CN108257528A CN201711396447.5A CN201711396447A CN108257528A CN 108257528 A CN108257528 A CN 108257528A CN 201711396447 A CN201711396447 A CN 201711396447A CN 108257528 A CN108257528 A CN 108257528A
Authority
CN
China
Prior art keywords
compartment
subplate
partition
project management
display board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711396447.5A
Other languages
Chinese (zh)
Inventor
董俊华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711396447.5A priority Critical patent/CN108257528A/en
Publication of CN108257528A publication Critical patent/CN108257528A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09FDISPLAYING; ADVERTISING; SIGNS; LABELS OR NAME-PLATES; SEALS
    • G09F15/00Boards, hoardings, pillars, or like structures for notices, placards, posters, or the like
    • G09F15/0006Boards, hoardings, pillars, or like structures for notices, placards, posters, or the like planar structures comprising one or more panels
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09FDISPLAYING; ADVERTISING; SIGNS; LABELS OR NAME-PLATES; SEALS
    • G09F15/00Boards, hoardings, pillars, or like structures for notices, placards, posters, or the like
    • G09F15/0006Boards, hoardings, pillars, or like structures for notices, placards, posters, or the like planar structures comprising one or more panels
    • G09F15/0037Boards, hoardings, pillars, or like structures for notices, placards, posters, or the like planar structures comprising one or more panels supported by a post

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Display Racks (AREA)

Abstract

The invention discloses a kind of project management progress chasing display boards,Including mainboard,Supporting rod and pedestal,The mainboard is mounted on supporting rod,The pedestal is mounted on supporting rod bottom,And base bottom is equipped with universal wheel,The first compartment and the setting of second compartment upper and lower opening,The third compartment and the 4th compartment or so opening setting,The first compartment and second compartment are located on the outside of third compartment and the 4th compartment,The first compartment,Second compartment,Subplate is separately installed in third compartment and the 4th compartment,Lower subplate,Right subplate and left secondary plate,The right subplate is slidably connected to first partition and second partition respectively by the first sliding block,The left secondary plate is slidably connected to second partition and third partition board respectively by the second sliding block,The present invention is logical can more to show project process,Can according to project schedule plan show number be unfolded,Adaptability is wider,Realize the classification displaying of project process,With very high practicability.

Description

A kind of project management progress chasing display board
Technical field
The present invention relates to project management techniques field, specially a kind of project management progress chasing display board.
Background technology
Project management refers in project activity with special knowledge, technical ability, tool and method, enables project limited Under resource qualifications, realize or the demand more than setting and desired process.Project management is to be successfully accomplished one to some The whole monitoring of list of target relevant movable (for example task) and management and control.This includes planning, schedule and safeguards composition item The progress of purpose activity, under limited resource constraint, with the viewpoint, method and theory of system, the whole being related to project Work is effectively managed.The overall process terminated since the investment decision of project to project is planned, is organized, is referred to It waves, coordinate, control and evaluates, to realize the target of project, project management belongs to the major class of project management engineering, project pipe in itself Science and engineering journey includes:Development management (DM), project management (PM), facilities management (FM) and Building Information Model (BIM) and project Management is then divided into three categories again:Information project management, project management, investment project management.
In project management process, needing to project process into line trace, traditional progress chasing displaying harden structure is fixed, Be inconvenient to move, with the development of project, due to display board limited area, display board can not be completely by all progress chasings It shows, manager is needed to change the project plan at any time, and the displaying of display board progress chasing is chaotic, it has not been convenient to which management makes With with certain limitation.
Invention content
The purpose of the present invention is to provide a kind of project management progress chasing display board, can more show project into Degree, can be shown according to project schedule plan number be unfolded, adaptability is wider, classification displaying, will not be chaotic, and fills The Universal wheel structure of bottom set portion setting, is moved, to solve the problems mentioned in the above background technology convenient for device.
To achieve the above object, the present invention provides following technical solution:A kind of project management progress chasing display board, including Mainboard, supporting rod and pedestal, the mainboard are mounted on supporting rod, and the pedestal is mounted on supporting rod bottom, and base bottom Universal wheel is installed, first compartment, second are divided by first partition, second partition and third partition board respectively in the mainboard Compartment, third compartment and the 4th compartment, the first compartment and the setting of second compartment upper and lower opening, the third compartment and the 4th Compartment or so opening setting, the first compartment and second compartment are located at third compartment and the 4th compartment outside, described first every Be separately installed with subplate, lower subplate, right subplate and left secondary plate in room, second compartment, third compartment and the 4th compartment, it is described on Subplate and lower subplate are separately fixed at by bolt in first compartment and second compartment, and the right subplate passes through the first sliding block point Be not slidably connected to first partition and second partition, the left secondary plate by the second sliding block be slidably connected to respectively second partition and Third partition board, the supporting rod are fixedly connected on mainboard by link block.
Preferably, it is welded with the bearing diagonal being connected with pedestal on the supporting rod.
Preferably, at the top of the upper subplate and lower subplate bottom is equipped with the first pulling plate, the right subplate right side and left secondary The second pulling plate is equipped on the left of plate.
Preferably, the sectional area of first pulling plate is more than the opening sectional area of first compartment and second compartment, described The sectional area of second pulling plate is more than the opening sectional area of third compartment and the 4th compartment.
Preferably, it corresponds to the first sliding block respectively on the second partition and the second sliding block sliding position offers what is matched First sliding rail and the second sliding rail, offer the third sliding rail to match with the first sliding block in the first partition, the third every The 4th sliding rail to match with the second sliding block is offered on plate.
Preferably, the link block both sides be equipped with the connecting plate that is connected, through there is the first bolt on the connecting plate.
Preferably, it is connected between the supporting rod and link block by reinforcement block, running through on the reinforcement block has the second spiral shell Bolt.
Preferably, the first compartment, second compartment, third compartment and the 4th compartment respectively with upper subplate, lower subplate, the right side The matching relationship of subplate and left secondary plate is clearance fit.
Preferably, the threaded hole to match with bolt is offered on the upper subplate and lower subplate.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, the present invention on the basis of mainboard by setting four subplate structures, upper subplate, lower subplate, right subplate and left secondary Plate is corresponding respectively to be unfolded up and down with right left four orientation, can more show project process, can be according to project schedule plan Displaying number be unfolded, adaptability is wider;
2nd, four groups of subplate structures can be unfolded and store, easy to use, realize the classification displaying of project process, will not mix It is random, and the Universal wheel structure of bottom of device setting, it is moved convenient for device, there is very high practicability.
Description of the drawings
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the main board overlooking the structure diagram of the present invention;
Fig. 3 is the subplate deployment opening structure diagram of the present invention;
Fig. 4 is the partial top structure diagram of the present invention;
Fig. 5 is enlarged structure schematic diagram at the A of the present invention;
Fig. 6 is enlarged structure schematic diagram at the B of the present invention;
Fig. 7 is the second partition part-structure schematic diagram of the present invention;
Fig. 8 is the first partition part-structure schematic diagram of the present invention;
Fig. 9 is the third partition part structure diagram of the present invention;
Figure 10 is the supporting rod of the present invention and link block partially connected architecture schematic diagram.
In figure:1 mainboard, 2 supporting rods, 3 pedestals, 4 universal wheels, 5 bearing diagonals, 6 bolts, 61 threaded holes, 7 first pulling plates, 8 Two pulling plates, 9 first partitions, 10 second partitions, 11 third partition boards, 12 first compartments, 13 second compartments, 14 third compartments, 15 It is four compartments, subplate on 16,17 times subplates, 18 right subplates, 181 first sliding blocks, 1,811 first sliding rails, 1812 third sliding rails, 19 left Subplate, 191 second sliding blocks, 1,911 second sliding rails, 1912 the 4th sliding rails, 20 link blocks, 21 connecting plates, 22 first bolts, 23 add Strong block, 24 second bolts.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment shall fall within the protection scope of the present invention.
- 10 are please referred to Fig.1, the present invention provides a kind of technical solution:A kind of project management progress chasing display board, including master Plate 1, supporting rod 2 and pedestal 3, the mainboard 1 are mounted on supporting rod 2, and the pedestal 3 is mounted on 2 bottom of supporting rod, and pedestal 3 bottoms are equipped with universal wheel 4, and setting universal wheel 4 facilitates the movement of device;Pass through first partition 9, in the mainboard 1 respectively Two partition boards 10 and third partition board 11 are divided into first compartment 12, second compartment 13,14 and the 4th compartment 15 of third compartment, and described One compartment 12 and the setting of 13 upper and lower opening of second compartment, 14 and the 4th compartment 15 or so of the third compartment opening setting are described First compartment 12 and second compartment 13 are located at 15 outside of third compartment 14 and the 4th compartment, the first compartment 12, second compartment 13rd, it is separately installed with subplate 16, lower subplate 17, right subplate 18 and left secondary plate 19 in 14 and the 4th compartment 15 of third compartment, four Group subplate structure can provide four display panels;The upper subplate 16 and lower subplate 17 are separately fixed at by bolt 6 It in one compartment 12 and second compartment 13, is fixed by bolt 6, easy disassembly, is adjusted convenient for upper subplate 16 and lower subplate 17;It is described Right subplate 18 is slidably connected to first partition 9 and second partition 10 respectively by the first sliding block 181, and the left secondary plate 19 passes through Two sliding blocks 191 are slidably connected to second partition 10 and third partition board 11 respectively, and the supporting rod 2 is fixedly connected by link block 20 In mainboard 1.
Specifically, the bearing diagonal 5 being connected with pedestal 3 is welded on the supporting rod 2;Setting bearing diagonal 5 is carried for supporting rod 2 For supporting role.
Specifically, 16 top of upper subplate and lower 17 bottom of subplate are equipped with the first pulling plate 7, right 18 right side of subplate The second pulling plate 8 is equipped with 19 left side of left secondary plate;Set the first pulling plate 7 and the second pulling plate 8 that pumping is facilitated to carry out four groups of subplate knots respectively Structure.
Specifically, the sectional area of first pulling plate 7 is more than the opening sectional area of first compartment 12 and second compartment 13, The sectional area of second pulling plate 8 is more than the opening sectional area of 14 and the 4th compartment 15 of third compartment;Using 7 He of the first pulling plate The sectional area of second pulling plate 8 is more than the mode of opening section product, can fall into opening to avoid pulling plate, facilitate pull.
Specifically, corresponding first sliding block 181 and 191 sliding position of the second sliding block offer respectively on the second partition 10 The first sliding rail 1811 and the second sliding rail 1911 to match offers what is matched with the first sliding block 181 in the first partition 9 Third sliding rail 1812 offers the 4th sliding rail 1912 to match with the second sliding block 191 on the third partition board 11;According to sliding block Corresponding rail structure is set, facilitates the slip of left and right subplate, and mobile and position-limiting action is provided by sliding rail.
Specifically, 20 both sides of link block are equipped with the connecting plate 21 being connected with 1, running through on the connecting plate 21 has first Bolt 22;It is fixed using 21 and first bolt 22 of connecting plate so that it is convenient for disassembly and assembly, convenient for safeguarding and replacing.
Specifically, being connected between the supporting rod 2 and link block 20 by reinforcement block 23, running through on the reinforcement block 23 has Second bolt 24;It is fixed using 23 and second bolt 24 of reinforcement block so that be arranged and fixed conveniently.
Specifically, the first compartment 12, second compartment 13,14 and the 4th compartment 15 of third compartment respectively with upper subplate 16th, the matching relationship of lower subplate 17, right subplate 18 and left secondary plate 19 is clearance fit;The mode being gap-matched facilitates four groups Subplate, which can pull out, to be come.
Specifically, offer the threaded hole 61 to match with bolt 6 on the upper subplate 16 and lower subplate 17;Spiral shell is set Pit 61 facilitates bolt 6 to be fixed.
Operation principle:In use, setting 1 structure of mainboard, it will by first partition 9, second partition 10 and third partition board 11 First compartment 12, second compartment 13,14 and the 4th compartment 15 of third compartment are divided into inside mainboard 1, respectively in four groups of compartments Subplate 16, lower subplate 17, right subplate 18 and left secondary plate 19 are installed respectively, and upper subplate 16 can pull upwardly on, solid by bolt 6 It is fixed, lower subplate 17 can downward pull, fixed also by bolt 6, right subplate 18 and left secondary plate 19 are taken out respectively with left side to the right It stretches out, realizes that four orientation can extend opening, facilitate the displaying of more project schedule plans, and can realize point Class is shown so that bandwagon effect is more clear, and 4 structure of universal wheel of 3 bottom of pedestal installation moves convenient for device, has Very high practicability.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (9)

1. a kind of project management progress chasing display board, including mainboard (1), supporting rod (2) and pedestal (3), it is characterised in that:Institute Mainboard (1) is stated on supporting rod (2), the pedestal (3) is mounted on supporting rod (2) bottom, and pedestal (3) bottom is equipped with Universal wheel (4) is divided into the in the mainboard (1) by first partition (9), second partition (10) and third partition board (11) respectively One compartment (12), second compartment (13), third compartment (14) and the 4th compartment (15), the first compartment (12) and second compartment (13) upper and lower opening is set, the third compartment (14) and the opening setting of the 4th compartment (15) left and right, the first compartment (12) With second compartment (13) on the outside of third compartment (14) and the 4th compartment (15), the first compartment (12), second compartment (13), be separately installed in third compartment (14) and the 4th compartment (15) subplate (16), lower subplate (17), right subplate (18) and Left secondary plate (19), the upper subplate (16) and lower subplate (17) are separately fixed at first compartment (12) and by bolt (6) In two compartments (13), the right subplate (18) by the first sliding block (181) be slidably connected to respectively first partition (9) and second every Plate (10), the left secondary plate (19) are slidably connected to second partition (10) and third partition board respectively by the second sliding block (191) (11), the supporting rod (2) is fixedly connected on mainboard (1) by link block (20).
2. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The supporting rod (2) On be welded with the bearing diagonal (5) being connected with pedestal (3).
3. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The upper subplate (16) Top and lower subplate (17) bottom are equipped with the first pulling plate (7), are all provided on the right side of the right subplate (18) with left secondary plate (19) left side There is the second pulling plate (8).
4. a kind of project management progress chasing display board according to claim 3, it is characterised in that:First pulling plate (7) sectional area is more than the opening sectional area of first compartment (12) and second compartment (13), the section of second pulling plate (8) Product is more than third compartment (14) and the opening sectional area of the 4th compartment (15).
5. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The second partition (10) it corresponds to the first sliding block (181) respectively on and the second sliding block (191) sliding position offers the first sliding rail to match (1811) and the second sliding rail (1911), the third sliding rail to match with the first sliding block (181) is offered on the first partition (9) (1812), the 4th sliding rail (1912) to match with the second sliding block (191) is offered on the third partition board (11).
6. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The link block (20) Both sides are equipped with the connecting plate (21) being connected with (1), and running through on the connecting plate (21) has the first bolt (22).
7. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The supporting rod (2) It is connected between link block (20) by reinforcement block (23), running through on the reinforcement block (23) has the second bolt (24).
8. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The first compartment (12), second compartment (13), third compartment (14) and the 4th compartment (15) respectively with upper subplate (16), lower subplate (17), right pair The matching relationship of plate (18) and left secondary plate (19) is clearance fit.
9. a kind of project management progress chasing display board according to claim 1, it is characterised in that:The upper subplate (16) With the threaded hole (61) that matches with bolt (6) is offered on lower subplate (17).
CN201711396447.5A 2017-12-21 2017-12-21 A kind of project management progress chasing display board Pending CN108257528A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711396447.5A CN108257528A (en) 2017-12-21 2017-12-21 A kind of project management progress chasing display board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711396447.5A CN108257528A (en) 2017-12-21 2017-12-21 A kind of project management progress chasing display board

Publications (1)

Publication Number Publication Date
CN108257528A true CN108257528A (en) 2018-07-06

Family

ID=62723499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711396447.5A Pending CN108257528A (en) 2017-12-21 2017-12-21 A kind of project management progress chasing display board

Country Status (1)

Country Link
CN (1) CN108257528A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105280092A (en) * 2015-10-30 2016-01-27 哈尔滨意创空间展览展示制作有限公司 Display board with stretching function and display method
CN205354389U (en) * 2015-12-01 2016-06-29 新余学院 College english teaching show board
CN106683493A (en) * 2016-12-26 2017-05-17 苏州沃森优金电子科技有限公司 Folding presenting board for psychology teaching
CN206441460U (en) * 2017-01-17 2017-08-25 王益东 World's wind direction and ocean current Pattern Teaching in Women panel
CN107301815A (en) * 2017-07-03 2017-10-27 郭林华 A kind of project management progress chasing Graphic Panel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105280092A (en) * 2015-10-30 2016-01-27 哈尔滨意创空间展览展示制作有限公司 Display board with stretching function and display method
CN205354389U (en) * 2015-12-01 2016-06-29 新余学院 College english teaching show board
CN106683493A (en) * 2016-12-26 2017-05-17 苏州沃森优金电子科技有限公司 Folding presenting board for psychology teaching
CN206441460U (en) * 2017-01-17 2017-08-25 王益东 World's wind direction and ocean current Pattern Teaching in Women panel
CN107301815A (en) * 2017-07-03 2017-10-27 郭林华 A kind of project management progress chasing Graphic Panel

Similar Documents

Publication Publication Date Title
CN101748915B (en) Modularization construction method for nuclear power station nuclear island
CN101752017A (en) Modularization construction method for nuclear power station nuclear island
CN212473851U (en) Cabin unit hoisting structure
CN101136259A (en) Modular construction method for nuclear island of nuclear power station
CN118710448A (en) A smart beam yard system
CN104213561B (en) A kind of high concrete pouring construction method building intensity dam
CN203603455U (en) Tool type hanger suitable for construction of vertical structure of super high-rise building
CN108257528A (en) A kind of project management progress chasing display board
CN106522550B (en) A method for setting up pipeline supports of an integral steel structure platform in an ultra-large underground refrigeration room
Kim et al. Marketing strategy and influential factors based on the attributes of unit modular system
CN101736925A (en) Modular construction method for nuclear island of nuclear power station
CN206737145U (en) For installing the node of multi-storied garage steel construction
CN109317911A (en) A kind of cross column welding production line
CN103982881A (en) Illuminating system with all-purpose lamp bracket and curtain wall and construction method thereof
CN202767578U (en) Modular data center
CN207513259U (en) A kind of twin spans two-wire production system of assembling type buildings material
CN208122340U (en) Detachable and recyclable discharging platform
CN207714690U (en) A kind of dismountable steel structure lift shaft
CN118419219A (en) Integrated building process for ocean engineering block
CN207480851U (en) One kind is used for flow production line novel steel skeleton die station
CN208082837U (en) Simple natural sand stone screening separator
CN208133264U (en) One kind is novel to pour truss manipulator
CN107905378A (en) Super High mixed type space steel lattice boxlike tube-in-tube structure and production method
CN206814241U (en) A kind of steel construction elevator ready-package corridor
JPH04368568A (en) How to build a versatile production system and buildings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180706