CN108412094A - 一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置 - Google Patents
一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置 Download PDFInfo
- Publication number
- CN108412094A CN108412094A CN201810433107.3A CN201810433107A CN108412094A CN 108412094 A CN108412094 A CN 108412094A CN 201810433107 A CN201810433107 A CN 201810433107A CN 108412094 A CN108412094 A CN 108412094A
- Authority
- CN
- China
- Prior art keywords
- wall
- shear wall
- pvc pipe
- masonry
- filling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 238000005192 partition Methods 0.000 claims abstract description 22
- 238000005336 cracking Methods 0.000 claims abstract description 11
- 238000006073 displacement reaction Methods 0.000 claims abstract description 7
- 238000005266 casting Methods 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 5
- 238000002347 injection Methods 0.000 claims description 2
- 239000007924 injection Substances 0.000 claims description 2
- 239000002699 waste material Substances 0.000 abstract description 4
- 230000007547 defect Effects 0.000 abstract description 3
- 239000011449 brick Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 230000032258 transport Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Retaining Walls (AREA)
Abstract
本发明公开了一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置,该装置包括现有的剪力墙,在剪力墙间的填充墙位置布置有PVC管,在PVC管的顶端口部封盖有PVC管帽,所述的PVC管与填充墙内的定位筋固定,在定位筋上绑扎有抗裂钢筋网片,同时在填充墙与剪力墙交接处固定安装有结构拉缝隔板,通过结构拉缝隔板将填充墙与剪力墙分隔开来,并在结构拉缝隔板上开设一组浇筑孔。本发明替代了传统剪力墙间砌体的施工方法,将剪力墙和空心混凝土墙一起浇筑施工,不仅避免了传统砌体施工方法延长工期、浪费人力机械资源等缺陷,而且提高了空心混凝土墙的质量,降低了砌体渗漏风险及施工成本。
Description
技术领域
本发明涉及一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置,属于主体结构工程施工技术领域。
背景技术
在建筑施工领域中,剪力墙间的填充墙多数采用砌体。传统砌体施工需待主体结构施工至一定阶段后方可介入施工,延长了施工工期;而且砌体材料运输、砌筑需大量的人工及机械,无法高效利用有限的劳动力及机械设备,造成资源浪费。另外,因砌筑工人水平不一,砌筑质量无法保证,易发生渗漏、裂缝等质量问题。因此,有必要改进传统砌体的施工方法。
发明内容
本发明的目的在于,提供一种工艺简单、施工方便、能够能够提高施工工效的替代剪力墙间砌体的空心混凝土墙的施工方法及装置,以克服现有技术中的不足。
本发明的技术方案:一种替代剪力墙间砌体的空心混凝土墙的施工方法,首先在剪力墙间的填充墙位置根据深化图纸布置PVC管,然后用PVC管帽将PVC管顶端口部封闭,并采用定位筋将PVC管固定,同时将填充墙与剪力墙交接处采用结构拉缝隔板分隔开来,并在结构拉缝隔板上开设一组浇筑孔,此时安装填充墙与剪力墙两侧的模板,待模板安装完成后,一起浇筑填充墙与剪力墙的混凝土,在浇筑过程中混凝土从结构拉缝隔板上的浇筑孔注入填充墙中,待混凝土凝固后,便在剪力墙之间形成具有PVC管的空心混凝土墙。
进一步,在浇筑混凝土的过程中,采用振捣棒进行振捣,保证混凝土的流动性和密实性。
同时,本发明还提供一种由上述替代剪力墙间砌体的空心混凝土墙的施工方法构建的替代剪力墙间砌体的空心混凝土墙的施工装置,包括现有的剪力墙,在剪力墙间的填充墙位置布置有PVC管,在PVC管的顶端口部封盖有PVC管帽,所述的PVC管与填充墙内的定位筋固定,在定位筋上绑扎有抗裂钢筋网片,同时在填充墙与剪力墙交接处固定安装有结构拉缝隔板,通过结构拉缝隔板将填充墙与剪力墙分隔开来,并在结构拉缝隔板上开设一组浇筑孔。
进一步,在定位筋上绑扎抗裂钢筋网片,防止浇筑后的空心混凝土墙开裂。
进一步,所述的PVC管布置有一排或者一排以上。
由于采用上述技术方案,本发明的优点在于:本发明替代了传统剪力墙间砌体的施工方法,将剪力墙和空心混凝土墙一起浇筑施工,不仅避免了传统砌体施工方法延长工期、浪费人力机械资源等缺陷,而且提高了空心混凝土墙的质量,降低了砌体渗漏风险及施工成本。
附图说明
图1是本发明的结构示意图;
图2是图1的A-A截面图;
图3是图2的B-B截面图;
图4是浇筑孔的布置图。
附图标记说明:1-PVC管;2-定位筋;3-结构拉缝隔板;4-抗裂钢筋网片;5-PVC管帽;6-浇筑孔。
具体实施方式
为了使本发明的目的、技术方案和优点更加清楚,下面结合附图和实施例对本发明作进一步的详细说明。
本发明的实施例:替代剪力墙间砌体的空心混凝土墙的施工装置的结构示意图如图1~4所示,包括现有的剪力墙,在剪力墙间的填充墙位置布置有一排PVC管1,在每根PVC管1的顶端口部封盖有PVC管帽5,所述的PVC管1与填充墙内的定位筋2固定,在定位筋2上绑扎有抗裂钢筋网片4,同时在填充墙与剪力墙交接处固定安装有结构拉缝隔板3,通过结构拉缝隔板3将填充墙与剪力墙分隔开来,并在结构拉缝隔板3上开设一组浇筑孔6。同时,在定位筋2上绑扎抗裂钢筋网片4,防止浇筑后的空心混凝土墙开裂。
采用上述空心混凝土墙的施工装置进行空心混凝土墙施工时,首先在剪力墙间的填充墙位置根据深化图纸布置一排PVC管1,然后用PVC管帽5将PVC管1顶端口部封闭,并采用定位筋2将PVC管1固定,同时将填充墙与剪力墙交接处采用结构拉缝隔板3分隔开来,并在结构拉缝隔板3上开设一组浇筑孔6,此时安装填充墙与剪力墙两侧的模板,待模板安装完成后,一起浇筑填充墙与剪力墙的混凝土,在浇筑混凝土的过程中,采用振捣棒进行振捣,保证混凝土的流动性和密实性;在浇筑过程中混凝土从结构拉缝隔板3上的浇筑孔6注入填充墙中,待混凝土凝固后,便在剪力墙之间形成具有PVC管1的空心混凝土墙。
本发明替代了传统剪力墙间砌体的施工方法,将剪力墙和空心混凝土墙一起浇筑施工,不仅避免了传统砌体施工方法延长工期、浪费人力机械资源等缺陷,而且提高了空心混凝土墙的质量,降低了砌体渗漏风险及施工成本。
Claims (5)
1.一种替代剪力墙间砌体的空心混凝土墙的施工方法,其特征在于:首先在剪力墙间的填充墙位置根据深化图纸布置PVC管(1),然后用PVC管帽(5)将PVC管(1)顶端口部封闭,并采用定位筋(2)将PVC管(1)固定,同时将填充墙与剪力墙交接处采用结构拉缝隔板(3)分隔开来,并在结构拉缝隔板(3)上开设一组浇筑孔(6),此时安装填充墙与剪力墙两侧的模板,待模板安装完成后,一起浇筑填充墙与剪力墙的混凝土,在浇筑过程中混凝土从结构拉缝隔板(3)上的浇筑孔(6)注入填充墙中,待混凝土凝固后,便在剪力墙之间形成具有PVC管(1)的空心混凝土墙。
2.根据权利要求1所述的替代剪力墙间砌体的空心混凝土墙的施工方法,其特征在于:在浇筑混凝土的过程中,采用振捣棒进行振捣,保证混凝土的流动性和密实性。
3.一种由权利要求1或2所述的替代剪力墙间砌体的空心混凝土墙的施工方法构建的替代剪力墙间砌体的空心混凝土墙的施工装置,包括现有的剪力墙,其特征在于:在剪力墙间的填充墙位置布置有PVC管(1),在PVC管(1)的顶端口部封盖有PVC管帽(5),所述的PVC管(1)与填充墙内的定位筋(2)固定,在定位筋(2)上绑扎有抗裂钢筋网片(4),同时在填充墙与剪力墙交接处固定安装有结构拉缝隔板(3),通过结构拉缝隔板(3)将填充墙与剪力墙分隔开来,并在结构拉缝隔板(3)上开设一组浇筑孔(6)。
4.根据权利要求3所述的替代剪力墙间砌体的空心混凝土墙的施工装置,其特征在于:在定位筋(2)上绑扎抗裂钢筋网片(4),防止浇筑后的空心混凝土墙开裂。
5.根据权利要求3所述的替代剪力墙间砌体的空心混凝土墙的施工装置,其特征在于:所述的PVC管(1)布置有一排或者一排以上。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810433107.3A CN108412094A (zh) | 2018-05-08 | 2018-05-08 | 一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810433107.3A CN108412094A (zh) | 2018-05-08 | 2018-05-08 | 一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108412094A true CN108412094A (zh) | 2018-08-17 |
Family
ID=63138201
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810433107.3A Pending CN108412094A (zh) | 2018-05-08 | 2018-05-08 | 一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108412094A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109440980A (zh) * | 2018-12-19 | 2019-03-08 | 中国新兴建筑工程有限责任公司 | 一种层高填充墙结构及其施工方法 |
CN110777983A (zh) * | 2019-11-12 | 2020-02-11 | 中国新兴建筑工程有限责任公司 | 一种混凝土填充墙与现浇结构同步施工结构及方法 |
CN113202215A (zh) * | 2021-04-25 | 2021-08-03 | 中冶南方城市建设工程技术有限公司 | 一种全混凝土外墙施工方法 |
CN113565237A (zh) * | 2021-07-19 | 2021-10-29 | 中国建筑一局(集团)有限公司 | 一种适用于净水厂的配水花墙结构及其施工方法 |
CN115354857A (zh) * | 2022-09-15 | 2022-11-18 | 中铁十一局集团有限公司 | 一种非承重结构与主体结构整体施工工艺 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101812882A (zh) * | 2009-06-15 | 2010-08-25 | 黑龙江宇辉新型建筑材料有限公司 | 带一次成型填充墙的混凝土剪力墙及其制作方法 |
CN104831829A (zh) * | 2015-05-11 | 2015-08-12 | 孟凡林 | 一种混凝土剪力墙与填充墙一体化预制的连接方法 |
EP3040497A1 (en) * | 2014-12-30 | 2016-07-06 | Associazione Nazionale degli Industriali dei Laterizi | Antiseismic masonry infill |
CN206707055U (zh) * | 2017-02-24 | 2017-12-05 | 朱凤起 | 装配式填充墙、内墙体结构和外墙体结构 |
CN107503450A (zh) * | 2017-08-22 | 2017-12-22 | 中建四局第六建筑工程有限公司 | 一种现浇中空钢筋混凝土填充墙及其施工工艺 |
-
2018
- 2018-05-08 CN CN201810433107.3A patent/CN108412094A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101812882A (zh) * | 2009-06-15 | 2010-08-25 | 黑龙江宇辉新型建筑材料有限公司 | 带一次成型填充墙的混凝土剪力墙及其制作方法 |
EP3040497A1 (en) * | 2014-12-30 | 2016-07-06 | Associazione Nazionale degli Industriali dei Laterizi | Antiseismic masonry infill |
CN104831829A (zh) * | 2015-05-11 | 2015-08-12 | 孟凡林 | 一种混凝土剪力墙与填充墙一体化预制的连接方法 |
CN206707055U (zh) * | 2017-02-24 | 2017-12-05 | 朱凤起 | 装配式填充墙、内墙体结构和外墙体结构 |
CN107503450A (zh) * | 2017-08-22 | 2017-12-22 | 中建四局第六建筑工程有限公司 | 一种现浇中空钢筋混凝土填充墙及其施工工艺 |
Non-Patent Citations (1)
Title |
---|
邓志峰;王炎伟;: "全现浇混凝土填充墙结构拉缝施工技术" * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109440980A (zh) * | 2018-12-19 | 2019-03-08 | 中国新兴建筑工程有限责任公司 | 一种层高填充墙结构及其施工方法 |
CN110777983A (zh) * | 2019-11-12 | 2020-02-11 | 中国新兴建筑工程有限责任公司 | 一种混凝土填充墙与现浇结构同步施工结构及方法 |
CN113202215A (zh) * | 2021-04-25 | 2021-08-03 | 中冶南方城市建设工程技术有限公司 | 一种全混凝土外墙施工方法 |
CN113565237A (zh) * | 2021-07-19 | 2021-10-29 | 中国建筑一局(集团)有限公司 | 一种适用于净水厂的配水花墙结构及其施工方法 |
CN115354857A (zh) * | 2022-09-15 | 2022-11-18 | 中铁十一局集团有限公司 | 一种非承重结构与主体结构整体施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108412094A (zh) | 一种替代剪力墙间砌体的空心混凝土墙的施工方法及装置 | |
CN105298020B (zh) | 一种半预制圆钢管再生混合混凝土柱及其制备方法 | |
CN104532985B (zh) | 一种用榫卯式预制混凝土砌块代替模板浇筑的剪力墙及其施工方法 | |
CN107443566A (zh) | 预制构造柱模壳的制作方法 | |
CN105839850A (zh) | 地下室逆作法柱身后浇注预压施工方法 | |
CN207616844U (zh) | 基础承台预制混凝土侧模及成型装置 | |
CN207177303U (zh) | 轨道式振捣棒 | |
CN207194467U (zh) | 可伸缩式防止不同标号混凝土混浇装置 | |
CN206233596U (zh) | 砌体外墙构造柱混凝土浇筑装置 | |
CN106499070A (zh) | 装配式建筑构件与构件间连接缝的施工方法 | |
CN106760050A (zh) | 剪力墙与后浇筑混凝土框架梁的连接结构及贯通式处理方法 | |
CN105696790B (zh) | 一种双层连梁洞口模板系统及其应用于双层连梁的工法 | |
CN104295003A (zh) | 一种构造柱施工方法 | |
CN107288263A (zh) | 预制构造柱的施工方法 | |
CN108638322B (zh) | 一种装配式建筑中预制柱混凝土浇筑方法 | |
CN107165411A (zh) | 一种构造柱施工工艺 | |
CN205804745U (zh) | 一种预制混凝土剪力墙构件 | |
JP2009191568A (ja) | 柱梁接合部材の製造方法、コンクリート部材の製造方法および柱梁接合部材 | |
CN208267171U (zh) | 一种替代剪力墙间砌体的空心混凝土墙的施工装置 | |
CN207092299U (zh) | 一种现浇中空钢筋混凝土填充墙 | |
CN206986727U (zh) | 一种用于桥梁斜腹板振捣的装置 | |
CN206233405U (zh) | 剪力墙与后浇筑混凝土框架梁的连接结构 | |
CN214941494U (zh) | 一种含预应力frp筋束纤维再生混凝土叠合板 | |
CN207077580U (zh) | 预制构造柱模壳制作装置 | |
CN207794321U (zh) | 整体式填充墙砌体拉结筋预埋件 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180817 |