CN107830804B - Battery cell overall dimension detection system and battery cell OCV test equipment thereof - Google Patents

Battery cell overall dimension detection system and battery cell OCV test equipment thereof Download PDF

Info

Publication number
CN107830804B
CN107830804B CN201711331195.8A CN201711331195A CN107830804B CN 107830804 B CN107830804 B CN 107830804B CN 201711331195 A CN201711331195 A CN 201711331195A CN 107830804 B CN107830804 B CN 107830804B
Authority
CN
China
Prior art keywords
cell
detection
horizontal
adjustment
battery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711331195.8A
Other languages
Chinese (zh)
Other versions
CN107830804A (en
Inventor
殷火初
黄皓
李斌
王世峰
刘金成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou Jinyuan Precision Automation Equipment Co Ltd
Original Assignee
Huizhou Jinyuan Precision Automation Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huizhou Jinyuan Precision Automation Equipment Co Ltd filed Critical Huizhou Jinyuan Precision Automation Equipment Co Ltd
Priority to CN201711331195.8A priority Critical patent/CN107830804B/en
Publication of CN107830804A publication Critical patent/CN107830804A/en
Application granted granted Critical
Publication of CN107830804B publication Critical patent/CN107830804B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • G—PHYSICS
    • G01—MEASURING; TESTING
    • G01B—MEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00—Measuring arrangements characterised by the use of optical techniques
    • G—PHYSICS
    • G01—MEASURING; TESTING
    • G01B—MEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00—Measuring arrangements characterised by the use of optical techniques
    • G01B11/02—Measuring arrangements characterised by the use of optical techniques for measuring length, width or thickness
    • G01B11/022—Measuring arrangements characterised by the use of optical techniques for measuring length, width or thickness by means of tv-camera scanning

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Secondary Cells (AREA)
  • Battery Mounting, Suspending (AREA)

Abstract

The invention discloses a battery cell overall dimension detection system and battery cell OCV test equipment thereof. Wherein, electric core overall dimension detecting system includes: overall dimension detects positioning seat, CCD detection device, overall dimension detects auxiliary device. The overall dimension detection auxiliary device includes: width auxiliary detection structure, length auxiliary detection structure. The width auxiliary detection structure comprises: the width detection driving part, the width detection left side fixture and the width detection right side fixture; the length auxiliary detection structure comprises: a length detection driving part and a length detection positioning block. According to the battery cell overall dimension detection system, the overall dimension detection positioning seat, the CCD detection device and the overall dimension detection auxiliary device are arranged, and particularly the structure of the overall dimension detection auxiliary device is optimally designed, so that the edge of the battery cell is captured better, the actual dimension of the battery cell is calculated more accurately, and the mechanical automation level of the whole equipment is improved.

Description

电芯外形尺寸检测系统及其电芯OCV测试设备Cell Outline Dimension Testing System and Cell OCV Testing Equipment

技术领域technical field

本发明涉及电芯机械自动化生产技术领域,特别是涉及一种电芯外形尺寸检测系统及其电芯OCV测试设备。The invention relates to the technical field of mechanical automatic production of battery cells, in particular to a battery core external dimension detection system and its battery core OCV testing equipment.

背景技术Background technique

随着社会不断发展和科技不断进步,机械自动化生产已经成为发展趋势,并逐渐代替传统的手工劳动,为企业可持续发展注入新的动力源。因此,电池生产制造企业也需要与时俱进,通过转型升级,积极推进技术改造,大力发展机械自动化生产,从而提高企业的“智造”水平,实现企业的可持续发展。With the continuous development of society and the continuous progress of science and technology, mechanical automation production has become a development trend, and gradually replaces traditional manual labor, injecting a new source of power for the sustainable development of enterprises. Therefore, battery manufacturing enterprises also need to keep pace with the times, actively promote technological transformation through transformation and upgrading, and vigorously develop mechanical automation production, so as to improve the "intelligent manufacturing" level of enterprises and achieve sustainable development of enterprises.

在实际的生产过程中,电芯经过OCV测试后,还需要对电芯的尺寸大小进行检测。通常,行业内会采用CCD的形式对电芯进行拍照式检测,从而判断电芯的尺寸是否符合要求。然而,只有让CCD更好的捕捉到电芯的边缘,才能够更加准确的计算出电芯的实际尺寸大小。因此,如何设计一套电芯外形尺寸检测系统,更好的捕捉到电芯的边缘,从而更加准确的计算出电芯的实际尺寸大小,进而提高设备整体的机械自动化水平,这是企业的研发人员需要解决的技术问题。In the actual production process, after the cells are tested by OCV, the size of the cells needs to be checked. Usually, the industry will use the form of CCD to carry out photographic inspection of the cell, so as to determine whether the size of the cell meets the requirements. However, only by allowing the CCD to better capture the edge of the cell, the actual size of the cell can be calculated more accurately. Therefore, how to design a cell size detection system to better capture the edge of the cell, so as to more accurately calculate the actual size of the cell, and then improve the overall mechanical automation level of the equipment, this is the research and development of the enterprise Technical issues that people need to solve.

发明内容SUMMARY OF THE INVENTION

本发明的目的是克服现有技术中的不足之处,提供一种电芯外形尺寸检测系统及其电芯OCV测试设备,更好的捕捉到电芯的边缘,从而更加准确的计算出电芯的实际尺寸大小,进而提高设备整体的机械自动化水平。The purpose of the present invention is to overcome the deficiencies in the prior art, and to provide a cell size detection system and its cell OCV testing equipment, which can better capture the edge of the cell, so as to more accurately calculate the cell The actual size of the equipment, thereby improving the overall mechanical automation level of the equipment.

本发明的目的是通过以下技术方案来实现的:The purpose of this invention is to realize through the following technical solutions:

一种电芯外形尺寸检测系统,包括:外形尺寸检测定位座、CCD检测装置、外形尺寸检测辅助装置;An external dimension detection system of a battery cell, comprising: an external dimension detection positioning seat, a CCD detection device, and an external dimension detection auxiliary device;

所述CCD检测装置用于对电芯的外形尺寸进行拍照检测;The CCD detection device is used for photographing and detecting the external dimension of the battery cell;

所述外形尺寸检测辅助装置包括:宽度辅助检测结构、长度辅助检测结构。The external dimension detection auxiliary device includes: a width auxiliary detection structure and a length auxiliary detection structure.

所述宽度辅助检测结构包括:宽度检测驱动部、宽度检测左侧卡具、宽度检测右侧卡具,所述宽度检测驱动部驱动所述宽度检测左侧卡具及所述宽度检测右侧卡具沿所述外形尺寸检测定位座水平横向相互靠近或远离;The width auxiliary detection structure includes: a width detection drive part, a width detection left clamp, and a width detection right clamp, and the width detection drive part drives the width detection left clamp and the width detection right clamp The positioning seats are horizontally and laterally approached or separated from each other along the outer dimension detection positioning seat;

所述长度辅助检测结构包括:长度检测驱动部、长度检测定位块,所述长度检测驱动部驱动所述长度检测定位块沿水平纵向伸缩以靠近或远离所述外形尺寸检测定位座。The length auxiliary detection structure includes: a length detection driving part and a length detection positioning block, the length detection driving part drives the length detection positioning block to expand and contract along the horizontal and longitudinal directions to approach or move away from the outer dimension detection positioning seat.

在其中一个实施例中,所述宽度检测右侧卡具上设有弹性缓冲件In one of the embodiments, an elastic buffer is provided on the width detection right clamp

在其中一个实施例中,所述弹性缓冲件为弹簧结构。In one of the embodiments, the elastic buffer member is a spring structure.

在其中一个实施例中,所述宽度检测驱动部包括宽度检测驱动电机及设于所述宽度检测驱动电机输出端的宽度检测调节丝杆,所述宽度检测左侧卡具及所述宽度检测右侧卡具螺合于所述宽度检测调节丝杆上。In one embodiment, the width detection drive part includes a width detection drive motor and a width detection adjustment screw disposed at the output end of the width detection drive motor, the width detection left clamp and the width detection right side The clamp is screwed on the width detection and adjustment screw.

在其中一个实施例中,所述长度检测驱动部为电机丝杆驱动结构。In one embodiment, the length detection driving part is a motor lead screw driving structure.

在其中一个实施例中,所述长度检测定位块为橡胶块结构。In one embodiment, the length detection positioning block is a rubber block structure.

一种电芯OCV测试设备,包括上述的电芯外形尺寸检测系统,还包括电芯OCV测试系统,所述电芯OCV测试系统用于对电芯的电压进行测试。A battery cell OCV testing device includes the above-mentioned battery cell external dimension detection system, and a battery cell OCV testing system, which is used to test the voltage of the battery cell.

本发明的电芯外形尺寸检测系统,通过设置外形尺寸检测定位座、CCD检测装置、外形尺寸检测辅助装置,特别是对外形尺寸检测辅助装置的结构进行优化设计,更好的捕捉到电芯的边缘,从而更加准确的计算出电芯的实际尺寸大小,进而提高设备整体的机械自动化水平。The battery outer dimension detection system of the present invention can better capture the battery cell by setting the outer dimension detection positioning seat, the CCD detection device and the outer dimension detection auxiliary device, especially the structure of the outer dimension detection auxiliary device is optimized. edge, so as to more accurately calculate the actual size of the cell, thereby improving the overall mechanical automation level of the equipment.

附图说明Description of drawings

图1为本发明一实施例的电芯OCV测试设备的结构图;1 is a structural diagram of a battery cell OCV testing device according to an embodiment of the present invention;

图2为图1所示的电芯OCV测试设备的电芯上料系统的结构图;FIG. 2 is a structural diagram of a cell feeding system of the cell OCV testing equipment shown in FIG. 1;

图3为图2所示的电芯上料系统的局部图;Fig. 3 is a partial view of the cell feeding system shown in Fig. 2;

图4为图1所示的电芯OCV测试设备的电芯调整定位系统的结构图;FIG. 4 is a structural diagram of a cell adjustment and positioning system of the cell OCV test equipment shown in FIG. 1;

图5为图1所示的电芯OCV测试设备的电芯中转系统的结构图;FIG. 5 is a structural diagram of the cell transfer system of the cell OCV test equipment shown in FIG. 1;

图6为图5所示的电芯中转系统的局部图;FIG. 6 is a partial view of the cell transfer system shown in FIG. 5;

图7为图1所示的电芯OCV测试设备的电芯极耳整形系统的结构图;FIG. 7 is a structural diagram of the cell ear shaping system of the cell OCV test equipment shown in FIG. 1;

图8为图1所示的电芯OCV测试设备的电芯外形尺寸检测系统的结构图;FIG. 8 is a structural diagram of a cell outer dimension detection system of the cell OCV testing equipment shown in FIG. 1;

图9为图1所示的电芯OCV测试设备的工件厚度检测系统的结构图。FIG. 9 is a structural diagram of a workpiece thickness detection system of the cell OCV testing equipment shown in FIG. 1 .

具体实施方式Detailed ways

为了便于理解本发明,下面将参照相关附图对本发明进行更全面的描述。附图中给出了本发明的较佳实施方式。但是,本发明可以以许多不同的形式来实现,并不限于本文所描述的实施方式。相反地,提供这些实施方式的目的是使对本发明的公开内容理解的更加透彻全面。In order to facilitate understanding of the present invention, the present invention will be described more fully hereinafter with reference to the related drawings. The preferred embodiments of the invention are shown in the accompanying drawings. However, the present invention may be embodied in many different forms and is not limited to the embodiments described herein. Rather, these embodiments are provided so that a thorough and complete understanding of the present disclosure is provided.

需要说明的是,当元件被称为“固定于”另一个元件,它可以直接在另一个元件上或者也可以存在居中的元件。当一个元件被认为是“连接”另一个元件,它可以是直接连接到另一个元件或者可能同时存在居中元件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的,并不表示是唯一的实施方式。It should be noted that when an element is referred to as being "fixed to" another element, it can be directly on the other element or intervening elements may also be present. When an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for the purpose of illustration only and do not represent the only embodiment.

除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施方式的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terms used herein in the description of the present invention are for the purpose of describing specific embodiments only, and are not intended to limit the present invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.

如图1所示,一种电芯OCV测试设备10,用于对电芯进行OCV测试,包括:电芯上料系统1000、电芯调整定位系统2000、电芯中转系统3000、电芯极耳整形系统4000、电芯扫码系统5000、电芯OCV测试系统6000、电芯外形尺寸检测系统7000、工件厚度检测系统8000、电芯分档收料系统9000。电芯依次经过电芯上料系统1000、电芯调整定位系统2000、电芯极耳整形系统4000、电芯扫码系统5000、电芯OCV测试系统6000、电芯外形尺寸检测系统7000、工件厚度检测系统8000、电芯分档收料系统9000,电芯中转系统3000用于对电芯调整定位系统2000中的电芯进行转移,并依次经过电芯极耳整形系统4000、电芯扫码系统5000、电芯OCV测试系统6000、电芯外形尺寸检测系统7000、工件厚度检测系统8000。As shown in FIG. 1 , a battery cell OCV testing device 10 is used for OCV testing of battery cells, including: a battery cell feeding system 1000 , a battery cell adjustment and positioning system 2000 , a battery cell transfer system 3000 , and a battery cell electrode lug Shaping system 4000, cell code scanning system 5000, cell OCV testing system 6000, cell size detection system 7000, workpiece thickness detection system 8000, cell grading and receiving system 9000. The cells pass through the cell feeding system 1000, the cell adjusting and positioning system 2000, the cell tab shaping system 4000, the cell scanning code system 5000, the cell OCV testing system 6000, the cell external dimension detection system 7000, and the workpiece thickness. The detection system 8000, the cell grading and receiving system 9000, and the cell transfer system 3000 are used to transfer the cells in the cell adjustment and positioning system 2000, and pass through the cell ear shaping system 4000 and the cell code scanning system in turn. 5000, battery cell OCV test system 6000, battery core dimension detection system 7000, workpiece thickness detection system 8000.

电芯上料系统1000用于将待测试的电芯上料于电芯调整定位系统2000中;电芯调整定位系统2000用于对待测试的电芯进行调整定位,保证电芯的一致性,提高后续测试工序的准确性和可靠性;电芯中转系统3000用于对电芯调整定位系统2000中的电芯进行转移,并依次经过电芯极耳整形系统4000、电芯扫码系统5000、电芯OCV测试系统6000、电芯外形尺寸检测系统7000、工件厚度检测系统8000,进行相应工序的加工;电芯极耳整形系统4000用于对待测试的电芯的极耳进行整形,将极耳捋平整,保证后续测试工位的可靠性;电芯扫码系统5000用于对电芯表面的条码进行扫描,记录当前电芯的信息,并将信息传送至控制中心;电芯OCV测试系统6000用于对电芯的电压进行测试;电芯外形尺寸检测系统7000用于对电芯的外形尺寸进行检测;工件厚度检测系统8000用于对电芯的厚度进行检测;电芯分档收料系统9000用于对完成相关测试的电芯进行分类式收料。The cell feeding system 1000 is used to load the cells to be tested in the cell adjustment and positioning system 2000; the cell adjustment and positioning system 2000 is used to adjust and position the cells to be tested, to ensure the consistency of the cells, and to improve the The accuracy and reliability of the subsequent testing process; the cell transfer system 3000 is used to transfer the cells in the cell adjustment and positioning system 2000, and sequentially passes through the cell tab shaping system 4000, the cell code scanning system 5000, the battery cell The core OCV testing system 6000, the battery core dimension detection system 7000, and the workpiece thickness detection system 8000 are used to process the corresponding processes; the battery core tab shaping system 4000 is used for shaping the tabs of the cells to be tested, and the tabs are drawn. Flat to ensure the reliability of subsequent test stations; the cell code scanning system 5000 is used to scan the barcode on the surface of the cell, record the current cell information, and transmit the information to the control center; the cell OCV test system 6000 is used for It is used to test the voltage of the battery cell; the battery core dimension detection system 7000 is used to detect the outer shape dimension of the battery core; the workpiece thickness detection system 8000 is used to detect the thickness of the battery core; the battery core classification and receiving system 9000 It is used for sorting and receiving the cells that have completed the relevant tests.

进一步的,本发明还提供一种电芯OCV测试方法,包括如下步骤:Further, the present invention also provides a battery cell OCV testing method, comprising the following steps:

电芯上料系统将电芯上料于电芯调整定位系统中;The cell feeding system feeds the cells into the cell adjustment and positioning system;

电芯调整定位系统对电芯进行调整定位;The cell adjustment and positioning system adjusts and positions the cell;

电芯中转系统对电芯调整定位系统中的电芯进行转移,并依次经过电芯极耳整形系统、电芯扫码系统、电芯OCV测试系统、电芯外形尺寸检测系统、工件厚度检测系统;The cell transfer system transfers the cells in the cell adjustment and positioning system, and passes through the cell tab shaping system, cell code scanning system, cell OCV test system, cell size detection system, and workpiece thickness detection system in turn. ;

电芯极耳整形系统对电芯的极耳进行整形,将极耳捋平整;The cell tab shaping system reshapes the tab of the cell and smoothes the tab;

电芯扫码系统对电芯表面的条码进行扫描,记录当前电芯的信息;The cell code scanning system scans the barcode on the surface of the cell and records the current cell information;

电芯OCV测试系统对电芯的电压进行测试;The cell OCV test system tests the voltage of the cell;

电芯外形尺寸检测系统对电芯的外形尺寸进行检测;The external dimension detection system of the cell detects the external dimension of the cell;

工件厚度检测系统对电芯的厚度进行检测;The workpiece thickness detection system detects the thickness of the cell;

电芯分档收料系统对完成测试的电芯进行分类式收料。The battery cell grading and material receiving system performs classified material collection for the battery cells that have completed the test.

如图2及图3所示,下面,对电芯上料系统1000的具体结构进行说明:As shown in FIG. 2 and FIG. 3 , the specific structure of the cell feeding system 1000 is described below:

电芯上料系统1000包括:电芯料盘移送机械手1100、储料装置1200;The battery cell feeding system 1000 includes: a battery cell material tray transfer robot 1100 and a material storage device 1200;

电芯料盘移送机械手1100包括:电芯料盘移送抓手1110及驱动电芯料盘移送抓手1110运动的电芯料盘移送模块1120;电芯料盘移送抓手1110包括:电芯料盘移送基座1111、设于电芯料盘移送基座1111上的电芯移送吸嘴1112、设于电芯料盘移送基座1111上的料盘移送吸嘴1113;The battery cell material tray transfer robot 1100 includes: a battery cell material tray transfer gripper 1110 and a battery cell material tray transfer module 1120 that drives the cell material tray transfer gripper 1110 to move; the battery cell material tray transfer gripper 1110 includes: battery cell material a disk transfer base 1111, a cell transfer suction nozzle 1112 set on the battery cell tray transfer base 1111, and a tray transfer suction nozzle 1113 set on the battery cell tray transfer base 1111;

储料装置1200包括:电芯料盘放置仓1210、料盘升降动力部1220、料盘托板1230,料盘托板1230收容于电芯料盘放置仓1210内,料盘升降动力部1220驱动料盘托板1230往复升降。The storage device 1200 includes: a battery cell tray placement bin 1210, a tray lift power unit 1220, and a tray tray 1230. The tray tray 1230 is accommodated in the battery cell tray placement bin 1210, and the tray lift power unit 1220 drives The tray tray 1230 reciprocates up and down.

电芯上料系统1000的工作原理如下:The working principle of the cell feeding system 1000 is as follows:

料盘内放置有待上料的电芯,多个料盘依次层叠并放置于电芯料盘放置仓1210内的料盘托板1230上;Cells to be loaded are placed in the tray, and a plurality of trays are stacked in sequence and placed on the tray tray 1230 in the cell tray placement bin 1210;

电芯料盘移送机械手1100工作,电芯料盘移送模块1120驱动电芯料盘移送抓手1110运动,并通过电芯移送吸嘴1112将最顶层料盘的电芯吸取,移送至下一工位的电芯调整定位系统2000中;The cell tray transfer manipulator 1100 works, the cell tray transfer module 1120 drives the cell tray transfer gripper 1110 to move, and sucks the cells on the top tray through the cell transfer nozzle 1112, and transfers them to the next process Positioning system 2000 for cell adjustment and positioning;

当最顶层的料盘中的电芯被全部取走后,最顶层的料盘为空料盘,电芯料盘移送模块1120驱动电芯料盘移送抓手1110运动,并通过料盘移送吸嘴1113将最顶层的料盘吸取,将空料盘从电芯料盘放置仓1210内取走;When all the cells in the topmost tray are taken away, the topmost tray is an empty tray, and the cell tray transfer module 1120 drives the cell tray transfer gripper 1110 to move, and transfers the suction tray through the tray. The nozzle 1113 sucks the topmost tray, and takes the empty tray from the cell tray placement bin 1210;

紧接着,料盘升降动力部1220驱动料盘托板1230上升一个高度,以使得目前处于最顶层的料盘到达指定位置,为下一次的电芯上料作好准备;Next, the tray lifting power unit 1220 drives the tray support plate 1230 to rise a height, so that the tray currently on the top layer reaches the designated position, and is ready for the next battery cell feeding;

通过将电芯移送吸嘴1112及料盘移送吸嘴1113集成于电芯料盘移送基座1111上,将电芯和料盘的移送结构合成一体,实用性强。By integrating the cell transfer nozzle 1112 and the tray transfer nozzle 1113 on the cell tray transfer base 1111 , the transfer structure of the cell and tray is integrated, and the practicability is strong.

要说明的是,电芯料盘放置仓1210内设置有料盘到位感应器1211。料盘到位感应器1211用于感应处于最顶层的料盘在料盘升降动力部1220的作用下是否到达指定位置,当最顶层的料盘到达指定高度后,料盘到位感应器1211发出感应信号,使得料盘升降动力部1220停止动作。在本实施例中,料盘升降动力部1220为电机丝杆驱动结构。It should be noted that the cell tray placement bin 1210 is provided with a tray position sensor 1211 . The tray position sensor 1211 is used to sense whether the tray at the top layer has reached the designated position under the action of the tray lifting power unit 1220. When the tray at the top layer reaches the designated height, the tray position sensor 1211 will send a sensing signal. , so that the tray lifting power part 1220 stops moving. In this embodiment, the material tray lifting power part 1220 is a motor screw driving structure.

进一步的,电芯移送吸嘴1112的数量为四个,四个电芯移送吸嘴1112呈矩形阵列分布于电芯料盘移送基座1111上。电芯料盘移送抓手1110还包括电芯移送气缸1114,电芯移送吸嘴1112设于电芯移送气缸1114的伸缩端。当需要对电芯进行移送时,电芯移送气缸1114驱动电芯移送吸嘴1112伸出,以使得电芯移送吸嘴1112凸出于料盘移送吸嘴1113,方便电芯移送吸嘴1112对料盘上的电芯进行吸取,同时也方便电芯移送吸嘴1112将电芯转移至下一工位;当需要对料盘进行移送时,电芯移送气缸1114驱动电芯移送吸嘴1112收缩,以使得电芯移送吸嘴1112凹陷于料盘移送吸嘴1113,方便料盘移送吸嘴1113将空的料盘吸取并转移出去。要说明的是,在此,并不仅限于电芯移送气缸这一驱动结构,只要是能驱动电芯移送吸嘴伸缩的驱动源,均可采用。Further, the number of the cell transfer nozzles 1112 is four, and the four cell transfer nozzles 1112 are distributed on the cell tray transfer base 1111 in a rectangular array. The cell material tray transfer gripper 1110 further includes a cell transfer cylinder 1114 , and the cell transfer suction nozzle 1112 is provided at the telescopic end of the cell transfer cylinder 1114 . When the cell needs to be transferred, the cell transfer cylinder 1114 drives the cell transfer nozzle 1112 to extend, so that the cell transfer nozzle 1112 protrudes from the tray transfer nozzle 1113, which is convenient for the cell transfer nozzle 1112 to The cells on the tray are sucked, and it is also convenient for the cell transfer nozzle 1112 to transfer the cells to the next station; when the tray needs to be transferred, the cell transfer cylinder 1114 drives the cell transfer nozzle 1112 to shrink , so that the cell transfer nozzle 1112 is recessed in the tray transfer nozzle 1113, so that the tray transfer nozzle 1113 can suck and transfer the empty tray out. It should be noted that, here, it is not limited to the drive structure of the cell transfer cylinder, and any drive source that can drive the cell transfer nozzle to expand and contract may be used.

更进一步的,电芯料盘移送基座1111上开设有料盘吸嘴调节孔1115,料盘移送吸嘴1113可调节位置地安装于料盘吸嘴调节孔1115中。通过开设料盘吸嘴调节孔1115,可以兼容多种型号料盘的移送,提高了兼容性。Furthermore, the cell material tray transfer base 1111 is provided with a material tray suction nozzle adjustment hole 1115, and the material tray transfer suction nozzle 1113 is installed in the material tray suction nozzle adjustment hole 1115 in an adjustable position. By opening the adjustment hole 1115 for the suction nozzle of the tray, it can be compatible with the transfer of various types of trays, and the compatibility is improved.

如图4所示,下面,对电芯调整定位系统2000的具体结构进行说明:As shown in FIG. 4 , the specific structure of the cell adjustment and positioning system 2000 will be described below:

电芯调整定位系统2000包括:电芯调整定位座2100、电芯水平横向调整装置2200、电芯水平纵向调整装置2300;The cell adjustment and positioning system 2000 includes: a cell adjustment and positioning seat 2100, a cell horizontal and lateral adjustment device 2200, and a cell horizontal and vertical adjustment device 2300;

电芯水平横向调整装置2200包括:电芯水平横向驱动部2210、电芯水平横向调整左侧板2220、电芯水平横向调整右侧板2230,电芯水平横向驱动部2210驱动电芯水平横向调整左侧板2220及电芯水平横向调整右侧板2230沿电芯调整定位座2100水平横向相互靠近或远离;The cell horizontal horizontal adjustment device 2200 includes: a cell horizontal horizontal driving part 2210, a cell horizontal horizontal adjustment left plate 2220, a cell horizontal horizontal adjustment right plate 2230, and the cell horizontal horizontal driving part 2210 drives the horizontal horizontal adjustment of the cell The left side plate 2220 and the right side plate 2230 for horizontal and lateral adjustment of the cell are approached or away from each other along the horizontal and lateral direction of the cell adjustment and positioning seat 2100;

电芯水平纵向调整装置2300包括:电芯水平纵向驱动部2310、电芯水平纵向调整块2320,电芯水平纵向驱动部2310驱动电芯水平纵向调整块2320沿水平纵向伸缩以靠近或远离电芯调整定位座2100。The cell horizontal and vertical adjustment device 2300 includes: a cell horizontal and vertical driving part 2310 and a cell horizontal and vertical adjustment block 2320. The cell horizontal and vertical driving part 2310 drives the cell horizontal and vertical adjustment block 2320 to expand and contract along the horizontal and vertical directions to approach or away from the cell Adjust the positioning seat 2100.

电芯调整定位系统2000的工作原理如下:The working principle of the cell adjustment and positioning system 2000 is as follows:

上一工位将电芯转移至电芯调整定位座2100中;Transfer the cells to the cell adjustment and positioning seat 2100 at the previous station;

电芯水平横向调整装置2200及电芯水平纵向调整装置2300动作,电芯水平横向驱动部2210驱动电芯水平横向调整左侧板2220及电芯水平横向调整右侧板2230沿水平横向相互靠近,以电芯进行夹持,以实现在水平横向方向上对电芯进行调整;电芯水平纵向驱动部2310驱动电芯水平纵向调整块2320沿水平纵向伸出,以使得电芯水平纵向调整块2320靠近电芯调整定位座2100的电芯,从而实现在水平纵向方向上对电芯进行调整;The cell horizontal and vertical adjustment device 2200 and the cell horizontal and vertical adjustment device 2300 act, and the cell horizontal and horizontal driving unit 2210 drives the cell horizontal and horizontal adjustment left side plate 2220 and the cell horizontal horizontal adjustment right plate 2230 to approach each other in the horizontal and horizontal direction, The cells are clamped to adjust the cells in the horizontal and transverse direction; the horizontal and vertical driving part 2310 of the cells drives the horizontal and vertical adjustment blocks 2320 of the cells to extend horizontally and longitudinally, so that the horizontal and vertical adjustment blocks 2320 of the cells are extended in the horizontal and vertical directions. The cells of the positioning seat 2100 are adjusted close to the cells, so that the cells can be adjusted in the horizontal and vertical direction;

电芯调整完毕后,电芯水平横向调整装置2200及电芯水平纵向调整装置2300的各部件复位,电芯等待被转移至下一工位中。After the cell is adjusted, the components of the cell horizontal and vertical adjustment device 2200 and the cell horizontal and vertical adjustment device 2300 are reset, and the cell is waiting to be transferred to the next station.

具体的,电芯水平横向驱动部包括水平横向驱动电机及设于水平横向驱动电机输出端的水平横向调节丝杆,电芯水平横向调整左侧板2220及电芯水平横向调整右侧板2230螺合于水平横向调节丝杆上。通过对电芯水平横向调整左侧板2220及电芯水平横向调整右侧板2230上的螺纹孔的螺纹方向进行适应性调整,这样,水平横向驱动电机驱动水平横向调节丝杆转动,从而使得滑动设于电芯调整定位座2100上的电芯水平横向调整左侧板2220及电芯水平横向调整右侧板2230可以相互靠近或远离运动。进一步的,电芯水平横向调整左侧板2220上设有电芯调整左侧定位块2221,电芯水平横向调整右侧板2230上设有电芯调整右侧定位块2231,电芯调整左侧定位块为橡胶块结构,电芯调整右侧定位块为橡胶块结构,这样,可以防止电芯在调整的过程中被夹坏。Specifically, the horizontal horizontal driving part of the cell includes a horizontal horizontal driving motor and a horizontal horizontal adjusting screw rod disposed at the output end of the horizontal horizontal driving motor. on the horizontal horizontal adjustment screw. By adaptively adjusting the thread directions of the threaded holes on the left side plate 2220 for horizontal and horizontal adjustment of cells and the right side plate 2230 for horizontal and horizontal adjustment of cells, in this way, the horizontal horizontal drive motor drives the horizontal horizontal adjustment screw to rotate, thereby making the sliding The left side plate 2220 and the right side plate 2230 for horizontal and lateral adjustment of the cells disposed on the cell adjustment and positioning base 2100 can move closer to or away from each other. Further, a cell adjustment left positioning block 2221 is provided on the left plate 2220 for horizontal horizontal adjustment of the cell, and a right positioning block 2231 for cell adjustment is provided on the right plate 2230 for horizontal horizontal adjustment of the cell. The positioning block is a rubber block structure, and the positioning block on the right side of the cell adjustment is a rubber block structure, which can prevent the cell from being clamped during the adjustment process.

具体的,电芯水平纵向驱动部为电机丝杆驱动结构,电芯水平纵向调整块为橡胶块结构,这样,可以防止电芯在调整的过程中被撞击而损坏。Specifically, the horizontal and longitudinal driving part of the cell is a motor screw drive structure, and the horizontal and longitudinal adjustment block of the cell is a rubber block structure, so that the cell can be prevented from being damaged by impact during the adjustment process.

如图5及图6所示,下面,对电芯中转系统3000的具体结构进行说明:As shown in FIG. 5 and FIG. 6 , the specific structure of the cell transfer system 3000 will be described below:

电芯中转系统3000包括:电芯移送机构3100、电芯中转流水线3200;在本实施例中,电芯移送机构3100的数量为三个,一个电芯移送机构3100用于将电芯调整定位座2100处的电芯转移至电芯中转流水线3200中,一个电芯移送机构3100用于将电芯中转流水线3200处的电芯转移至电芯外形尺寸检测系统7000中,一个电芯移送机构3100用于将电芯外形尺寸检测系统7000处的电芯转移至工件厚度检测系统8000中。The cell transfer system 3000 includes: a cell transfer mechanism 3100 and a cell transfer assembly line 3200; in this embodiment, the number of cell transfer mechanisms 3100 is three, and one cell transfer mechanism 3100 is used to adjust the positioning seat of the cell The cells at 2100 are transferred to the cell transfer line 3200. A cell transfer mechanism 3100 is used to transfer the cells at the cell transfer line 3200 to the cell size detection system 7000. A cell transfer mechanism 3100 is used for The cells at the cell outer dimension detection system 7000 are transferred to the workpiece thickness detection system 8000 .

电芯移送机构3100包括:电芯移送驱动部3110、电芯移动基座3120、电芯移送杆3130,电芯移送驱动部3110驱动电芯移动基座3120运动,电芯移送杆3130可旋转及伸缩地安装于电芯移动基座3120上,电芯移送杆3130上设有电芯移送吸嘴组件3140。The cell transfer mechanism 3100 includes: a cell transfer driving part 3110, a cell moving base 3120, and a cell transfer rod 3130. The cell transfer driving part 3110 drives the cell moving base 3120 to move, and the cell transfer rod 3130 can rotate and It is telescopically installed on the cell moving base 3120 , and the cell transfer rod 3130 is provided with a cell transfer suction nozzle assembly 3140 .

具体的,电芯移送驱动部3110包括:水平移送模组3111、升降移送模组3112,水平移送模组3111驱动电芯移动基座3120沿水平方向往复移动,升降移送模组3112驱动电芯移动基座3120沿竖直方向往复升降。这样,通过设置水平移送模组3111及升降移送模组3112,从而实现电芯移动基座3120在水平及竖直方向的运动,进而实现电芯移送吸嘴组件3140吸取电芯由一个工位转移至另一个工位。Specifically, the cell transfer driving unit 3110 includes: a horizontal transfer module 3111 and a lift transfer module 3112. The horizontal transfer module 3111 drives the cell moving base 3120 to reciprocate in the horizontal direction, and the lift transfer module 3112 drives the cell to move. The base 3120 reciprocates up and down in the vertical direction. In this way, by setting the horizontal transfer module 3111 and the lift transfer module 3112, the movement of the cell moving base 3120 in the horizontal and vertical directions is realized, and the cell transfer suction nozzle assembly 3140 can absorb the cells and transfer them from one station. to another station.

进一步的,电芯移送吸嘴组件3140包括多种不同结构的真空吸嘴,多种不同结构的真空吸嘴安装于移送杆松紧件上。这样,通过电芯移送杆可旋转及伸缩地安装于电芯移动基座上,一方面可以对电芯移送杆进行旋转调节,另一方面可以对电芯移送杆进行伸缩调节,从而对多种不同结构的真空吸嘴进行位置调节,以适应不同型号的电芯,从而更好的对电芯进行吸取。在本实施例中,电芯移送吸嘴组件包括两种不同结构的真空吸嘴,其中一种结构的真空吸嘴由两个吸嘴组成,另一种结构的真空吸嘴则由一个吸嘴组成,这样,可以对吸嘴数量进行调节,即电芯移送杆的平位两面分别为双气嘴和单气嘴结构,可根据电芯大小选择合适平面旋转至下侧,同时,还可以对吸嘴位置进行调节,即电芯移送杆水平方向可伸出和收缩,人工可根据电芯位置调节至其中心位置。Further, the cell transfer suction nozzle assembly 3140 includes vacuum suction nozzles with different structures, and the vacuum suction nozzles with different structures are mounted on the elastic member of the transfer rod. In this way, the cell transfer rod can be rotatably and telescopically installed on the cell moving base. On the one hand, the cell transfer rod can be rotated and adjusted, and on the other hand, the cell transfer rod can be telescopically adjusted, so that various The position of the vacuum nozzles of different structures is adjusted to adapt to different types of batteries, so as to better absorb the batteries. In this embodiment, the cell transfer suction nozzle assembly includes two types of vacuum suction nozzles with different structures, wherein the vacuum suction nozzle of one structure is composed of two suction nozzles, and the vacuum suction nozzle of the other structure is composed of one suction nozzle In this way, the number of suction nozzles can be adjusted, that is, the two flat sides of the battery transfer rod are double-air nozzle and single-air nozzle structure respectively. The position of the suction nozzle is adjusted, that is, the cell transfer rod can be extended and retracted in the horizontal direction, and can be manually adjusted to its center position according to the position of the cell.

进一步的,电芯移送机构3100还包括移送杆松紧件3150,移送杆松紧件3150使得电芯移送杆3130松开或紧固于电芯移动基座3120上。由于电芯移送杆3130可旋转及伸缩地安装于电芯移动基座3120上,当需要对电芯移送杆3130进行调节时,则松开移送杆松紧件,当调节完毕后,则拧紧移送杆松紧件。例如,移送杆松紧件3150可以为螺旋杆结构,通过拧动螺旋杆,使得螺旋杆紧压或脱离电芯移送杆,从而实现电芯移送杆的松紧调节。Further, the cell transfer mechanism 3100 further includes a transfer rod elastic member 3150 , and the transfer rod elastic member 3150 makes the cell transfer rod 3130 loosen or fasten on the cell moving base 3120 . Since the cell transfer rod 3130 is rotatably and telescopically installed on the cell moving base 3120, when the cell transfer rod 3130 needs to be adjusted, loosen the transfer rod elastic member, and after the adjustment is completed, tighten the transfer rod Elastics. For example, the transfer rod tensioner 3150 may be a screw rod structure, and by twisting the screw rod, the screw rod is pressed against or separated from the cell transfer rod, thereby realizing the tightness adjustment of the cell transfer rod.

电芯中转流水线3200包括:第一中转流水线3210、第二中转流水线3220、第一流水线驱动装置3230、第二流水线驱动装置3240,第一流水线驱动装置3230驱动第一中转流水线3210流动,第二流水线驱动装置3240驱动第二中转流水线3220流动,第一中转流水线3210的流动方向与第二中转流水线3220的流动方向相互平行,第一中转流水线3210上设有第一治具3211,第二中转流水线3220上设有第二治具3221。The cell transfer assembly line 3200 includes: a first transfer assembly line 3210, a second transfer assembly line 3220, a first assembly line drive device 3230, and a second assembly line drive device 3240. The first assembly line drive device 3230 drives the first transfer assembly line 3210 to flow, and the second assembly line The driving device 3240 drives the second transfer assembly line 3220 to flow. The flow direction of the first transfer assembly line 3210 and the flow direction of the second transfer assembly line 3220 are parallel to each other. The first transfer assembly line 3210 is provided with a first fixture 3211 and the second transfer assembly line 3220 There is a second fixture 3221 thereon.

电芯中转流水线的工作原理如下:将电芯放置于第一中转流水线3210及第二中转流水线3220上,并且电芯限位于第一治具3211与第二治具3221之间,第一中转流水线3210在第一流水线驱动装置3230的驱动下发生流动,第二中转流水线3220在第二流水线驱动装置3240的驱动下发生流动,第一中转流水线3210与第二中转流水线3220沿着同一个方向流动,从而实现了电芯的中转运输。The working principle of the cell transfer line is as follows: the cells are placed on the first transfer line 3210 and the second transfer line 3220, and the cells are limited between the first fixture 3211 and the second fixture 3221, and the first transfer line 3210 flows under the driving of the first pipeline driving device 3230, and the second intermediate pipeline 3220 flows under the driving of the second pipeline driving device 3240. The first intermediate pipeline 3210 and the second intermediate pipeline 3220 flow in the same direction, In this way, the transit transportation of the battery cells is realized.

要特别说明的是,不同型号的电芯,其尺寸大小不一,为了更好对不同型号的电芯进行运输,需要适应性调节第一治具3211与第二治具3221之间的间距。调节过程如下:第一流水线驱动装置3230驱动第一中转流水线3210正转或反转一段距离,第二流水线驱动装置3240驱动第二中转流水线3220正转或反转一段距离,于是,位于第一中转流水线3210上的第一治具3211以及位于第二中转流水线3220上的第二治具3221相互之间便可以分开合适的距离,从而适应不同型号的电芯,提高了兼容性。It should be noted that different types of batteries have different sizes. In order to better transport batteries of different types, the distance between the first fixture 3211 and the second fixture 3221 needs to be adaptively adjusted. The adjustment process is as follows: the first assembly line driving device 3230 drives the first transfer assembly line 3210 to rotate forward or reverse for a certain distance, and the second assembly line driving device 3240 drives the second transfer assembly line 3220 to rotate forward or reverse for a certain distance. The first jig 3211 on the assembly line 3210 and the second jig 3221 on the second transfer assembly line 3220 can be separated by a suitable distance from each other, thereby adapting to different types of batteries and improving compatibility.

进一步的,电芯中转流水线3200还包括第一感应器3250及第二感应器3260,第一感应器3250及第二感应器3260相互间可调节距离的设置。例如,第一感应器3250固定设于第一中转流水线3210及第二中转流水线3220的一侧,第二感应器3250活动设于第一中转流水线3210及第二中转流水线3220的一侧,当需要调节第一治具3211与第二治具3221之间的距离时,首先,活动的调节第二感应器3260,以使得第二感应器3260与第一感应器3250分开合适的距离,接着,第一流水线驱动装置3230驱动第一中转流水线3210正转或反转,当第一中转流水线3210上的第一治具3211到达第一感应器3250处时,第一治具3211调整到位,第一中转流水线3210停止,第二流水线驱动装置3240驱动第二中转流水线3220正转或反转,当第二中转流水线3220上的第二治具3221到达第二感应器3260处时,第二治具3221调整到位,第二中转流水线3220停止,于是,第一治具3211与第二治具3221调整到合适的位置,从而适应不同型号的电芯,提高了兼容性,保证设备生产过程换型快,可靠性高。Further, the cell transfer line 3200 further includes a first sensor 3250 and a second sensor 3260, and the distance between the first sensor 3250 and the second sensor 3260 can be adjusted. For example, the first sensor 3250 is fixedly disposed on one side of the first transfer line 3210 and the second transfer line 3220, and the second sensor 3250 is movably disposed on one side of the first transfer line 3210 and the second transfer line 3220. When necessary When adjusting the distance between the first jig 3211 and the second jig 3221, first, the second sensor 3260 is adjusted movably so that the second sensor 3260 and the first sensor 3250 are separated by a suitable distance, and then the second sensor 3260 is adjusted. The pipeline driving device 3230 drives the first transfer line 3210 to rotate forward or reversely. When the first fixture 3211 on the first transfer line 3210 reaches the first sensor 3250, the first fixture 3211 is adjusted in place, and the first transfer The assembly line 3210 stops, the second assembly line driving device 3240 drives the second transfer assembly line 3220 to rotate forward or reversely, when the second jig 3221 on the second transfer assembly line 3220 reaches the second sensor 3260, the second jig 3221 adjusts When in place, the second transfer line 3220 stops, so the first jig 3211 and the second jig 3221 are adjusted to appropriate positions, so as to adapt to different types of cells, improve compatibility, and ensure the equipment production process is fast and reliable. Sex is high.

如图7所示,下面,对电芯极耳整形系统4000的具体结构进行说明:As shown in FIG. 7 , the specific structure of the cell electrode ear shaping system 4000 will be described below:

电芯极耳整形系统4000包括:极耳固定装置4100、极耳捋平装置4200,极耳固定装置4100包括:极耳固定驱动部4110、极耳固定压块4120,极耳固定驱动部4110驱动极耳固定压块4120往复运动,极耳捋平装置4200包括:第一张夹滚轮4210、第二张夹滚轮4220、夹极耳驱动部4230、拉极耳驱动部4240,夹极耳驱动部4230驱动第一张夹滚轮4210与第二张夹滚轮4220相互靠近或远离,拉极耳驱动部4240驱动第一张夹滚轮4210与第二张夹滚轮4220往复运动。具体的,极耳固定驱动部驱动4110极耳固定压块4120沿竖直方向往复升降运动,以使得极耳固定压块4120可以固定极耳,为后续极耳的捋平作好准备,防止极耳发生移动;夹极耳驱动部4230驱动第一张夹滚轮4210沿竖直方向往复升降运动,以使得第一张夹滚轮4210可以靠近第二张夹滚轮4220,从而实现将极耳夹紧;拉极耳驱动部驱动第一张夹滚轮与第二张夹滚轮沿水平方向往复运动,从而实现将夹紧后的极耳进行捋平。The cell tab shaping system 4000 includes: a tab fixing device 4100, a tab flattening device 4200, and the tab fixing device 4100 includes: a tab fixing driving part 4110, a tab fixing pressing block 4120, and the tab fixing driving part 4110 drives The tab fixing pressing block 4120 reciprocates, and the tab flattening device 4200 includes: a first clip roller 4210, a second clip roller 4220, a pole clip drive part 4230, a pole tab drive part 4240, and a pole clip drive part 4230 drives the first clamping roller 4210 and the second clamping roller 4220 to approach or move away from each other, and the tab driving part 4240 drives the first clamping roller 4210 and the second clamping roller 4220 to reciprocate. Specifically, the tab fixing drive part drives 4110 the tab fixing pressing block 4120 to reciprocate up and down in the vertical direction, so that the tab fixing pressing block 4120 can fix the tab, prepare for the subsequent flattening of the tab, and prevent the tab Movement occurs; the electrode clip driving part 4230 drives the first clamping roller 4210 to reciprocate up and down in the vertical direction, so that the first clamping roller 4210 can be close to the second clamping roller 4220, thereby realizing clamping the tab; pulling The pole lug driving part drives the first clamping roller and the second clamping roller to reciprocate in the horizontal direction, so as to flatten the clamped pole lug.

电芯极耳整形系统4000的工作原理如下:The working principle of the cell ear shaping system 4000 is as follows:

电芯中转流水线运输极耳到达指定位置,电芯极耳整形系统4000开始工作;The cell transfer line transports the tabs to the designated position, and the cell tab shaping system 4000 starts to work;

首先,极耳固定装置4100动作,极耳固定驱动部4110驱动极耳固定压块4120沿竖直方向下降,从而使得极耳固定压块4120可以压紧极耳,从而实现极耳的固定,防止极耳发生移动;First, the tab fixing device 4100 is actuated, and the tab fixing driving part 4110 drives the tab fixing pressing block 4120 to descend in the vertical direction, so that the tab fixing pressing block 4120 can compress the tab, thereby realizing the fixing of the tab and preventing the the polar ears move;

接着,夹极耳驱动部4230驱动第一张夹滚轮4210沿竖直方向下降,以使得第一张夹滚轮4210可以靠近第二张夹滚轮4220,从而实现将极耳夹紧;Next, the tab driving part 4230 drives the first clamping roller 4210 to descend in the vertical direction, so that the first clamping roller 4210 can be close to the second clamping roller 4220, so as to clamp the tab;

然后,拉极耳驱动部4240驱动第一张夹滚轮4210与第二张夹滚轮4220沿水平方向一侧移动,从而实现将夹紧后的极耳进行捋平;Then, the tab driving part 4240 drives the first clamping roller 4210 and the second clamping roller 4220 to move along one side of the horizontal direction, so as to flatten the clamped tab;

极耳被捋平后,各个部件复位,为下一次的极耳整形作好准备。After the tabs are flattened, all parts are reset to prepare for the next tab shaping.

在本实施例中,极耳固定驱动部4110、夹极耳驱动部4230驱动及拉极耳驱动部4240均为气缸驱动结构。In this embodiment, the tab fixing driving part 4110 , the tab driving part 4230 and the pulling tab driving part 4240 are all cylinder-driven structures.

进一步的,电芯极耳整形系统4000还包括高度调整装置4250,高度调整装置4250驱动极耳捋平装置4220沿竖直方向往复升降。高度调整装置4250包括:高度调整电机4251、高度调整丝杆4252、高度调整支架4253,极耳捋平装置4220安装于高度调整支架4253上,高度调整丝杆4252一端设于高度调整电机4251的输出端,高度调整丝杆4252另一端螺合于高度调整支架4253上。可知,高度调整电机4251驱动高度调整丝杆4252正转或反转,从而实现高度调整支架4253在高度上的调节,进而实现了极耳捋平装置4220在高度上的调节,于是,可以根据不同型号电芯的尺寸大小,进行适应性的高度调节,提高了兼容性。Further, the cell tab shaping system 4000 further includes a height adjusting device 4250, and the height adjusting device 4250 drives the tab flattening device 4220 to reciprocate up and down in the vertical direction. The height adjustment device 4250 includes: a height adjustment motor 4251, a height adjustment screw 4252, and a height adjustment bracket 4253. The pole lug leveling device 4220 is installed on the height adjustment bracket 4253, and one end of the height adjustment screw 4252 is set at the output of the height adjustment motor 4251. The other end of the height adjustment screw 4252 is screwed to the height adjustment bracket 4253. It can be seen that the height adjustment motor 4251 drives the height adjustment screw 4252 to rotate forward or reversely, thereby realizing the height adjustment of the height adjustment bracket 4253, thereby realizing the height adjustment of the pole lug leveling device 4220. The size of the battery cell of the model can be adjusted by adapting the height to improve the compatibility.

如图8所示,下面,对电芯外形尺寸检测系统7000的具体结构进行说明:As shown in FIG. 8 , the specific structure of the cell outer dimension detection system 7000 will be described below:

电芯外形尺寸检测系统7000包括:外形尺寸检测定位座7100、CCD检测装置7200、外形尺寸检测辅助装置7300。The battery outer dimension detection system 7000 includes an outer dimension detection positioning seat 7100 , a CCD detection device 7200 , and an outer dimension detection auxiliary device 7300 .

CCD检测装置用于对电芯的外形尺寸进行拍照检测;例如,CCD检测装置的摄像头位于外形尺寸检测定位座的上方。The CCD detection device is used to photograph and detect the external dimensions of the battery cells; for example, the camera of the CCD detection device is located above the external dimension detection positioning seat.

外形尺寸检测辅助装置7300包括:宽度辅助检测结构7310、长度辅助检测结构7320。The external dimension detection auxiliary device 7300 includes: a width auxiliary detection structure 7310 and a length auxiliary detection structure 7320 .

宽度辅助检测结构7310包括:宽度检测驱动部7311、宽度检测左侧卡具7312、宽度检测右侧卡具7313,宽度检测驱动部7311驱动宽度检测左侧卡具7312及宽度检测右侧卡具7313沿外形尺寸检测定位座7100水平横向相互靠近或远离;The width auxiliary detection structure 7310 includes: a width detection drive part 7311 , a width detection left clamp 7312 , a width detection right clamp 7313 , and the width detection drive part 7311 drives the width detection left clamp 7312 and the width detection right clamp 7313 The positioning bases 7100 are horizontally and laterally approached or separated from each other along the external dimension;

长度辅助检测结构7320包括:长度检测驱动部7321、长度检测定位块7322,长度检测驱动部7321驱动长度检测定位块7322沿水平纵向伸缩以靠近或远离外形尺寸检测定位座7100。The auxiliary length detection structure 7320 includes: a length detection driving part 7321 and a length detection positioning block 7322 .

电芯外形尺寸检测系统7000的工作原理如下:The working principle of the cell size detection system 7000 is as follows:

首先要说明的是,电芯的外形尺寸是利用CCD检测装置的摄像头进行拍照而得到,为了使得CCD检测装置更准确的捕捉到电芯的边缘,实现高精度的电芯外形尺寸检测,需要提供外形尺寸检测辅助装置,通过外形尺寸检测辅助装置对电芯的边缘进行定位,使得电芯的边缘与外形尺寸检测辅助装置产生强烈的色差,这样,就能使得CCD检测装置更准确的捕捉到电芯的边缘,实现高精度的电芯外形尺寸检测。例如,待检测的电芯为银白色,而外形尺寸检测辅助装置中与电芯边缘接触的部分则为黑色,这样,便能产生强烈的色差,使得CCD检测装置更准确的捕捉到电芯的边缘,实现高精度的电芯外形尺寸检测;First of all, it should be noted that the external dimension of the cell is obtained by taking pictures with the camera of the CCD detection device. In order to make the CCD detection device more accurately capture the edge of the cell and achieve high-precision detection of the external dimension of the cell, it is necessary to provide The external dimension detection auxiliary device locates the edge of the cell through the external dimension detection auxiliary device, so that the edge of the cell and the external dimension detection auxiliary device have a strong chromatic aberration, so that the CCD detection device can more accurately capture the battery. The edge of the core can realize high-precision detection of the outer dimension of the battery. For example, the cell to be detected is silver-white, and the part of the external dimension detection auxiliary device that is in contact with the edge of the cell is black, so that a strong chromatic aberration can be generated, so that the CCD detection device can more accurately capture the cell's edge. edge, to achieve high-precision cell size detection;

通过电芯移送机构3100的作用,将电芯中转流水线3200中的电芯转移至外形尺寸检测定位座7100上;Through the function of the cell transfer mechanism 3100, the cells in the cell transfer line 3200 are transferred to the external dimension detection positioning seat 7100;

外形尺寸检测辅助装置7300动作,宽度检测驱动部7311驱动宽度检测左侧卡具7312及宽度检测右侧卡具7313沿外形尺寸检测定位座7100水平横向相互靠近,从而实现将外形尺寸检测定位座上的电芯夹紧,接着,长度检测驱动部7321驱动长度检测定位块7322沿水平纵向靠近外形尺寸检测定位座7100,从而碰触到外形尺寸检测定位座7100上的电芯,此时,宽度检测左侧卡具7312、宽度检测右侧卡具7313、长度检测定位块7322为黑色,而电芯为银白色,这样,便能产生强烈的色差;The external dimension detection auxiliary device 7300 is actuated, and the width detection drive part 7311 drives the width detection left clamp 7312 and the width detection right clamp 7313 to approach each other horizontally and laterally along the external dimension detection positioning seat 7100, thereby realizing the external dimension detection positioning seat. Then, the length detection driving part 7321 drives the length detection positioning block 7322 to approach the outer dimension detection positioning seat 7100 in the horizontal and longitudinal direction, so as to touch the battery cells on the outer dimension detection positioning seat 7100. At this time, the width detection The left fixture 7312, the width detection right fixture 7313, and the length detection positioning block 7322 are black, and the battery cells are silver-white, so that a strong color difference can be produced;

CCD检测装置7200对外形尺寸检测定位座上的电芯进行拍照检测,实现高精度的电芯外形尺寸检测。The CCD detection device 7200 takes pictures and detects the cells on the outer dimension detection positioning seat, so as to realize high-precision outer dimension detection of the electric cells.

要特别说明的是,在水平纵向方向上,只需要设置一个长度检测定位块即可达到外形检测要求,而不需要设置两个长度检测定位块对电芯进行包夹。这是因为,在这之前的工序中,即在电芯调整定位系统2000中,电芯水平纵向调整装置已经将电芯在水平纵向方向上调整好位置,后续工位就无需再对电芯进行水平纵向方向上调整位置,电芯在水平纵向的位置保持不变,在电芯外形尺寸检测系统7000中,只需要使用单一的长度检测定位块在水平纵向碰撞至电芯的边缘,就可以实现电芯在长度方向的尺寸检测。It should be noted that, in the horizontal and longitudinal direction, only one length detection positioning block needs to be set to meet the shape detection requirements, and there is no need to set two length detection positioning blocks to clamp the cells. This is because, in the previous process, that is, in the cell adjustment and positioning system 2000, the cell horizontal and vertical adjustment device has already adjusted the position of the cell in the horizontal and vertical direction, and the subsequent work station does not need to perform any further adjustment on the cell. Adjust the position in the horizontal and vertical direction, and the position of the cell in the horizontal and vertical directions remains unchanged. In the cell size detection system 7000, it is only necessary to use a single length detection positioning block to collide with the edge of the cell in the horizontal and vertical direction. The size of the cell in the length direction is detected.

进一步的,宽度检测右侧卡具7313上设有弹性缓冲件7314,弹性缓冲件7314用于防止宽度检测左侧卡具7312与宽度检测右侧卡具7313在对电芯进行夹持时将电芯夹变形,有效保护了电芯不被压坏。在本实施例中,弹性缓冲件7314为弹簧结构。Further, an elastic buffer member 7314 is provided on the width detection right clamp 7313, and the elastic cushion member 7314 is used to prevent the width detection left clamp 7312 and the width detection right clamp 7313 from compressing the battery cells when clamping the cells. The core clip is deformed, which effectively protects the cell from being crushed. In this embodiment, the elastic buffer member 7314 is a spring structure.

具体的,宽度检测驱动部包括宽度检测驱动电机及设于宽度检测驱动电机输出端的宽度检测调节丝杆,宽度检测左侧卡具及宽度检测右侧卡具螺合于宽度检测调节丝杆上。通过在宽度检测左侧卡具及宽度检测右侧卡具上的螺纹孔的螺纹方向进行适应性调整,这样,宽度检测驱动电机驱动宽度检测调节丝杆转动,从而使得滑动于外形尺寸检测定位座上的宽度检测左侧卡具及宽度检测右侧卡具可以相互靠近或远离运动。Specifically, the width detection drive part includes a width detection drive motor and a width detection adjustment screw disposed at the output end of the width detection drive motor. The width detection left clamp and the width detection right clamp are screwed on the width detection adjustment screw. By adjusting the thread direction of the threaded holes on the width detection left clamp and the width detection right clamp, the width detection drive motor drives the width detection adjustment screw to rotate, so as to slide on the outer dimension detection positioning seat The width detection on the left clamp and the width detection right clamp can move closer to or away from each other.

具体的,长度检测驱动部为电机丝杆驱动结构,长度检测定位块为橡胶块结构,这样,可以防止长度检测定位块与电芯碰触的过程中,电芯被撞击而损坏。Specifically, the length detection driving part is a motor screw drive structure, and the length detection positioning block is a rubber block structure, which can prevent the battery cell from being damaged by impact during the contact between the length detection positioning block and the battery cell.

如图9所示,下面,对工件厚度检测系统8000的具体结构进行说明:As shown in FIG. 9 , the specific structure of the workpiece thickness detection system 8000 will be described below:

工件厚度检测系统8000用于对工件的厚度进行检测,例如对电芯的厚度进行检测,工件厚度检测系统8000包括:工件测厚放置平台8100、工件测厚驱动部8200、工件测厚升降架8300、工件测厚下压板8400、下压板压力调节结构8500、工件厚度测量器8600;The workpiece thickness detection system 8000 is used to detect the thickness of the workpiece, such as the thickness of the battery cell. The workpiece thickness detection system 8000 includes: a workpiece thickness measurement placing platform 8100, a workpiece thickness measurement driving part 8200, and a workpiece thickness measurement lifting frame 8300 , Workpiece thickness measurement lower pressure plate 8400, lower pressure plate pressure adjustment structure 8500, workpiece thickness measurer 8600;

工件测厚下压板8400活动设于工件测厚升降架8300上;The workpiece thickness measuring lower pressure plate 8400 is movably arranged on the workpiece thickness measuring lifting frame 8300;

工件测厚驱动部8200驱动工件测厚升降架8300,以使得工件测厚下压板8400靠近或远离工件测厚放置平台8100的方向运动,工件厚度测量器8600用于识别工件测厚放置平台8100到工件测厚下压板8400之间的距离;The workpiece thickness measurement driving part 8200 drives the workpiece thickness measurement lifting frame 8300 to move the workpiece thickness measurement lower pressure plate 8400 toward or away from the workpiece thickness measurement placement platform 8100. The workpiece thickness measurement device 8600 is used to identify the workpiece thickness measurement placement platform 8100 to the direction. The distance between the workpiece thickness measurement and the lower platen 8400;

下压板压力调节结构8500与工件测厚下压板8400连接,下压板压力调节结构8500用于提供与工件测厚下压板8400的重力方向相反的可调节拉扯力。The lower platen pressure adjustment structure 8500 is connected with the workpiece thickness measurement lower platen 8400 , and the lower platen pressure adjustment structure 8500 is used to provide an adjustable pulling force opposite to the gravitational direction of the workpiece thickness measurement lower platen 8400 .

工件厚度检测系统8000的工作原理如下:The working principle of the workpiece thickness detection system 8000 is as follows:

将待测厚度的工件放置于工件测厚放置平台8100上;Place the workpiece whose thickness is to be measured on the workpiece thickness measurement placing platform 8100;

工件测厚驱动部8200驱动工件测厚升降架8300,工件测厚升降架8300进而带动工件测厚下压板8400运动,从而使得工件测厚下压板8400向靠近工件测厚放置平台8100的方向运动;The workpiece thickness measurement driving part 8200 drives the workpiece thickness measurement lifting frame 8300, and the workpiece thickness measurement lifting frame 8300 further drives the workpiece thickness measurement lower pressure plate 8400 to move, so that the workpiece thickness measurement lower pressure plate 8400 moves to the direction close to the workpiece thickness measurement placement platform 8100;

当工件测厚下压板8400碰触到工件的表面时,工件测厚下压板8400停止运动,于是,工件厚度测量器8600便可以测得当前工件测厚放置平台8100到工件测厚下压板8400之间的距离,进而可以得到工件的厚度,从而判断当前的工件厚度是否满足要求;When the workpiece thickness measuring lower platen 8400 touches the surface of the workpiece, the workpiece thickness measuring lower platen 8400 stops moving, so the workpiece thickness measuring device 8600 can measure the distance between the current workpiece thickness measuring placing platform 8100 and the workpiece thickness measuring lower platen 8400 The distance between them, and then the thickness of the workpiece can be obtained, so as to judge whether the current workpiece thickness meets the requirements;

要说明的是,工件厚度测量器8600既可以设于工件测厚下压板8400上,也可以设于工件测厚放置平台8100上,还可以设于工件测厚下压板8400与工件测厚放置平台8100之间,只要能实现测量工件测厚放置平台8100到工件测厚下压板8400之间的距离,均可采用。在本实施例中,工件厚度测量器8600利用弹簧可弹性伸缩的设于工件测厚放置平台8100上,在测量之前,工件厚度测量器8600凸出于工件的上表面,工件测厚下压板8400在下压的过程中,首先与工件厚度测量器8600接触,工件厚度测量器8600受到压力的作用发生收缩,直至工件测厚下压板8400碰触到工件的上表面,工件厚度测量器8600停止收缩,于是,工件厚度测量器8600便可以测算出当前工件的厚度。It should be noted that the workpiece thickness measuring device 8600 can be installed on the workpiece thickness measurement lower platen 8400, the workpiece thickness measurement placement platform 8100, or the workpiece thickness measurement lower platen 8400 and the workpiece thickness measurement placement platform. 8100, as long as the distance between the workpiece thickness measurement placement platform 8100 and the workpiece thickness measurement lower pressure plate 8400 can be measured, it can be used. In the present embodiment, the workpiece thickness measuring instrument 8600 is elastically retractable by a spring and is installed on the workpiece thickness measuring placing platform 8100. Before the measurement, the workpiece thickness measuring instrument 8600 protrudes from the upper surface of the workpiece, and the workpiece thickness measuring lower pressing plate 8400 In the process of pressing down, the workpiece thickness measuring device 8600 is first contacted, and the workpiece thickness measuring device 8600 shrinks under the action of the pressure until the workpiece thickness measuring lower pressure plate 8400 touches the upper surface of the workpiece, and the workpiece thickness measuring device 8600 stops shrinking. Thus, the workpiece thickness measuring device 8600 can measure the thickness of the current workpiece.

要特别说明是的,不同型号的工件,其所能承受工件测厚下压板8400的压力不一样,因此,需要根据当前型号的工件适应性的调节工件测厚下压板对工件的下压力。为此,特别设置了下压板压力调节结构8500,下压板压力调节结构8500用于提供与工件测厚下压板8400的重力方向相反的可调节拉扯力。It should be noted that different types of workpieces can withstand different pressures of the workpiece thickness gauge lower pressure plate 8400. Therefore, it is necessary to adjust the downward pressure of the workpiece thickness gauge lower pressure plate on the workpiece according to the current type of workpiece. For this purpose, a lower pressing plate pressure regulating structure 8500 is specially provided, and the lower pressing plate pressure regulating structure 8500 is used to provide an adjustable pulling force opposite to the gravitational direction of the workpiece thickness measuring lower pressing plate 8400 .

在其中一实施例中,下压板压力调节结构8500包括:定滑轮8510、平衡线绳8520、砝码8530,定滑轮8510固定于工件测厚升降架8300上,平衡线绳8520绕设于定滑轮8510上,平衡线绳8520的两端分别与工件测厚下压板8400及砝码8530连接。在此,通过更换砝码或调节砝码的重量,使得砝码通过平衡线绳对工件测厚下压板提供可调节的拉扯力,拉扯力的方向与工件测厚下压板的重力方向相反,于是,拉扯力可以抵消工件测厚下压板的一部分重力,进而可以使得工件测厚下压板以合适的压力作用于工件表面,防止工件受过大的压力而出现变形,提高了工件测量厚度的准确性。In one embodiment, the lower pressure plate pressure adjustment structure 8500 includes: a fixed pulley 8510, a balance wire 8520, and a weight 8530. The fixed pulley 8510 is fixed on the workpiece thickness measurement lifting frame 8300, and the balance wire 8520 is wound around the fixed pulley On the 8510, the two ends of the balance line 8520 are respectively connected with the workpiece thickness measuring lower pressure plate 8400 and the weight 8530. Here, by replacing the weight or adjusting the weight of the weight, the weight can provide an adjustable pulling force to the lower platen of the workpiece thickness measurement through the balance wire, and the direction of the pulling force is opposite to the direction of gravity of the lower platen of the workpiece thickness measurement, so , the pulling force can offset part of the gravity of the workpiece thickness measurement lower platen, and then the workpiece thickness measurement lower platen can act on the workpiece surface with a suitable pressure to prevent the workpiece from being deformed by excessive pressure, and improve the workpiece thickness measurement accuracy.

在另一实施例中,下压板压力调节结构8500包括弹性件,弹性件的两端分别与工件测厚下压板及砝码连接。其中,弹性件可以为弹簧,弹性件还可以为弹性橡胶条。同样的,通过更换弹性件或调节弹性件的弹力,使得弹性件对工件测厚下压板提供可调节的拉扯力,拉扯力的方向与工件测厚下压板的重力方向相反,于是,拉扯力可以抵消工件测厚下压板的一部分重力,进而可以使得工件测厚下压板以合适的压力作用于工件表面,防止工件受过大的压力而出现变形,提高了工件测量厚度的准确性。In another embodiment, the lower pressure plate pressure adjustment structure 8500 includes an elastic piece, and two ends of the elastic piece are respectively connected with the workpiece thickness measuring lower pressure plate and the weight. Wherein, the elastic member may be a spring, and the elastic member may also be an elastic rubber strip. Similarly, by replacing the elastic piece or adjusting the elastic force of the elastic piece, the elastic piece can provide an adjustable pulling force to the lower platen of the workpiece thickness measurement, and the direction of the pulling force is opposite to the direction of gravity of the lower platen of the workpiece thickness measurement, so the pulling force can be It can offset part of the gravity of the workpiece thickness measuring lower platen, so that the workpiece thickness measuring lower platen can act on the workpiece surface with appropriate pressure, prevent the workpiece from being deformed by excessive pressure, and improve the accuracy of the workpiece thickness measurement.

还要进一步说明的是,在对工件的厚度进行检测前,需要对工件测厚下压板8400的压力值进行测试,从而判断工件测厚下压板8400的当前压力值是否达标,是否是当前型号工件所能承受的最舒适的压力。也就是说,如何使得下压板压力调节结构可以调节到最优的拉扯力。工件厚度检测系统8000还包括压力感应器8700,压力感应器安装于工件测厚放置平台上。It should be further explained that, before testing the thickness of the workpiece, it is necessary to test the pressure value of the workpiece thickness measurement lower platen 8400, so as to determine whether the current pressure value of the workpiece thickness measurement lower platen 8400 meets the standard and whether it is the current model workpiece. The most comfortable pressure to bear. That is, how to adjust the pressure adjustment structure of the lower pressing plate to the optimal pulling force. The workpiece thickness detection system 8000 further includes a pressure sensor 8700, and the pressure sensor is installed on the workpiece thickness measurement placing platform.

测试过程如下:在不放置待测工件的情况下,工件测厚驱动部8200驱动工件测厚升降架8300,工件测厚升降架8300进而带动工件测厚下压板8400运动,从而使得工件测厚下压板8400向靠近工件测厚放置平台8100的方向运动,工件测厚下压板8400与压力感应器8700接触,于是,压力感应器接触8700测得当前情况下工件测厚下压板8400的压力,如果工件测厚下压板8400的压力不达标,继续对下压板压力调节结构8500的拉扯力进行调节,如果工件测厚下压板8400的压力达标,则可以对工件进行测量厚度。The test process is as follows: without placing the workpiece to be measured, the workpiece thickness measurement driving part 8200 drives the workpiece thickness measurement lifting frame 8300, and the workpiece thickness measurement lifting frame 8300 then drives the workpiece thickness measurement lower pressure plate 8400 to move, thereby making the workpiece thickness measurement lower. The pressure plate 8400 moves to the direction close to the workpiece thickness measurement placing platform 8100, and the workpiece thickness measurement lower pressure plate 8400 is in contact with the pressure sensor 8700. Therefore, the pressure sensor contacts 8700 to measure the pressure of the workpiece thickness measurement lower pressure plate 8400 under the current situation. If the pressure of the lower platen 8400 for thickness measurement does not meet the standard, continue to adjust the pulling force of the lower platen pressure adjustment structure 8500. If the pressure of the lower platen 8400 for thickness measurement of the workpiece reaches the standard, the thickness of the workpiece can be measured.

还要说明的是,工件测厚下压板8400上设有防脱钩8401,工件测厚升降架8300上设有与防脱钩8401配合的防脱挡杆8301,工件测厚下压板8400滑动设于工件测厚升降架8300上,防脱钩8401与防脱挡杆8301接触或分离。这样,当需要对下压板压力调节结构8500进行拉扯力的调整时,工件测厚下压板8400会在重力的作用下往下掉,而通过设置防脱钩8401及防脱挡杆8301,使得防脱钩8401钩住防脱挡杆8301,就可以很好的防止了工件测厚下压板8400往下掉落,提高了下压板压力调节结构8500在进行拉扯力调节时稳定性,防止工件测厚下压板8400砸坏工件或平台。It should also be noted that the workpiece thickness measuring lower pressure plate 8400 is provided with an anti-releasing hook 8401, the workpiece thickness measuring lifting frame 8300 is provided with an anti-releasing blocking rod 8301 that cooperates with the anti-releasing hook 8401, and the workpiece thickness measuring lower pressing plate 8400 is slidably arranged on the workpiece. On the thickness measuring lifting frame 8300, the anti-releasing hook 8401 contacts or separates from the anti-releasing blocking rod 8301. In this way, when it is necessary to adjust the pulling force of the lower platen pressure adjustment structure 8500, the workpiece thickness measurement lower platen 8400 will fall down under the action of gravity. 8401 hooks the anti-dropping bar 8301, which can well prevent the workpiece thickness measurement lower pressure plate 8400 from falling down, improve the stability of the lower pressure plate pressure adjustment structure 8500 when adjusting the pulling force, and prevent the workpiece thickness measurement lower pressure plate 8400 Smashed workpiece or platform.

如图1所示,下面,对电芯分档收料系统9000的具体结构进行说明:As shown in FIG. 1 , below, the specific structure of the battery cell grading and receiving system 9000 will be described:

电芯分档收料系统9000包括:外形不良料仓9100、内阻不良料仓9200、扫码不良料仓9300、电压压降不良料仓9400、良品电芯料仓9500。外形不良料仓用于收容外形不良的电芯,内阻不良料仓用于收容内阻不良的电芯,扫码不良料仓用于收容扫码不良的电芯,电压压降不良料仓用于收容电压压降测得不良的电芯,良品电芯料仓用于收容测试合格的电芯。The battery cell sorting and receiving system 9000 includes: bad shape silos 9100, bad internal resistance silos 9200, scan code bad silos 9300, voltage drop bad silos 9400, and good battery silos 9500. The bad shape silo is used to store the cells with bad shape, the bad internal resistance silo is used to store the bad internal resistance cells, the bad scan code bin is used to store the bad scan code cells, and the bad voltage drop bin is used to store the cells with bad internal resistance. The good-quality battery silo is used to accommodate the batteries that have passed the test.

进一步的,电芯OCV测试设备10还包括电芯空料盘输送系统9600,电芯空料盘输送系统9600衔接于电芯上料系统1000与电芯分档收料系统9000之间,电芯分档收料系统9000还包括电芯料盘下料机械手9700。Further, the battery cell OCV testing equipment 10 further includes a battery cell empty material tray conveying system 9600. The battery cell empty material tray conveying system 9600 is connected between the battery cell feeding system 1000 and the battery cell grading and receiving system 9000. The grading and receiving system 9000 also includes a manipulator 9700 for unloading the battery cell material tray.

在电芯上料系统1000中,当最顶层的料盘中的电芯被全部取走后,最顶层的料盘为空料盘,电芯料盘移送机械手将空料盘转移至电芯空料盘输送系统9600中;In the cell feeding system 1000, when all the cells in the topmost tray are taken out, the topmost tray is an empty tray, and the cell tray transfer robot transfers the empty tray to the empty tray In the tray conveying system 9600;

电芯空料盘输送系统9600将空料盘输送至电芯分档收料系统9000处;The cell empty tray conveying system 9600 transports the empty tray to the cell grading and receiving system 9000;

电芯料盘下料机械手9700将电芯空料盘输送系统9600处的空料盘转移至外形不良料仓、内阻不良料仓、扫码不良料仓、电压压降不良料仓、良品电芯料仓中;The battery cell tray unloading manipulator 9700 transfers the empty tray at 9600 of the battery cell empty tray conveying system to the storage bin with poor appearance, poor internal resistance, poor scanning code, and poor voltage and voltage drop. in the core silo;

于是,电芯料盘下料机械手9700可以将完成测试后的电芯对应的放置于各个料仓的空料盘中;Therefore, the battery cell tray unloading manipulator 9700 can place the cells after the test in the empty trays of each silo correspondingly;

可知,空料盘在电芯空料盘输送系统9600的输送下,由电芯上料系统1000到达电芯分档收料系统9000处,使得空料盘可以对测试完成后的电芯进行重新装载,结构巧妙。It can be seen that the empty material tray is conveyed by the cell empty material tray conveying system 9600, and the battery cell feeding system 1000 arrives at the battery cell grading and receiving system 9000, so that the empty material tray can be used to reload the battery cells after the test is completed. Loaded, cleverly constructed.

本发明的电芯OCV测试设备10,通过设置电芯上料系统1000、电芯调整定位系统2000、电芯中转系统3000、电芯极耳整形系统4000、电芯扫码系统5000、电芯OCV测试系统6000、电芯外形尺寸检测系统7000、工件厚度检测系统8000、电芯分档收料系统9000,并对各个系统的结构进行优化设计,提高了机械自动化水平,实现对电芯的OCV测试。The battery cell OCV testing device 10 of the present invention is provided with a battery cell feeding system 1000, a battery cell adjustment and positioning system 2000, a battery cell transfer system 3000, a battery core ear shaping system 4000, a battery cell code scanning system 5000, and a battery cell OCV. Test system 6000, cell size detection system 7000, workpiece thickness detection system 8000, cell grading and receiving system 9000, and optimize the structure of each system, improve the level of mechanical automation, and realize the OCV test of cells .

以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only represent several embodiments of the present invention, and the descriptions thereof are specific and detailed, but should not be construed as a limitation on the scope of the invention patent. It should be pointed out that for those of ordinary skill in the art, without departing from the concept of the present invention, several modifications and improvements can also be made, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the appended claims.

Claims (1)

1.一种电芯OCV测试设备,用于对电芯进行OCV测试,其特征在于,包括:电芯上料系统、电芯调整定位系统、电芯中转系统、电芯极耳整形系统、电芯扫码系统、电芯OCV测试系统、电芯外形尺寸检测系统、工件厚度检测系统、电芯分档收料系统;电芯依次经过所述电芯上料系统、所述电芯调整定位系统、所述电芯极耳整形系统、所述电芯扫码系统、所述电芯OCV测试系统、所述电芯外形尺寸检测系统、所述工件厚度检测系统、所述电芯分档收料系统,所述电芯中转系统用于对所述电芯调整定位系统中的电芯进行转移,并依次经过所述电芯极耳整形系统、所述电芯扫码系统、所述电芯OCV测试系统、所述电芯外形尺寸检测系统、所述工件厚度检测系统;1. A battery cell OCV test equipment is used to carry out an OCV test to a battery cell, and is characterized in that, comprising: a battery core feeding system, a battery core adjustment and positioning system, a battery core transfer system, a battery core ear shaping system, a battery core Cell code scanning system, cell OCV testing system, cell external dimension detection system, workpiece thickness detection system, cell grading and receiving system; cells sequentially pass through the cell feeding system and the cell adjustment and positioning system , the cell tab shaping system, the cell code scanning system, the cell OCV test system, the cell size detection system, the workpiece thickness detection system, and the cell bin collection The battery transfer system is used to transfer the battery cells in the battery cell adjustment and positioning system, and sequentially passes through the battery cell tab shaping system, the battery cell code scanning system, and the battery cell OCV a testing system, the battery outer dimension detection system, and the workpiece thickness detection system; 所述电芯调整定位系统包括:电芯调整定位座、电芯水平横向调整装置、电芯水平纵向调整装置;所述电芯水平横向调整装置包括:电芯水平横向驱动部、电芯水平横向调整左侧板、电芯水平横向调整右侧板,所述电芯水平横向驱动部驱动所述电芯水平横向调整左侧板及所述电芯水平横向调整右侧板沿所述电芯调整定位座水平横向相互靠近或远离;所述电芯水平纵向调整装置包括:电芯水平纵向驱动部、电芯水平纵向调整块,所述电芯水平纵向驱动部驱动所述电芯水平纵向调整块沿水平纵向伸缩以靠近或远离所述电芯调整定位座;The cell adjustment and positioning system includes: a cell adjustment and positioning seat, a cell horizontal and lateral adjustment device, and a cell horizontal and vertical adjustment device; the cell horizontal and lateral adjustment device Adjusting the left side plate and the right side plate of the horizontal and horizontal adjustment of the battery cell, the horizontal and horizontal driving part of the battery cell drives the horizontal and horizontal adjustment of the battery cell to the left side plate and the horizontal and horizontal adjustment of the battery cell. The right side plate is adjusted along the battery cell The positioning seats are horizontally and laterally close to or away from each other; the horizontal and vertical adjustment device of the cell includes: a horizontal and vertical driving part of the cell and a horizontal and vertical adjustment block of the cell, and the horizontal and vertical driving part of the cell drives the horizontal and longitudinal adjustment block of the cell Extend and retract horizontally and vertically to adjust the positioning seat close to or away from the battery cell; 所述电芯外形尺寸检测系统包括:外形尺寸检测定位座、CCD检测装置、外形尺寸检测辅助装置;所述CCD检测装置用于对电芯的外形尺寸进行拍照检测;所述外形尺寸检测辅助装置包括:宽度辅助检测结构、长度辅助检测结构;所述宽度辅助检测结构包括:宽度检测驱动部、宽度检测左侧卡具、宽度检测右侧卡具,所述宽度检测驱动部驱动所述宽度检测左侧卡具及所述宽度检测右侧卡具沿所述外形尺寸检测定位座水平横向相互靠近或远离;所述长度辅助检测结构包括:长度检测驱动部、长度检测定位块,所述长度检测驱动部驱动所述长度检测定位块沿水平纵向伸缩以靠近或远离所述外形尺寸检测定位座;所述宽度检测驱动部包括宽度检测驱动电机及设于所述宽度检测驱动电机输出端的宽度检测调节丝杆,所述宽度检测左侧卡具及所述宽度检测右侧卡具螺合于所述宽度检测调节丝杆上;The battery outer dimension detection system includes: an outer dimension detection positioning seat, a CCD detection device, and an outer dimension detection auxiliary device; the CCD detection device is used to take pictures and detect the outer dimension of the battery cell; the outer dimension detection auxiliary device It includes: a width auxiliary detection structure and a length auxiliary detection structure; the width auxiliary detection structure includes: a width detection drive part, a width detection left clamp, and a width detection right clamp, the width detection drive part drives the width detection The left clamp and the width detection right clamp approach or move away from each other horizontally and laterally along the outer dimension detection positioning seat; the length auxiliary detection structure includes: a length detection drive part, a length detection positioning block, the length detection The driving part drives the length detection positioning block to extend and retract along the horizontal and longitudinal directions to approach or stay away from the outer dimension detection positioning seat; the width detection driving part includes a width detection driving motor and a width detection adjustment set at the output end of the width detection driving motor a screw, the width detection left clamp and the width detection right clamp are screwed on the width detection adjustment screw; 所述宽度检测右侧卡具上设有弹性缓冲件,所述弹性缓冲件为弹簧结构;所述长度检测驱动部为电机丝杆驱动结构;所述长度检测定位块为橡胶块结构。The width detection right clamp is provided with an elastic buffer member, the elastic buffer member is a spring structure; the length detection driving part is a motor screw driving structure; the length detection positioning block is a rubber block structure.
CN201711331195.8A 2017-12-13 2017-12-13 Battery cell overall dimension detection system and battery cell OCV test equipment thereof Active CN107830804B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711331195.8A CN107830804B (en) 2017-12-13 2017-12-13 Battery cell overall dimension detection system and battery cell OCV test equipment thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711331195.8A CN107830804B (en) 2017-12-13 2017-12-13 Battery cell overall dimension detection system and battery cell OCV test equipment thereof

Publications (2)

Publication Number Publication Date
CN107830804A CN107830804A (en) 2018-03-23
CN107830804B true CN107830804B (en) 2020-06-12

Family

ID=61644277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711331195.8A Active CN107830804B (en) 2017-12-13 2017-12-13 Battery cell overall dimension detection system and battery cell OCV test equipment thereof

Country Status (1)

Country Link
CN (1) CN107830804B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108548491A (en) * 2018-04-20 2018-09-18 桑顿新能源科技有限公司 A kind of method and apparatus of test lamination type electric core pole piece cladding situation
CN109358064B (en) * 2018-08-31 2022-07-08 广州超音速自动化科技股份有限公司 Full-function detection method, equipment, medium and system for pole piece production and winding defects
CN109443418A (en) * 2018-08-31 2019-03-08 广州超音速自动化科技股份有限公司 Pole piece film-making rubberizing and naked battery core detection method, equipment, storage medium and system
CN109269419B (en) * 2018-08-31 2022-01-18 广州超音速自动化科技股份有限公司 Naked battery cell appearance size detection method, electronic equipment, storage medium and system
CN109556520A (en) * 2018-11-22 2019-04-02 宁波维科电池有限公司 A kind of detection system detecting lithium battery piece fitted position
CN109579717B (en) * 2018-12-14 2024-11-01 惠州锂威新能源科技有限公司 A CCD calibration block, calibration device and method for battery core winding process
CN109682315A (en) * 2019-01-22 2019-04-26 深圳市达俊宏科技股份有限公司 A kind of disc type tab CCD camera automatically rechecks machine
CN109990737A (en) * 2019-04-10 2019-07-09 无锡先导智能装备股份有限公司 Battery production equipment and its battery cell testing device
CN110068296A (en) * 2019-05-14 2019-07-30 郑州大学 A kind of battery core detection of characteristic parameters platform
CN111392403B (en) * 2020-03-18 2022-04-12 深圳市昊天宸科技有限公司 Multifunctional battery cell detection equipment
CN113405475A (en) * 2021-08-20 2021-09-17 武汉逸飞激光股份有限公司 Battery cell size measuring method, device and system
CN116298894B (en) * 2023-05-25 2023-08-15 上海君屹工业自动化股份有限公司 High-beat high-flexibility double-station battery cell test board

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202676134U (en) * 2012-06-12 2013-01-16 东莞新能源科技有限公司 A device for detecting the width dimension of square wound bare electric core
CN103737167A (en) * 2013-12-20 2014-04-23 惠州市德赛电池有限公司 An Intelligent Automatic Resistance Spot Welding Equipment
CN106058136A (en) * 2016-06-13 2016-10-26 上海捷新动力电池系统有限公司 A multi-station turntable battery automatic punching machine
CN106129447A (en) * 2016-08-08 2016-11-16 深圳市海目星激光科技有限公司 A kind of automatic production line for battery battery core with shell assembling
CN206248801U (en) * 2016-12-12 2017-06-13 深圳市德星云科技有限公司 A kind of automatic battery core OCV mechanism for testing
CN107359371A (en) * 2017-08-29 2017-11-17 东莞阿李自动化股份有限公司 A kind of lithium battery system of processing
CN206683582U (en) * 2017-05-03 2017-11-28 东莞市中旺精密仪器有限公司 An intelligent dual-station imager

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8682569B2 (en) * 2009-12-17 2014-03-25 GM Global Technology Operations LLC Systems and methods for diagnosing valve lift mechanisms and oil control valves of camshaft lift systems
CN101752888A (en) * 2009-12-24 2010-06-23 深圳华为通信技术有限公司 Voltage balancing device and method of battery system, and electric equipment
JP2012237665A (en) * 2011-05-12 2012-12-06 Toyota Motor Corp Battery state estimation device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202676134U (en) * 2012-06-12 2013-01-16 东莞新能源科技有限公司 A device for detecting the width dimension of square wound bare electric core
CN103737167A (en) * 2013-12-20 2014-04-23 惠州市德赛电池有限公司 An Intelligent Automatic Resistance Spot Welding Equipment
CN106058136A (en) * 2016-06-13 2016-10-26 上海捷新动力电池系统有限公司 A multi-station turntable battery automatic punching machine
CN106129447A (en) * 2016-08-08 2016-11-16 深圳市海目星激光科技有限公司 A kind of automatic production line for battery battery core with shell assembling
CN206248801U (en) * 2016-12-12 2017-06-13 深圳市德星云科技有限公司 A kind of automatic battery core OCV mechanism for testing
CN206683582U (en) * 2017-05-03 2017-11-28 东莞市中旺精密仪器有限公司 An intelligent dual-station imager
CN107359371A (en) * 2017-08-29 2017-11-17 东莞阿李自动化股份有限公司 A kind of lithium battery system of processing

Also Published As

Publication number Publication date
CN107830804A (en) 2018-03-23

Similar Documents

Publication Publication Date Title
CN108069238B (en) Cell transfer line, cell transfer system, cell OCV test equipment
CN108067436B (en) A battery cell OCV test equipment
CN105382551B (en) An automatic production line for smart watches
CN205406643U (en) Production line of soft -packaged electrical core module
CN109499926B (en) Battery detection and gear-shifting integrated machine
CN108043740A (en) Battery core OCV test equipments and its test method
CN108045945A (en) Battery core feeding system and its battery core OCV test equipments
CN107830804A (en) Battery core appearance and size detecting system and its battery core OCV test equipments
CN114156524A (en) Battery cell hot press and battery cell hot pressing method
CN103920653A (en) Integrated automatic flatness-detecting, feeding and sorting apparatus and control method
CN216780918U (en) Motor worm assembling machine
CN205309782U (en) An automatic production line for smart watches
CN107883907A (en) Thickness of workpiece detecting system and its battery core OCV test equipments
CN110542704B (en) An ultra-thin heat pipe automatic power testing machine and its working method
CN113804701B (en) Visual inspection device
CN111146491A (en) Position adjusting device and automatic detection equipment for appearance of power battery
CN112758677A (en) Automatic jig cover plate elasticity testing device and testing method
CN108807598A (en) A kind of full-automatic on-line weighting system
CN114725524A (en) Automatic folding and capability test equipment of lithium cell FPC
CN108160511B (en) Cell adjustment and positioning system and its cell OCV test equipment
CN211292672U (en) An automatic power testing machine for ultra-thin heat pipes
CN109319477B (en) Lifting type high-speed material taking and discharging platform and working method
CN110549087B (en) Automatic installation equipment for processor frame
CN108132398B (en) Cell tab shaping system and cell OCV test equipment
CN207649582U (en) Thickness of workpiece detecting system and its battery core OCV test equipments

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant