A kind of novel road bridge attachment strap structure and its construction method Download PDFInfo
- Publication number
- CN108316128B CN108316128B CN201810016922.XA CN201810016922A CN108316128B CN 108316128 B CN108316128 B CN 108316128B CN 201810016922 A CN201810016922 A CN 201810016922A CN 108316128 B CN108316128 B CN 108316128B
- Authority
- CN
- China
- Prior art keywords
- attachment strap
- steel
- king
- post
- abutment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 16
- 238000004873 anchoring Methods 0.000 claims abstract description 4
- 238000007596 consolidation process Methods 0.000 claims abstract description 4
- 229910000831 Steel Inorganic materials 0.000 claims description 54
- 239000010959 steel Substances 0.000 claims description 54
- 239000004567 concrete Substances 0.000 claims description 21
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 19
- 239000000463 material Substances 0.000 claims description 14
- 239000002689 soil Substances 0.000 claims description 10
- 238000005266 casting Methods 0.000 claims description 9
- 210000003205 muscle Anatomy 0.000 claims description 8
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 6
- 239000010426 asphalt Substances 0.000 claims description 6
- 239000002131 composite material Substances 0.000 claims description 6
- 239000004033 plastic Substances 0.000 claims description 6
- 229920003023 plastic Polymers 0.000 claims description 6
- 239000003365 glass fiber Substances 0.000 claims description 5
- 238000009434 installation Methods 0.000 claims description 5
- 239000011248 coating agent Substances 0.000 claims description 4
- 238000000576 coating method Methods 0.000 claims description 4
- 239000003973 paint Substances 0.000 claims description 4
- 229920002748 Basalt fiber Polymers 0.000 claims description 3
- 229920000049 Carbon (fiber) Polymers 0.000 claims description 3
- 229910001141 Ductile iron Inorganic materials 0.000 claims description 3
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 claims description 3
- 229910052782 aluminium Inorganic materials 0.000 claims description 3
- 229920006231 aramid fiber Polymers 0.000 claims description 3
- 238000009412 basement excavation Methods 0.000 claims description 3
- 239000004917 carbon fiber Substances 0.000 claims description 3
- 239000004568 cement Substances 0.000 claims description 3
- 238000002425 crystallisation Methods 0.000 claims description 3
- 230000008025 crystallization Effects 0.000 claims description 3
- 229920001971 elastomer Polymers 0.000 claims description 3
- 239000000806 elastomer Substances 0.000 claims description 3
- 239000000835 fiber Substances 0.000 claims description 3
- 229910052742 iron Inorganic materials 0.000 claims description 3
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 claims description 3
- 230000035515 penetration Effects 0.000 claims description 3
- 239000011414 polymer cement Substances 0.000 claims description 3
- 229920002635 polyurethane Polymers 0.000 claims description 3
- 239000004814 polyurethane Substances 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 238000010079 rubber tapping Methods 0.000 claims description 3
- 239000000758 substrate Substances 0.000 claims description 3
- 238000004078 waterproofing Methods 0.000 claims description 3
- 239000004411 aluminium Substances 0.000 claims 1
- 230000003044 adaptive effect Effects 0.000 abstract description 2
- 238000005516 engineering process Methods 0.000 abstract 1
- 238000004062 sedimentation Methods 0.000 description 5
- 238000000034 method Methods 0.000 description 3
- 238000005260 corrosion Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000945 filler Substances 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 206010039203 Road traffic accident Diseases 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 230000032683 aging Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000002512 chemotherapy Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000003912 environmental pollution Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000035772 mutation Effects 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 238000009958 sewing Methods 0.000 description 1
- 238000004162 soil erosion Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 230000035882 stress Effects 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 238000005406 washing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Abstract
The invention belongs to the construction of bridge, mounting technology field, specifically a kind of novel road bridge attachment strap structure and its construction method.Hazard to bridge's pier device is disclosed fundamentally to solve the problems, such as bumping at bridge-head, including king-post, attachment strap, connecting strand and guarded drainage facility;The king-post is arranged in abutment two sides, and it is connected with abutment consolidation, described connecting strand one end is connect by anchoring with king-post, the other end is bolted with attachment strap two sides, described attachment strap one end rides upon on abutment and is connected with beam body, the other end two sides of attachment strap are connect with connecting strand, and the guarded drainage facility is arranged below attachment strap.The adaptability to foundation settlement deformation is improved to realize the absolute altitude adjustability of attachment strap by changing connecting strand and the longitudinally connected position of attachment strap.The invention has whole service life long, highly-safe, the small, height difference of deformation is adaptive adjustable and the advantages of being easy to construct and safeguard.
Description
Technical field
The invention belongs to bridge construction, the technical field of assembly, specifically a kind of novel road bridge attachment strap structure and its construction
Method.
Background technique
With flourishing for high-grade highway construction, safety during highway is used and service, comfort and quick
Property be to evaluation road quality important indicator.However, in southern soft soil areas and Midwest Canal in Loess Area, bumping at bridge-head
Phenomenon is a relatively common phenomenon.
Bumping at bridge-head will cause interior driver and passenger's body and jolt discomfort, seriously affected vehicle pass-through safety,
Comfort.Simultaneously as the unexpected speedup of vehicle end of the bridge or deceleration, will increase traffic risk and cause traffic accident, in break off a friendship
It is logical, threat is brought to people's life security, generates undesirable social influence.Meanwhile the additional dynamic load pair that bumping at bridge-head generates
Bridge top, substructure have an adverse effect, according to statistics annual nearly 30% bridge influence due to jumping vehicle and must not be without
Maintenance and repairing, thus have brought tremendous economic losses.Moreover, in a sense, the speedup of vehicle and deceleration also increase
Extra bus energy consumption and exhaust emissions increase risk of environmental pollution, need enough attention particularly with Urban Bridge.Bumping at bridge-head
Producing reason be it is various, in theory, bridge structures using pile foundation or the Extended chemotherapy of basement process,
Posterior settlement amount is small, and roadbed is directly filled by the soil body, after platform filler can road operation after be self-possessed and wheel load
Under effect, larger sedimentation is generated, the difference of sedimentation forms the height difference between bridge and embankment.And for construction angle, In
In abutment back embankment construction, since the duration factor of construction influences, there is no static balance times after roadbed filling is complete, carry out at once
Pavement construction;The filler of this between outer land behind leans on the general compacting machinary in close-table wall position in irregular shape because road roller working face is small
It is difficult operation, and small-sized ramming machine is used to tamp, standard is not achieved in compactness.After being open to traffic, these factors all will affect joining place
The sedimentation of this part banketed, causes the height difference of abutment and embankment.
Problem of bumping at bridge-head, most common treating method in engineering are generated in order to solve the differential settlement of bridge and road
It is that attachment strap is set after abutment.Attachment strap is shelved between cantilever beam slab end or abutment and embankment filled soil, with the sedimentation banketed
Tail end can sink, and realize the slow transition of step height difference of platform dike joining place mutation, effectively slow down vehicle in end of the bridge
Jump vehicle phenomenon.However, there are service lifes not to grow for currently used attachment strap, the problems such as serious end of the bridge is not applicable is settled, mainly
Showing attachment strap and abutment joining place, there are seams, and year leads to material to the water proof material of seam crossing setting long afterwards in use
Aging, contracting rise and generate crack, and rainy day rainwater is easy to seep under seam crossing, so that the strength and stability of the soil body reduces, cause
Soil erosion is generated under attachment strap and is come to nothing, and attachment strap stress is destroyed, and after sedimentation of banketing attachment strap can also generated along road direction
Straight skidding.In addition, the attachment strap that Practical Project uses be eventually finite length (3m <L< 12m), attachment strap end subgrade settlement difference
In plate junction often occurs on road-so-called " secondary jump vehicle " phenomenon.It can be seen that this engineering circles problem of bumping at bridge-head does not obtain
It solves very well, there is an urgent need to invent a kind of hazard to bridge's pier device for overcoming prior art defect fundamentally to solve bumping at bridge-head
The problem of.
Summary of the invention
The present invention fundamentally solves bumping at bridge-head to solve the problems, such as hazard to bridge's pier device, provides a kind of Novel road
Bridge attachment strap structure and its construction method.
The present invention takes following technical scheme: a kind of novel road bridge attachment strap structure, including king-post, attachment strap, connecting strand and anti-
Pumping equipment;The king-post is arranged in abutment two sides, and is connected with abutment consolidation, and described connecting strand one end passes through anchoring and king-post
Connection, the other end is fixedly connected with attachment strap two sides, and described attachment strap one end rides upon on abutment and is connected with beam body, attachment strap it is another
End two sides are fixedly connected with connecting strand, and the guarded drainage facility is arranged below attachment strap.
The two sides of the attachment strap are edge-on U-steels, and the longitudinal side of U-steel and above and below are equipped with aperture, laterally
The pre-buried internal thread steel pipe of position of opening, tapping is equipped with transverse bar above and below the U-steel edge of a wing, and transverse bar forms reinforced steel bar ring, steel
It is laid with vertical muscle below muscle ring and forms steel mesh, casting concrete.
The guarded drainage facility includes foundation pit, water storage tank and drainpipe, and foundation pit is arranged below attachment strap, and foundation pit lowest part is set
It is equipped with water storage tank, is provided with drainpipe on water storage tank.
The waterproof material that the foundation pit and ponding rooved face use is elastomer modified asphalt waterproof roll, asphalt felt or glass
Any one in fine felt or polymer cement waterproof paint or polyurethane felt or cement based penetration crystallization type water proofing paint;Draining
Pipe is any one in coating steel pipe or aluminum plastic composite pipe or plastic tube or composite material tube or nodular cast iron pipe.
The connecting strand is that carbon fiber, high tensile steel wire, basalt fibre, PE fiber, aramid fiber, glass fibre are any one
Kind material is made, and cord hole is arranged in rope lower end, is bolted by cord hole and the steel pipe hole of attachment strap two sides.
The king-post is H-type or herringbone or A type or only column type is trapezoidal or any one inverted Y-shaped, the material of king-post
For armored concrete or steel or one of reinforcing bar-concrete or FRP- concrete.
A kind of construction method of novel road bridge attachment strap structure, includes the following steps,
1) the requirement arrangement that is designed according to king-post in abutment two sides, assembling reinforcement, the pre-buried dragline anchorage in king-post top, installation
Tower column formwork, casting concrete;
2) according to bridge location, the length of attachment strap, road width center line determines the position of foundation pit, excavation pit and water storage tank, to base
The substrate soil in hole is handled, and is pressed using weight closely knit, waterproof material is laid in foundation pit and ponding rooved face, in water storage tank
Drainpipe is arranged in end;
3) prefabricated band hole slot fashioned iron in factory, lower opening wears transverse steel and forms reinforced steel bar ring on U-steel, and longitudinal bottom is worn
If vertical muscle, disposed thread pipe, installation template, casting concrete are welded in the lateral hole site of U-steel;
4) after concrete reaches intensity, then attachment strap lifting is placed in corresponding position, by connecting strand one by form removal
End is anchored on king-post, and connecting strand band cord hole one end is aligned with U-steel sidewise hole, and it is pre-buried that bolt is passed through cord hole precession
Disposed thread pipe, realization connect with attachment strap.
Compared with prior art, the beneficial effects of the present invention are: setting one end of attachment strap when lap slab of bridge is installed in setting
In abutment, the other end is connected by drag-line with king-post, by changing cord hole and the link position of attachment strap along longitudinal direction below rope, thus
The absolute altitude of adjustment attachment strap ensure that bridge is connect with road surface by attachment strap to adapt to attachment strap caused by settlement of foundation-embankment height difference
The smooth transition of position avoids the jump vehicle of abutment.Meanwhile the guarded drainage processing after abutment parados and under attachment strap, make attachment strap-
The rainwater that abutment, attachment strap-road surface connecting sewing are penetrated into converges water storage tank, is then exhausted by drainpipe, without washing away attachment strap
Lower section water and soil causes the loss of water and soil, solves the problems, such as that service life existing for previous attachment strap is not grown.Therefore, the present invention has
Have that whole service life is long, it is highly-safe, deformation is small, height difference is adaptive adjustable and the advantages of being easy to construct and safeguard.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention;
Fig. 2 is U-steel part connection structure diagram;
1- king-post in figure, 2- attachment strap, 3- connecting strand, 4- guarded drainage facility, 5- abutment, 6- steel pipe hole, 7- bolt, 8- beam
Body, 9- U-steel, 10- transverse bar, 11- indulge muscle, 41- foundation pit, 42- water storage tank, 43- drainpipe.
Specific embodiment
As shown in Figure 1, 2, a kind of novel road bridge attachment strap structure comprising king-post 1, attachment strap 2, connecting strand 3, guarded drainage facility
4;The king-post is arranged in 5 two sides of abutment, and is connected with abutment consolidation, and described cable wire one end is connect by anchoring with king-post, and one
End is connect with the default screw-thread steel pore 6 of attachment strap two sides by bolt 7 by cord hole, and described attachment strap one end rides upon on abutment,
And be connected with beam body 8, the other end two sides of attachment strap are connected by screw bolts with cable wire 3 by reserving hole 6, and cable wire upper end passes through anchor
Gu being connected with king-post.The guarded drainage facility 4 is arranged below attachment strap.
Further, the two sides of the attachment strap are equipped with edge-on U-steel 9, and U-steel longitudinal side and above and below are all provided with
There is aperture, in the pre-buried steel pipe 6 for including screw thread in lateral duct position, tapping is equipped with transverse bar 10 above and below the U-steel edge of a wing,
Reinforced steel bar ring is formed, vertical muscle 11 is laid with below reinforced steel bar ring and forms steel mesh, casting concrete.U-steel, steel mesh, concrete are solid
Chemical conversion type overlaps compoboard.
Further, the guarded drainage facility is made of foundation pit 41, water storage tank 42, drainpipe 43, the foundation pit and ponding
The waterproof material that rooved face uses is elastomer modified asphalt waterproof roll, and asphalt felt, glass fiber felt, polymer cement waterproof apply
Expect, polyurethane felt, any one in cement based penetration crystallization type water proofing paint;Drainpipe is coating steel pipe, aluminum plastic composite pipe,
Plastic tube, composite material tube, any one in nodular cast iron pipe.
Further, the drag-line is carbon fiber, high tensile steel wire, basalt fibre, PE fiber, aramid fiber, glass fibers
It ties up any one material to be made, cord hole is arranged in rope lower end.
Further, the king-post shape is H-type, herringbone, A type, only column type, trapezoidal, any one inverted Y-shaped, material
For armored concrete or steel or one of reinforcing bar-concrete or FRP- concrete.
Construction method of the invention are as follows:
1) the requirement arrangement that is designed according to king-post in abutment two sides, assembling reinforcement, the pre-buried dragline anchorage in king-post top, installation
Tower column formwork, casting concrete.
2) according to bridge location, the length of attachment strap, road width center line determines the position of foundation pit, excavation pit, water storage tank.To substrate
Soil is handled, and is pressed using weight closely knit, is laid with waterproof material in foundation pit and ponding rooved face, is arranged in water storage tank end
Drainpipe.
3) prefabricated band hole slot fashioned iron in factory, lower opening wears transverse steel and forms reinforced steel bar ring on U-steel, and longitudinal bottom is worn
If vertical muscle, disposed thread pipe, installation template, casting concrete are welded in the lateral hole site of U-steel.
4) after concrete reaches intensity, then attachment strap lifting is placed in corresponding position by form removal.By Suo Yiduan anchor
Gu on king-post, and drag-line band cord hole one end is aligned with U-steel sidewise hole, bolt is screwed into disposed thread pipe by cord hole,
Realization is connect with attachment strap.
In addition, drag-line, U-steel in construction method of the present invention, bolt surface also needs anti-corrosion, corrosion protection processing.
Claims (2)
1. a kind of novel road bridge attachment strap structure, it is characterised in that: set including king-post (1), attachment strap (2), connecting strand (3) and guarded drainage
Apply (4);The king-post (1) is arranged in abutment (5) two sides, and is connected with abutment consolidation, and described connecting strand (3) one end passes through anchoring
Connect with king-post, the other end is fixedly connected with attachment strap (2) two sides, described attachment strap (2) one end ride upon on abutment and with beam body (8)
It is connected, the other end two sides of attachment strap (2) are fixedly connected with connecting strand (3), and the guarded drainage facility (4) is arranged under attachment strap (2)
Side;The two sides of the attachment strap (2) are equipped with edge-on U-steel (9), and the longitudinal side of U-steel (9) and above and below are equipped with out
Hole, lateral position of opening are embedded with the steel pipe (6) for including screw thread, and on U-steel (9) edge of a wing, tapping wears transverse bar (10) up and down,
Transverse bar (10) forms reinforced steel bar ring, is laid with vertical muscle (11) below reinforced steel bar ring and forms steel mesh, casting concrete;Guarded drainage facility (4)
Including foundation pit (41), water storage tank (42) and drainpipe (43), foundation pit (41) setting is below attachment strap (2), foundation pit (41) lowest part
It is provided with water storage tank (42), drainpipe (43) is provided on water storage tank (42);Foundation pit (41) and water storage tank (42)
The waterproof material that surface uses is elastomer modified asphalt waterproof roll, asphalt felt or glass fiber felt or polymer cement waterproof
Any one in coating or polyurethane felt or cement based penetration crystallization type water proofing paint;Drainpipe (43) is coating steel pipe or aluminium
Any one in plastic composite or plastic tube or composite material tube or nodular cast iron pipe;The connecting strand (3) is carbon fiber, height
Strong steel wire, basalt fibre, PE fiber, aramid fiber, glass fibre any one material are made, and cord hole is arranged in rope lower end,
It is connect with the steel pipe hole (6) of attachment strap two sides by bolt (7) by cord hole;King-post (1) is H-type or herringbone or A type or only column
Type is trapezoidal or any one inverted Y-shaped, the material of king-post (1) are that armored concrete or steel or reinforcing bar-concrete or FRP- are mixed
One of solidifying soil.
2. a kind of construction method of novel road bridge attachment strap structure as described in claim 1, it is characterised in that: including following step
Suddenly,
1) the requirement arrangement that is designed according to king-post in abutment two sides, assembling reinforcement, the pre-buried dragline anchorage in king-post top install king-post
Template, casting concrete;
2) according to bridge location, the length of attachment strap, road width center line determines the position of foundation pit, excavation pit and water storage tank, to foundation pit
Substrate soil is handled, and is pressed using weight closely knit, waterproof material is laid in foundation pit and ponding rooved face, in water storage tank end
Drainpipe is set;
3) prefabricated band hole slot fashioned iron in factory, lower opening wears transverse steel and forms reinforced steel bar ring on U-steel, and longitudinal bottom wears vertical
Muscle welds disposed thread pipe, installation template, casting concrete in the lateral hole site of U-steel;
4) after concrete reaches intensity, then attachment strap lifting is placed in corresponding position, by connecting strand one end anchor by form removal
Gu on king-post, and connecting strand band cord hole one end is aligned with U-steel sidewise hole, bolt is screwed into disposed thread by cord hole
Pipe, realization are connect with attachment strap.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810016922.XA CN108316128B (en) | 2018-01-09 | 2018-01-09 | A kind of novel road bridge attachment strap structure and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810016922.XA CN108316128B (en) | 2018-01-09 | 2018-01-09 | A kind of novel road bridge attachment strap structure and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108316128A CN108316128A (en) | 2018-07-24 |
CN108316128B true CN108316128B (en) | 2019-11-19 |
Family
ID=62893980
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810016922.XA Expired - Fee Related CN108316128B (en) | 2018-01-09 | 2018-01-09 | A kind of novel road bridge attachment strap structure and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108316128B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111236043A (en) * | 2020-01-10 | 2020-06-05 | 山西大学 | Novel road bridge attachment strap connection structure of self-adaptation height |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0945162A (en) * | 1995-07-27 | 1997-02-14 | Showa Electric Wire & Cable Co Ltd | Sz wire shield device |
CN2533153Y (en) * | 2002-03-20 | 2003-01-29 | 宁波市城市建设设计院 | Bridge approach capable of preventing car from skipping |
DE202008016445U1 (en) * | 2008-12-15 | 2009-02-26 | Abs Safety Gmbh | Lifting point for personal security |
CN104213499A (en) * | 2013-06-05 | 2014-12-17 | 陈从春 | Novel bridge structure without expansion joints |
CN103741595B (en) * | 2014-01-21 | 2016-01-20 | 浙江省交通规划设计研究院 | A kind of bridgehead structures for administering bumping at bridge-head |
CN105780670A (en) * | 2014-12-23 | 2016-07-20 | 任丘市永基建筑安装工程有限公司 | Overall stabilization technology for steel bridge frame |
CN105862595A (en) * | 2015-01-20 | 2016-08-17 | 任丘市永基建筑安装工程有限公司 | Construction technology of connecting abutment back of steel bridge and road |
CN106012797A (en) * | 2016-07-25 | 2016-10-12 | 同济大学 | All-ground-anchor type single-tower double-span cable-stayed bridge structure and construction method thereof |
CN107460820B (en) * | 2017-09-12 | 2019-01-15 | 山西大学 | A kind of support device of the slow drop of control hazard to bridge's pier |
-
2018
- 2018-01-09 CN CN201810016922.XA patent/CN108316128B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN108316128A (en) | 2018-07-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106522037B (en) | Side broad way based structures based on existing railway roadbed and its construction method | |
CN103711056B (en) | Steel tool-type temporary construction road and construction method thereof | |
WO2016138776A1 (en) | Lowly disposed line structure used in medium-low speed magnetic levitation traffic engineering fill section | |
CN105672450A (en) | Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure | |
CN203716051U (en) | Soft soil foundation based bridgehead structure | |
CN107460820B (en) | A kind of support device of the slow drop of control hazard to bridge's pier | |
CN211973067U (en) | Road and bridge connection transition structure for preventing and treating vehicle bump at bridge head | |
CN106930315B (en) | A kind of moving tower crane foundation structure and construction method | |
CN110820471A (en) | Crossing plate, level crossing structure and laying method | |
CN108316128B (en) | A kind of novel road bridge attachment strap structure and its construction method | |
CN214782979U (en) | Transition section structure of slate roadbed filler road bridge | |
CN204530425U (en) | Prestressed steel truss bridge | |
CN210507176U (en) | Road and bridge crack reinforced structure | |
CN102635104A (en) | Wedge-shaped Geocell cement reinforced soil structure for road-bridge connection and construction method thereof | |
CN100535392C (en) | Bridge type shield construction method for box type bridge | |
CN109537440B (en) | Abutment approach structure | |
CN104313993B (en) | A kind of highway bridge and construction method thereof | |
CN107401142B (en) | Bank revetment heightening construction method is refuted in active service | |
CN205617370U (en) | Arrange anchor head structure in anchored bolt retaining wall concrete panel in | |
CN205000232U (en) | Z shape transition slab structure | |
CN111926649A (en) | Reinforced integrally-built crossing plate for railway special line and line rail fixing device | |
CN113137243A (en) | Reinforcing method for corrosion-resistant interchange roadway of loose coal cylinder | |
CN218911107U (en) | Active control type structural system for controlling bridge head jumping | |
CN203160089U (en) | Anti-settling bridgehead slope structure | |
CN105862595A (en) | Construction technology of connecting abutment back of steel bridge and road |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191119 |