CN108400650A - Power of alterating and direct current integral system - Google Patents
Power of alterating and direct current integral system Download PDFInfo
- Publication number
- CN108400650A CN108400650A CN201810209501.9A CN201810209501A CN108400650A CN 108400650 A CN108400650 A CN 108400650A CN 201810209501 A CN201810209501 A CN 201810209501A CN 108400650 A CN108400650 A CN 108400650A
- Authority
- CN
- China
- Prior art keywords
- power supply
- feeder
- supply system
- panel
- power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J11/00—Circuit arrangements for providing service supply to auxiliaries of stations in which electric power is generated, distributed or converted
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J9/00—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
- H02J9/04—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
- H02J9/06—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J9/00—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
- H02J9/04—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
- H02J9/06—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
- H02J9/062—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems for AC powered loads
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B10/00—Integration of renewable energy sources in buildings
- Y02B10/70—Hybrid systems, e.g. uninterruptible or back-up power supplies integrating renewable energies
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Business, Economics & Management (AREA)
- Emergency Management (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Charge And Discharge Circuits For Batteries Or The Like (AREA)
Abstract
本发明涉及一种交直流电源一体化系统,包括:交流电源系统、连接蓄电池的直流电源系统以及连接海上风电场交流用电设备的交流不间断电源系统;直流电源系统的一端连接交流不间断电源系统,另一端通过交流电源系统连接交流不间断电源系统。基于海上风电场的应用场景,通过将交流不间断电源系统、交流电源系统以及直流电源系统合并为交直流电源一体化电源系统,共用蓄电池供电,简化了电源设备的结构,实现一体化监控,提高了海上风电场的自动化程度,同时可针对全系统进行自动管理运行,有效减少屏柜数量和空间,减少调试工作量和维护费用。
The invention relates to an integrated AC and DC power supply system, comprising: an AC power supply system, a DC power supply system connected to batteries, and an AC uninterrupted power supply system connected to AC power equipment in offshore wind farms; one end of the DC power supply system is connected to the AC uninterrupted power supply system, and the other end is connected to the AC uninterruptible power supply system through the AC power system. Based on the application scenarios of offshore wind farms, by combining AC UPS, AC power systems and DC power systems into an integrated AC and DC power system, and sharing battery power supply, the structure of power equipment is simplified, integrated monitoring is realized, and improved The degree of automation of offshore wind farms is improved, and at the same time, automatic management and operation of the entire system can be carried out, effectively reducing the number and space of panel cabinets, reducing the workload of commissioning and maintenance costs.
Description
技术领域technical field
本发明涉及海上风电场技术领域,特别是涉及一种交直流电源一体化系统。The invention relates to the technical field of offshore wind farms, in particular to an integrated AC and DC power supply system.
背景技术Background technique
我国海上风能资源丰富,海上10m(米)高度可开发利用的风能储量约7.5亿kW(千瓦),海上风电将成为我国未来清洁能源开发重点。随着我国海上风电的发展,距离越来越远、规模越来越大,海上升压站是海上风电送电的枢纽,陆上集控中心是针对在无人值班、集控站集中监控的运行模式下必不可少的监控系统中心。my country is rich in offshore wind energy resources, and the wind energy reserves that can be developed and utilized at a height of 10m (meters) offshore are about 750 million kW (kilowatts). Offshore wind power will become the focus of my country's future clean energy development. With the development of offshore wind power in my country, the distance is getting farther and larger, and the offshore booster station is the hub of offshore wind power transmission. The onshore centralized control center is for centralized monitoring at unattended and centralized control stations Indispensable monitoring system center in run mode.
在传统技术中,发明人发现至少存在如下问题:一方面,海上升压站和陆上集控中心的用电源资源不能统筹考虑,如蓄电池配置存在严重浪费问题;另一方面,由不同生产商提供的各子系统通信规约不能兼容,无法进行集中监控以及综合分析,严重限制了集中管理水平和状态检修等,使得交直流电源自动化监控程度低,导致的总体经济效益差,投资成本高。In the traditional technology, the inventors found at least the following problems: on the one hand, the power resources of the offshore booster station and the land centralized control center cannot be considered as a whole, such as serious waste of storage battery configuration; on the other hand, different manufacturers The communication protocols provided by the subsystems are not compatible, and centralized monitoring and comprehensive analysis cannot be performed, which severely limits the level of centralized management and condition maintenance, resulting in a low degree of automatic monitoring of AC and DC power supplies, resulting in poor overall economic benefits and high investment costs.
发明内容Contents of the invention
基于此,有必要针对无法统筹考虑海上风电场用电资源的问题,提供一种交直流电源一体化系统。Based on this, it is necessary to provide an integrated AC and DC power supply system for the problem that the power resources of offshore wind farms cannot be considered as a whole.
为了实现上述目的,本发明实施例提供了一种交直流电源一体化系统,包括:交流电源系统、连接蓄电池的直流电源系统以及连接海上风电场交流用电设备的交流不间断电源系统;In order to achieve the above purpose, an embodiment of the present invention provides an integrated AC and DC power supply system, including: an AC power supply system, a DC power supply system connected to a battery, and an AC uninterruptible power supply system connected to the AC power equipment of an offshore wind farm;
直流电源系统的一端连接交流不间断电源系统,另一端通过交流电源系统连接交流不间断电源系统。One end of the DC power supply system is connected to the AC uninterruptible power supply system, and the other end is connected to the AC uninterruptible power supply system through the AC power supply system.
在其中一个实施例中,还包括连接通信设备的通信电源屏;In one of the embodiments, it also includes a communication power screen connected to communication equipment;
通信电源屏的一端连接直流电源系统,另一端通过交流电源系统连接直流电源系统。One end of the communication power panel is connected to the DC power system, and the other end is connected to the DC power system through the AC power system.
在其中一个实施例中,交流不间断电源系统包括第一交流不间断电源和第二交流不间断电源;交流电源系统包括第一交流开关柜、第二交流开关柜、第一交流馈线柜以及第二交流馈线柜;所述直流电源系统包括第一直流馈线屏、第二直流馈线屏、第一直流充电屏以及第二直流充电屏;In one of the embodiments, the AC uninterruptible power supply system includes a first AC uninterruptible power supply and a second AC uninterruptible power supply; the AC power supply system includes a first AC switch cabinet, a second AC switch cabinet, a first AC feeder cabinet, and a second AC switch cabinet. Two AC feeder cabinets; the DC power supply system includes a first DC feeder panel, a second DC feeder panel, a first DC charging panel, and a second DC charging panel;
第一直流充电屏通过第一直流馈线柜分别连接第一交流不间断电源、第一交流馈线柜,通过所述第一交流馈线柜分别连接所述第一交流不间断电源、第一交流开关柜;The first DC charging screen is respectively connected to the first AC uninterruptible power supply and the first AC feeder cabinet through the first DC feeder cabinet, and is respectively connected to the first AC uninterruptible power supply and the first AC feeder cabinet through the first AC feeder cabinet. Switchgear;
第二直流充电屏通过第二直流馈线柜分别连接第二交流不间断电源、第二交流馈线柜,通过第二交流馈线柜分别连接第二交流不间断电源、第二交流开关柜。The second DC charging panel is respectively connected to the second AC uninterruptible power supply and the second AC feeder cabinet through the second DC feeder cabinet, and is respectively connected to the second AC uninterruptible power supply and the second AC switch cabinet through the second AC feeder cabinet.
第一交流馈线柜连接第二直流充电屏;第二交流馈线柜连接第一直流充电屏。The first AC feeder cabinet is connected to the second DC charging screen; the second AC feeder cabinet is connected to the first DC charging screen.
在其中一个实施例中,还包括连接通信设备的通信电源屏;In one of the embodiments, it also includes a communication power screen connected to communication equipment;
第一直流充电屏分别通过第一直流馈线屏、第一交流馈线柜连接通信电源屏;The first DC charging screen is respectively connected to the communication power supply screen through the first DC feeder screen and the first AC feeder cabinet;
第二直流充电屏分别通过第二直流馈线屏、第二交流馈线柜连接通信电源屏。The second DC charging screen is respectively connected to the communication power supply screen through the second DC feeder screen and the second AC feeder cabinet.
在其中一个实施例中,第一交流不间断电源包括第一控制器电路以及连接第一控制器电路的第一旁路电路、第一自动切换装置;其中,第一旁路电路连接第一交流开关柜;第一交流馈线柜、第一直流馈线屏分别通过第一自动切换装置连接第一控制器电路;In one of the embodiments, the first AC uninterruptible power supply includes a first controller circuit, a first bypass circuit connected to the first controller circuit, and a first automatic switching device; wherein, the first bypass circuit is connected to the first AC switch cabinet; the first AC feeder cabinet and the first DC feeder screen are respectively connected to the first controller circuit through the first automatic switching device;
第二交流不间断电源包括第二控制器电路以及连接第二控制器电路的第二旁路电路、第二自动切换装置;其中,第二旁路电路连接第二交流开关柜;第二交流馈线柜、第二直流馈线屏分别通过第二自动切换装置连接第二控制器电路。The second AC uninterruptible power supply includes a second controller circuit, a second bypass circuit connected to the second controller circuit, and a second automatic switching device; wherein, the second bypass circuit is connected to the second AC switch cabinet; the second AC feeder The cabinet and the second DC feeder screen are respectively connected to the second controller circuit through the second automatic switching device.
在其中一个实施例中,第一直流充电屏包括第一单母线和第二单母线;第一直流馈线屏包括第一母线段;其中,蓄电池通过第一单母线连接第一母线段;第一交流馈线柜、第二交流馈线柜分别通过第二单母线连接第一母线段;In one of the embodiments, the first DC charging panel includes a first single busbar and a second single busbar; the first DC feeder panel includes a first busbar section; wherein, the battery is connected to the first busbar section through the first single busbar; The first AC feeder cabinet and the second AC feeder cabinet are respectively connected to the first bus section through the second single bus;
第二直流充电屏包括第三单母线和第四单母线;第二直流馈线屏包括第二母线段;其中,蓄电池通过第三单母线连接第二母线段;第一交流馈线柜、第二交流馈线柜分别通过第四单母线连接第二母线段。The second DC charging panel includes the third single busbar and the fourth single busbar; the second DC feeder panel includes the second busbar section; wherein, the battery is connected to the second busbar section through the third single busbar; the first AC feeder cabinet, the second AC The feeder cabinets are respectively connected to the second bus section through the fourth single bus.
在其中一个实施例中,直流电源系统包括联络电器;In one of the embodiments, the DC power supply system includes a contact appliance;
联络电器的一端连接第一母线段,另一端连接第二母线段。One end of the contact appliance is connected to the first bus section, and the other end is connected to the second bus section.
在其中一个实施例中,通信电源屏包括直流-直流模块、交流-直流模块和第二自动切换装置;In one of the embodiments, the communication power panel includes a DC-DC module, an AC-DC module and a second automatic switching device;
交流-直流模块、直流-直流模块分别通过第三自动切换装置连接通信电源屏的直流母线段;The AC-DC module and the DC-DC module are respectively connected to the DC bus section of the communication power panel through the third automatic switching device;
交流电源系统连接交流-直流模块;直流电源系统连接直流-直流模块。The AC power system is connected to the AC-DC module; the DC power system is connected to the DC-DC module.
在其中一个实施例中,通信电源屏还包括直流断路器;In one of the embodiments, the communication power panel further includes a DC circuit breaker;
直流断路器一端连接直流电源系统,另一端连接直流-直流模块。One end of the DC circuit breaker is connected to the DC power system, and the other end is connected to the DC-DC module.
在其中一个实施例中,直流断路器为B型脱扣曲线的直流断路器;B型脱扣曲线的直流断路器的额定电流小于或等于四分之一通信电源屏的输出电流。In one embodiment, the DC circuit breaker is a DC circuit breaker with a Type B tripping curve; the rated current of the DC circuit breaker with a Type B tripping curve is less than or equal to a quarter of the output current of the communication power supply panel.
上述技术方案中的一个技术方案具有如下优点和有益效果:One of the above technical solutions has the following advantages and beneficial effects:
本发明交直流电源一体化系统,通过将交流不间断电源系统、交流电源系统以及直流电源系统合并为交直流电源一体化电源系统,共用蓄电池供电,简化了电源设备的结构,实现一体化监控,提高了海上风电场的自动化程度,同时可针对全系统进行自动管理运行,有效减少屏柜数量和空间,减少调试工作量和维护费用。The integrated AC and DC power supply system of the present invention simplifies the structure of the power supply equipment and realizes integrated monitoring by combining the AC uninterruptible power supply system, the AC power supply system and the DC power supply system into the AC and DC power supply integrated power supply system, and sharing the battery for power supply. The degree of automation of offshore wind farms is improved, and at the same time, automatic management and operation of the entire system can be carried out, effectively reducing the number and space of panel cabinets, and reducing commissioning workload and maintenance costs.
附图说明Description of drawings
图1为本发明应用于陆上集控中心的一个实施例的结构示意图;Fig. 1 is the structural representation of an embodiment of the present invention being applied to land centralized control center;
图2为本发明应用于海上升压站的一个实施例的结构示意图;Fig. 2 is a structural schematic diagram of an embodiment of the present invention applied to an offshore booster station;
图3为本发明应用于陆上集控中心的一个具体实施例的结构示意图;Fig. 3 is a structural schematic diagram of a specific embodiment of the present invention applied to a centralized control center on land;
图4为本发明应用于海上升压站的一个具体实施例的结构示意图;Fig. 4 is a structural schematic diagram of a specific embodiment of the present invention applied to an offshore booster station;
图5为本发明一个具体实施例中的交流不间断电源系统的电路结构示意图;Fig. 5 is the schematic diagram of the circuit structure of the AC uninterruptible power supply system in a specific embodiment of the present invention;
图6为本发明一个具体实施例中的直流电源系统的电路结构示意图;6 is a schematic diagram of the circuit structure of a DC power supply system in a specific embodiment of the present invention;
图7为本发明一个具体实施例中的通信电源屏的电路结构示意图。Fig. 7 is a schematic diagram of the circuit structure of the communication power screen in a specific embodiment of the present invention.
具体实施方式Detailed ways
为了便于理解本发明,下面将参照相关附图对本发明进行更全面的描述。附图中给出了本发明的首选实施例。但是,本发明可以以许多不同的形式来实现,并不限于本文所描述的实施例。相反地,提供这些实施例的目的是使对本发明的公开内容更加透彻全面。In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the associated drawings. A preferred embodiment of the invention is shown in the drawings. However, the present invention can be embodied in many different forms and is not limited to the embodiments described herein. Rather, these embodiments are provided so that the disclosure of the present invention will be thorough and complete.
需要说明的是,当一个元件被认为是“连接”另一个元件,它可以是直接连接到另一个元件并与之结合为一体,或者可能同时存在居中元件。本文所使用的术语“连接”、“通过”以及类似的表述只是为了说明的目的。It should be noted that when an element is considered to be "connected" to another element, it may be directly connected to and integrally integrated with the other element, or there may be an intervening element at the same time. The terms "connected", "via" and similar expressions are used herein for the purpose of description only.
除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field of the invention. The terms used herein in the description of the present invention are for the purpose of describing specific embodiments only, and are not intended to limit the present invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
本发明交直流电源一体化系统的一个应用场景说明:Description of an application scenario of the integrated AC and DC power supply system of the present invention:
海上风电的交直流电源,一般采用分散设计,独立配置、独立组屏。380V交流系统、220V直流系统、交流不间断电源系统(UPS:Uninterruptible Power System)、逆变电源、DC48V通信电源系统等,各子系统采用分散设计,独立组屏安装于不同的设备室内,设备由不同的厂家生产、安装、调试,并按不同专业的班组和检修人员进行检修维护管理,以一海上风电场工程为例:将65×4MW机组以35kV等级电压接入220kV海上升压站,布置两台220/35kV容量为140MVA的主变压器,采用2回220kV三芯3×400mm2XLPE(Cross-linkedpolyethylene,交联聚乙烯)绝缘海底电缆将海上升压站的电能信息传送至陆上集控中心。The AC and DC power supply of offshore wind power generally adopts a decentralized design, independent configuration, and independent grouping of screens. 380V AC system, 220V DC system, AC uninterruptible power system (UPS: Uninterruptible Power System), inverter power supply, DC48V communication power system, etc., each subsystem adopts a decentralized design, and independent group screens are installed in different equipment rooms. The equipment consists of Different manufacturers produce, install and debug, and carry out maintenance and management according to different professional teams and maintenance personnel. Take an offshore wind farm project as an example: 65×4MW units are connected to a 220kV offshore booster station with a voltage of 35kV, and the layout Two 220/35kV main transformers with a capacity of 140MVA use two circuits of 220kV three-core 3×400mm2XLPE (Cross-linkedpolyethylene, cross-linked polyethylene) insulated submarine cables to transmit the power information of the offshore step-up station to the onshore centralized control center.
针对传统技术中无法统筹考虑海上风电场用电资源的问题,本发明实施例提供了一种交直流电源一体化系统实施例1;In view of the problem that the traditional technology cannot take into account the overall consideration of the power resources of the offshore wind farm, the embodiment of the present invention provides an embodiment 1 of an integrated AC and DC power supply system;
如图1所示:本发明实施例交直流电源一体化系统可以包括交流电源系统120、连接蓄电池100的直流电源系统130以及连接海上风电场交流用电设备的交流不间断电源系统110;As shown in FIG. 1 , the integrated AC and DC power supply system of the embodiment of the present invention may include an AC power supply system 120, a DC power supply system 130 connected to a storage battery 100, and an AC uninterruptible power supply system 110 connected to the AC power equipment of an offshore wind farm;
直流电源系统130的一端连接交流不间断电源系统110,另一端通过交流电源系统120连接交流不间断电源系统110。One end of the DC power supply system 130 is connected to the AC uninterruptible power supply system 110 , and the other end is connected to the AC uninterruptible power supply system 110 through the AC power supply system 120 .
具体而言,本发明实施例中,直流电源系统直接连接蓄电池,即可以通过蓄电池直接供电;直流电源系统的一端可以直接连接交流不间断电源系统、直接为交流不间断电源系统供电,同时,直流电源系统的另一端可以通过交流电源系统连接交流不间断电源系统,即直流电源系统可以通过交流电源系统为交流不间断电源系统供电。交流不间断电源系统不设专用蓄电池,采用主机冗余配置方式,为站内重要的交流用电设备供电,如监控系统、电能采集系统、导航系统、逆变电源等,与用于海上风电场的事故照明柜一同布置在海上升压站或者陆上集控中心的二次设备室。本发明实施例通过将交流不间断电源系统、交流电源系统以及直流电源系统合并为交直流电源一体化电源系统,共用蓄电池供电,简化了电源设备的结构,实现一体化监控,提高了海上风电场的自动化程度,同时可针对全系统进行自动管理运行,有效减少屏柜数量和空间,减少调试工作量和维护费用。Specifically, in the embodiment of the present invention, the DC power supply system is directly connected to the battery, that is, it can directly supply power through the battery; one end of the DC power supply system can be directly connected to the AC uninterruptible power supply system to directly supply power for the AC uninterruptible power supply system. The other end of the power system can be connected to the AC UPS system through the AC power system, that is, the DC power system can supply power to the AC UPS system through the AC power system. The AC uninterruptible power supply system does not have a special battery, and adopts the host redundant configuration mode to supply power for important AC power equipment in the station, such as monitoring system, power collection system, navigation system, inverter power supply, etc., and used in offshore wind farms. The emergency lighting cabinets are arranged together in the secondary equipment room of the offshore step-up station or the onshore centralized control center. The embodiments of the present invention combine the AC uninterruptible power supply system, the AC power supply system, and the DC power supply system into an integrated AC and DC power supply system, share the battery power supply, simplify the structure of the power supply equipment, realize integrated monitoring, and improve the efficiency of offshore wind farms. At the same time, it can automatically manage and run the whole system, effectively reducing the number and space of screen cabinets, reducing the debugging workload and maintenance costs.
在一个实施例中,如图2所示:本发明实施例交直流电源一体化系统还可以包括连接通信设备的通信电源屏240;In one embodiment, as shown in FIG. 2 : the integrated AC and DC power supply system of the embodiment of the present invention may also include a communication power supply screen 240 connected to communication equipment;
通信电源屏240的一端连接直流电源系统230,另一端通过交流电源系统220连接直流电源系统230。One end of the communication power panel 240 is connected to the DC power system 230 , and the other end is connected to the DC power system 230 through the AC power system 220 .
具体而言,基于本发明实施例的一应用场景,为保证通信电源系统的可靠性,海上风电场需配置双重化通信电源。应用于海上升压站的交直流电源一体化系统还包括通信电源屏,即为海上升压站配置的通信电源系统,通信电源屏的一端连接直流电源系统,另一端通过交流电源系统连接直流电源系统,即通信电源屏可以由站内直流系统供电,能够有效减少海上升压站空间。Specifically, based on an application scenario of the embodiment of the present invention, in order to ensure the reliability of the communication power supply system, the offshore wind farm needs to be equipped with a dual communication power supply. The integrated AC and DC power supply system applied to the offshore booster station also includes a communication power supply panel, which is the communication power supply system configured for the offshore booster station. One end of the communication power supply panel is connected to the DC power supply system, and the other end is connected to the DC power supply through the AC power supply system. The system, that is, the communication power panel can be powered by the DC system in the station, which can effectively reduce the space of the offshore step-up station.
在其中一个具体实施例中,如图3所示,交流不间断电源系统包括第一交流不间断电源(第一UPS)332和第二交流不间断电源(第二UPS)334;交流电源系统包括第一交流开关柜314、第二交流开关柜328、第一交流馈线柜312以及第二交流馈线柜316;直流电源系统包括第一直流馈线屏324、第二直流馈线屏328、第一直流充电屏322以及第二直流充电屏326;In one of the specific embodiments, as shown in Figure 3, the AC uninterruptible power supply system includes a first AC uninterruptible power supply (the first UPS) 332 and a second AC uninterruptible power supply (the second UPS) 334; the AC power supply system includes The first AC switch cabinet 314, the second AC switch cabinet 328, the first AC feeder cabinet 312 and the second AC feeder cabinet 316; the DC power supply system includes the first DC feeder panel 324, the second DC feeder panel 328, the first DC A current charging screen 322 and a second DC charging screen 326;
第一直流充电屏通过第一直流馈线柜分别连接第一交流不间断电源、第一交流馈线柜,通过第一交流馈线柜分别连接第一交流不间断电源、第一交流开关柜;第二直流充电屏通过第二直流馈线柜分别连接第二交流不间断电源、第二交流馈线柜,通过第二交流馈线柜分别连接第二交流不间断电源、第二交流开关柜。第一交流馈线柜连接第二直流充电屏;第二交流馈线柜连接第一直流充电屏。The first DC charging panel is respectively connected to the first AC uninterruptible power supply and the first AC feeder cabinet through the first DC feeder cabinet, and is respectively connected to the first AC uninterruptible power supply and the first AC switch cabinet through the first AC feeder cabinet; The two DC charging screens are respectively connected to the second AC uninterruptible power supply and the second AC feeder cabinet through the second DC feeder cabinet, and are respectively connected to the second AC uninterruptible power supply and the second AC switch cabinet through the second AC feeder cabinet. The first AC feeder cabinet is connected to the second DC charging screen; the second AC feeder cabinet is connected to the first DC charging screen.
具体而言,本发明实施例中,交流不间断电源系统包括第一交流不间断电源和第二交流不间断电源,并且还配置有对应的事故照明屏即第一事故照明屏、第二事故照明屏;交流不间断电源系统为交流负载供电,第一交流不间断电源可以为第一事故照明屏供电,第二交流不间断电源可以为第二事故照明屏供电。交流不间断电源系统可以采用主机冗余配置方式,为站内重要的交流用电设备供电,如监控系统、电能采集系统、导航系统、逆变电源等,交流不间断电源系统与220V直流电源系统的蓄电池系统相连,不设专用的蓄电池。交流不间断电源及事故照明屏布置在升压站二次设备室。Specifically, in the embodiment of the present invention, the AC uninterruptible power supply system includes a first AC uninterruptible power supply and a second AC uninterruptible power supply, and is also equipped with corresponding emergency lighting screens, that is, the first emergency lighting screen, the second emergency lighting screen screen; the AC uninterruptible power supply system supplies power for the AC load, the first AC uninterruptible power supply can supply power for the first emergency lighting screen, and the second AC uninterruptible power supply can supply power for the second emergency lighting screen. The AC uninterruptible power supply system can adopt the host redundant configuration mode to supply power for important AC power equipment in the station, such as monitoring system, power collection system, navigation system, inverter power supply, etc. The AC uninterruptible power supply system and 220V DC power supply system The storage battery system is connected, and there is no special storage battery. The AC uninterruptible power supply and emergency lighting screen are arranged in the secondary equipment room of the booster station.
连接蓄电池的直流电源系统包括第一直流馈线屏、第二直流馈线屏以及相互连接的第一直流充电屏、第二直流充电屏;具体的,蓄电池电压为220V,直流电源系统是通过第一直流充电屏和第二直流充电屏分别连接蓄电池,220V蓄电池可以直接为直流电源系统供电;蓄电池可以依次通过第一直流充电屏、第一直流馈线屏连接第一交流不间断电源供电,以及蓄电池依次通过第二直流充电屏、第二直流馈线屏连接第二交流不间断电源供电,即交流不间断电源和直流电源系统共用蓄电池。The DC power supply system connected to the battery includes a first DC feeder panel, a second DC feeder panel, and a first DC charging panel and a second DC charging panel connected to each other; specifically, the voltage of the battery is 220V, and the DC power supply system is provided through the first The first DC charging screen and the second DC charging screen are respectively connected to the battery, and the 220V battery can directly supply power for the DC power system; the battery can be connected to the first AC uninterruptible power supply through the first DC charging screen and the first DC feeder screen in turn. , and the battery is connected to the second AC uninterruptible power supply through the second DC charging panel and the second DC feeder panel in turn, that is, the AC uninterruptible power supply and the DC power supply system share the battery.
交流不间断电源系统没有配置蓄电池,当交流失电时,都由直流电源系统供电。当直流-交流(DC/AC)模块故障时,直接转入旁路输出。为保证系统可靠性,交流不间断电源系统考虑配置第一交流不间断电源和第二交流不间断电源并采用分列运行方式接线,可以充分保证系统的可靠性。The AC uninterruptible power supply system is not equipped with batteries, and when the AC power fails, it is powered by the DC power supply system. When the direct current - alternating current (DC/AC) module fails, transfer directly to the bypass output. In order to ensure the reliability of the system, the AC UPS system considers configuring the first AC UPS and the second AC UPS and adopts separate operation mode wiring, which can fully guarantee the reliability of the system.
进一步的,在本发明实施例中,直流电源系统还可以通过交流电源系统连接交流不间断电源系统,交流电源系统包括第一交流开关柜、第二交流开关柜以及相互连接的第一交流馈线柜、第二交流馈线柜;蓄电池依次通过第一直流充电屏、第一交流馈线柜连接第一交流不间断电源供电,以及蓄电池依次通过第二直流充电屏、第二交流馈线柜连接第二交流不间断电源供电,能够有效的减少海上升压站的空间,节省蓄电池的配备。Further, in the embodiment of the present invention, the DC power supply system can also be connected to the AC uninterruptible power supply system through the AC power supply system, and the AC power supply system includes a first AC switch cabinet, a second AC switch cabinet, and a first AC feeder cabinet connected to each other , the second AC feeder cabinet; the battery is connected to the first AC uninterruptible power supply through the first DC charging screen and the first AC feeder cabinet in turn, and the battery is connected to the second AC through the second DC charging screen and the second AC feeder cabinet in turn The uninterruptible power supply can effectively reduce the space of the offshore booster station and save the equipment of the battery.
在其中一个具体实施例中,如图4所示,还包括连接通信设备的通信电源屏440;第一直流充电屏422分别通过第一直流馈线屏424、第一交流馈线柜412连接通信电源屏440;第二直流充电屏426分别通过第二直流馈线屏428、第二交流馈线柜416连接通信电源屏440。In one of the specific embodiments, as shown in FIG. 4 , it also includes a communication power screen 440 connected to communication equipment; the first DC charging screen 422 is connected to the communication power supply screen 422 through the first DC feeder screen 424 and the first AC feeder cabinet 412 respectively. The power supply panel 440 and the second DC charging panel 426 are respectively connected to the communication power supply panel 440 through the second DC feeder panel 428 and the second AC feeder cabinet 416 .
具体而言,基于本发明实施例的应用场景,交直流电源一体化系统中通信电源屏由直流电源系统供电,如图4所示,可以理解的是,直流电源系统供电实质是蓄电池通过直流电源系统连接通信电源屏供电,一方面是第一直流充电屏通过第一直流馈线柜、第二直流充电屏通过第二直流馈线柜连接通信电源屏,另一方面是第一直流电源屏通过第一交流馈线柜、第二直流充电屏通过第二交流馈线柜连接通信电源屏,能够有效保证通信电源的可靠性。Specifically, based on the application scenario of the embodiment of the present invention, the communication power panel in the integrated AC and DC power supply system is powered by the DC power supply system, as shown in Figure 4. It can be understood that the essence of the DC power supply system is that the battery is powered The system is connected to the communication power supply screen for power supply. On the one hand, the first DC charging screen is connected to the communication power supply screen through the first DC feeder cabinet, and the second DC charging screen is connected to the communication power screen through the second DC feeder cabinet. On the other hand, the first DC power supply screen The first AC feeder cabinet and the second DC charging panel are connected to the communication power supply panel through the second AC feeder cabinet, which can effectively ensure the reliability of the communication power supply.
在一个具体实施例中,如图5所示,第一交流不间断电源包括第一控制器电路以及连接第一控制器电路的第一旁路电路、第一自动切换装置;其中,第一旁路电路连接第一交流开关柜;第一交流馈线柜、第一直流馈线屏分别通过第一自动切换装置连接第一控制器电路;In a specific embodiment, as shown in Figure 5, the first AC uninterruptible power supply includes a first controller circuit, a first bypass circuit connected to the first controller circuit, and a first automatic switching device; wherein, the first bypass circuit The circuit is connected to the first AC switch cabinet; the first AC feeder cabinet and the first DC feeder screen are respectively connected to the first controller circuit through the first automatic switching device;
第二交流不间断电源包括第二控制器电路以及连接第二控制器电路的第二旁路电路、第二自动切换装置;其中,第二旁路电路连接第二交流开关柜;第二交流馈线柜、第二直流馈线屏分别通过第二自动切换装置连接第二控制器电路。The second AC uninterruptible power supply includes a second controller circuit, a second bypass circuit connected to the second controller circuit, and a second automatic switching device; wherein, the second bypass circuit is connected to the second AC switch cabinet; the second AC feeder The cabinet and the second DC feeder screen are respectively connected to the second controller circuit through the second automatic switching device.
基于本发明实施例的应用场景,应用于海上升压站或陆上集控中心的交直流电源一体化系统中的交流不间断电源系统包括第一交流不间断电源和第二交流不间断电源,即可采用双套冗余配置方式,具体而言,海上升压站容量为220KV,蓄电池为220V,本发明实施例中交流不间断电源系统通过直流电源系统连接蓄电池,配置第一交流不间断电源(第一UPS)、第二交流不间断电源(第二UPS),还配置有第一事故照明屏和第二事故照明屏。如图5所示,第一UPS及第一事故照明屏为图中UPS电源及事故照明A屏,第二UPS及第二事故照明屏为图中UPS电源及事故照明B屏。具体的,图5中的UPS电源及事故照明A屏中:UPS旁路为第一旁路电路,自动切换装置为第一自动切换装置,控制器电路为第一控制器电路;图5中的UPS电源及事故照明B屏中:UPS旁路为第二旁路电路,自动切换装置为第二自动切换装置,控制器电路为第二控制器电路;Based on the application scenario of the embodiment of the present invention, the AC uninterruptible power supply system applied to the integrated AC and DC power supply system of the offshore step-up station or the land centralized control center includes a first AC uninterruptible power supply and a second AC uninterruptible power supply, That is to say, a dual-set redundant configuration mode can be adopted. Specifically, the capacity of the offshore step-up station is 220KV, and the storage battery is 220V. In the embodiment of the present invention, the AC uninterruptible power supply system is connected to the storage battery through the DC power supply system, and the first AC uninterruptible power supply is configured. (the first UPS), the second AC uninterruptible power supply (the second UPS), and the first emergency lighting screen and the second accident lighting screen are also configured. As shown in Figure 5, the first UPS and the first emergency lighting screen are the UPS power supply and the emergency lighting screen A in the figure, and the second UPS and the second accident lighting screen are the UPS power supply and the emergency lighting screen B in the figure. Specifically, in the UPS power supply and accident lighting A screen in Figure 5: the UPS bypass is the first bypass circuit, the automatic switching device is the first automatic switching device, and the controller circuit is the first controller circuit; In UPS power supply and emergency lighting B screen: UPS bypass is the second bypass circuit, the automatic switching device is the second automatic switching device, and the controller circuit is the second controller circuit;
采用双套冗余配置方式具体工作过程如下所述:The specific working process of dual-set redundant configuration is as follows:
当第一UPS和第二UPS的输出电源正常时,整流器提供直流电给第一UPS、第二UPS的逆变器,此时,第一UPS、第二UPS的逆变器并联输出,各平分负载电流的50%;When the output power of the first UPS and the second UPS is normal, the rectifier provides DC power to the inverters of the first UPS and the second UPS. At this time, the inverters of the first UPS and the second UPS are connected in parallel to share the load equally. 50% of current;
当第一UPS和第二UPS的输入电源故障时,自动切换装置将供电电源切换为由220V蓄电池向逆变器供电,第一UPS和第二UPS的逆变器并联输出,各评分负载电流的50%;When the input power of the first UPS and the second UPS fails, the automatic switching device will switch the power supply to the inverter from the 220V storage battery, and the inverters of the first UPS and the second UPS will output in parallel, and the rated load current of each 50%;
当第一UPS和第二UPS中的任一UPS电源故障时,故障UPS自动退出并联运行状态,该故障UPS的静态旁路开关将故障UPS从输出母线隔离,正常UPS的逆变器继续输出,承担全部的负载电流,且输出过程是自动完成,对负载没有任何扰动;When any one of the first UPS and the second UPS fails, the faulty UPS will automatically exit the parallel operation state, the static bypass switch of the faulty UPS will isolate the faulty UPS from the output bus, and the inverter of the normal UPS will continue to output. Bear all the load current, and the output process is completed automatically, without any disturbance to the load;
进一步的,其中任意一UPS故障时,对故障UPS进行检修时,不需要转手动维修旁路,可以通过将故障UPS的电源输入、旁路输入、内部直流电池开关、输出开关都打开来实现对故障UPS的内部检修,此时,负载由正常UPS供电;当第一UPS和第二UPS因为故障退出运行的时候,负载可以由静态旁路电源供电,且逆变器转旁路供电的时间小于0.5ms,对于负载基本无扰动;当第一UPS和第二UPS同时存在故障需要检修时,可以将操作转手动维修旁路,以使旁路为负载供电,再将故障的第一UPS、第二UPS的电源输入、旁路输入、内部直流电池卡关、输出开关全部打开来实现对故障UPS的内部检修,此时,负载由手动旁路供电。Furthermore, when any one of the UPSs fails, when the faulty UPS is overhauled, it is not necessary to switch to the manual maintenance bypass, and the power input, bypass input, internal DC battery switch, and output switch of the faulty UPS can be turned on. Internal inspection of the faulty UPS. At this time, the load is powered by the normal UPS; when the first UPS and the second UPS are out of operation due to a fault, the load can be powered by the static bypass power supply, and the time for the inverter to switch to the bypass power supply is less than 0.5ms, there is basically no disturbance to the load; when the first UPS and the second UPS have faults at the same time and need to be repaired, the operation can be transferred to the manual maintenance bypass, so that the bypass can supply power to the load, and then the faulty first UPS, the second UPS 2. Turn on the power input, bypass input, internal DC battery, and output switch of the UPS to realize the internal maintenance of the faulty UPS. At this time, the load is powered by the manual bypass.
需要说明的是,本发明实施例中,基于应用场景的参数说明:交流输入电压:380V(85~115%),交流输入频率:50HZ±5%,直流系统输入电压:220V:(80~115%),纹波系数≤5%,交流输出电压:220V±2%(不包括交流直接输入),交流输出频率:50HZ±0.5%(不包括交流直接输出)。It should be noted that in the embodiment of the present invention, the parameter description based on the application scenario: AC input voltage: 380V (85-115%), AC input frequency: 50HZ±5%, DC system input voltage: 220V: (80-115% %), ripple coefficient ≤5%, AC output voltage: 220V±2% (excluding AC direct input), AC output frequency: 50HZ±0.5% (excluding AC direct output).
海上升压站UPS负荷清单见表1所示:The UPS load list of the offshore booster station is shown in Table 1:
表1海上升压站的UPS负荷清单Table 1 UPS load list of offshore booster station
根据规范DL/T 5491-2014《电力工程交流不间断电源系统设计技术规程》附录C计算方法,UPS的计算容量为:According to the calculation method in Appendix C of the specification DL/T 5491-2014 "Technical Regulations for the Design of AC Uninterruptible Power Supply Systems in Electric Power Engineering", the calculation capacity of UPS is:
式中,S为UPS计算容量(kVA),SC为计算负荷(kVA),Kk为可靠系数,取1.25,Kf为功率校正系数、取0.89,Kd为降容系统,取1。考虑一定冗余容量,选取UPS容量为20kVA。In the formula, S is the UPS calculation capacity (kVA), S C is the calculation load (kVA), K k is the reliability coefficient, which is 1.25, K f is the power correction coefficient, which is 0.89, and K d is the derating system, which is 1. Considering a certain redundant capacity, select the UPS capacity as 20kVA.
UPS的电流为: The current of the UPS is:
式中:SC为UPS的计算负荷;U为直流系统的电压,直流220V;KUPS为风电场UPS的负荷系数,取0.5。In the formula: S C is the calculated load of the UPS; U is the voltage of the DC system, DC 220V; K UPS is the load factor of the UPS of the wind farm, which is 0.5.
根据规范DL/T 5491-2014,海上升压站属于无人值班的变电站,UPS的备电时间可以为2小时。According to the specification DL/T 5491-2014, the offshore step-up substation is an unattended substation, and the UPS backup time can be 2 hours.
UPS系统与220V直流电源系统的蓄电池系统相连,不设专用的蓄电池。UPS电源及事故照明柜布置在海上升压站二次设备室。The UPS system is connected to the storage battery system of the 220V DC power supply system, and there is no dedicated storage battery. UPS power supply and emergency lighting cabinets are arranged in the secondary equipment room of the offshore booster station.
陆上集控中心的UPS负荷清单见表2所示:The UPS load list of the land centralized control center is shown in Table 2:
表2陆上集控中心的UPS负荷清单Table 2 UPS load list of onshore centralized control center
同样,根据上述海上升压站的UPS容量的计算方法,得到陆上集控中心的UPS计算容量为14kVA,备电时间为2小时,其电流值为27.27A。UPS系统与220V直流电源系统的蓄电池系统相连,不设专用的蓄电池。UPS电源及事故照明柜布置在陆上集控中心的继电器室。Similarly, according to the calculation method of the UPS capacity of the above-mentioned offshore step-up station, the calculation capacity of the UPS of the land centralized control center is 14kVA, the backup time is 2 hours, and its current value is 27.27A. The UPS system is connected to the storage battery system of the 220V DC power supply system, and there is no dedicated storage battery. The UPS power supply and emergency lighting cabinet are arranged in the relay room of the onshore centralized control center.
在一个具体实施例中,如图6所示,第一直流充电屏包括第一单母线和第二单母线;第一直流馈线屏包括第一母线段;其中,蓄电池通过第一单母线连接第一母线段;第一交流馈线柜、第二交流馈线柜分别通过第二单母线连接第一母线段;In a specific embodiment, as shown in Figure 6, the first DC charging panel includes a first single busbar and a second single busbar; the first DC feeder panel includes a first busbar section; wherein, the storage battery passes through the first single busbar Connect the first bus section; the first AC feeder cabinet and the second AC feeder cabinet are respectively connected to the first bus section through the second single bus;
第二直流充电屏包括第三单母线和第四单母线;第二直流馈线屏包括第二母线段;其中,蓄电池通过第三单母线连接第二母线段;第一交流馈线柜、第二交流馈线柜分别通过第四单母线连接第二母线段。The second DC charging panel includes the third single busbar and the fourth single busbar; the second DC feeder panel includes the second busbar section; wherein, the battery is connected to the second busbar section through the third single busbar; the first AC feeder cabinet, the second AC The feeder cabinets are respectively connected to the second bus section through the fourth single bus.
具体而言,本发明实施例中的直流电源系统电压为220V,根据规范DL/T5491-2014,海上升压站为无人值班的变电站,直流电源系统的事故放电时间为2小时,同时,兼顾通信电源的可靠性,通信电源采用直流-直流模块的事故放电时间为8小时。基于上述说明,本发明实施例中的直流电源系统采用单母线接线,其中,第一直流充电屏和第二直流充电屏分别连接的蓄电池为固定型阀控式密封免维护胶体蓄电池,供保护、控制、防盗报警、综合自动化设备等电源,蓄电池的事故放电时间为2小时。Specifically, the voltage of the DC power system in the embodiment of the present invention is 220V. According to the specification DL/T5491-2014, the offshore step-up station is an unattended substation, and the accident discharge time of the DC power system is 2 hours. At the same time, taking into account The reliability of the communication power supply, the accident discharge time of the communication power supply using the DC-DC module is 8 hours. Based on the above description, the DC power supply system in the embodiment of the present invention adopts single-bus connection, wherein the batteries connected to the first DC charging panel and the second DC charging panel are fixed valve-controlled sealed maintenance-free colloidal batteries for protection , control, anti-theft alarm, integrated automation equipment and other power supplies, the accident discharge time of the battery is 2 hours.
如图6所示,第一直流充电屏的蓄电池及其充电装置和第二直流充电屏的蓄电池及其充电装置分别接入不同的母线段,其充电装置为第一交流馈线柜(图中#1交流馈线柜)和第二交流馈线柜(图中#2交流馈线柜),即连接第一直流充电屏(图中#1直流充电屏)的蓄电池通过第一单母线、充电装置通过第二单母接入对应第一直流馈线屏(图中#1直流馈线屏)的第一母线段;连接第二直流充电屏(图中#2直流充电屏)的蓄电池通过第三单母线、充电装置通过第四单母线接入对应第二直流馈线屏(图中#2直流馈线屏)的第二母线段。As shown in Figure 6, the storage battery and its charging device of the first DC charging panel and the storage battery and its charging device of the second DC charging panel are respectively connected to different bus sections, and the charging device is the first AC feeder cabinet (in the figure # 1 AC feeder cabinet) and the second AC feeder cabinet ( # 2 AC feeder cabinet in the figure), that is, the battery connected to the first DC charging panel ( # 1 DC charging panel in the figure) passes through the first single bus, and the charging device passes through The second single bus is connected to the first bus section corresponding to the first DC feeder panel ( # 1 DC feeder panel in the figure); the battery connected to the second DC charging panel ( # 2 DC charging panel in the figure) passes through the third single busbar , The charging device is connected to the second bus section corresponding to the second DC feeder panel ( # 2 DC feeder panel in the figure) through the fourth single busbar.
优选的,本发明实施例中的直流电源系统包括联络电器,联络电器的一端连接第一直流馈线屏(图中#1直流馈线屏)的第一母线段,另一端连接第二直流馈线屏(图中#2直流馈线屏)的第二母线段。具体而言,联络电器可以作为联络开关连接第一直流馈线屏和第二直流馈线屏的母线段。当接线正常、充电装置在直流电源系统中能分别正常充电时,联络开关处于常开的状态;当充电装置在第一直流充电屏或第二直流充电屏出现充电故障时,联络开关闭合,第一直流馈线屏和第二直流馈线屏的母线段连接,连接第一直流充电屏的蓄电池可以为第二直流充电屏供电,同样,连接第二直流充电屏的蓄电池可以为第一直流充电屏供电,有效的解决了电路故障而影响系统正常运行的问题,同时节约了用电资源。Preferably, the DC power supply system in the embodiment of the present invention includes a connecting appliance, one end of the connecting appliance is connected to the first bus section of the first DC feeder panel ( # 1 DC feeder panel in the figure), and the other end is connected to the second DC feeder panel ( # 2 DC feeder screen in the figure) for the second bus section. Specifically, the tie appliance can be used as a tie switch to connect the first DC feeder panel and the bus section of the second DC feeder panel. When the wiring is normal and the charging device can charge normally in the DC power system respectively, the contact switch is in the normally open state; when the charging device fails to charge in the first DC charging screen or the second DC charging screen, the contact switch is closed, The first DC feeder panel is connected to the bus section of the second DC feeder panel, and the battery connected to the first DC charging panel can supply power for the second DC charging panel. The current charging screen is powered, which effectively solves the problem that the circuit failure affects the normal operation of the system, and at the same time saves power resources.
需要说明的是,本发明实施例中,基于应用场景的参数说明:It should be noted that, in the embodiment of the present invention, the parameter description based on the application scenario:
海上升压站的交直流电源一体化系统的直流电源系统中,根据DL/T5044-2014规范要求,放电终止电压取1.87V,可靠系数Kk取1.4。按照UPS的容量计算方法计算得到蓄电池容量为519.99Ah,考虑一定的冗余容量,故蓄电池容量选为600Ah。按照本发明实施例的方式选择20A的高频开关电源模块,充电模块按(N+1)配置,可以采用6个20A的高频开关电源模块连接充电装置。蓄电池布置在海上升压站蓄电池室内,第一直流充电屏、第二直流充电屏、第一直流馈线屏以及第二直流馈线屏布置在海上升压站二次设备室。本发明实施例,有效节省了海上升压站空间。可节省2台UPS旁路柜、2台UPS馈线柜、2台通信电源馈线柜等屏柜。同时,节省2组通讯电源蓄电池In the DC power system of the integrated AC and DC power supply system of the offshore step-up station, according to the requirements of the DL/T5044-2014 specification, the discharge termination voltage is 1.87V, and the reliability factor K is 1.4. According to the calculation method of UPS capacity, the battery capacity is calculated as 519.99Ah, considering a certain redundant capacity, so the battery capacity is selected as 600Ah. According to the method of the embodiment of the present invention, a 20A high-frequency switching power supply module is selected, and the charging module is configured according to (N+1), and six 20A high-frequency switching power supply modules can be used to connect to the charging device. The battery is arranged in the battery room of the offshore booster station, and the first DC charging panel, the second DC charging panel, the first DC feeder panel and the second DC feeder panel are arranged in the secondary equipment room of the offshore booster station. The embodiment of the present invention effectively saves the space of the offshore booster station. It can save 2 UPS bypass cabinets, 2 UPS feeder cabinets, 2 communication power feeder cabinets and other screen cabinets. At the same time, save 2 sets of communication power battery
陆上集控中心的交直流电源一体化系统的直流电源系统中,根据DL/T5044-2014规范要求,按阶梯计算法计算蓄电池容量,计算得到蓄电池容量为394.46Ah,考虑一定的冗余容量,故蓄电池容量选为400Ah。基于蓄电池容量,可以采用4个20A的高频开关电源模块连接充电装置。蓄电池布置在陆上集控中心蓄电池室内,第一直流充电屏、第二直流充电屏、第一直流馈线屏以及第二直流馈线屏布置在陆上集控中心二次设备室。本发明实施例有效节省了陆上集控中心的空间,简化了电源系统,可节省2台UPS旁路柜、2台UPS馈线柜等屏柜。In the DC power supply system of the integrated AC and DC power supply system of the centralized control center on land, according to the requirements of the DL/T5044-2014 specification, the battery capacity is calculated according to the ladder calculation method, and the calculated battery capacity is 394.46Ah. Considering a certain redundant capacity, Therefore, the battery capacity is selected as 400Ah. Based on the battery capacity, four 20A high-frequency switching power supply modules can be used to connect to the charging device. The battery is arranged in the battery room of the onshore centralized control center, and the first DC charging panel, the second DC charging panel, the first DC feeder panel and the second DC feeder panel are arranged in the secondary equipment room of the onshore centralized control center. The embodiment of the present invention effectively saves the space of the centralized control center on land, simplifies the power supply system, and can save 2 UPS bypass cabinets, 2 UPS feeder cabinets and other screen cabinets.
在其中一个实施例中,如图7所示,通信电源屏包括直流-直流模块、交流-直流模块和第二自动切换装置;交流-直流模块、直流-直流模块分别通过第三自动切换装置连接通信电源屏的直流母线段;交流电源系统连接交流-直流模块;直流电源系统连接直流-直流模块。In one of the embodiments, as shown in Figure 7, the communication power panel includes a DC-DC module, an AC-DC module, and a second automatic switching device; the AC-DC module and the DC-DC module are respectively connected through the third automatic switching device The DC bus section of the communication power panel; the AC power system is connected to the AC-DC module; the DC power system is connected to the DC-DC module.
具体而言,本发明实施例中应用于海上升压站的交直流一体化电源系统,通信电源屏由站内直流电源系统供电,根据规范DL/T 5491-2014,基于通信设备的直流负荷统计,得到直流交接电源(DC/DC)负荷为3.65kW。DC/DC模块的负荷系数为0.8,根据上述UPS的电流计算方法得到DC/DC模块的电流为13.27A。为确保通信电源的可靠性,通信电源屏的DC/DC模块的放电时间为8小时,在通信电源屏中的母线上可以增加一套与直流-直流(DC/DC)模块对应的交流-直流(AC/DC)模块输出,直流电源系统可以通过两种方式连接通信电源屏,即通信电源屏中每段母线可以有2套AC/DC模块输出。Specifically, the embodiment of the present invention is applied to the AC-DC integrated power system of the offshore step-up station. The communication power panel is powered by the DC power system in the station. According to the specification DL/T 5491-2014, based on the DC load statistics of communication equipment, The DC/DC load is obtained to be 3.65kW. The load factor of the DC/DC module is 0.8, and the current of the DC/DC module is 13.27A according to the above UPS current calculation method. In order to ensure the reliability of the communication power supply, the discharge time of the DC/DC module of the communication power supply panel is 8 hours, and a set of AC-DC corresponding to the DC-DC (DC/DC) module can be added to the busbar in the communication power supply panel. (AC/DC) module output, the DC power system can be connected to the communication power supply panel in two ways, that is, each bus in the communication power supply panel can have 2 sets of AC/DC module output.
具体如图7所示,图中的四栋切换装置即为本发明实施例的第三自动切换装置,第一交流馈线柜(图中#1交流馈线柜)通过AC/DC模块连接第三自动切换装置的第一端,第一直流馈线屏(图中#1直流馈线屏)通过DC/DC模块连接第三自动切换装置的第一端,第三自动切换装置的第二端连接在通信电源屏的母线上;同样,第二交流馈线柜(图中#2交流馈线柜)通过AC/DC模块连接自动切换装置的第一端,第二直流馈线屏(图中#2直流馈线屏)通过DC/DC模块连接自动切换装置的第一端,第三自动切换装置的第二端连接在通信电源屏的母线上,连接的通信电源屏的母线为同一段直流48V母线。当系统对通信设备供电正常时,由DC/DC模块提供电源输出,当直流故障或者DC/DC模块故障,可自动零毫秒切换至AC/DC模块,有效的提高的系统的工作效率,并保证了系统供电的可靠性。Specifically as shown in Figure 7, the four switching devices in the figure are the third automatic switching device in the embodiment of the present invention, and the first AC feeder cabinet ( # 1 AC feeder cabinet in the figure) is connected to the third automatic switching device through the AC/DC module. The first end of the switching device, the first DC feeder screen ( # 1 DC feeder screen in the figure) is connected to the first end of the third automatic switching device through the DC/DC module, and the second end of the third automatic switching device is connected to the communication On the busbar of the power supply panel; similarly, the second AC feeder cabinet ( # 2 AC feeder cabinet in the figure) is connected to the first end of the automatic switching device through the AC/DC module, and the second DC feeder panel ( # 2 DC feeder panel in the figure) The first end of the automatic switching device is connected through the DC/DC module, and the second end of the third automatic switching device is connected to the bus bar of the communication power supply panel. The bus bar of the connected communication power supply panel is the same section of DC 48V bus bar. When the system supplies power to the communication equipment normally, the DC/DC module provides power output. When the DC fault or the DC/DC module fails, it can automatically switch to the AC/DC module in zero milliseconds, effectively improving the working efficiency of the system and ensuring reliability of the system power supply.
为保证通信电源的可靠性,风电场可以配置双重化通信电源。陆上的通讯直流部分设置独立的通信机房和通信直流蓄电池室,应用于陆上集控中心的交直流一体化系统中不包括通信电源屏和相应的蓄电池。In order to ensure the reliability of the communication power supply, the wind farm can be equipped with dual communication power supply. The onshore communication DC part is equipped with an independent communication machine room and communication DC battery room, and the AC and DC integrated system applied to the land centralized control center does not include the communication power supply panel and the corresponding battery.
在一个具体实施例中,通信电源屏还包括直流断路器;In a specific embodiment, the communication power panel further includes a DC circuit breaker;
直流断路器一端连接直流电源系统,另一端连接直流-直流模块。One end of the DC circuit breaker is connected to the DC power system, and the other end is connected to the DC-DC module.
优选的,直流断路器为B型脱扣曲线的直流断路器;B型脱扣曲线的直流断路器的额定电流小于或等于四分之一通信电源屏的输出电流。Preferably, the DC circuit breaker is a DC circuit breaker with a Type B tripping curve; the rated current of the DC circuit breaker with a Type B tripping curve is less than or equal to a quarter of the output current of the communication power supply panel.
具体而言,当通信负荷出现大电流过载冲击或馈线回路发生短路故障时,DC/DC模块的输出限流保护动作有可能造成母线电压跌落,使通信设备失电。对于海上风电场交直流电源一体化系统,可以通过断路器的配合进行可靠动作。Specifically, when there is a large current overload impact on the communication load or a short-circuit fault occurs in the feeder circuit, the output current limiting protection action of the DC/DC module may cause the bus voltage to drop and the communication equipment to lose power. For the integrated system of AC and DC power supply in offshore wind farms, it can operate reliably through the cooperation of circuit breakers.
DC/DC模块总输出电流不宜小于馈线回路中最大直流断路器额定电流的4倍,保证馈线开关的过流保护能够动作。B型微断的瞬时脱扣范围为4In~7In,适用于保护短路电流较小的负载。馈线断路器宜选用B型脱扣曲线的直流断路器,降低断路器脱扣动作值。The total output current of the DC/DC module should not be less than 4 times the rated current of the largest DC circuit breaker in the feeder circuit to ensure that the overcurrent protection of the feeder switch can operate. The instantaneous tripping range of B-type micro-break is 4In~7In, which is suitable for protecting loads with small short-circuit current. The DC circuit breaker with B-type tripping curve should be selected as the feeder circuit breaker to reduce the tripping action value of the circuit breaker.
本发明实施例简化了海上风电场的电源设备的结构,使得站用电源的可靠性、可用性和和可维性得到了提高,同时,有效地节省了海上升压站的投资成本。在实际工程应用中,还有其特殊的优势,包括:全部设备由唯一供货商负责,确保所有柜体的尺寸和大小的一致性,有效地减少屏柜数量和空间,减少调试工作量和维护费用;一体化监控,提高了海上风电场的自动化程度。可针对全系统进行自动管理运行,对各馈电系统的输出电压电流进行控制,及时、准确判断异常或故障类型,并自动实现故障保护和声光报警显示等功能。The embodiment of the present invention simplifies the structure of the power supply equipment of the offshore wind farm, so that the reliability, availability and maintainability of the station power supply are improved, and at the same time, the investment cost of the offshore booster station is effectively saved. In practical engineering applications, it also has its special advantages, including: all equipment is in charge of the only supplier, ensuring the size and size consistency of all cabinets, effectively reducing the number and space of screen cabinets, reducing debugging workload and Maintenance costs; integrated monitoring improves the automation of offshore wind farms. It can carry out automatic management and operation for the whole system, control the output voltage and current of each feeding system, timely and accurately judge the abnormality or fault type, and automatically realize functions such as fault protection and sound and light alarm display.
以上所述实施例的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施例中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The technical features of the above-mentioned embodiments can be combined arbitrarily. To make the description concise, all possible combinations of the technical features in the above-mentioned embodiments are not described. However, as long as there is no contradiction in the combination of these technical features, should be considered as within the scope of this specification.
以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only express several implementation modes of the present invention, and the descriptions thereof are relatively specific and detailed, but should not be construed as limiting the patent scope of the invention. It should be pointed out that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent for the present invention should be based on the appended claims.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810209501.9A CN108400650A (en) | 2018-03-14 | 2018-03-14 | Power of alterating and direct current integral system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810209501.9A CN108400650A (en) | 2018-03-14 | 2018-03-14 | Power of alterating and direct current integral system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN108400650A true CN108400650A (en) | 2018-08-14 |
Family
ID=63091852
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810209501.9A Pending CN108400650A (en) | 2018-03-14 | 2018-03-14 | Power of alterating and direct current integral system |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108400650A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110635553A (en) * | 2019-09-24 | 2019-12-31 | 中水淮河规划设计研究有限公司 | Based on direct current, UPS, EPS integration intelligent power supply |
| CN110867946A (en) * | 2019-11-15 | 2020-03-06 | 中国能源建设集团江苏省电力设计院有限公司 | Alternating current-direct current hybrid power supply integrated power supply |
| CN111162602A (en) * | 2020-01-16 | 2020-05-15 | 国网湖北省电力有限公司宜昌供电公司 | Comprehensive maintenance and first-aid repair platform for direct-current system of transformer substation based on alternating-current and direct-current integrated power supply |
| CN112202190A (en) * | 2020-11-06 | 2021-01-08 | 中国电建集团福建省电力勘测设计院有限公司 | Station Power Screen and Distributed Station Power System Based on Energy Storage Station |
| CN112701673A (en) * | 2021-01-15 | 2021-04-23 | 华电电力科学研究院有限公司 | Power plant comprehensive direct current system based on storage battery pack switching |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105162125A (en) * | 2015-10-27 | 2015-12-16 | 北京百度网讯科技有限公司 | Alternating/direct current power supply device and uninterruptible power supply system |
-
2018
- 2018-03-14 CN CN201810209501.9A patent/CN108400650A/en active Pending
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105162125A (en) * | 2015-10-27 | 2015-12-16 | 北京百度网讯科技有限公司 | Alternating/direct current power supply device and uninterruptible power supply system |
Non-Patent Citations (1)
| Title |
|---|
| 曾涛等: "交直流一体化电源在海上风电场的应用", 《设备管理与维修》 * |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110635553A (en) * | 2019-09-24 | 2019-12-31 | 中水淮河规划设计研究有限公司 | Based on direct current, UPS, EPS integration intelligent power supply |
| CN110867946A (en) * | 2019-11-15 | 2020-03-06 | 中国能源建设集团江苏省电力设计院有限公司 | Alternating current-direct current hybrid power supply integrated power supply |
| CN111162602A (en) * | 2020-01-16 | 2020-05-15 | 国网湖北省电力有限公司宜昌供电公司 | Comprehensive maintenance and first-aid repair platform for direct-current system of transformer substation based on alternating-current and direct-current integrated power supply |
| CN112202190A (en) * | 2020-11-06 | 2021-01-08 | 中国电建集团福建省电力勘测设计院有限公司 | Station Power Screen and Distributed Station Power System Based on Energy Storage Station |
| CN112202190B (en) * | 2020-11-06 | 2024-04-02 | 中国电建集团福建省电力勘测设计院有限公司 | Station power screen based on energy storage station and distributed station power system |
| CN112701673A (en) * | 2021-01-15 | 2021-04-23 | 华电电力科学研究院有限公司 | Power plant comprehensive direct current system based on storage battery pack switching |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107612051B (en) | An AC-DC Hybrid System Based on Dual Redundant Power Electronic Transformers | |
| Boroyevich et al. | Future electronic power distribution systems a contemplative view | |
| CN207753466U (en) | A kind of Ac/dc Power Systems based on dual redundant electric power electric transformer | |
| CN109449945B (en) | 10kV closed-loop current constraint optimization method for distribution network transfer based on DG regulation | |
| CN213521301U (en) | Data center power distribution system | |
| WO2023093172A1 (en) | Energy control system of direct current networking ship hybrid power laboratory and control method therefor | |
| CN103595071A (en) | Energy system of micro-grid | |
| CN103887834A (en) | Storage battery set flexible equalization charging and discharging management rectification module, device and system | |
| CN104242338A (en) | Micro grid system for transformer substation with distributed power supplies and control method | |
| CN106505605A (en) | Sodium-sulphur battery power station energy storage subsystem | |
| CN109004738A (en) | A kind of atomic-powered ship primary Ioops emergency power supply system and method | |
| CN107612138A (en) | A kind of low-voltage direct-current system | |
| CN211089207U (en) | Parallel charging module and double-mixed type direct current screen system applying same | |
| CN118889494A (en) | Multi-source microgrid energy storage system based on multi-port energy router and control method thereof | |
| CN203377670U (en) | Distributed intelligent direct current power supply | |
| CN118040871A (en) | A modular power guarantee system | |
| CN118889501B (en) | Emergency Power Supply Switching Strategy for Distribution Areas Based on Converged Terminals and Shared Energy Storage Systems | |
| CN105809576A (en) | Power distribution network oriented power supply safety load hierarchical evaluation method | |
| CN219592127U (en) | Energy storage unit's switching system that goes out of network | |
| CN112701673A (en) | Power plant comprehensive direct current system based on storage battery pack switching | |
| CN104065064B (en) | 110 kv substation microgrid control methods | |
| CN215601042U (en) | Power utilization system wiring of offshore flexible direct current converter station | |
| CN116632889A (en) | A new type of energy storage power supply and distribution integrated platform device and configuration method | |
| CN116191628A (en) | A mobile substation DC emergency power supply box | |
| CN118300243A (en) | Uninterruptible power supply system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180814 |