CN108316647A - Multifunction scaffold and its application method for subway side wall - Google Patents

Multifunction scaffold and its application method for subway side wall Download PDF

Info

Publication number
CN108316647A
CN108316647A CN201810141982.4A CN201810141982A CN108316647A CN 108316647 A CN108316647 A CN 108316647A CN 201810141982 A CN201810141982 A CN 201810141982A CN 108316647 A CN108316647 A CN 108316647A
Authority
CN
China
Prior art keywords
climbing frame
platform
column
support bar
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810141982.4A
Other languages
Chinese (zh)
Inventor
杨晓军
邵东雪
徐芳
李维华
张志青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201810141982.4A priority Critical patent/CN108316647A/en
Publication of CN108316647A publication Critical patent/CN108316647A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/14Bracing or strutting arrangements for formwalls; Devices for aligning forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The present invention provides a kind of Multifunction scaffold and application method for subway side wall, which includes:Climbing frame template, the first climbing frame component, the second climbing frame component and verticality regulating part;First climbing frame component includes the first platform, the second platform, first support bar and telescopic first climbing frame column;Climbing frame template is mounted on perpendicular to ground on the first climbing frame column by verticality regulating part;First platform and the second platform are respectively perpendicular to wall and pour the both ends that face is mounted on the first climbing frame column, and first support bar is used for the height adjusting support angle according to the first climbing frame column;Second climbing frame component includes third platform, second support bar and telescopic second climbing frame column;Second climbing frame uprights vertical is in ground and for passing through distal end apart from ground and the first stage+module, third platform pours the near end that face is mounted on the second climbing frame column perpendicular to wall, and second support bar is used for the height adjusting support angle according to the second climbing frame column.

Description

Multifunction scaffold and its application method for subway side wall
Technical field
The present invention relates to subway engineering fields, more particularly to a kind of Multifunction scaffold for subway side wall and are somebody's turn to do The application method of Multifunction scaffold.
Background technology
Currently, with the high speed development of China's subway engineering, subway station and open cut section height of side wall are higher and higher, Conventional template, which pours, reinforces time-consuming and laborious, and safe mass cannot be guaranteed, and is badly in need of new pouring and reinforcing side using a kind of Formula improves construction safety, quality and ensures construction efficiency.
Invention content
To solve the above problems, the present invention provides a kind of Multifunction scaffold and its application method for subway side wall, it can It poured with realization, reinforce observation, repairing maintenance in the multi-platform construction of one, not only had reasonable for structure, swift to operate, steady It the advantages that qualitative good, also greatly increases working security, improve construction quality and efficiency, it can be extensive in construction Using.
Multifunction scaffold provided by the present invention for subway side wall includes:Climbing frame template, the first climbing frame component, second Climbing frame component and verticality regulating part;The first climbing frame component include the first platform, the second platform, first support bar with And telescopic first climbing frame column;The climbing frame template is mounted on by the verticality regulating part perpendicular to ground described On first climbing frame column, the verticality regulating part is used to adjust the vertical of the first climbing frame column and the climbing frame template Degree;First platform and the second platform are respectively perpendicular to the wall and pour face is mounted on the first climbing frame column two End, and first stage+module is in the near end of the first climbing frame column, the first climbing frame column and the first platform it Between the first support bar is installed, the first support bar is used for the height adjusting support according to the first climbing frame column Angle;The second climbing frame component includes third platform, second support bar and telescopic second climbing frame column;Described Two climbing frame uprights verticals are in ground and for passing through distal end apart from ground and first stage+module, the third platform The near end that face is mounted on the second climbing frame column, the second climbing frame column and described the are poured perpendicular to the wall The second support bar is installed, the second support bar is used for the height according to the second climbing frame column between one platform Adjust support angle.
Preferably, one end of the first support bar and the first climbing frame column are hinged, the other end and described first flat Platform is slidably connected, for the support angle by first support bar described in the slidable adjustment on first platform;Described second One end of supporting rod is hinged with the second climbing frame column, and the other end is slidably connected with first platform, for by institute State the support angle of second support bar described in slidable adjustment on the first platform.
Preferably, the verticality regulating part is adjusting nut.
Preferably, the second climbing frame component further includes protection cable wire, and the protection cable wire for being in when wall pours Tensioned state is connected between the second climbing frame column and first platform.
Preferably, the wall described in the distance of first platform, the second platform and third platform pours the distal end in face It is separately installed with guardrail perpendicular to ground.
Preferably, between the guardrail of second platform and the climbing frame template and the guardrail of the third platform It pours between face to pour face perpendicular to the wall and be separately installed with the wall and is used to support the guardrail of the guardrail and supports Bar.
Preferably, the first climbing frame column, the verticality regulating part, the first support bar, second climbing frame Column, the second support bar are multiple, and every 1 first climbing frame column passes through corresponding verticality regulating part and the climbing frame Template is installed and passes through corresponding first support bar and the first stage+module;Every 1 second climbing frame column passes through corresponding second Supporting rod and the first stage+module.
Preferably, verticality fine tuning is both provided in the junction of first platform and every 1 first climbing frame column to tie Structure, it is vertical to adjust first climbing frame for the connection angle by adjusting first platform with the first climbing frame column The verticality of column.
On the other hand, the present invention also provides a kind of application method of Multifunction scaffold provided by the invention, installation first is climbed Frame component, and first segment wall is poured by climbing frame template;After completing the pouring of the first segment wall, move up described First climbing frame component installs the second climbing frame component and first platform, and pours second by the climbing frame template Section wall;After completing the pouring of the second segment wall, the height by adjusting the second climbing frame column moves up described First climbing frame component, and third section wall is poured by the climbing frame template.
It is arranged using modularization provided by the present invention for the Multifunction scaffold of subway side wall, it can be according to subway side wall Height will need pour subway side wall segmentation pour, for example, since ground, it would be desirable to which the subway side wall poured is divided into Three sections, first segment wall, second segment wall and third section wall are poured by installing the segmentation of climbing frame component, in casting process In, pouring construction personnel, which may stand on different platforms, to carry out wall and pours, is monitored to work progress and reinforces sight It examines and maintenance repairing is carried out to the wall poured, climbed using provided by the present invention for the multi-functional of subway side wall Frame may be implemented to integrate the multi-platform construction for pouring, reinforcing observation, repairing maintenance, not only have reasonable for structure, operation Fast, the advantages that stability is good also greatly increases working security, improves construction quality and efficiency, can be in construction It is widely used.
The other feature and advantage of the embodiment of the present invention will be described in detail in subsequent specific embodiment part.
Description of the drawings
Attached drawing is further understood to the embodiment of the present invention for providing, an and part for constitution instruction, under The specific implementation mode in face is used to explain the embodiment of the present invention together, but does not constitute the limitation to the embodiment of the present invention.Attached In figure:
Fig. 1 is the structural schematic diagram of the first climbing frame component in the Multifunction scaffold according to one embodiment of the present invention;
Fig. 2 is the structural schematic diagram of the second climbing frame component in the Multifunction scaffold according to one embodiment of the present invention;
Fig. 3 is multi-functional in step 1) in the application method according to the Multifunction scaffold of one embodiment of the present invention The structural schematic diagram of climbing frame;
Fig. 4 is multi-functional in step 2) in the application method according to the Multifunction scaffold of one embodiment of the present invention The structural schematic diagram of climbing frame;And
Fig. 5 is multi-functional in step 3) in the application method according to the Multifunction scaffold of one embodiment of the present invention The structural schematic diagram of climbing frame.
Reference sign
1 climbing frame template, 2 first climbing frame component
3 second climbing frame component, 4 verticality regulating part
5 first support bar, 6 first platform
7 walls pour 8 first climbing frame column of face
9 second platform, 10 second support bar
11 second climbing frame column, 12 third platform
13 protection 14 guardrails of cable wire
15 guardrail supporting rod, 16 first segment wall
17 second segment wall, 18 third section wall
Specific implementation mode
The specific implementation mode of the embodiment of the present invention is described in detail below in conjunction with attached drawing.It should be understood that this The described specific implementation mode in place is merely to illustrate and explain the present invention embodiment, is not intended to restrict the invention embodiment.
Below in conjunction with the accompanying drawings, technical solution in the embodiment of the present invention is described in detail.
As shown in-Fig. 5, a kind of Multifunction scaffold for subway side wall provided by the invention includes:Climbing frame template 1, One climbing frame component 2, the second climbing frame component 3 and verticality regulating part 4;The first climbing frame component 2 includes the first platform 6, the Two platforms 9, first support bar 5 and telescopic first climbing frame column 8;The climbing frame template 1 is adjusted by the verticality Part 4 is mounted on perpendicular to ground on the first climbing frame column 8, and the verticality regulating part 4 is for adjusting first climbing frame The verticality of column 8 and the climbing frame template 1;First platform, 6 and second platform 9 is respectively perpendicular to the wall and pours Face 7 is mounted on the both ends of the first climbing frame column 8, and first platform 6 is mounted on the close of the first climbing frame column 8 Ground terminal, is equipped with the first support bar 5 between the first climbing frame column 8 and the first platform 6, the first support bar 5 is used In the height adjusting support angle according to the first climbing frame column 8;The second climbing frame component 3 includes third platform 12, the Two supporting rods 10 and telescopic second climbing frame column 11;The second climbing frame column 11 is perpendicular to ground and for passing through Distal end apart from ground is installed with first platform 6, and the third platform 12 pours face 7 perpendicular to the wall and is mounted on The near end of the second climbing frame column 11 is equipped with described between the second climbing frame column 11 and first platform 6 Two supporting rods 10, the second support bar 10 are used for the height adjusting support angle according to the second climbing frame column 11.
Preferably, the first climbing frame column 8, the verticality regulating part 4, the first support bar 5, described second Climbing frame column 11, the second support bar 10 are multiple, and every 1 first climbing frame column 8 passes through corresponding verticality regulating part 4 It installs with the climbing frame template 1 and is installed by corresponding first support bar 5 and the first platform 6;Every 1 second climbing frame column 11 It is installed by corresponding second support bar 10 and the first platform 6.
Since the height of subway side wall is higher, in order to ensure the quality of the safety and construction constructed, usually subway side wall Segmentation pours, for example, since ground, it would be desirable to which the subway side wall poured is divided into three sections, first segment wall respectively to be poured Body 16, second segment wall 17 and third section wall 18.First, as shown in figure 3, installing the first climbing frame component 2 on the ground, And first segment wall 16 is poured by climbing frame template 1.
Preferably, by being embedded in the pre-embedded bolt on ground, the first climbing frame component 2 is fixed on the ground;The climbing frame Template 1 is mounted on perpendicular to ground on the first climbing frame column 8 by the verticality regulating part 4, and climbing frame template 1 is hung down Straight degree determines that is formed pours the verticality for pouring face of wall, therefore is provided with verticality regulating part 4, for adjusting The verticality for stating the first climbing frame column 8 and the climbing frame template 1, ensure that the quality requirement of construction.
According to the technique and scheme of the present invention, according to walling body to be poured along the length in ground direction and perpendicular to ground Highly, the length and height of the climbing frame template 1 are selected, for example, the length of first segment wall 16 to be poured is 10 meters, height Degree is 2 meters, that is, selects the climbing frame template 1 that length is 10 meters and height is 2 meters, the length and height of climbing frame template 1 can bases Actual use situation is selected, and the present invention is not limited thereof.
According to the technique and scheme of the present invention, according to length of the walling body along ground direction to be poured and the height perpendicular to ground The intensity requirement of degree and the first climbing frame component 2 selects the quantity and height of the first climbing frame column 8.Such as it is pouring The length of first segment wall 16 is 10 meters, be highly 2 meters in the case of, it is preferable that the quantity of the first climbing frame column 8 is selected as 8 A, uniformly distributed to arrange, the height of the first climbing frame column 8 is 2.05 meters, ensure that can as required the length needed for pouring construction and Highly, the quantity of the first climbing frame column 8 and elongation height can be selected according to actual use situation, and the present invention is not to it It is defined.
According to the technique and scheme of the present invention, first platform, 6 and second platform 9 is respectively perpendicular to the wall and pours Face 7 is mounted on the both ends of the first climbing frame column 8, and first platform 6 is mounted on the close of the first climbing frame column 8 Ground terminal is equipped with the first support bar 5 between the first climbing frame column 8 and the first platform 6, further enhances first The intensity of climbing frame component 2 ensure that the safety of construction.The first support bar 5 is used for according to the first climbing frame column 8 Height adjusting support angle, if for example, wall height adjustment, the height of the height of climbing frame template 1 and the first climbing frame column 8 Degree adjusts therewith, and the support angle of first support bar 5 is also adjusted therewith, for example, the height of the first climbing frame column 8 increases Height, the angle of first support bar 5 and horizontal plane is with becoming larger, the security requirement for meeting climbing frame.
After installation is complete, pouring construction personnel station carries out pouring first segment wall 16 on the second platform 9, applying in addition Worker person may stand on the first platform 6 and is monitored to work progress, and can be added on platform after the completion of pouring Gu observation and repairing maintenance.
According to the technique and scheme of the present invention, it as shown in figure 4, after completing the pouring of the first segment wall 16, moves up The first climbing frame component 2, the second climbing frame component 3 and first platform 6 are installed, and are poured by the climbing frame template 1 Second segment wall 17.
According to the technique and scheme of the present invention, the second climbing frame component 3 include third platform 12, second support bar 10 with And telescopic second climbing frame column 11;The second climbing frame column 11 is perpendicular to ground and for by apart from the remote of ground End is installed with first platform 6, and the third platform 12 pours face 7 perpendicular to the wall and is mounted on second climbing frame The near end of column 11 is equipped with the second support bar 10 between the second climbing frame column 11 and first platform 6, The intensity for further enhancing the second climbing frame component 3, ensure that the safety of construction.The second support bar 10 is used for basis The height adjusting support angle of the second climbing frame column 11.
According to the technique and scheme of the present invention, according to the first segment wall 16 poured along ground direction length and Perpendicular to the height on ground and the intensity requirement of required second climbing frame component 3, select the quantity of the second climbing frame column 11 with And the height of elongation.Such as in the case where first segment wall 16 is 10 meters, is highly 2 meters, it is preferable that the second climbing frame column 11 quantity is selected as 8, uniformly distributed to arrange, and the height of the second climbing frame column 11 is 1.85 meters, ensure that the length needed for construction And height, the quantity and elongation height of the second climbing frame column 11 can be selected, the present invention is not according to actual use situation It is defined.
After installation is complete, pouring construction personnel station carries out pouring second segment wall 17 on the second platform 9, applying in addition Worker person may stand on the first platform 6 and observation be monitored and reinforced to work progress, can also be right on third platform 12 The first segment wall 16 poured carries out maintenance repairing.
According to the technique and scheme of the present invention, as shown in figure 5, after completing the pouring of the second segment wall 17, pass through The height for adjusting the second climbing frame column 11 moves up the first climbing frame component 2, and pours by the climbing frame template 1 Three sections of walls 18.
According to the first segment wall 16 and second segment wall 17 poured perpendicular to the height on ground, second is selected The height of the elongation of climbing frame column 11.Such as in the case where first segment wall 16 and 17 height of second segment wall are 2 meters, In order to meet the mounting condition of upper layer the first climbing frame component 2, the thickness of the first platform 6 and the thickness of third platform 12 are dispelled Etc. factors, it is preferable that the height of the second climbing frame column 11 is selected as 3.85 meters, ensure that construction needed for height, the second climbing frame The elongation height of column 11 can be selected according to actual use situation, and the present invention is not limited thereof.
The second support bar 10 is used for the height adjusting support angle according to the second climbing frame column 11, in order to protect Demonstrate,prove the support strength requirement of the second climbing frame component 3, the support angle of second support bar 10 with the second climbing frame column 11 height Increase adjust support angle, for example, the height of the second climbing frame column 11 increases, the angle of second support bar 10 and horizontal plane Become larger therewith.
After installation is complete, pouring construction personnel station carries out pouring third section wall 18 on the second platform 9, applying in addition Worker person may stand on the first platform 6 and observation be monitored and reinforced to work progress, can also be right on third platform 12 The first segment wall 16 and second segment wall 17 poured carries out maintenance repairing.
According to the technique and scheme of the present invention, one end of the first support bar 5 and the first climbing frame column 8 are hinged, separately One end is slidably connected with first platform 6, for passing through first support bar 5 described in the slidable adjustment on first platform 6 Support angle;One end of the second support bar 10 and the second climbing frame column 11 are hinged, the other end and described first flat Platform 6 is slidably connected, for the support angle by second support bar 10 described in the slidable adjustment on first platform 6.
Preferably, the verticality regulating part 4 is adjusting nut, and the quantity of verticality adjusting part 4 is vertical with the first climbing frame The quantity of column 8 is consistent, and 4 one end of verticality adjusting part is fixed in the template 1, and bolt arrangement is arranged in the other end, passes through institute It states the first climbing frame column 8 and is fixed by nut, screwed out using screw-in of the nut on bolt and be used for adjusting first climbing frame The verticality of column 8.
Preferably, verticality fine tuning is both provided in the junction of first platform and every 1 first climbing frame column to tie Structure, it is vertical to adjust first climbing frame for the connection angle by adjusting first platform with the first climbing frame column The verticality of column, the verticality fine tuning structure are bolt and nut structure, and the screw rod is fixed with the first climbing frame column 8 Connection is flexibly connected with first platform 6, and the nut is engaged with the screw rod, by rotating nuts so that the screw rod It moves left and right so as to adjust the verticality of the first climbing frame column 8.
Preferably, the second climbing frame component further includes protection cable wire 13, and the protection cable wire 13 in wall for pouring When be connected between the second climbing frame column 11 and first platform 6 in tensioned state, protect the quantity of cable wire 13 can be with It is parallel to the length on ground according to wall and the quantity of the second climbing frame column 11 is configured, such as the length of wall is 10 meters, the quantity that protection cable wire 13 can be arranged is 8, is evenly arranged, and the quantity of protection cable wire 13 can be according to actual use Situation is selected, and the present invention is not limited thereof.
Preferably, the wall described in the distance of first platform 6, the second platform 9 and third platform 12 pours face 7 Distal end be separately installed with guardrail 14 perpendicular to ground.
Preferably, between the guardrail 14 of second platform 9 and the climbing frame template 1 and the third platform 12 Guardrail 14 and the wall pour between face 7 to pour face 7 perpendicular to the wall and be separately installed with and be used to support the guardrail 14 guardrail supporting rod 15, it is preferable that guardrail supporting rod 15 is respectively arranged one in the two ends of guardrail.
On the other hand, the present invention also provides a kind of application method of Multifunction scaffold, step 1) installs the first climbing frame group Part 2, and first segment wall 16 is poured by climbing frame template 1;Step 2), after completing the pouring of the first segment wall 16, The first climbing frame component 2 is moved up, the second climbing frame component 3 and first platform 6 are installed, and passes through the climbing frame template 1 Pour second segment wall 17;Step 3) is climbed after completing the pouring of the second segment wall 17 by adjusting described second The height for erecting column 11 moves up the first climbing frame component 2, and pours third section wall 18 by the climbing frame template 1.
To solve, subway height of side wall is higher, pours and reinforces time-consuming and laborious, and asking of cannot be guaranteed of safe mass Topic chooses mould provided by the present invention for the Multifunction scaffold and application method of subway side wall according to the height of subway side wall The climbing frame of blockization setting and installing climbing frame template will need the subway side wall poured segmentation to pour, will for example, since ground The subway side wall poured is needed to be divided into three sections, first segment wall 16 respectively to be poured, second segment wall 17 and third section Wall 18 installs the first climbing frame component 2, and pours first segment wall 16 by climbing frame template 1;Complete the first segment wall After the pouring of body 16, the first climbing frame component 2 is moved up, the second climbing frame component 3 and first platform 6 are installed, and Second segment wall 17 is poured by the climbing frame template 1;After completing the pouring of the second segment wall 17, pass through adjusting The height of the second climbing frame column 11 moves up the first climbing frame component 2, and pours third section by the climbing frame template 1 Wall 18.Pouring construction personnel station carries out pouring third section wall 18 on the second platform 9, and construction personnel in addition can stand On the first platform 6 observation is monitored and reinforced to work progress, it can also be on third platform 12 to having poured First segment wall 16 and second segment wall 17 carry out maintenance repairing, may be implemented to pour, reinforce observation, repairing maintenance in one The multi-platform construction of body not only has many advantages, such as that reasonable for structure, swift to operate, stability is good, also greatly increases construction safety Property improves construction quality and efficiency, can be widely used in construction.
The optional embodiment of the embodiment of the present invention is described in detail above in association with attached drawing, still, the embodiment of the present invention is simultaneously The detail being not limited in the above embodiment can be to of the invention real in the range of the technology design of the embodiment of the present invention The technical solution for applying example carries out a variety of simple variants, these simple variants belong to the protection domain of the embodiment of the present invention.
It is further to note that specific technical features described in the above specific embodiments, in not lance In the case of shield, it can be combined by any suitable means.In order to avoid unnecessary repetition, the embodiment of the present invention Various combinations of possible ways are no longer separately illustrated.
In addition, arbitrary combination can also be carried out between a variety of different embodiments of the embodiment of the present invention, as long as it is not The thought of the embodiment of the present invention is violated, disclosure of that of the embodiment of the present invention is equally should be considered as.

Claims (9)

1. a kind of Multifunction scaffold for subway side wall, which is characterized in that the climbing frame includes:Climbing frame template (1), the first climbing frame Component (2), the second climbing frame component (3) and verticality regulating part (4);
The first climbing frame component (2) includes the first platform (6), the second platform (9), first support bar (5) and telescopic First climbing frame column (8);The climbing frame template (1) is mounted on described the by the verticality regulating part (4) perpendicular to ground On one climbing frame column (8), the verticality regulating part (4) is for adjusting the first climbing frame column (8) and the climbing frame template (1) verticality;
First platform (6) and the second platform (9) are respectively perpendicular to the wall and pour face (7) mounted on first climbing frame The both ends of column (8), and first platform (6) is mounted on the near end of the first climbing frame column (8), first climbing frame The first support bar (5) is installed, the first support bar (5) is used for according between column (8) and the first platform (6) The height adjusting support angle of first climbing frame column (8);
The second climbing frame component (3) includes that third platform (12), second support bar (10) and telescopic second climbing frame are vertical Column (11);The second climbing frame column (11) is perpendicular to ground and for passing through distal end apart from ground and first platform (6) it installs, the third platform (12) pours face (7) mounted on the close of the second climbing frame column (11) perpendicular to the wall Ground terminal, is equipped with the second support bar (10) between the second climbing frame column (11) and first platform (6), and described Two supporting rods (10) are used for the height adjusting support angle according to the second climbing frame column (11).
2. climbing frame according to claim 1, which is characterized in that one end of the first support bar (5) is climbed with described first It is hinged to erect column (8), the other end is slidably connected with first platform (6), for by being slided on first platform (6) Adjust the support angle of the first support bar (5);One end of the second support bar (10) and the second climbing frame column (11) hinged, the other end is slidably connected with first platform (6), for passing through the slidable adjustment on first platform (6) The support angle of the second support bar (10).
3. climbing frame according to claim 1, which is characterized in that the verticality regulating part (4) is adjusting nut.
4. climbing frame according to claim 1, which is characterized in that the second climbing frame component further includes protection cable wire (13), The protection cable wire (13) is used to be connected to the second climbing frame column (11) and described the in tensioned state when wall is poured Between one platform (6).
5. climbing frame according to claim 1, which is characterized in that in first platform (6), the second platform (9) and The distal end that wall described in the distance of three platforms (12) pours face (7) is separately installed with guardrail (14) perpendicular to ground.
6. climbing frame according to claim 5, which is characterized in that climbed with described in the guardrail (14) of second platform (9) Between frame template (1) and the guardrail of the third platform (12) (14) and the wall pour between face (7) perpendicular to described Wall pours face (7) and is separately installed with the guardrail supporting rod (15) for being used to support the guardrail (14).
7. climbing frame according to claim 1, which is characterized in that the first climbing frame column (8), the verticality regulating part (4), the first support bar (5), the second climbing frame column (11), the second support bar (10) are multiple, and every 1 One climbing frame column (8) is installed with the climbing frame template (1) by corresponding verticality regulating part (4) and passes through corresponding first Strut (5) is installed with the first platform (6);Every 1 second climbing frame column (11) is flat by corresponding second support bar (10) and first Platform (6) is installed.
8. climbing frame according to claim 7, which is characterized in that in first platform (6) and every 1 first climbing frame column (8) junction is both provided with verticality fine tuning structure, for vertical with first climbing frame by adjusting first platform (6) The connection angle of column (8) adjusts the verticality of the first climbing frame column (8).
9. the application method of the Multifunction scaffold described in a kind of any one of claim 1-8 claims, which is characterized in that should Method includes:
Step 1) installs the first climbing frame component (2), and pours first segment wall (16) by climbing frame template (1);
Step 2) moves up the first climbing frame component (2), by second after completing the pouring of the first segment wall (16) Climbing frame component (3) is installed with first platform (6), and pours second segment wall (17) by the climbing frame template (1);
Step 3) passes through after completing the pouring of the second segment wall (17) and adjusts the second climbing frame column (11) Height moves up the first climbing frame component (2), and pours third section wall (18) by the climbing frame template (1).
CN201810141982.4A 2018-02-11 2018-02-11 Multifunction scaffold and its application method for subway side wall Withdrawn CN108316647A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810141982.4A CN108316647A (en) 2018-02-11 2018-02-11 Multifunction scaffold and its application method for subway side wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810141982.4A CN108316647A (en) 2018-02-11 2018-02-11 Multifunction scaffold and its application method for subway side wall

Publications (1)

Publication Number Publication Date
CN108316647A true CN108316647A (en) 2018-07-24

Family

ID=62902901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810141982.4A Withdrawn CN108316647A (en) 2018-02-11 2018-02-11 Multifunction scaffold and its application method for subway side wall

Country Status (1)

Country Link
CN (1) CN108316647A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915250A (en) * 2018-09-29 2018-11-30 贵州卓良模板有限公司 A kind of cantilever form
CN112112422A (en) * 2020-09-18 2020-12-22 中铁济南工程建设监理有限公司 Template support assembly for subway station side wall and supervision method thereof
CN113062578A (en) * 2021-03-25 2021-07-02 中交二航局成都城市建设工程有限公司 Liftable mobile operation platform
CN116397696A (en) * 2023-05-05 2023-07-07 中铁四局集团有限公司 A construction method for high-clearance arc-shaped side walls under cover plates

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0350525B1 (en) * 1988-07-14 1991-12-27 Gleitbau-Gesellschaft mit beschränkter Haftung Method for producing building-walls and a shuttering system
CN2660028Y (en) * 2003-09-18 2004-12-01 山东省路桥集团有限公司 Hydraulic self-lifting climbing mould
CN102518148A (en) * 2011-12-29 2012-06-27 中铁上海工程局有限公司 Architecture related to triangular bracing structure of underground open cut station and construction method thereof
CN203452375U (en) * 2013-08-09 2014-02-26 中建四局第六建筑工程有限公司 Hydraulic self-jacking oblique creeping formwork
CN204876547U (en) * 2015-06-26 2015-12-16 中国核工业华兴建设有限公司 Big template system of APC shell structure
CN204983635U (en) * 2015-07-30 2016-01-20 中国核工业第二二建设有限公司 AP1000 nuclear island barrier shield template adjusting device
CN205063332U (en) * 2015-09-30 2016-03-02 中建六局建设发展有限公司 A creeping formwork structure of climbing for wall body variable cross section department
CN206736864U (en) * 2017-03-21 2017-12-12 中国葛洲坝集团三峡建设工程有限公司 Hydraulic self-lifting cantilever heavy type arch dam shuttering work platform
CN207268080U (en) * 2017-10-16 2018-04-24 中铁十二局集团有限公司 A kind of Multifunction scaffold template for subway side wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0350525B1 (en) * 1988-07-14 1991-12-27 Gleitbau-Gesellschaft mit beschränkter Haftung Method for producing building-walls and a shuttering system
CN2660028Y (en) * 2003-09-18 2004-12-01 山东省路桥集团有限公司 Hydraulic self-lifting climbing mould
CN102518148A (en) * 2011-12-29 2012-06-27 中铁上海工程局有限公司 Architecture related to triangular bracing structure of underground open cut station and construction method thereof
CN203452375U (en) * 2013-08-09 2014-02-26 中建四局第六建筑工程有限公司 Hydraulic self-jacking oblique creeping formwork
CN204876547U (en) * 2015-06-26 2015-12-16 中国核工业华兴建设有限公司 Big template system of APC shell structure
CN204983635U (en) * 2015-07-30 2016-01-20 中国核工业第二二建设有限公司 AP1000 nuclear island barrier shield template adjusting device
CN205063332U (en) * 2015-09-30 2016-03-02 中建六局建设发展有限公司 A creeping formwork structure of climbing for wall body variable cross section department
CN206736864U (en) * 2017-03-21 2017-12-12 中国葛洲坝集团三峡建设工程有限公司 Hydraulic self-lifting cantilever heavy type arch dam shuttering work platform
CN207268080U (en) * 2017-10-16 2018-04-24 中铁十二局集团有限公司 A kind of Multifunction scaffold template for subway side wall

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915250A (en) * 2018-09-29 2018-11-30 贵州卓良模板有限公司 A kind of cantilever form
CN112112422A (en) * 2020-09-18 2020-12-22 中铁济南工程建设监理有限公司 Template support assembly for subway station side wall and supervision method thereof
CN113062578A (en) * 2021-03-25 2021-07-02 中交二航局成都城市建设工程有限公司 Liftable mobile operation platform
CN113062578B (en) * 2021-03-25 2022-11-15 中交二航局成都城市建设工程有限公司 Liftable mobile operation platform
CN116397696A (en) * 2023-05-05 2023-07-07 中铁四局集团有限公司 A construction method for high-clearance arc-shaped side walls under cover plates

Similar Documents

Publication Publication Date Title
CN108316647A (en) Multifunction scaffold and its application method for subway side wall
CN104032678B (en) H type king-post internal force adjustable false stull structure and construction method thereof
CN209482679U (en) Tub brace type integral steel platform suitable for sloping core construction
CN106284988A (en) Oblique circular cylinder template and construction method thereof
CN106087744A (en) Cable-stayed bridge beams of concrete cable guide pipe supporting and positioning device and method
CN102061668A (en) Vertical swiveling construction method of dual-steel-arch tower
CN102337782A (en) Lift system for constructing truss platform on top of tall and large space and construction method for lift system
CN105804110B (en) A kind of construction method and mounting bracket of railway contact line foundation bolt
CN208899516U (en) Insert-type steel pipe concrete column installing mechanism
CN206888904U (en) A kind of cat ladder for bridge pier column construction
CN103434933B (en) Large member hoisting in-position device and in-position method
CN103628692B (en) A kind of floor beam mounting bracket and use it to install the method for floor beam
CN206289963U (en) For the climbing form system of section Core tube construction
CN108868096A (en) It is fixed on the outer protection tripod of pin-connected panel safety and its application method of precast facade
CN109267493A (en) Construction method for installing steel cover beam across river course
CN206308990U (en) A kind of moveable overhanging type operating platform and construction system
CN110318337A (en) A kind of bridge side guardrail formwork structure and its construction method
CN109763644B (en) Large-diameter cylinder sliding form system and construction method thereof
CN202925471U (en) Hydraulic formwork system for high pier construction
CN211569905U (en) Net rack short column embedded part hoisting device
CN212428008U (en) Lower supporting type overhanging scaffold construction device
CN107190974B (en) Cable tower combined type inner sliding die construction method and inner platform frame used by same
CN209011132U (en) A kind of fixed foundation pit berm structure of assembled two point
CN218621822U (en) Stores pylon assembled operation platform
CN112681732A (en) Supporting system of assembled composite membrane shell beam and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180724