CN108130915B - Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof - Google Patents

Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof Download PDF

Info

Publication number
CN108130915B
CN108130915B CN201810127846.XA CN201810127846A CN108130915B CN 108130915 B CN108130915 B CN 108130915B CN 201810127846 A CN201810127846 A CN 201810127846A CN 108130915 B CN108130915 B CN 108130915B
Authority
CN
China
Prior art keywords
frame
raft
post
template
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810127846.XA
Other languages
Chinese (zh)
Other versions
CN108130915A (en
Inventor
蒋文娟
胡斌
赵璐
骆军
牛文龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Seventh Construction Group Co ltd
Original Assignee
Gansu Seventh Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Seventh Construction Group Co ltd filed Critical Gansu Seventh Construction Group Co ltd
Priority to CN201810127846.XA priority Critical patent/CN108130915B/en
Publication of CN108130915A publication Critical patent/CN108130915A/en
Application granted granted Critical
Publication of CN108130915B publication Critical patent/CN108130915B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/013Shuttering specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种预制装配式钢筋框架筏板基础后浇带模板及其施工方法,该模板包括多个首尾固定连接的长方体形钢筋框架模板单元,钢筋框架模板单元包括上框架、下框架以及设置在上框架与下框架之间的止水钢板,止水钢板为两根且分别焊接在上框架长边侧面与下框架长边侧面之间,上框架的两个长边侧面以及下框架的两个长边侧面上均设有网状模板面层,上框架的两个长边侧面顶部分别固定有梳子模。本发明改变了在筏板后浇带位置钢筋绑扎完成后,再进行现场焊接、绑扎、安装、封堵后浇带模板的施工工艺,促使后续工序的开始时间提前,加快了施工进度,节约了工期。同时,改变了在筏板钢筋之间狭窄的施工空间,施工条件加以改善,施工质量得到保证。

The present invention discloses a prefabricated assembled steel frame raft foundation post-cast strip template and a construction method thereof. The template comprises a plurality of rectangular steel frame template units that are fixedly connected end to end. The steel frame template unit comprises an upper frame, a lower frame, and a water-stop steel plate arranged between the upper frame and the lower frame. The water-stop steel plates are two and are respectively welded between the long side surfaces of the upper frame and the long side surfaces of the lower frame. The two long side surfaces of the upper frame and the two long side surfaces of the lower frame are provided with mesh template surface layers. The tops of the two long side surfaces of the upper frame are respectively fixed with comb molds. The present invention changes the construction process of welding, tying, installing, and sealing the post-cast strip template on site after the steel bars at the raft post-cast strip position are tied, thereby advancing the start time of subsequent processes, accelerating the construction progress, and saving construction period. At the same time, the narrow construction space between the raft steel bars is changed, the construction conditions are improved, and the construction quality is guaranteed.

Description

预制装配式钢筋框架筏板基础后浇带模板及其施工方法Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof

技术领域Technical Field

本发明属于建筑施工技术领域,具体涉及一种预制装配式钢筋框架筏板基础后浇带模板及其施工方法。The invention belongs to the technical field of building construction, and in particular relates to a prefabricated assembled steel frame raft foundation post-casting strip template and a construction method thereof.

背景技术Background Art

近年来,随着我国经济的迅速发展,高层、超高层建筑越来越多,大型、超厚型筏板基础占比逐渐增多,为了防止现浇混凝土结构由于自身收缩不均,消除或减轻混凝土因温度、湿度变形,以及结构沉降变形等对建筑产生不利影响,应在基础筏板和结构主体上的适当位置设置后浇带,而筏板后浇带的施工质量成为筏板基础施工的关键。In recent years, with the rapid development of my country's economy, there are more and more high-rise and super-high-rise buildings, and the proportion of large and super-thick raft foundations has gradually increased. In order to prevent the cast-in-place concrete structure from shrinking unevenly, eliminate or reduce the deformation of concrete due to temperature and humidity, and the adverse effects of structural settlement deformation on the building, post-cast strips should be set at appropriate positions on the foundation raft and the main structure, and the construction quality of the raft post-cast strip has become the key to the construction of the raft foundation.

传统后浇带模板和止水钢板的制作安装,需要在筏板后浇带位置的钢筋绑扎完成后,再进行现场安装、焊接,制约了后续工序的开始时间,拖延了基础施工进度,而且焊接工作在筏板钢筋上操作,焊接质量难以保证,固定不牢靠,容易导致跑模、漏浆等质量问题,在不同厚度筏板交界区域,安装质量更加难以控制,施工效率较低。The production and installation of traditional post-casting joint formwork and water-stop steel plate require on-site installation and welding after the reinforcement binding at the post-casting joint position of the raft slab is completed, which restricts the start time of subsequent processes and delays the progress of foundation construction. In addition, the welding work is performed on the raft slab reinforcement, and the welding quality is difficult to guarantee. The fixation is not reliable, which can easily lead to quality problems such as mold running and leakage. In the junction area of raft slabs of different thicknesses, the installation quality is more difficult to control and the construction efficiency is low.

发明内容Summary of the invention

本发明的目的是针对现有技术中存在的技术问题,提供一种结构简单、制作容易、便于安装且能提高工作效率、降低操作难度、节约施工成本、提升工程效益的预制装配式钢筋框架筏板基础后浇带模板。The purpose of the present invention is to provide a prefabricated assembled steel frame raft foundation post-cast strip template which is simple in structure, easy to manufacture, convenient to install and can improve work efficiency, reduce operation difficulty, save construction costs and improve engineering benefits in order to solve the technical problems existing in the prior art.

本发明的另一个目的是为了提供一种预制装配式钢筋框架筏板基础后浇带模板的施工方法。Another object of the present invention is to provide a construction method for a prefabricated assembled steel frame raft foundation post-casting strip formwork.

为了达到上述目的,本发明采用以下技术方案:一种预制装配式钢筋框架筏板基础后浇带模板,包括多个首尾固定连接的长方体形钢筋框架模板单元,所述钢筋框架模板单元包括上框架、下框架以及设置在上框架与下框架之间的止水钢板,所述止水钢板为两根且分别焊接在上框架长边侧面与下框架长边侧面之间,所述上框架的两个长边侧面以及下框架的两个长边侧面上均设有网状模板面层,所述上框架的两个长边侧面顶部分别固定有梳子模。In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a prefabricated assembled steel frame raft foundation post-cast strip formwork, comprising a plurality of rectangular steel frame formwork units fixedly connected at the head and tail, the steel frame formwork units comprising an upper frame, a lower frame and a waterstop steel plate arranged between the upper frame and the lower frame, the waterstop steel plates are two and are respectively welded between the long side surfaces of the upper frame and the long side surfaces of the lower frame, the two long side surfaces of the upper frame and the two long side surfaces of the lower frame are provided with a mesh formwork surface layer, and comb molds are respectively fixed on the tops of the two long side surfaces of the upper frame.

进一步地,所述上框架的长边侧面包括平行设置的两根上框架纵向横杆以及安装在两根上框架纵向横杆之间的多根上框架立杆,所述上框架的两个长边侧面之间设有多组上框架连接杆构件且每组上框架连接杆构件包括两根上下平行设置的上框架横向横杆。Furthermore, the long side surface of the upper frame includes two upper frame longitudinal cross bars arranged in parallel and a plurality of upper frame vertical bars installed between the two upper frame longitudinal cross bars, and a plurality of upper frame connecting rod components are arranged between the two long side surfaces of the upper frame, and each group of upper frame connecting rod components includes two upper frame transverse cross bars arranged in parallel up and down.

进一步地,所述上框架连接杆构件的两根上框架横向横杆之间设有相互交叉设置的两根上框架斜撑。Furthermore, two upper frame diagonal braces are arranged crosswise with each other between the two upper frame transverse cross bars of the upper frame connecting rod member.

进一步地,所述上框架连接杆构件为三组且分别设置在上框架长边侧面的两端及中部。Furthermore, the upper frame connecting rod components are in three groups and are respectively arranged at both ends and the middle of the long side surfaces of the upper frame.

进一步地,所述下框架的长边侧面包括平行设置的两根下框架纵向横杆以及安装在两根下框架纵向横杆之间的多根下框架立杆,所述下框架的两个长边侧面之间设有多组下框架连接杆构件且每组下框架连接杆构件包括两根上下平行设置的下框架横向横杆。Furthermore, the long side surface of the lower frame includes two lower frame longitudinal cross bars arranged in parallel and a plurality of lower frame vertical bars installed between the two lower frame longitudinal cross bars, and a plurality of groups of lower frame connecting rod components are arranged between the two long side surfaces of the lower frame, and each group of lower frame connecting rod components includes two lower frame transverse cross bars arranged in parallel up and down.

进一步地,所述下框架连接杆构件的两根下框架横向横杆之间设有相互交叉设置的两根下框架斜撑。Furthermore, two lower frame diagonal braces are arranged crosswise with each other between the two lower frame transverse cross bars of the lower frame connecting rod member.

进一步地,所述下框架连接杆构件为三组且分别设置在下框架长边侧面的两端及中部。Furthermore, the lower frame connecting rod components are in three groups and are respectively arranged at both ends and the middle of the long side surfaces of the lower frame.

进一步地,所述网状模板面层为钢板网与钢丝网的组合结构或快易收口网。Furthermore, the mesh template surface layer is a combination structure of steel plate mesh and steel wire mesh or a quick-closing mesh.

进一步地,所述梳子模包括枋木,所述枋木的底部均匀开有多条凹槽。Furthermore, the comb mold includes a beam, and a plurality of grooves are evenly formed on the bottom of the beam.

一种预制装配式钢筋框架筏板基础后浇带模板的施工方法,包括以下步骤:A construction method for a prefabricated assembled steel frame raft foundation post-casting strip formwork comprises the following steps:

A、施工准备:由施工技术人员依据筏板施工图纸详细计算后浇带各部位的尺寸,设计预制装配式钢筋框架筏板基础后浇带模板的尺寸,并绘制加工图纸,制作装配式钢筋框架筏板基础后浇带模板;A. Construction preparation: The construction technicians shall calculate the dimensions of each part of the post-casting strip in detail according to the raft construction drawings, design the dimensions of the prefabricated assembled steel frame raft foundation post-casting strip template, draw the processing drawings, and make the assembled steel frame raft foundation post-casting strip template;

B、施工放线:根据设计图纸放出后浇带的位置线;B. Construction layout: lay out the position line of the post-casting strip according to the design drawings;

C、垫层、防水层、保护层施工:按进度计划要求组织垫层、防水层及保护层的施工,同时安装绑扎后浇带附加钢筋;C. Construction of cushion layer, waterproof layer and protective layer: Organize the construction of cushion layer, waterproof layer and protective layer according to the schedule requirements, and install additional steel bars for post-casting belts at the same time;

D、组织筏板下层钢筋网安装绑扎:先从后浇带位置开始绑扎安装筏板下层钢筋,再向其他区域扩展;D. Organize the installation and binding of the lower layer steel mesh of the raft slab: start from the position of the post-casting belt to tie and install the lower layer steel bars of the raft slab, and then expand to other areas;

E、安装后浇带模板:后浇带位置的下层钢筋网绑扎安装完成后,立即进行后浇带模板的安装,由于后浇带模板采用了分段预制,采用塔吊将钢筋框架模板单元吊装到后浇带位置处,再采用电焊,将各钢筋框架模板单元焊接成为整体,同时将止水钢板焊接贯通;E. Install the post-casting strip template: After the lower layer of steel mesh at the post-casting strip is tied and installed, the post-casting strip template is installed immediately. Since the post-casting strip template is prefabricated in sections, a tower crane is used to hoist the steel frame template unit to the post-casting strip position, and then electric welding is used to weld each steel frame template unit into a whole, and the water stop steel plate is welded through at the same time;

F、整理网状模板面层:将各钢筋框架模板单元焊接成整体后,对网状模板面层进行整理、封堵,尤其钢筋框架模板单元连接处和筏板下层钢筋的底下要封堵严密,将网状模板面层向下延伸,与筏板垫层重合,再采用比筏板混凝土强度高一等级的细石混凝土进行封堵;F. Arrange the mesh formwork surface layer: After welding the steel frame formwork units into a whole, arrange and seal the mesh formwork surface layer, especially the joints of the steel frame formwork units and the bottom of the lower steel bars of the raft slab should be sealed tightly, extend the mesh formwork surface layer downward to overlap with the raft slab cushion layer, and then use fine stone concrete with a higher strength than the raft slab concrete for sealing;

G、绑扎筏板上层钢筋:筏板下层钢筋绑扎完成后,立即绑扎筏板上层钢筋网,此时装配式钢筋框架筏板基础后浇带模板可以作为筏板上层钢筋的支架,无须在此部位再单独设置支架;G. Binding of upper reinforcement of raft slab: After the binding of lower reinforcement of raft slab is completed, the upper reinforcement mesh of raft slab shall be immediately bound. At this time, the post-casting strip formwork of assembled reinforcement frame raft slab foundation can be used as the support of upper reinforcement of raft slab, and there is no need to set up a separate support at this position;

H、安装梳子模:筏板上层钢筋网绑扎完成后,按照钢筋直径和钢筋间距大小将枋木的下部裁割成梳子形状,安装在后浇带位置的上部,用于封堵筏板表层混凝土,梳子模的高度应略大于筏板钢筋保护层的厚度;H. Install the comb mold: After the upper steel mesh of the raft is tied, cut the lower part of the beam into a comb shape according to the diameter and spacing of the steel bars, and install it on the upper part of the post-casting strip to seal the surface concrete of the raft. The height of the comb mold should be slightly larger than the thickness of the raft steel bar protective layer;

I、浇筑混凝土:筏板钢筋绑扎完成后,经各方验收合格后,即可浇筑混凝土。I. Pouring concrete: After the raft slab reinforcement is tied and accepted by all parties, concrete can be poured.

本发明相对现有技术具有以下有益效果:本发明的预制装配式钢筋框架筏板基础后浇带模板包括多个首尾固定连接的长方体形钢筋框架模板单元,每个钢筋框架模板单元包括上框架、下框架以及设置在上框架与下框架之间的止水钢板,可预先按照后浇带的设计尺寸大小在场地外加工好一定数量的钢筋框架模板单元,在绑扎筏板钢筋的同时,安装后浇带模板,改变了在筏板后浇带位置钢筋绑扎完成后,再进行现场焊接、绑扎、安装、封堵后浇带模板的施工工艺,促使后续工序的开始时间提前,加快了施工进度,节约了工期。同时,由于在场地外预先制作,无须钻到筏板钢筋笼中进行焊接、安装、绑扎等工作,改变了在筏板钢筋之间狭窄的施工空间,施工条件加以改善,施工质量得到保证。另外,钢筋框架具有一定的承载力、刚度和稳定性,可以充当部分筏板上层钢筋的支架,既节约了成本,也提高了施工的安全性。本发明结构简单、容易制作、便于安装,降低了操作难度,提高了工作效率,节约了施工成本,提升了工程效益。The present invention has the following beneficial effects relative to the prior art: the prefabricated assembled steel frame raft foundation post-casting strip template of the present invention comprises a plurality of rectangular steel frame template units fixedly connected at the head and tail, each steel frame template unit comprises an upper frame, a lower frame and a water-stop steel plate arranged between the upper frame and the lower frame, a certain number of steel frame template units can be processed in advance outside the site according to the design size of the post-casting strip, and the post-casting strip template is installed while tying the raft steel bars, which changes the construction process of welding, tying, installing and blocking the post-casting strip template on site after the steel bars are tied at the raft post-casting strip position, promotes the start time of the subsequent process to be advanced, speeds up the construction progress and saves the construction period. At the same time, since it is prefabricated outside the site, there is no need to drill into the raft steel cage for welding, installation, tying and other work, which changes the narrow construction space between the raft steel bars, improves the construction conditions and ensures the construction quality. In addition, the steel frame has a certain bearing capacity, rigidity and stability, and can serve as a support for the upper steel bars of some rafts, which saves costs and improves the safety of construction. The invention has a simple structure, is easy to manufacture and install, reduces the difficulty of operation, improves work efficiency, saves construction costs, and improves engineering benefits.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本发明的结构示意图;Fig. 1 is a schematic diagram of the structure of the present invention;

图2为本发明钢筋框架模板单元的结构示意图;FIG2 is a schematic structural diagram of a steel frame template unit of the present invention;

图3为本发明上框架的结构示意图;FIG3 is a schematic structural diagram of an upper frame of the present invention;

图4为本发明下框架的结构示意图。FIG. 4 is a schematic structural diagram of the lower frame of the present invention.

本发明附图标记含义如下:1、上框架;2、下框架;3、止水钢板;4、网状模板面层;5、梳子模;101、上框架纵向横杆;102、上框架横向横杆;103、上框架立杆;104、上框架斜撑;201、下框架纵向横杆;202、下框架横向横杆;203、下框架立杆;204、下框架斜撑。The meanings of the reference numerals in the accompanying drawings of the present invention are as follows: 1. upper frame; 2. lower frame; 3. water-stop steel plate; 4. mesh formwork surface layer; 5. comb mold; 101. longitudinal cross bar of upper frame; 102. transverse cross bar of upper frame; 103. vertical pole of upper frame; 104. diagonal brace of upper frame; 201. longitudinal cross bar of lower frame; 202. transverse cross bar of lower frame; 203. vertical pole of lower frame; 204. diagonal brace of lower frame.

具体实施方式DETAILED DESCRIPTION

下面结合附图和具体实施方式对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

如图1-2所示,一种预制装配式钢筋框架筏板基础后浇带模板,包括多个首尾固定连接的长方体形钢筋框架模板单元,钢筋框架模板单元包括上框架1、下框架2以及设置在上框架1与下框架2之间的止水钢板3,止水钢板3为两根且分别焊接在上框架1长边侧面与下框架2长边侧面之间,上框架1的两个长边侧面以及下框架2的两个长边侧面上均设有网状模板面层4,网状模板面层4为钢板网与钢丝网的组合结构或快易收口网,封闭在上框架1的两个长边侧面以及下框架2的两个长边侧面的外表面,起到阻隔混凝土,确保后浇带按设计成型的作用,上框架1的两个长边侧面顶部分别固定有梳子模5,梳子模5包括枋木,枋木的底部均匀开有多条凹槽。As shown in Figures 1-2, a prefabricated assembled steel frame raft foundation post-cast strip formwork includes a plurality of rectangular steel frame formwork units fixedly connected end to end, the steel frame formwork units include an upper frame 1, a lower frame 2 and a waterstop steel plate 3 arranged between the upper frame 1 and the lower frame 2, there are two waterstop steel plates 3 and they are respectively welded between the long side surfaces of the upper frame 1 and the long side surfaces of the lower frame 2, mesh formwork surface layers 4 are provided on the two long side surfaces of the upper frame 1 and the two long side surfaces of the lower frame 2, the mesh formwork surface layers 4 are a combination structure of steel plate mesh and steel wire mesh or a quick-closing mesh, which is closed on the outer surfaces of the two long side surfaces of the upper frame 1 and the two long side surfaces of the lower frame 2, plays a role in blocking concrete and ensuring that the post-cast strip is formed as designed, comb molds 5 are respectively fixed to the tops of the two long side surfaces of the upper frame 1, the comb molds 5 include beams, and a plurality of grooves are evenly opened on the bottom of the beams.

如图3所示,上框架1的长边侧面包括平行设置的两根上框架纵向横杆101以及安装在两根上框架纵向横杆101之间的多根上框架立杆103,上框架1的两个长边侧面之间设有多组上框架连接杆构件,上框架连接杆构件为三组且分别设置在上框架1长边侧面的两端及中部,每组上框架连接杆构件包括两根上下平行设置的上框架横向横杆102,上框架连接杆构件的两根上框架横向横杆102之间设有相互交叉设置的两根上框架斜撑104。As shown in Figure 3, the long side of the upper frame 1 includes two upper frame longitudinal cross bars 101 arranged in parallel and multiple upper frame vertical bars 103 installed between the two upper frame longitudinal cross bars 101. Multiple groups of upper frame connecting rod components are arranged between the two long side surfaces of the upper frame 1. The upper frame connecting rod components are three groups and are respectively arranged at the two ends and the middle of the long side surfaces of the upper frame 1. Each group of upper frame connecting rod components includes two upper frame transverse cross bars 102 arranged in parallel up and down. Two upper frame diagonal braces 104 arranged crosswise with each other are arranged between the two upper frame transverse cross bars 102 of the upper frame connecting rod components.

如图4所示,下框架2的长边侧面包括平行设置的两根下框架纵向横杆201以及安装在两根下框架纵向横杆201之间的多根下框架立杆203,下框架2的两个长边侧面之间设有多组下框架连接杆构件,下框架连接杆构件为三组且分别设置在下框架2长边侧面的两端及中部,每组下框架连接杆构件包括两根上下平行设置的下框架横向横杆202,下框架连接杆构件的两根下框架横向横杆202之间设有相互交叉设置的两根下框架斜撑204。As shown in Figure 4, the long side of the lower frame 2 includes two lower frame longitudinal cross bars 201 arranged in parallel and multiple lower frame vertical bars 203 installed between the two lower frame longitudinal cross bars 201. Multiple groups of lower frame connecting rod components are arranged between the two long side surfaces of the lower frame 2. The lower frame connecting rod components are three groups and are respectively arranged at the two ends and the middle of the long side surfaces of the lower frame 2. Each group of lower frame connecting rod components includes two lower frame transverse cross bars 202 arranged in parallel up and down. Two lower frame diagonal braces 204 arranged crosswise with each other are arranged between the two lower frame transverse cross bars 202 of the lower frame connecting rod components.

使用该预制装配式钢筋框架筏板基础后浇带模板施工时包括以下步骤:The following steps are included in the construction of the prefabricated assembled steel frame raft foundation post-casting strip formwork:

A、施工准备:由施工技术人员依据筏板施工图纸详细计算后浇带各部位的尺寸,设计预制装配式钢筋框架筏板基础后浇带模板的尺寸,并绘制加工图纸,制作装配式钢筋框架筏板基础后浇带模板。A. Construction preparation: The construction technicians shall calculate the dimensions of each part of the post-casting strip in detail according to the raft construction drawings, design the dimensions of the prefabricated assembled steel frame raft foundation post-casting strip template, draw the processing drawings, and make the assembled steel frame raft foundation post-casting strip template.

B、施工放线:根据设计图纸放出后浇带的位置线。B. Construction layout: Lay out the position line of the post-cast joint according to the design drawings.

C、垫层、防水层、保护层施工:按进度计划要求组织垫层、防水层及保护层的施工,同时安装绑扎后浇带附加钢筋。C. Construction of cushion layer, waterproof layer and protective layer: Organize the construction of cushion layer, waterproof layer and protective layer according to the schedule requirements, and install and tie additional steel bars for post-cast joints at the same time.

D、组织筏板下层钢筋网安装绑扎:先从后浇带位置开始绑扎安装筏板下层钢筋,再向其他区域扩展。D. Organize the installation and binding of the lower layer of steel mesh of the raft slab: start from the position of the post-casting zone to bind and install the lower layer of steel bars of the raft slab, and then expand to other areas.

E、安装后浇带模板:后浇带位置的下层钢筋网绑扎安装完成后,立即进行后浇带模板的安装,由于后浇带模板采用了分段预制,采用塔吊将钢筋框架模板单元吊装到后浇带位置处,再采用电焊,将各钢筋框架模板单元焊接成为整体,同时将止水钢板3焊接贯通。E. Install the post-casting strip formwork: After the lower layer of steel mesh at the post-casting strip position is tied and installed, the post-casting strip formwork is installed immediately. Since the post-casting strip formwork is prefabricated in sections, a tower crane is used to lift the steel frame formwork unit to the post-casting strip position, and then electric welding is used to weld each steel frame formwork unit into a whole, and at the same time, the waterstop steel plate 3 is welded through.

F、整理网状模板面层:将各钢筋框架模板单元焊接成整体后,对网状模板面层4进行整理、封堵,尤其钢筋框架模板单元连接处和筏板下层钢筋的底下要封堵严密,将网状模板面层4向下延伸,与筏板垫层重合,再采用比筏板混凝土强度高一等级的细石混凝土进行封堵。F. Arrange the mesh formwork surface layer: After welding the steel frame formwork units into a whole, arrange and seal the mesh formwork surface layer 4, especially the joints of the steel frame formwork units and the bottom of the lower steel bars of the raft slab must be tightly sealed, extend the mesh formwork surface layer 4 downward to overlap with the raft slab cushion layer, and then use fine stone concrete with a strength one grade higher than that of the raft slab concrete for sealing.

G、绑扎筏板上层钢筋:筏板下层钢筋绑扎完成后,立即绑扎筏板上层钢筋网,此时装配式钢筋框架筏板基础后浇带模板可以作为筏板上层钢筋的支架,无须在此部位再单独设置支架。G. Binding of the upper steel bars of the raft slab: After the binding of the lower steel bars of the raft slab is completed, the upper steel mesh of the raft slab shall be immediately bound. At this time, the post-cast strip formwork of the assembled steel frame raft slab foundation can be used as a support for the upper steel bars of the raft slab, and there is no need to set up a separate support at this position.

H、安装梳子模:筏板上层钢筋网绑扎完成后,按照钢筋直径和钢筋间距大小将枋木的下部裁割成梳子形状制得梳子模5,安装在后浇带位置的上部,用于封堵筏板表层混凝土,梳子模5的高度应略大于筏板钢筋保护层的厚度。H. Install the comb mold: After the upper steel mesh of the raft slab is tied, cut the lower part of the beam into a comb shape according to the diameter of the steel bars and the spacing between the steel bars to make a comb mold 5, which is installed on the upper part of the post-casting zone to seal the surface concrete of the raft slab. The height of the comb mold 5 should be slightly larger than the thickness of the raft slab steel bar protective layer.

I、浇筑混凝土:筏板钢筋绑扎完成后,经各方验收合格后,即可浇筑混凝土。I. Pouring concrete: After the raft slab reinforcement is tied and accepted by all parties, concrete can be poured.

Claims (5)

1. The utility model provides a prefabricated assembled steel bar framework raft foundation post-cast strip template which characterized in that: including a plurality of cuboid reinforcing bar frame template units of end-to-end fixed connection, reinforcing bar frame template unit includes frame (1), underframe (2) and sets up sealing steel sheet (3) between frame (1) and underframe (2) in the top, sealing steel sheet (3) are two and fix respectively between frame (1) long limit side and underframe (2) long limit side in the top, all be equipped with netted template surface course (4) on two long limit sides of frame (1) and the two long limit sides of underframe (2), frame (1) two long limit side tops are fixed with comb submodule (5) respectively in the top, frame (1) long limit side includes parallel arrangement's two upper frame longitudinal cross bar (101) and installs many upper frame pole (103) between two upper frame longitudinal cross bar (101), be equipped with multiunit upper frame connecting rod member and every group upper frame connecting rod member and including two upper and lower parallel arrangement's upper frame transverse bar (102) between two long limit sides of upper frame (1), two upper frame longitudinal cross bar (201) are equipped with between two longitudinal cross bar (201) of two upper frame longitudinal cross bar (102), a plurality of groups of lower frame connecting rod members are arranged between two long side surfaces of the lower frame (2), each group of lower frame connecting rod members comprises two lower frame transverse cross rods (202) which are arranged in parallel up and down, and two lower frame diagonal braces (204) which are arranged in a mutually crossing manner are arranged between the two lower frame transverse cross rods (202) of the lower frame connecting rod members; the construction method comprises the following steps:
A. And (3) preparation of construction: calculating the size of each part of the post-cast strip in detail by construction technicians according to raft construction drawings, designing the size of a post-cast strip template of a prefabricated reinforced frame raft foundation, drawing processing drawings, and manufacturing the post-cast strip template of the prefabricated reinforced frame raft foundation;
B. And (3) construction paying-off: discharging a position line of the post-cast strip according to the design drawing;
C. And (3) cushion layer, waterproof layer and protective layer construction: organizing the construction of the cushion layer, the waterproof layer and the protective layer according to the schedule requirement, and simultaneously installing and binding additional steel bars of the post-pouring belt;
D. installing and binding a reinforcing mesh at the lower layer of the tissue raft plate: firstly binding and installing raft lower layer steel bars from the post-pouring belt position, and then expanding to other areas;
E. Installing a post-cast strip template: immediately installing a post-pouring strip template after binding and installing a lower layer reinforcing steel bar net at the post-pouring strip position, hoisting reinforcing steel bar frame template units to the post-pouring strip position by adopting a tower crane due to the adoption of segmented prefabrication, welding all reinforcing steel bar frame template units into a whole by adopting electric welding, and simultaneously welding a water stop steel plate (3) through;
F. Finishing a reticular template surface layer: after welding the reinforcing steel bar framework template units into a whole, arranging and plugging the net-shaped template surface layer (4), tightly plugging the joints of the reinforcing steel bar framework template units and the bottoms of the reinforcing steel bars at the lower layer of the raft, downwards extending the net-shaped template surface layer (4), overlapping with the raft cushion layer, and plugging by adopting fine stone concrete with a grade higher than the strength of the raft concrete;
G. Binding upper layer steel bars of the raft plates: immediately binding the upper layer steel bar net of the raft after the binding of the lower layer steel bars of the raft is completed, and taking the post-cast strip template of the raft foundation of the assembled steel bar frame as a bracket of the upper layer steel bars of the raft at the moment, wherein the bracket is not required to be arranged at the position separately;
H. Installing a comb sub-die: after binding of the upper layer reinforcing steel bar net of the raft, cutting the lower part of the balk wood into a comb shape according to the diameter of the reinforcing steel bars and the size of the spacing between the reinforcing steel bars to obtain comb dies (5), and installing the comb dies (5) at the upper part of the post-cast strip for plugging the surface layer concrete of the raft, wherein the height of the comb dies (5) is slightly larger than the thickness of the reinforcing steel bar protection layer of the raft;
I. Pouring concrete: and after the raft steel bars are bound, pouring concrete after being accepted by all parties.
2. The prefabricated rebar framework raft foundation post-cast strip template of claim 1, wherein: the upper frame connecting rod members are three groups and are respectively arranged at two ends and the middle of the long side surface of the upper frame (1).
3. The prefabricated rebar framework raft foundation post-cast strip template of claim 1, wherein: the lower frame connecting rod members are three groups and are respectively arranged at the two ends and the middle part of the long side surface of the lower frame (2).
4. The prefabricated rebar framework raft foundation post-cast strip template of claim 1, wherein: the reticular template surface layer (4) is a combined structure of a steel plate net and a steel wire net or a fast and easy closing net.
5. The prefabricated rebar framework raft foundation post-cast strip template of claim 1, wherein: the comb die (5) comprises wood beams, and a plurality of grooves are uniformly formed in the bottom of the wood beams.
CN201810127846.XA 2018-02-08 2018-02-08 Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof Active CN108130915B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810127846.XA CN108130915B (en) 2018-02-08 2018-02-08 Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810127846.XA CN108130915B (en) 2018-02-08 2018-02-08 Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof

Publications (2)

Publication Number Publication Date
CN108130915A CN108130915A (en) 2018-06-08
CN108130915B true CN108130915B (en) 2024-11-05

Family

ID=62430704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810127846.XA Active CN108130915B (en) 2018-02-08 2018-02-08 Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof

Country Status (1)

Country Link
CN (1) CN108130915B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820785B (en) * 2019-11-14 2021-06-11 中国建筑第八工程局有限公司 Shear assembly and construction method thereof
CN113833004A (en) * 2021-11-04 2021-12-24 中铁三局集团有限公司 Deep large raft foundation post-cast strip formwork system and foundation construction method
CN114673346B (en) * 2022-04-17 2023-04-18 南通新华建筑集团有限公司 Modular post-cast strip assembled side mold structure and construction method thereof
CN115233720A (en) * 2022-08-28 2022-10-25 中建八局第一建设有限公司 Super-thick radiation-proof raft plate L-shaped construction joint structure and construction method
CN117605279A (en) * 2023-12-28 2024-02-27 南通职业大学 A kind of construction method of basement floor post-cast belt prefabricated formwork

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649113A (en) * 2015-02-05 2016-06-08 中国建筑第四工程局有限公司 Structure and construction method of basement post-cast strip
CN207959244U (en) * 2018-02-08 2018-10-12 甘肃第七建设集团股份有限公司 Prefabricated assembling type reinforced frame raft foundation alter-pouring strips mould plate

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101109320B1 (en) * 2011-06-27 2012-02-08 주식회사 한양피씨 Concrete culvert box with easy installation on slope with on-site assembled anti-sedimentation structure and its construction method
CN102635128B (en) * 2012-04-27 2014-09-03 天津二十冶建设有限公司 Foundation slab post-cast strip waterproof steel plate combined structure and bracing method thereof
CN102720216A (en) * 2012-07-11 2012-10-10 南通市达欣工程股份有限公司 Foundation post-pouring belt template constructing method
CN203795479U (en) * 2014-05-05 2014-08-27 上海绿地建设(集团)有限公司 Raft post-pouring joint construction structure
CN105133663A (en) * 2015-09-18 2015-12-09 中铁十六局集团城市建设发展有限公司 Post-cast strip device and construction method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649113A (en) * 2015-02-05 2016-06-08 中国建筑第四工程局有限公司 Structure and construction method of basement post-cast strip
CN207959244U (en) * 2018-02-08 2018-10-12 甘肃第七建设集团股份有限公司 Prefabricated assembling type reinforced frame raft foundation alter-pouring strips mould plate

Also Published As

Publication number Publication date
CN108130915A (en) 2018-06-08

Similar Documents

Publication Publication Date Title
CN108130915B (en) Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof
CN105756252B9 (en) Prestressed concrete truss laminated slab and manufacturing method thereof
CN207878747U (en) A kind of laminated floor slab prefabricated board
CN108381746B (en) Construction method of prefabricated box girder with sliding pedestal
CN102251667B (en) Construction method for reinforced concrete arched roof of grain store
CN105484403B (en) Assembly concrete two-way ribbed slab floor and its method of construction
CN110512727B (en) A kind of prefabricated building lotus root beam pre-embedded insulation board post-tensioning method anchoring node structure and construction method
CN212358846U (en) A prefabricated concrete composite beam
CN110005109A (en) A kind of open flume type prestressed concrete overlapped slab
CN203440965U (en) Splicing structure of laminated floor slab
CN105863140A (en) Precast hollow floor's component for stress island based hollow floor system
CN109555252B (en) Floor slab with rectangular ribs extending outwards, shear wall structure and connecting method
CN208586815U (en) Beam form shell and exempt from template reinforced beam
CN207959244U (en) Prefabricated assembling type reinforced frame raft foundation alter-pouring strips mould plate
CN111691598B (en) Efficient processing of prefabricated coupling beams and node structures for composite shear walls
CN105696453A (en) Steel-concrete composite beam
CN204919605U (en) Prefabricated assembled reinforced concrete utility tunnel and production mould thereof
CN209760544U (en) Floor slab with overhanging rectangular ribs and shear wall structure
CN209227581U (en) Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure
CN209353550U (en) A kind of sandwich loss of weight superimposed sheet
CN109339244B (en) Prefabricated plate and shear wall connection structure and construction method
CN103321153A (en) Construction method for medium and small span trough girder bridge
CN207919891U (en) A kind of assembled partial precast part external wrapping concrete combination beam
CN206722216U (en) A kind of prefabricated girder of laminated floor slab
CN206554342U (en) A kind of bound edge prestressing force composite floor plate

Legal Events

Date Code Title Description