CN108442380A - A kind of reservoir engineering shotcrete concrete construction - Google Patents

A kind of reservoir engineering shotcrete concrete construction Download PDF

Info

Publication number
CN108442380A
CN108442380A CN201710084567.5A CN201710084567A CN108442380A CN 108442380 A CN108442380 A CN 108442380A CN 201710084567 A CN201710084567 A CN 201710084567A CN 108442380 A CN108442380 A CN 108442380A
Authority
CN
China
Prior art keywords
spray
concrete
bar
jetting cement
mat reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710084567.5A
Other languages
Chinese (zh)
Inventor
冯立
王泽建
鲁飞
程福印
胡永彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang North Construction Group Co Ltd
Original Assignee
Xinjiang North Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang North Construction Group Co Ltd filed Critical Xinjiang North Construction Group Co Ltd
Priority to CN201710084567.5A priority Critical patent/CN108442380A/en
Publication of CN108442380A publication Critical patent/CN108442380A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

The invention discloses a kind of reservoir engineering shotcrete concrete constructions, during the reservoir construction of Southern Xinjiang, all there is destabilizing factor in all side slope rocks, stone is fallen at any time under its own gravity, especially rainy day, sometimes it has a large amount of rocks integrally to come down, there are severe compromise, spray shield must spray the case where protecting when excavating;The engineering method is optimized by protecting anchor pole, being laid with bar-mat reinforcement and jetting cement, and to specific construction parameter, and having reached reduces cost, improves the effect of working security.

Description

A kind of reservoir engineering shotcrete concrete construction
Technical field
The present invention relates to technical field of building construction more particularly to a kind of reservoir engineering shotcrete concrete constructions.
Background technology
Applicant enters Hami Prefecture in South Sinkiang section, and through painstaking efforts in a few years, water conservancy industry is opened in Hami Market, and established certain basis.This area is since geological structure is inconsistent, and according to design requirement, all excavation slopes are naked It is exposed at surface rock, to prevent weathering to be required to carry out spray shield processing.It is divided by construction part, every reservoir, which mainly sprays, protects and lead stream Spray shield in hole and irrigation tunnel inlet and outlet rock slope, diversion tunnel and irrigation tunnel hole, Spillway Slope spray shield, road slope spray protect and 5 parts of dam body side slope spray shield;According to live rock actual conditions, it is divided into shotcrete concrete and element spray concrete;All side slope rocks are all deposited In destabilizing factor, stone, especially rainy day are fallen at any time under its own gravity, have a large amount of rocks sometimes and integrally come down, There are severe compromise, spray shield must spray shield when excavating.
Invention content
Technical problems based on background technology, the present invention propose a kind of reservoir engineering shotcrete concrete construction.
Technical scheme is as follows:
A kind of reservoir engineering shotcrete concrete construction, includes the following steps:
A, the landing stage of scaffold is set up;
B, the slope surface cubic metre of earth and stone is cleared up:Remove surface dust, float stone at the top of linked network region;
C, anchor pole protects:It is by design elevation requirement, anchor pole hole site is accurate after the completion of bolthole surveying setting-out slope excavating For surveying setting-out in slope surface, hole position error must not exceed ± 50mm;
D, linked network and jetting cement:It is laid with bar-mat reinforcement and jetting cement;
Preferably, the bar-mat reinforcement laying method, includes the following steps:First injection 4~5cm thickness concretes close rock for jetting cement construction Face hangs bar-mat reinforcement, design thickness is sprayed onto again to just spraying after scar is cleared up.
When bar-mat reinforcement is laid with, following main points are should be noted:
A. bar-mat reinforcement spreads extension, protective layer thickness >=2cm after first 4~5cm of jetting cement;
B. bar-mat reinforcement is laid with the fluctuating of first spray plane, with the gap by spray plane it is general≤3cm;
Reduce nozzle when c. opening spray extremely by spray plane distance, and adjusts spray angle, bar-mat reinforcement protective layer thickness >=4cm;
When being blocked by bar-mat reinforcement if any the stone or concrete block to fall off in d. spraying, fill-before-fire concrete after removing in time.
Injection concrete ratio is designed according to the requirement of concrete strength and other physical and mechanical properties and spray technology, is specifically set Meter step includes the following steps:
Determine the maximum particle diameter and sand coarse aggregate ratio of aggregate;
Determine cement consumption;
Determine the ratio of mud and water consumption;
Determine sand, stone dosage;
Examination spray;
It adjusts, determine coordination in works.
Preferably, the injection concrete construction method, includes the following steps:
A, first to being handled by spray scar before injection, general scar is first with high pressure water washing by floating dust, the landwaste of spray scar, rock When the easy deliquescence of water, argillization are met in face, scar is blown off with high-pressure blast;
B, one layer of cement mortar, the fill-before-fire concrete after final set are first sprayed before jetting cement;
C, mark of the steel bar end as control jetting cement thickness is buried;
D, the routes of pipe line such as plant and wind, water, electricity are checked, by wet-spraying machine simultaneously test running in place;
E, concrete strictly presses coordination in works dispensing, and accelerator is added in spraying machine feeding;
F, jetting cement operation is carried out:Jetting cement using segmentation, fragment, be layered carry out successively, injection order from bottom to top, sector boss Degree≤6m.First low-lying place is substantially sprayed when injection and is put down, then sequence from low to uper part layering, reciprocal injection.
G, the final set of maintenance jetting cement is conserved in time after 2 hours, and curing time is not less than 14d;Temperature is prohibited when being less than 5 DEG C Only watering maintenance.
H, quality examination checks jetting cement surface, if has phenomena such as loosening, cracking, tenesmus, sliding, if any clear in time Except respraying.Sprinkler body can listen sound after reaching some strength with hammering, to being handled in time at hollowing shelling.Jewel hole measures, and thickness is not Enough places fill spray.Rebound degree and practical match ratio are measured in time, mechanical test is carried out to sprinkler body test specimen, to instruct lower step construction.
Preferably, when specific jetting cement operation, pay attention to following main points:
A) when section constructions, inclined-plane is reserved in leading portion jetting cement joint, surface width is 20~30cm, and pressure is first used on inclined-plane Power water rinses fill-before-fire concrete after wetting;
B) fragments are injected from down and upper progress;
C) when layerings injection, later layer carries out after being injected in preceding layer concrete final set.When being sprayed again after final set 1h, wind is first used Water cleans spray-up surface.The thickness of jetting cement is not slid with concrete not to fall to spend, and can neither influence concrete because thickness is too big Cohesive force and cohesiveness, can not be too thin and increase springback capacity.
D) controls jet velocity, compacted in favor of concrete.Wind pressure is excessive, and jet velocity increases, and rebound increases;Wind pressure Too small, jet velocity is too small, and compaction force is small, influences concrete strength.Therefore notice that observation wind pressure, starting wind pressure reach after powering Just start to operate after 0.5MPa, and wind pressure is adjusted according to nozzle discharging situation;
E) make nozzle when sprays and keep suitable distance between by spray plane, spray angle is as close possible to 90 °, to obtain maximum pressure Real and minimum rebound.Nozzle is controlled with by spray plane spacing in 1.5~2.0m.
The invention has the beneficial effects that:During the reservoir construction of Southern Xinjiang, all side slope rocks all exist not Ballast, falls stone, especially rainy day at any time under its own gravity, has a large amount of rocks sometimes and integrally comes down, exists Severe compromise, spray shield must spray shield when excavating;The present invention provides a kind of reservoir engineering shotcrete concrete construction, the works Method is optimized by protecting anchor pole, being laid with bar-mat reinforcement and jetting cement, and to specific construction parameter, reached reduction at This, improves the effect of working security.
Specific implementation mode
Embodiment:
A kind of reservoir engineering shotcrete concrete construction, includes the following steps:
A, the landing stage of scaffold is set up;
B, the slope surface cubic metre of earth and stone is cleared up:Remove surface dust, float stone at the top of linked network region;
C, anchor pole protects:It is by design elevation requirement, anchor pole hole site is accurate after the completion of bolthole surveying setting-out slope excavating For surveying setting-out in slope surface, hole position error must not exceed ± 50mm;
D, linked network and jetting cement:It is laid with bar-mat reinforcement and jetting cement;
The bar-mat reinforcement laying method, includes the following steps:First injection 4~5cm thickness concretes close scar for jetting cement construction, hang steel Muscle net is sprayed onto design thickness again to just spraying after scar is cleared up.
The described anchor pole protection, includes the following steps and construction point:
(1), after the completion of bolthole surveying setting-out slope excavating, by design elevation requirement, anchor pole hole site is accurately measured and is put For line in slope surface, hole position error must not exceed ± 50mm.The specific length of perpendicular rib can be determined according to practical slope height, but anchor pole Position must carry out setting-out by the length of decile slope surface, its spacing can adjust suitably.Such as existing brush side's slope surface irregularity or spy When different difficulty place, it need to approve through design surpervision unit, under the premise of ensuring slope stability and structure safety, it is fixed suitably to relax Position precision or adjustment anchor hole position
(2), the selection of drilling device drilling machine, according to the classification on anchoring stratum, anchor pole aperture, anchor pole depth and construction Site condition etc. selects drilling device.Diameter phi 50mm down-the-hole impact holings are used in rock stratum;In crushing rock formation or soft full Water etc. be easy to collapse hole and bit freezing burying stratum in use pipe-following drilling technology.
(3), drilling machine sets up platform using φ 50mm scaffolding poles in place, and platform is fixed with anchor pole and slope surface, and drilling machine is with three Foot support is promoted onto platform.Bolthole drilling construction sets up the scaffold for meeting respective carrier ability and firm condition, according to Slope surface measuring hole position, the accurate fixed drilling machine of installation, and strictly conscientiously carry out seat in the plane adjustment, it is ensured that anchor cable, bolthole spud in place Error must not exceed ± 50mm in length and breadth, and vertical error must not exceed ± 100mm, and dip angle of hole and direction meet design requirement, incline Angle allowable error position ± 1.0 °, orientation allowable error ± 2.0 °.The angle of cut z of anchor cable, anchor pole and horizontal plane is not more than 20 °, generally Between 15 °~20 °.
(4), mode is crept into
Boring requirement drilled dry is forbidden using water drilling.
(5), drilling process
To the formation variation in each hole in drilling process, state is crept into(Bit pressure, drilling speed), underground water and some special circumstances perform Site operation records.It when drilling phenomenon as bad such as collapse hole shrinkage cavity etc., must stop to bore immediately, carry out grouting for braced wall processing in time(It fills Starch 0.1~0.2MPa of pressure), after cement mortar initial set, cleaning bottom of hole is crept into again.
(6), hole diameter, deep drilling
Boring aperture, hole depth require to cannot be less than design value.To ensure anchor pole bore dia and depth, it is desirable that actual use drill bit is straight Diameter cannot be less than design aperture, and practical hole depth is more than projected depth 0.2m or more.
(7), bolthole is cleared up
After drilling reaches projected depth, it cannot stop to bore immediately, it is desirable that surely bore 1~2 minute, prevent bottom hole pinching, design is not achieved Aperture.Borehole wall must not have heavy quarrel and water body viscous, it is necessary to clean out, after the completion of drilling, use pressure-air(Wind pressure 0.2~0.4MPa)Rock powder in hole and water body are all removed outside portalling, in order to avoid reduce the bonding of cement mortar and hole wall Rock And Soil Intensity.In addition to the complete rock anchorage of relative rigid, high pressure water washing must not be used.If meeting in anchor hole has artesian water outflow, wait for Hydraulic pressure, water can pacify down dowel and slip casting after becoming smaller, and suitable position setting osculum is handled around when necessary.If design It is required that processing anchor hole accumulated inside water body, generally using the processing of the methods of the secondary drilling of grout sealing.
(8), bolthole is examined
After anchor pole hole drill is made, next procedure must can be carried out through site supervision after the assay was approved.Aperture, hole depth check one As using verifying under conditions of station by design aperture, drill bit and standard drill pipe at the scene management, it is desirable that drill bit is flat during verifying Forwards is not into generating impact or shake, drilling tool, which is tested, send length to meet design anchor pole hole depth, moves back brill and requires smooth, uses high-pressure blast It blows to test and does not deposit apparent splashing dirt quarrel and water body phenomenon.Check anchor hole hole position, inclination angle and orientation, whole anchor hole constructions point are required simultaneously After item work is qualified, you can think that anchor hole brill makes inspection qualification.
(9), anchor bar body makes and installs
Anchor pole is made by design requirement, not only to ensure length in hole, and to have enough protective layers.Dowel tail end anti-corrosion It is handled using anti-corrosion measures such as mopping, oilings.Before installation, it is to be ensured that every reinforcing bar is straight, derusts, degreases, and installs anchor bar body Preceding conscientiously verification anchor hole is numbered again, uses high-pressure blast aperture blowing after confirmation is errorless again, manually slowly anchor bar body is put into hole.
(10), anchor bolt grouting
Slip casting uses Twice High Pressure Splitting Grouting.Since bottom hole, practical grouting amount is generally greater than for common pressure grouting operation Theoretical grouting amount, or no longer be vented using anchorage gas vent and standard that slurries spilling underflow in aperture terminates as slip casting.
When bar-mat reinforcement is laid with, following main points are should be noted:
A. bar-mat reinforcement spreads extension, protective layer thickness >=2cm after first 4~5cm of jetting cement;
B. bar-mat reinforcement is laid with the fluctuating of first spray plane, with the gap by spray plane it is general≤3cm;
Reduce nozzle when c. opening spray extremely by spray plane distance, and adjusts spray angle, bar-mat reinforcement protective layer thickness >=4cm;
When being blocked by bar-mat reinforcement if any the stone or concrete block to fall off in d. spraying, fill-before-fire concrete after removing in time.
Injection concrete ratio is designed according to the requirement of concrete strength and other physical and mechanical properties and spray technology, is specifically set Meter step includes the following steps:
Determine the maximum particle diameter and sand coarse aggregate ratio of aggregate;
Determine cement consumption;
Determine the ratio of mud and water consumption;
Determine sand, stone dosage;
Examination spray;
It adjusts, determine coordination in works.
The injection concrete construction method, includes the following steps:
A, first to being handled by spray scar before injection, general scar is first with high pressure water washing by floating dust, the landwaste of spray scar, rock When the easy deliquescence of water, argillization are met in face, scar is blown off with high-pressure blast;
B, one layer of cement mortar, the fill-before-fire concrete after final set are first sprayed before jetting cement;
C, mark of the steel bar end as control jetting cement thickness is buried;
D, the routes of pipe line such as plant and wind, water, electricity are checked, by wet-spraying machine simultaneously test running in place;
E, concrete strictly presses coordination in works dispensing, and accelerator is added in spraying machine feeding;
F, jetting cement operation is carried out:Jetting cement using segmentation, fragment, be layered carry out successively, injection order from bottom to top, sector boss Degree≤6m.First low-lying place is substantially sprayed when injection and is put down, then sequence from low to uper part layering, reciprocal injection.
G, the final set of maintenance jetting cement is conserved in time after 2 hours, and curing time is not less than 14d;Temperature is prohibited when being less than 5 DEG C Only watering maintenance.
H, quality examination checks jetting cement surface, if has phenomena such as loosening, cracking, tenesmus, sliding, if any clear in time Except respraying.Sprinkler body can listen sound after reaching some strength with hammering, to being handled in time at hollowing shelling.Jewel hole measures, and thickness is not Enough places fill spray.Rebound degree and practical match ratio are measured in time, mechanical test is carried out to sprinkler body test specimen, to instruct lower step construction.
When specific jetting cement operation, following main points are paid attention to:
A) when section constructions, inclined-plane is reserved in leading portion jetting cement joint, surface width is 20~30cm, and pressure is first used on inclined-plane Power water rinses fill-before-fire concrete after wetting;
B) fragments are injected from down and upper progress;
C) when layerings injection, later layer carries out after being injected in preceding layer concrete final set.When being sprayed again after final set 1h, wind is first used Water cleans spray-up surface.The thickness of jetting cement is not slid with concrete not to fall to spend, and can neither influence concrete because thickness is too big Cohesive force and cohesiveness, can not be too thin and increase springback capacity.
D) controls jet velocity, compacted in favor of concrete.Wind pressure is excessive, and jet velocity increases, and rebound increases;Wind pressure Too small, jet velocity is too small, and compaction force is small, influences concrete strength.Therefore notice that observation wind pressure, starting wind pressure reach after powering Just start to operate after 0.5MPa, and wind pressure is adjusted according to nozzle discharging situation;
E) make nozzle when sprays and keep suitable distance between by spray plane, spray angle is as close possible to 90 °, to obtain maximum pressure Real and minimum rebound.Nozzle is controlled with by spray plane spacing in 1.5~2.0m.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Any one skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (5)

1. a kind of reservoir engineering shotcrete concrete construction, which is characterized in that include the following steps:
A, the landing stage of scaffold is set up;
B, the slope surface cubic metre of earth and stone is cleared up:Remove surface dust, float stone at the top of linked network region;
C, anchor pole protects:It is by design elevation requirement, anchor pole hole site is accurate after the completion of bolthole surveying setting-out slope excavating For surveying setting-out in slope surface, hole position error must not exceed ± 50mm;
D, linked network and jetting cement:It is laid with bar-mat reinforcement and jetting cement.
2. reservoir engineering shotcrete concrete construction as described in claim 1, which is characterized in that the bar-mat reinforcement laying side Method includes the following steps:First injection 4~5cm thickness concretes close scar for jetting cement construction, hang bar-mat reinforcement, clear to just spraying scar progress Design thickness is sprayed onto after reason again.
3. reservoir engineering shotcrete concrete construction as described in claim 1, which is characterized in that when bar-mat reinforcement is laid with, should be noted Following main points:
A. bar-mat reinforcement spreads extension, protective layer thickness >=2cm after first 4~5cm of jetting cement;
B. bar-mat reinforcement is laid with the fluctuating of first spray plane, with the gap by spray plane it is general≤3cm;
Reduce nozzle when c. opening spray extremely by spray plane distance, and adjusts spray angle, bar-mat reinforcement protective layer thickness >=4cm;
When being blocked by bar-mat reinforcement if any the stone or concrete block to fall off in d. spraying, fill-before-fire concrete after removing in time.
4. reservoir engineering shotcrete concrete construction as described in claim 1, which is characterized in that the jetting cement construction party Method includes the following steps:
A, first to being handled by spray scar before injection, general scar is first with high pressure water washing by floating dust, the landwaste of spray scar, rock When the easy deliquescence of water, argillization are met in face, scar is blown off with high-pressure blast;
B, one layer of cement mortar, the fill-before-fire concrete after final set are first sprayed before jetting cement;
C, mark of the steel bar end as control jetting cement thickness is buried;
D, the routes of pipe line such as plant and wind, water, electricity are checked, by wet-spraying machine simultaneously test running in place;
E, concrete strictly presses coordination in works dispensing, and accelerator is added in spraying machine feeding;
F, jetting cement operation is carried out:Jetting cement using segmentation, fragment, be layered carry out successively, injection order from bottom to top, sector boss Degree≤6m;First low-lying place is substantially sprayed when injection and is put down, then sequence from low to uper part layering, reciprocal injection;
G, the final set of maintenance jetting cement is conserved in time after 2 hours, and curing time is not less than 14d;Temperature is forbidden spilling when being less than 5 DEG C Water curing;
H, quality examination checks jetting cement surface, if has phenomena such as loosening, cracking, tenesmus, sliding, weight is removed if any timely Spray;Sprinkler body can listen sound after reaching some strength with hammering, to being handled in time at hollowing shelling;Jewel hole measures, at thickness low LCL It fills spray;Rebound degree and practical match ratio are measured in time, mechanical test is carried out to sprinkler body test specimen, to instruct lower step construction.
5. reservoir engineering shotcrete concrete construction as described in claim 1, which is characterized in that when specific jetting cement operation, note It anticipates following main points:
A) when section constructions, inclined-plane is reserved in leading portion jetting cement joint, surface width is 20~30cm, and pressure is first used on inclined-plane Power water rinses fill-before-fire concrete after wetting;
B) fragments are injected from down and upper progress;
C) when layerings injection, later layer carries out after being injected in preceding layer concrete final set;
D) controls jet velocity, compacted in favor of concrete;Notice that observation wind pressure, starting wind pressure reach 0.5MPa after powering Just start to operate afterwards, and wind pressure is adjusted according to nozzle discharging situation;
E) make nozzle when sprays and keep suitable distance between by spray plane, spray angle is as close possible to 90 °;Nozzle with by spray plane Spacing is controlled in 1.5~2.0m.
CN201710084567.5A 2017-02-16 2017-02-16 A kind of reservoir engineering shotcrete concrete construction Pending CN108442380A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710084567.5A CN108442380A (en) 2017-02-16 2017-02-16 A kind of reservoir engineering shotcrete concrete construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710084567.5A CN108442380A (en) 2017-02-16 2017-02-16 A kind of reservoir engineering shotcrete concrete construction

Publications (1)

Publication Number Publication Date
CN108442380A true CN108442380A (en) 2018-08-24

Family

ID=63190789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710084567.5A Pending CN108442380A (en) 2017-02-16 2017-02-16 A kind of reservoir engineering shotcrete concrete construction

Country Status (1)

Country Link
CN (1) CN108442380A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1131221A (en) * 1995-12-29 1996-09-18 曾宪明 Supporting and protecting method for base pit, side slope, flat anchor and spray net
CN204098049U (en) * 2014-10-15 2015-01-14 中冶集团武汉勘察研究院有限公司 A kind of protective reinforcing structure of broken rock mass slope
CN105220698A (en) * 2015-08-21 2016-01-06 武汉沃田生态科技有限公司 A kind of rock slope ecological protection method
CN205399445U (en) * 2016-03-10 2016-07-27 马鞍山钢铁建设集团有限公司 High cliff stone side slope combined bolting and shotcrete structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1131221A (en) * 1995-12-29 1996-09-18 曾宪明 Supporting and protecting method for base pit, side slope, flat anchor and spray net
CN204098049U (en) * 2014-10-15 2015-01-14 中冶集团武汉勘察研究院有限公司 A kind of protective reinforcing structure of broken rock mass slope
CN105220698A (en) * 2015-08-21 2016-01-06 武汉沃田生态科技有限公司 A kind of rock slope ecological protection method
CN205399445U (en) * 2016-03-10 2016-07-27 马鞍山钢铁建设集团有限公司 High cliff stone side slope combined bolting and shotcrete structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
LZQ2756: "隧道喷射混凝土施工作业指导书(2016年根据最新规范及文件编制第三次修订,制得拥有再也不担心查资料了)", 《HTTPS://WENKU.BAIDU.COM/VIEW/EA8B121BAD51F01DC381F1B5.HTML?FROM=SEARCH》 *

Similar Documents

Publication Publication Date Title
CN106050266B (en) The construction method of shield section service channel tunneling in rich water sand-pebble layer tunnel
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN204098049U (en) A kind of protective reinforcing structure of broken rock mass slope
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN103244128B (en) A kind of big cross section Karst Tunnel double-side approach remaining core soil in advance construction method
CN106013191A (en) Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN106368224A (en) Graded slope reinforcing reverse construction method for high slope under complicated geology
CN105201513A (en) Shaft construction method for rail transit
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN205999903U (en) Environment-friendly type grass planting Concrete Highway protective slope structure
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN103669374A (en) Combined supporting construction method of steel sheet pile used in silt soil slope
CN111576481A (en) Tunnel portal open cut tunnel reinforcing construction method
CN107938692A (en) A kind of draining and recharge construction method and structure
CN104831734A (en) Construction method of jet-grouting pile and composite soil-nailed wall support for deep foundation pit construction
CN106522235A (en) Narrow site deep foundation pit excavation supporting construction method
CN109706945A (en) Come down fracture belt tunnel construction method
CN106522248A (en) Method for reinforcing soil slope and slope reinforcing device
CN103938637A (en) Construction method for rigid pile and flexible pile combination foundation pit supporting for hard-interlayer soft soil geology
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN107514266A (en) Shield export & import bolt anchorage soil body construction method
CN105484269B (en) Foundation pit enclosure structure seepage prevention and treatment construction method under blasting condition
CN110952586A (en) Construction process for bearing platform below expressway
CN108824460A (en) A kind of construction technology of cut subgrade banket
CN108442380A (en) A kind of reservoir engineering shotcrete concrete construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180824