CN108396711A - A kind of detachable gravity dam and its construction, method for dismounting - Google Patents
A kind of detachable gravity dam and its construction, method for dismounting Download PDFInfo
- Publication number
- CN108396711A CN108396711A CN201810071121.3A CN201810071121A CN108396711A CN 108396711 A CN108396711 A CN 108396711A CN 201810071121 A CN201810071121 A CN 201810071121A CN 108396711 A CN108396711 A CN 108396711A
- Authority
- CN
- China
- Prior art keywords
- concrete
- block
- dam
- anchor
- block standard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/02—Fixed barrages
- E02B7/04—Dams across valleys
- E02B7/08—Wall dams
- E02B7/10—Gravity dams, i.e. those in which the weight of the structure prevents overturning
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Revetment (AREA)
Abstract
本发明涉及一种拆卸式重力坝及其施工、拆除方法,属于水利工程技术领域。本发明包括排水灌浆廊道、防渗帷幕、坝基排水孔、中墩、边墩、横缝,还包括上游混凝土面板、砌块混凝土、下游混凝土面板、素混凝土垫层、坝基锚筋;所述砌块混凝土由预制砌块按照一定的顺序通过螺栓连接而成;所述上游混凝土面板、下游混凝土面板分别浇筑在坝体的上、下游侧,素混凝土垫层铺垫在坝基上,素混凝土垫层上砌筑可拆卸的砌块混凝土,坝基锚筋布置在最底层砌块混凝土的吊装孔中。本发明可充分利用预制式混凝土构件质量可靠、施工效率高的优点,减小坝体内的温度裂缝,确保重力坝的安全,同时满足坝体拆卸方便,既经济,又环保。
The invention relates to a detachable gravity dam and its construction and removal methods, belonging to the technical field of hydraulic engineering. The invention includes drainage grouting corridor, anti-seepage curtain, dam foundation drainage hole, middle pier, side pier, transverse joint, and also includes upstream concrete panel, block concrete, downstream concrete panel, plain concrete cushion, dam foundation anchor bar; The block concrete is made of prefabricated blocks connected by bolts in a certain order; the upstream concrete panel and the downstream concrete panel are respectively poured on the upstream and downstream sides of the dam body, and the plain concrete cushion is laid on the dam foundation, and the plain concrete cushion Detachable block concrete is built on the top, and the anchor bars of the dam foundation are arranged in the hoisting holes of the bottom block concrete. The invention can make full use of the advantages of reliable quality and high construction efficiency of prefabricated concrete components, reduce the temperature cracks in the dam body, ensure the safety of the gravity dam, and meet the requirements of convenient disassembly of the dam body, which is economical and environmentally friendly.
Description
技术领域technical field
本发明涉及一种拆卸式重力坝及其施工、拆除方法,属于水利工程技术领域。The invention relates to a detachable gravity dam and its construction and removal methods, belonging to the technical field of hydraulic engineering.
背景技术Background technique
传统重力坝都是采用现浇混凝土的方法来修建,由于混凝土中的水泥在水化过程中散发出大量的水化热,可使得大体积混凝土与外界环境形成较大的温差时,很容易使得混凝土产生裂缝,从而破坏了混凝土的整体性。为了防止这种温度裂缝的产生,施工中不但要采取人工冷却、降温、散热等措施,而且还必须采用分块分层浇筑,两层之间浇筑的间隔需要5~ 10天或更长的时间,因而严重地影响了施工速度。由于施工速度受到限制,主坝体不能在短期内实现挡水或泄洪功能,施工导流工程的等级就不得不提高,因而大大的增加了施工导流的困难与费用。预制式混凝土在土木工程中应用十分广泛,在水利工程中的应用还不多,在筑坝方面的应用则更少。尽管目前已有关于装配式的筑坝的报道,比如:蒲沂大坝,但是这些坝高都很低,其方法不能简单直接应用于高坝的建设。因为目前装配式的坝体,砌块之间采用水泥砂浆来连接,由于水泥砂浆的厚度有限,与砌块之间的粘接强度不高,其抗剪能力相比砌块明显要低,因此无法满足高坝的建设。另外,目前混凝土重力坝设计时都没有考虑如何拆卸,大坝服役期满后如何处理。Traditional gravity dams are built by cast-in-place concrete. Since the cement in the concrete emits a large amount of heat of hydration during the hydration process, it is easy to cause large-volume concrete to form a large temperature difference with the external environment. Concrete develops cracks, thereby destroying the integrity of the concrete. In order to prevent such temperature cracks, not only artificial cooling, cooling, heat dissipation and other measures must be taken during construction, but also block and layer pouring must be adopted. The interval between two layers of pouring needs 5~10 days or longer , thus seriously affecting the construction speed. Due to the limited construction speed, the main dam body cannot realize the function of water retaining or flood discharge in a short period of time, so the level of construction diversion works has to be improved, thus greatly increasing the difficulty and cost of construction diversion. Precast concrete is widely used in civil engineering, but not so much in water conservancy engineering, and even less in dam building. Although there have been reports on prefabricated dams, such as the Puyi Dam, these dams are very low in height, and their methods cannot be simply and directly applied to the construction of high dams. Because of the current prefabricated dam body, the blocks are connected by cement mortar. Due to the limited thickness of the cement mortar, the bonding strength with the blocks is not high, and its shear resistance is obviously lower than that of the blocks. Therefore, Can not meet the construction of high dam. In addition, the current design of concrete gravity dams has not considered how to dismantle it, and how to deal with it after the dam's service period expires.
发明内容Contents of the invention
针对传统高重力坝容易出现温度裂缝的问题,施工中对温度控制严格,筑坝速度较低的不足,以及未考虑如何拆卸坝体的问题,本发明提出一种拆卸式重力坝及其施工、拆除方法。Aiming at the problem that the traditional high-gravity dam is prone to temperature cracks, the temperature is strictly controlled during construction, the dam-building speed is low, and the problem of how to dismantle the dam body is not considered, the present invention proposes a detachable gravity dam and its construction, Dismantling method.
本发明的技术方案是:一种拆卸式重力坝,包括排水灌浆廊道3、防渗帷幕6、坝基排水孔7、中墩10、边墩11、横缝12,还包括上游混凝土面板1、砌块混凝土2、下游混凝土面板4、素混凝土垫层5、坝基锚筋8;The technical solution of the present invention is: a detachable gravity dam, including a drainage grouting gallery 3, an anti-seepage curtain 6, a dam foundation drainage hole 7, a middle pier 10, a side pier 11, a transverse joint 12, and an upstream concrete panel 1, Block concrete 2, downstream concrete face plate 4, plain concrete cushion 5, dam foundation anchor bar 8;
所述上游混凝土面板1、下游混凝土面板4分别浇筑在坝体的上、下游侧,素混凝土垫层5铺垫在坝基上,素混凝土垫层5上砌筑可拆卸的砌块混凝土2,坝基锚筋8布置在最底层砌块混凝土2的吊装孔205中。The upstream concrete panel 1 and the downstream concrete panel 4 are respectively poured on the upstream and downstream sides of the dam body, a plain concrete cushion 5 is laid on the dam foundation, and a detachable block concrete 2 is built on the plain concrete cushion 5, and the dam foundation is anchored The ribs 8 are arranged in the hoisting holes 205 of the block concrete 2 at the bottom.
所述砌块混凝土2砌筑从上游往下游逐排逐层施工。The block concrete 2 is constructed row by row and layer by layer from upstream to downstream.
所述砌块混凝土2由砌块标准件20、1/2砌块标准件21装配而成;同层的砌块标准件20、1/2砌块标准件21之间通过锚索208连接,上、下层之间的砌块标准件20、1/2砌块标准件21通过上层侧面锚固螺杆206与下层凹面锚固螺杆203利用角铁207连接。The block concrete 2 is assembled by block standard parts 20 and 1/2 block standard parts 21; the block standard parts 20 and 1/2 block standard parts 21 of the same layer are connected by anchor cables 208, The block standard parts 20 and 1/2 block standard parts 21 between the upper and lower layers are connected with the lower layer concave anchor screw rods 203 through the upper layer side anchor screw rods 206 using angle irons 207 .
所述砌块标准件20采用四棱柱形,1/2砌块标准件21的宽度为砌块标准件20的一半,二者上表面设置凹下的键齿窝201,二者下表面设置凸出的键齿202,上表面的键齿窝201与下表面的键齿202形状、尺寸完全相同能相互嵌套;The block standard part 20 adopts a quadrangular prism shape, and the width of 1/2 block standard part 21 is half of the block standard part 20. The upper surface of the two is provided with a concave key tooth socket 201, and the lower surface of the two is provided with a convex Out of the key teeth 202, the key tooth socket 201 on the upper surface and the key tooth 202 on the lower surface are exactly the same in shape and size and can be nested with each other;
所述砌块标准件20上表面的每个键齿窝201内向外设置2个锚索孔204,共8个;砌块标准件20的键齿窝201之间设置凹面锚固螺杆203,共4个;砌块标准件20每个侧面下部设置2个侧面锚固螺杆206,侧面锚固螺杆206中心对准下表面的键齿202中心,在每个键齿窝201中心设置椭圆形吊装孔205共4个;Each key socket 201 on the upper surface of the block standard part 20 is provided with 2 anchor holes 204, a total of 8; a concave anchor screw 203 is arranged between the key tooth sockets 201 of the block standard part 20, a total of 4 Two side anchoring screw rods 206 are arranged at the lower part of each side of the block standard part 20, and the center of the side anchoring screw rods 206 is aligned with the center of the key tooth 202 on the lower surface, and an oval hoisting hole 205 is arranged at the center of each key tooth socket 201. 4 indivual;
所述1/2砌块标准件21上表面的每个键齿窝内向外设置3个锚索孔204,共6个;1/2砌块标准件21的键齿窝201之间设置1个凹面锚固螺杆203;1/2砌块标准件21砌块长边侧面下部设置2个侧面锚固螺杆206,短边侧面下部设置1个侧面锚固螺杆206,侧面锚固螺杆206中心对准下表面的键齿202中心,在每个键齿窝201中心设置椭圆形吊装孔205,共2个。3 anchor cable holes 204 are set outward in each key tooth socket on the upper surface of the 1/2 block standard part 21, a total of 6; 1 is set between the key tooth sockets 201 of the 1/2 block standard part 21 Concave anchoring screw 203; 1/2 block standard part 21 is provided with two side anchoring screws 206 on the lower side of the long side of the block, and one side anchoring screw 206 is set on the lower side of the short side, and the center of the side anchoring screw 206 is aligned with the key on the lower surface At the center of the tooth 202, an oval hoisting hole 205 is provided at the center of each tooth socket 201, a total of 2.
所述砌块标准件20、1/2砌块标准件21采用C15或C20混凝土。The block standard part 20 and 1/2 block standard part 21 adopt C15 or C20 concrete.
所述角铁207为L形钢板,板厚取25~35mm,板的两翼开有圆孔。The angle iron 207 is an L-shaped steel plate with a thickness of 25-35mm, and round holes are opened on the two wings of the plate.
所述锚索208为钢绞线,直径取30~50mm,两端带螺丝杆。The anchor cable 208 is a steel strand with a diameter of 30-50 mm and screw rods at both ends.
所述凹面锚固螺杆203、侧面锚固螺杆206二者直径取30~50mm,长度取40~60cm,凹面锚固螺杆203一端焊接一块钢板浇筑在砌块内,凹面锚固螺杆203另一端出露在砌块上表面的锚固孔内;侧面锚固螺杆206一端焊接一块钢板浇筑在砌块内,侧面锚固螺杆206另一端出露在砌块上侧面的锚固孔内;其中砌块为砌块标准件20或1/2砌块标准件21。The diameter of the concave anchor screw 203 and the side anchor screw 206 is 30-50 mm, and the length is 40-60 cm. One end of the concave anchor screw 203 is welded with a steel plate and poured into the block, and the other end of the concave anchor screw 203 is exposed on the block. In the anchor hole on the upper surface; one end of the side anchor screw 206 is welded with a steel plate and poured in the block, and the other end of the side anchor screw 206 is exposed in the anchor hole on the upper side of the block; the block is a block standard part 20 or 1 /2 block standard parts 21.
所述上游混凝土面板1厚度从坝顶向坝底逐渐加厚,坝顶厚度取0.3m,坝底厚度取0.5~1.5m;上游混凝土面板1强度不低于C25,抗渗等级不低于W8;对于非溢流坝段下游混凝土面板4取等厚,厚度取20cm,板上间隔设置排水孔;对于溢流坝段,下游混凝土面板4厚度取50cm,在堰顶和堰下游反弧段厚度加厚,混凝土强度不低于C25。The thickness of the upstream concrete panel 1 gradually increases from the top to the bottom of the dam, the thickness of the dam top is 0.3m, and the thickness of the dam bottom is 0.5~1.5m; the strength of the upstream concrete panel 1 is not lower than C25, and the impermeability level is not lower than W8 ; For the downstream concrete face plate 4 of the non-overflow dam section, the thickness is equal to 20cm, and drainage holes are arranged at intervals on the plate; Thickened, the concrete strength is not lower than C25.
所述排水灌浆廊道3采用普通钢筋混凝土结构,在排水灌浆廊道3与砌块之间充填混凝土;排水灌浆廊道3边墙和顶拱间隔设置排水孔;其中砌块为砌块标准件20或1/2砌块标准件21。The drainage and grouting corridor 3 adopts ordinary reinforced concrete structure, and concrete is filled between the drainage and grouting corridor 3 and the blocks; the side walls and the top arch of the drainage and grouting corridor 3 are provided with drainage holes at intervals; the blocks are block standard parts 20 or 1/2 block standard pieces 21.
所述素混凝土垫层5厚度取1~2m。The thickness of the plain concrete cushion layer 5 is 1-2m.
所述坝基锚筋8深入地基2~3m,直径40~50mm。The dam foundation anchor bar 8 is 2-3m deep into the foundation, and has a diameter of 40-50mm.
所述上游混凝土面板1、下游混凝土面板4分别通过其邻近的砌块混凝土2内布置面板锚筋9与面板钢筋骨架相连接浇筑在坝体的上、下游侧。The upstream concrete panel 1 and the downstream concrete panel 4 are respectively poured on the upstream and downstream sides of the dam body through the connection of the panel anchor bar 9 arranged in the adjacent block concrete 2 to the panel reinforcement skeleton.
所述中墩10、边墩11采用钢筋混凝土结构浇筑在溢流堰上。The middle pier 10 and the side pier 11 are poured on the overflow weir with a reinforced concrete structure.
一种拆卸式重力坝的施工方法,包括如下步骤:A construction method for a dismantled gravity dam, comprising the steps of:
S1、清基,清除河床冲积层至设计高程,清除坝轴线两岸坡积层;S1. Clear the foundation, remove the alluvial layer of the riverbed to the design elevation, and remove the slope layer on both sides of the dam axis;
S2、浇筑坝基素混凝土垫层5;S2, pouring the dam foundation element concrete cushion 5;
S3、施工排水灌浆廊道3,门洞形截面;S3. Construction drainage and grouting corridor 3, doorway-shaped section;
S4、砌块砌筑,沿坝轴线每隔15~20m距离设置横缝12;其中砌块为砌块标准件20或1/2砌块标准件21;S4, block masonry, set transverse joints 12 at intervals of 15-20m along the axis of the dam; the blocks are block standard parts 20 or 1/2 block standard parts 21;
S5、最底层砌块砌筑好后,再施工砌块中的坝基锚筋8;S5, after the lowest floor block is built, then construct the dam foundation anchor bar 8 in the block;
S6、施工上游混凝土面板1和下游混凝土面板4,直至坝顶预定高程:首先绑扎钢筋骨架,并在砌块的侧面的锚索孔204内埋设面板锚筋9,一切准备就绪后即可浇筑混凝土;S6. Construct the upstream concrete panel 1 and the downstream concrete panel 4 until the predetermined height of the dam crest: first bind the reinforcement skeleton, and bury the panel anchor bar 9 in the anchor cable hole 204 on the side of the block, and pour the concrete after everything is ready ;
S7、当坝体砌筑到3~5m高度后,就可同时施工防渗帷幕6和坝基排水孔7;S7, when the dam body is built to a height of 3-5m, the anti-seepage curtain 6 and the dam foundation drainage hole 7 can be constructed simultaneously;
S8、当砌块坝体施工到坝顶预定高程后,再浇筑坝顶构件;S8, when the block dam body is constructed to the predetermined height of the dam crest, then pour the dam crest components;
S9、溢流坝段上的中墩10、边墩11采用钢筋混凝土结构浇筑在溢流堰上。S9. The middle pier 10 and the side pier 11 on the overflow dam section are poured on the overflow weir with a reinforced concrete structure.
所述坝顶构件包括坝顶混凝土保护层、防浪墙;坝顶浇筑20~30cm厚钢筋混凝土板作为坝顶混凝土保护层。The crest components include a crest concrete protective layer and a wave wall; a 20-30 cm thick reinforced concrete slab is poured on the dam crest as the dam crest concrete protective layer.
一种拆卸式重力坝的拆除方法,首先凿开坝顶浇筑的混凝土和下游混凝土面板4,露出砌块标准件20、1/2砌块标准件21,拆卸掉砌块标准件20或1/2砌块标准件21四周的角铁207和锚索208,即可用起重机将砌块标准件20、1/2砌块标准件21吊走实现拆除。A dismantling method of a dismountable gravity dam, firstly, the concrete poured on the top of the dam and the downstream concrete face plate 4 are cut open to expose the block standard part 20 and 1/2 block standard part 21, and the block standard part 20 or 1/2 2 The angle iron 207 and the anchor cable 208 around the block standard part 21 can be hoisted away by a crane to remove the block standard part 20 and 1/2 block standard part 21.
拆除时从下游往上游逐排逐层拆除。When dismantling, it is removed row by row from downstream to upstream.
本发明的有益效果是:The beneficial effects of the present invention are:
1、混凝土砌块便于工厂化生产,质量易于控制,不会出现温度裂缝;同时预制件质量易于检验,若出现问题可及时弥补,从而提高工程质量。1. Concrete blocks are convenient for factory production, the quality is easy to control, and there will be no temperature cracks; at the same time, the quality of prefabricated parts is easy to inspect, and any problems can be made up in time, thereby improving the quality of the project.
2、混凝土砌块可全面逐层连续不断地进行砌筑,不受混凝土现场浇筑施工的制约,更不需要立模、拆模、养护等工序,受气候影响小,所以施工简便,施工速度快。2. Concrete blocks can be built continuously layer by layer without being restricted by concrete pouring on site, and do not need to formwork, formwork removal, maintenance and other processes, and are less affected by the climate, so the construction is simple and the construction speed is fast .
3、由于施工速度加快,大坝主体工程可在短时间内实现挡水和泄洪功能,可大大减少施工导流的工程量及费用。3. Due to the accelerated construction speed, the main project of the dam can realize the functions of water retaining and flood discharge in a short time, which can greatly reduce the engineering volume and cost of construction diversion.
4、坝体主要由砌块组成,砌块之间通过螺栓连接,拆卸方便,拆卸的砌块可以回收再利用,既经济,又环保。4. The dam body is mainly composed of blocks. The blocks are connected by bolts, which is easy to disassemble. The disassembled blocks can be recycled and reused, which is economical and environmentally friendly.
5、由于砌块之间通过螺栓连接,砌块之间存在缝隙可以排泄坝体渗水,坝体可以不设置排水管。5. Since the blocks are connected by bolts, there are gaps between the blocks to drain the seepage of the dam body, and the dam body may not be provided with a drainpipe.
综上,本发明可充分利用预制式混凝土构件质量可靠、施工效率高的优点,减小坝体内的温度裂缝,确保重力坝的安全,同时满足坝体拆卸方便,既经济,又环保。In summary, the invention can make full use of the advantages of reliable quality and high construction efficiency of prefabricated concrete components, reduce the temperature cracks in the dam body, ensure the safety of the gravity dam, and at the same time meet the convenience of disassembly of the dam body, which is economical and environmentally friendly.
附图说明Description of drawings
图1为本发明的典型坝段剖面示意图;Fig. 1 is a typical dam section schematic diagram of the present invention;
图2为本发明的大坝下游立视图;Fig. 2 is the vertical view of the downstream of the dam of the present invention;
图3为本发明的砌块标准件示意图;Fig. 3 is the block schematic diagram of the present invention;
图4为本发明的1/2砌块标准件示意图;Fig. 4 is the schematic diagram of 1/2 block standard part of the present invention;
图5为本发明的砌块标准件凹面示意图;Fig. 5 is the concave schematic diagram of block standard part of the present invention;
图6为本发明的砌块标准件凸面示意图;Fig. 6 is the schematic diagram of the convex surface of block standard part of the present invention;
图7为本发明的砌块标准件立视图;Fig. 7 is the vertical view of block standard part of the present invention;
图8为本发明的角铁示意图;Fig. 8 is the angle iron schematic diagram of the present invention;
图9为本发明的锚索示意图;Fig. 9 is a schematic diagram of the anchor cable of the present invention;
图10为本发明砌块砌体横剖面图;Fig. 10 is a cross-sectional view of a block masonry of the present invention;
图11为本发明砌块砌体平面图;Fig. 11 is a block masonry plan view of the present invention;
图中各标号为:1-上游混凝土面板、2-砌块混凝土、3-排水灌浆廊道、4-下游混凝土面板、5-素混凝土垫层、6-防渗帷幕、7-坝基排水孔、8-坝基锚筋、9-面板锚筋、10-中墩、11-边墩、12-横缝12、20-砌块标准件、21-1/2砌块标准件、201-键齿窝、202-键齿、203-凹面锚固螺杆、204-锚索孔、205-吊装孔、206-侧面锚固螺杆、207-角铁、208-锚索。The labels in the figure are: 1-upstream concrete panel, 2-block concrete, 3-drainage grouting corridor, 4-downstream concrete panel, 5-plain concrete cushion, 6-seepage-proof curtain, 7-dam foundation drainage hole, 8-dam foundation anchor bar, 9-face plate anchor bar, 10-middle pier, 11-side pier, 12-transverse joint 12, 20-block standard part, 21-1/2 block standard part, 201-key socket , 202-key tooth, 203-concave anchor screw, 204-anchor cable hole, 205-hoisting hole, 206-side anchor screw, 207-angle iron, 208-anchor cable.
具体实施方式Detailed ways
下面结合附图和实施例,对本发明作进一步说明,但本发明的内容并不限于所述范围。The present invention will be further described below in conjunction with the accompanying drawings and embodiments, but the content of the present invention is not limited to the stated scope.
实施例1:如图1-11所示,一种拆卸式重力坝,包括排水灌浆廊道3、防渗帷幕6、坝基排水孔7、中墩10、边墩11、横缝12,还包括上游混凝土面板1、砌块混凝土2、下游混凝土面板4、素混凝土垫层5、坝基锚筋8;Embodiment 1: As shown in Figure 1-11, a detachable gravity dam includes drainage grouting corridor 3, anti-seepage curtain 6, dam foundation drainage hole 7, middle pier 10, side pier 11, transverse joint 12, and also includes Upstream concrete face 1, block concrete 2, downstream concrete face 4, plain concrete cushion 5, dam foundation anchor bars 8;
所述上游混凝土面板1、下游混凝土面板4分别浇筑在坝体的上、下游侧,素混凝土垫层5铺垫在坝基上,素混凝土垫层5上砌筑可拆卸的砌块混凝土2,坝基锚筋8布置在最底层砌块混凝土2的吊装孔205中。The upstream concrete panel 1 and the downstream concrete panel 4 are respectively poured on the upstream and downstream sides of the dam body, a plain concrete cushion 5 is laid on the dam foundation, and a detachable block concrete 2 is built on the plain concrete cushion 5, and the dam foundation is anchored The ribs 8 are arranged in the hoisting holes 205 of the block concrete 2 at the bottom.
进一步地,可以设置所述砌块混凝土由预制砌块按照一定的顺序通过螺栓连接而成;具体的可以设置:所述砌块混凝土2砌筑从上游往下游逐排逐层施工。所述砌块混凝土2由砌块标准件20、1/2砌块标准件21装配而成;同层的砌块标准件20、1/2砌块标准件21之间通过锚索208连接,上、下层之间的砌块标准件20、1/2砌块标准件21通过上层侧面锚固螺杆206与下层凹面锚固螺杆203利用角铁207连接。Further, it can be set that the block concrete is made of prefabricated blocks connected by bolts in a certain order; specifically, it can be set that: the block concrete 2 is constructed row by row from upstream to downstream. The block concrete 2 is assembled by block standard parts 20 and 1/2 block standard parts 21; the block standard parts 20 and 1/2 block standard parts 21 of the same layer are connected by anchor cables 208, The block standard parts 20 and 1/2 block standard parts 21 between the upper and lower layers are connected with the lower layer concave anchor screw rods 203 through the upper layer side anchor screw rods 206 using angle irons 207 .
进一步地,可以设置所述砌块标准件20采用四棱柱形(如尺寸为3m×1.5m×1.5m),1/2砌块标准件21的宽度为砌块标准件20的一半(如1/2砌块标准件21尺寸可取),二者上表面设置凹下的键齿窝201,二者下表面设置凸出的键齿202,上表面的键齿窝201与下表面的键齿202形状、尺寸完全相同能相互嵌套(如尺寸长宽可取0.5m×0.5m);所述砌块标准件20上表面的每个键齿窝201内向外设置2个锚索孔204,共8个;砌块标准件20的键齿窝201之间设置凹面锚固螺杆203,共4个;砌块标准件20每个侧面下部设置2个侧面锚固螺杆206,侧面锚固螺杆206中心对准下表面的键齿202中心,在每个键齿窝201中心设置椭圆形吊装孔205共4个;所述1/2砌块标准件21上表面的每个键齿窝内向外设置3个锚索孔204,共6个;1/2砌块标准件21的键齿窝201之间设置1个凹面锚固螺杆203;1/2砌块标准件21砌块长边侧面下部设置2个侧面锚固螺杆206,短边侧面下部设置1个侧面锚固螺杆206,侧面锚固螺杆206中心对准下表面的键齿202中心,在每个键齿窝201中心设置椭圆形吊装孔205,共2个。Further, it can be set that the block standard part 20 adopts a quadrangular prism shape (for example, the size is 3m×1.5m×1.5m), and the width of 1/2 block standard part 21 is half of the block standard part 20 (such as 1 /2 block standard part 21 size is optional), the upper surface of the two is provided with a concave tooth socket 201, and the lower surface of the two is provided with a protruding key tooth 202, the key tooth socket 201 on the upper surface and the key tooth 202 on the lower surface The shape and size are exactly the same and can be nested with each other (for example, the size, length and width can be 0.5m×0.5m); each key tooth socket 201 on the upper surface of the block standard part 20 is provided with 2 anchor holes 204 inside and outside, a total of 8 Concave anchoring screw rods 203 are arranged between the key tooth sockets 201 of the block standard part 20, a total of 4; two side anchoring screw rods 206 are arranged at the lower part of each side of the block standard part 20, and the center of the side anchoring screw rods 206 is aligned with the lower surface At the center of the key tooth 202, a total of 4 elliptical hoisting holes 205 are set in the center of each key tooth socket 201; 3 anchor holes are set outward in each key tooth socket on the upper surface of the 1/2 block standard part 21 204, 6 in total; 1 concave anchor screw 203 is set between the key tooth sockets 201 of 1/2 block standard part 21; 2 side anchor screw rods 206 are set at the lower part of the long side of 1/2 block standard part 21 , a side anchoring screw 206 is arranged at the lower part of the side of the short side, the center of the side anchoring screw 206 is aligned with the center of the key tooth 202 on the lower surface, and an oval hoisting hole 205 is set at the center of each key tooth socket 201, a total of 2.
进一步地,可以设置所述砌块标准件20、1/2砌块标准件21采用C15混凝土。Further, it can be set that the block standard part 20 and 1/2 block standard part 21 adopt C15 concrete.
进一步地,可以设置所述角铁207为L形钢板,板厚取25mm,板的两翼开有圆孔。Further, the angle iron 207 can be set as an L-shaped steel plate with a thickness of 25 mm, and round holes are opened on both wings of the plate.
进一步地,可以设置所述锚索208为钢绞线,直径取30mm,两端带螺丝杆。Further, the anchor cable 208 can be set as a steel strand with a diameter of 30 mm and screw rods at both ends.
进一步地,可以设置所述凹面锚固螺杆203、侧面锚固螺杆206二者直径取30mm,长度取40cm,凹面锚固螺杆203一端焊接一块钢板浇筑在砌块内,凹面锚固螺杆203另一端出露在砌块上表面的锚固孔内;侧面锚固螺杆206一端焊接一块钢板浇筑在砌块内,侧面锚固螺杆206另一端出露在砌块上侧面的锚固孔内;其中砌块为砌块标准件20或1/2砌块标准件21。Further, the concave anchor screw 203 and the side anchor screw 206 can be set to have a diameter of 30 mm and a length of 40 cm. One end of the concave anchor screw 203 is welded with a steel plate and poured into the block, and the other end of the concave anchor screw 203 is exposed on the block. In the anchor hole on the upper surface of the block; one end of the side anchor screw 206 is welded with a steel plate and poured in the block, and the other end of the side anchor screw 206 is exposed in the anchor hole on the upper side of the block; the block is a block standard part 20 or 1/2 block standard 21.
进一步地,可以设置所述上游混凝土面板1厚度从坝顶向坝底逐渐加厚,坝顶厚度取0.3m,坝底厚度取0.5m;上游混凝土面板1强度不低于C25,抗渗等级不低于W8;对于非溢流坝段下游混凝土面板4取等厚,厚度取20cm,板上间隔设置排水孔;对于溢流坝段,下游混凝土面板4厚度取50cm,在堰顶和堰下游反弧段厚度加厚,混凝土强度不低于C25。Further, the thickness of the upstream concrete panel 1 can be set to gradually thicken from the crest to the bottom of the dam, the thickness of the dam crest is 0.3m, and the thickness of the dam bottom is 0.5m; the strength of the upstream concrete panel 1 is not lower than C25, and the impermeability level is not lower than lower than W8; for the non-overflow dam section, the thickness of the downstream concrete panel 4 is equal to 20cm, and drainage holes are arranged at intervals on the panel; The thickness of the arc section is thickened, and the concrete strength is not lower than C25.
进一步地,可以设置所述排水灌浆廊道3采用普通钢筋混凝土结构,尺寸可取2.5m×3.5m左右,在排水灌浆廊道3与砌块之间充填混凝土;排水灌浆廊道3边墙和顶拱间隔设置排水孔;其中砌块为砌块标准件20或1/2砌块标准件21。Further, the drainage grouting corridor 3 can be set to adopt an ordinary reinforced concrete structure, and the size can be about 2.5m×3.5m, and concrete is filled between the drainage grouting corridor 3 and the blocks; the side walls and the top of the drainage grouting corridor 3 Drainage holes are arranged at intervals in the arch; the blocks are block standard parts 20 or 1/2 block standard parts 21.
进一步地,可以设置所述素混凝土垫层5厚度取1m。Further, the thickness of the plain concrete cushion layer 5 can be set to be 1m.
进一步地,可以设置所述坝基锚筋8深入地基2m,直径40mm。Further, the dam foundation anchor bar 8 can be set to be 2m deep into the foundation, with a diameter of 40mm.
进一步地,可以设置所述上游混凝土面板1、下游混凝土面板4分别通过其邻近的砌块混凝土2内布置面板锚筋9与面板钢筋骨架相连接浇筑在坝体的上、下游侧。Further, the upstream concrete panel 1 and the downstream concrete panel 4 can be set to be poured on the upstream and downstream sides of the dam body through the panel anchor bars 9 arranged in the adjacent block concrete 2 to connect with the panel steel skeleton.
所述中墩10、边墩11采用钢筋混凝土结构浇筑在溢流堰上。The middle pier 10 and the side pier 11 are poured on the overflow weir with a reinforced concrete structure.
一种拆卸式重力坝的施工方法,包括如下步骤:A construction method for a dismantled gravity dam, comprising the steps of:
S1、清基,清除河床冲积层至设计高程,清除坝轴线两岸坡积层;S1. Clear the foundation, remove the alluvial layer of the riverbed to the design elevation, and remove the slope layer on both sides of the dam axis;
S2、浇筑坝基素混凝土垫层5;S2, pouring the dam foundation element concrete cushion 5;
S3、施工排水灌浆廊道3,门洞形截面;S3. Construction drainage and grouting corridor 3, doorway-shaped section;
S4、砌块砌筑,沿坝轴线每隔15m距离设置横缝12;其中砌块为砌块标准件20或1/2砌块标准件21;S4, block masonry, set transverse joints 12 at intervals of 15m along the axis of the dam; the blocks are block standard parts 20 or 1/2 block standard parts 21;
S5、最底层砌块砌筑好后,再施工砌块中的坝基锚筋8;S5, after the lowest floor block is built, then construct the dam foundation anchor bar 8 in the block;
S6、施工上游混凝土面板1和下游混凝土面板4,直至坝顶预定高程:首先绑扎钢筋骨架,并在砌块的侧面的锚索孔204内埋设面板锚筋9,一切准备就绪后即可浇筑混凝土;S6. Construct the upstream concrete panel 1 and the downstream concrete panel 4 until the predetermined height of the dam crest: first bind the reinforcement skeleton, and bury the panel anchor bar 9 in the anchor cable hole 204 on the side of the block, and pour the concrete after everything is ready ;
S7、当坝体砌筑到3m高度后,就可同时施工防渗帷幕6和坝基排水孔7;S7, when the dam body is built to a height of 3m, the anti-seepage curtain 6 and the dam foundation drainage hole 7 can be constructed simultaneously;
S8、当砌块坝体施工到坝顶预定高程后,再浇筑坝顶构件;S8, when the block dam body is constructed to the predetermined height of the dam crest, then pour the dam crest components;
S9、溢流坝段上的中墩10、边墩11采用钢筋混凝土结构浇筑在溢流堰上。S9. The middle pier 10 and the side pier 11 on the overflow dam section are poured on the overflow weir with a reinforced concrete structure.
进一步地,可以设置所述坝顶构件包括坝顶混凝土保护层、防浪墙;坝顶浇筑20cm厚钢筋混凝土板作为坝顶混凝土保护层。Further, the dam crest member may be set to include a crest concrete protective layer and a wave wall; a 20cm thick reinforced concrete slab is poured on the dam crest as the dam crest concrete protective layer.
一种拆卸式重力坝的拆除方法,首先凿开坝顶浇筑的混凝土和下游混凝土面板4,露出砌块标准件20、1/2砌块标准件21,拆卸掉砌块标准件20或1/2砌块标准件21四周的角铁207和锚索208,即可用起重机将砌块标准件20、1/2砌块标准件21吊走实现拆除。A dismantling method of a dismountable gravity dam, firstly, the concrete poured on the top of the dam and the downstream concrete face plate 4 are cut open to expose the block standard part 20 and 1/2 block standard part 21, and the block standard part 20 or 1/2 2 The angle iron 207 and the anchor cable 208 around the block standard part 21 can be hoisted away by a crane to remove the block standard part 20 and 1/2 block standard part 21.
进一步地,可以设置拆除时从下游往上游逐排逐层拆除。Further, it can be set to dismantle row by row and layer by row from downstream to upstream during dismantling.
实施例2:如图1-11所示,一种拆卸式重力坝,包括排水灌浆廊道3、防渗帷幕6、坝基排水孔7、中墩10、边墩11、横缝12,还包括上游混凝土面板1、砌块混凝土2、下游混凝土面板4、素混凝土垫层5、坝基锚筋8;所述上游混凝土面板1、下游混凝土面板4分别浇筑在坝体的上、下游侧,素混凝土垫层5铺垫在坝基上,素混凝土垫层5上砌筑可拆卸的砌块混凝土2,坝基锚筋8布置在最底层砌块混凝土2的吊装孔205中。Embodiment 2: As shown in Figure 1-11, a detachable gravity dam includes drainage grouting corridor 3, anti-seepage curtain 6, dam foundation drainage hole 7, middle pier 10, side pier 11, transverse joint 12, and also includes Upstream concrete panel 1, block concrete 2, downstream concrete panel 4, plain concrete cushion 5, dam foundation anchor bars 8; the upstream concrete panel 1 and downstream concrete panel 4 are respectively poured on the upstream and downstream sides of the dam body, and the plain concrete Cushion layer 5 is paved on the dam foundation, and detachable block concrete 2 is built on the plain concrete cushion layer 5 , and anchor bar 8 of the dam foundation is arranged in the hoisting hole 205 of the bottom block concrete 2 .
进一步地,可以设置所述砌块混凝土由预制砌块按照一定的顺序通过螺栓连接而成;具体的可以设置:所述砌块混凝土2砌筑从上游往下游逐排逐层施工。所述砌块混凝土2由砌块标准件20、1/2砌块标准件21装配而成;同层的砌块标准件20、1/2砌块标准件21之间通过锚索208连接,上、下层之间的砌块标准件20、1/2砌块标准件21通过上层侧面锚固螺杆206与下层凹面锚固螺杆203利用角铁207连接。Further, it can be set that the block concrete is made of prefabricated blocks connected by bolts in a certain order; specifically, it can be set that: the block concrete 2 is constructed row by row from upstream to downstream. The block concrete 2 is assembled by block standard parts 20 and 1/2 block standard parts 21; the block standard parts 20 and 1/2 block standard parts 21 of the same layer are connected by anchor cables 208, The block standard parts 20 and 1/2 block standard parts 21 between the upper and lower layers are connected with the lower layer concave anchor screw rods 203 through the upper layer side anchor screw rods 206 using angle irons 207 .
进一步地,可以设置所述砌块标准件20采用四棱柱形,1/2砌块标准件21的宽度为砌块标准件20的一半,二者上表面设置凹下的键齿窝201,二者下表面设置凸出的键齿202,上表面的键齿窝201与下表面的键齿202形状、尺寸完全相同能相互嵌套;所述砌块标准件20上表面的每个键齿窝201内向外设置2个锚索孔204,共8个;砌块标准件20的键齿窝201之间设置凹面锚固螺杆203,共4个;砌块标准件20每个侧面下部设置2个侧面锚固螺杆206,侧面锚固螺杆206中心对准下表面的键齿202中心,在每个键齿窝201中心设置椭圆形吊装孔205共4个;所述1/2砌块标准件21上表面的每个键齿窝内向外设置3个锚索孔204,共6个;1/2砌块标准件21的键齿窝201之间设置1个凹面锚固螺杆203;1/2砌块标准件21砌块长边侧面下部设置2个侧面锚固螺杆206,短边侧面下部设置1个侧面锚固螺杆206,侧面锚固螺杆206中心对准下表面的键齿202中心,在每个键齿窝201中心设置椭圆形吊装孔205,共2个。Further, it can be set that the block standard part 20 adopts a quadrangular prism shape, and the width of 1/2 block standard part 21 is half of the block standard part 20, and the upper surface of the two is provided with a concave key tooth socket 201, two Or the lower surface is provided with protruding teeth 202, and the shape and size of the teeth 201 on the upper surface and the teeth 202 on the lower surface are exactly the same and can be nested with each other; each tooth socket on the upper surface of the block standard part 20 There are 2 anchor cable holes 204 inside and outside of 201, 8 in total; concave anchor screw rods 203 are set between the key tooth sockets 201 of block standard part 20, 4 in total; 2 side faces are set at the lower part of each side of block standard part 20 Anchor screw 206, the center of side anchor screw 206 is aligned with the center of the key teeth 202 on the lower surface, and a total of 4 oval hoisting holes 205 are set in the center of each key tooth socket 201; the upper surface of the 1/2 block standard part 21 3 anchor cable holes 204 are set outward in each key tooth socket, a total of 6; 1/2 block standard part 21 is provided with a concave anchor screw 203 between the key tooth sockets 201; 1/2 block standard part 21 Two side anchoring screws 206 are set on the lower side of the long side of the block, and one side anchoring screw 206 is set on the lower side of the short side. There are 2 oval hoisting holes 205 in total.
进一步地,可以设置所述砌块标准件20、1/2砌块标准件21采用C20混凝土。Further, it can be set that the block standard part 20 and 1/2 block standard part 21 adopt C20 concrete.
进一步地,可以设置所述角铁207为L形钢板,板厚取35mm,板的两翼开有圆孔。Further, the angle iron 207 can be set as an L-shaped steel plate with a thickness of 35mm, and round holes are opened on both wings of the plate.
进一步地,可以设置所述锚索208为钢绞线,直径取50mm,两端带螺丝杆。Further, the anchor cable 208 can be set as a steel strand with a diameter of 50 mm and screw rods at both ends.
进一步地,可以设置所述凹面锚固螺杆203、侧面锚固螺杆206二者直径取50mm,长度取60cm,凹面锚固螺杆203一端焊接一块钢板浇筑在砌块内,凹面锚固螺杆203另一端出露在砌块上表面的锚固孔内;侧面锚固螺杆206一端焊接一块钢板浇筑在砌块内,侧面锚固螺杆206另一端出露在砌块上侧面的锚固孔内;其中砌块为砌块标准件20或1/2砌块标准件21。Further, the concave anchoring screw 203 and the side anchoring screw 206 can be set to have a diameter of 50 mm and a length of 60 cm. One end of the concave anchoring screw 203 is welded with a steel plate and poured into the block, and the other end of the concave anchoring screw 203 is exposed on the masonry. In the anchor hole on the upper surface of the block; one end of the side anchor screw 206 is welded with a steel plate and poured in the block, and the other end of the side anchor screw 206 is exposed in the anchor hole on the upper side of the block; the block is a block standard part 20 or 1/2 block standard 21.
进一步地,可以设置所述上游混凝土面板1厚度从坝顶向坝底逐渐加厚,坝顶厚度取0.3m,坝底厚度取1.5m;上游混凝土面板1强度不低于C25,抗渗等级不低于W8;对于非溢流坝段下游混凝土面板4取等厚,厚度取20cm,板上间隔设置排水孔;对于溢流坝段,下游混凝土面板4厚度取50cm,在堰顶和堰下游反弧段厚度加厚,混凝土强度不低于C25。Further, the thickness of the upstream concrete panel 1 can be set to gradually thicken from the crest to the bottom of the dam, the thickness of the dam crest is 0.3m, and the thickness of the dam bottom is 1.5m; the strength of the upstream concrete panel 1 is not lower than C25, and the impermeability level is not lower than lower than W8; for the non-overflow dam section, the thickness of the downstream concrete panel 4 is equal to 20cm, and drainage holes are arranged at intervals on the panel; The thickness of the arc section is thickened, and the concrete strength is not lower than C25.
进一步地,可以设置所述排水灌浆廊道3采用普通钢筋混凝土结构,在排水灌浆廊道3与砌块之间充填混凝土;排水灌浆廊道3边墙和顶拱间隔设置排水孔;其中砌块为砌块标准件20或1/2砌块标准件21。Further, the drainage grouting corridor 3 can be set to adopt an ordinary reinforced concrete structure, and concrete is filled between the drainage grouting corridor 3 and the blocks; drainage holes are arranged at intervals between the side walls and the top arch of the drainage grouting corridor 3; It is block standard part 20 or 1/2 block standard part 21.
进一步地,可以设置所述素混凝土垫层5厚度取2m。Further, the thickness of the plain concrete cushion 5 can be set to be 2m.
进一步地,可以设置所述坝基锚筋8深入地基3m,直径50mm。Further, the dam foundation anchor bar 8 can be set to be 3m deep into the foundation, with a diameter of 50mm.
进一步地,可以设置所述上游混凝土面板1、下游混凝土面板4分别通过其邻近的砌块混凝土2内布置面板锚筋9与面板钢筋骨架相连接浇筑在坝体的上、下游侧。Further, the upstream concrete panel 1 and the downstream concrete panel 4 can be set to be poured on the upstream and downstream sides of the dam body through the panel anchor bars 9 arranged in the adjacent block concrete 2 to connect with the panel steel skeleton.
进一步地,可以设置所述中墩10、边墩11采用钢筋混凝土结构浇筑在溢流堰上。Further, the middle pier 10 and the side pier 11 can be set to be poured on the overflow weir with a reinforced concrete structure.
一种拆卸式重力坝的施工方法,包括如下步骤:A construction method for a dismantled gravity dam, comprising the steps of:
S1、清基,清除河床冲积层至设计高程,清除坝轴线两岸坡积层;S1. Clear the foundation, remove the alluvial layer of the riverbed to the design elevation, and remove the slope layer on both sides of the dam axis;
S2、浇筑坝基素混凝土垫层5;S2, pouring the dam foundation element concrete cushion 5;
S3、施工排水灌浆廊道3,门洞形截面;S3. Construction drainage and grouting corridor 3, doorway-shaped section;
S4、砌块砌筑,沿坝轴线每隔20m距离设置横缝12;其中砌块为砌块标准件20或1/2砌块标准件21;S4, block masonry, set transverse joints 12 at intervals of 20m along the axis of the dam; the blocks are block standard parts 20 or 1/2 block standard parts 21;
S5、最底层砌块砌筑好后,再施工砌块中的坝基锚筋8;S5, after the lowest floor block is built, then construct the dam foundation anchor bar 8 in the block;
S6、施工上游混凝土面板1和下游混凝土面板4,直至坝顶预定高程:首先绑扎钢筋骨架,并在砌块的侧面的锚索孔204内埋设面板锚筋9,一切准备就绪后即可浇筑混凝土;S6. Construct the upstream concrete panel 1 and the downstream concrete panel 4 until the predetermined height of the dam crest: first bind the reinforcement skeleton, and bury the panel anchor bar 9 in the anchor cable hole 204 on the side of the block, and pour the concrete after everything is ready ;
S7、当坝体砌筑到5m高度后,就可同时施工防渗帷幕6和坝基排水孔7;S7, when the dam body is built to a height of 5m, the anti-seepage curtain 6 and the dam foundation drainage hole 7 can be constructed simultaneously;
S8、当砌块坝体施工到坝顶预定高程后,再浇筑坝顶构件;S8, when the block dam body is constructed to the predetermined height of the dam crest, then pour the dam crest components;
S9、溢流坝段上的中墩10、边墩11采用钢筋混凝土结构浇筑在溢流堰上。S9. The middle pier 10 and the side pier 11 on the overflow dam section are poured on the overflow weir with a reinforced concrete structure.
进一步地,可以设置所述坝顶构件包括坝顶混凝土保护层、防浪墙;坝顶浇筑30cm厚钢筋混凝土板作为坝顶混凝土保护层。Further, the crest member may be set to include a crest concrete protection layer and a wave wall; a 30cm thick reinforced concrete slab is poured on the dam crest as the dam crest concrete protection layer.
一种拆卸式重力坝的拆除方法,首先凿开坝顶浇筑的混凝土和下游混凝土面板4,露出砌块标准件20、1/2砌块标准件21,拆卸掉砌块标准件20或1/2砌块标准件21四周的角铁207和锚索208,即可用起重机将砌块标准件20、1/2砌块标准件21吊走实现拆除。A dismantling method of a dismountable gravity dam, firstly, the concrete poured on the top of the dam and the downstream concrete face plate 4 are cut open to expose the block standard part 20 and 1/2 block standard part 21, and the block standard part 20 or 1/2 2 The angle iron 207 and the anchor cable 208 around the block standard part 21 can be hoisted away by a crane to remove the block standard part 20 and 1/2 block standard part 21.
进一步地,可以设置拆除时从下游往上游逐排逐层拆除。Further, it can be set to dismantle row by row and layer by row from downstream to upstream during dismantling.
上面结合附图对本发明的具体实施方式作了详细说明,但是本发明并不限于上述实施方式,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化。The specific implementation of the present invention has been described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above-mentioned implementation, within the knowledge of those of ordinary skill in the art, it can also be made without departing from the gist of the present invention. Variations.
Claims (18)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810071121.3A CN108396711B (en) | 2018-01-25 | 2018-01-25 | Detachable gravity dam and construction and dismantling method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810071121.3A CN108396711B (en) | 2018-01-25 | 2018-01-25 | Detachable gravity dam and construction and dismantling method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108396711A true CN108396711A (en) | 2018-08-14 |
| CN108396711B CN108396711B (en) | 2020-04-07 |
Family
ID=63094210
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810071121.3A Active CN108396711B (en) | 2018-01-25 | 2018-01-25 | Detachable gravity dam and construction and dismantling method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108396711B (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110004885A (en) * | 2019-04-04 | 2019-07-12 | 昆明理工大学 | A full dam section overflow, anchor cable fixed modular combined retaining dam |
| CN110468795A (en) * | 2019-08-02 | 2019-11-19 | 昆明理工大学 | A prefabricated concrete gravity dam based on a superimposed structure and its construction method |
| CN110939107A (en) * | 2019-12-27 | 2020-03-31 | 中水北方勘测设计研究有限责任公司 | Prefabricated reinforced concrete doorway unit for roller compacted concrete dam and construction method of doorway |
| CN111139789A (en) * | 2020-01-13 | 2020-05-12 | 昆明理工大学 | An assembled tailings dam and its construction method |
| CN114892607A (en) * | 2022-05-31 | 2022-08-12 | 昆明理工大学 | Assembled dam core wall structure and construction method thereof |
| CN116122229A (en) * | 2023-04-03 | 2023-05-16 | 昆明理工大学 | Device and protection method for preventing earth and rockfill dam from exceeding standard and flooding |
| CN116770767A (en) * | 2023-07-06 | 2023-09-19 | 长江三峡集团重庆能源投资有限公司 | Prefabricated concrete water retaining building based on assembly and construction method |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20130006222A (en) * | 2011-07-08 | 2013-01-16 | 권오준 | Method for constructing stone block of housing |
| CN204626333U (en) * | 2015-05-20 | 2015-09-09 | 李清华 | A kind of Novel portable structure of flood bank |
| CN205857134U (en) * | 2016-06-24 | 2017-01-04 | 中国电建集团华东勘测设计研究院有限公司 | A kind of economical mud-rock flow blocking dam structure |
-
2018
- 2018-01-25 CN CN201810071121.3A patent/CN108396711B/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20130006222A (en) * | 2011-07-08 | 2013-01-16 | 권오준 | Method for constructing stone block of housing |
| CN204626333U (en) * | 2015-05-20 | 2015-09-09 | 李清华 | A kind of Novel portable structure of flood bank |
| CN205857134U (en) * | 2016-06-24 | 2017-01-04 | 中国电建集团华东勘测设计研究院有限公司 | A kind of economical mud-rock flow blocking dam structure |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110004885A (en) * | 2019-04-04 | 2019-07-12 | 昆明理工大学 | A full dam section overflow, anchor cable fixed modular combined retaining dam |
| CN110004885B (en) * | 2019-04-04 | 2023-10-27 | 昆明理工大学 | A modular combined retaining dam with overflow in the entire dam section and fixed anchor cables |
| CN110468795A (en) * | 2019-08-02 | 2019-11-19 | 昆明理工大学 | A prefabricated concrete gravity dam based on a superimposed structure and its construction method |
| CN110939107A (en) * | 2019-12-27 | 2020-03-31 | 中水北方勘测设计研究有限责任公司 | Prefabricated reinforced concrete doorway unit for roller compacted concrete dam and construction method of doorway |
| CN111139789A (en) * | 2020-01-13 | 2020-05-12 | 昆明理工大学 | An assembled tailings dam and its construction method |
| CN114892607A (en) * | 2022-05-31 | 2022-08-12 | 昆明理工大学 | Assembled dam core wall structure and construction method thereof |
| CN114892607B (en) * | 2022-05-31 | 2023-01-31 | 昆明理工大学 | A prefabricated dam core wall structure and its construction method |
| CN116122229A (en) * | 2023-04-03 | 2023-05-16 | 昆明理工大学 | Device and protection method for preventing earth and rockfill dam from exceeding standard and flooding |
| CN116770767A (en) * | 2023-07-06 | 2023-09-19 | 长江三峡集团重庆能源投资有限公司 | Prefabricated concrete water retaining building based on assembly and construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108396711B (en) | 2020-04-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108396711A (en) | A kind of detachable gravity dam and its construction, method for dismounting | |
| CN104831617B (en) | Steel-Ultra High Performance Concrete Composite Beam Based on Ribbed Deck and Its Construction Method | |
| CN106013172B (en) | Double-row pile combines Deep Foundation Pit Support for Soft Soil structure and construction method with diagonal brace | |
| CN103334422B (en) | Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof | |
| CN206189455U (en) | a corridor | |
| CN102839601A (en) | Consolidated structure of steel piers and caps of portal-type rigid frame overpass and its construction method | |
| CN105201012B (en) | Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench | |
| CN110485430A (en) | A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall | |
| CN105134009B (en) | Sill coping concrete structure of frame structure infilled wall and construction method | |
| CN206545215U (en) | A kind of precast spliced sinking type garage parking | |
| CN204590038U (en) | A kind of permanent foundation pit supporting construction | |
| CN205297580U (en) | Soft rock bate distension control structure | |
| CN104652417A (en) | High-performance concrete corrugated sheet pile, forming die and production method for high-performance concrete corrugated sheet pile | |
| CN108643133B (en) | Detachable arch dam and construction and dismantling method thereof | |
| CN202787055U (en) | Pier fixed connection structure of steel structure overhead bridge | |
| CN108775084A (en) | Steel-concrete combines precast beam and prefabricated post connection structure and construction method | |
| CN103924581A (en) | Underground continuous wall with prefabricated concrete-filled steel tube composite structure and method for constructing underground continuous wall | |
| CN110485431A (en) | A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall | |
| CN208023601U (en) | A kind of prefabricated pile foundation support table side form of mutual buckle type | |
| CN204753627U (en) | Prefabricated comprehensive piping lane | |
| CN110468795B (en) | Fabricated concrete gravity dam based on laminated structure and construction method thereof | |
| CN210152316U (en) | A prefabricated reinforcement device for reinforced concrete beams | |
| CN104074131B (en) | A kind of assembled inverted T-shaped slab bridge structure and construction method thereof | |
| CN209227556U (en) | Prefabricated quick-install lattice beam system | |
| CN207362867U (en) | A kind of soft layer construction elevator processing infrastructure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |