CN107931419A - One kind of multiple gauge material continuous stamping process - Google Patents

One kind of multiple gauge material continuous stamping process Download PDF

Info

Publication number
CN107931419A
CN107931419A CN201711155788.3A CN201711155788A CN107931419A CN 107931419 A CN107931419 A CN 107931419A CN 201711155788 A CN201711155788 A CN 201711155788A CN 107931419 A CN107931419 A CN 107931419A
Authority
CN
China
Prior art keywords
station
punching
product
product discharge
thick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711155788.3A
Other languages
Chinese (zh)
Inventor
王春生
贾志江
姚永奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Anjie Technology Co Ltd
Original Assignee
Suzhou Anjie Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Anjie Technology Co Ltd filed Critical Suzhou Anjie Technology Co Ltd
Priority to CN201711155788.3A priority Critical patent/CN107931419A/en
Publication of CN107931419A publication Critical patent/CN107931419A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D35/00Combined processes according to or processes combined with methods covered by groups B21D1/00 - B21D31/00
    • B21D35/001Shaping combined with punching, e.g. stamping and perforating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Perforating, Stamping-Out Or Severing By Means Other Than Cutting (AREA)

Abstract

The present invention provides one kind of multiple gauge material continuous stamping process, it is used for the punching press at the same time of multiple products, realizes that the disposable punching press of product obtains multiple products, so that production efficiency improves more than 3 times, safeguard that production background, ram efficiency improve, improve yield, reduce production cost.The first punching station, the second punching station, the first product discharge station, the second product discharge station, fracture station are provided between the upper die and lower die of mould, first punching station, the second punching station, the first product discharge station, the second product discharge station each station corresponding to material strip length it is identical, long banding pattern metal material belt is conveyed along the material delivery chute stepping formed between the upper die and lower die of mould, per walking into length be each station punching length, its pass through continuous punching formed two products.

Description

One kind of multiple gauge material continuous stamping process
Technical field
The present invention relates to the technical field of electronics BUSBAR punching presses, is specially one kind of multiple gauge material continuous punching works Skill.
Background technology
Electronics industry punching press is usually using either simplex sequence or continuous punch forming technology, traditional Mold Making technology, once Property can only the mutually same product of punching press or two, the punching press at the same time of multiple products can not realize disposable punching due to manufacture craft limitation For pressure, it is necessary to point more sets or either simplex skill punching press, punching press effect bottom, easy batch mixing, maintenance cost are big, take larger manpower, production cost Improve.
The content of the invention
In view of the above-mentioned problems, the present invention provides one kind of multiple gauge material continuous stamping process, it is same for multiple products When punching press, realize that the disposable punching press of product obtains multiple products so that production efficiency improve more than 3 times, safeguard production background, punching Press efficiency to improve, improve yield, reduce production cost.
One kind of multiple gauge material continuous stamping process, it is characterised in that:Is provided between the upper die and lower die of mould One punching station, the second punching station, the first product discharge station, the second product discharge station, fracture station, first punching Hole station, the second punching station, the first product discharge station, the second product discharge station each station corresponding to material strip Length is identical, long banding pattern metal material belt is conveyed along the material delivery chute stepping formed between the upper die and lower die of mould, often Walking into length be each station punching length, its pass through continuous punching formed two products.
It is further characterized by:
The first product is provided between second punching station and the first product discharge station and cuts the thick station of material, institute State to be provided with the second product between the first product discharge station and the second product discharge station and cut and expect thick station, first product is cut The thick station of material, the second product cut material strip corresponding to the thick station of material length and first punching station corresponding to material strip Length is identical;
First punching station, the second punching station, the first product cut the thick station of material, the first product discharge station, the Two products cut the thick station of material, the second product discharge station is preset with contraposition punch, and first punching station rushes on material strip Swaging carries out punching press into registration holes after aligning punch and the accurate contraposition of registration holes;
First punching station is used for the circular hole and registration holes for being stamped and formed out all products;
Second punching station is used for the irregularly-shaped hole for being stamped and formed out all products;
First product cuts the thick station of material and is used for the punching 70% at the outer contour of the first product corresponding to material strip Material is thick, easy to the smooth blanking of the first product discharge station;
Second product cuts the thick station of material and is used for the punching 70% at the outer contour of the second product corresponding to material strip Material is thick, easy to the smooth blanking of the second product discharge station;
The first product quantity included by each station is two, the quantity of the second product is two;
The lower die is respectively arranged with waste material receipts corresponding to the first punching station, the position directly below of the second punching station Header, the lower die are respectively arranged with corresponding to the first product discharge station, the position directly below of the second product discharge station First product collects magazine, the second product collects magazine, the rear of the mould, the exterior setting corresponding to the fracture station There is the 3rd scrap collecting tank.
After applying the present invention, using forcing press continuous cutting, at the same drive material strip stepping convey, due to upper die and lower die Between be provided with the first punching station, the second punching station, the first product discharge station, the second product discharge station, fracture work Position, first punching station, the second punching station, the first product discharge station, each station of the second product discharge station The length of corresponding material strip is identical, and long banding pattern metal material belt is conveyed along the material formed between the upper die and lower die of mould Groove stepping convey, per walking into length be each station punching length, its by continuous punching formed the first product, Second two kinds of product product, it is used for the punching press at the same time of multiple products, realizes that the disposable punching press of product obtains multiple products so that Production efficiency improves more than 3 times, safeguards that production background, ram efficiency improve, improves yield, reduce production cost.
Brief description of the drawings
Fig. 1 is that the station of the mould of this technique corresponds to the distribution schematic diagram of material strip;
Title in figure corresponding to sequence number is as follows:
First punching station 1, the second punching station 2, the first product discharge station 3, the second product discharge station 4, fracture Station 5, the first product cut the thick station 6 of material, the second product cuts the thick station 7 of material, registration holes 8, circular hole 9, irregularly-shaped hole 10, the first product 11st, the second product 12, material strip 13.
Embodiment
One kind of multiple gauge material continuous stamping process, are shown in Fig. 1:The first punching is provided between the upper die and lower die of mould Station 1, the second punching station 2, the first product discharge station 3, the second product discharge station 4, fracture station 5, the first punching work The 1, second punching station 2 of position, the first product discharge station 3, the second product discharge station 4 each station corresponding to material strip Length is identical, and long banding pattern metal material belt 13 is conveyed along the material delivery chute stepping formed between the upper die and lower die of mould, Per walking into length be each station punching length, its pass through continuous punching formed two products.
In specific embodiment:The first product is provided between second punching station 2 and the first product discharge station 3 and cuts material thickness Station 6, is provided with the second product and cuts the thick station 7 of material, the first production between the first product discharge station 3 and the second product discharge station 4 Product cut the thick station 5 of material, the second product cut material strip corresponding to the thick station 7 of material length and the first punching station 1 corresponding to material The length of band is identical;
First punching station 1, the second punching station 2, the first product cut the thick station 5 of material, the first product discharge station 3, the Two products cut the thick station 6 of material, the second product discharge station 4 is preset with contraposition punch, the first punching press on material strip of punching station 1 Registration holes 8 are formed, punching press is carried out after aligning punch and the accurate contraposition of registration holes 8;
First punching station 1 is used for the circular hole 9 and registration holes 8 for being stamped and formed out all products;
Second punching station 2 is used for the irregularly-shaped hole 10 for being stamped and formed out all products;
First product cuts the material that the thick station 5 of material is used for the punching 70% at the outer contour of the first product 11 corresponding to material strip Thickness, easy to the smooth blanking of the first product discharge station 3;
Second product cuts the material that the thick station 6 of material is used for the punching 70% at the outer contour of the second product 12 corresponding to material strip Thickness, easy to the smooth blanking of the second product discharge station 4;
11 quantity of the first product included by each station is two, the quantity of the second product 12 is two;
Lower die is respectively arranged with garbage collection corresponding to the first punching station 1, the position directly below of the second punching station 2 Case, lower die are respectively arranged with first corresponding to the first product discharge station 3, the position directly below of the second product discharge station 4 Product collects magazine, the second product collects magazine, and the rear of mould, the outside corresponding to fracture station 5 are provided with the 3rd waste material Collecting box.
Its operation principle is as follows:Using forcing press continuous cutting, at the same drive material strip stepping convey, due to upper mold and under The first punching station, the second punching station, the first product discharge station, the second product discharge station, fracture are provided between mould Station, the first punching station, the second punching station, the first product discharge station, each station institute of the second product discharge station The length of corresponding material strip is identical, by long banding pattern metal material belt along the material delivery chute formed between the upper die and lower die of mould Stepping conveys, per walking into length be each station punching length, it forms the first product, the by continuous punching Two two kinds of product products.
The specific embodiment of the present invention is described in detail above, but content is only the preferable implementation of the invention Example, it is impossible to be construed as limiting the practical range of the invention.All impartial changes made according to the invention application range Change and improvement etc., should all still belong within this patent covering scope.

Claims (9)

1. one kind of multiple gauge material continuous stamping process, it is characterised in that:First is provided between the upper die and lower die of mould Punching station, the second punching station, the first product discharge station, the second product discharge station, fracture station, first punching Station, the second punching station, the first product discharge station, the second product discharge station each station corresponding to material strip length Spend identical, long banding pattern metal material belt is conveyed along the material delivery chute stepping that is formed between the upper die and lower die of mould, is often walked The length of traveling is the punching length of each station, it forms two products by continuous punching.
2. one kind of multiple gauge material continuous stamping process as claimed in claim 1, it is characterised in that:The second punching work The first product is provided between position and the first product discharge station and cuts the thick station of material, the first product discharge station and the The second product is provided between two product discharge stations and cuts the thick station of material, first product cuts the thick station of material, the second product cuts material The length of material strip corresponding to thick station is identical with the length of the material strip corresponding to first punching station.
3. one kind of multiple gauge material continuous stamping process as claimed in claim 2, it is characterised in that:The first punching work Position, the second punching station, the first product cut the thick station of material, the first product discharge station, the second product and cut the thick station of material, the second production Product discharge station is preset with contraposition punch, and first punching station is stamped and formed out registration holes on material strip, contraposition punch and Registration holes carry out punching press after precisely aligning.
4. one kind of multiple gauge material continuous stamping process as claimed in claim 1, it is characterised in that:The first punching work Position is used for the circular hole and registration holes for being stamped and formed out all products.
5. one kind of multiple gauge material continuous stamping process as claimed in claim 1, it is characterised in that:The second punching work Position is used for the irregularly-shaped hole for being stamped and formed out all products.
6. one kind of multiple gauge material continuous stamping process as claimed in claim 2, it is characterised in that:First product is cut The material that the thick station of material is used for the punching 70% at the outer contour of the first product corresponding to material strip is thick, easy to the first product blankers The smooth blanking of position.
7. one kind of multiple gauge material continuous stamping process as claimed in claim 2, it is characterised in that:Second product is cut The material that the thick station of material is used for the punching 70% at the outer contour of the second product corresponding to material strip is thick, easy to the second product blankers The smooth blanking of position.
8. one kind of multiple gauge material continuous stamping process as claimed in claim 1 or 2, it is characterised in that:Each station institute Including the first product quantity be two, the quantity of the second product be two.
9. one kind of multiple gauge material continuous stamping process as claimed in claim 1 or 2, it is characterised in that:The lower die Scrap collecting tank, pair of the lower die are respectively arranged with corresponding to the position directly below of the first punching station, the second punching station Should in the position directly below of the first product discharge station, the second product discharge station be respectively arranged with the first product collect magazine, Second product collects magazine, and the rear of the mould, the outside corresponding to the fracture station are provided with the 3rd scrap collecting tank.
CN201711155788.3A 2017-11-20 2017-11-20 One kind of multiple gauge material continuous stamping process Pending CN107931419A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711155788.3A CN107931419A (en) 2017-11-20 2017-11-20 One kind of multiple gauge material continuous stamping process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711155788.3A CN107931419A (en) 2017-11-20 2017-11-20 One kind of multiple gauge material continuous stamping process

Publications (1)

Publication Number Publication Date
CN107931419A true CN107931419A (en) 2018-04-20

Family

ID=61929191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711155788.3A Pending CN107931419A (en) 2017-11-20 2017-11-20 One kind of multiple gauge material continuous stamping process

Country Status (1)

Country Link
CN (1) CN107931419A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112427566A (en) * 2020-10-30 2021-03-02 苏州斯穹精密科技有限公司 Low damage car aluminium core pencil bender of high accuracy
CN112916725A (en) * 2019-12-05 2021-06-08 观致汽车有限公司 Blanking process for anti-collision beam material belt of battery pack
CN115532943A (en) * 2022-11-24 2022-12-30 苏州铭峰精密机械有限公司 Forming method of product with large length-width ratio and forming die with shortened length
CN116099941A (en) * 2022-12-15 2023-05-12 安徽大昌科技股份有限公司 A die applied in the stamping process of automobile sheet metal parts
CN120502625A (en) * 2025-07-18 2025-08-19 江苏南方精工股份有限公司 Product stamping method and die
CN120715089A (en) * 2025-08-14 2025-09-30 珠海嘉程科技有限公司 Stamping equipment with multiple stamping positions

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202278088U (en) * 2011-10-09 2012-06-20 江阴华新电器有限公司 Pre-blanking device for stamping
CN203565674U (en) * 2013-11-27 2014-04-30 张家港市锦力标准件制造有限公司 Continuous punching mold for construction connecting piece
CN204429986U (en) * 2014-12-31 2015-07-01 上海诚烨汽车零部件有限公司 A kind of part continuous seepage mould
CN105195613A (en) * 2015-09-30 2015-12-30 四川腾邦摩托车配件有限公司 Progressive punching die used for machining eight-level stator iron core and small skeleton iron core
CN105436303A (en) * 2016-01-07 2016-03-30 安徽江淮汽车股份有限公司 One-die and multi-part stamping die and process
CN106040868A (en) * 2016-07-27 2016-10-26 武汉华夏精冲技术有限公司 Multi-part stamping-pressing forming die

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202278088U (en) * 2011-10-09 2012-06-20 江阴华新电器有限公司 Pre-blanking device for stamping
CN203565674U (en) * 2013-11-27 2014-04-30 张家港市锦力标准件制造有限公司 Continuous punching mold for construction connecting piece
CN204429986U (en) * 2014-12-31 2015-07-01 上海诚烨汽车零部件有限公司 A kind of part continuous seepage mould
CN105195613A (en) * 2015-09-30 2015-12-30 四川腾邦摩托车配件有限公司 Progressive punching die used for machining eight-level stator iron core and small skeleton iron core
CN105436303A (en) * 2016-01-07 2016-03-30 安徽江淮汽车股份有限公司 One-die and multi-part stamping die and process
CN106040868A (en) * 2016-07-27 2016-10-26 武汉华夏精冲技术有限公司 Multi-part stamping-pressing forming die

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112916725A (en) * 2019-12-05 2021-06-08 观致汽车有限公司 Blanking process for anti-collision beam material belt of battery pack
CN112427566A (en) * 2020-10-30 2021-03-02 苏州斯穹精密科技有限公司 Low damage car aluminium core pencil bender of high accuracy
CN115532943A (en) * 2022-11-24 2022-12-30 苏州铭峰精密机械有限公司 Forming method of product with large length-width ratio and forming die with shortened length
CN116099941A (en) * 2022-12-15 2023-05-12 安徽大昌科技股份有限公司 A die applied in the stamping process of automobile sheet metal parts
CN120502625A (en) * 2025-07-18 2025-08-19 江苏南方精工股份有限公司 Product stamping method and die
CN120715089A (en) * 2025-08-14 2025-09-30 珠海嘉程科技有限公司 Stamping equipment with multiple stamping positions

Similar Documents

Publication Publication Date Title
CN107931419A (en) One kind of multiple gauge material continuous stamping process
CN209597991U (en) A kind of double material strips intersection stamping riveting equipment
CN104785639B (en) A kind of automobile rear backrest left plate progressive die
CN204093949U (en) One Seed packaged band continuous seepage mould
CN103286200A (en) Brake shoe bending plate continuous die and method for using continuous die to machine brake shoe bending plate
CN206316204U (en) A kind of stamping parts production mechanism of use progressive die
CN207057387U (en) A kind of secondary punching metal plate punching mould
CN202318439U (en) Film-overlaying, punching and pressing integrated device
CN104588476B (en) The single-station composite precision die tool of processing vehicle synchronous taper ring gear and method thereof
CN204338727U (en) Stainless steel coated precise punching die
CN205309107U (en) Realize product design mould inner chamfering's mould that upgrades
CN107774803A (en) A kind of progressive die
CN203265404U (en) Progressive die applicable to material tail stamping
CN107159957A (en) A kind of plate shearing machine
CN106180464A (en) The technique that a kind of whole raw material punching press carries out filling out lid
CN217528882U (en) Tableware punch forming machine tool
CN205380192U (en) Blanking and punching progressive die
CN202447482U (en) Waste discharging mechanism of plate type discharging die
CN205818530U (en) There is the middle side sealing bag machine of fixed point thermoprint mechanism
CN205889381U (en) Semi -manufactured goods separation paper collecting device of concora crush flat -die cutter
CN106216506B (en) For producing the progressive die of automobile inserted sheet
CN204974888U (en) Hinge page or leaf piece position of axle mould processing machinery
CN104971981B (en) Automatic transport die punching machine for the shaping of keel sheet metal
CN210023448U (en) Progressive die iron piece die of communication equipment mounting plate
CN102632368A (en) Press line automatic tapping process and processing system thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420

RJ01 Rejection of invention patent application after publication