CN108457409A - A kind of string hangs the external decoration facade and its installation method of clay brick - Google Patents

A kind of string hangs the external decoration facade and its installation method of clay brick Download PDF

Info

Publication number
CN108457409A
CN108457409A CN201810468902.6A CN201810468902A CN108457409A CN 108457409 A CN108457409 A CN 108457409A CN 201810468902 A CN201810468902 A CN 201810468902A CN 108457409 A CN108457409 A CN 108457409A
Authority
CN
China
Prior art keywords
clay brick
hanging rod
installation
string
brick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810468902.6A
Other languages
Chinese (zh)
Inventor
孟宁
刘威
吉乃木沙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Decoration Engineering Co Ltd
China Construction Eighth Bureau Decoration Engineering Co Ltd
Original Assignee
China Construction Eighth Bureau Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Bureau Decoration Engineering Co Ltd filed Critical China Construction Eighth Bureau Decoration Engineering Co Ltd
Priority to CN201810468902.6A priority Critical patent/CN108457409A/en
Publication of CN108457409A publication Critical patent/CN108457409A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The present invention provides the external decoration facades that a kind of string hangs clay brick, it is characterised in that:Including clay brick skeleton, hanging rod component and clay brick;Wherein, the clay brick skeleton includes several main joists and several transoms;The main joist is vertically arranged in parallel on metope;The transom is set in parallel longitudinal, lateral same level height between main joist, is divided into several to install window metope with main joist;Each installation window is arranged with basic splash guard;It is fixed with L-type support frame on the position of the transom;The hanging rod component includes hanging rod;The hanging rod is fixedly connected with L-type support frame;The clay brick string is hung on hanging rod.The installation that method and structure through the invention carries out, decorative effect have the guarantee of explicitly, improve the surface smoothness and verticality of clay brick.Meanwhile the method increase the construction efficiency of clay brick installation.

Description

A kind of string hangs the external decoration facade and its installation method of clay brick
Technical field
The present invention relates to construction process fields, and in particular, to a kind of string hangs external decoration facade and its installation of clay brick Method.
Background technology
The project that country's large area uses string extension clay brick to carry out decoration of exterior wall at present is less, most of to use decoration of exterior wall Phenomena such as that there are seams is not straight for the project of brick, and gap width differs, generally in process of construction, when to hang the clay brick scale of construction big for string, Hole is more, closes up complicated, and when material required precision is high, the verticality and flatness of clay brick can not be effectively ensured, so, material Processing and installation accuracy be maximum difficult point in work progress.
Invention content
The present invention is directed to overcome drawbacks described above, a kind of installation difficulty of solution large area string extension clay brick external wall construction is provided The mounting process of problem.
The present invention provides the external decoration facades that a kind of string hangs clay brick, it is characterised in that:Including clay brick skeleton, hanging rod Component and clay brick;
Wherein, above-mentioned clay brick skeleton includes several main joists and several transoms;The quantity of the main joist and transom It is hung according to the size of metope and string and arranges to be configured.
Above-mentioned main joist is vertically arranged in parallel on metope;
Above-mentioned transom is set between main joist in parallel longitudinal, lateral same level height, with main joist by metope It is divided into several that window is installed;
Each installation window is arranged with basic splash guard;
It is fixed with L-type support frame on the position of above-mentioned transom;
The basis splash guard can cover transom, to which L-type support frame is consolidated by basic splash guard and transom Dingan County fills;The basis splash guard can also be laid with using upper and lower two L-type support frames as edge respectively;
Above-mentioned hanging rod component includes hanging rod;The hanging rod be typically in or beyond screw thread the body of rod, can by with nut Or the mode of inner thread sleeve connection realizes being fixed to each other between multiple components.
Above-mentioned hanging rod is fixedly connected with L-type support frame;The fixed method such as has riveting, is spirally connected at the directly fixed mode, Or in L-type support frame be equipped with can accommodate hanging rod by through-hole, realized in such a way that hanging rod is sealed in through-hole, Hanging rod is fixed and supported on plate, it is further realized into opposite position with other structures/component by equipment such as sleeves again later The fixation set.In general, its top of the hanging rod of top and bottom or end are carried out using the modes such as be spirally connected, the extension of middle section It is installed in such a way that sleeve or sleeve cooperation are spirally connected between bar.
Above-mentioned clay brick string is hung on hanging rod.At one install window in string hang process can be from bottom to up ( In the present invention, in order to avoid being socketed the unnecessary components such as screw, and the convenience installed, often installed using from lower layer Carried out to the mode on upper layer) installation or installation from top to bottom.Sequence about each installation window can also adopt With from bottom to up installation from top to bottom or from it is intermediate upwards under mounting means carry out.
Further, a kind of string provided by the invention hangs the external decoration facade of clay brick, also has a structure in which feature: I.e., above-mentioned hanging rod component further includes sleeve;
The hanging rod of both sides passes through the fixation that sleeve carries out relative position above and below above-mentioned L-type support frame.
Further, a kind of string provided by the invention hangs the external decoration facade of clay brick, also has a structure in which feature: I.e., bed course is equipped between above-mentioned clay brick.I.e., upper, lower, left and right positions can be equipped with bed course.
Further, a kind of string provided by the invention hangs the external decoration facade of clay brick, also has a structure in which feature: I.e., it is in the setting of I-shaped seam type between above-mentioned clay brick.Fasten the mounting means of lower dislocation, that is to say, that general on clay brick Two or more holes can be beaten, to ensure the stability of arranged in dislocation.
Further, a kind of string provided by the invention hangs the external decoration facade of clay brick, also has a structure in which feature: I.e., above-mentioned clay brick includes L font clay bricks;Effect for successively sealing.The seal location can also have bed course.
Above-mentioned L fonts clay brick is set to L-type support frame both sides up and down.
Further, a kind of string provided by the invention hangs the external decoration facade of clay brick, also has a structure in which feature: I.e., further include top waterproof construction;
Above-mentioned top waterproof construction includes proof mechanism of water at the top of first of top proof mechanism of water and second;
Wherein, the upper edge of the basic splash guard at above-mentioned first of top proof mechanism of water masking top;
Proof mechanism of water is installed on the top of first of top proof mechanism of water at the top of above-mentioned second, covers the clay at top Brick.
Further, a kind of string provided by the invention hangs the external decoration facade of clay brick, also has a structure in which feature: I.e., further include bottom waterproof construction;
Above-mentioned bottom waterproof construction is set on the extending direction of basic splash guard of bottom.
In addition, the present invention also provides a kind of method that external decoration facade string hangs clay brick, hung for installing string as above The external decoration facade of clay brick, which is characterized in that carried out using following processing step:
S1. surveying setting-out:Axis is drawn out to the construction surface of outer curtain wall by datum line when according to main structure construction, according to One layer of indoor elevation line leads to clay brick construction finished surface using spirit level;The outdoor elevation line of review, is applied with carrying out agent structure The correction of work deviation and the accumulation for avoiding measurement error;It should be in conjunction with civil engineering structure construction deviation, by deviation point when surveying setting-out Solution prevents accumulated error;According to the finished surface axis and elevation line checked, snap the line will be carried out after main joist location determination, according to Snap the line determines angular position closing in size;
S2. keel are constructed, including the installation of main joist and the installation of transom;
S2-1. the installation of main joist:When main joist is installed, first by column and code should be connect by being bolted to wearing, it is vertical Column connect lower prop, lock pin and column close proximity with upright column joint by lock pin, is slidably matched, upper lower prop is fixed with bolt; Connection code is welded and fixed with embedded part, column installation post-tensioning in place sets logical line column whole height and verticality carries out school Core, timely fixing bolt after the completion of check;
S2-2. the installation of transom:It is according to the lattice size of construction drawing, the installation site of transom is accurate on column Really mark, transom and main joist be fixed with corner brace, the drilling bore hole position in transom, with fastener by anti-corrosion gasket and L-type support frame is fixed in transom;
S3. basic splash guard installation and gluing processing:The plate of basic splash guard is controlled according to the spacing of lateral L-type support frame Block size, adjacent two pieces batches of water aluminium sheets are directly handled using close spelling, ensure that top aluminium sheet pushes down lower section aluminium sheet, seam crossing gluing; It criticizes and is fixed by upper and lower L-type support frame above and below water aluminium sheet, aluminium sheet is covered with aluminum corner brace seam crossing gluing;Left and right is two pieces adjacent Aluminium sheet is using equally using laminated arrangement, seam crossing gluing;
S4. the cladding installation of the fixation of hanging rod and clay brick:According to the position of opening requirement of clay brick design, in L-type branch The fixed position of hanging rod is accurately positioned out on support, drilling bore hole position coordinates nut and gasket that hanging rod is fixed in transom, on Lower two hanging rods are vertically connected using sleeve, square above and/or under first by peg installs in L-type support frame when cladding Nut fixes hanging rod and L-type support frame, and clay brick, which is then penetrated hanging rod, carries out cladding installation, to be installed to hanging rod end When, female connector cylinder continues cladding remaining clay brick, after the completion of the earthenware brick among upper and lower L-type support frame is cladding, is inserted into hanging rod, Precession sleeve is tightened, then carries out the installation of follow-up clay brick.
Further, the method that a kind of external decoration facade string provided by the invention hangs clay brick, also has the characteristics that such: I.e., when cladding, the adjacent two pieces of clay brick bed courses in left and right are into between-line spacing, it is ensured that the vertical gap size between brick and brick;On Under adjacent two pieces of clay bricks be separated with bed course, ensure transverse slot size, answer section construction when clay brick is cladding, construction one Section checks one section, and every section is completed to be checked after construction, be adjusted, and is finally screwed end nut and is reinforced, it is ensured that cladding finished surface Seam verticality meets design requirement;
Meanwhile logical line is set according to drawing in time after the completion of every section of clay brick construction and carries out checking whole disengaging flatness, it is ensured that The flatness of cladding finished surface meets design requirement.
Further, the method that a kind of external decoration facade string provided by the invention hangs clay brick, also has the characteristics that such: I.e., further include top water-proofing treatment and bottom water-proofing treatment;
Above-mentioned top water-proofing treatment uses two pass waterproof process;
Wherein, first of waterproof process is:Using aluminium sheet sealing of bearing down on one at the top of all clay bricks;
Second waterproof process is:The installation that batch water steel plate is carried out after the completion of clay brick is cladding, ensures aluminium sheet glue-line suitable for reading Leakage hidden trouble caused by cracking;
Above-mentioned bottom water-proofing treatment is:In clay brick bottom using batch water aluminium sheet, extension fixation is carried out according to live structure, Bottom is handled using weather proofing sealant, ensures lower mouth waterproof.
The function and effect of the present invention:
The installation that method and structure through the invention carries out, decorative effect have the guarantee of explicitly, improve pottery The surface smoothness and verticality of cob brick.Meanwhile the method increase the construction efficiency of clay brick installation.
In addition, processing of the present invention by multiple waterproof, effectively increases the waterproof effect of clay brick curtain wall.
Description of the drawings
The string hanging hang structure schematic diagram for the decoration for vertical face wall that clay brick installation is hung using string that attached drawing 1, the present embodiment are related to;
The clay brick mounting plane effect diagram that attached drawing 2, the present embodiment are related to;
The top waterproof construction schematic diagram that attached drawing 3, the present embodiment are related to;
The bottom waterproof construction schematic diagram that attached drawing 4, the present embodiment are related to;
The stainless steel scheme of installation that attached drawing 5, the present embodiment are related to;
The clay brick string that attached drawing 6, the present embodiment are related to hangs schematic diagram;
The scheme of installation for the upper lateral part rust steel pole that attached drawing 7, the present embodiment are related to.
Specific implementation mode
A kind of external decoration facade of string extension clay brick is present embodiments provided, as shown in Figs 1-4, including clay brick skeleton, Stainless steel component and string hang the clay brick of technique;
The clay brick skeleton includes several main joists and the Zinc-coated angle steel transom 1 of several 50*50*4mm;The main joist is in Parallel is vertically arranged on metope;The transom is set in parallel longitudinal, lateral same level height between main joist, with Metope is divided into several to install window by main joist;L-type aluminum corner brace 3 is installed in the transom.Each installation window is arranged There is batch water aluminium sheet 2 that the 2mm with water-proof function is thick, surface is fluorocarbon-sprayed, the cover type that this batch of water aluminium sheet can be as shown in Figure 1 Be installed on transom after, then L-type aluminum corner brace is fixed thereon, can also be installed in the range of L-type aluminum corner brace up and down, It is sealed by the way of gluing with the interface of aluminum corner brace.
304 stainless steel screw thread bar assemblies include several stainless steel threaded rods 4 being vertically arranged in L-type aluminum corner brace, this is not Installation is fixed by gasket and L-type aluminum corner brace using M8 stainless steels nut in the end of rust steel threaded rod, and two above and below L-type aluminum corner brace Root stainless steel threaded rod is screwed tight using 304 stainless steel internally threaded sleeve 4-1;
The clay brick 5 of 240*60*60mm mode as shown in Figure 2, is hung in I-shaped string on stainless steel threaded rod, Pass through the polyester fiber gasket of 4mm thickness between clay brick up and down as shown in Figure 1.
As shown in figure 3, after the completion of entire Ornamented facade string is hung, the waterproof construction at the top of the installation of top;The top waterproof Structure is proof mechanism of water at the top of the structure of dual waterproof, including first of top proof mechanism of water and second;This first top Proof mechanism of water is water steel plate 6-2 waterproofs, and shape is the waterproof plate body that edge is inclined-plane, covers the top of batch water aluminium sheet at top Edge is exported water by the inclined-plane when there are leak;
Proof mechanism of water is aluminium sheet 6-1 waterproofs of bearing down on one at the top of the second, is installed on the top of first of top proof mechanism of water, There is the plate body of U-shaped protrusion, the U-shaped protrusion to protrude from clay brick facade for edge, it can be completely from the pottery at top masking top Cob brick.
As shown in figure 4, after the completion of entire Ornamented facade string is hung, bottom waterproof construction is also installed in bottom, the bottom is anti- Water-bound is, according to the environment of clay brick bottom and scene, according to live structure extend using 2mm batches of water aluminium sheets fixed Extended structure 7-1, bottom are sealed processing using weather proofing sealant 7-2, ensure effective waterproof of lower mouth with this.
As illustrated in figs. 5-7, concrete construction method is as follows:
1. surveying setting-out:
Axis is drawn out to the construction surface of outer curtain wall by datum line when according to main structure construction, according to one layer of indoor absolute altitude Line leads to clay brick construction finished surface using spirit level;The outdoor elevation line of review, to carry out the correction of main structure construction deviation And avoid the accumulation of measurement error;It should prevent accumulation from missing deviation decomposition in conjunction with civil engineering structure construction deviation when surveying setting-out Difference.According to the finished surface axis and elevation line checked, snap the line will be carried out after main joist location determination, corner is determined according to snap the line Position closing in size.
2. keel are constructed:
The installation of 2.1 main joists
When main joist is installed, first by column and should connect code by being bolted to wearing, column and upright column joint pass through slotting The upper lower prop of core connection, lock pin and column close proximity, are slidably matched, and upper lower prop is fixed with bolt, and lock pin is inserted into the length of upper lower prop Degree is preferably greater than 150mm and meets related specifications and design requirement, and there are the gaps of 15mm between upper lower prop.It will connection code and embedded part It is welded and fixed, column installation post-tensioning in place sets logical line column whole height and verticality is checked, after the completion of check Timely fixing bolt.Column installed height mark deviation should not exceed 3mm, and deviation should not exceed 2mm before and after axis, and left-right deviation is not answered More than 3mm.Adjacent two root posts installed height mark deviation should not exceed 3mm, and the maximum absolute altitude deviation of same layer entirety column should not be big In 5mm;The range deviation of adjacent two root posts should not exceed 2mm.
The installation of 2.2 transoms
According to the lattice size of construction drawing, the installation site of transom is accurately marked on column, it will be horizontal with corner brace Keel are fixed with main joist.Anti-corrosion gasket and L-type aluminum corner brace are fixed on horizontal dragon by the drilling bore hole position in transom with fastener On bone.Crossbeam should be met the following requirements when installing:The connection code and resilient rubbber cushion at crossbeam both ends are pre-positioned mounted on column It sets, it is desirable that firmly install, seam is tight;The horizontal absolute altitude deviation of adjacent two crossbeams is not more than l mm, and same layer absolute altitude deviation is not More than 5mm;To avoid installation accumulated error value excessive, after the completion of every layer of keel installation, it should be checked, checked, be adjusted in time It is whole, ensure control errors in designing quality claimed range.
3. batch water aluminium sheet installation and gluing processing:
Criticizing water aluminium sheet uses 2mm aluminum veneers, the fluorocarbon-sprayed processing in surface to enhance durability.According between lateral L-type aluminum corner brace Plate size away from control batch water aluminium sheet, adjacent two pieces batches of water aluminium sheets are directly handled using close spelling, ensure that top aluminium sheet is pushed down down Square aluminium sheet 3-5mm, seam crossing gluing;It criticizes and is fixed by upper and lower L-type aluminum corner brace above and below water aluminium sheet, aluminium sheet and aluminum corner brace seam crossing Gluing covers;The adjacent two blocks of aluminium sheets in left and right are using equally using laminated arrangement, two blocks of aluminium sheets are superimposed 3-5mm, seam crossing gluing.Batch Water aluminium sheet is fixed using sunk screw, and gluing covering in screw surface ensures leakproofness.
4. the fixation of stainless steel and the cladding installation of clay brick:
According to the position of opening requirement of clay brick design, the fixation of stainless steel threaded rod is accurately positioned out in L-type aluminum corner brace Position, drilling bore hole position coordinate nut and gasket that stainless steel is fixed in transom.Upper and lower two stainless steels are using stainless Steel screw shell vertically connects.The length of single clay brick stainless steel is identical as the vertical spacing of curtain wall transom, when installation not Rust steel pole should be synchronized with the cladding process of clay brick to carry out installing one layer of stainless steel and then carries out the clay brick of this layer It is cladding.When cladding, first stainless steel is mounted in the L-type aluminum corner brace of downside, by the nut of lower section by stainless steel and L-type aluminum corner brace It is fixed, clay brick is then penetrated into stainless steel and carries out cladding installation, upper and lower cladding guarantee " I-shaped seam " installation of clay brick waits pacifying It is filled to stainless steel end, accesses stainless steel sleeve, continues cladding remaining clay brick, the earthenware brick among upper and lower L-type aluminum corner brace After the completion of cladding, it is inserted into the stainless steel of upside from top to bottom, and will be tightened in its precession stainless steel sleeve, then carries out last layer Clay brick installation.
5. the quality control of clay brick
5.1 clay brick processing quality controls
Mismachining tolerance is strictly controlled in clay brick process, surface smoothness control errors are used within 2mm before installing Sand paper is suitably polished, and the cleaning waste slag that clay brick surface is retained in process is clean.
Finished product protection in 5.2 transportational processes
The clay brick produced must use wooden case to carry out joint sealing protection, be carried out with foamed plastics between wooden case and clay brick Caching liner.
5.3 clay brick trepanning holes position deviation adjusting
The hole position offset generated in clay brick sintering procedure is modified, is repaiied using hand-held cutting machine device to hole position It is whole, ensure the centre-to-centre spacing trueness error control of clay brick hole position within 2mm.
5.4 seams control
When cladding, the adjacent two pieces of clay bricks in left and right are with the hard cushion block of 10mm into between-line spacing, it is ensured that between brick and brick Vertical gap size;Neighbouring two pieces of clay bricks are separated with 4mm hard washers, ensure transverse slot size, clay brick Answer section construction when cladding, construct one section and check one section, every section is completed to be checked after construction, be adjusted, last tightening nut into Row is reinforced, it is ensured that cladding finished surface seam verticality meets design requirement.
5.5 overall effects control.
Logical line is set after the completion of every section of clay brick construction according to drawing in time to carry out checking whole disengaging flatness, it is ensured that cladding complete Meet design requirement at the flatness in face.
6 cladding clay brick curtain wall waterproofs
6.1 big face waterproofs
The big face waterproof of cladding clay brick relies primarily on batch water aluminum veneer and carries out waterproof, is used between adjacent left and right aluminium sheet resistance to It waits fluid sealant to be sealed, neighbouring aluminium sheet carries out gluing with L-type crossbeam aluminum corner brace delivery position, all to use nail fixed part Position carries out gluing sealing, ensures the integrality of waterproof system, is conserved after the completion of big face gluing 2-3 days and carry out water pouring test, it is ensured that The installation of clay brick is carried out after no infiltration again.
6.2 top waterproofs
Top uses two pass waterproof, that is, criticizes water steel plate waterproof and aluminium sheet waterproof of bearing down on one.It uses and bears down on one at the top of all clay bricks Aluminium sheet seals, and according to drawing lattice, there are the gaps 15mm to carry out gluing processing for aluminium sheet seam crossing;It is carried out after the completion of clay brick is cladding The installation for criticizing water steel plate, leakage hidden trouble caused by ensureing aluminium sheet glue-line cracking suitable for reading, constitutes second waterproof.
6.3 bottom waterproofs
Clay brick bottom is extended according to live structure and is fixed using 2mm batches of water aluminium sheets, and bottom uses at weather proofing sealant Reason ensures lower mouth waterproof.

Claims (10)

1. a kind of string hangs the external decoration facade of clay brick, it is characterised in that:Including clay brick skeleton, hanging rod component and clay brick;
Wherein, the clay brick skeleton includes several main joists and several transoms;
The main joist is vertically arranged in parallel on metope;
The transom is set in parallel longitudinal, lateral same level height between main joist, divides metope with main joist At several installation windows;
Each installation window is arranged with basic splash guard;
It is fixed with L-type support frame on the position of the transom;
The hanging rod component includes hanging rod;
The hanging rod is fixedly connected with L-type support frame;
The string of the clay brick from bottom to up is hung on hanging rod.
2. a kind of string as described in claim 1 hangs the external decoration facade of clay brick, it is characterised in that:
The hanging rod component further includes sleeve;
The hanging rod of both sides passes through the fixation that sleeve carries out relative position above and below the L-type support frame.
3. a kind of string as described in claim 1 hangs the external decoration facade of clay brick, it is characterised in that:
Bed course is equipped between the clay brick.
4. a kind of string as described in claim 1 hangs the external decoration facade of clay brick, it is characterised in that:
It is in the setting of I-shaped seam type between the clay brick.
5. a kind of string as described in claim 1 hangs the external decoration facade of clay brick, it is characterised in that:
The clay brick includes L font clay bricks;
The L fonts clay brick is set to L-type support frame both sides up and down.
6. a kind of string as described in claim 1 hangs the external decoration facade of clay brick, it is characterised in that:
It further include top waterproof construction;
The top waterproof construction includes proof mechanism of water at the top of first of top proof mechanism of water and second;
Wherein, the upper edge of the basic splash guard at first of top proof mechanism of water masking top;
Proof mechanism of water is installed on the top of first of top proof mechanism of water at the top of the second, covers the clay brick at top.
7. a kind of string as described in claim 1-6 is any hangs the external decoration facade of clay brick, it is characterised in that:
It further include bottom waterproof construction;
The bottom waterproof construction is set on the extending direction of basic splash guard of bottom.
8. a kind of method that external decoration facade string hangs clay brick hangs clay for installing the string as described in claim 1-7 is any The external decoration facade of brick, which is characterized in that carried out using following processing step:
S1. surveying setting-out:Axis is drawn out to the construction surface of outer curtain wall by datum line when according to main structure construction, according to one layer Indoor elevation line leads to clay brick construction finished surface using spirit level;The outdoor elevation line of review, it is inclined to carry out main structure construction The correction of difference and the accumulation for avoiding measurement error;Deviation should be decomposed anti-in conjunction with civil engineering structure construction deviation when surveying setting-out Only accumulated error;According to the finished surface axis and elevation line checked, snap the line will be carried out after main joist location determination, according to snap the line Determine angular position closing in size;
S2. keel are constructed, including the installation of main joist and the installation of transom;
S2-1. the installation of main joist:When main joist is installed, first by column and code should be connect by being bolted to wearing, column and Upright column joint connects upper lower prop, lock pin and column close proximity by lock pin, is slidably matched, upper lower prop is fixed with bolt;It will be even Jointer is welded and fixed with embedded part, and column installation post-tensioning in place sets logical line column whole height and verticality is checked, Timely fixing bolt after the completion of check;
S2-2. the installation of transom:According to the lattice size of construction drawing, the installation site of transom is accurately marked on column Go out, transom and main joist are fixed with corner brace, the drilling bore hole position in transom, with fastener by anti-corrosion gasket and L-type Supporting rack is fixed in transom;
S3. basic splash guard installation and gluing processing:The plate ruler of basic splash guard is controlled according to the spacing of lateral L-type support frame Very little, adjacent two pieces batches of water aluminium sheets are directly handled using close spelling, ensure that top aluminium sheet pushes down lower section aluminium sheet, seam crossing gluing;Criticize water It is fixed by upper and lower L-type support frame above and below aluminium sheet, aluminium sheet is covered with aluminum corner brace seam crossing gluing;The adjacent two blocks of aluminium sheets in left and right Using equally using laminated arrangement, seam crossing gluing;
S4. the cladding installation of the fixation of hanging rod and clay brick:According to the position of opening requirement of clay brick design, in L-type support frame On the fixed position of hanging rod is accurately positioned out, drilling bore hole position coordinates nut and gasket that hanging rod is fixed in transom, upper and lower two Root hanging rod is vertically connected using sleeve, when cladding, first by peg installs in L-type support frame, and the square nut above and/or under Hanging rod and L-type support frame are fixed, clay brick, which is then penetrated hanging rod, carries out cladding installation, when the end to be installed to hanging rod, connects Sleeve continues cladding remaining clay brick, after the completion of the earthenware brick among upper and lower L-type support frame is cladding, is inserted into hanging rod, precession set Cylinder is tightened, then carries out the installation of follow-up clay brick.
9. the method that a kind of external decoration facade string as claimed in claim 8 hangs clay brick, it is characterised in that:
When cladding, the adjacent two pieces of clay brick bed courses in left and right are into between-line spacing, it is ensured that the vertical gap size between brick and brick;On Under adjacent two pieces of clay bricks be separated with bed course, ensure transverse slot size, answer section construction when clay brick is cladding, construction one Section checks one section, and every section is completed to be checked after construction, be adjusted, and is finally screwed end nut and is reinforced, it is ensured that cladding finished surface Seam verticality meets design requirement;
Meanwhile logical line is set according to drawing in time after the completion of every section of clay brick construction and carries out checking whole disengaging flatness, it is ensured that is cladding The flatness of finished surface meets design requirement.
10. the method that a kind of external decoration facade string as claimed in claim 8 hangs clay brick, it is characterised in that:
Further include top water-proofing treatment and bottom water-proofing treatment;
The top water-proofing treatment uses two pass waterproof process;
Wherein, first of waterproof process is:Using aluminium sheet sealing of bearing down on one at the top of all clay bricks;
Second waterproof process is:The installation that batch water steel plate is carried out after the completion of clay brick is cladding ensures aluminium sheet glue-line cracking suitable for reading Caused by leakage hidden trouble;
The bottom water-proofing treatment is:In clay brick bottom using batch water aluminium sheet, extension fixation, bottom are carried out according to live structure It is handled using weather proofing sealant, ensures lower mouth waterproof.
CN201810468902.6A 2018-05-16 2018-05-16 A kind of string hangs the external decoration facade and its installation method of clay brick Pending CN108457409A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810468902.6A CN108457409A (en) 2018-05-16 2018-05-16 A kind of string hangs the external decoration facade and its installation method of clay brick

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810468902.6A CN108457409A (en) 2018-05-16 2018-05-16 A kind of string hangs the external decoration facade and its installation method of clay brick

Publications (1)

Publication Number Publication Date
CN108457409A true CN108457409A (en) 2018-08-28

Family

ID=63215274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810468902.6A Pending CN108457409A (en) 2018-05-16 2018-05-16 A kind of string hangs the external decoration facade and its installation method of clay brick

Country Status (1)

Country Link
CN (1) CN108457409A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914646A (en) * 2019-03-29 2019-06-21 上海方大勍瓴科技有限公司 Earthenware brick decorative wall and its installation method
CN110130550A (en) * 2019-05-31 2019-08-16 中建东方装饰有限公司 The dried hanging hang structure and its construction method of assembled hollow out earthenware brick curtain wall
CN113431237A (en) * 2021-05-17 2021-09-24 中国建筑第七工程局有限公司 Green brick grid curtain wall system and construction method thereof
CN113585657A (en) * 2021-06-25 2021-11-02 筑友建筑装饰装修工程有限公司 BIM-based dry hanging pottery clay brick exterior facing mounting structure and mounting method
CN114033075A (en) * 2021-10-28 2022-02-11 北京城建设计发展集团股份有限公司 Hollow ceramic brick curtain wall structure and construction process

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11141078A (en) * 1997-11-07 1999-05-25 Toshio Tamakoshi Coping and structure of rooftop parapet using it
JP2001065129A (en) * 1999-08-25 2001-03-13 Sekisui House Ltd Waterproofing structure of parapet
CN1333854A (en) * 1999-01-21 2002-01-30 中尾繁男 Blocks for wall surface of houses
KR20080101266A (en) * 2007-05-16 2008-11-21 주식회사 신우세라믹 The outer wall for easy construction
JP2014129682A (en) * 2012-12-28 2014-07-10 Takenaka Komuten Co Ltd Wall surface structure of brick wall, and construction method of brick wall
CN204001481U (en) * 2014-07-28 2014-12-10 冠鲁建设股份有限公司 A kind of cladding marble curtain wall parapet place water proof structure
CN205840219U (en) * 2016-07-22 2016-12-28 无锡金城幕墙装饰工程有限公司 A kind of clay brick stainless steel perforated support system
CN208219946U (en) * 2018-05-16 2018-12-11 中建八局装饰工程有限公司 A kind of string hangs the external decoration facade of clay brick

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11141078A (en) * 1997-11-07 1999-05-25 Toshio Tamakoshi Coping and structure of rooftop parapet using it
CN1333854A (en) * 1999-01-21 2002-01-30 中尾繁男 Blocks for wall surface of houses
JP2001065129A (en) * 1999-08-25 2001-03-13 Sekisui House Ltd Waterproofing structure of parapet
KR20080101266A (en) * 2007-05-16 2008-11-21 주식회사 신우세라믹 The outer wall for easy construction
JP2014129682A (en) * 2012-12-28 2014-07-10 Takenaka Komuten Co Ltd Wall surface structure of brick wall, and construction method of brick wall
CN204001481U (en) * 2014-07-28 2014-12-10 冠鲁建设股份有限公司 A kind of cladding marble curtain wall parapet place water proof structure
CN205840219U (en) * 2016-07-22 2016-12-28 无锡金城幕墙装饰工程有限公司 A kind of clay brick stainless steel perforated support system
CN208219946U (en) * 2018-05-16 2018-12-11 中建八局装饰工程有限公司 A kind of string hangs the external decoration facade of clay brick

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914646A (en) * 2019-03-29 2019-06-21 上海方大勍瓴科技有限公司 Earthenware brick decorative wall and its installation method
CN109914646B (en) * 2019-03-29 2021-01-05 上海方大勍瓴科技有限公司 Ceramic brick decorative wall and installation method thereof
CN110130550A (en) * 2019-05-31 2019-08-16 中建东方装饰有限公司 The dried hanging hang structure and its construction method of assembled hollow out earthenware brick curtain wall
CN113431237A (en) * 2021-05-17 2021-09-24 中国建筑第七工程局有限公司 Green brick grid curtain wall system and construction method thereof
CN113585657A (en) * 2021-06-25 2021-11-02 筑友建筑装饰装修工程有限公司 BIM-based dry hanging pottery clay brick exterior facing mounting structure and mounting method
CN114033075A (en) * 2021-10-28 2022-02-11 北京城建设计发展集团股份有限公司 Hollow ceramic brick curtain wall structure and construction process

Similar Documents

Publication Publication Date Title
CN108457409A (en) A kind of string hangs the external decoration facade and its installation method of clay brick
CN101824895B (en) Drily hung vitrolite wall surface decoration system and construction method thereof
CN102864932B (en) Construction method of hanging type transparent and implicit combined glass curtain wall
CN103061505B (en) A kind of multi-functional split bolt and uses thereof
CN103321434B (en) Cambered surface type unitized curtain wall construction method and structure
CN111677163B (en) Construction method of glass curtain wall
CN105756369B (en) A kind of structure built-in heat insulation decorates integrated prefabricated buildings and its construction method
CN102644382B (en) Mounting technology of large-module wall
CN105525712B (en) Slotted stone curtain wall system
CN104652740A (en) Installation method for thermal insulation and decoration integrated facade panels
CN108894488A (en) A kind of construction method of Novel section steel keel steel and wood composite template
CN103206088B (en) Parts of shear wall structure wall, slab integral pouring construction method
CN113006353A (en) Construction method of prefabricated hanging plate curtain wall
CN107630531B (en) Large-cantilever bare concrete stair and construction method thereof
CN112814235A (en) Construction method of layered diversion open type stone curtain wall
CN113931446A (en) Construction method of one-time pouring bay window template supporting structure
CN104153495A (en) Multifunctional lightweight concrete curtain wall connecting structure
CN208219946U (en) A kind of string hangs the external decoration facade of clay brick
CN207553360U (en) A kind of lightweight aerated concrete integrated wall plate with window
CN112726898B (en) Water-proof heat-insulating system for exposed brick exterior wall and construction method
CN204001309U (en) A kind of syndeton of Multi-function light concrete curtain wall
CN219081040U (en) Mounting and positioning structure for PCF (prestressed concrete cylinder pipe) board of assembled building
CN207017474U (en) A kind of antidetonation Low-rise Lightweight Steel framework lightweight concrete integral structure system
CN109083420A (en) Building body and indoor and outdoor decoration integral construction method
CN201649524U (en) Wall decoration system for dry-hanging porcelain plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination