的装配式结构体系中预制主梁与第一预制次梁的连接节点的另一种结构示意图;Fig. 8a is another structural schematic diagram of the connection node between the prefabricated main beam and the first prefabricated secondary beam in the prefabricated structural system shown in Fig. 1;

图8b是图8a所示的装配式结构体系中预制主梁与第一预制次梁的连接节点的A-A剖面图;Fig. 8b is an A-A sectional view of the connection node between the prefabricated main beam and the first prefabricated secondary beam in the prefabricated structural system shown in Fig. 8a;

图9a是图1所示的装配式结构体系中预制主梁与第一预制次梁的连接节点的又一种结构示意图;Fig. 9a is another structural schematic diagram of the connection node between the prefabricated main girder and the first prefabricated secondary girder in the prefabricated structural system shown in Fig. 1;

图9b是图9a所示的装配式结构体系中预制主梁与第一预制次梁的连接节点的A-A剖面图;Fig. 9b is an A-A sectional view of the connection node between the prefabricated main beam and the first prefabricated secondary beam in the prefabricated structural system shown in Fig. 9a;

图10a是图1所示的装配式结构体系中预制主梁与第二预制次梁的连接节点的一种结构示意图;Fig. 10a is a structural schematic diagram of the connection node between the prefabricated main girder and the second prefabricated secondary girder in the prefabricated structural system shown in Fig. 1;

图10b是图10a所示的装配式结构体系中预制主梁与第二预制次梁的连接节点的A-A剖面图;Fig. 10b is an A-A sectional view of the connection node between the prefabricated main beam and the second prefabricated secondary beam in the prefabricated structural system shown in Fig. 10a;

图11a是图1所示的装配式结构体系中预制主梁与第二预制次梁的连接节点的另一种结构示意图;Fig. 11a is another structural schematic diagram of the connection node between the prefabricated main beam and the second prefabricated secondary beam in the prefabricated structural system shown in Fig. 1;

图11b是图11a所示的装配式结构体系中预制主梁与第二预制次梁的连接节点的A-A剖面图;Figure 11b is an A-A cross-sectional view of the connection node between the prefabricated main beam and the second prefabricated secondary beam in the prefabricated structural system shown in Figure 11a;

图12a是图1所示的装配式结构体系中预制主梁与第二预制次梁的连接节点的又一种结构示意图;Fig. 12a is another structural schematic diagram of the connection node between the prefabricated main girder and the second prefabricated secondary girder in the prefabricated structural system shown in Fig. 1;

图12b是图12a所示的装配式结构体系中预制主梁与第二预制次梁的连接节点的A-A剖面图。Fig. 12b is an AA sectional view of the connection node between the prefabricated main girder and the second prefabricated secondary girder in the prefabricated structural system shown in Fig. 12a.

图中:100-基础;200-预制柱;300-预制主梁;400-预制次梁;500-施工混凝土;In the figure: 100 - foundation; 200 - prefabricated column; 300 - prefabricated main beam; 400 - prefabricated secondary beam; 500 - construction concrete;

210-上层预制柱;220-下层预制柱;21-柱第一侧板;22-柱第二侧板;23-柱第三侧板;24-柱第四侧板;25-柱纵筋;26-柱钢筋网片;261-柱第一筋;262-柱第二筋;263-柱第一凸起;264-柱第二凸起;210-upper prefabricated column; 220-lower prefabricated column; 21-column first side panel; 22-column second side panel; 23-column third side panel; 24-column fourth side panel; 25-column longitudinal reinforcement; 26-column reinforcement mesh; 261-column first reinforcement; 262-column second reinforcement; 263-column first protrusion; 264-column second protrusion;

31-主梁左侧板;32-主梁右侧板;33-主梁底板;34-主梁纵筋;35-主梁钢筋网片;351-主梁第一筋;352-主梁第二筋;353-主梁第一凸起;354-主梁第二凸起;31-left side plate of main beam; 32-right side plate of main beam; 33-bottom plate of main beam; 34-longitudinal reinforcement of main beam; Second rib; 353 - the first protrusion of the main beam; 354 - the second protrusion of the main beam;

410-第一预制次梁;420-第二预制次梁;41-次梁左侧板;42-次梁右侧板;43-次梁底板;44-次梁纵筋;45-次梁钢筋网片;451-次梁第一筋;452-次梁第二筋;453-次梁第一凸起;454-次梁第二凸起;410 - the first prefabricated secondary beam; 420 - the second prefabricated secondary beam; 41 - the left side plate of the secondary beam; 42 - the right side plate of the secondary beam; 43 - the bottom plate of the secondary beam; 44 - the longitudinal reinforcement of the secondary beam; 45 - the reinforcement of the secondary beam Mesh; 451 - the first rib of the secondary beam; 452 - the second rib of the secondary beam; 453 - the first protrusion of the secondary beam; 454 - the second protrusion of the secondary beam;

01-基础连接钢筋;02-柱连接钢筋笼;03-梁柱连接纵筋;04-柱连接纵筋;05-第一主次梁连接纵筋;06-第二主次梁连接贯通纵筋;071-第一主次梁连接插槽;072-第一主次梁连接间隔;073-第一主次梁连接插孔;081-第二主次梁连接插槽;082-第二主次梁连接间隔;083-第二主次梁连接插孔。01 - foundation connection reinforcement; 02 - column connection reinforcement cage; 03 - beam column connection longitudinal reinforcement; 04 - column connection longitudinal reinforcement; 05 - first primary and secondary beam connection longitudinal reinforcement; 06 - second primary and secondary beam connection through longitudinal reinforcement ;071 - the first primary and secondary beam connection slot; 072 - the first primary and secondary beam connection interval; 073 - the first primary and secondary beam connection socket; 081 - the second primary and secondary beam connection slot; 082 - the second primary and secondary beam Beam connection interval; 083 - the second primary and secondary beam connection socket.

具体实施方式Detailed ways

需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本发明。It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and examples.

如图1至图12所示,本发明提供的装配式结构体系至少包括以下构件:基础100、预制柱200、预制主梁300以及预制次梁400。As shown in FIGS. 1 to 12 , the prefabricated structural system provided by the present invention includes at least the following components: a foundation 100 , a prefabricated column 200 , a prefabricated main beam 300 and a prefabricated secondary beam 400 .

如图2所示,预制柱200如下:As shown in Figure 2, the prefabricated columns 200 are as follows:

预制柱200包括柱外壳以及柱钢筋笼,柱外壳包裹在柱钢筋笼的外侧。其中,柱外壳的材质可以为多种,例如:木板、塑料板或者金属板等。The prefabricated column 200 includes a column shell and a column reinforcement cage, and the column shell wraps the outside of the column reinforcement cage. Wherein, the column shell can be made of various materials, such as wood board, plastic board or metal board.

优选地,柱外壳采用混凝土预制而成,即在工厂进行混凝土预制,这样可以与预制柱200到达施工现场后现场浇筑的施工混凝土100成为一体,从而使柱的材质统一,种类少,结构规整。Preferably, the column shell is prefabricated by concrete, that is, the concrete is prefabricated in the factory, so that it can be integrated with the construction concrete 100 poured on site after the prefabricated column 200 arrives at the construction site, so that the material of the column is uniform, the types are less, and the structure is regular.

在上述实施例基础之上,进一步地,柱钢筋笼包括柱纵筋25以及钢筋网片组,柱外壳包裹在柱钢筋网片组的外侧,柱纵筋25设置在柱钢筋网片组内。柱钢筋网片组包括多个柱钢筋网片26,多个柱钢筋网片26沿柱纵筋的延伸方向依次间隔地设置;每个柱钢筋网片26均包括多个柱第一筋261以及多个柱第二筋262;多个柱第一筋261与多个柱第二筋262一一交错设置,以形成网格结构;多个柱第一筋261的两端均伸出所有柱第二筋262外,多个柱第二筋262的两端均伸出所有柱第一筋261外;柱外壳包括首尾依次连接的柱第一侧板21,柱第三侧板23,柱第二侧板22以及柱第四侧板24,多个柱第一筋261的第一端均柱第一侧21板连接,多个柱第一筋261的第二端均与柱第二侧板22连接,多个柱第二筋262的第一端与柱第三侧板23连接,多个柱第二筋262的第二端均与柱第四侧24板连接。On the basis of the above embodiments, further, the column reinforcement cage includes column longitudinal bars 25 and reinforcement mesh groups, the column shell is wrapped outside the column reinforcement mesh groups, and the column longitudinal reinforcement 25 is arranged in the column reinforcement mesh groups. The column reinforcement mesh group includes a plurality of column reinforcement mesh sheets 26, and a plurality of column reinforcement mesh sheets 26 are arranged at intervals successively along the extending direction of the column longitudinal reinforcement; each column reinforcement mesh sheet 26 includes a plurality of column first ribs 261 and A plurality of column second ribs 262; a plurality of column first ribs 261 and a plurality of column second ribs 262 are alternately arranged to form a grid structure; both ends of the plurality of column first ribs 261 protrude from all column second ribs Outside the second rib 262, the two ends of the second rib 262 of a plurality of columns all extend outside the first rib 261 of all columns; The side plate 22 and the fourth side plate 24 of the column, the first ends of the first ribs 261 of the plurality of columns are all connected to the first side 21 of the column, and the second ends of the first ribs 261 of the plurality of columns are connected with the second side plate 22 of the column. Connection, the first ends of the plurality of second ribs 262 of the column are connected with the third side plate 23 of the column, and the second ends of the second ribs 262 of the plurality of columns are all connected with the plate of the fourth side 24 of the column.

本实施例中,柱外壳以及柱纵筋通过柱钢筋网片组隔离开来,在现场浇筑施工时,柱外壳能够起到模板作用,简化了施工步骤,提高了施工效率。预制柱采用壳体的形式,整体重量轻,方便运输和吊装。In this embodiment, the column shell and the column longitudinal reinforcement are separated by the column reinforcement mesh group, and the column shell can serve as a formwork during on-site pouring construction, which simplifies the construction steps and improves the construction efficiency. The prefabricated column is in the form of a shell, and the overall weight is light, which is convenient for transportation and hoisting.

本实施例中,通过柱钢筋网片的端部实现与柱壳体的连接,简单方便易施工,从而节省大量钢材,无需折弯绑固,适合批量生产,工业化程度高。In this embodiment, the connection with the column shell is realized through the end of the column reinforcement mesh, which is simple, convenient and easy to construct, thereby saving a large amount of steel, without bending and binding, suitable for mass production, and has a high degree of industrialization.

在上述实施例基础之上,进一步地,柱第一筋的两端均设置有柱第一凸起263,柱第一凸起263的截面尺寸大于柱第一筋的截面尺寸。多个柱第二筋的两端均设置有柱第二凸起264,柱第二凸起的截面尺寸大于柱第二筋的截面尺寸。On the basis of the above embodiments, further, both ends of the first column ribs are provided with first column protrusions 263 , and the cross-sectional size of the first column protrusions 263 is larger than that of the first column ribs. Both ends of the plurality of column second ribs are provided with column second projections 264, and the cross-sectional size of the second column projections is larger than that of the second column ribs.

其中,柱第一凸起263的结构形式以及柱第二凸起264的结构形式有多种,例如:凸起可以为板状、杆状或者柱状等;当凸起呈杆状时,可以为直杆、曲杆,与筋呈角度设置,凸起上还可以设置多个倒刺或者小突起。Wherein, there are many structural forms of the first post protrusion 263 and the second post protrusion 264, for example: the protrusion can be plate-shaped, rod-shaped or column-shaped, etc.; when the protrusion is rod-shaped, it can be Straight rods and curved rods are arranged at an angle to the ribs, and multiple barbs or small protrusions can also be arranged on the protrusions.

优选地,柱凸起为筋的端部直接墩粗而成,结构简单,方便加工。Preferably, the column protrusion is formed by directly thickening the end of the rib, which has a simple structure and is convenient for processing.

柱第一凸起263以及柱第二凸起264均可以为一个还可以为多个。There can be one or more post first protrusions 263 and post second protrusions 264 .

本实施例中,柱第一凸起263能够提高柱第一筋与柱第一侧板和柱第二侧板的连接强度,尤其是当柱第一侧板21和柱第二侧板22采用混凝土预制时,柱第一凸起263像根须一样伸入混凝土内,柱第一凸起263可以提高柱第一筋与柱第一侧板和柱第二侧板的锚固力,从而使两者的更加牢固,进而使后期灌浇施工混凝土更加方便。In this embodiment, the first protrusion 263 of the column can improve the connection strength between the first rib of the column and the first side plate of the column and the second side plate of the column, especially when the first side plate 21 of the column and the second side plate 22 of the column adopt When the concrete is prefabricated, the first protrusion 263 of the column extends into the concrete like a root, and the first protrusion 263 of the column can improve the anchoring force between the first tendon of the column and the first side plate of the column and the second side plate of the column, so that the two The concrete is more firm, which makes it more convenient to pour the concrete in the later stage.

柱第二凸起能够提高柱第二筋与柱第三侧板和柱第四侧板的连接强度,尤其是当柱第三侧板和柱第四侧板采用混凝土预制时,柱第二凸起像根须一样伸入混凝土内,柱第二凸起264可以提高柱第二筋与柱第三侧板和柱第四侧板的锚固力,从而使两者的更加牢固,进而使后期灌浇施工混凝土更加方便。The second protrusion of the column can improve the connection strength between the second reinforcement of the column and the third side plate of the column and the fourth side plate of the column, especially when the third side plate of the column and the fourth side plate of the column are prefabricated with concrete, the second protrusion of the column Like roots extending into the concrete, the second protrusion 264 of the column can increase the anchoring force between the second bar of the column and the third side plate of the column and the fourth side plate of the column, thereby making the two more firm, and then making the later pouring Pouring construction concrete is more convenient.

预制柱200为多个,多个预制柱200由上而下依次设置,处于最底层的预制柱200通过基础连接钢筋01与基础100连接;相邻两个预制柱200中,位于上方的为上层预制柱,位于下方的为下层预制柱。There are a plurality of prefabricated columns 200, and the plurality of prefabricated columns 200 are arranged sequentially from top to bottom. The prefabricated column 200 at the bottom is connected to the foundation 100 through the foundation connecting steel bar 01; among the two adjacent prefabricated columns 200, the upper one is the upper layer Prefabricated columns, the lower ones are the lower prefabricated columns.

如图3所示,预制主梁如下:As shown in Figure 3, the prefabricated main girder is as follows:

预制主梁包括主梁外壳以及主梁钢筋笼;主梁外壳包裹在主梁钢筋笼外侧。其中,主梁外壳的材质可以为多种,例如:木板、塑料板或者金属板等。The prefabricated main girder includes the main girder shell and the main girder reinforcement cage; the main girder shell is wrapped on the outside of the main girder reinforcement cage. Wherein, the main girder shell can be made of various materials, such as wood board, plastic board or metal board.

优选地,采用混凝土预制而成,即在工厂进行混凝土预制,这样可以与预制主梁到达施工现场后现场浇筑的施工混凝土成为一体,从而使梁的材质统一,种类少,结构规整。Preferably, the concrete is prefabricated, that is, the concrete is prefabricated in the factory, so that it can be integrated with the construction concrete poured on site after the prefabricated main beam arrives at the construction site, so that the beam has uniform material, fewer types, and regular structure.

主梁外壳包括依次连接的主梁左侧板31、主梁底板33以及主梁右侧板32;主梁钢筋笼包括主梁钢筋网片组以及连接在主梁钢筋网片组内的主梁纵筋34,主梁左侧板连接在主梁钢筋网片组的左外侧,主梁右侧板连接在主梁钢筋网片组的右外侧,主梁底板连接在主梁钢筋网片组的底外侧。The shell of the main girder includes the left side plate 31 of the main girder, the bottom plate 33 of the main girder and the right side plate 32 of the main girder connected in sequence; The longitudinal reinforcement is 34, the left plate of the main beam is connected to the left outer side of the main beam steel mesh group, the right side plate of the main beam is connected to the right outer side of the main beam steel mesh group, and the main beam bottom plate is connected to the main beam steel mesh group Bottom outside.

本实施例中,主梁外壳以及主梁纵筋34通过主梁钢筋网片组隔离开来,在现场浇筑施工时,主梁外壳能够起到模板作用,简化了施工步骤,提高了施工效率。预制主梁采用壳体的形式,整体重量轻,方便运输和吊装。In this embodiment, the main girder shell and the main girder longitudinal reinforcement 34 are separated by the main girder reinforcement mesh group. During on-site pouring construction, the main girder shell can serve as a formwork, which simplifies the construction steps and improves the construction efficiency. The prefabricated main girder is in the form of a shell, and the overall weight is light, which is convenient for transportation and hoisting.

在上述实施例基础之上,进一步地,主梁钢筋网片组包括沿主梁纵筋方向依次间隔设置的多个主梁钢筋网片35;主梁钢筋网片包括相对设置的主梁第一筋351,以及沿主梁第一筋的延伸方向依次间隔设置的多个主梁第二筋352;多个主梁第二筋352的左端均伸出一个主梁第一筋351,多个主梁第二筋352的右端均伸出另一个主梁第一筋351;主梁第一筋351的下端均伸出所有主梁第二筋352;多个主梁第二筋352的左端均与主梁左侧板连接,多个主梁第二筋352的右端均与主梁右侧板连接,两个主梁第一筋的下端均与主梁底板连接。On the basis of the above-mentioned embodiments, further, the main girder reinforcement mesh group includes a plurality of main girder reinforcement mesh sheets 35 arranged at intervals along the direction of the main girder longitudinal bars; Rib 351, and a plurality of main beam second ribs 352 arranged at intervals along the extending direction of the first main beam; the left ends of the plurality of main beam second ribs 352 all stretch out a main beam first rib 351, and a plurality of main beam second ribs 352 extend out from each other. The right end of beam second rib 352 all stretches out another main beam first rib 351; The lower end of main beam first rib 351 all stretches out all main beam second ribs 352; The left side plate of the main beam is connected, the right ends of the second ribs 352 of the main beam are connected with the right side plate of the main beam, and the lower ends of the first ribs of the two main beams are connected with the bottom plate of the main beam.

本实施例中,通过主梁钢筋网片35的端部实现与主梁外壳的连接,简单方便易施工,从而节省大量钢材,无需折弯绑固,适合批量生产,工业化程度高。In this embodiment, the connection to the shell of the main beam is realized through the end of the steel mesh sheet 35 of the main beam, which is simple, convenient and easy to construct, thereby saving a large amount of steel, without bending and binding, suitable for mass production, and has a high degree of industrialization.

在上述实施例基础之上,进一步地,主梁第一筋351的下端设置有主梁第一凸起353,主梁第一凸起353的截面尺寸大于主梁第一筋的截面尺寸。多个主梁第二筋的左端以及右端均设置有主梁第二凸起354,主梁第二凸起354的截面尺寸大于主梁第二筋的截面尺寸。On the basis of the above embodiments, further, the lower end of the first rib 351 of the main beam is provided with a first protrusion 353 of the main beam, and the cross-sectional size of the first protrusion 353 of the main beam is larger than that of the first rib of the main beam. The left and right ends of the plurality of second ribs of the main beam are provided with second protrusions 354 of the main beam, and the cross-sectional size of the second protrusions 354 of the main beam is larger than that of the second ribs of the main beam.

其中,主梁第一凸起353以及主梁第二凸起354的结构形式有多种,例如:可以为板状、杆状或者柱状等;当主梁第一凸起或者主梁第二凸起呈杆状时,可以为直杆、曲杆,与筋呈角度设置,主梁第一凸起或者主梁第二凸起上还可以设置多个倒刺或者小突起;又或者主梁第一凸起为第一筋的下端头直接墩粗而成。Wherein, the structural forms of the first protrusion 353 of the main beam and the second protrusion 354 of the main beam are various, for example: they can be plate-shaped, rod-shaped or column-shaped; when the first protrusion of the main beam or the second protrusion of the main beam When it is in the shape of a rod, it can be a straight rod or a curved rod, which is set at an angle to the ribs, and a plurality of barbs or small protrusions can also be arranged on the first protrusion of the main beam or the second protrusion of the main beam; or the first protrusion of the main beam The bulge is directly formed by piering the lower end of the first rib.

优选地,主梁第二凸起为第二筋的端部直接墩粗而成,结构简单,方便加工。进一步地,主梁第一凸起与主梁第一筋呈T字型,主梁第二凸起与主梁第二筋呈T字型结构简单。Preferably, the second protrusion of the main girder is directly thickened from the end of the second rib, which has a simple structure and is convenient for processing. Further, the first protrusion of the main beam and the first rib of the main beam form a T-shape, and the second protrusion of the main beam and the second rib of the main beam form a T-shape, which is simple in structure.

主梁第一凸起以及主梁第二凸起均可以为一个还可以为多个。There can be one or more main beam first protrusions and main beam second protrusions.

本实施例中,主梁第一凸起能够提高主梁第一筋与主梁底板连接的强度,主梁第二凸起能够提高主梁第二筋与主梁侧板连接的强度,尤其是当主梁外壳采用混凝土预制时,主梁第一凸起和主梁第二凸起像根须一样伸入混凝土内,从而提高主梁钢筋网片组与混凝土的锚固力,从而使两者的更加牢固,进而使后期灌浇施工混凝土更加方便。In this embodiment, the first protrusion of the main beam can increase the strength of the connection between the first rib of the main beam and the bottom plate of the main beam, and the second protrusion of the main beam can increase the strength of the connection between the second rib of the main beam and the side plate of the main beam, especially When the shell of the main beam is prefabricated with concrete, the first protrusion of the main beam and the second protrusion of the main beam extend into the concrete like roots, thereby increasing the anchoring force between the steel mesh group of the main beam and the concrete, so that the two are more It is firm, which makes it more convenient to pour concrete in the later stage.

如图4所示,预制次梁如下:As shown in Figure 4, the prefabricated secondary beams are as follows:

预制次梁包括次梁外壳以及次梁钢筋笼;主梁钢筋笼包括主梁钢筋网片组以及连接在主梁钢筋网片组内的主梁纵筋34,次梁外壳包括依次连接的次梁左侧板41、次梁底板43以及次梁右侧板42。The prefabricated secondary beam includes the secondary beam shell and the secondary beam reinforcement cage; the main beam reinforcement cage includes the main beam reinforcement mesh group and the main beam longitudinal reinforcement 34 connected in the main beam reinforcement mesh group, and the secondary beam casing includes the sequentially connected secondary beams The left side plate 41 , the secondary beam bottom plate 43 and the secondary beam right side plate 42 .

次梁钢筋网片组包括沿次梁纵筋方向依次间隔设置的多个次梁钢筋网片45;次梁钢筋网片包括相对设置的次梁第一筋451,以及沿次梁第一筋451的延伸方向依次间隔设置的多个次梁第二筋452;多个次梁第二筋452的左端均伸出一个次梁第一筋451,多个次梁第二筋452的右端均伸出另一个次梁第一筋451;次梁第一筋451的下端均伸出所有次梁第二筋452;多个次梁第二筋的左端均与次梁左侧板连接,多个次梁第二筋的右端均与次梁右侧板连接,两个次梁第一筋的下端均与次梁底板连接。The secondary beam reinforcement mesh group includes a plurality of secondary beam reinforcement mesh sheets 45 arranged at intervals along the longitudinal reinforcement direction of the secondary beam; A plurality of secondary beam second ribs 452 arranged at intervals in the direction of extension; the left ends of the plurality of secondary beam second ribs 452 stretch out a secondary beam first rib 451, and the right ends of a plurality of secondary beam second ribs 452 stretch out The first rib 451 of another secondary beam; the lower end of the first rib 451 of the secondary beam all stretches out the second rib 452 of all secondary beams; The right end of the second rib is connected with the right side plate of the secondary beam, and the lower ends of the first ribs of the two secondary beams are connected with the bottom plate of the secondary beam.

次梁第一筋的下端设置有次梁第一凸起453,次梁一凸起453的截面尺寸大于次梁第一筋的截面尺寸。多个次梁第二筋的左端以及右端均设置有次梁第二凸起454,次梁第二凸起454的截面尺寸大于次梁第二筋的截面尺寸。The lower end of the first rib of the secondary beam is provided with a first protrusion 453 of the secondary beam, and the cross-sectional size of the first protrusion 453 of the secondary beam is larger than that of the first rib of the secondary beam. The left end and the right end of the plurality of secondary beam second ribs are provided with secondary beam second protrusions 454 , and the cross-sectional size of the secondary beam second protrusions 454 is larger than the cross-sectional size of the secondary beam second ribs.

预制次梁中的各个结构可以与预制主梁中的各个结构相同设置,结构统一方便生产,如上所述,在此不再赘述。Each structure in the prefabricated secondary girder can be set in the same way as each structure in the prefabricated main girder, and the structure is unified to facilitate production. As mentioned above, details will not be repeated here.

根据预制次梁与预制主梁连接形式不同,预制次梁可以分为第一预制次梁410和第二预制次梁420,第一预制次梁410的端部与预制主梁连接,能够形成丁字型;两个第二预制次梁420的一端分别于预制主梁连接,两个预制次梁分别位于预制主梁相对侧。According to the different connection forms between the prefabricated secondary beam and the prefabricated main beam, the prefabricated secondary beam can be divided into a first prefabricated secondary beam 410 and a second prefabricated secondary beam 420, and the end of the first prefabricated secondary beam 410 is connected with the prefabricated main beam to form a T type; one ends of the two second prefabricated secondary beams 420 are respectively connected to the prefabricated main beam, and the two prefabricated secondary beams are respectively located on opposite sides of the prefabricated main beam.

将预制主梁、预制次梁以及预制柱200运至施工现场后,After transporting the prefabricated main beam, prefabricated secondary beam and prefabricated column 200 to the construction site,

可以按照如下步骤进行施工:Construction can be carried out as follows:

第一步:如图5所示,放线,基础定位,现场灌浇形成基础100;基础100包括基础本体以及设置在基础本体内且伸出基础本体的上端面的基础钢筋。将基础连接钢筋01的一端与基础钢筋连接,另一端与底层预制柱200的钢筋笼连接。Step 1: As shown in FIG. 5 , the foundation 100 is formed by laying out wires, positioning the foundation, and pouring on site; the foundation 100 includes the foundation body and the foundation steel bars arranged in the foundation body and protruding from the upper end surface of the foundation body. Connect one end of the foundation connecting reinforcement 01 to the foundation reinforcement, and connect the other end to the reinforcement cage of the prefabricated column 200 on the ground floor.

其中,基础连接钢筋01与基础钢筋的连接方式可以为多种,例如:焊接、铁丝绑定等。Wherein, the connection mode between the basic connecting steel bar 01 and the basic steel bar can be various, for example: welding, iron wire binding and so on.

优选地,连接钢筋与基础钢筋通过钢筋连接件连接(可以为螺纹连接件,可以为挤压连接件,连接件不限形式)。通过连接件连接,连接快捷方便,成本低。Preferably, the connecting steel bar is connected to the basic steel bar through a steel bar connecting piece (it may be a threaded connecting piece, it may be an extruded connecting piece, and the connecting piece is not limited in form). The connection is quick and convenient, and the cost is low.

基础连接钢筋01与柱钢筋笼的连接方式可以为多种,例如:焊接、铁丝绑定或者通过钢筋连接件连接等。There are many ways to connect the foundation connecting reinforcement 01 and the column reinforcement cage, for example: welding, binding with iron wires, or connecting through reinforcement connectors, etc.

优选地,柱连接钢筋包括柱连接纵筋,柱钢筋笼包括柱纵筋以及柱钢筋网片组,柱外壳包裹在柱钢筋网片组的外侧,柱纵筋设置在柱钢筋网片组内;连接纵筋的一端与柱纵筋一体设置,另一端与基础钢筋连接。Preferably, the column connection reinforcement includes column connection longitudinal reinforcement, the column reinforcement cage includes column longitudinal reinforcement and column reinforcement mesh group, the column shell is wrapped on the outside of the column reinforcement mesh group, and the column longitudinal reinforcement is arranged in the column reinforcement mesh group; One end of the connecting longitudinal reinforcement is integrated with the column longitudinal reinforcement, and the other end is connected with the foundation reinforcement.

本实施例中,基础连接纵筋与柱纵筋一体设置,即在预制柱200生产过程中,柱纵筋伸柱外壳的下端,柱纵筋的伸出部分形成连接纵筋,直接将柱纵筋的伸出部分与基础钢筋,从而减少基础连接纵筋与柱纵筋的连接过程进一步提高施工效率,还能够减少运输部件,进一步方便施工。In this embodiment, the foundation connecting longitudinal reinforcement and the column longitudinal reinforcement are integrally arranged, that is, during the production process of the prefabricated column 200, the column longitudinal reinforcement extends the lower end of the column shell, and the protruding part of the column longitudinal reinforcement forms the connecting longitudinal reinforcement, which directly connects the column longitudinal reinforcement. The protruding part of the reinforcement is connected with the foundation reinforcement, thereby reducing the connection process between the foundation connection longitudinal reinforcement and the column longitudinal reinforcement to further improve construction efficiency, and can also reduce transportation parts, further facilitating construction.

基础连接纵筋与预制柱200的延伸方向一致,基础连接钢筋01还可以包括与预制柱200的延伸方向垂直设置的基础连接横筋,基础连接纵筋与基础连接横筋相互交错设置形成镂空装结构,从而可以加强节点处的强度。The extension direction of the foundation connection longitudinal reinforcement is consistent with the extension direction of the prefabricated column 200, the foundation connection reinforcement 01 may also include the foundation connection transverse reinforcement perpendicular to the extension direction of the prefabricated column 200, the foundation connection longitudinal reinforcement and the foundation connection transverse reinforcement are interlaced to form a hollow structure, Thereby the strength at the node can be strengthened.

以此方法完成底层所有柱的安装。In this way, the installation of all the columns on the ground floor is completed.

第二步:如图1所示,安装底层的预制主梁。连接件包括柱连接钢筋笼02以及梁柱连接钢筋;梁柱连接钢筋的延伸方向与预制主梁的延伸方向一致,柱连接钢筋笼02的一端与柱钢筋笼的上端连接,两个预制主梁一一位于预制柱200的上端的两侧,梁柱钢筋穿过柱连接钢筋笼02,且一端与一个梁钢筋笼连接,另一端与另一个梁钢筋笼连接;预制柱200竖直设置,预制主梁水平设置。Step 2: As shown in Figure 1, install the prefabricated main beam on the ground floor. Connectors include column connection reinforcement cage 02 and beam-column connection reinforcement; the extension direction of the beam-column connection reinforcement is consistent with the extension direction of the prefabricated main beam, one end of the column connection reinforcement cage 02 is connected to the upper end of the column reinforcement cage, and the two prefabricated main beams One is located on both sides of the upper end of the prefabricated column 200, the beam-column reinforcement passes through the column to connect the reinforcement cage 02, and one end is connected to a beam reinforcement cage, and the other end is connected to another beam reinforcement cage; the prefabricated column 200 is vertically arranged, and the prefabricated The main girder is set horizontally.

柱连接钢筋笼02与下层柱钢筋笼(底层预制柱200为最下层预制柱220)的连接方式有多种,例如:焊接、铁丝绑固或者通过钢筋连接件固定。There are many ways to connect the column connection reinforcement cage 02 to the lower column reinforcement cage (the bottom prefabricated column 200 is the lowermost prefabricated column 220 ), for example: welding, iron wire binding or fixing by steel connectors.

优选地,柱连接钢筋笼02与下层柱钢筋笼一体设置;即下层预制柱220生产过程中,下层预制柱220的钢筋笼伸出下层预制柱220的外壳的上端,下层预制柱220的钢筋笼的伸出部分形成柱连接钢筋笼02,从而柱连接钢筋笼02与下层预制柱220的钢筋笼的连接过程,进一步提高施工效率,还能够减少运输部件,进一步方便施工。Preferably, the column connection reinforcement cage 02 is integrated with the lower column reinforcement cage; that is, during the production process of the lower prefabricated column 220, the reinforcement cage of the lower prefabricated column 220 protrudes from the upper end of the lower shell of the lower prefabricated column 220, and the reinforcement cage of the lower layer prefabricated column 220 The protruding part forms the column connection reinforcement cage 02, so that the connection process between the column connection reinforcement cage 02 and the reinforcement cage of the lower prefabricated column 220 can further improve the construction efficiency, and can also reduce the transportation parts, further facilitating the construction.

在上述实施例基础之上,进一步地,梁柱连接钢筋包括梁柱连接腰筋;梁柱连接腰筋穿设在柱连接钢筋笼02内,且梁柱连接腰筋的一端搭接在一个主梁钢筋笼上,另一端搭接在另一个主梁钢筋笼上。梁柱连接腰筋结构简单易安装,施工简单。On the basis of the above-mentioned embodiments, further, the beam-column connection reinforcement includes beam-column connection waist reinforcement; the beam-column connection waist reinforcement is penetrated in the column connection reinforcement cage 02, and one end of the beam-column connection waist Beam reinforcement cage, and the other end is lapped on another main beam reinforcement cage. The beam-column connection structure is simple and easy to install, and the construction is simple.

梁柱连接腰筋的个数可以为一个还可以为多个,连接腰筋可以为一层还可以为多层。The number of beam-column connecting ribs can be one or multiple, and the connecting ribs can be one layer or multiple layers.

在上述实施例基础之上,进一步地,梁柱连接钢筋还包括梁柱贯通纵筋;梁柱贯通纵筋穿过柱连接钢筋笼02,梁柱贯通纵筋的一端搭接在一个主梁钢筋笼的远离梁柱连接钢筋笼02的一端,另一端搭接在另一个主梁钢筋笼远离梁柱连接钢筋笼02的一端。On the basis of the above embodiments, further, the beam-column connection reinforcement also includes beam-column penetration longitudinal reinforcement; the beam-column penetration longitudinal reinforcement passes through the column connection reinforcement cage 02, and one end of the beam-column penetration longitudinal reinforcement is lapped on a main beam reinforcement One end of the cage away from the beam-column connection reinforcement cage 02 is overlapped with another end of the main beam reinforcement cage away from the beam-column connection reinforcement cage 02.

本实施例中,梁柱贯通纵筋的长度不小于两个预制主梁的长度加两个预制主梁之间的间隙距离,梁柱贯通纵筋能够进一步加强节点连接强度,能够保障浇筑施工混凝土后形成的梁的强度。In this embodiment, the length of the beam-column passing through the longitudinal reinforcement is not less than the length of the two prefabricated main beams plus the gap distance between the two prefabricated main beams. strength of the resulting beam.

其中,梁柱贯通纵筋可以为一个还可以为多这个。Wherein, the beam-column penetrating longitudinal reinforcement may be one or more.

优选地,梁柱贯通纵筋包括梁柱上贯通纵筋和梁柱下贯通纵筋;梁柱上贯通纵筋设置在预制主梁的顶部,梁柱下贯通纵筋设置在预制主梁的底部。预制主梁的上下均设置贯通纵筋则能够进一步提高连接强度。Preferably, the beam-column penetrating longitudinal reinforcement includes the beam-column upper penetrating longitudinal rib and the beam-column lower penetrating longitudinal rib; the beam-column upper penetrating longitudinal rib is arranged at the top of the prefabricated main beam, and the beam-column lower penetrating longitudinal rib is arranged at the bottom of the prefabricated main beam . The upper and lower sides of the prefabricated main girder are provided with through longitudinal reinforcement, which can further improve the connection strength.

需要说明的是,预制主梁可以为四个,一一位于预制柱的上端的四侧。It should be noted that there may be four prefabricated main girders, each located on four sides of the upper end of the prefabricated column.

第三步:安装底层预制次梁。按照预制次梁与预制主梁安装的形式不同,可以将预制次梁分为第一预制次梁410和第二预制次梁420,一个第一预制次梁的端部与预制主梁连接,两个第二预制次梁的一端均与预制主梁连接。Step 3: Install the prefabricated secondary beams on the ground floor. According to the different installation forms of the prefabricated secondary beam and the prefabricated main beam, the prefabricated secondary beam can be divided into a first prefabricated secondary beam 410 and a second prefabricated secondary beam 420, one end of the first prefabricated secondary beam is connected with the prefabricated main beam, and the two One end of each second prefabricated secondary beam is connected to the prefabricated main beam.

其中,第一预制次梁410与预制主梁的连接:Among them, the connection between the first prefabricated secondary beam 410 and the prefabricated main beam:

装配式结构体系还包括第一主次梁连接口以及第一主次梁连接纵筋05;第一主次梁连接口设置在主梁外壳上的指定位置,第一主次梁连接纵筋05的一端插设在第一主次梁连接口内,另一端与第一次梁钢筋笼连接;可采用三种连接方式。The prefabricated structure system also includes the first primary and secondary beam connection port and the first primary and secondary beam connection longitudinal reinforcement 05; the first primary and secondary beam connection port is set at a designated position on the main beam shell, and the first primary and secondary One end is inserted in the connection port of the first primary and secondary beams, and the other end is connected with the reinforcement cage of the primary beam; three connection methods can be used.

第一种,如图7a至7b所示,第一主梁连接口包括第一主次梁连接插槽071。第一主次梁连接插槽071设置在预制主梁上,主梁外壳上设置豁口,以形成第一主次梁连接插槽,第一主次梁连接插槽的尺寸不小于预制次梁的截面尺寸,可以在生产预制主梁过程中,采用模具使主梁外壳预留豁口;或者在预制主梁完成生产后,对主梁外壳进行切割。The first type, as shown in FIGS. 7 a to 7 b , the first main beam connection port includes a first primary and secondary beam connection slot 071 . The first primary and secondary beam connection slot 071 is set on the prefabricated main beam, and a gap is set on the main beam shell to form the first primary and secondary beam connection slot, and the size of the first primary and secondary beam connection slot is not smaller than that of the prefabricated secondary beam. The cross-sectional size can be prepared by using a mold to make gaps in the shell of the main beam during the production of the prefabricated main beam; or cutting the shell of the main beam after the production of the prefabricated main beam is completed.

当主梁外壳包括依次连接的主梁左侧板、主梁底板以及主梁右侧板时,主梁左侧板和主梁右侧板中靠近第一预制次梁410的一个上设置有豁口。When the main girder shell includes the main girder left side plate, the main girder bottom plate and the main girder right side plate connected in sequence, a notch is provided on one of the main girder left side plate and the main girder right side plate that is close to the first prefabricated secondary girder 410 .

预制主梁与第一预制次梁410垂直设置,将预制主梁和第一预制次梁410运至施工现场,吊装定位后,将第一预制次梁410的一端紧挨预制主梁外壳的一侧壁;第一主次梁连接纵筋05的一端插在连接插槽内,另一端与次梁钢筋笼连接。The prefabricated main girder and the first prefabricated secondary girder 410 are vertically arranged, and the prefabricated main girder and the first prefabricated secondary girder 410 are transported to the construction site. Side wall; one end of the first primary and secondary beam connecting longitudinal reinforcement 05 is inserted into the connection slot, and the other end is connected with the secondary beam reinforcement cage.

第二种,如图8a至8b所示,第一主次梁连接口包括第一主次梁连接间隔072,主梁外壳包括沿主梁钢筋笼的延伸方向间隔设置的第一主梁外壳以及第二主梁外壳,以形成第一主次梁连接间隔,第一主梁外壳与第二主梁外壳的间隔处的所述主梁钢筋笼裸露,第一主次梁连接间隔072的尺寸不小于第一预制次梁410的截面尺寸,以使第一预制次梁410的一端能够与预制主梁紧密抵接,主梁钢筋笼保持完整,第一主次梁连接间隔072将主梁钢筋笼的相应部分裸露,可以在生产预制主梁过程中,采用模具使主梁外壳预留间隔。In the second type, as shown in Figures 8a to 8b, the first primary and secondary beam connection ports include first primary and secondary beam connection intervals 072, and the main beam shell includes first main beam shells arranged at intervals along the extension direction of the main beam reinforcement cage and The second main beam shell is to form the first primary and secondary beam connection interval, the main beam reinforcement cage at the interval between the first main beam shell and the second main beam shell is exposed, and the size of the first primary and secondary beam connection interval 072 is not Smaller than the cross-sectional size of the first prefabricated secondary beam 410, so that one end of the first prefabricated secondary beam 410 can be closely abutted with the prefabricated main beam, the main beam reinforcement cage remains intact, and the first primary and secondary beam connection interval 072 connects the main beam reinforcement cage The corresponding part of the exposed part can be used in the process of producing the prefabricated main beam, so that the shell of the main beam can be reserved with a mold.

施工过程中,预制主梁与第一预制次梁410垂直设置,将预制主梁和第一预制次梁410运至施工现场,吊装定位后,将第一预制次梁410的一端紧挨主梁外壳的一侧壁;第一主次梁连接纵筋05的一端由第一预制次梁410这一侧穿过第一主次梁连接间隔072插入裸露在外的主梁钢筋笼内,另一端与第一预制次梁410的钢筋笼连接。During the construction process, the prefabricated main beam and the first prefabricated secondary beam 410 are vertically arranged, and the prefabricated main beam and the first prefabricated secondary beam 410 are transported to the construction site. After hoisting and positioning, one end of the first prefabricated secondary beam 410 is placed close to the main beam One side wall of the shell; one end of the first primary and secondary beam connecting longitudinal reinforcement 05 is inserted into the exposed main beam reinforcement cage from the side of the first prefabricated secondary beam 410 through the first primary and secondary beam connection interval 072, and the other end is connected with the The steel cage connection of the first prefabricated secondary beam 410 .

第三种,如图9a至9b所示,第一主次梁连接口包括第一主次梁连接插孔073,在主梁外壳上设置第一主次梁连接插孔073,以使第一主次梁连接纵筋05可以由主梁外壳外穿过第一主次梁连接插孔073进入主梁钢筋笼内。可以在生产预制主梁过程中,采用模具使主梁外壳预留第一主次梁连接插孔073;或者在预制主梁完成生产后,对主梁外壳进行钻孔。The third type, as shown in Figures 9a to 9b, the first primary and secondary beam connection port includes a first primary and secondary beam connection socket 073, and the first primary and secondary beam connection socket 073 is set on the main beam shell, so that the first The primary and secondary beam connecting longitudinal reinforcement 05 can pass through the first primary and secondary beam connecting socket 073 from the outside of the main beam shell and enter the main beam reinforcement cage. During the production of the prefabricated main girder, molds can be used to reserve the first primary and secondary girder connecting sockets 073 in the shell of the main girder; or after the production of the prefabricated main girder is completed, the shell of the main girder can be drilled.

施工过程中,预制主梁与第一预制次梁410垂直设置,将预制主梁和第二预制次梁420运至施工现场,吊装定位后,将第一预制次梁410的一端紧挨主梁外壳的一侧壁;第一主次梁连接纵筋05的一端由第一预制次梁410这一侧穿过第一主次梁连接插孔073插入主梁外壳内的梁钢筋笼内,另一端与第一次梁的次梁钢筋笼连接。During the construction process, the prefabricated main girder and the first prefabricated secondary girder 410 are vertically arranged, and the prefabricated main girder and the second prefabricated secondary girder 420 are transported to the construction site. One side wall of the shell; one end of the first primary and secondary beam connecting longitudinal reinforcement 05 is inserted from the side of the first prefabricated secondary beam 410 through the first primary and secondary beam connecting socket 073 into the beam reinforcement cage in the main beam shell, and the other One end is connected with the secondary beam reinforcement cage of the primary beam.

其中,第一主次梁连接纵筋05与次梁钢筋笼的连接方式有多种,例如:铁丝绑定或者通过钢筋紧固件连接等。Among them, there are many ways to connect the longitudinal reinforcement 05 of the first primary and secondary beams to the reinforcement cage of the secondary beams, for example, binding with iron wires or connecting with steel fasteners.

优选地,第一主次梁连接纵筋05的一端位于主梁钢筋笼内,另一端搭接在第一次梁钢筋笼内且延伸至第一次梁钢筋笼的远离预制主梁的一端,安装简单,能够在后期完成现场浇筑施工混凝土后,使形成的梁具有足够的强度。Preferably, one end of the connecting longitudinal reinforcement 05 of the first primary and secondary beams is located in the reinforcement cage of the main beam, and the other end is overlapped in the reinforcement cage of the primary beam and extends to an end of the reinforcement cage of the primary beam away from the prefabricated main beam, The installation is simple, and after the construction concrete is poured on site in the later stage, the formed beam has sufficient strength.

在上述实施例基础之上,进一步地,第一主次梁连接纵筋包括第一主次梁上部纵筋和第一主次梁下部纵筋;第一主次梁上部纵筋设置在第一次梁钢筋笼的上部,第一主次梁下部纵筋设置在第一次梁钢筋笼的下部,能够进一步加强梁的强度。On the basis of the above embodiment, further, the connecting longitudinal reinforcement of the first primary and secondary beams includes the upper longitudinal reinforcement of the first primary and secondary beams and the lower longitudinal reinforcement of the first primary and secondary beams; the upper longitudinal reinforcement of the first primary and secondary beams is arranged on the first The upper part of the reinforcement cage of the secondary beam, and the lower longitudinal reinforcement of the first primary and secondary beams are arranged at the lower part of the reinforcement cage of the primary beam, which can further strengthen the strength of the beam.

第一主次梁连接纵筋包括第一主次梁上部纵筋和第一主次梁下部纵筋,两者的个数均可以为一个,还可以为多个。The connecting longitudinal reinforcements of the first primary and secondary beams include the upper longitudinal reinforcements of the first primary and secondary beams and the lower longitudinal reinforcements of the first primary and secondary beams, and the number of both may be one or multiple.

优选地,第一主次梁上部纵筋呈L形,且所述上部纵筋的拐角处位于所述主梁钢筋笼内,则能够增大第一主次梁上部纵筋与施工混凝土100的锚固力。Preferably, the upper longitudinal bars of the first primary and secondary beams are L-shaped, and the corners of the upper longitudinal bars are located in the reinforcement cage of the main beam, so that the distance between the upper longitudinal bars of the first primary and secondary beams and the construction concrete 100 can be increased. anchoring force.

当然,第一主次梁下部纵筋也就可以呈L形。两者上还可以设置凸起、倒刺等以增加与施工混凝土100的锚固力。Of course, the longitudinal reinforcement at the lower part of the first primary and secondary beams can also be L-shaped. Protrusions, barbs, etc. can also be provided on both to increase the anchoring force with the construction concrete 100 .

当然还可以在上侧和下侧之间设置多层连接纵筋Of course, it is also possible to arrange multi-layer connecting longitudinal ribs between the upper side and the lower side

第二预制次梁420与预制主梁的连接:The connection between the second prefabricated secondary beam 420 and the prefabricated main beam:

装配式结构体系还包括第二主次梁连接口以及第二主次梁连接钢筋;两个第二预制次梁420相对设置在预制主梁的两侧;第二主次梁连接口设置在主梁外壳上的指定位置,第二主次梁连接钢筋穿设在第一主次梁连接口内,第二主次梁连接贯通纵筋06的一端与一个第二次梁钢筋笼连接,另一端与另一个次梁钢筋笼连接,连接结构形式有三种。The prefabricated structural system also includes the second primary and secondary beam connection ports and the second primary and secondary beam connection reinforcement; two second prefabricated secondary beams 420 are arranged on both sides of the prefabricated main beam; the second primary and secondary beam connection ports are set on the main At the specified position on the beam shell, the second primary and secondary beam connecting reinforcement is pierced in the first primary and secondary beam connection opening, and one end of the second primary and secondary beam connecting through longitudinal reinforcement 06 is connected to a second beam reinforcement cage, and the other end is connected to Another secondary beam steel cage connection, there are three types of connection structure.

第一种,如图10a至10b所示,第二主次梁连接口包括第二主次梁连接插槽081,第二主次梁连接插槽081设置在预制主梁上,主梁外壳上设置豁口,以形成第二主次梁连接插槽081,第二主次梁连接插槽081的尺寸不小于预制次梁的截面尺寸,可以在生产预制主梁过程中,采用模具使主梁外壳预留豁口;或者在预制主梁完成生产后,对主梁外壳进行切割。The first type, as shown in Figures 10a to 10b, the second primary and secondary beam connection port includes a second primary and secondary beam connection slot 081, and the second primary and secondary beam connection slot 081 is arranged on the prefabricated main beam, on the main beam shell Set the gap to form the second primary and secondary beam connection slot 081, the size of the second primary and secondary beam connection slot 081 is not smaller than the cross-sectional size of the prefabricated secondary beam, and the mold can be used to make the main beam shell Reserve gaps; or cut the shell of the main girder after the production of the prefabricated main girder is completed.

第二主次梁连接插槽至少包括两个开口,两个开口相对设置,以使第二主次梁连接贯通纵筋06放置在第二主次梁连接插槽081后,第二主次梁连接贯通纵筋06的两端可以伸出分别与两个第二预制次梁的钢筋笼连接,或者两个次梁钢筋笼伸入连接插槽与连接纵筋连接。The second primary and secondary beam connection slots include at least two openings, and the two openings are arranged opposite to each other, so that the second primary and secondary beams are connected through longitudinal ribs 06 and placed behind the second primary and secondary beam connection slots 081, and the second primary and secondary beams The two ends of the connecting through longitudinal reinforcement 06 can protrude to be respectively connected with the reinforcement cages of the two second prefabricated secondary beams, or the reinforcement cages of the two secondary beams can extend into the connecting slots to connect with the connecting longitudinal reinforcements.

施工过程中,预制主梁与第二预制次梁垂直设置,将预制主梁和两个第二预制次梁420运至施工现场,吊装定位后,将两个第二预制次梁420的一端分别紧挨主梁外壳的两个侧壁;第二主次梁连接贯通纵筋06位于第二主次梁连接插槽内,一端与一个第一预制次梁410的钢筋笼连接,另一端与另一个第二预制次梁420的钢筋笼连接。During the construction process, the prefabricated main girder and the second prefabricated secondary girder are vertically arranged, and the prefabricated main girder and the two second prefabricated secondary girders 420 are transported to the construction site. Close to the two side walls of the main beam shell; the second primary and secondary beam connecting through longitudinal reinforcement 06 is located in the second primary and secondary beam connecting slot, one end is connected with a steel cage of a first prefabricated secondary beam 410, and the other end is connected with the other A steel cage connection of the second prefabricated secondary beam 420 .

第二种,如图11a至11b所示,第一主次梁连接口包括第二主次梁连接间隔082,主梁外壳包括沿主梁钢筋笼的延伸方向间隔设置的第一主梁外壳以及第二主梁外壳,以形成第二主次梁连接间隔082,第一主梁外壳与第二主梁外壳的间隔处的所述主梁钢筋笼裸露,第二主次梁连接间隔的尺寸不小于第二预制次梁的截面尺寸,以使第二预制次梁的一端能够与预制主梁紧密抵接,主梁钢筋笼保持完整,可以在生产预制主梁过程中,采用模具使主梁外壳预留间隔。The second type, as shown in Figures 11a to 11b, the first primary and secondary beam connection port includes a second primary and secondary beam connection interval 082, and the main beam shell includes first main beam shells arranged at intervals along the extension direction of the main beam reinforcement cage and The second main beam shell is to form the second primary and secondary beam connection interval 082, the main beam reinforcement cage at the interval between the first main beam shell and the second main beam shell is exposed, and the size of the second primary and secondary beam connection interval is different. Smaller than the cross-sectional size of the second prefabricated secondary beam, so that one end of the second prefabricated secondary beam can be closely contacted with the prefabricated main beam, and the reinforcement cage of the main beam remains intact. During the production of the prefabricated main beam, the mold can be used to make the shell of the main beam Reserve interval.

施工过程中,两个第二预制次梁420均与预制主梁300垂直设置,且分别位于预制主梁的两侧,将两个第二预制次梁420的一端分别紧挨主梁外壳的两个侧壁;第二主次梁连接贯通纵筋06穿过第二主次梁连接间隔082位于相应位置的主梁钢筋笼内,一端与一个第二预制次梁420的钢筋笼连接,另一端与另一个第二预制次梁420的钢筋笼连接。During the construction process, the two second prefabricated secondary beams 420 are perpendicular to the prefabricated main beam 300, and are respectively located on both sides of the prefabricated main beam. side walls; the second primary and secondary beams connect through longitudinal reinforcement 06 and pass through the second primary and secondary beams connecting interval 082 in the main beam reinforcement cage at the corresponding position, one end is connected with the reinforcement cage of a second prefabricated secondary beam 420, and the other end It is connected with the reinforcement cage of another second prefabricated secondary beam 420 .

第三种,如图12a至12b所示,第二主次梁连接口包括第二主次梁连接插孔083,在主梁外壳左右侧板上均设置第二主次梁连接插孔,以使第二主次梁连接贯通纵筋06可以由主梁外壳外穿过第二主次梁连接插孔进入主梁钢筋笼内。可以在生产预制主梁过程中,采用模具使主梁外壳预留第二主次梁连接插孔083;或者在预制主梁完成生产后,对主梁外壳进行钻孔。The third type, as shown in Figures 12a to 12b, the second primary and secondary beam connection ports include the second primary and secondary beam connection sockets 083, and the second primary and secondary beam connection sockets are provided on the left and right side plates of the main beam shell, so as to The second primary and secondary beams are connected through the longitudinal reinforcement 06 to enter the main beam reinforcement cage through the second primary and secondary beam connection sockets from the outside of the main beam shell. In the process of producing the prefabricated main girder, the mold can be used to reserve the second primary and secondary beam connecting sockets 083 in the shell of the main girder; or after the production of the prefabricated main girder is completed, the shell of the main girder can be drilled.

施工过程中,预制主梁与第二预制次梁420垂直设置,将两个第二预制次梁420的一端分别紧挨主梁外壳的两个侧壁;第二主次梁连接贯通纵筋06穿过左右侧板上的第二主次梁连接插孔083,一端通过左侧板上的第二主次梁连接插孔与左侧第二次梁钢筋笼连接,另一端通过右侧板上的第二主次梁连接插孔与右侧第二次梁钢筋笼连接。During the construction process, the prefabricated main beam and the second prefabricated secondary beam 420 are vertically arranged, and one end of the two second prefabricated secondary beams 420 is respectively close to the two side walls of the main beam shell; the second primary and secondary beams are connected through longitudinal reinforcement 06 Pass through the second primary and secondary beam connection socket 083 on the left and right side panels, one end is connected to the left secondary beam reinforcement cage through the second primary and secondary beam connection socket on the left panel, and the other end is connected to the left secondary beam reinforcement cage through the right panel The connecting socket of the second primary and secondary beams is connected with the reinforcement cage of the second secondary beam on the right side.

本实施例中,次梁外壳以及次梁纵筋通过主梁钢筋网片组隔离开来,在现场浇筑施工时,次梁外壳能够起到模板作用,简化了施工步骤,提高了施工效率。预制次梁采用壳体的形式,整体重量轻,方便运输和吊装。In this embodiment, the outer shell of the secondary beam and the longitudinal reinforcement of the secondary beam are separated by the reinforcement mesh group of the main beam, and the outer shell of the secondary beam can serve as a formwork during on-site pouring construction, which simplifies the construction steps and improves the construction efficiency. The prefabricated secondary beam is in the form of a shell, which is light in overall weight and convenient for transportation and hoisting.

第二主次梁连接贯通纵筋06与次梁钢筋笼的连接方式有多种,例如:铁丝绑定或者通过钢筋紧固件连接等。There are many ways to connect the second primary and secondary beams through the longitudinal reinforcement 06 and the reinforcement cage of the secondary beam, for example: binding with iron wires or connecting with steel fasteners.

优选地,第二主次梁连接贯通纵筋06的一端与一个第二预制次梁的远离预制主梁的一端连接,另一端穿过第二主次梁连接口且与另一第二预制次梁的远离预制主梁的一端连接。Preferably, one end of the second primary and secondary beams connecting through the longitudinal reinforcement 06 is connected to one end of a second prefabricated secondary beam away from the prefabricated main beam, and the other end passes through the connection port of the second primary and secondary beams and is connected to another second prefabricated secondary beam. The beams are connected at one end away from the prefabricated main beam.

本实施例中,将第二主次梁连接贯通纵筋06的一端搭接在一个第二预制次梁的远离预制主梁的一端,另一端搭接在另一个第二预制次梁的远离预制主梁的一端。后期现场浇筑混凝土。第二主次梁连接贯通纵筋06设置方便,能够进一步提高施工效率,能够保障梁的强度。In this embodiment, one end of the second primary and secondary beams connecting through longitudinal ribs 06 is lapped on one end of a second prefabricated secondary beam far away from the prefabricated main beam, and the other end is lapped on another second prefabricated secondary beam far away from the prefabricated end of the main beam. Concrete poured on site later. The connection of the second primary and secondary beams through the longitudinal reinforcement 06 is easy to set, which can further improve the construction efficiency and ensure the strength of the beams.

在上述实施例基础之上,进一步地,第二主次梁连接贯通纵筋06包括第二主次梁上部贯通纵筋和第二主次梁下部贯通纵筋,第二主次梁上部贯通纵筋位于两个第二预制次梁的上部,第二主次梁下部贯通纵筋位于两个第二预制次梁的下部。On the basis of the above-mentioned embodiments, further, the second primary and secondary beam connecting through longitudinal reinforcement 06 includes the upper part of the second primary and secondary beam through the longitudinal reinforcement and the second primary and secondary beam through the lower part of the longitudinal reinforcement, the second primary and secondary beam The reinforcement is located at the upper part of the two second prefabricated secondary beams, and the longitudinal reinforcement at the lower part of the second primary and secondary beams is located at the lower part of the two second prefabricated secondary beams.

本实施例中,第二主次梁上部贯通纵筋和第二主次梁下部贯通纵筋,两者的个数均可以为一个,还可以为多个。同时设置第二主次梁上部贯通纵筋和第二主次梁下部贯通纵筋,可以进一步提高连接节点强度,进一步提高梁的强度。In this embodiment, the upper part of the second primary and secondary beams penetrates the longitudinal ribs and the lower part of the second primary and secondary beams penetrates the longitudinal ribs, and the number of both can be one or more. At the same time, the upper through longitudinal reinforcement of the second primary and secondary beam and the lower through longitudinal reinforcement of the second primary and secondary beam can be arranged to further increase the strength of the connection node and further increase the strength of the beam.

第二主次梁连接贯通纵筋可以为多个还可以为多层。The second primary and secondary beams connecting through longitudinal reinforcements can be multiple or multi-layered.

第四步,现场浇筑施工混凝土。待所有底层的预制主梁、预制次梁以及预制柱200,均安装完毕后,再安装楼板(楼板形式不限,可为叠合楼板、SP板、现浇楼板等),再浇筑混凝土,将楼板、预制主梁、预制次梁以及预制柱200整体浇筑。完成底层框架的安装。The fourth step is to pour construction concrete on site. After all the prefabricated main beams, prefabricated secondary beams and prefabricated columns 200 on the bottom floor have been installed, install the floor slab (the form of the floor slab is not limited, it can be a laminated floor slab, SP slab, cast-in-place slab, etc.), and then pour concrete. Floor slabs, prefabricated main beams, prefabricated secondary beams and prefabricated columns 200 are integrally poured. Complete the installation of the underlying frame.

第五步:如图6所示,上层柱与下层柱的连接。装配式结构体系还包括柱连接纵筋,柱连接纵筋的延伸方向与预制柱200的延伸方向一致。每相邻两个预制柱200之间均设置有柱连接钢筋笼02以及柱连接纵筋,其中,柱连接钢筋笼02与下层预制柱220的钢筋笼连接,柱连接纵筋的一端与上层预制柱210的纵筋连接,另一端插入柱连接钢筋笼02并固定Step 5: As shown in Figure 6, the connection between the upper column and the lower column. The prefabricated structure system also includes column connecting longitudinal reinforcement, and the extending direction of the column connecting longitudinal reinforcement is consistent with the extending direction of the prefabricated column 200 . Between every two adjacent prefabricated columns 200, there are column connecting reinforcement cages 02 and column connecting longitudinal reinforcements, wherein the column connecting reinforcement cages 02 are connected to the reinforcement cages of the lower prefabricated columns 220, and one end of the column connecting longitudinal reinforcements is connected to the upper prefabricated The longitudinal reinforcement of the column 210 is connected, and the other end is inserted into the column connection reinforcement cage 02 and fixed

柱连接纵筋与上层预制柱210的柱纵筋的下端连接方式有多种,例如:焊接、铁丝绑定、或者通过钢筋紧固件连接等。There are many ways to connect the column connecting longitudinal reinforcement to the lower end of the column longitudinal reinforcement of the upper prefabricated column 210 , for example: welding, iron wire binding, or connection through steel fasteners.

柱连接钢筋笼02与下层预制柱220的柱钢筋笼的上端连接方式有多种,例如:焊接、铁丝绑定、或者通过钢筋紧固件连接等。There are many ways to connect the upper end of the column connection reinforcement cage 02 to the column reinforcement cage of the lower prefabricated column 220 , for example: welding, iron wire binding, or connection through reinforcement fasteners.

优选地,柱连接纵筋与上层预制柱210的柱纵筋一体设置,柱连接钢筋笼02与下层预制柱220的柱钢筋笼一体设置。即在上层预制柱210生产过程中,上层预制柱210的柱纵筋伸出上层预制柱210的柱外壳的下端,上层柱的柱纵筋的伸出部分形成柱连接纵筋,下层预制柱220生产过程中,下层预制柱220的柱钢筋笼伸出下层预制柱220的柱外壳的上端,下层柱的柱钢筋笼的伸出部分形成柱连接钢筋笼02,直接将上层柱的柱纵筋的伸出部分与下层柱的柱钢筋笼的伸出部分连接,从而减少柱连接纵筋与柱纵筋的连接过程以及柱连接钢筋笼02与柱钢筋笼的连接过程,进一步提高施工效率,还能够减少运输部件,进一步方便施工。Preferably, the column connecting longitudinal reinforcement is integrated with the column longitudinal reinforcement of the upper prefabricated column 210 , and the column connecting reinforcement cage 02 is integrated with the column reinforcement cage of the lower prefabricated column 220 . That is, during the production process of the upper precast column 210, the column longitudinal reinforcement of the upper precast column 210 protrudes from the lower end of the column shell of the upper precast column 210, and the protruding part of the column longitudinal reinforcement of the upper column forms a column connecting longitudinal reinforcement, and the lower precast column 220 During the production process, the column reinforcement cage of the lower prefabricated column 220 protrudes from the upper end of the column shell of the lower prefabricated column 220, and the protruding part of the column reinforcement cage of the lower column forms a column connecting reinforcement cage 02, directly connecting the column longitudinal reinforcement of the upper column The protruding part is connected with the protruding part of the column reinforcement cage of the lower column, thereby reducing the connection process between the column connection longitudinal reinforcement and the column longitudinal reinforcement and the connection process of the column connection reinforcement cage 02 and the column reinforcement cage, further improving the construction efficiency, and can also Reduced transport parts further facilitate construction.

柱连接纵筋与柱连接钢筋笼02固定连接的方式有多种,例如:焊接或者通过铁丝绑定等There are many ways of fixed connection between column connection longitudinal reinforcement and column connection reinforcement cage 02, for example: welding or binding by iron wire, etc.

优选地,柱连接钢筋与柱连接钢筋笼02通过钢筋连接件连接。连接快捷方便,成本低。Preferably, the column connecting steel bar is connected to the column connecting steel bar cage 02 through a steel bar connecting piece. The connection is fast and convenient, and the cost is low.

完成二层预制柱200的安装后,然后在二层柱端部支模,主梁、次梁、楼板安装步骤参照第二、三、四步。如此往复,最后完成建筑主体结构安装。After completing the installation of the prefabricated column 200 on the second floor, formwork is then set up at the end of the column on the second floor. For the installation steps of the main beam, secondary beam and floor slab, refer to the second, third, and fourth steps. This reciprocation finally completes the installation of the main structure of the building.

本发明提供的装配式结构体系中,预制柱200、预制主梁300以及预制次梁400均包括钢筋笼以及包裹在钢筋笼外的外壳,当各个预制构件按照要求吊装定位后,可在需要的小部分区域例如上层预制柱210与下层预制柱220之间的柱连接钢筋笼02处支模,然后完成整体的现场灌浇施工混凝土。外壳即可充当模板,无需预制柱200、预制主梁以及预制次梁处均设置大量模板,则能够极大减少支模量,从而使施工简单,施工效率高。In the prefabricated structural system provided by the present invention, the prefabricated column 200, the prefabricated main beam 300 and the prefabricated secondary beam 400 all include a reinforcement cage and a shell wrapped outside the reinforcement cage. A small part of the area, such as the column between the upper precast column 210 and the lower precast column 220, supports the formwork at the reinforcement cage 02, and then completes the overall on-site pouring of construction concrete. The shell can be used as a formwork, and there is no need to set a large number of formworks at the prefabricated columns 200, prefabricated main beams, and prefabricated secondary beams, which can greatly reduce the modulus, so that the construction is simple and the construction efficiency is high.

现场钢筋绑扎工作量大大减少,施工工序简单,从而能够提高施工效率,节省施工成本。The workload of on-site steel bar binding is greatly reduced, and the construction process is simple, so that the construction efficiency can be improved and the construction cost can be saved.

预制梁、预制柱及其他预制构件现场整体浇筑,结构受力合理,整体性能与普通现浇混凝土结构相当,具有安全可靠、简化施工、节约耗材、减少扬尘和建筑垃圾等特点,具有较强的市场竞争力。The prefabricated beams, prefabricated columns and other prefabricated components are integrally poured on site, the structural force is reasonable, and the overall performance is equivalent to that of ordinary cast-in-place concrete structures. It has the characteristics of safety and reliability, simplified construction, saving materials, reducing dust and construction waste, etc. Market Competitiveness.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (10)

1.一种装配式结构体系,其特征在于,包括:基础、预制柱以及预制柱梁;1. A prefabricated structural system, characterized in that it comprises: a foundation, prefabricated columns and prefabricated column beams; 所述基础包括基础本体以及设置在所述基础本体内且伸出所述基础本体的上端面的基础钢筋;所述预制柱包括柱钢筋笼以及两端开口的柱外壳,所述柱外壳包裹在所述柱钢筋笼的外侧;所述预制柱梁包括柱梁钢筋笼以及至少两端开口的柱梁外壳,所述柱梁外壳包裹在所述柱梁钢筋笼的外侧;The foundation includes a foundation body and foundation steel bars that are arranged in the foundation body and protrude from the upper end surface of the foundation body; the prefabricated column includes a column reinforcement cage and a column shell with openings at both ends, and the column shell is wrapped in The outside of the column reinforcement cage; the prefabricated column beam includes a column beam reinforcement cage and a column beam shell with openings at least at both ends, and the column beam shell is wrapped on the outside of the column beam reinforcement cage; 还包括基础连接钢筋;所述基础连接钢筋的一端与所述基础钢筋连接,另一端与所述柱钢筋笼的下端连接;It also includes foundation connecting reinforcement; one end of the foundation connecting reinforcement is connected to the foundation reinforcement, and the other end is connected to the lower end of the column reinforcement cage; 还包括柱连接钢筋笼以及梁柱连接钢筋;所述梁柱连接钢筋的延伸方向与所述预制柱梁的延伸方向一致,所述柱连接钢筋笼的一端与所述柱钢筋笼的上端连接,两个所述预制柱梁一一位于所述预制柱的上端的两侧,所述梁柱钢筋穿过所述柱连接钢筋笼,且一端与一个所述梁钢筋笼连接,另一端与另一个所述梁钢筋笼连接;所述预制柱竖直设置,所述预制梁水平设置;It also includes a column connection reinforcement cage and a beam-column connection reinforcement; the extension direction of the beam-column connection reinforcement is consistent with the extension direction of the prefabricated column beam, and one end of the column connection reinforcement cage is connected to the upper end of the column reinforcement cage, The two prefabricated column beams are located on both sides of the upper end of the prefabricated column, and the beam-column reinforcement passes through the column connection reinforcement cage, and one end is connected to one of the beam reinforcement cages, and the other end is connected to the other. The beams are connected with reinforcement cages; the prefabricated columns are arranged vertically, and the prefabricated beams are arranged horizontally; 所述预制柱的内腔、所述预制柱梁的内腔、所述基础连接钢筋处以及所述柱连接钢筋笼均现场浇筑有施工混凝土。The inner cavity of the prefabricated column, the inner cavity of the prefabricated column beam, the foundation connection reinforcement and the column connection reinforcement cage are all poured with construction concrete on site. 2.根据权利要求1所述的装配式结构体系,其特征在于,还包括延伸方向与所述预制柱的延伸方向一致的柱连接纵筋;所述预制柱为多个,多个所述预制柱由上而下依次设置,处于最底层的预制柱通过所述基础连接钢筋与所述基础连接;2. The prefabricated structural system according to claim 1, characterized in that, it also includes column connecting longitudinal reinforcements whose extension direction is consistent with that of the prefabricated column; there are multiple prefabricated columns, and multiple prefabricated columns The columns are arranged sequentially from top to bottom, and the prefabricated columns at the bottom are connected to the foundation through the foundation connecting reinforcement; 相邻两个所述预制柱中,位于上方的为上层预制柱,位于下方的为下层预制柱;每相邻两个所述预制柱之间均设置有柱连接钢筋笼以及柱连接纵筋,其中,所述柱连接钢筋笼与所述下层预制柱的钢筋笼连接,所述柱连接纵筋的一端与所述上层预制柱的纵筋连接,另一端插入所述柱连接钢筋笼并固定;Among the two adjacent prefabricated columns, the upper one is the upper prefabricated column, and the lower one is the lower prefabricated column; a column connecting reinforcement cage and a column connecting longitudinal reinforcement are arranged between each adjacent two prefabricated columns, Wherein, the column connection reinforcement cage is connected with the reinforcement cage of the lower prefabricated column, one end of the column connection longitudinal reinforcement is connected with the longitudinal reinforcement of the upper prefabricated column, and the other end is inserted into the column connection reinforcement cage and fixed; 上层预制柱、下层预制柱以及所述柱连接钢筋笼同时现场浇筑有所述施工混凝土。The upper prefabricated column, the lower prefabricated column and the column connecting reinforcement cage are simultaneously poured with the construction concrete on site. 3.根据权利要求1所述的装配式结构体系,其特征在于,还包括第一预制次梁,所述第一预制次梁包括第一次梁钢筋笼以及至少两端开口的第一次梁外壳,所述第一次梁外壳包裹在所述第一次梁钢筋笼的外侧;3. The prefabricated structural system according to claim 1, further comprising a first prefabricated secondary beam, said first prefabricated secondary beam comprising a primary beam reinforcement cage and a primary beam with openings at least at both ends an outer shell, the outer shell of the first beam is wrapped around the reinforcement cage of the first beam; 还包括第一主次梁连接口以及第一主次梁连接纵筋;所述第一主次梁连接口设置在所述柱梁外壳上的指定位置,所述第一主次梁连接纵筋的一端插设在所述第一主次梁连接口内,另一端与所述第一次梁钢筋笼连接;It also includes a first primary and secondary beam connecting port and a first primary and secondary beam connecting longitudinal reinforcement; the first primary and secondary beam connecting port is arranged at a designated position on the column-beam shell, and the first primary and secondary beam connecting longitudinal reinforcement one end of which is inserted into the first primary and secondary beam connection port, and the other end is connected to the primary beam reinforcement cage; 所述第一主次梁连接口以及所述第一预制次梁的内腔同时现场浇筑有施工混凝土。The first primary and secondary beam connection ports and the inner cavity of the first prefabricated secondary beam are simultaneously poured with construction concrete on site. 4.根据权利要求1所述的装配式结构体系,其特征在于,还包括两个第二预制次梁,两个所述第二预制次梁相对设置在所述预制柱梁的两侧;4. The prefabricated structural system according to claim 1, further comprising two second prefabricated secondary beams, the two second prefabricated secondary beams are oppositely arranged on both sides of the prefabricated column beams; 每个所述第二预制次梁包括第二次梁钢筋笼以及至少两端开口的第二次梁外壳,所述第二次梁外壳包裹在所述第二次梁钢筋笼的外侧;Each of the second prefabricated secondary beams includes a second beam reinforcement cage and a second beam shell with at least two ends open, and the second beam shell is wrapped around the outside of the second beam reinforcement cage; 还包括第二主次梁连接口以及第二主次梁连接钢筋;所述第二主次梁连接口设置在所述柱梁外壳上的指定位置,所述第二主次梁连接钢筋穿设在所述第二主次梁连接口内,所述第二主次梁连接贯通纵筋的一端与一个所述第二次梁钢筋笼连接,另一端与另一个所述第二次梁钢筋笼连接;It also includes a second primary and secondary beam connecting port and a second primary and secondary beam connecting reinforcement; the second primary and secondary beam connecting port is arranged at a designated position on the column-beam shell, and the second primary and secondary beam connecting reinforcing bar is passed through In the connection port of the second primary and secondary beams, one end of the second primary and secondary beams connecting through longitudinal bars is connected to one of the second beam reinforcement cages, and the other end is connected to the other second beam reinforcement cage ; 所述第二主次梁连接口以及所述预制次梁的内腔同时浇筑有施工混凝土。Construction concrete is poured at the connection port of the second primary and secondary beams and the inner cavity of the prefabricated secondary beams at the same time. 5.根据权利要求2所述的装配式结构体系,其特征在于,所述柱连接钢筋笼与所述柱钢筋笼一体设置;5. The fabricated structural system according to claim 2, characterized in that, the column connecting reinforcement cage is integrated with the column reinforcement cage; 所述柱钢筋笼包括柱钢筋网片组以及所述柱外壳的延伸方向延伸的柱纵筋,所述柱外壳包裹在所述钢筋网片组外,所述柱纵筋设置在所述钢筋网片组内;The column reinforcement cage includes a column reinforcement mesh group and column longitudinal reinforcement extending in the extension direction of the column casing, the column casing is wrapped outside the reinforcement mesh group, and the column longitudinal reinforcement is arranged on the reinforcement mesh in the film group; 所述柱连接纵筋与所述柱纵筋一体设置。The column connecting longitudinal reinforcement is integrated with the column longitudinal reinforcement. 6.根据权利要求1-5中任一项所述的装配式结构体系,其特征在于,所述梁柱连接钢筋包括梁柱连接腰筋;所述梁柱连接腰筋穿设在所述柱连接钢筋笼内,且所述梁柱连接腰筋的一端搭接在一个所述梁钢筋笼上,另一端搭接在另一个所述梁钢筋笼上;6. The prefabricated structural system according to any one of claims 1-5, characterized in that, the beam-column connecting steel bars include beam-column connecting waist bars; the beam-column connecting waist bars are installed on the column connected to the reinforcement cage, and one end of the beam-column connecting waist bar is overlapped on one of the beam reinforcement cages, and the other end is overlapped on the other beam reinforcement cage; 和/或,所述梁柱连接钢筋还包括梁柱贯通纵筋;所述梁柱贯通纵筋穿过所述柱连接钢筋笼,所述梁柱贯通纵筋的一端搭接在一个梁钢筋笼的远离所述柱连接钢筋笼的一端,另一端搭接在另一个所述梁钢筋笼远离所述柱连接钢筋笼的一端。And/or, the beam-column connection reinforcement further includes a beam-column through-through longitudinal bar; the beam-column through-through longitudinal bar passes through the column-connection reinforcement cage, and one end of the beam-column through-through longitudinal bar is lapped on a beam reinforcement cage One end of the reinforcement cage far away from the column connection, and the other end is lapped on the other end of the beam reinforcement cage away from the column connection reinforcement cage. 7.根据权利要求5所述的装配式结构体系,其特征在于,所述柱钢筋网片组包括多个沿所述柱纵筋的延伸方向依次间隔设置的多个柱钢筋网片;7. The fabricated structural system according to claim 5, wherein the group of column reinforcement meshes comprises a plurality of column reinforcement meshes sequentially arranged at intervals along the extension direction of the column longitudinal reinforcement; 每个所述柱钢筋网片均包括多个柱第一筋以及多个柱第二筋;多个所述柱第一筋与多个所述柱第二筋一一交错设置,以形成网格结构;多个所述柱第一筋的两端均伸出所有所述柱第二筋外,多个所述柱第二筋的两端均伸出所有所述柱第一筋外;Each of the column reinforcement mesh sheets includes a plurality of column first reinforcements and a plurality of column second reinforcements; a plurality of the column first reinforcements and a plurality of the column second reinforcements are arranged alternately to form a grid Structure; both ends of the plurality of first ribs of the columns extend out of all the second ribs of the columns, and both ends of the plurality of second ribs of the columns extend out of the first ribs of all the columns; 所述柱外壳包括首尾依次连接的柱第一侧板,柱第三侧板,柱第二侧板以及柱第四侧板,多个所述柱第一筋的第一端均所述柱第一侧板连接,多个所述柱第一筋的第二端均与所述柱第二侧板连接,多个所述柱第二筋的第一端与所述柱第三侧板连接,多个所述柱第二筋的第二端均与所述柱第四侧板连接。The column shell includes the first column side panel, the column third side panel, the column second side panel and the column fourth side panel connected end to end in sequence, and the first ends of the plurality of column first ribs are connected to the column second side panel. One side plate is connected, the second ends of the plurality of first ribs of the column are connected with the second side plate of the column, the first ends of the second ribs of the plurality of columns are connected with the third side plate of the column, The second ends of the plurality of second ribs of the column are all connected to the fourth side plate of the column. 8.根据权利要求7所述的装配式结构体系,其特征在于,所述柱第一筋的两端均设置有柱第一凸起,所述柱第一凸起的截面尺寸大于所述柱第一筋的截面尺寸;8. The prefabricated structure system according to claim 7, characterized in that, both ends of the first rib of the column are provided with a first projection of the column, and the cross-sectional size of the first projection of the column is larger than that of the column The cross-sectional size of the first rib; 多个所述柱第二筋的两端均设置有柱第二凸起,所述柱第二凸起的截面尺寸大于所述柱第二筋的截面尺寸。Both ends of the plurality of second ribs are provided with second protrusions, and the cross-sectional size of the second protrusions is larger than that of the second ribs. 9.根据权利要求1所述的装配式结构体系,其特征在于,所述柱梁外壳包括依次连接的柱梁左侧板、柱梁底板以及柱梁右侧板;所述柱梁钢筋笼包括柱梁钢筋网片组以及连接在所述柱梁钢筋网片组内的柱梁纵筋,所述柱梁左侧板连接在所述柱梁钢筋网片组的左外侧,所述柱梁右侧板连接在所述柱梁钢筋网片组的右外侧,所述柱梁底板连接在所述柱梁钢筋网片组的底外侧。9. The fabricated structural system according to claim 1, wherein the column-beam shell includes a column-beam left panel, a column-beam bottom panel, and a column-beam right panel connected in sequence; the column-beam reinforcement cage includes The column beam reinforcement mesh group and the column beam longitudinal reinforcement connected in the column beam reinforcement mesh group, the column beam left plate is connected to the left outer side of the column beam reinforcement mesh group, the column beam right The side plate is connected to the right outer side of the column-beam reinforcement mesh group, and the column-beam bottom plate is connected to the bottom outer side of the column-beam reinforcement mesh group. 10.根据权利要求9所述的装配式结构体系,其特征在于,所述柱梁钢筋网片包括相对设置的柱梁第一筋,以及沿所述柱梁第一筋的延伸方向依次间隔设置的多个柱梁第二筋;10. The prefabricated structure system according to claim 9, characterized in that, the column-beam reinforcement mesh sheet includes oppositely arranged first column-beam ribs, and is arranged at intervals along the extending direction of the column-beam first ribs The second reinforcement of multiple columns and beams; 多个所述柱梁第二筋的左端均伸出一个所述柱梁第一筋,多个所述柱梁第二筋的右端均伸出另一个所述柱梁第一筋;所述柱梁第一筋的下端均伸出所有所述柱梁第二筋;The left ends of a plurality of the second ribs of the column and beams all protrude from the first ribs of the column and beams, and the right ends of the second ribs of the plurality of column and beams all protrude from the other first ribs of the column and beams; The lower ends of the first ribs of the beam protrude from all the second ribs of the column and beam; 多个所述柱梁第二筋的左端均与所述柱梁左侧板连接,多个所述柱梁第二筋的右端均与所述柱梁右侧板连接,两个所述柱梁第一筋的下端均与所述柱梁底板连接;The left ends of the second ribs of the plurality of column beams are all connected to the left side panel of the column beam, the right ends of the second ribs of the plurality of column beams are all connected with the right side panel of the column beam, and the two column beams The lower ends of the first ribs are all connected to the column-beam bottom plate; 所述柱梁第一筋的下端设置有柱梁第一凸起,所述柱梁第一凸起的截面尺寸大于所述柱梁第一筋的截面尺寸。The lower end of the first rib of the column beam is provided with a first protrusion of the column beam, and the cross-sectional size of the first protrusion of the column beam is larger than the cross-sectional size of the first rib of the column beam.
CN201810738891.9A 2018-07-06 2018-07-06 Fabricated construction system Pending CN108560701A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810738891.9A CN108560701A (en) 2018-07-06 2018-07-06 Fabricated construction system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810738891.9A CN108560701A (en) 2018-07-06 2018-07-06 Fabricated construction system

Publications (1)

Publication Number Publication Date
CN108560701A true CN108560701A (en) 2018-09-21

Family

ID=63555699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810738891.9A Pending CN108560701A (en) 2018-07-06 2018-07-06 Fabricated construction system

Country Status (1)

Country Link
CN (1) CN108560701A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111350204A (en) * 2020-02-05 2020-06-30 重庆大学 a fabricated foundation
CN116791655A (en) * 2022-03-16 2023-09-22 巴拿那节能科技(厦门)有限公司 Pre-assembled raft foundation and construction method using same

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06306935A (en) * 1993-04-28 1994-11-01 Tobishima Corp Connection structure of column and beam of rc structure and its construction
JPH0711736A (en) * 1993-06-24 1995-01-13 Toda Constr Co Ltd Precast reinforced concrete columns
JPH0762731A (en) * 1993-08-27 1995-03-07 Okumura Corp Column / beam joining method
CN101660327A (en) * 2008-08-29 2010-03-03 万科企业股份有限公司 Connecting structure of precast concrete secondary beam and main beam, construction method and building
CN203866982U (en) * 2014-05-28 2014-10-08 江苏尚昇建设集团有限公司 Prefabricated beam end joint structure
CN104594561A (en) * 2014-12-22 2015-05-06 西安建筑科技大学 Prefabricated reinforced concrete column with high-performance concrete frame and construction method
KR101570484B1 (en) * 2014-06-27 2015-11-20 삼성물산 주식회사 Half-PC Column using lightweight Encased Inner Form And Manufacturing Method Thereof, And Construction Method Using The Same
CN105804241A (en) * 2016-03-22 2016-07-27 哈尔滨工业大学 Single-layer prefabricated assembly type reinforced concrete beam-column joint
CN108086693A (en) * 2017-12-13 2018-05-29 西南科技大学 A kind of assembled steel reinforced concrete frame structure system method of construction of low multilayer
CN208486362U (en) * 2018-07-06 2019-02-12 沈阳三一建筑设计研究有限公司 Fabricated construction system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06306935A (en) * 1993-04-28 1994-11-01 Tobishima Corp Connection structure of column and beam of rc structure and its construction
JPH0711736A (en) * 1993-06-24 1995-01-13 Toda Constr Co Ltd Precast reinforced concrete columns
JPH0762731A (en) * 1993-08-27 1995-03-07 Okumura Corp Column / beam joining method
CN101660327A (en) * 2008-08-29 2010-03-03 万科企业股份有限公司 Connecting structure of precast concrete secondary beam and main beam, construction method and building
CN203866982U (en) * 2014-05-28 2014-10-08 江苏尚昇建设集团有限公司 Prefabricated beam end joint structure
KR101570484B1 (en) * 2014-06-27 2015-11-20 삼성물산 주식회사 Half-PC Column using lightweight Encased Inner Form And Manufacturing Method Thereof, And Construction Method Using The Same
CN104594561A (en) * 2014-12-22 2015-05-06 西安建筑科技大学 Prefabricated reinforced concrete column with high-performance concrete frame and construction method
CN105804241A (en) * 2016-03-22 2016-07-27 哈尔滨工业大学 Single-layer prefabricated assembly type reinforced concrete beam-column joint
CN108086693A (en) * 2017-12-13 2018-05-29 西南科技大学 A kind of assembled steel reinforced concrete frame structure system method of construction of low multilayer
CN208486362U (en) * 2018-07-06 2019-02-12 沈阳三一建筑设计研究有限公司 Fabricated construction system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈忠范: "《工业化村镇建筑》", 30 June 2017, 东南大学出版社, pages: 36 - 39 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111350204A (en) * 2020-02-05 2020-06-30 重庆大学 a fabricated foundation
CN116791655A (en) * 2022-03-16 2023-09-22 巴拿那节能科技(厦门)有限公司 Pre-assembled raft foundation and construction method using same

Similar Documents

Publication Publication Date Title
CN104264786B (en) A Reinforcement Connection Method of Prefabricated Concrete Components and Its Application
CN110792163B (en) Prefabricated beam-column-slab connection node and construction method thereof
CN101736809A (en) Spatial light steel reinforced concrete frame building and construction method thereof
CN114293686A (en) Profiled steel reinforced concrete combined shear wall, connecting joint and construction method
CN117738322A (en) Prefabricated room module, building and construction method
WO2012065534A1 (en) Prefabricated reinforced concrete formwork and manufacturing method thereof, as well as building and construction method thereof
CN102071746B (en) T-shaped connecting node for superposed external wall and prefabricated internal wall of shear wall structure
CN104895231B (en) Assembled composite floor slab and manufacturing method thereof
CN110984367B (en) Prefabricated building frame structure component and construction method thereof
CN116220266B (en) Floor structure
CN210194867U (en) Assembly type building structure
CN102116058A (en) L-shaped connection node of superposed outer wall of shear wall structure
CN108560701A (en) Fabricated construction system
CN216920791U (en) T-shaped shear wall assembly and building structure
CN206090815U (en) Prefabricated assembled tube structure public building
CN114250898B (en) A bidirectional dense-rib cavity floor module for steel structure and construction method thereof
CN206581482U (en) A kind of assembled architecture of concrete prefabricated wallboard and its composition
CN217517913U (en) One-way multi-ribbed cavity floor module for steel structure
CN114232865B (en) Unidirectional multi-ribbed cavity floor system module for steel structure and construction method thereof
JPH04202940A (en) Wall construction of building and construction method thereof
CN110306656A (en) A prefabricated concrete frame structure and its construction technology
CN117403934A (en) Novel assembled concrete structure system for low-rise residence
CN204571004U (en) A kind of assembly type heat-preservation shear wall element of construction and structural system
CN114164978A (en) One-way dense rib cavity floor module for steel structure and construction method thereof
CN210105041U (en) Self-supporting prefabricated steel reinforced concrete wallboard component, wall and structural system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 102200 Room 302, building 6, 8 Beiqing Road, Changping District, Beijing

Applicant after: Beijing Sany Architectural Design Research Co.,Ltd.

Address before: 110000 rooms 1701 and 1702, No. 92 Shengli South Street, Shenyang City, Liaoning Province

Applicant before: SHENYANG SANYI BUILDING DESIGN RESEARCH Co.,Ltd.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20180921

RJ01 Rejection of invention patent application after publication