CN107780509B - Drainage system with regulation facility and integrated treatment facility and drainage control method - Google Patents
Drainage system with regulation facility and integrated treatment facility and drainage control method Download PDFInfo
- Publication number
- CN107780509B CN107780509B CN201710915222.XA CN201710915222A CN107780509B CN 107780509 B CN107780509 B CN 107780509B CN 201710915222 A CN201710915222 A CN 201710915222A CN 107780509 B CN107780509 B CN 107780509B
- Authority
- CN
- China
- Prior art keywords
- water
- conservancy switch
- water conservancy
- monitoring
- state
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 184
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 1648
- 239000010865 sewage Substances 0.000 claims abstract description 35
- 238000012544 monitoring process Methods 0.000 claims description 222
- 239000007788 liquid Substances 0.000 claims description 123
- 239000008239 natural water Substances 0.000 claims description 98
- 238000012806 monitoring device Methods 0.000 claims description 86
- 230000004308 accommodation Effects 0.000 claims description 18
- 239000003344 environmental pollutant Substances 0.000 claims description 17
- 231100000719 pollutant Toxicity 0.000 claims description 17
- 238000012876 topography Methods 0.000 claims description 15
- 239000000356 contaminant Substances 0.000 claims description 10
- 230000003287 optical effect Effects 0.000 claims description 10
- 238000009825 accumulation Methods 0.000 claims description 9
- 238000012545 processing Methods 0.000 claims description 9
- XKMRRTOUMJRJIA-UHFFFAOYSA-N ammonia nh3 Chemical compound N.N XKMRRTOUMJRJIA-UHFFFAOYSA-N 0.000 claims description 8
- 230000007613 environmental effect Effects 0.000 claims description 6
- 238000000790 scattering method Methods 0.000 claims description 5
- 238000005189 flocculation Methods 0.000 claims description 3
- 230000016615 flocculation Effects 0.000 claims description 3
- 238000004062 sedimentation Methods 0.000 claims description 3
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 claims 4
- 239000001301 oxygen Substances 0.000 claims 4
- 229910052760 oxygen Inorganic materials 0.000 claims 4
- 239000000126 substance Substances 0.000 claims 2
- 238000001514 detection method Methods 0.000 claims 1
- 239000004576 sand Substances 0.000 claims 1
- 239000000463 material Substances 0.000 abstract description 4
- 230000000694 effects Effects 0.000 abstract description 2
- 230000008569 process Effects 0.000 abstract description 2
- 210000001124 body fluid Anatomy 0.000 description 17
- 239000010839 body fluid Substances 0.000 description 17
- 239000002351 wastewater Substances 0.000 description 8
- 239000010842 industrial wastewater Substances 0.000 description 3
- 238000013461 design Methods 0.000 description 2
- 238000007599 discharging Methods 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000011144 upstream manufacturing Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 210000003608 fece Anatomy 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000010841 municipal wastewater Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
- E03F1/002—Methods, systems, or installations for draining-off sewage or storm water with disposal into the ground, e.g. via dry wells
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F7/00—Other installations or implements for operating sewer systems, e.g. for preventing or indicating stoppage; Emptying cesspools
- E03F7/02—Shut-off devices
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01D—MEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
- G01D21/00—Measuring or testing not otherwise provided for
- G01D21/02—Measuring two or more variables by means not covered by a single other subclass
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F2201/00—Details, devices or methods not otherwise provided for
- E03F2201/10—Dividing the first rain flush out of the stormwater flow
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F2201/00—Details, devices or methods not otherwise provided for
- E03F2201/20—Measuring flow in sewer systems
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Water Treatment By Electricity Or Magnetism (AREA)
- Sewage (AREA)
Abstract
The invention discloses a drainage system with a regulation facility and an integrated treatment facility and a drainage control method. The drainage system has the effect of intelligent drainage, reasonable drainage of water is realized through reasonable control of the opening degree of the water conservancy switch and related components in the drainage system by the control system, dirty water or initial rainwater is stopped to a regulation facility to the greatest extent while flood safety is ensured, the water stored in the regulation facility is treated by the integrated treatment facility and is directly drained, and the treatment pressure of a sewage treatment plant in rainy days is greatly relieved; the method effectively solves the problems that in the prior art, a sewage interception pipe cannot limit flow, clean water or later rainwater can enter the sewage interception pipe to be conveyed to a sewage treatment plant. And in the use process, manual operation is not needed, and the automatic adjustment of the water conservancy switch can be realized through the control unit, so that the hydraulic switch has the characteristics of flexibility, variability and the like, and a large amount of manpower and material resources are reduced.
Description
Technical Field
The invention belongs to the technical field of drainage, and particularly relates to a drainage system with a regulation facility and an integrated treatment facility and a drainage control method.
Background
At present, drainage systems of cities and building groups mainly comprise a diversion system, a confluence system and a mixed flow system, and the main purpose of the drainage systems is to collect, convey and treat water bodies. For example, a system for treating all waste water in one way is called a combined system. It has only one drainage system, called confluence system, and its drainage pipeline is called confluence pipeline. The system for treating wastewater with different properties in different ways is called split system, and generally has two drainage systems. One, which may be referred to as a rainwater system, is used to collect rainwater and low-pollution industrial wastewater that is directly discharged from a water body without treatment, and the pipeline is called a rainwater pipeline. Another type of system may be called a sewage system, in which domestic sewage is collected and industrial waste water which needs to be treated before it is discharged, and a pipeline thereof is called a sewage pipeline. The mixed flow system is a system between the split flow system and the combined flow system, and is mainly caused by that part of pipelines are connected in a staggered manner, mixed manner and the like in the split flow system area, so that wastewater with different properties appears in part of pipelines, namely, a rainwater pipeline or a sewage pipeline is actually changed into a combined flow pipeline. The wastewater in municipal sewage pipelines and converging pipelines is often referred to collectively as municipal wastewater.
With the advent of modern house sanitary equipment and high-rise buildings, the population is dense, and the feces are conveyed by water flow, so that the strength of urban sewage is greatly increased; in addition, the industrial wastewater is greatly increased, and intolerable pollution is caused in rivers and lakes near the city. And then, adding a sewage treatment plant, connecting the sewage treatment plant with each water outlet by using a pipeline, and collecting and treating the wastewater in each drainage main pipe by using the sewage treatment plant to form a closure type converging system. The pipeline which is connected with the water outlet and intercepts wastewater to the sewage treatment plant is called an intercepting pipeline or a sewage intercepting pipeline.
The amount of wastewater suddenly increases during rainfall, and if all the wastewater is trapped, the interception pipeline and the sewage treatment plant are inevitably required to be large in scale, and engineering cost is excessively increased. The manhole at the intersection of the drain main and the cutoff pipe is typically replaced with a diverter well. The structure of the diversion well can have different designs, but the current design is not perfect, and no improvement is made for different sewage and rain water quantities. In dry seasons, only sewage is contained in the pipe, so that the sewage can be caught by the diversion well and flows to the sewage pipe; during rainy season, part of rainwater and sewage are caught and flow into the sewage pipe, and the rest rainwater overflows through the well weir and flows to the downstream. Most of the current control methods for the flow direction of rainwater and sewage adopt water level or rainfall to control, but the current water level control method or rainfall control method is not good for the diversion control of the rainwater and the sewage, so that the meaning of a diversion well is lost.
Disclosure of Invention
In order to solve the defects of the prior art, the invention provides a drainage system with a regulation facility and an integrated treatment facility and a drainage control method, wherein the drainage system is used for intercepting and diverting rainwater and/or sewage, and the reasonable regulation and control are adopted to reasonably divert water and realize reasonable allocation of resources.
The invention provides a drainage system, which comprises a diversion well, wherein the diversion well comprises a diversion well body and three openings which are respectively a water inlet, a first water outlet and a second water outlet, wherein the three openings are arranged in the diversion well body;
the drainage system further comprises a regulation and storage facility and an integrated treatment facility, and the integrated treatment facility is connected with the first water outlet through the regulation and storage facility;
the drainage system further comprises a second water conservancy switch, a fourth water conservancy switch and an eighth water conservancy switch; the second water conservancy switch is arranged near the first water outlet and used for controlling the water passing quantity passing through the first water outlet; a fourth water conservancy switch is arranged near the second water outlet and is used for controlling the water passing quantity passing through the second water outlet; an eighth water conservancy switch is arranged near the outlet end of the regulation facility or the inlet end of the integrated treatment facility and is used for controlling the water passing through the outlet end of the regulation facility or the inlet end of the integrated treatment facility.
The invention also provides a drainage control method of the drainage system, which comprises at least one of a water level method, a water quality-water level method, a time method, a total amount method, a rainfall method, a time-water level method, a total amount-water level method and a rainfall-water level method.
The invention has the beneficial effects that:
1) The drainage system has the advantages of small occupied area, powerful functions and the like, and can realize effective separation treatment of rainwater and sewage by using a small amount of land area. The use of the drainage system is not limited by occasions, and the drainage system can be suitable for any pipe network in the drainage pipe network system.
2) The drainage system is provided with the control system, manual operation is not needed in the use process, automatic adjustment of the water conservancy switch can be realized through the control unit, the drainage system has the characteristics of flexibility, variability and the like, and a large amount of manpower and material resources are reduced. Specifically, the drainage system has the effect of intelligent drainage, reasonable drainage of water is realized by reasonably controlling the opening of the water conservancy switch and related components in the drainage system through the control system, and dirty water or initial rainwater is stopped to the greatest extent while flood safety is ensured.
3) According to the drainage system, the storage facility and the integrated treatment facility are arranged at the first water outlet, so that the safety of flood discharge is ensured, dirty water or initial rainwater is stopped to the regulation facility to the greatest extent, and the water stored in the regulation facility is further treated by the integrated treatment facility and is directly discharged, and the treatment pressure of a sewage treatment plant in rainy days is greatly relieved.
4) The second water outlet of the drainage system can be provided with an on-line treatment facility; the on-line treatment facility can effectively solve the dirty water which is still mixed when the fourth water conservancy switch is in the on state and can pollute the natural water body, and the diversion treatment of the initial rainwater and the middle and later rainwater is achieved thoroughly.
5) The drainage control method comprises a water level method, a water quality-water level method, a time method, a total amount method, a rainfall method, a time-water level method, a total amount-water level method and a rainfall-water level method, and the regulation and control of the method effectively solves the problems that a sewage interception pipe cannot limit current, clean water or later rainwater can enter the sewage interception pipe to be conveyed to a sewage treatment plant in the prior art. Through reasonable control dirty water, initial rainwater and the drainage way of middle and later period rainwater, furthest cut off dirty water to the regulation facility, discharge cleaner water to natural water.
6) According to the drainage control method, when rainfall occurs, initial rainwater which cannot be intercepted in time to a sewage treatment plant is sent to a regulation facility for storage due to high rainfall intensity, and meanwhile, the integrated treatment facility can treat the water body in the regulation facility at a constant flow, and the treated clean water body is directly discharged to a pipeline connected with a natural water body; the later-period cleaner rainwater is directly discharged to the natural water body, so that the overflow times and overflow amount during rainfall can be reduced, and the overflow pollution of the rainwater is reduced.
Drawings
FIG. 1 is a schematic view showing a structure of a drainage system according to a preferred embodiment of the present invention;
FIG. 2 is a schematic view showing the structure of a drainage system according to a preferred embodiment of the present invention;
FIG. 3 is a schematic view showing the structure of a drainage system according to a preferred embodiment of the present invention;
FIG. 4 is a schematic view showing the structure of a drainage system according to a preferred embodiment of the present invention;
FIG. 5 is a schematic view showing the structure of a drainage system according to a preferred embodiment of the present invention;
FIG. 6 is a schematic view showing the structure of a drainage system according to a preferred embodiment of the present invention;
wherein, 1-water inlet; 2-a first water outlet; 3-a second water outlet; 4-a second water conservancy switch; 5-a fourth water conservancy switch; 6-splitting the well body; 7-a regulation facility; 8-piping or galleries; 9-a water outlet pipe; 10-an integrated treatment facility; 11-eighth water conservancy switch; 41-an on-line treatment facility; 42-seventh water conservancy switch.
Detailed Description
[ drainage System ]
A first aspect of the present invention provides a drainage system comprising a diverter well body and three openings disposed in the diverter well body, a water inlet, a first water outlet and a second water outlet, respectively;
The drainage system further comprises a regulation and storage facility and an integrated treatment facility, and the integrated treatment facility is connected with the first water outlet through the regulation and storage facility;
the drainage system further comprises a second water conservancy switch, a fourth water conservancy switch and an eighth water conservancy switch; the second water conservancy switch is arranged near the first water outlet and used for controlling the water passing quantity passing through the first water outlet; a fourth water conservancy switch is arranged near the second water outlet and is used for controlling the water passing quantity passing through the second water outlet; an eighth water conservancy switch is arranged near the outlet end of the regulation facility or the inlet end of the integrated treatment facility and is used for controlling the water passing through the outlet end of the regulation facility or the inlet end of the integrated treatment facility.
In a preferred embodiment of the present invention, the drainage system further comprises a control system including a first monitoring device, a second monitoring device, and a control unit in signal connection with both; the control unit is in signal connection with the second hydraulic switch, the fourth hydraulic switch and the eighth hydraulic switch; the first monitoring device and the second monitoring device are used for monitoring signals and transmitting the monitored signals to the control unit, and the control unit controls the opening degrees of the second hydraulic switch, the fourth hydraulic switch and the eighth hydraulic switch according to the received signals.
In a preferred embodiment of the invention, the inlet end of the regulation facility is connected to the first water outlet; the outlet end of the regulation facility is connected with the integrated treatment facility.
In a preferred embodiment of the invention, the inlet end of the regulation facility is connected to the first water outlet via a pipe or gallery; the outlet end of the regulation facility is connected with the inlet end of the integrated treatment facility through a pipeline or a gallery; the outlet end of the integrated treatment facility is connected with a pipeline leading to the natural water body or directly connected with the natural water body.
In a preferred embodiment of the present invention, the drainage system further comprises a water outlet pipe; the second water outlet is connected with a pipeline leading to the natural water body through a water outlet pipe.
In a preferred embodiment of the present invention, the first monitoring device comprises a device for monitoring the water level (such as a liquid level sensor, a liquid level meter, a liquid level switch, etc.), and a device for monitoring the water quality (such as a water quality detector, an on-line COD monitor, an on-line TSS monitor, an on-line BOD monitor, an on-line TN monitor, an on-line TP monitor, an on-line NH) 3 -N monitor, on-line ammonia nitrogen monitor, electrode, conductivity meter, etc.), means for monitoring the total amount of water (for example, it may be an electric hoist with metering function, etc.), means for monitoring rainfall (such as a rain gauge, etc.), means for monitoring time (such as a timer, etc.).
In a preferred embodiment of the invention, the first monitoring device may be located inside the diverter well body or outside the diverter well body, depending on the type of requirements. For example, the device for monitoring the water level of the water body and the device for monitoring the water quality of the water body are arranged in the well body of the diversion well, the device for monitoring the rainfall is arranged outside the well body of the diversion well, the device for monitoring the total water body is arranged on a water switch in the well body of the diversion well, and the device for monitoring the time is arranged in the well body of the diversion well or outside the well body of the diversion well.
In a preferred embodiment of the invention, the second monitoring means comprises means for monitoring the level of the body of water (which may be, for example, a level sensor, a level gauge, a level switch, etc.).
In a preferred embodiment of the invention, the second monitoring device is arranged in a regulation facility.
In a preferred embodiment of the present invention, the second hydraulic switch, the fourth hydraulic switch and the eighth hydraulic switch are each independently selected from one of valves (ball valve, gate valve, knife gate valve, butterfly valve, elevation type rubber plate shutoff check valve, etc.), gates (upper open gate, lower open gate, etc.), weirs (upper open weirs, lower open weirs, rotary weirs, etc.), flaps (shutoff flaps, etc.).
In a preferred embodiment of the invention, the second hydraulic switch may perform a maximum flow restriction function, i.e. to ensure that the flow through the second hydraulic switch does not exceed a set flow value.
In a preferred embodiment of the invention, the eighth hydraulic switch may perform a maximum flow restriction function, i.e. to ensure that the flow through the eighth hydraulic switch does not exceed a set flow value.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the shapes and opening sizes of the water inlet, the first water outlet and the second water outlet are not particularly limited, and may be matched with the shape of the pipe or gallery connected thereto or the shape of the hydraulic switch provided therewith. For example, the water inlet, the first water outlet and the second water outlet are circular in shape.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the arrangement order and arrangement manner of the water inlet, the first water outlet and the second water outlet in the well body of the diversion well are not limited, and the relative positions of the water inlet, the first water outlet and the second water outlet may be set according to the area of the area where the diversion well is disposed and the topography. For example, the water inlet, the first water outlet and the second water outlet are arranged on the side wall of the well body of the diversion well.
When the water inlet, the first water outlet and the second water outlet are arranged on the side wall of the well body of the diversion well, the heights of the bottoms of the water inlet, the first water outlet and the second water outlet from the bottom of the diversion well are not particularly limited, for example, a pipeline connected with the water inlet is positioned in a high topography, and the water inlet can be arranged at any position on the side wall of the well body of the diversion well; the pipeline connected with the first water outlet and the second water outlet is positioned at a low-grade position, and the first water outlet and the second water outlet are arranged at the position, close to the bottom of the diversion well, of the side wall of the diversion well. The purpose of this is to better flow downstream so that water does not build up in the diverter well volume.
In a preferred embodiment of the present invention, those skilled in the art will understand that the shape of the well body of the diverter well is not particularly limited, and reasonable drainage of the water body may be achieved, for example, the shape of the well body of the diverter well is square or circular.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the number and arrangement of the storage facilities in the drainage system are not particularly limited, and may be reasonably arranged according to the area of the area where the system is used, for example, a plurality of storage facilities may be connected in series or in parallel. The regulation facility may be a regulation facility known in the art, including, for example, a regulation tank, a regulation box culvert, a deep tunnel, a shallow tunnel, or the like.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the number and arrangement of the integrated treatment facilities in the system are not particularly limited, and may be a plurality of integrated treatment facilities connected in series or parallel; the specific arrangement mode can be reasonably arranged according to the area of the area using the system. The integrated treatment facility may be an integrated treatment facility known in the art, including for example an integrated sewage treatment station or the like.
In a preferred embodiment of the invention, the drainage system further comprises an on-line treatment facility; the on-line treatment facility is arranged on the water outlet pipe or on a branch which is separated from the water outlet pipe pipeline and the terminal of which is integrated into the water outlet pipe pipeline; or is arranged on a branch which is separated from the water outlet pipe line and the terminal is communicated with the natural water body.
When the online processing facility is arranged on a branch which is separated from the water outlet pipe pipeline and the terminal is integrated into the water outlet pipe pipeline, a seventh water conservancy switch is arranged on the water outlet pipe pipeline and between the positions of the branch which is separated and integrated; or when the online treatment facility is arranged on the branch which is separated from the water outlet pipe pipeline and the terminal is communicated with the natural water body, a seventh water conservancy switch is arranged on the water outlet pipe pipeline and at the downstream end of the branch separating position. The seventh water conservancy switch is connected with the control unit in a signal mode, and the control unit controls the opening of the seventh water conservancy switch according to the received signal.
When the online treatment facility is arranged on the water outlet pipe line; the water body flows through the water outlet pipe and flows into the online treatment facility from the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility.
When the online treatment facility is arranged on the branch of the water outlet pipe, the flow direction of the water body is adjusted by adjusting the opening of the seventh water conservancy switch; when the seventh water conservancy switch is in an on state, part of water flows through the water outlet pipe and is directly discharged to a pipeline leading to the natural water, part of water flows through a branch arranged beside the water outlet pipe and enters the on-line treatment facility from the inlet end of the on-line treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the on-line treatment facility or is directly discharged to the pipeline leading to the natural water; when the seventh water conservancy switch is in a cut-off state, all water flows through the branch passage to enter the online treatment facility through the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility or is directly discharged to a pipeline leading to the natural water body.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the number and arrangement of the in-line processing facilities in the system are not particularly limited, and may be a plurality of in-line processing facilities connected in series or in parallel; the specific arrangement mode can be reasonably arranged according to the area of the area using the system. The on-line treatment facility may be an on-line treatment facility known in the art, including, for example, a biological filter, an on-line treatment tank, a flocculation tank, an inclined plate sedimentation tank, a grit chamber, or an artificial wetland, or the like.
In a preferred embodiment of the present invention, the seventh hydraulic switch is selected from one of a valve (ball valve, gate valve, knife gate valve, butterfly valve, elevation rubber plate shutoff check valve, etc.), a gate (upper open gate, lower open gate, etc.), a weir gate (upper open weir gate, lower open weir gate, rotary weir gate, etc.), a flap gate (shutoff flap gate, etc.).
In a preferred embodiment of the present invention, the seventh hydraulic switch may implement a maximum flow restriction function, i.e. to ensure that the flow through the seventh hydraulic switch does not exceed a set flow value.
[ drainage control method ]
The invention also provides a drainage control method of the drainage system, which comprises at least one of a water level method, a water quality-water level method, a time method, a total amount method, a rainfall method, a time-water level method, a total amount-water level method and a rainfall-water level method.
[ Water level method ]
A second aspect of the present invention provides a drainage control method controlled by a water level method, the drainage control method is based on the drainage system, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a regulation facility, and a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1a) The water body enters the diversion well from the water inlet, and the water body liquid level height H in the diversion well is monitored in real time through a device for monitoring the water body liquid level; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2a) When H is smaller than H2 and H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3a) When H is more than or equal to H2 and H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4a) When H'. Gtoreq.H2, the second water conservancy switch is in the off state, the fourth water conservancy switch is in the on state, and the eighth water conservancy switch is in the on state to guarantee that the water flows through the eighth water conservancy switch with invariable flow.
[ Water quality method ]
A third aspect of the present invention provides a drainage control method controlled by a water quality method, the drainage control method is based on the drainage system, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring water quality of a water body and is arranged in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in a regulation facility, and a standard value C1 of pollutant concentration and a highest water storage level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1b) The water body enters the diversion well from the water inlet, and the water quality C in the well body of the diversion well is monitored in real time through a device for monitoring the water quality of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2b) When C is more than or equal to C1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3b) When C < C1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
[ Water level-Water quality method ]
A fourth aspect of the present invention provides a drainage control method controlled by a water level-water quality method, the drainage control method is based on the drainage system, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water level of a water body and a device for monitoring the water quality of the water body and is arranged in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water level of the water body and is arranged in a regulation facility, and a warning water level H2 of the diversion well, a pollutant concentration standard value C1 and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1c) The water body enters the diversion well from the water inlet, the water body height H in the diversion well is monitored in real time through a device for monitoring the water body liquid level, and the water quality C in the well is monitored in real time through a device for monitoring the water quality of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2c) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3c) When H is smaller than H2 and C is larger than or equal to C1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4c) When H < H2 > and C < C1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
[ Total method ]
A fifth aspect of the present invention provides a drainage control method controlled by a total amount method, the drainage control method is based on the drainage system, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the total amount of water and is arranged on a second water switch in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water level and is arranged in a regulation facility, and a control unit of the control system is provided with a total amount of initial rain Q1 required to be intercepted by the diversion well and a highest water storage level H3 of the regulation facility; the method comprises the following steps:
1d) In rainy days, water enters the diversion well from the water inlet, and the total quantity Q of the water passing through the second water conservancy switch is monitored in real time through a device for monitoring the total quantity of the water; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2d) When Q < Q1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3d) When Q is more than or equal to Q1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
In a preferred embodiment of the invention, the method further comprises the steps of:
4d) When sunny days, the water body enters the diversion well from the water inlet, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate.
[ Total amount-Water level method ]
A sixth aspect of the present invention provides a drainage control method controlled by a total amount-water level method, the drainage control method is based on the drainage system, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the total amount of water and is arranged on a second water switch in a well body of a diversion well, the first monitoring device in the control system further comprises a device for monitoring the water level and is arranged in the well body of the diversion well, a second monitoring device in the control system comprises a device for monitoring the water level and is arranged in a regulation facility, and a standard initial rain total amount Q1 required to be intercepted by the diversion well, a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1e) In rainy days, water enters the diversion well from the water inlet, the height H of the water body in the diversion well is monitored in real time through a device for monitoring the liquid level of the water body, and the total quantity Q of the water body passing through the second water conservancy switch is monitored in real time through a device for monitoring the total quantity of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2e) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3e) When H < H2 and Q < Q1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4e) When H is smaller than H2 and Q is larger than or equal to Q1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
In a preferred embodiment of the invention, the method further comprises the steps of:
5e) When sunny days, the water body enters the diversion well from the water inlet, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate.
[ rainfall method ]
A seventh aspect of the present invention provides a drainage control method controlled by a rainfall method, where the drainage control method is based on the drainage system described above, the drainage system includes a control system, a first monitoring device in the control system includes a device for monitoring rainfall and is disposed outside a well body of a diversion well, a second monitoring device in the control system includes a device for monitoring a water body liquid level and is disposed in a regulation facility, and a standard initial rainfall L1 required to be intercepted by the diversion well and a highest water storage level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1f) The water enters the diversion well from the water inlet, and the initial rain quantity L is monitored in real time through a device for monitoring the rain quantity;
2f) When l=0, on a sunny day, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3f) When L >0, in rainy days, monitoring the water level height H' in the regulation facility in real time through a device for monitoring the water level;
4f) When 0< L1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
5f) When L is more than or equal to L1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
[ rainfall-Water level method ]
An eighth aspect of the present invention provides a drainage control method controlled by a rainfall-water level method, the drainage control method is based on the drainage system, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring rainfall and is arranged outside a well body of a diversion well, a first monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in the well body of the diversion well, a second monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in a regulation facility, and a standard initial rainfall L1 required to be intercepted by the diversion well, a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1g) The water enters the diversion well from the water inlet, and the initial rain quantity L is monitored in real time through a device for monitoring the rain quantity;
2g) When l=0, on a sunny day, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3g) When L is more than 0, in rainy days, monitoring H in real time through a device for monitoring the water level; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
4g) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
5g) When H < H2 and 0< L1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
6g) When H is smaller than H2 and L is larger than or equal to L1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
[ time law ]
A ninth aspect of the present invention provides a drainage control method controlled by a time method, the drainage control method being based on the drainage system described above, the drainage system comprising a control system, a first monitoring device in the control system comprising a device for monitoring time and being disposed in or out of a diversion well, a second monitoring device in the control system comprising a device for monitoring water level and being disposed in a regulation facility, a standard time T1 and a highest water storage level H3 of the regulation facility being set in a control unit of the control system; the method comprises the following steps:
1h) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
2h) In rainy days, water enters the diversion well from the water inlet, and rainfall time T is monitored in real time through a device for monitoring time; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
3h) When T is smaller than T1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4h) When T is more than or equal to T1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
[ time-Water level method ]
A tenth aspect of the present invention provides a drainage control method controlled by a time-water level method, the drainage control method being based on the drainage system described above, the drainage system including a control system, a first monitoring device in the control system including a device for monitoring time and being disposed in or out of a diverter well body, a first monitoring device in the control system including a device for monitoring water level and being disposed in the diverter well body, a second monitoring device in the control system including a device for monitoring water level and being disposed in a regulation facility, a standard time T1, a warning water level H2 of the diverter well, and a highest water storage water level H3 of the regulation facility being set in a control unit of the control system; the method comprises the following steps:
1i) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
2i) In rainy days, water enters the diversion well from the water inlet, the water level height H in the diversion well is monitored in real time through a device for monitoring the water level, and the rainfall time T is monitored in real time through a device for monitoring the time; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
3i) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4i) When H < H2 and T < T1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
5i) When H is smaller than H2 and T is larger than or equal to T1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
[ concrete limitation of the above method ]
In a preferred embodiment of the present invention, when the drainage system comprises an on-line treatment facility, the method further comprises the steps of:
when the fourth water conservancy switch is in an on state and the on-line treatment facility is arranged on the water outlet pipe line; the water body flows through the water outlet pipe and flows into the online treatment facility from the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility.
When the fourth water conservancy switch is in an on state and the on-line treatment facility is arranged on the branch of the water outlet pipe, the flow direction of the water body is adjusted by adjusting the opening of the seventh water conservancy switch; when the seventh water conservancy switch is in an on state, part of water flows through the water outlet pipe and is directly discharged to a pipeline leading to the natural water, part of water flows through a branch arranged beside the water outlet pipe and enters the on-line treatment facility from the inlet end of the on-line treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the on-line treatment facility or is directly discharged to the pipeline leading to the natural water; when the seventh water conservancy switch is in a cut-off state, all water flows through a branch arranged beside the water outlet pipe and enters the online treatment facility from the inlet end of the online treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility or is directly discharged to a pipeline leading to natural water.
In a preferred embodiment of the invention, the warning water level H2 of the diverter well is set in the control unit of the control system according to the height of the diverter well corresponding to the lowest point of the topography in the water receiving area when there is a risk of water accumulation.
In a preferred embodiment of the invention, the highest water storage level H3 of the regulation facility is set in the control unit of the control system as a function of the capacity of the regulation facility.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
In a preferred embodiment of the present invention, the standard value of the pollutant concentration C1 is set in the control unit of the control system according to the environmental capacity of the natural water discharged and the quality of the water entering the diversion well.
In a preferred embodiment of the invention, the device for monitoring the water quality of the water body is a water quality detector, an online COD monitor, an online ammonia nitrogen monitor, an online TSS monitor, an online BOD monitor and an online NH 3 -N monitor, on-line TP monitor, on-line TN monitor, electrode, conductivity meter, etc., which monitors the concentration of contaminants in the water in the well body of the shunt well, said contaminants comprising TSS, COD, BOD, NH 3 -N, TN or TP.
In a preferred embodiment of the present invention, the water quality detector may detect the water quality of the water body by using an electrode method, a UV optical method, an optical scattering method, or the like.
In a preferred embodiment of the present invention, the environmental capacity of the natural water body discharged by the diversion well may be a natural water body such as a river, a lake or a sea; when the environment capacity of the natural water body is large (such as ocean), the pollutant concentration standard value C1 can be properly improved; when the environment capacity of the natural water body is smaller (such as a lake), the pollutant concentration standard value C1 can be properly reduced. When the water quality of the water body entering the diversion well is good, if the water body is middle-late-stage rainwater, the pollutant concentration standard value C1 can be properly reduced; when the water quality of the water body entering the diversion well is poor, such as domestic sewage and/or initial rainwater, the pollutant concentration standard value C1 can be properly improved. The purpose is to reduce pollution to natural water as little as possible.
In a preferred embodiment of the invention, a standard total amount of initial rain Q1 required to be intercepted by the diversion well is set in the control unit of the control system according to the total amount of initial rain required to be collected in the corresponding water receiving area of the diversion well.
In a preferred embodiment of the invention, the device for monitoring the total water body is selected from an electric hoist with a metering function.
In a preferred embodiment of the invention, a standard initial rain amount L1 of the diversion well to be intercepted is set in a control unit of the control system according to the millimeter number of the initial rain to be collected in the corresponding water receiving area of the diversion well.
In a preferred embodiment of the present invention, the device for monitoring rainfall is a rain gauge.
In a preferred embodiment of the present invention, the standard time T1 is set in the control unit of the control system according to the rainfall time of the initial rainwater and the time required for the entire initial rainwater to flow to the diversion well in the corresponding water receiving area of the diversion well.
In a preferred embodiment of the present invention, the means for monitoring the time is a timer.
In a preferred embodiment of the present invention, the second hydraulic switch, the seventh hydraulic switch and the eighth hydraulic switch may implement a maximum flow limiting function, and the on state of the second hydraulic switch, which means that the flow value through the hydraulic switch is less than or equal to a set maximum flow value, may be implemented by adjusting the opening of the hydraulic switch by a control unit in a control system.
In a preferred embodiment of the present invention, the fourth hydraulic switch being in an on state means that the water body can flow to the natural water body through the hydraulic switch.
In a preferred embodiment of the present invention, the fourth hydraulic switch and the seventh hydraulic switch are in a shut-off state, which means that the opening degree of the hydraulic switch is adjusted, so that the water body is shut-off at the upstream end of the hydraulic switch, and cannot flow to the natural water body through the hydraulic switch.
In a preferred embodiment of the present invention, the water conservancy switch being in an off state means that the flow value of the water body passing through the water conservancy switch is zero.
The invention will be further illustrated with reference to specific examples. It is to be understood that these examples are illustrative of the present invention and are not intended to limit the scope of the present invention. Further, it is understood that various changes and modifications of the invention will become apparent to those skilled in the art upon reading the description herein, and such equivalents are intended to fall within the scope of the invention as defined by the appended claims.
In the description of the present invention, it should be noted that the terms "first," "second," "fourth," "seventh," and "eighth" are used for descriptive purposes only and are not intended to indicate or imply relative importance.
Example 1
As shown in fig. 1 and 2, the present embodiment provides a drainage system, which includes a diversion well including a diversion well body 6 and three openings provided in the diversion well body 6, namely a water inlet 1, a first water outlet 2 and a second water outlet 3;
the drainage system further comprises a regulation facility 7 and an integrated treatment facility 10, wherein the integrated treatment facility is connected with the first water outlet through the regulation facility;
the drainage system further comprises a second water conservancy switch 4, a fourth water conservancy switch 5 and an eighth water conservancy switch 11; wherein, a second water conservancy switch 4 is arranged near the first water outlet 2 and is used for controlling the water passing through the first water outlet 2; a fourth water conservancy switch 5 is arranged near the second water outlet 3 and is used for controlling the water passing amount passing through the second water outlet 3; an eighth water switch 11 is provided near the outlet end of the regulation facility 7 or the inlet end of the integrated treatment facility 10 for controlling the amount of excess water passing through the outlet end of the regulation facility 7 or the inlet end of the integrated treatment facility 10.
In a preferred embodiment of the present invention, the drainage system further comprises a control system including a first monitoring device, a second monitoring device and a control unit signally connected thereto; the control unit is in signal connection with the second water conservancy switch 4, the fourth water conservancy switch 5 and the eighth water conservancy switch 11; the first monitoring device and the second monitoring device are used for monitoring signals and transmitting the monitored signals to the control unit, and the control unit controls the opening degrees of the second water conservancy switch 4, the fourth water conservancy switch 5 and the eighth water conservancy switch 11 according to the received signals.
In a preferred embodiment of the invention, the inlet end of the regulation facility 7 is connected to the first water outlet 2; the outlet end of the regulation facility 7 is connected with an integrated treatment facility 10.
In a preferred embodiment of the invention, the inlet end of the regulation facility 7 is connected to the first water outlet 2 by a pipe or gallery 8; the outlet end of the regulation facility 7 is connected with the inlet end of the integrated treatment facility 10 through a pipeline or a gallery; the outlet end of the integrated treatment facility 10 is connected to a pipeline leading to a natural body of water or directly to a natural body of water.
In a preferred embodiment of the invention, the drainage system further comprises a water outlet pipe 9; the second water outlet 3 is connected with a pipeline leading to the natural water body through a water outlet pipe 9.
In a preferred embodiment of the present invention, the first monitoring device comprises a device for monitoring the water level (such as a liquid level sensor, a liquid level meter, a liquid level switch, etc.), and a device for monitoring the water quality (such as a water quality detector, an on-line COD monitor, an on-line TSS monitor, an on-line BOD monitor, an on-line TN monitor, an on-line TP monitor, an on-line NH) 3 -N monitor, online ammonia nitrogen monitor, electrode, conductivity meter, etc.), device for monitoring total water (for example, it can be electric hoist with metering function, etc.), device for monitoring rainfall (such as rain gauge, etc.), device for monitoring time At least one of (e.g., a timer, etc.).
In a preferred embodiment of the invention, the first monitoring device may be located inside the diverter well body or outside the diverter well body, depending on the type of requirements. For example, the device for monitoring the water level of the water body and the device for monitoring the water quality of the water body are arranged in the well body of the diversion well, the device for monitoring the rainfall is arranged outside the well body of the diversion well, the device for monitoring the total water body is arranged on a water switch in the well body of the diversion well, and the device for monitoring the time is arranged in the well body of the diversion well or outside the well body of the diversion well.
In a preferred embodiment of the invention, the second monitoring means comprises means for monitoring the level of the body of water (which may be, for example, a level sensor, a level gauge, a level switch, etc.); the second monitoring device is arranged in the regulation facility.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the arrangement order and arrangement manner of the water inlet, the first water outlet and the second water outlet in the well body of the diversion well are not limited, and the relative positions of the water inlet, the first water outlet and the second water outlet may be set according to the area of the area where the diversion well is disposed and the topography. For example, the water inlet, the first water outlet and the second water outlet are arranged on the side wall of the well body of the diversion well.
When the water inlet, the first water outlet and the second water outlet are arranged on the side wall of the well body of the diversion well, the heights of the bottoms of the water inlet, the first water outlet and the second water outlet from the bottom of the diversion well are not particularly limited, for example, a pipeline connected with the water inlet is positioned in a high topography, and the water inlet can be arranged at any position on the side wall of the well body of the diversion well; the pipeline connected with the first water outlet and the second water outlet is positioned at a low-grade position, and the first water outlet and the second water outlet are arranged at the position, close to the bottom of the diversion well, of the side wall of the diversion well. The purpose of this is to better flow downstream so that water does not build up in the diverter well volume.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the number and arrangement of the storage facilities in the drainage system are not particularly limited, and may be reasonably arranged according to the area of the area where the system is used, for example, a plurality of storage facilities may be connected in series or in parallel; the regulation facility may be a regulation facility known in the art, including, for example, a regulation tank, a regulation box culvert, a deep tunnel, a shallow tunnel, or the like.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the number and arrangement of the integrated treatment facilities in the system are not particularly limited, and may be a plurality of integrated treatment facilities connected in series or parallel; the specific arrangement mode can be reasonably arranged according to the area of the area using the system. The integrated treatment facility may be an integrated treatment facility known in the art, including for example an integrated sewage treatment station or the like.
In a preferred embodiment of the present invention, the second hydraulic switch, the fourth hydraulic switch and the eighth hydraulic switch are each independently selected from one of valves (ball valve, gate valve, knife gate valve, butterfly valve, elevation type rubber plate shutoff check valve, etc.), gates (upper open gate, lower open gate, etc.), weirs (upper open weirs, lower open weirs, rotary weirs, etc.), flaps (shutoff flaps, etc.).
In a preferred embodiment of the invention, the second hydraulic switch may perform a maximum flow restriction function, i.e. to ensure that the flow through the second hydraulic switch does not exceed a set flow value.
In a preferred embodiment of the invention, the eighth hydraulic switch may perform a maximum flow restriction function, i.e. to ensure that the flow through the eighth hydraulic switch does not exceed a set flow value.
Example 2
As shown in fig. 3-6, the present embodiment also provides a drainage system comprising the drainage system of embodiment 1, further comprising an on-line treatment facility 41;
as shown in fig. 3-4, the on-line treatment facility is arranged on the water outlet pipe 9;
when the online treatment facility is arranged on the water outlet pipe line; the water body flows through the water outlet pipe and flows into the online treatment facility from the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility.
As shown in fig. 5-6, the on-line treatment facility is arranged on a branch which branches off from the pipe of the water outlet pipe 9 and the terminal ends of which merge into the pipe of the water outlet pipe 9; or is arranged on a branch which is separated from the pipeline of the water outlet pipe 9 and the terminal is communicated with the natural water body.
When the on-line processing facility is arranged on a branch which is separated from the water outlet pipe line and the terminal is integrated into the water outlet pipe line, a seventh water conservancy switch 42 is arranged on the water outlet pipe line and between the positions where the branch is separated and integrated; alternatively, when the on-line treatment facility is disposed on a branch line branching from the water outlet pipe line and terminating in communication with the natural water body, a seventh water conservancy switch 42 is disposed on the water outlet pipe line and at a downstream end of the branching position. The seventh water conservancy switch is connected with the control unit in a signal mode, and the control unit controls the opening of the seventh water conservancy switch according to the received signal.
When the online treatment facility is arranged on the branch of the water outlet pipe, the flow direction of the water body is adjusted by adjusting the opening of the seventh water conservancy switch; when the seventh water conservancy switch is in an on state, part of water flows through the water outlet pipe and is directly discharged to a pipeline leading to the natural water, part of water flows through a branch arranged beside the water outlet pipe and enters the on-line treatment facility from the inlet end of the on-line treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the on-line treatment facility or is directly discharged to the pipeline leading to the natural water; when the seventh water conservancy switch is in a cut-off state, all water flows through the branch passage to enter the online treatment facility through the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility or is directly discharged to a pipeline leading to the natural water body.
In a preferred embodiment of the present invention, it will be understood by those skilled in the art that the number and arrangement of the in-line processing facilities in the system are not particularly limited, and may be a plurality of in-line processing facilities connected in series or in parallel; the specific arrangement mode can be reasonably arranged according to the area of the area using the system. The on-line treatment facility may be an on-line treatment facility known in the art, including, for example, a biological filter, an on-line treatment tank, a flocculation tank, an inclined plate sedimentation tank, a grit chamber, or an artificial wetland, or the like.
In a preferred embodiment of the present invention, the seventh hydraulic switch is selected from one of a valve (ball valve, gate valve, knife gate valve, butterfly valve, elevation rubber plate shutoff check valve, etc.), a gate (upper open gate, lower open gate, etc.), a weir gate (upper open weir gate, lower open weir gate, rotary weir gate, etc.), a flap gate (shutoff flap gate, etc.).
In a preferred embodiment of the present invention, the seventh hydraulic switch may implement a maximum flow restriction function, i.e. to ensure that the flow through the seventh hydraulic switch does not exceed a set flow value.
In the above embodiments 1-2, it will be understood by those skilled in the art that the shape of the well body of the diversion well is different when the diversion well is used in different places, and the shape of the well body of the diversion well is particularly suitable for the area with smaller area when the diversion well is circular, the occupation area of the circular diversion well is generally smaller, and the installation and arrangement of other drainage devices are realized by saving the area of the land. When not limited by the area of use, a diverting well of square structure may be used, in which the space that can be accommodated is large, and a plurality of devices having different functions, such as a device for removing silt and a device for removing floating materials and suspended materials, may be provided in the space.
Specifically, the shape of the well body of the diversion well is circular, as shown in fig. 1, 3 and 5; the shape of the well body of the diversion well is square, as shown in fig. 2, 4 and 6.
Example 3
The embodiment provides a drainage control method controlled by a water level method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a well body of a diversion well, and a warning water level H2 of the diversion well is set in a control unit of the control system according to the height of a lowest point of a topography in a corresponding water receiving area of the diversion well when a ponding risk occurs; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1a) The water body enters the diversion well from the water inlet, and the water body liquid level height H in the diversion well is monitored in real time through a device for monitoring the water body liquid level; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2a) When the height H of the water body fluid in the diversion well is smaller than the warning water level H2 and the height H' of the water body fluid in the regulation facility is smaller than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3a) When the water body height H in the diversion well is more than or equal to the warning water level H2 and the water body level height H' in the regulation facility is less than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; discharging part of water body to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
4a) When the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility into the integrated treatment facility at a constant flow rate.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
Example 4
The embodiment provides a drainage control method controlled by a water quality method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring water quality of a water body and is arranged in a well body of a diversion well, and a pollutant concentration standard value C1 is set in a control unit of the control system according to the environmental capacity of a discharged natural water body and the water quality of the water body entering the diversion well; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1b) The water body enters the diversion well from the water inlet, and the water quality C in the well body of the diversion well is monitored in real time through a device for monitoring the water quality of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2b) When the water quality C of the water body in the well is more than or equal to the pollutant concentration standard value C1, if the water body liquid level height H' in the regulation facility is smaller than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3b) When the water quality C of the water body in the well is smaller than the standard value C1 of the pollutant concentration, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state; the water body flows through a pipeline connected with the natural water body through the water outlet pipe and is further discharged into the natural water body.
In a preferred embodiment of the invention, the device for monitoring the water quality of the water body is a water quality detector, an online COD monitor, an online ammonia nitrogen monitor, an online TSS monitor, an online BOD monitor and an online NH 3 -N monitor, on-line TP monitor, on-line TN monitor, electrode, conductivity meter, etc., which monitors the concentration of contaminants in the water in the well body of the shunt well, said contaminants comprising TSS, COD, BOD, NH 3 -N, TN or TP. The water quality detector can be used for detecting the water quality of the water body by adopting an electrode method, a UV optical method, an optical scattering method and the like.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
Example 5
The embodiment provides a drainage control method controlled by a water level-water quality method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water level of a water body and a device for monitoring the water quality of the water body, the first monitoring device and the device are both arranged in a well body of a diversion well, and the warning water level H2 of the diversion well is set in a control unit of the control system according to the height of a lowest point of a topography in a corresponding water receiving area of the diversion well when a ponding risk occurs; setting a pollutant concentration standard value C1 in a control unit of the control system according to the environmental capacity of the discharged natural water body and the water quality of the water body entering the diversion well; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1c) The water body enters the diversion well from the water inlet, the water body height H in the diversion well is monitored in real time through a device for monitoring the water body liquid level, and the water quality C in the well is monitored in real time through a device for monitoring the water quality of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2c) When the height H of the water body fluid in the diversion well is more than or equal to the warning water level H2; if the water level height H' of the water body in the regulation and storage facility is smaller than the highest water storage level H3 of the regulation and storage facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; discharging part of water body to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3c) When the height H of the water body in the diversion well is smaller than the warning water level H2 and the water quality C of the water body in the well is larger than or equal to the standard value C1 of the pollutant concentration, if the height H' of the water body in the regulation facility is smaller than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
4c) When the height H of the water body in the diversion well is smaller than the warning water level H2 and the water quality C of the water body in the well is smaller than the standard value C1 of the pollutant concentration, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state; the water body flows through a pipeline connected with the natural water body through the water outlet pipe and is further discharged into the natural water body.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
In a preferred embodiment of the invention, the device for monitoring the water quality of the water body is a water quality detector, an online COD monitor, an online ammonia nitrogen monitor, an online TSS monitor, an online BOD monitor and an online NH 3 -N monitor, on-line TP monitor, on-line TN monitor, electrode, conductivity meter, etc., which monitors the concentration of contaminants in the water in the well body of the shunt well, said contaminants comprising TSS, COD, BOD, NH 3 -N, TN or TP. The water quality detector can be used for detecting the water quality of the water body by adopting an electrode method, a UV optical method, an optical scattering method and the like.
Example 6
The embodiment provides a drainage control method controlled by a total amount method, the drainage control method is based on the drainage system described in the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the total amount of water body and is arranged on a second water conservancy switch in a well body of a diversion well, and the total amount Q1 of initial rain needed to be intercepted by the diversion well is set in a control unit of the control system according to the millimeter number of the initial rain needed to be collected in a corresponding water receiving area of the diversion well; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1d) In rainy days, water enters the diversion well from the water inlet, and the total quantity Q of the water passing through the second water conservancy switch is monitored in real time through a device for monitoring the total quantity of the water; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2d) When the total water volume Q passing through the second water conservancy switch is smaller than Q1, if the water level height H' in the regulation facility is smaller than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3d) When the total water quantity Q passing through the second water conservancy switch is more than or equal to Q1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body;
4d) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility into the integrated treatment facility at a constant flow rate.
In a preferred embodiment of the invention, the device for monitoring the total water body is selected from an electric hoist with a metering function.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
Example 7
The embodiment provides a drainage control method controlled by a total amount-water level method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the total amount of water and is arranged on a second water switch in a well body of a diversion well, the first monitoring device in the control system also comprises a device for monitoring the water level and is arranged in the well body of the diversion well, and a standard total amount Q1 of initial rain needed to be intercepted by the diversion well is set in a control unit of the control system according to the total amount of initial rain needed to be collected in a corresponding water collecting area of the diversion well; setting a warning water level H2 of the diversion well in a control unit of the control system according to the height of the lowest point of the topography in the corresponding water receiving area of the diversion well when the water accumulation risk occurs; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1e) In rainy days, water enters the diversion well from the water inlet, the height H of the water body in the diversion well is monitored in real time through a device for monitoring the liquid level of the water body, and the total quantity Q of the water body passing through the second water conservancy switch is monitored in real time through a device for monitoring the total quantity of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2e) When the water body fluid level H in the diversion well is more than or equal to the warning water level H2, if the water body fluid level H' in the regulation facility is less than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3e) When the height H of the water body fluid in the diversion well is smaller than the warning water level H2 and the total water body quantity Q < Q1 of the second water conservancy switch is passed, if the height H' of the water body fluid in the regulation facility is smaller than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
4e) When the height H of the water body in the diversion well is smaller than the warning water level H2 and the total water quantity Q of the second water conservancy switch is more than or equal to Q1, the fourth water conservancy switch is in an on state, the second water conservancy switch is in an off state, and the eighth water conservancy switch is in an off state; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body;
5e) When sunny days, the water body enters the diversion well from the water inlet, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
In a preferred embodiment of the invention, the device for monitoring the total water body is selected from an electric hoist with a metering function.
Example 8
The embodiment provides a drainage control method controlled by a rainfall method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring rainfall and is arranged outside a well body of a diversion well, and a standard initial rainfall L1 of the diversion well to be intercepted is set in a control unit of the control system according to the initial rainfall millimeter number required to be collected in a corresponding water receiving area of the diversion well; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1f) The water enters the diversion well from the water inlet, and the initial rain quantity L is monitored in real time through a device for monitoring the rain quantity;
2f) When l=0, on a sunny day, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3f) When L >0, in rainy days, monitoring the water level height H' in the regulation facility in real time through a device for monitoring the water level;
4f) When the initial rain amount L is 0< the standard initial rain amount L1, if the water level height H' in the regulation facility is equal to the highest water storage level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
5f) When the initial rain quantity L is more than or equal to the standard initial rain quantity L1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state; the water body flows through a pipeline connected with the natural water body through the water outlet pipe and is further discharged into the natural water body.
In a preferred embodiment of the present invention, the device for monitoring rainfall is a rain gauge.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
Example 9
The embodiment provides a drainage control method controlled by a rainfall-water level method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring rainfall and is arranged outside a well body of a diversion well, the first monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in the well body of the diversion well, and a standard initial rainfall L1 required to be intercepted by the diversion well is set in a control unit of the control system according to the number of initial rainfall millimeters required to be collected in a corresponding water receiving area of the diversion well; setting a warning water level H2 of the diversion well in a control unit of the control system according to the height of the lowest point of the topography in the corresponding water receiving area of the diversion well when the water accumulation risk occurs; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1g) The water enters the diversion well from the water inlet, and the initial rain quantity L is monitored in real time through a device for monitoring the rain quantity;
2g) When l=0, on a sunny day, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
3g) When L is more than 0, in rainy days, the water level height H in the diversion well is monitored in real time through a device for monitoring the water level; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
4g) When the water body fluid level H in the diversion well is more than or equal to the warning water level H2, if the water body fluid level H' in the regulation facility is less than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
5g) When the height H of the water body fluid in the diversion well is smaller than the warning water level H2 and the initial rain quantity L is smaller than the standard initial rain quantity L1, if the height H' of the water body fluid in the regulation facility is smaller than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
6g) When the height H of the water body fluid in the diversion well is smaller than the warning water level H2 and the initial rain quantity L is more than or equal to the standard initial rain quantity L1, the fourth water conservancy switch is in an on state, the second water conservancy switch is in an off state, and the eighth water conservancy switch is in an off state; the water body flows through a pipeline connected with the natural water body through the water outlet pipe and is further discharged into the natural water body.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
In a preferred embodiment of the present invention, the device for monitoring rainfall is a rain gauge.
Example 10
The embodiment provides a drainage control method controlled by a time method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring time and is arranged in or out of a diversion well body, and standard time T1 is set in a control unit of the control system according to the rainfall time of initial rainwater and the time required by the diversion well to totally run off the initial rainwater in a corresponding water receiving area to the diversion well; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1h) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
2h) In rainy days, water enters the diversion well from the water inlet, and rainfall time T is monitored in real time through a device for monitoring time; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
3h) When the rainfall time T is less than the standard time T1, if the water level height H' in the regulation facility is less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
4h) When the rainfall time T is more than or equal to the standard time T1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state; the water body flows through a pipeline connected with the natural water body through the water outlet pipe and is further discharged into the natural water body.
In a preferred embodiment of the present invention, the means for monitoring the time is a timer.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
Example 11
The embodiment provides a drainage control method controlled by a time-water level method, the drainage control method is based on the drainage system of the embodiment 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring time and is arranged in or out of a diversion well body, the first monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in the diversion well body, and standard time T1 is set in a control unit of the control system according to rainfall time of initial rainwater and time required by the diversion well to totally run off the initial rainwater to the diversion well in a corresponding water receiving area; setting a warning water level H2 of the diversion well in a control unit of the control system according to the height of the lowest point of the topography in the area corresponding to the water receiving area of the diversion well when the water accumulation risk occurs; the second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the regulation facility, and the highest water storage water level H3 of the regulation facility is set in the control unit of the control system according to the accommodation capacity of the regulation facility; the method comprises the following steps:
1i) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
2i) In rainy days, water enters the diversion well from the water inlet, the water level height H in the diversion well is monitored in real time through a device for monitoring the water level, and the rainfall time T is monitored in real time through a device for monitoring the time; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
3i) When the water body fluid level H in the diversion well is more than or equal to the warning water level H2, if the water body fluid level H' in the regulation facility is less than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
4i) When the height H of the water body fluid in the diversion well is smaller than the warning water level H2 and the rainfall time T is smaller than the standard time T1, if the height H' of the water body fluid in the regulation facility is smaller than the highest water storage water level H3 of the regulation facility, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an intercepting state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body is discharged to a regulation facility for temporary storage; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility; if the water level height H' of the water body in the regulation facility is not less than the highest water storage level H3 of the regulation facility, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; the water body flows through a pipeline connected with the natural water body through a water outlet pipe and is further discharged into the natural water body; at this time, the water body temporarily stored in the regulation facility flows through the outlet end of the regulation facility at a constant flow rate into the integrated treatment facility;
5i) When the height H of the water body fluid in the diversion well is smaller than the warning water level H2 and the rainfall time T is more than or equal to the standard time T1, the fourth water conservancy switch is in an on state, the second water conservancy switch is in an off state, and the eighth water conservancy switch is in an off state; the water body flows through a pipeline connected with the natural water body through the water outlet pipe and is further discharged into the natural water body.
In a preferred embodiment of the invention, the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter, a liquid level switch and the like.
In a preferred embodiment of the present invention, the means for monitoring the time is a timer.
Example 12
When the drainage system includes an on-line treatment facility, that is, the drainage system corresponding to embodiment 2, the drainage control methods of embodiments 3 to 11 described above are adopted, and further include the steps of:
when the fourth water conservancy switch is in an on state and the on-line treatment facility is arranged on the water outlet pipe line; the water body flows through the water outlet pipe and flows into the online treatment facility from the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility.
When the fourth water conservancy switch is in an on state and the on-line treatment facility is arranged on the branch of the water outlet pipe, the flow direction of the water body is adjusted by adjusting the opening of the seventh water conservancy switch; when the seventh water conservancy switch is in an on state, part of water flows through the water outlet pipe and is directly discharged to a pipeline leading to the natural water, part of water flows through a branch arranged beside the water outlet pipe and enters the on-line treatment facility from the inlet end of the on-line treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the on-line treatment facility or is directly discharged to the pipeline leading to the natural water; when the seventh water conservancy switch is in a cut-off state, all water flows through a branch arranged beside the water outlet pipe and enters the online treatment facility from the inlet end of the online treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility or is directly discharged to a pipeline leading to natural water.
In the above embodiments 3 to 12, the second hydraulic switch, the seventh hydraulic switch and the eighth hydraulic switch may implement a maximum flow restriction function, and the on state of the second hydraulic switch, the seventh hydraulic switch and the eighth hydraulic switch means that the flow value through the hydraulic switch is smaller than or equal to the set maximum flow value, which may be implemented by adjusting the opening of the hydraulic switch by a control unit in the control system.
In the above embodiments 3 to 12, the fourth hydraulic switch being in the on state means that the water body may flow to the natural water body through the hydraulic switch.
In the foregoing embodiments 3 to 12, the fourth hydraulic switch and the seventh hydraulic switch being in the shut-off state means that the opening degree of the hydraulic switch is adjusted, so that the water body is guaranteed to be shut off at the upstream end of the hydraulic switch, and cannot flow to the natural water body through the hydraulic switch.
In embodiments 3-12 above, the water conservancy switch being in the off state means that the flow value of the water body passing through the water conservancy switch is zero.
The embodiments of the present invention have been described above. However, the present invention is not limited to the above embodiment. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (30)
1. The drainage system is characterized by comprising a diversion well, wherein the diversion well comprises a diversion well body and three openings which are respectively a water inlet, a first water outlet and a second water outlet and are arranged in the diversion well body;
the drainage system further comprises a regulation and storage facility and an integrated treatment facility, wherein the integrated treatment facility is connected with the first water outlet through the regulation and storage facility, and the inlet end of the regulation and storage facility is connected with the first water outlet; the outlet end of the regulation facility is connected with the integrated treatment facility;
the drainage system further comprises a water outlet pipe; the second water outlet is connected with a pipeline leading to the natural water body through a water outlet pipe;
the drainage system further comprises a second water conservancy switch, a fourth water conservancy switch and an eighth water conservancy switch; the second water conservancy switch is arranged near the first water outlet and used for controlling the water passing quantity passing through the first water outlet; a fourth water conservancy switch is arranged near the second water outlet and is used for controlling the water passing quantity passing through the second water outlet; an eighth water conservancy switch is arranged near the outlet end of the regulation facility or the inlet end of the integrated treatment facility and is used for controlling the water passing through the outlet end of the regulation facility or the inlet end of the integrated treatment facility;
The drainage system further comprises a control system, wherein the control system comprises a first monitoring device, a second monitoring device and a control unit in signal connection with the first monitoring device and the second monitoring device; the control unit is in signal connection with the second hydraulic switch, the fourth hydraulic switch and the eighth hydraulic switch; the first monitoring device and the second monitoring device are used for monitoring signals and transmitting the monitored signals to the control unit, and the control unit controls the opening degrees of the second hydraulic switch, the fourth hydraulic switch and the eighth hydraulic switch according to the received signals;
the first monitoring device can be arranged in the well body of the diversion well or outside the well body of the diversion well according to type requirements; the second monitoring device is arranged in the regulation facility.
2. The drainage system of claim 1, wherein the inlet end of the storage facility is connected to the first water outlet by a pipe or gallery; the outlet end of the regulation facility is connected with the inlet end of the integrated treatment facility through a pipeline or a gallery; the outlet end of the integrated treatment facility is connected with a pipeline leading to the natural water body or directly connected with the natural water body.
3. The drainage system of claim 1 wherein the first monitoring means comprises at least one of means for monitoring the level of the body of water, means for monitoring the quality of the body of water, means for monitoring the total amount of water, means for monitoring the amount of rain, and means for monitoring time.
4. A system according to claim 3, wherein the means for monitoring the level of the body of water is selected from a level sensor, a level gauge or a level switch; the device for monitoring the water quality of the water body is selected from a water quality detector, an online COD monitor, an online TSS monitor, an online BOD monitor, an online TN monitor, an online TP monitor and an online NH 3 -an N monitor, an online ammonia nitrogen monitor, an electrode or a conductivity meter; the device for monitoring the total water body is selected from an electric hoist with a metering function; the device for monitoring the rainfall is selected from a rain gauge; the means for monitoring the time is selected from a timer.
5. A system according to claim 3, wherein the means for monitoring the level of the body of water and the means for monitoring the quality of the body of water are located in the diverter well body, the means for monitoring the amount of rain is located outside the diverter well body, the means for monitoring the total amount of water is located on a water switch in the diverter well body, and the means for monitoring the time is located in or outside the diverter well body.
6. A system according to any one of claims 1-3, wherein the second monitoring means comprises means for monitoring the level of the body of water, the means for monitoring the level of the body of water being selected from a level sensor, a level gauge or a level switch.
7. A system according to any one of claims 1-3, characterized in that the regulation facility is a plurality of regulation facilities connected in series or in parallel; the regulation facility comprises a regulation pool, a regulation box culvert and a deep tunnel or shallow tunnel;
the integrated treatment facilities are a plurality of integrated treatment facilities connected in series or in parallel; the integrated treatment facility includes an integrated sewage treatment station.
8. A system according to any one of claims 1-3, wherein the drainage system further comprises an on-line treatment facility; the on-line treatment facility is arranged on the water outlet pipe or on a branch which is separated from the water outlet pipe pipeline and the terminal of which is integrated into the water outlet pipe pipeline; or is arranged on a branch which is separated from the water outlet pipe line and the terminal is communicated with the natural water body.
9. The system of claim 8, wherein when the on-line processing facility is disposed on a branch that branches off from and terminates in the outlet pipe line, a seventh water switch is disposed on the outlet pipe line between the locations where the branches branch off and merge; or when the online treatment facility is arranged on the branch which is separated from the water outlet pipe pipeline and the terminal is communicated with the natural water body, a seventh water conservancy switch is arranged on the water outlet pipe pipeline and at the downstream end of the branch separating position.
10. The system of claim 9, wherein the seventh hydraulic switch is in signal connection with a control unit, the control unit controlling the opening of the seventh hydraulic switch based on the received signal;
and/or the online processing facility is a plurality of online processing facilities connected in series or in parallel; the online treatment facility comprises a biological filter, an online treatment tank, a flocculation tank, an inclined plate sedimentation tank, a sand setting tank or an artificial wetland.
11. A water level method controlled drainage control method, characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a regulation facility, and a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1a) The water body enters the diversion well from the water inlet, and the water body liquid level height H in the diversion well is monitored in real time through a device for monitoring the water body liquid level; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2a) When H is smaller than H2 and H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3a) When H is more than or equal to H2 and H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4a) When H'. Gtoreq.H2, the second water conservancy switch is in the off state, the fourth water conservancy switch is in the on state, and the eighth water conservancy switch is in the on state to guarantee that the water flows through the eighth water conservancy switch with invariable flow.
12. The drainage control method according to claim 11, wherein the guard water level H2 of the diversion well is set in the control unit of the control system according to the height of the lowest point of the topography in the corresponding water receiving area of the diversion well when the risk of water accumulation occurs;
and/or setting a highest water storage level H3 of the regulation facility in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch.
13. A drainage control method controlled by a water quality method, which is characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water quality of a water body and is arranged in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a regulation facility, and a pollutant concentration standard value C1 and the highest water storage level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1b) The water body enters the diversion well from the water inlet, and the water quality C of the water body in the well is monitored in real time through a device for monitoring the water quality of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2b) When C is more than or equal to C1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3b) When C < C1, the fourth water conservancy switch is in an on state, the second water conservancy switch is in an off state, and the eighth water conservancy switch is in an off state.
14. The drain control method according to claim 13, wherein a highest water storage level H3 of the regulation facility is set in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting a pollutant concentration standard value C1 in a control unit of the control system according to the environmental capacity of the discharged natural water body and the water quality of the water body entering the diversion well;
and/or the device for monitoring the water quality of the water body is a water quality detector, an online COD (chemical oxygen demand) monitor, an online ammonia nitrogen monitor, an online TSS (TSS) monitor, an online BOD (biochemical oxygen demand) monitor and an online NH (NH) monitor 3 -N monitor, on-line TP monitor, on-line TN monitor, electrode, conductivity meter, which monitors the concentration of contaminants in the water in the well body of the shunt well, said contaminants comprising TSS, COD, BOD, NH 3 -one or more of N, TN or TP;
and/or the water quality detector adopts an electrode method, a UV optical method and an optical scattering method to realize the detection of the water quality of the water body.
15. A water level-water quality method controlled drainage control method, characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the water level of a water body and a device for monitoring the water quality of the water body and is arranged in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water level of the water body and is arranged in a regulation facility, and a warning water level H2 of the diversion well, a pollutant concentration standard value C1 and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1c) The water body enters the diversion well from the water inlet, the water body height H in the diversion well is monitored in real time through a device for monitoring the water body liquid level, and the water quality C in the well is monitored in real time through a device for monitoring the water quality of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2c) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3c) When H is smaller than H2 and C is larger than or equal to C1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4c) When H < H2 > and C < C1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
16. The drainage control method according to claim 15, wherein the guard water level H2 of the diversion well is set in the control unit of the control system according to the height of the lowest point of the topography in the corresponding water receiving area of the diversion well when the risk of water accumulation occurs;
and/or setting a highest water storage level H3 of the regulation facility in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting a pollutant concentration standard value C1 in a control unit of the control system according to the environmental capacity of the discharged natural water body and the water quality of the water body entering the diversion well;
And/or the device for monitoring the water quality of the water body is a water quality detector, an online COD (chemical oxygen demand) monitor, an online ammonia nitrogen monitor, an online TSS (TSS) monitor, an online BOD (biochemical oxygen demand) monitor and an online NH (NH) monitor 3 -N monitor, on-line TP monitor, on-line TN monitor, electrode, conductivity meter, which monitors the concentration of contaminants in the water in the well body of the shunt well, said contaminants comprising TSS, COD, BOD, NH 3 -one or more of N, TN or TP;
and/or the water quality detector adopts an electrode method, a UV optical method and an optical scattering method to detect the water quality of the water body.
17. A drainage control method controlled by a total amount method is characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the total amount of water body and is arranged on a second water switch in a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the liquid level of the water body and is arranged in a regulation facility, and the total amount of initial rain Q1 required to be intercepted by the diversion well and the highest water storage level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1d) In rainy days, water enters the diversion well from the water inlet, and the total quantity Q of the water passing through the second water conservancy switch is monitored in real time through a device for monitoring the total quantity of the water; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2d) When Q < Q1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3d) When Q is more than or equal to Q1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state;
4d) When sunny days, the water body enters the diversion well from the water inlet, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate.
18. The drain control method according to claim 17, wherein a highest water storage level H3 of the regulation facility is set in a control unit of the control system according to the accommodation capacity of the regulation facility;
And/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting the standard total amount of primary rain Q1 required to be intercepted by the diversion well in a control unit of the control system according to the total amount of primary rain required to be collected in the corresponding water receiving area of the diversion well;
and/or the device for monitoring the total water body is selected from an electric hoist with a metering function.
19. A drainage control method controlled by a total water level method, which is characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the total water amount and is arranged on a second water switch in a well body of a diversion well, the first monitoring device in the control system also comprises a device for monitoring the water level and is arranged in the well body of the diversion well, a second monitoring device in the control system comprises a device for monitoring the water level and is arranged in a regulation facility, and a standard initial rain total amount Q1 required to be intercepted by the diversion well, a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1e) In rainy days, water enters the diversion well from the water inlet, the height H of the water body in the diversion well is monitored in real time through a device for monitoring the liquid level of the water body, and the total quantity Q of the water body passing through the second water conservancy switch is monitored in real time through a device for monitoring the total quantity of the water body; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
2e) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3e) When H < H2 and Q < Q1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4e) When H is smaller than H2 and Q is larger than or equal to Q1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
20. The drainage control method of claim 19, wherein the method further comprises the steps of:
5e) When sunny days, the water body enters the diversion well from the water inlet, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate.
21. The drainage control method according to claim 20, wherein the guard water level H2 of the diversion well is set in the control unit of the control system according to the height of the lowest point of the topography in the corresponding water receiving area of the diversion well when the risk of water accumulation occurs;
and/or setting a highest water storage level H3 of the regulation facility in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting the standard total amount of primary rain Q1 required to be intercepted by the diversion well in a control unit of the control system according to the total amount of primary rain required to be collected in the corresponding water receiving area of the diversion well;
And/or the device for monitoring the total water body is selected from an electric hoist with a metering function.
22. A drainage control method controlled by a rainfall method, which is characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring rainfall and is arranged outside a well body of a diversion well, a second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a regulation facility, and a control unit of the control system is provided with a standard initial rainfall L1 required to be intercepted by the diversion well and a highest water storage level H3 of the regulation facility; the method comprises the following steps:
1f) The water enters the diversion well from the water inlet, and the initial rain quantity L is monitored in real time through a device for monitoring the rain quantity;
2f) When l=0, on a sunny day, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3f) When L >0, in rainy days, monitoring the water level height H' in the regulation facility in real time through a device for monitoring the water level;
4f) When 0< L1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
5f) When L is more than or equal to L1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
23. The drain control method according to claim 22, wherein a highest water storage level H3 of the regulation facility is set in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting a standard initial rain amount L1 of the diversion well to be intercepted in a control unit of the control system according to the initial rain millimeter number required to be collected in the corresponding water receiving area of the diversion well;
and/or the device for monitoring the rainfall is a rain gauge.
24. A drainage control method controlled by a rainfall-water level method, which is characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring the rainfall and is arranged outside a well body of a diversion well, a first monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in the well body of the diversion well, a second monitoring device in the control system comprises a device for monitoring the water body liquid level and is arranged in a regulation facility, and a standard initial rainfall L1 required to be intercepted by the diversion well, a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1g) The water enters the diversion well from the water inlet, and the initial rain quantity L is monitored in real time through a device for monitoring the rain quantity;
2g) When l=0, on a sunny day, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
3g) When L is more than 0, in rainy days, monitoring H in real time through a device for monitoring the water level; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
4g) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
5g) When H < H2 and 0< L1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
6g) When H is smaller than H2 and L is larger than or equal to L1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
25. The drainage control method of claim 24, wherein the guard water level H2 of the diverter well is set in the control unit of the control system according to the height of the diverter well corresponding to the lowest point of the topography in the water receiving area when the risk of water accumulation occurs;
And/or setting a highest water storage level H3 of the regulation facility in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting a standard initial rain amount L1 of the diversion well to be intercepted in a control unit of the control system according to the initial rain millimeter number required to be collected in the corresponding water receiving area of the diversion well;
and/or the device for monitoring the rainfall is a rain gauge.
26. A time-controlled drainage control method, characterized in that the drainage control method is based on the drainage system according to claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring time and is arranged in or out of a diversion well body, a second monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in a regulation facility, and a standard time T1 and the highest water storage level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1h) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
2h) In rainy days, water enters the diversion well from the water inlet, and rainfall time T is monitored in real time through a device for monitoring time; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
3h) When T is smaller than T1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4h) When T is more than or equal to T1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
27. The drain control method according to claim 26, wherein a highest water storage level H3 of the regulation facility is set in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting standard time T1 in a control unit of the control system according to the rainfall time of the initial rainwater and the time required for the total initial rainwater in the corresponding water receiving area of the diversion well to flow to the diversion well;
And/or, the device for monitoring the time is a timer.
28. A drainage control method controlled by a time-water level method, characterized in that the drainage control method is based on the drainage system of claim 1, the drainage system comprises a control system, a first monitoring device in the control system comprises a device for monitoring time and is arranged in a well body of a diversion well or outside the well body of the diversion well, a first monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in the well body of the diversion well, a second monitoring device in the control system comprises a device for monitoring water body liquid level and is arranged in a regulation facility, and a standard time T1, a warning water level H2 of the diversion well and a highest water storage water level H3 of the regulation facility are set in a control unit of the control system; the method comprises the following steps:
1i) When the water enters the diversion well from the water inlet on sunny days, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
2i) In rainy days, water enters the diversion well from the water inlet, the water level height H in the diversion well is monitored in real time through a device for monitoring the water level, and the rainfall time T is monitored in real time through a device for monitoring the time; the water level height H' in the regulation facility is monitored in real time through a device for monitoring the water level;
3i) When H is more than or equal to H2, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in an on state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
4i) When H < H2 and T < T1, if H' < H3, the second water conservancy switch is in an on state, the fourth water conservancy switch is in a cut-off state, the eighth water conservancy switch is in an on state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate; if H'. Gtoreq.H2, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, the eighth water conservancy switch is in an open state, and the water body is ensured to flow through the eighth water conservancy switch at a constant flow rate;
5i) When H is smaller than H2 and T is larger than or equal to T1, the second water conservancy switch is in a closed state, the fourth water conservancy switch is in an open state, and the eighth water conservancy switch is in a closed state.
29. The drainage control method of claim 28, wherein the guard water level H2 of the diverter well is set in the control unit of the control system according to the height of the diverter well corresponding to the lowest point of the topography in the water receiving area when the risk of water accumulation occurs;
And/or setting a highest water storage level H3 of the regulation facility in a control unit of the control system according to the accommodation capacity of the regulation facility;
and/or the device for monitoring the water body liquid level is a liquid level sensor, a liquid level meter and a liquid level switch;
and/or setting standard time T1 in a control unit of the control system according to the rainfall time of the initial rainwater and the time required for the total initial rainwater in the corresponding water receiving area of the diversion well to flow to the diversion well;
and/or, the device for monitoring the time is a timer.
30. The method of any one of claims 11-29, wherein when the drainage system comprises an on-line treatment facility, the method further comprises the steps of:
when the fourth water conservancy switch is in an on state and the on-line treatment facility is arranged on the water outlet pipe line; the water body flows through the water outlet pipe to flow into the online treatment facility from the inlet end of the online treatment facility, and after being treated, flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility;
when the fourth water conservancy switch is in an on state and the on-line treatment facility is arranged on the branch of the water outlet pipe, the flow direction of the water body is adjusted by adjusting the opening of the seventh water conservancy switch; when the seventh water conservancy switch is in an on state, part of water flows through the water outlet pipe and is directly discharged to a pipeline leading to the natural water, part of water flows through a branch arranged beside the water outlet pipe and enters the on-line treatment facility from the inlet end of the on-line treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the on-line treatment facility or is directly discharged to the pipeline leading to the natural water; when the seventh water conservancy switch is in a cut-off state, all water flows through a branch arranged beside the water outlet pipe and enters the online treatment facility from the inlet end of the online treatment facility, and after treatment, the water flows into the downstream end of the water outlet pipe from the outlet end of the online treatment facility or is directly discharged to a pipeline leading to natural water.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710915222.XA CN107780509B (en) | 2017-09-30 | 2017-09-30 | Drainage system with regulation facility and integrated treatment facility and drainage control method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710915222.XA CN107780509B (en) | 2017-09-30 | 2017-09-30 | Drainage system with regulation facility and integrated treatment facility and drainage control method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107780509A CN107780509A (en) | 2018-03-09 |
CN107780509B true CN107780509B (en) | 2024-03-26 |
Family
ID=61434077
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710915222.XA Active CN107780509B (en) | 2017-09-30 | 2017-09-30 | Drainage system with regulation facility and integrated treatment facility and drainage control method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107780509B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109736252B (en) * | 2019-02-21 | 2020-02-18 | 中国水利水电科学研究院 | Urban river sewage interception box culvert sewage disposal and diversion method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04265329A (en) * | 1991-02-21 | 1992-09-21 | Hazama Gumi Ltd | Rain-water disposal method of sewerags system, and construction method of rain-water disposal equipment and rain-water retardation pipe line |
CN103410215A (en) * | 2013-08-06 | 2013-11-27 | 嘉兴市规划设计研究院有限公司 | Method for separate system rainwater discharge outlet tail end regulation and storage and pollution interception and control |
CN105064494A (en) * | 2015-07-17 | 2015-11-18 | 武汉圣禹排水系统有限公司 | Rainwater closure system |
CN106592735A (en) * | 2016-12-30 | 2017-04-26 | 武汉圣禹排水系统有限公司 | Separate-zone rainwater flow, regulation and storage, and on-line treatment system with obvious initial rainwater feature under separate system and mixed flow system |
CN107190842A (en) * | 2017-05-27 | 2017-09-22 | 武汉圣禹排水系统有限公司 | A kind of control method for shunting of accurately being removed contamination for rainwater |
-
2017
- 2017-09-30 CN CN201710915222.XA patent/CN107780509B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04265329A (en) * | 1991-02-21 | 1992-09-21 | Hazama Gumi Ltd | Rain-water disposal method of sewerags system, and construction method of rain-water disposal equipment and rain-water retardation pipe line |
CN103410215A (en) * | 2013-08-06 | 2013-11-27 | 嘉兴市规划设计研究院有限公司 | Method for separate system rainwater discharge outlet tail end regulation and storage and pollution interception and control |
CN105064494A (en) * | 2015-07-17 | 2015-11-18 | 武汉圣禹排水系统有限公司 | Rainwater closure system |
CN106592735A (en) * | 2016-12-30 | 2017-04-26 | 武汉圣禹排水系统有限公司 | Separate-zone rainwater flow, regulation and storage, and on-line treatment system with obvious initial rainwater feature under separate system and mixed flow system |
CN107190842A (en) * | 2017-05-27 | 2017-09-22 | 武汉圣禹排水系统有限公司 | A kind of control method for shunting of accurately being removed contamination for rainwater |
Also Published As
Publication number | Publication date |
---|---|
CN107780509A (en) | 2018-03-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107605006B (en) | Drainage system and drainage control method | |
CN107587580B (en) | Drainage system with hydraulic downward opening type weir gate and pump drainage and drainage control method | |
CN100429360C (en) | Water flow quality-divided discharge method for urban river rain and sewage mixed flow pipe network | |
CN107761900A (en) | It is a kind of to carry the double shunting wells of flap gate including the drainage system of the shunting well and water discharge control method | |
CN107653958B (en) | A kind of drainage system and water discharge control method with facility of regulating and storing | |
CN107620367B (en) | Drainage system with sewage interception pipe and regulation facility and drainage control method | |
CN107842088A (en) | A kind of drainage system and water discharge control method with regulate and store facility and online treatment facility | |
CN207959445U (en) | A kind of drainage system with regulate and store facility and online processing facility | |
CN107558593B (en) | Drainage system comprising one-in four-out type diversion well and drainage control method | |
CN107605005A (en) | A kind of drainage system and water discharge control method arranged with waterpower non-return weir gate and pump | |
CN207761004U (en) | A kind of shunting well with downflow weir and the drainage system including the shunting well | |
CN107587579B (en) | Drainage system with sewage interception pipe and rainwater treatment facility and drainage control method | |
CN107806154B (en) | Drainage system with on-line treatment facility and drainage control method | |
CN107780509B (en) | Drainage system with regulation facility and integrated treatment facility and drainage control method | |
CN207761003U (en) | A kind of drainage system with regulate and store facility and integrated treatment facility | |
CN207760985U (en) | A kind of band surges the drainage system of bottom-open type weir gate and pump row | |
CN107761902B (en) | Drainage system with sewage interception pipe and on-line treatment facility and drainage control method | |
CN207760984U (en) | A kind of drainage system managed with section dirt with online processing facility | |
CN107587581B (en) | Drainage system with rainwater treatment system and drainage control method | |
CN207436183U (en) | A kind of carry cuts dirty pipe, a drainage system for regulate and store facility and online treatment facility | |
CN107605007B (en) | Drainage system with treatment facility and drainage control method | |
CN207436176U (en) | A kind of drainage system with online treatment facility | |
CN107747347B (en) | Drainage system with rainwater treatment system and drainage control method | |
CN107761898B (en) | A kind of drainage system and water discharge control method with facility of regulating and storing | |
CN207760980U (en) | It is a kind of to carry the drainage system for cutting dirty pipe and facility of regulating and storing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |