CN108412033A - The outer cantilevered balcony structure of vertical forest and its construction method outside building body - Google Patents

The outer cantilevered balcony structure of vertical forest and its construction method outside building body Download PDF

Info

Publication number
CN108412033A
CN108412033A CN201810070225.2A CN201810070225A CN108412033A CN 108412033 A CN108412033 A CN 108412033A CN 201810070225 A CN201810070225 A CN 201810070225A CN 108412033 A CN108412033 A CN 108412033A
Authority
CN
China
Prior art keywords
greening
vertical
floor
steel
box
Prior art date
Application number
CN201810070225.2A
Other languages
Chinese (zh)
Other versions
CN108412033B (en
Inventor
陈二平
顾洪平
李启宏
张春春
陈华柱
丁平
梅伟
赵本超
李逵
杨中华
Original Assignee
江苏省建筑工程集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 江苏省建筑工程集团有限公司 filed Critical 江苏省建筑工程集团有限公司
Priority to CN201810070225.2A priority Critical patent/CN108412033B/en
Publication of CN108412033A publication Critical patent/CN108412033A/en
Application granted granted Critical
Publication of CN108412033B publication Critical patent/CN108412033B/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/003Balconies; Decks
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G24/00Growth substrates; Culture media; Apparatus or methods therefor
    • A01G24/40Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure
    • A01G24/44Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure in block, mat or sheet form
    • A01G24/46Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure in block, mat or sheet form multi-layered
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • A01G9/022Pots for vertical horticulture
    • A01G9/025Containers and elements for greening walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/066Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for overhangs

Abstract

The invention discloses cantilevered balcony structure and its construction methods outside a kind of building body outside vertical forest, it is related to architectural design, it is intended to provide the vertical outer cantilevered balcony structure of forest outside a kind of building body, with making every floor have greening platform, the advantages of resident family is to greening platform ornamental value is improved, its key points of the technical solution are that:Include several sections of greening platforms being up arranged since layer 6 floor, for the greening platform along the vertical staggered floor overhanging of floor, the same area in corresponding floor is arranged every five floors in every section of greening platform on same floor.

Description

The outer cantilevered balcony structure of vertical forest and its construction method outside building body

Technical field

The present invention relates to architectural design, more particularly to the outer cantilevered balcony structure of vertical forest and its construction party outside a kind of building body Method.

Background technology

Currently, all buildings in city are looked using exterior wall as boundary at a glance, what people were seen is external wall metope The groups of building to stand in great numbers with reinforced concrete building body make entire city seem uninteresting, dry, make most fine sunlight, air, sky and The Nature is obstructed by exterior wall.Meanwhile as long as people once enter in building, the just cage as shut off oneself from society to one It in son, faces the wall and meditates, breaks contacts completely with extraneous sunlight, air, the Nature everywhere.

The patent that Chinese patent notification number is CN106801535A discloses a kind of urban forests garden building and groups of building, Urban forests garden building includes:Odd floors, even floors, external wall metope, corresponding to each odd floors house type Wall face is respectively provided with the high outdoor overhead green platform of upward two floor;Wall face corresponding to each even floors house type The high outdoor overhead green platform of one upward two floor is set.

But it can be influenced in adjacent two layers building after each greening platform setting since greening platform is that two floors are high Ornamental value of the resident family in upper layer building to greening platform.

Invention content

The object of the present invention is to provide cantilevered balcony structures outside a kind of building body outside vertical forest, have so that having per floor Greening platform improves the advantages of resident family is to greening platform ornamental value.

The present invention above-mentioned technical purpose technical scheme is that:Vertical forest outside a kind of building body Outer cantilevered balcony structure includes several sections of greening platforms being up arranged since layer 6 floor, and the greening platform is along floor The same area in corresponding floor is arranged every five floors in vertical staggered floor overhanging, every section of greening platform on same floor.

By using above-mentioned technical proposal, the floor less than six layers is close to extraneous plant, therefore resident family can watch the external world Plant, positioned at six layers or more of floors far from extraneous plant, the greening platform being arranged at this time furthered green plants and resident family it Between distance, the ornamental value that the greening platform being all arranged on each layer improves resident family to greening platform, greening platform is along floor Vertical staggered floor overhanging reduces interfering with each other for the greening platform between each floor, is conducive to photograph of the sunlight to each greening platform It penetrates.

The present invention is further set as:The greening platform includes greening box, includes successively from top to bottom in the greening box Layer, geotextiles drainage layer, drainage plate, stopping area, EVA waterproof layers are planted, the EVA waterproof layers are spread along the inner wall of greening box And if being fixed on greening box inner wall by cement nail.

By using above-mentioned technical proposal, plantation layer is convenient for the growth of plant, and geotextiles drainage layer and drainage plate are just In that will plant moisture discharge plantation layer extra in layer, the plant that stopping area reduces in plantation layer penetrates greening box, EVA waterproofs Layer do not absorb water, be moisture-proof, water resistance it is good, heat-insulated, heat-insulating and cold and low temperature performance excellent, can cold-resistant and exposure, can subtract Influence of the small ambient temperature to plantation layer.

The present invention is further set as:The upper end box wall of the greening box is covered by grey aluminum veneer, on the greening box Box wall is held to be equipped with the zinc-plated square steel bone dragon frame of support grey aluminum veneer.

By using above-mentioned technical proposal, grey aluminum veneer is light-weight, and rigidity is good convenient for construction, durability and corrosion resistance It is good, therefore service life is long, is not easy to stain, convenient for cleaning and maintaining advantage, zinc-plated square steel bone dragon frame supports grey aluminum veneer.

The present invention is further set as:The greening box is equipped with pottery to the direction far from greening box successively away from the side of floor Plate, galvanizing square steel skeleton and armoured concrete slab, the skeleton is equipped with the fixed link extended into greening box, described Fixed link enters across ceramic plate in greening box, and is threaded with the locking contradicted with ceramic plate away from the side of greening box in ceramic plate Nut, the skeleton are equipped with threaded rod in the side towards armoured concrete slab, and the armoured concrete slab is towards skeleton Side be equipped with fixed plate, described threaded rod one end is pierced by fixed plate and is connected with limited block in the threaded one end being pierced by, another Hold across the side of skeleton and across threaded one end be connected with latch segment.

By using above-mentioned technical proposal, ceramic plate has the advantages that environmentally friendly, energy saving, moisture-proof, sound insulation, ventilative, passes through fixation Ceramic plate is fixed on greening box by the locking nut on bar, is reduced temperature of the greening box far from floor side and is distributed, and is conducive to plant The growth of object, skeleton are also fixed on the side of greening box by fixed link, and fixed armoured concrete slab is decorated on skeleton The outer wall of greening box also protects greening box simultaneously.

The present invention is further set as:The greening box is equipped with rock-wool heat insulation plate, the rock wool heat-preservation towards the side of floor Side of the backboard from greening box is equipped with brick protective layer.

By using above-mentioned technical proposal, rock-wool heat insulation plate is durable, there is fabulous wind resistance, impact resistance, resistance to height The advantages of temperature, soda acid, anticorrosive, anti-aging, good heat insulating so that the side temperature of greening box towards floor, which distributes, to be slowed down, Conducive to the growth of plant, brick protective layer protects rock-wool heat insulation plate.

It is a further object to provide a kind of construction method of cantilevered balcony structure outside building body outside vertical forest, packets It includes, step 1:Overhanging type support system is set up;Step 2:Console mode support system is set up;Step 3:Template is installed;Step Four:Concreting;Step 5:Frame body sets up, use, dismounting.

By using above-mentioned technical proposal, step 1 and step 2 are convenient for the installation of template, template to be mixed after installing Solidifying soil pours, you can forms outer cantilevered balcony, then removes frame body, construction is simple is convenient.

The present invention is further set as:In step 1 overhanging type support system set up including:Overhang I-steel arrangement, oblique rollering steel Cord arranges that vertical frame body is set up;

Overhanging I-steel, which is arranged, includes:Pre-buried anchor ring, steel plate embedded part-unwrapping wire positions-install cantilever steel girder-fixation cantilever steel girder- Hound welds or the antitorque steel pipe of plane of arrangement-stretching wire rope-frame body bottom lock-sets up steel pipe framed bent.

By using above-mentioned technical proposal, overhanging I-steel arrangement enhances the support strength of overhanging type support system, at this time Oblique pull steel wire rope holds I-steel, and I-steel is fixed.

The present invention is further set as:Console mode support system sets up flow and is in step 2:Unwrapping wire positioning-weldering positions short steel Muscle head-upright bar is set up-bar of sweeping the floor, the longitudinal and transverse bar in middle part, bridging are synchronized and are set up.

By using above-mentioned technical proposal, upright bar, bar of sweeping the floor, the longitudinal and transverse bar in middle part and building for bridging stabilization are risen and fallen Ground formula support system is convenient for the construction of follow-up template.

The present invention is further set as:Template in step 3 is assembled using the field fabrication of 15m thickness glued boards;Piece is using flat Seam, piece want neat, close gapless;It connects raft corner and inlays closing in using handling smooth 40 × 90mm wood stupefieds through planer.

By using above-mentioned technical proposal, template splicing post gap is smaller, is conducive to the cast of later stage concrete, reduces coagulation The leakage of soil.

The present invention is further set as:Concreting method is in step 4 concreting:1)Vertical structure and level Concrete In Structures separately pour, and frame column concrete pours in advance, plate face once-pouring of concrete;2)When beam slab concrete placings, Ying You Change pours route, pours the cantilevered structure beam of overhanging plantation platform in advance, and overhanging plantation platform is then poured from both ends to centre Structural slab.

By using above-mentioned technical proposal, vertical structure is separately poured with horizontal structure concrete convenient for vertical and horizontal structure It is separately formed.

In conclusion the invention has the advantages that:It is equipped with greening platform above per floor layer, is conducive to resident family Ornamental, the greening platform above floor is located at every section of greening platform on same floor every five along the vertical staggered floor overhanging of floor The same area in corresponding floor is arranged in floor, is conducive to the daylighting of every layer of greening platform.

Description of the drawings

Fig. 1 is the structural schematic diagram of embodiment 1;

Fig. 2 is the enlarged structure schematic diagram in the portions A in Fig. 1;

Fig. 3 is the enlarged structure schematic diagram in the portions B in Fig. 1;

Fig. 4 is the enlarged structure schematic diagram in the portions C in Fig. 1;

Fig. 5 is the enlarged structure schematic diagram in the portions D in Fig. 1;

Fig. 6 is the structural schematic diagram for embodying greening platform of embodiment 1;

Fig. 7 is the construction method schematic diagram of the outer cantilevered balcony structure of embodiment 2;

Fig. 8 is the construction method schematic diagram of the overhanging I-steel arrangement of embodiment 2;

Fig. 9 is that the console mode support system of embodiment 2 sets up the construction method schematic diagram of flow.

In figure, 1, greening platform;11, greening box;111, ceramic plate;112, skeleton;113, armoured concrete slab;114, fixed Bar;115, locking nut;116, threaded rod;117, fixed plate;1171, limited block;1172, latch segment;118, rock-wool heat insulation plate; 1181, brick protective layer;12, layer is planted;13, geotextiles drainage layer;14, drainage plate;15, stopping area;16, EVA waterproof layers; 17, grey aluminum veneer;171, zinc-plated square steel bone dragon frame.

Specific implementation mode

Below in conjunction with attached drawing, invention is further described in detail.

Embodiment 1:

The vertical outer cantilevered balcony structure of forest, such as Fig. 6 outside a kind of building body, include up be arranged since layer 6 floor it is several Section greening platform 1, greening platform 1 up have for every layer from six floor layers, and the floor less than six layers is lived close to extraneous plant Family is close to extraneous plant, and convenient for ornamental, positioned at six layers or more of floors far from extraneous plant, the greening platform 1 being arranged at this time is drawn Close the distance between green plants and resident family, the greening platform 1 being all arranged on each layer improve resident family to greening platform 1 Ornamental value.Along the vertical staggered floor overhanging of floor, every section of greening platform 1 on same floor is set greening platform 1 every five floors The same area in corresponding floor is set, interfering with each other for the greening platform 1 between each floor is reduced, is conducive to sunlight to each The irradiation of greening platform 1.

Such as Fig. 1, greening platform 1 includes greening box 11, include successively from top to bottom such as Fig. 2, in greening box 11 plantation layer 12, Geotextiles drainage layer 13, drainage plate 14, stopping area 15, EVA waterproof layers 16, EVA waterproof layers 16 are spread along the inner wall of greening box 11 And if be fixed on 11 inner wall of greening box by cement nail, cement nail every 40 millimeters be arranged one, EVA waterproof layers 16 are consolidated It is scheduled in greening box 11.EVA waterproof layers 16 do not absorb water, are moisture-proof, water resistance is good, heat-insulated, and heat-insulating and cold and cryogenic property are excellent It is different, can cold-resistant and exposure, ambient temperature can be reduced to planting the influence of layer 12, geotextiles drainage layer 13 and drainage plate 14 plant layer 12 convenient for that will plant moisture discharge extra in layer 12.

Such as Fig. 4, after being set in greening box 11, covered by grey aluminum veneer 17 in the upper end box wall of greening box 11, it is green Change the zinc-plated square steel bone dragon frame 171 that 11 upper end box wall of box is equipped with support grey aluminum veneer 17, grey aluminum veneer 17 is light-weight, steel Property it is good convenient for construction, durability and good corrosion resistance, therefore service life is long, is not easy to stain, convenient for cleaning and maintenance advantage, ash Color aluminum veneer 17 increases the aesthetics of greening box 11.

Such as Fig. 4, greening box 11 is equipped with ceramic plate 111, hot dip to the direction far from greening box 11 successively away from the side of floor Zinc square steel skeleton 112 and armoured concrete slab 113, ceramic plate 111 have the advantages that environmentally friendly, energy saving, moisture-proof, sound insulation, ventilative, bone Frame 112 is equipped with the fixed link 114 extended into greening box 11, and fixed link 114 passes through ceramic plate 111 to enter in greening box 11, And it is threaded with the locking nut 115 contradicted with ceramic plate 111 away from the side of greening box 11 in ceramic plate 111, pass through lock at this time Ceramic plate 111 is fixed on 11 outer wall of greening box by tight nut 115, and reduce greening box 11 is influenced by ambient temperature, skeleton 112 with There are gaps, such as Fig. 5, skeleton 112 to be equipped with threaded rod 116 in the side towards armoured concrete slab 113 between ceramic plate 111, Armoured concrete slab 113 the side towards skeleton 112 be equipped with fixed plate 117,116 one end of threaded rod be pierced by fixed plate 117 and Be connected with limited block 1171 in the threaded one end being pierced by, the other end pass through the side of skeleton 112 and across threaded one end connect It is connected to latch segment 1172, armoured concrete slab 113 is fixed on skeleton 112 by limited block 1171 and latch segment 1172, steel Reinforced concrete plate 113 has decorated the outer wall of greening box 11 while also having protected greening box 11.

Such as Fig. 3, greening box 11 is equipped with the rock-wool heat insulation plate 118 of 40 millimeters thicks, rock-wool heat insulation plate 118 towards the side of floor The brick protective layer 1181 of 10 millimeters thicks is equipped with away from the side of greening box 11, rock-wool heat insulation plate 118 is durable, there is fabulous resist The advantages of wind, impact resistance, high temperature resistant, soda acid, anticorrosive, anti-aging, good heat insulating so that greening box 11 is towards floor Side temperature distribute and slow down, be conducive to the growth of plant.

Embodiment 2:

The construction method of the vertical outer cantilevered balcony structure of forest outside a kind of building body, such as Fig. 7, including, step 1:Overhanging type supporter System sets up;Step 2:Console mode support system is set up;Step 3:Template is installed;Step 4:Concreting;Step 5:Frame Body sets up, use, dismounting.

In step 1 overhanging type support system set up including:Overhang I-steel arrangement, oblique pull steel wire rope arrangement, vertical frame body It sets up.

Such as Fig. 8, overhanging I-steel arrangement includes:Pre-buried anchor ring, steel plate embedded part-unwrapping wire positions-install cantilever steel girder-fixation Cantilever steel girder-hound welding or the antitorque steel pipe of plane of arrangement-stretching wire rope-frame body bottom lock-set up steel pipe framed bent.It is outstanding Positioning and unwrapping wire should be carried out by the upright bar advance and array pitch requirement of builder's jack by choosing girder steel placement;The anchor of overhanging type steel anchored end Ring in strict accordance with design drawing position it is pre-buried, in addition to added inside anchor ring 2 root long degree be 1.5m D18 reinforcing bars, anchor ring It should be passed through below board bottom bottom muscle;Girder hound is No. 16 I-steel at frame column, and lower fulcrum buries in lower floor's post If 600 × 400 × 20mm pre-embedded steel slabs:It occupies in column and is arranged, long side is parallel to pillar height degree;No. 16 I-steel diagonal braces at frame column The upper and lower fulcrum of bar should calculate diagonal brace welding inclined-plane and with cutting with before built-in fitting welding in overhanging I-steel girder and lower floor's post Cutting mill is cut;At frame column overhang I-steel girder on cross-arm I-steel short beam, according to framed bent in length and breadth spacing overhanging girder on Positioning welding, and crossbeam and Main Girder Welding are firm;After overhanging I-steel is adjusted according to commitment positions, between both sides and anchor ring Gap timber wedge it is tight, and weld the short muscle of Φ 25mm of 250mm high on I-steel according to upright bar arrangement spacing, taken as upright bar If positioning and limit control;After overhanging I-steel all installs, steel basketry piece envelope is completely spread in overhanging I-steel top surface immediately It closes, steel basketry piece tied silk binds secured.

Oblique pull steel wire rope arrangement requires:Each drawing point is in I-steel both sides and respectively sets together, and steel wire rope draws point according to shaped steel Arrangement detail positioning must not arbitrarily move position.Draw the form that use service sleeve in beam wears beam of putting in steel wire rope top.

Such as Fig. 9, console mode support system sets up flow and is in step 2:Unwrapping wire positioning-weldering positioning bar dowel head-upright bar is taken If bar of sweeping the floor, the longitudinal and transverse bar in middle part, bridging are synchronized and are set up.

Upright bar arrangement is divided into overhanging type support system and console mode support system is treated with a certain discrimination:

Using the upright bar arrangement of overhanging support system, due to overhanging the arrangement factor of I-steel, platform branch should be planted with overhanging Support region other than floor support system it is relatively independent, also to ensure two relatively independent supporting zone frame bodies convenient for drawknot with Enhance the overall stability of frame body;

Upright bar arrangement for console mode support system then needs collaboration to consider that overhanging plantation platform is vertically propped up with the floor of exterior domain Support body system, the horizon bar of vertical supporting system can draw it is logical, effectively to enhance the overall stability of frame body.Upright bar and vertical equity The connector of bar will mutually be staggered, and the distance that is staggered is no less than 0.5m.

Template in step 3 is assembled using the field fabrication of 15m thickness glued boards;Piece uses flush joint, piece to want neat, tight Close gapless;It connects raft corner and inlays closing in using handling smooth 40 × 90mm wood stupefieds through planer.Template nail is on flitch, wood Square joint will be staggered, and girder will do the connection tongue and groove installed with secondary beam junction, and mark center line in notable place.It prepares each The template of type will standardize, regularization, and the crosspiece of template and the section thickness of frame material are as consistent as possible, are conducive in this way Formwork is convenient.Before template installation, it is necessary to which the brushing interleaving agent in template, to be convenient in demoulding after concrete formation, template should be put down It is whole, excellent, the rubbish incidental in template, brushing interleaving agent are removed before each use;The bottom of template will there are cleanings Mouthful, to remove rubbish.After template installs, the rubbish incidental in template is removed it is clean, with sharp next procedure into Row.The support of all templates must have enough intensity, rigidity and stability, and accomplish smooth vertical and horizontal.Absolute altitude level suitable for reading The line of ink marker on bullet after instrument repetition measurement, to control level height when concrete cast.To ensure the accuracy of geometrical scale, mould Plate Zhi Haohou, it is necessary to check mould inside dimension, verticality and absolute altitude, joint bar position, and reinforcing bar in template is rinsed well, through management Next procedure could be entered after acceptance(check).

Concreting method is in step 4 concreting:1)Vertical structure is separately poured with horizontal structure concrete, frame Trestle concrete pours in advance, plate face once-pouring of concrete;2)When beam slab concrete placings, it should optimize and pour route, pour in advance The cantilevered structure beam for building overhanging plantation platform then pours overhanging plantation platform structure plate from both ends to centre.

Step 5:Frame body sets up, use, dismounting.Form bracing system set up and dismounting belongs to working at height, therefore take And if dismounting must be carried out strictly in sequence, must not arbitrarily be operated.Prevent the rod piece power transmission caused by construction wrong not conforming to Reason, leaves security risk.Take, tear open must in strict accordance with taking conveniently, safely, tear step open and carry out, must not arbitrarily change.Frame body is not Must overload use, must not load.The console mode support system of overhanging plantation platform, with the connection for closing on floor support system It must not arbitrarily remove.If after the support system in floor meets dismounting condition, should platform be planted in overhanging in time after its dismounting Console mode support system steel pipe and the frame column that closes on do effective drawknot.Remove the time:Platform plane is planted in view of overhanging The characteristic distributions of vertical staggered floor are segmented, causes outrigger distance structure edge at without overhanging plantation platform larger, therefore overhangs plantation The dismounting time of the console mode supporting rack of platform is suitably delayed, that is, waits for that the secondary construction of breast board of overhanging plantation platform after the completion can Consider to remove.

This specific embodiment is only explanation of the invention, is not limitation of the present invention, people in the art Member can as needed make the present embodiment the modification of not creative contribution after reading this specification, but as long as at this It is all protected by Patent Law in the right of invention.

Claims (10)

1. the vertical outer cantilevered balcony structure of forest outside a kind of building body, it is characterised in that:Including up setting since the layer 6 floor Several sections of greening platforms set(1), the greening platform(1)Along the vertical staggered floor overhanging of floor, every section be located on same floor Greening platform(1)Every five floors, the same area in corresponding floor is set.
2. the vertical outer cantilevered balcony structure of forest outside building body according to claim 1, it is characterised in that:The greening platform (1)Including greening box(11), the greening box(11)Include inside plantation layer successively from top to bottom(12), geotextiles drainage layer (13), drainage plate(14), stopping area(15), EVA waterproof layers(16), the EVA waterproof layers(16)Along greening box(11)It is interior Wall is laid with, and is fixed on greening box by cement nail(11)On inner wall.
3. the vertical outer cantilevered balcony structure of forest outside building body according to claim 2, it is characterised in that:The greening box (11)Upper end box wall pass through grey aluminum veneer(17)Covering, the greening box(11)Upper end box wall is equipped with support grey aluminium list Plate(17)Zinc-plated square steel bone dragon frame(171).
4. the vertical outer cantilevered balcony structure of forest outside building body according to claim 1, it is characterised in that:The greening box (11)Away from the side of floor successively to far from greening box(11)Direction be equipped with ceramic plate(111), galvanizing square steel skeleton(112) And armoured concrete slab(113), the skeleton(112)It is equipped with and extends into greening box(11)Interior fixed link(114), institute State fixed link(114)Across ceramic plate(111)Into greening box(11)It is interior, and in ceramic plate(111)Away from greening box(11)Side It is threaded with and ceramic plate(111)The locking nut of conflict(115), the skeleton(112)Towards armoured concrete slab(113) Side be equipped with threaded rod(116), the armoured concrete slab(113)Towards skeleton(112)Side be equipped with fixed plate (117), the threaded rod(116)One end is pierced by fixed plate(117)And it is connected with limited block in the threaded one end being pierced by(1171), The other end passes through skeleton(112)Side and across threaded one end be connected with latch segment(1172).
5. the vertical outer cantilevered balcony structure of forest outside building body according to claim 4, it is characterised in that:The greening box (11)It is equipped with rock-wool heat insulation plate towards the side of floor(118), the rock-wool heat insulation plate(118)Away from greening box(11)Side Equipped with brick protective layer(1181).
6. the construction method of the vertical outer cantilevered balcony structure of forest outside a kind of building body, it is characterised in that:Including step 1:Overhanging Formula support system is set up;Step 2:Console mode support system is set up;Step 3:Template is installed;Step 4:Concreting;Step Rapid five:Frame body sets up, use, dismounting.
7. the construction method of the vertical outer cantilevered balcony structure of forest outside building body according to claim 6, it is characterised in that:Step In rapid one overhanging type support system set up including:Overhang I-steel arrangement, oblique pull steel wire rope arrangement, vertical frame body is set up;
Overhanging I-steel, which is arranged, includes:Pre-buried anchor ring, steel plate embedded part-unwrapping wire positions-install cantilever steel girder-fixation cantilever steel girder- Hound welds or the antitorque steel pipe of plane of arrangement-stretching wire rope-frame body bottom lock-sets up steel pipe framed bent.
8. the construction method of the vertical outer cantilevered balcony structure of forest outside building body according to claim 6, it is characterised in that:Step Console mode support system sets up flow and is in rapid two:Unwrapping wire positioning-weldering positions bar dowel head-upright bar is set up-bar of sweeping the floor, middle part Longitudinal and transverse bar, bridging, which synchronize, to be set up.
9. the construction method of the vertical outer cantilevered balcony structure of forest outside building body according to claim 6, it is characterised in that:Step Template in rapid three is assembled using the field fabrication of 15m thickness glued boards;Piece uses flush joint, piece to want neat, close gapless;It connects Closing in is inlayed using handling smooth 40 × 90mm wood stupefieds through planer in raft corner.
10. the construction method of the vertical outer cantilevered balcony structure of forest outside building body according to claim 6, it is characterised in that: Concreting method is in step 4 concreting:1)Vertical structure is separately poured with horizontal structure concrete, frame column coagulation Soil pours in advance, plate face once-pouring of concrete;2)When beam slab concrete placings, it should optimize and pour route, pour overhanging kind in advance The cantilevered structure beam for planting platform then pours overhanging plantation platform structure plate from both ends to centre.
CN201810070225.2A 2018-01-24 2018-01-24 External vertical forest overhanging balcony structure of building and construction method thereof CN108412033B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810070225.2A CN108412033B (en) 2018-01-24 2018-01-24 External vertical forest overhanging balcony structure of building and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810070225.2A CN108412033B (en) 2018-01-24 2018-01-24 External vertical forest overhanging balcony structure of building and construction method thereof

Publications (2)

Publication Number Publication Date
CN108412033A true CN108412033A (en) 2018-08-17
CN108412033B CN108412033B (en) 2020-01-07

Family

ID=63126426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810070225.2A CN108412033B (en) 2018-01-24 2018-01-24 External vertical forest overhanging balcony structure of building and construction method thereof

Country Status (1)

Country Link
CN (1) CN108412033B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7801174A (en) * 1978-02-01 1979-08-03 Ir Frederik Hendrik Dominicus Balcony garden for offices or flats - comprises earth filled water tight concrete tank with drain for surplus water
CN1667218A (en) * 2005-04-30 2005-09-14 王治国 6-50 floors tower and slab type building with platform and slab structured garden
CN201818066U (en) * 2010-09-30 2011-05-04 胡德明 Anti-leakage balcony and balcony type overhead ecological garden
CN101538896B (en) * 2009-04-03 2011-05-11 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
CN203072446U (en) * 2012-10-29 2013-07-24 庄任抄 Flower bed apparatus suitable for flower garden of un-closed balcony or terrace of multi-storey building
CN105298100A (en) * 2015-10-22 2016-02-03 广州市恒盛建设工程有限公司 Construction method of cantilever construction platform with ultrahigh cast-in-place flaring structure in cylindrical building
CN205296611U (en) * 2015-12-15 2016-06-08 湖北工业大学 Optimizing structure of green roofing
CN105794517A (en) * 2014-12-30 2016-07-27 上海浦东建筑设计研究院有限公司 Three-dimensional-greening planting constructive system for building
CN106801535A (en) * 2015-11-26 2017-06-06 天九城市森林花园建筑科技成都有限公司 Urban forests garden building and groups of building

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7801174A (en) * 1978-02-01 1979-08-03 Ir Frederik Hendrik Dominicus Balcony garden for offices or flats - comprises earth filled water tight concrete tank with drain for surplus water
CN1667218A (en) * 2005-04-30 2005-09-14 王治国 6-50 floors tower and slab type building with platform and slab structured garden
CN101538896B (en) * 2009-04-03 2011-05-11 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
CN201818066U (en) * 2010-09-30 2011-05-04 胡德明 Anti-leakage balcony and balcony type overhead ecological garden
CN203072446U (en) * 2012-10-29 2013-07-24 庄任抄 Flower bed apparatus suitable for flower garden of un-closed balcony or terrace of multi-storey building
CN105794517A (en) * 2014-12-30 2016-07-27 上海浦东建筑设计研究院有限公司 Three-dimensional-greening planting constructive system for building
CN105298100A (en) * 2015-10-22 2016-02-03 广州市恒盛建设工程有限公司 Construction method of cantilever construction platform with ultrahigh cast-in-place flaring structure in cylindrical building
CN106801535A (en) * 2015-11-26 2017-06-06 天九城市森林花园建筑科技成都有限公司 Urban forests garden building and groups of building
CN205296611U (en) * 2015-12-15 2016-06-08 湖北工业大学 Optimizing structure of green roofing

Also Published As

Publication number Publication date
CN108412033B (en) 2020-01-07

Similar Documents

Publication Publication Date Title
CN103015565B (en) Prefabricated and assembled type integrated reinforced concrete load bearing wall and building construction method
CN104947788B (en) A kind of modular assembly formula building systems and its method of construction
CN100464043C (en) Bound-type composite heat-insulation wall with support body
CN102116061B (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN103711262B (en) A kind of curved surface aluminum-magnesium-manganese alloy roof plate system construction method
CN101319525B (en) Externally reinforced concrete irrigated and heat preservation wall structure embedded energy-saving system and its construction method
US9016025B2 (en) Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN101457556A (en) Core beam constructional column mixed combination wall, building method and relevant building block
CN102691411A (en) Beam plate post-cast strip template support system and construction method thereof
CN100575632C (en) The job practices of cast-in-situ hollow building roof
CN103225360A (en) Light and heat insulation roof board or floor slab
CN102003080B (en) Anti-seismic reinforcing structure and method of old brickwork building
CN103711238B (en) Assembled ring muscle fastens and is anchored concrete shear wall structure system
CN202324571U (en) Overhanging type double-row scaffold
CN104631857B (en) Movable dwellings
CN105421818B (en) Built-in steel Standard house
CN103195214B (en) Wood roof cornice decking and concrete composite structure in archaized buildings and construction method thereof
CN104895346B (en) Hardened system and its construction technology that the anti-local soil body of crude cave house vault caves in
CN104179250B (en) Light-board house system and construction method thereof
US20170260735A1 (en) Method of basement construction
CN101845857B (en) Metal mesh built-in insulating outer wall and construction method thereof
CN204326299U (en) The antidetonation adobe wall that a kind of steel concrete sleeper and dark beam are strengthened
CN103572866A (en) Assembly type wall
CN105926444A (en) Concrete arch bridge arching method
CN101096850A (en) Plastics water discharge plate application method for underground engineering wall surface, bottom plating and top board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant