CN108252510A - A kind of concrete divides storehouse to obstruct grid - Google Patents

A kind of concrete divides storehouse to obstruct grid Download PDF

Info

Publication number
CN108252510A
CN108252510A CN201810269764.9A CN201810269764A CN108252510A CN 108252510 A CN108252510 A CN 108252510A CN 201810269764 A CN201810269764 A CN 201810269764A CN 108252510 A CN108252510 A CN 108252510A
Authority
CN
China
Prior art keywords
grid
barrier
item
concrete
grid layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810269764.9A
Other languages
Chinese (zh)
Inventor
丁杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN201810269764.9A priority Critical patent/CN108252510A/en
Publication of CN108252510A publication Critical patent/CN108252510A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention provides a kind of concrete to divide storehouse to obstruct grid, belongs to technical field of building construction.A kind of concrete divides storehouse to obstruct grid, including multiple grid layers, grid layer includes more first barrier items arranged in a crossed manner and more second barrier items, and the junction of the first barrier item and the second barrier item is connecting portion, and corresponding connecting portion is connected by elastic component between adjacent grid layer.When needing installation, the end of the first barrier item of grid layer, the second barrier item is fixed on structure reinforcing bars, the elastic component between adjacent grid layer is stretched, and the distance between grid layer and grid layer become larger.When concrete point storehouse, barrier grid is fixed against, when carrying out concreting to different parts, the concrete structure first poured can be intercepted by the partitive case grid layer of concrete point storehouse barrier grid, and formation connects a batch face.By the iris action of grid layer layer by layer, concrete spilling can be effectively prevented.

Description

A kind of concrete divides storehouse to obstruct grid
Technical field
The present invention relates to technical field of building construction, storehouse are divided to obstruct grid in particular to a kind of concrete.
Background technology
At present, beam column when different parts structural concrete is constructed, successively apply by the concrete often referred to different labels Work, the prior art generally first stop different labels boundary using fast-easy closing-up net.
When concrete is poured into a mould behind template, complementary angle piece on mesh just in concrete, formed one with it is neighbouring The mechanical wedge that castable is connected.The quality of seam is strictly controlled.Intensity in terms of its bonding and shearing can be good with process The suture of scabbling of benefit reason compares favourably.The processes such as punching, plucking can be removed during second pouring from can shorten construction period, increase simultaneously Pour the intensity of building body.
But when using fast-easy closing-up net, there is cut in fast easy-to-closing Netease, and concrete is caused to overflow.
Invention content
The purpose of the present invention is to provide a kind of concrete to divide storehouse to obstruct grid.
The invention is realized in this way:
A kind of concrete divides storehouse to obstruct grid, and including multiple grid layers, grid layer includes arranged in a crossed manner more first Obstruct item and more second barrier items, first barrier item with second barrier item junction be connecting portion, adjacent grid layer Between corresponding connecting portion connected by elastic component.
Further, in an embodiment of the present invention:
Elastic component is spring part.
Further, in an embodiment of the present invention:
First barrier item and the second barrier item are each configured to scalable.
Further, in an embodiment of the present invention:
First barrier item and the second barrier item are spring part.
Further, in an embodiment of the present invention:
First barrier item and the second barrier item are connected by fixing piece and fixed.
Further, in an embodiment of the present invention:
Fixing piece is binding piece, and the first barrier item and the second barrier item tie up fixation by binding piece.
Further, in an embodiment of the present invention:
Binding piece obstructs item, the second barrier item and elastic component by first and ties up fixation jointly.
Further, in an embodiment of the present invention:
Grid layer is made of zinc-coated wire.
Further, in an embodiment of the present invention:
First barrier item and the second barrier item are in 30-120 ° of angle.
Further, in an embodiment of the present invention:
First barrier item and the second barrier item are in 90 ° of angle.
The beneficial effects of the invention are as follows:The present invention obstructs grid by the concrete point storehouse that above-mentioned design obtains, due to The junction of first barrier item and the second barrier item is connecting portion, and corresponding connecting portion passes through bullet between adjacent grid layer Property part connection, then can stretch and compress between adjacent grid layer, be when not in use, between grid layer and grid layer in pressure Contracting state, entire concrete divides volume shared by storehouse barrier grid smaller, when needing installation, by the first barrier of grid layer Item, the second end for obstructing item are fixed on structure reinforcing bars, due to the presence of elastic component, elastic component quilt between adjacent grid layer It stretches, then the distance between grid layer and grid layer become larger.When concrete point storehouse, barrier grid is fixed against, to difference When position carries out concreting, the concrete structure first poured can be blocked by the partitive case grid layer of concrete point storehouse barrier grid It stops, formation connects a batch face.Due to dividing storehouse barrier grid that there is Multi-layer lattice grid layer by concrete, then pass through the resistance of grid layer layer by layer Every effect, concrete spilling can be effectively prevented.
Description of the drawings
It, below will be to use required in embodiment in order to illustrate more clearly of the technical solution of embodiment of the present invention Attached drawing be briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not to be seen as It is the restriction to range, it for those of ordinary skill in the art, without creative efforts, can be with root Other relevant attached drawings are obtained according to these attached drawings.
Fig. 1 is the structure diagram of barrier grid in concrete point storehouse provided in an embodiment of the present invention;
Fig. 2 is the connection relation structure diagram of adjacent grid layer provided in an embodiment of the present invention;
Fig. 3 is a kind of structure diagram of grid layer provided in an embodiment of the present invention;
Fig. 4 is the structure diagram of another grid layer provided in an embodiment of the present invention.
Icon:100- concrete divides storehouse to obstruct grid;110- grid layers;111- first obstructs item;112- second is obstructed Item;113- connecting portions;114- elastic components;115- binding pieces.
Specific embodiment
Purpose, technical scheme and advantage to make embodiment of the present invention are clearer, implement below in conjunction with the present invention The technical solution in embodiment of the present invention is clearly and completely described in attached drawing in mode, it is clear that described reality The mode of applying is the embodiment of a part of embodiment of the present invention rather than whole.Based on the embodiment in the present invention, ability The every other embodiment that domain those of ordinary skill is obtained without creative efforts, belongs to the present invention The range of protection.
Therefore, the detailed description of the embodiments of the present invention to providing in the accompanying drawings is not intended to limit requirement guarantor below The scope of the present invention of shield, but it is merely representative of the selected embodiment of the present invention.Based on the embodiment in the present invention, ability The every other embodiment that domain those of ordinary skill is obtained without creative efforts, belongs to the present invention The range of protection.
It should be noted that:Similar label and letter represents similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need to that it is further defined and explained in subsequent attached drawing.
In the description of the present invention, it is to be understood that the orientation of the instructions such as term " longitudinal direction ", " transverse direction ", " on ", " under " Or position relationship is based on orientation shown in the drawings or position relationship, is for only for ease of the description present invention and simplifies description, and It is not instruction or implies signified equipment or element there must be specific orientation, with specific azimuth configuration and operation, therefore It is not considered as limiting the invention.
In addition, term " first ", " second " are only used for description purpose, and it is not intended that instruction or hint relative importance Or the implicit quantity for indicating indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Implicitly include one or more this feature.In the description of the present invention, " multiple " are meant that two or more, Unless otherwise specifically defined.
In the present invention unless specifically defined or limited otherwise, term " installation ", " setting ", " connection ", " fixation " etc. Term should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected or integral;It can be direct phase Even, it can also be indirectly connected by intermediary, can be that connection inside two elements or the interaction of two elements are closed System.For the ordinary skill in the art, above-mentioned term in the present invention specific can be understood as the case may be Meaning.
In the present invention unless specifically defined or limited otherwise, fisrt feature second feature it " on " or it " under " It can be in direct contact including the first and second features, it is not to be in direct contact but pass through it that can also include the first and second features Between other characterisation contact.Moreover, fisrt feature second feature " on ", " top " and " above " including first spy Sign is right over second feature and oblique upper or is merely representative of fisrt feature level height higher than second feature.Fisrt feature exists Second feature " under ", " lower section " and " following " immediately below second feature and obliquely downward or be merely representative of including fisrt feature Fisrt feature level height is less than second feature.
Embodiment
At present, beam column when different parts structural concrete is constructed, successively apply by the concrete often referred to different labels Work, the prior art generally first stop different labels boundary using fast-easy closing-up net.
When concrete is poured into a mould behind template, complementary angle piece on mesh just in concrete, formed one with it is neighbouring The mechanical wedge that castable is connected.The quality of seam is strictly controlled.Intensity in terms of its bonding and shearing can be good with process The suture of scabbling of benefit reason compares favourably.The processes such as punching, plucking can be removed during second pouring from can shorten construction period, increase simultaneously Pour the intensity of building body.
But when using fast-easy closing-up net, installation is complex, and cut occurs in fast easy-to-closing Netease, causes concrete It overflows.
Based on this, the present embodiment provides a kind of concrete to divide storehouse to obstruct grid 100, please refers to Fig. 1 and Fig. 2.
Specifically, concrete divides storehouse barrier grid 100 to include multiple grid layers 110, and grid layer 110 includes arranged in a crossed manner More first barrier items 111 and Duo Gen second obstruct item 112, first barrier item 111 with second obstruct item 112 junction be Connecting portion 113, corresponding connecting portion 113 is connected by elastic component 114 between adjacent grid layer 110.
As shown in Figure 1, multiple grid layers 110 are set gradually from left to right.As shown in figure 3, each grid layer 110 is respectively provided with There are more first barrier items 111 and Duo Gen second to obstruct item 112.The first barrier barrier item 112 of item 111 and second is arranged in a crossed manner, In the present embodiment, the first laterally setting of barrier item 111, the second barrier item 112 is longitudinally disposed, the first barrier item 111 and second Barrier item 112 is arranged on same plane, more first barrier item 111 parallel interval settings, more second barrier items 112 parallel Every setting, the first barrier item 111 and second, which obstructs item 112, has certain angle, and the first barrier item 111 and second obstructs item The 112 multiple mesh of formation arranged in a crossed manner.
Due to first barrier item 111 and second obstruct item 112 junction be connecting portion 113, adjacent grid layer 110 Between corresponding connecting portion 113 connected by elastic component 114, then can stretch and compress between adjacent grid layer 110, when It is in compressive state between grid layer 110 and grid layer 110, entire concrete divides shared by storehouse barrier grid 100 when being not used Volume is smaller, and when needing installation, the end that the first barrier item 111, second of grid layer 110 is obstructed to item 112 is fixed on On structure reinforcing bars, since the presence of elastic component 114, elastic component 114 are stretched between adjacent grid layer 110, then grid layer 110 The distance between grid layer 110 becomes larger.When concrete point storehouse barrier grid 100 be fixed against when, to different parts into During row concreting, the concrete structure first poured can be blocked by the partitive case grid layer 110 of concrete point storehouse barrier grid 100 It stops, formation connects a batch face, while grid layer 110 can also increase the intensity and connectivity of conjunction old and new concret.Due to by coagulation Soil divides storehouse barrier grid 100 to have Multi-layer lattice grid layer 110, then by the iris action of grid layer 110 set layer by layer, can have Prevent concrete from overflowing to effect.
Further, in the present embodiment, elastic component 114 is spring part.It should be noted that elastic component 114 is alternatively Other parts with scalability energy.
Further, it please refers to, Fig. 4, in the present embodiment, the first barrier item 111 and second obstructs item 112 and is configured Into scalable.
Due to first barrier item 111 and second obstruct item 112 be also configured to it is telescopic, when not in use, first barrier Item 111 and second obstructs item 112 also into compressive state, at this point, the first barrier item 111 and second arranged in a crossed manner obstructs item 112 Between the mesh that is formed it is smaller, when the end that the first barrier item 111, second is obstructed to item 112 is fixed on structure reinforcing bars, the One barrier item 111 and second obstructs item 112 and is stretched, and the first barrier item 111 and second obstructs the mesh formed between item 112 and becomes Greatly.Can the first barrier item 111 and second be obstructed by item 112 according to practice of construction demand in this way and be banded in the default of structure reinforcing bars Position, so as to adjust the mesh size formed between the first barrier item 111 and the second barrier item 112.In the present embodiment, First barrier item 111 and second obstructs the angle that item 112 is in 30-120 °.Optionally, the first barrier item 111 and second obstructs item 112 be in 90 ° of angle.
Further, in the present embodiment, it is spring part that the first barrier item 111 and second, which obstructs item 112,.Grid layer 110 the first barrier item 111, second obstructs item 112 and is made of zinc-coated wire.The grid layer 110 of connection adjacent two layers connects The elastic component 114 in portion 113 is also to be made of zinc-coated wire.
In addition, in the present embodiment, the first barrier item 111 connects fixation with the second barrier item 112 by fixing piece.Pass through The place of fixing piece connection is connecting portion 113.
In the present embodiment, fixing piece is binding piece 115, and the first barrier item 111 and second obstructs item 112 and passes through binding piece 115 tie up fixation.Binding piece 115 is zinc-coated wire, and the crossover location that the first barrier item 111 and second obstructs item 112 leads in advance Zinc-coated wire is crossed to be tied up to be fixed.
Further, in this example, the first barrier item 111, second is obstructed item 112 and elastic component 114 by binding piece 115 Fixation is tied up jointly.It ties up in this way and enables to entire concrete point storehouse barrier 100 structure of grid more stable, by concrete Point storehouse barrier grid 100 is whole pull loose during, will not scatter easily.Such structure also more securely, avoids what is poured Concrete is revealed.
To sum up, the concrete of the present embodiment divides storehouse to obstruct grid 100, since the first barrier item 111 and second obstructs item 112 junction is connecting portion 113, and corresponding connecting portion 113 is connected by elastic component 114 between adjacent grid layer 110 It connects, then can stretch and compress between adjacent grid layer 110, when not in use, be between grid layer 110 and grid layer 110 In compressive state, entire concrete divides volume shared by storehouse barrier grid 100 smaller, when needing installation, by grid layer 110 First barrier item 111, second obstruct item 112 end be fixed on structure reinforcing bars, due to bullet between adjacent grid layer 110 The presence of property part 114, elastic component 114 are stretched, then the distance between grid layer 110 and grid layer 110 become larger.When concrete point When storehouse barrier grid 100 is fixed against, when carrying out concreting to different parts, the concrete structure first poured can quilt The partitive case grid layer 110 of concrete point storehouse barrier grid 100 intercepts, and formation connects a batch face, while grid layer 110 can also increase The intensity and connectivity of conjunction old and new concret.Due to dividing storehouse barrier grid 100 that there is Multi-layer lattice grid layer 110 by concrete, Then by the iris action of grid layer 110 set layer by layer, concrete spilling can be effectively prevented.
The foregoing is merely the preferred embodiment of the present invention, are not intended to restrict the invention, for this field For technical staff, the invention may be variously modified and varied.All within the spirits and principles of the present invention, that is made is any Modification, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of concrete divides storehouse to obstruct grid, which is characterized in that including multiple grid layers, the grid layer, which includes intersecting, to be set The more first barrier items and more second barrier items put, the junction of the first barrier item and the described second barrier item is Connecting portion, the corresponding connecting portion is connected by elastic component between the adjacent grid layer.
2. concrete according to claim 1 divides storehouse to obstruct grid, which is characterized in that the elastic component is spring part.
3. concrete according to claim 1 divides storehouse to obstruct grid, which is characterized in that the first barrier item and second Barrier item is each configured to scalable.
4. concrete according to claim 3 divides storehouse to obstruct grid, which is characterized in that the first barrier item and described Second barrier item is spring part.
5. concrete according to claim 1 divides storehouse to obstruct grid, which is characterized in that the first barrier item and described Second barrier item is connected by fixing piece to be fixed.
6. concrete according to claim 5 divides storehouse to obstruct grid, which is characterized in that the fixing piece is binding piece, The first barrier item and the second barrier item tie up fixation by binding piece.
7. concrete according to claim 6 divides storehouse to obstruct grid, which is characterized in that the binding piece is by described first Barrier item, the second barrier item and elastic component tie up fixation jointly.
8. concrete according to claim 1 divides storehouse to obstruct grid, which is characterized in that the grid layer is by zinc-coated wire It is made.
9. concrete according to claim 1 divides storehouse to obstruct grid, which is characterized in that the first barrier item and described Second barrier item is in 30-120 ° of angle.
10. concrete according to claim 9 divides storehouse to obstruct grid, which is characterized in that the first barrier item and institute State the angle that the second barrier item is in 90 °.
CN201810269764.9A 2018-03-28 2018-03-28 A kind of concrete divides storehouse to obstruct grid Pending CN108252510A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810269764.9A CN108252510A (en) 2018-03-28 2018-03-28 A kind of concrete divides storehouse to obstruct grid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810269764.9A CN108252510A (en) 2018-03-28 2018-03-28 A kind of concrete divides storehouse to obstruct grid

Publications (1)

Publication Number Publication Date
CN108252510A true CN108252510A (en) 2018-07-06

Family

ID=62747551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810269764.9A Pending CN108252510A (en) 2018-03-28 2018-03-28 A kind of concrete divides storehouse to obstruct grid

Country Status (1)

Country Link
CN (1) CN108252510A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1966903A (en) * 2006-11-25 2007-05-23 范吉廷 High-strength steel mesh for use in concrete and its making method
KR100891299B1 (en) * 2008-07-07 2009-04-06 허택인 Mesh panel type retaining wall and operation thereof
CN103314168A (en) * 2011-01-07 2013-09-18 阿海珐有限公司 Protective system for walls of buildings or containers
CN203441000U (en) * 2013-08-01 2014-02-19 江筠 Anti-slip device for concrete pouring of gentle slope oblique beam structure
CN204738538U (en) * 2015-05-28 2015-11-04 中国建筑第二工程局有限公司 Stubble blocking and turnover back ridge for concrete construction with different strength grades
CN206289962U (en) * 2016-12-21 2017-06-30 胡连义 Foaming concrete wall and cast-in-place foamed concrete wall mould
CN206376431U (en) * 2017-01-11 2017-08-04 保定恒超新型材料科技有限公司 A kind of cast-in-situ open-web floor obturator
CN107313592A (en) * 2017-07-27 2017-11-03 中国建筑第五工程局有限公司 Extension type prevents different labels concrete is mixed from pouring device
CN206666955U (en) * 2017-03-25 2017-11-24 河北福朗斯金属丝网制品有限公司 Reinforced civil grille
CN208456121U (en) * 2018-03-28 2019-02-01 中铁十一局集团第二工程有限公司 A kind of concrete divides storehouse to obstruct grid

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1966903A (en) * 2006-11-25 2007-05-23 范吉廷 High-strength steel mesh for use in concrete and its making method
KR100891299B1 (en) * 2008-07-07 2009-04-06 허택인 Mesh panel type retaining wall and operation thereof
CN103314168A (en) * 2011-01-07 2013-09-18 阿海珐有限公司 Protective system for walls of buildings or containers
CN203441000U (en) * 2013-08-01 2014-02-19 江筠 Anti-slip device for concrete pouring of gentle slope oblique beam structure
CN204738538U (en) * 2015-05-28 2015-11-04 中国建筑第二工程局有限公司 Stubble blocking and turnover back ridge for concrete construction with different strength grades
CN206289962U (en) * 2016-12-21 2017-06-30 胡连义 Foaming concrete wall and cast-in-place foamed concrete wall mould
CN206376431U (en) * 2017-01-11 2017-08-04 保定恒超新型材料科技有限公司 A kind of cast-in-situ open-web floor obturator
CN206666955U (en) * 2017-03-25 2017-11-24 河北福朗斯金属丝网制品有限公司 Reinforced civil grille
CN107313592A (en) * 2017-07-27 2017-11-03 中国建筑第五工程局有限公司 Extension type prevents different labels concrete is mixed from pouring device
CN208456121U (en) * 2018-03-28 2019-02-01 中铁十一局集团第二工程有限公司 A kind of concrete divides storehouse to obstruct grid

Similar Documents

Publication Publication Date Title
CN208456121U (en) A kind of concrete divides storehouse to obstruct grid
CN108301534A (en) A kind of card slot type shear wall horizontal connection structure and preparation method thereof, construction method
EP2586935B1 (en) Method for reinforcing a wall structure and corresponding reinforcement system
CN108252510A (en) A kind of concrete divides storehouse to obstruct grid
KR101531626B1 (en) Shear reinforcement member for precast concrete composite slab
DE102017216383A1 (en) LOST SHUTTERING FOR CONCRETE CONSTRUCTION
CN106088639A (en) Perforation rib pull bar constraint rectangular steel pipe outsourcing self-compacting concrete reinforces RC post
CN207727797U (en) Wall column node different labels concrete separating device
CN209323834U (en) A kind of self-locking reinforcing bar limiting card
WO2016071847A1 (en) A joint between beam elements and column elements made of prefabricated reinforced concrete
CN207934247U (en) A kind of shear wall card slot type horizontal connection structure
CN209760830U (en) Prevent framework of steel reinforcement skew structure
CN205677244U (en) Template splicing ruggedized construction
CN108661188A (en) A kind of wall tie bar fastener inserts and construction method
CN105952183A (en) Reinforcing structure and reinforcing method of construction joint in reinforced concrete structure
CN206308811U (en) Assembled construction joint beam muscle location and plugging device
CN207177095U (en) Building precast template and building
CN207091902U (en) Arch bridge flexibility hinge device and arch bridge
CN201714079U (en) Construction separating device for reinforced concrete with different grades in vertical and horizontal structures
CN109610729A (en) A kind of T-shaped shaped rc columns
CN204754277U (en) Reinforced concrete wall's reinforced structure and reinforcing apparatus thereof
KR102128316B1 (en) Wire Mesh Module and Construction Method Thereof
CN207543624U (en) A kind of heel post
CN206815673U (en) Reinforcing ferroconcrete prop
CN108824704A (en) A kind of steel bar framework builds mechanism

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination