CN107762055A - The body composite board of Fast Installation heat insulation decorative load-bearing one - Google Patents

The body composite board of Fast Installation heat insulation decorative load-bearing one Download PDF

Info

Publication number
CN107762055A
CN107762055A CN201711241231.1A CN201711241231A CN107762055A CN 107762055 A CN107762055 A CN 107762055A CN 201711241231 A CN201711241231 A CN 201711241231A CN 107762055 A CN107762055 A CN 107762055A
Authority
CN
China
Prior art keywords
steel pipe
light steel
vertical
plate
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711241231.1A
Other languages
Chinese (zh)
Other versions
CN107762055B (en
Inventor
张延年
刘悦
汪青杰
董天泽
刘金升
刘庆
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201711241231.1A priority Critical patent/CN107762055B/en
Publication of CN107762055A publication Critical patent/CN107762055A/en
Application granted granted Critical
Publication of CN107762055B publication Critical patent/CN107762055B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/26Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups
    • E04C2/284Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups at least one of the materials being insulating
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/46Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose specially adapted for making walls

Abstract

The present invention relates to a kind of body composite board of Fast Installation heat insulation decorative load-bearing one, its inside and outside two surface is arranged to interior decoration flaggy and exterior decoration flaggy, centre sets equally distributed vertical light steel pipe and horizontal light steel pipe, and sets vertical macroporous cellulose net respectively inside and outside the two;Respectively pre-buried insulation tension member, the insulation equal transverse and longitudinal of tension member are in a row for decorative plies, exterior decoration flaggy indoors;Full bubble concrete layer is poured between decorative plies, exterior decoration flaggy indoors.The method have the advantages that the overall coordination performance of wall is good, energy-efficient performance is high, using entirety without heat bridge technology, can effectively cut off heat bridge, have good heat-insulating property, significantly improve anti-seismic performance;Using dry construction, connector quantity is greatly reduced;Wallboard density is greatly reduced, reduces wall piece quantity, reduces connection, significantly shortens the duration, reduces cost, promotes China's housing industrialization development process, reduces resource and energy resource consumption.

Description

The body composite board of Fast Installation heat insulation decorative load-bearing one
Technical field
The present invention relates to a kind of building energy conservation wall, is protected more particularly to the Fast Installation load-bearing that a kind of energy saving building uses Warm decorating integrative composite plate.
Background technology
Assembly concrete building refers to based on the concrete prefabricated element with factorial praluction, pass through site-assembled side The concrete structure class building construction of formula design-build.The assembly method of component pours overlapping layer concrete, steel after typically having scene Pouring concrete connection etc. after muscle anchors, bar connecting can be connected, welded using sleeve grouting, mechanically connected and reserving hole overlaps The ways such as connection.In the 1980s, in the popular prefabricated big plate house in China, due to structural integrity is poor, seepage, The reasons such as cracks on floor slab, the hidden danger and defect of many influence structure safety and normal use be present, gradually by cast-in-place concrete knot Structure is substituted.But with the application of current emerging prefabricated concrete structure, particularly introduce in recent years many external first Enter technology, localized prefabricated concrete structure is built new technology and just gradually formed.
As the quickening of China " building industrialization, housing industrialization " process, and the continuous of Chinese " demographic dividend " subtract Less, the waste appearance of building trade recruitment, the trend of housing industry industrialization are increasingly obvious.The application weight of prefabricated concrete structure New to turn into current research focus, all parts of the country continue to bring out out new technology, the new model of residential housing prefabricated concrete structure. Precast reinforced concrete structure is one of important directions of China's building structure development, and it is advantageous to China's building industrialization Development, improve production efficiency and save the energy, develop Green environmental-protection building, and be advantageous to improve and ensure construction engineering quality. Compared with cast-in-situ construction method, assembled reinforced concrete structure is advantageous to green construction, because fabricated construction can more meet green construction Save land, save, saving the requirement such as material, water saving and environmental protection, reduce the negative effect to environment, including reduce noise, prevent Airborne dust, reduce environmental pollution, clean transport, reduce place interference, save resource and the energy such as water, electricity, material, it then follows be sustainable The principle of development.Moreover, fabricated construction can continuously complete multiple or whole processes of engineering in order, so as to reduce into The engineering machinery type and quantity of field, eliminate procedure connection rests the time, realizes interchange operation, reduces workmen, So as to improve work efficiency, reduction supplies consumption, reduce environmental pollution, provided safeguard for green construction.In addition, fabricated construction compared with Building waste (account for municipal refuse total amount 30% -40%) is reduced in big degree, such as steel scrap muscle, waste iron wire, useless bamboo wood material, useless Abandon concrete etc..
Assembly concrete building can be divided into two major classes of full assembling and part assembling according to assembling degree height.Full assembling Building is generally limited to low layer or the relatively low tier building of requirements for fortification against earthquake;Part assembling concrete construction main member is general Using prefabricated components, at the scene connected by cast-in-place concrete, form the building of cast in place and precast construction.
North America region is mainly based on America & Canada.Because prefabricated/prestressed concrete association (PCI) studies for a long period of time With promoting pre-cast building, the Specification of precast concrete is also very perfect, so its assembly concrete Application in Building is non- It is often universal.The pre-cast building of North America mainly includes building prefabrication exterior wall and structure prefabricated components two are serial greatly, and prefabricated components are total to It is that maximization and prestressing force are combined with feature, structural reinforcement and connecting structure can be optimized.Reduce making and installation workload, contracting The short Yi works duration, fully demonstrate industrialization, standardization and Technical Economy feature.In 20th century, the pre-cast building of North America is main For the non-antidetonation fortified defence area of low layer.Due to the earthquake effect in California area, antidetonation and on the middle and senior level prefabricated is paid much attention in recent years The engineer applied technical research of structure.PCI is published recently《Precast concrete Aseismic Design》One book, from theory and practice Analyze the Aseismic Design problem of pre-cast building, the newest section for summarizing many precast construction Aseismic Designs is ground into angle system Fruit, to instructing precast construction design and engineer applied popularization that there is very strong directive significance.
Europe is the cradle of pre-cast building, and the road of building industrialization has been begun to early in the 17th century.Second of the world is big After the war, due to human resources shortage, Europe further research and probe building industrialization pattern.Either economically developed north Europe, West Europe, or Eastern Europe underdeveloped, all actively carrying out the design and construction side of prefabrication and assembly construction concrete construction always Formula.The design and construction experience of many pre-cast buildings is have accumulated, various special precast building systems is formd and standardizes general Pre-manufactured product series, and a series of precast concrete engineering specifications and application manual have been worked out, to promoting precast concrete complete The application in the world serves very important effect.
Japan and South Korea have used for reference the successful experience of America and Europe, on the basis of the standardized designs construction of pre-cast building is explored, With reference to oneself requirement, breakthrough is achieved in terms of precast construction system globality antidetonation and shock design, has and represents Property achievement two 58 floor for being Japan 2008 and being built up using prefabrication and assembly construction frame structure Tokyo Tower.It is meanwhile Japanese pre- Concrete construction System Design processed, making and the standard criterion of construction are also very perfect, and the prefabricated specification used at present has《It is prefabricated mixed Coagulate geotechnological journey (JASSl0) and《Concrete curtain wall) (JASSl4).
China from the sixties in 20th century five begin one's study assembly concrete building design and construction technology, form one Serial assembly concrete building system, more typical building system have assembled single storey industry workshop building system, assembling Formula multistory frame building system, assembled large panel building system etc..To the application of assembly concrete building the 1980s Reach the period of full bloom, many places in the whole nation all form the assembly concrete industry of design, making and construction and installation integration Change architectural mode.Assembly concrete is built and turns into two kinds of most important building bodies using the masonry building of prefabricated hollow floor System, application popularization rate is up to more than 70%.Because many limitations and deficiency, China be present in the function and physical property of assembled architecture Assembly concrete architectural design and construction technology R & D Level do not catch up with also social demand and Building technology development change. To mid-term the 1990s, assembly concrete building is gradually substituted by full cast-in-place concrete building system, at present except dress Applied with formula single storey industry workshop building system outside wide, the engineer applied of other prefabrication systems is few, in advance The globality of structural seismic processed and the specialized research of management in design and operation are inadequate, cause its Technical Economy poor, are to cause The basic reason that precast construction stagnates for a long time.
At present, prefabricated concrete structure is wet construction, and complicated construction technique, cost is high, and due to wall density Greatly, therefore wallboard can not be prefabricated larger, otherwise can run into series of problems in processing, transport and hoisting engineering;Due to insulation No matter the presence of layer, set inside holding, sandwich heat preservation or external thermal insulation, can significantly reduce the globality of wall piece;In addition, even It is more complicated to connect mode, execute-in-place runs into more difficulty, and adds the duration, and cost is obviously improved.
The content of the invention
It is integrally multiple the invention provides a kind of Fast Installation heat insulation decorative load-bearing in order to solve above-mentioned technical problem Plywood, using the insulation material with higher-strength and bond performance, effectively solves the entirety of assembly concrete energy-saving wall Synergisticing performance, improve energy-efficient performance;Using dry construction, simplify construction technology, and connector quantity is greatly reduced, be obviously improved It industrializes efficiency;Wallboard density is greatly reduced, reduces wall piece quantity, reduces connection, reduces in processing, transport and hoisting engineering In caused by wallboard weight is excessive series of problems;Process is connected by simplifying, execute-in-place difficulty is reduced, significantly shortens Duration, cost is reduced, promote China's housing industrialization development process, reduce resource and energy resource consumption.
The technical solution adopted by the present invention is as follows:
The body composite board of Fast Installation heat insulation decorative load-bearing one, including it is interior decoration flaggy (1), exterior decoration flaggy (2), vertical light Steel pipe (3), vertically connect end plate (4), horizontal light steel pipe (5), horizontal connection end plate (6), bubble concrete layer (7), macropore fibre Tie up net (8), insulation tension member (9), adjustable screw (10) and installation reserved opening (11);
The body composite board of Fast Installation heat insulation decorative load-bearing one is arranged to rectangular slab, and two surface is respectively interior decoration flaggy (1) and exterior decoration flaggy (2), interior decoration flaggy (1) and exterior decoration flaggy (2) they are reinforcing fiber concrete slab, Side sets vertical and equally distributed enhancing tooth respectively in plate;
Indoors among decorative plies (1) and exterior decoration flaggy (2), some be parallel to each other and equally distributed vertical light is set Steel pipe (3), vertical light steel pipe (3) to 2 to two/5ths that the distance of plate left and right ends is vertically light steel pipe (3) spacing/ One, vertical light steel pipe (3) elongated setting up and down, and internal filling high-strength concrete, strength of high strength concrete C40-C60; Vertical light steel pipe (3) upper and lower ends connect vertical connection end plate (4) respectively, vertically connect end plate (4) and are welded with vertical light steel pipe (3) Connect, it is rectangular slab vertically to connect end plate (4);
In the horizontal direction, set it is some be parallel to each other and equally distributed horizontal light steel pipe (5), on horizontal light steel pipe (5) to plate The distance at lower both ends is horizontal light steel pipe (5) spacing 2/5ths to half, horizontal light steel pipe (5) and vertical light steel pipe (3) selection type is identical with size, and between vertical light steel pipe (3), horizontal light steel pipe (5) welds with vertical light steel pipe (3), Light steel pipe (5) inner opposite end of level in outside welds with vertical light steel pipe (3), and lateral ends set horizontal connection end plate (6), Horizontal connection end plate (6) respectively extends the left and right outward flange of the body composite board of Fast Installation heat insulation decorative load-bearing one;Wall both ends Horizontal connection end plate (6) on respectively open up 4 adjustable screws (10), adjustable screw (10) is strip hole, strip hole Centre is rectangle, and both ends are semicircle;Adjustable screw (10) is located at four angles of horizontal connection end plate (6) respectively, in level Or vertical direction arrangement;Adjacent adjustable screw (10) is mutually vertical, and one of them adjustable screw (10) is pointed to separately The midpoint of one adjustable screw (10):When the adjustable screw of one end same position (10) is horizontal, then other end correspondence position Adjustable screw (10) it is vertical;When the adjustable screw of one end same position (10) is vertical, then other end correspondence position can Mode screw (10) is horizontal;Central plane and interior decoration flaggy (1) where vertical light steel pipe (3) and horizontal light steel pipe (5) Distance be with the distance of exterior decoration flaggy (2) 1/2 ~ 1;
Vertical macroporous cellulose net (8) is set respectively inside and outside vertical light steel pipe (3) and horizontal light steel pipe (5);Macropore The mesh diameter of web (8) is 3-10mm, and macroporous cellulose net (8) extends Fast Installation heat insulation decorative load-bearing one up and down The outward flange of body composite board;
Decorative plies (1), exterior decoration flaggy (2) are respectively pre-buried indoors is incubated tension member (9), the insulation tension member of both sides (9) correspond and be connected with each other, insulation tension member (9) transverse and longitudinal is in a row;
Full bubble concrete layer (7) is poured between decorative plies (1), exterior decoration flaggy (2) indoors;
Vertical connection end plate (4) and horizontal connection end plate (6) and coupled vertical light steel pipe (3) and horizontal light steel pipe (5) installation reserved opening (11) is reserved in decorative plies (1) side indoors for end, and installation reserved opening (11) is rectangle, is vertically connected End plate (4) and horizontal connection end plate (6) is connect in reserved installation reserved opening (11) to expose.
Further, described interior decoration flaggy (1) uses cement fibrolite plate, thickness 5-15mm;Indoor decorative plate The outer surface of layer (1) is straight, and inner surface carries equally distributed vertical rib.
Further, described exterior decoration flaggy (2) uses cement fibrolite plate, thickness 10-40mm;Exterior decoration plate The outer surface of layer (2) is straight or carries equally distributed vertical rib with uniform vertical impression, inner surface.
Further, the thermal conductivity factor of described bubble concrete layer (7) is 0.06-0.08W/ (m.K), and its dry volume is close Spend for 300-400kg/m3
Further, described macroporous cellulose net (8) prioritizing selection polypropylene fiber net, steel wire, wire netting or the Black Warrior Rock web, mesh diameter 3-10mm.
Further, described insulation tension member (9) prioritizing selection PVC tension members, glass fibre tension member, synthetic resin Tension member or basalt fibre tension member.
Beneficial effects of the present invention are:It is an advantage of the invention that the overall coordination performance of wall is good, energy-efficient performance is high, uses Entirety can effectively cut off heat bridge, have good heat-insulating property, significantly improve anti-seismic performance, simplification is applied without heat bridge technology Work;Using dry construction, simplify construction technology, and connector quantity is greatly reduced, be obviously improved it and industrialize efficiency;Significantly drop Parapet plate density, wall piece quantity is reduced, reduce connection, be easy to process, transport and lift;Connect process significantly to simplify, scene behaviour It is convenient to make very simple, significantly shortens the duration, reduces cost, promotes China's housing industrialization development process, reduces resource and energy Source consumes.
Brief description of the drawings
Fig. 1 is elevational schematic view on the inside of the body composite board of Fast Installation heat insulation decorative load-bearing one.
Fig. 2 is the body composite board indoor perspective diagram of Fast Installation heat insulation decorative load-bearing one.
Fig. 3 is Fig. 1 A-A diagrammatic cross-sections.
Fig. 4 is the side view perspective diagram of the body composite board of Fast Installation heat insulation decorative load-bearing one
In figure, 1 is interior decoration flaggy;2 be exterior decoration flaggy;3 be vertical light steel pipe;4 be vertical connection end plate;5 be water Put down light steel pipe;6 be horizontal connection end plate;7 be bubble concrete layer;8 be macroporous cellulose net;9 be insulation tension member;10 be adjustable Formula screw;11 be installation reserved opening.
Embodiment
In order to further illustrate the present invention, below in conjunction with the accompanying drawings and the present invention is described in detail embodiment, but not They can be interpreted as limiting the scope of the present invention.
Embodiment:As Figure 1-Figure 4, the body composite board of Fast Installation heat insulation decorative load-bearing one is arranged to rectangular slab, and it two Individual surface is respectively interior decoration flaggy (1) and exterior decoration flaggy (2), interior decoration flaggy (1) and exterior decoration flaggy (2) It is reinforcing fiber concrete slab, vertical and equally distributed enhancing tooth is set respectively;Interior decoration flaggy (1) is fine using cement Plate is tieed up, thickness is that its outer surface of 5-15mm is straight, and side carries equally distributed vertical rib in plate;Exterior decoration flaggy (2) Using cement fibrolite plate, thickness 10-40mm;Its outer surface is straight or carries equal with uniform vertical impression, inner surface The vertical rib of even distribution.
As shown in figure 1, indoors among decorative plies (1) and exterior decoration flaggy (2), some be parallel to each other and is set The vertical light steel pipe (3) of even distribution, the distance of vertical light steel pipe (3) to plate left and right ends is the five of vertical light steel pipe (3) spacing / bis- to half, vertical light steel pipe (3) elongated setting up and down, and internal filling high-strength concrete, high-strength concrete are strong Spend for C40-C60;Connect vertical connection end plate (4) respectively in vertical light steel pipe (3) upper and lower ends, vertically connect end plate (4) with Vertical light steel pipe (3) welding, it is rectangular slab vertically to connect end plate (4);Vertical connection end plate (4) and horizontal connection end plate (6) with And the end reserved installation in decorative plies (1) side indoors of coupled vertical light steel pipe (3) and horizontal light steel pipe (5) Reserved opening (11), installation reserved opening (11) is rectangle, and it is pre- in reserved installation vertically to connect end plate (4) and horizontal connection end plate (6) Stay and expose in mouth (11).
As shown in Fig. 2 in the horizontal direction, set it is some be parallel to each other and equally distributed horizontal light steel pipe (5), it is horizontal light Steel pipe (5) to the distance of plate upper and lower ends is horizontal light steel pipe (5) spacing 2/5ths to half, horizontal light steel pipe (5) identical with size with vertical light steel pipe (3) selection type, between vertical light steel pipe (3), horizontal light steel pipe (5) is with erecting Welded to light steel pipe (3), light steel pipe (5) inner opposite end of the level in outside is welded with vertical light steel pipe (3), and lateral ends are set Horizontal connection end plate (6), horizontal connection end plate (6) respectively extend the left and right of the body composite board of Fast Installation heat insulation decorative load-bearing one Outward flange.
As shown in figure 4,4 adjustable screws (10) are respectively opened up on the horizontal connection end plate (6) at wall both ends, it is adjustable Formula screw (10) is strip hole, is rectangle among strip hole, and both ends are semicircle;Adjustable screw (10) connects positioned at horizontal respectively Four angles of end plate (6) are connect, are arranged in horizontal or vertical direction;Adjacent adjustable screw (10) is mutually vertical, and wherein One adjustable screw (10) points to the midpoint of another adjustable screw (10):When the adjustable screw of one end same position (10) When horizontal, then the adjustable screw (10) of other end correspondence position is vertical;When the adjustable screw of one end same position (10) is vertical When, then the adjustable screw (10) of other end correspondence position is horizontal.
As Figure 3-Figure 4, vertical light steel pipe (3) and the horizontal gently central plane and Indoor decorative plate where steel pipe (5) The distance of layer (1) is 1/2 ~ 1 with the distance of exterior decoration flaggy (2);
Vertical macroporous cellulose net (8) is set respectively inside and outside vertical light steel pipe (3) and horizontal light steel pipe (5);Macropore The mesh diameter of web (8) is 3-10mm, and macroporous cellulose net (8) extends Fast Installation heat insulation decorative load-bearing one up and down The outward flange of body composite board;Macroporous cellulose net (8) prioritizing selection polypropylene fiber net, steel wire, wire netting or basalt fibre Net, mesh diameter 3-10mm;
Decorative plies (1), exterior decoration flaggy (2) are respectively pre-buried indoors is incubated tension member (9), the insulation tension member of both sides (9) correspond and be connected with each other, insulation tension member (9) transverse and longitudinal is in a row;Insulation tension member (9) prioritizing selection PVC tension members, Glass fibre tension member, synthetic resin tension member or basalt fibre tension member;
Full bubble concrete layer (7) is poured between decorative plies (1), exterior decoration flaggy (2) indoors;Bubble concrete layer (7) thermal conductivity factor is 0.06-0.08W/ (m.K), and its dry volume density is 300-400kg/m3
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (6)

1. a kind of body composite board of Fast Installation heat insulation decorative load-bearing one, including interior decoration flaggy (1), exterior decoration flaggy (2), Vertical light steel pipe (3), vertically connect end plate (4), horizontal light steel pipe (5), horizontal connection end plate (6), bubble concrete layer (7), Macroporous cellulose net (8), insulation tension member (9), adjustable screw (10) and installation reserved opening (11), it is characterised in that:
The described body composite board of Fast Installation heat insulation decorative load-bearing one is arranged to rectangular slab, and two surface is respectively interior decoration Flaggy (1) and exterior decoration flaggy (2), interior decoration flaggy (1) and exterior decoration flaggy (2) are reinforcing fiber concrete Plate, side sets vertical and equally distributed enhancing tooth respectively in plate;
Indoors among decorative plies (1) and exterior decoration flaggy (2), some be parallel to each other and equally distributed vertical light is set Steel pipe (3), vertical light steel pipe (3) to 2 to two/5ths that the distance of plate left and right ends is vertically light steel pipe (3) spacing/ One, vertical light steel pipe (3) elongated setting up and down, and internal filling high-strength concrete, strength of high strength concrete C40-C60; Vertical light steel pipe (3) upper and lower ends connect vertical connection end plate (4) respectively, vertically connect end plate (4) and are welded with vertical light steel pipe (3) Connect, it is rectangular slab vertically to connect end plate (4);
In the horizontal direction, set it is some be parallel to each other and equally distributed horizontal light steel pipe (5), on horizontal light steel pipe (5) to plate The distance at lower both ends is horizontal light steel pipe (5) spacing 2/5ths to half, horizontal light steel pipe (5) and vertical light steel pipe (3) selection type is identical with size, and between vertical light steel pipe (3), horizontal light steel pipe (5) welds with vertical light steel pipe (3), Light steel pipe (5) inner opposite end of level in outside welds with vertical light steel pipe (3), and lateral ends set horizontal connection end plate (6), Horizontal connection end plate (6) respectively extends the left and right outward flange of the body composite board of Fast Installation heat insulation decorative load-bearing one;Wall both ends Horizontal connection end plate (6) on respectively open up 4 adjustable screws (10), adjustable screw (10) is strip hole, strip hole Centre is rectangle, and both ends are semicircle;Adjustable screw (10) is located at four angles of horizontal connection end plate (6) respectively, in level Or vertical direction arrangement;Adjacent adjustable screw (10) is mutually vertical, and one of them adjustable screw (10) is pointed to separately The midpoint of one adjustable screw (10):When the adjustable screw of one end same position (10) is horizontal, then other end correspondence position Adjustable screw (10) it is vertical;When the adjustable screw of one end same position (10) is vertical, then other end correspondence position can Mode screw (10) is horizontal;Central plane and interior decoration flaggy (1) where vertical light steel pipe (3) and horizontal light steel pipe (5) Distance be with the distance of exterior decoration flaggy (2) 1/2 ~ 1;
Vertical macroporous cellulose net (8) is set respectively inside and outside vertical light steel pipe (3) and horizontal light steel pipe (5);Macropore The mesh diameter of web (8) is 3-10mm, and macroporous cellulose net (8) extends Fast Installation heat insulation decorative load-bearing one up and down The outward flange of body composite board;
Decorative plies (1), exterior decoration flaggy (2) are respectively pre-buried indoors is incubated tension member (9), the insulation tension member of both sides (9) correspond and be connected with each other, insulation tension member (9) transverse and longitudinal is in a row;
Full bubble concrete layer (7) is poured between decorative plies (1), exterior decoration flaggy (2) indoors;
Vertical connection end plate (4) and horizontal connection end plate (6) and coupled vertical light steel pipe (3) and horizontal light steel pipe (5) installation reserved opening (11) is reserved in decorative plies (1) side indoors for end, and installation reserved opening (11) is rectangle, is vertically connected End plate (4) and horizontal connection end plate (6) is connect in reserved installation reserved opening (11) to expose.
2. the body composite board of Fast Installation heat insulation decorative load-bearing one according to claim 1, it is characterised in that:Described interior Decorative plies (1) use cement fibrolite plate, thickness 5-15mm;The outer surface of interior decoration flaggy (1) is straight, inner surface band There is equally distributed vertical rib.
3. the body composite board of Fast Installation heat insulation decorative load-bearing one according to claim 1, it is characterised in that:Described outdoor Decorative plies (2) use cement fibrolite plate, thickness 10-40mm;The outer surface of exterior decoration flaggy (2) is straight or with equal Even vertical impression, inner surface carry equally distributed vertical rib.
4. the body composite board of Fast Installation heat insulation decorative load-bearing one according to claim 1, it is characterised in that:Described foam The thermal conductivity factor of concrete layer (7) is 0.06-0.08W/ (m.K), and its dry volume density is 300-400kg/m3
5. the body composite board of Fast Installation heat insulation decorative load-bearing one according to claim 1, it is characterised in that:Described macropore Web (8) prioritizing selection polypropylene fiber net, steel wire, wire netting or basalt fibre net, mesh diameter 3-10mm.
6. the body composite board of Fast Installation heat insulation decorative load-bearing one according to claim 1, it is characterised in that:Described insulation Tension member (9) prioritizing selection PVC tension members, glass fibre tension member, synthetic resin tension member or basalt fibre tension member.
CN201711241231.1A 2017-11-30 2017-11-30 Install bearing heat preservation fast and decorate integrative composite sheet Active CN107762055B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711241231.1A CN107762055B (en) 2017-11-30 2017-11-30 Install bearing heat preservation fast and decorate integrative composite sheet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711241231.1A CN107762055B (en) 2017-11-30 2017-11-30 Install bearing heat preservation fast and decorate integrative composite sheet

Publications (2)

Publication Number Publication Date
CN107762055A true CN107762055A (en) 2018-03-06
CN107762055B CN107762055B (en) 2021-01-08

Family

ID=61275792

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711241231.1A Active CN107762055B (en) 2017-11-30 2017-11-30 Install bearing heat preservation fast and decorate integrative composite sheet

Country Status (1)

Country Link
CN (1) CN107762055B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090188187A1 (en) * 2008-01-24 2009-07-30 Nucor Corporation Composite wall and floor system
CN101831963A (en) * 2009-01-09 2010-09-15 冯刚克 Novel multipurpose composite insulation board and construction method and processing device thereof
CN202577860U (en) * 2012-04-01 2012-12-05 青岛德才装饰安装工程有限公司 Pottery plate side-perforating hanging piece
CN203603316U (en) * 2013-11-06 2014-05-21 苏州金螳螂建筑装饰股份有限公司 Integrated light partition wall system with ultrahigh space
CN105888099A (en) * 2016-06-03 2016-08-24 湖南省建筑工程集团总公司 Heat preservation and decoration integrated composite wall serving as building outer wall and construction method of integrated composite wall
CN207597695U (en) * 2017-11-30 2018-07-10 沈阳建筑大学 One body composite board of Fast Installation heat insulation decorative load-bearing

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090188187A1 (en) * 2008-01-24 2009-07-30 Nucor Corporation Composite wall and floor system
CN101831963A (en) * 2009-01-09 2010-09-15 冯刚克 Novel multipurpose composite insulation board and construction method and processing device thereof
CN202577860U (en) * 2012-04-01 2012-12-05 青岛德才装饰安装工程有限公司 Pottery plate side-perforating hanging piece
CN203603316U (en) * 2013-11-06 2014-05-21 苏州金螳螂建筑装饰股份有限公司 Integrated light partition wall system with ultrahigh space
CN105888099A (en) * 2016-06-03 2016-08-24 湖南省建筑工程集团总公司 Heat preservation and decoration integrated composite wall serving as building outer wall and construction method of integrated composite wall
CN207597695U (en) * 2017-11-30 2018-07-10 沈阳建筑大学 One body composite board of Fast Installation heat insulation decorative load-bearing

Also Published As

Publication number Publication date
CN107762055B (en) 2021-01-08

Similar Documents

Publication Publication Date Title
CN106121107B (en) Assemble type concrete slab and its plate dry type connection method
CN207597695U (en) One body composite board of Fast Installation heat insulation decorative load-bearing
CN207597635U (en) One body composite board L-shaped wall of Fast Installation heat insulation decorative load-bearing
CN207892081U (en) One body composite board T shape walls of Fast Installation heat insulation decorative load-bearing
CN207812740U (en) One body composite board linear type wall of Fast Installation heat insulation decorative load-bearing
CN107747378A (en) The body composite board processing method of Fast Installation heat insulation decorative load-bearing one
CN206616695U (en) A kind of concrete panel and girt strip floor dry type connecting node
CN206016048U (en) Assemble type concrete slab
CN206016002U (en) Assembly concrete beam
CN107762055A (en) The body composite board of Fast Installation heat insulation decorative load-bearing one
CN109296074A (en) A kind of assembly concrete column beam connecting node
CN201614679U (en) Assembled building reinforced concrete precast plate
CN107747365A (en) The body composite board T-shaped wall of Fast Installation heat insulation decorative load-bearing one
CN107761992A (en) The body composite board L-shaped wall of Fast Installation heat insulation decorative load-bearing one
CN107806198A (en) The body composite board in-line wall of Fast Installation heat insulation decorative load-bearing one
CN208441226U (en) Dry construction bilayer core plate sleeper shear connector assembly concrete wallboard
CN106284739A (en) Assembly concrete entirety is without heat bridge gusset
CN106759877A (en) Assembly concrete node and its dry type connection method
CN106284741B (en) Dry type is linked and packed the structural envelope integrated system of the wide pillar height beam of formula concrete
CN208578229U (en) Dry construction bilayer core plate thermal insulation concrete roof boarding
CN206189606U (en) Whole afebril bridge plate wall of assembled concrete and running -on floor connected node
CN206015946U (en) A kind of assembly concrete is overall without heat bridge gusset
CN208578154U (en) Assembled shear connector concrete parapet
CN208777440U (en) Dry construction bilayer core plate sleeper shear connector concrete panel
CN208870174U (en) Dry construction sleeper shear connector concrete panel and its T shape wall connecting node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220224

Address after: 110015 352, No. 608-1, Shenshui Road, Shenhe District, Shenyang City, Liaoning Province

Patentee after: Zhang Yannian

Address before: 110168 No. 9 Hunnan East Road, Hunnan District, Shenyang City, Liaoning Province

Patentee before: SHENYANG JIANZHU University