CN107740570A - The huge post protective platform system of Super High housing and its installation method - Google Patents
The huge post protective platform system of Super High housing and its installation method Download PDFInfo
- Publication number
- CN107740570A CN107740570A CN201711050010.6A CN201711050010A CN107740570A CN 107740570 A CN107740570 A CN 107740570A CN 201711050010 A CN201711050010 A CN 201711050010A CN 107740570 A CN107740570 A CN 107740570A
- Authority
- CN
- China
- Prior art keywords
- fixed
- hanger
- horizontal
- card
- brace
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/001—Safety or protective measures against falling down relating to scaffoldings
Abstract
The present invention discloses a kind of huge post protective platform system of Super High housing and its installation method, and the system includes hanger and the huge post of housing, and the huge post is surrounded by workbench;The lower section of the workbench is provided with horizontal card, and horizontal card one end is fixed on hanger;Brace is provided with below the horizontal card, brace one end is fixed on the end of horizontal card, and the other end is fixed on hanger;Steel wire rope is provided with below the brace, steel wire rope one end is fixed on the fixing point that horizontal card connects with brace, and the other end is fixed on hanger;Horizontal card upper end is provided with I-steel, the apical support workbench of I-steel.Protective platform of the present invention is practical, is applicable to face side cantilever span on the outside of different floor heights, different huge column sections and huge post;Transfer can be directly lifted after protective platform once mounting of the present invention, is used in turn so as to quickly realize, is improved operating efficiency, reduce cost, while also reduce the working strength of workmen.
Description
Technical field
The present invention relates to the realm of building construction, the huge post protective platform system of specifically a kind of Super High housing and its installation side
Method.
Background technology
With the increase of China's scientific and technological progress, economic development and the density of population, ground of the high-rise building as modern city
Mark, constantly breaks through new high degree, and various New Complex structure systems largely occur, wherein, Frame-Shear wall is current superelevation
One of structure type being most widely used in Rotating fields.The huge column cross-section size of high-rise building peripheral frame is big, bean column node
Complexity, difficulty of construction is big, then it is particularly important to face side operation safety protection problem for the huge post of housing.
In order to solve the problems, such as the huge post construction safety protection of high-rise building housing, prior art can typically by use
The facilities such as the scaffold of Fast Installation are supported protection, while are protected in huge post outer ledge installation protection network.But
These facilities are required to manually go to install, and need to assemble again after removing transhipment during turnover, and so efficiency just greatly drops
It is low.
The content of the invention
It is an object of the invention to provide a kind of huge post protective platform system of Super High housing and its installation method.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of huge post protective platform system of Super High housing, including hanger and the huge post of housing, the huge post are surrounded by work
Make platform;The top and bottom of the hanger are separately fixed on workbench.
The lower section of the workbench is provided with horizontal card, and horizontal card one end is fixed on hanger;Set below the horizontal card
There is brace, brace one end is fixed on the end of horizontal card, and the other end is fixed on hanger;Steel is provided with below the brace
Cord, steel wire rope one end are fixed on the fixing point that horizontal card connects with brace, and the other end is fixed on hanger;Horizontal card upper end
Provided with I-steel, the apical support workbench of I-steel.
The horizontal card includes horizontal base and deck, and deck is fixed on horizontal base.
The horizontal base includes horizontal cross bar, and one end of horizontal cross bar is fixed on hanger, the top of the horizontal cross bar other end
Portion is provided with quarter butt, and quarter butt is provided with the first card article, and horizontal cross bar bottom is provided with two symmetrical ear blocks, and ear block is provided with through hole;
The horizontal cross bar is provided with screwed hole.
The deck includes the second card article, and the both sides of the second card article are provided with symmetrically arranged rectangular strip, and rectangular strip is provided with
Through hole;The bottom of second card article is provided with balance base.
Through hole and screwed hole on the rectangular strip is concentric, is consolidated deck by being screwed into bolt into through hole and screwed hole
It is scheduled on horizontal base.
One end of the I-steel lower flange is stuck in the downside of the first card article, and the other end is stuck in the downside of the second card article.
The hanger is the overall structure of the fixation formed by welded steel.
The outer side edges of the hanger are provided with protection network.
The flange width of quarter butt and the rectangular strip inner side edge away from equal to I-steel.
A kind of installation method of the huge post protective platform system of Super High housing, comprises the following steps:
A, the hanger being welded is sling, and the top and bottom of hanger is each attached on workbench;
B, after hanger is fixed, horizontal card is fixed on hanger;
C, after horizontal card is fixed, brace one end is fixed in horizontal card, the other end is fixed on hanger;
D, after horizontal card and brace are fixed, steel wire rope is fixed on brace and hanger, so as to play off-load
The effect of load;
E, I-steel is fixed in horizontal card;
F, after This floor construction terminates, directly by protective platform system integral hoisting to upper floor, so that quickly real
Now it is used in turn.
Beneficial effects of the present invention:
1st, protective platform of the present invention is practical, is applicable to outside different floor heights, different huge column sections and huge post
Side cantilever span is faced in side;
2nd, transfer can be directly lifted after protective platform once mounting of the present invention, is used in turn, carries so as to quickly realize
High operating efficiency, reduces cost, while also reduce the working strength of workmen;
3rd, simple in construction, short construction period of the invention, it is safe, while safeguard it is also very convenient, either from
Security standpoint or economic angle suffer from very strong superiority.
Brief description of the drawings
The present invention is further illustrated below in conjunction with the accompanying drawings.
Fig. 1 is protective platform system front view of the present invention;
Fig. 2 is protective platform system top view of the present invention;
Fig. 3 is protective platform system side view of the present invention;
Fig. 4 is horizontal base structural representation;
Fig. 5 is deck configuration diagram;
Fig. 6 is horizontal card and I-steel assembling assumption diagram.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained all other under the premise of creative work is not made
Embodiment, belong to the scope of protection of the invention.
In the description of the invention, it is to be understood that term " perforate ", " on ", " under ", " thickness ", " top ", " in ",
Indicating position or the position relationship such as " length ", " interior ", " surrounding ", it is for only for ease of the description present invention and simplifies description, without
It is that the component of instruction or hint meaning or element must have specific orientation, with specific azimuth configuration and operation, therefore not
It is understood that as limitation of the present invention.
The huge post protective platform system of Super High housing, including hanger 1 and the huge post 2 of housing, as shown in figure 1, hanger 1 is by steel
The overall structure for the fixation that material is welded, huge post 2 are surrounded by workbench 3, and the top and bottom of hanger 1 are separately fixed at
On workbench 3.The outer side edges of hanger 1 are provided with protection network 11, prevent falling object from high altitude from accidentally injuring other people.
The lower section of workbench 3 is provided with horizontal card 4, and the one end of horizontal card 4 is fixed on hanger 1;The lower section of horizontal card 4 is provided with oblique
Pull bar 5, the one end of brace 5 are fixed on the end of horizontal card 4, and the other end is fixed on hanger 1;The lower section of brace 5 is provided with steel wire
Rope 6, the fixing point that the one end of steel wire rope 6 is fixed on horizontal card 4 and brace 5 connects, the other end are fixed on hanger 1.
The upper end of horizontal card 4 is provided with I-steel 7, the apical support workbench 3 of I-steel 7.
As Figure 4-Figure 6, horizontal card 4 includes horizontal base 41 and deck 42 for horizontal card 4 and the fixed form of I-steel 7, card
Seat 42 is fixed on horizontal base 41, and horizontal base 41 is horizontal as shown in figure 4, Fig. 4 show the end structure schematic diagram of horizontal base 41
Seat 41 includes horizontal cross bar 4101, and one end of horizontal cross bar 4101 is fixed on hanger 1, the top of the other end of horizontal cross bar 4101
Provided with quarter butt 4102, quarter butt 4102 is provided with the first card article 4103, and the bottom of horizontal cross bar 4101 is provided with two symmetrical ear blocks
4104, ear block 4104 is provided with through hole, and ear block 4104 is used for and brace 5 connects;Horizontal cross bar 4101 is provided with screwed hole
4105。
Deck 42 includes the second card article 4201, and the both sides of the second card article 4201 are provided with symmetrically arranged rectangular strip 4202, square
Shape bar 4202 is provided with through hole;The bottom of second card article 4201 is provided with balance base 4203.Quarter butt 4102 and the inner side of rectangular strip 4202
Back gauge is equal to the flange width of I-steel 7
When fixed, the side of the bottom of I-steel 7 is stuck in the downside of the first card article 4103, the other end is stuck in the second card article
4201 downside, the through hole and screwed hole 4105 on rectangular strip 4202 are concentric, and are screwed into spiral shell into through hole and screwed hole 4105
Bolt, so as to which deck 42 is fixed on horizontal base 41.
The present invention installation method be:
1st, the hanger 1 being welded is sling, and the top and bottom of hanger 1 is each attached on workbench 3;
2nd, after hanger 1 is fixed, horizontal card 4 is fixed on hanger 1;
3rd, after horizontal card 4 is fixed, the one end of brace 5 is fixed in horizontal card 4, the other end is fixed on hanger 1;
4th, after horizontal card 4 and brace 5 are fixed, steel wire rope 6 is fixed on brace 5 and hanger 1, so as to play
Unload the effect of load;
5th, I-steel 7 is fixed in horizontal card 4;
6th, after This floor construction terminates, directly by protective platform system integral hoisting to upper floor, so that quickly real
Now it is used in turn.
In the description of this specification, the description of reference term " one embodiment ", " example ", " specific example " etc. means
At least one implementation of the present invention is contained in reference to specific features, structure, material or the feature that the embodiment or example describe
In example or example.In this manual, identical embodiment or example are not necessarily referring to the schematic representation of above-mentioned term.
Moreover, specific features, structure, material or the feature of description can close in any one or more embodiments or example
Suitable mode combines.
General principle, principal character and the advantages of the present invention of the present invention has been shown and described above.The technology of the industry
Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the simply explanation described in above-described embodiment and specification is originally
The principle of invention, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these changes
Change and improvement all fall within the protetion scope of the claimed invention.
Claims (5)
1. a kind of huge post protective platform system of Super High housing, including hanger (1) and the huge post of housing (2), it is characterised in that described
Huge post (2) is surrounded by workbench (3);The top and bottom of the hanger (1) are separately fixed on workbench (3);
The lower section of the workbench (3) is provided with horizontal card (4), and horizontal card (4) one end is fixed on hanger (1);The level
Brace (5) is provided with below card (4), brace (5) one end is fixed on the end of horizontal card (4), and the other end is fixed on hanger (1)
On;Steel wire rope (6) is provided with below the brace (5), steel wire rope (6) one end is fixed on horizontal card (4) and brace (5) connection
Fixing point, the other end is fixed on hanger (1);Horizontal card (4) upper end is provided with I-steel (7), the apical support of I-steel (7)
Workbench (3);
The horizontal card (4) includes horizontal base (41) and deck (42), and deck (42) is fixed on horizontal base (41);
The horizontal base (41) includes horizontal cross bar (4101), and one end of horizontal cross bar (4101) is fixed on hanger (1), horizontal
The top of cross bar (4101) other end is provided with quarter butt (4102), and quarter butt (4102) is provided with the first card article (4103), horizontal cross bar
(4101) bottom is provided with two symmetrical ear blocks (4104), and ear block (4104) is provided with through hole;On the horizontal cross bar (4101)
Provided with screwed hole (4105);
The deck (42) includes the second card article (4201), and the both sides of the second card article (4201) are provided with symmetrically arranged rectangular strip
(4202), rectangular strip (4202) is provided with through hole;The bottom of second card article (4201) is provided with balance base (4203);
Through hole and screwed hole (4105) on the rectangular strip (4202) is concentric, by being twisted into through hole and screwed hole (4105)
Enter bolt deck (42) is fixed on horizontal base (41);
One end of I-steel (7) lower flange is stuck in the downside of the first card article (4103), and the other end is stuck in the second card article
(4201) downside.
A kind of 2. huge post protective platform system of Super High housing according to claim 1, it is characterised in that the hanger
(1) be the fixation formed by welded steel overall structure.
A kind of 3. huge post protective platform system of Super High housing according to claim 1, it is characterised in that the hanger
(1) outer side edges are provided with protection network (11).
A kind of 4. huge post protective platform system of Super High housing according to claim 1, it is characterised in that the quarter butt
And flange width of rectangular strip (4202) inner side edge away from equal to I-steel (7) (4102).
5. a kind of installation method of the huge post protective platform system of Super High housing, it is characterised in that comprise the following steps:
A, the hanger being welded (1) is sling, and the top and bottom of hanger (1) is each attached on workbench (3);
B, after hanger (1) is fixed, horizontal card (4) is fixed on hanger (1);
C, after horizontal card (4) is fixed, brace (5) one end is fixed in horizontal card (4), the other end is fixed on hanger (1);
D, after horizontal card (4) and brace (5) are fixed, steel wire rope (6) is fixed on brace (5) and hanger (1), from
And play a part of unloading load;
E, I-steel (7) is fixed in horizontal card (4);
F, it is all so as to quickly realize directly by protective platform system integral hoisting to upper floor after This floor construction terminates
Turn to use.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711050010.6A CN107740570B (en) | 2017-10-31 | 2017-10-31 | Super high-rise outer frame giant column protection platform system and installation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711050010.6A CN107740570B (en) | 2017-10-31 | 2017-10-31 | Super high-rise outer frame giant column protection platform system and installation method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107740570A true CN107740570A (en) | 2018-02-27 |
CN107740570B CN107740570B (en) | 2020-10-09 |
Family
ID=61233805
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711050010.6A Active CN107740570B (en) | 2017-10-31 | 2017-10-31 | Super high-rise outer frame giant column protection platform system and installation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107740570B (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2523293C (en) * | 2003-05-16 | 2011-09-13 | Denis Paquette | Safety restraint system |
CN203271096U (en) * | 2013-04-16 | 2013-11-06 | 中建钢构有限公司 | Operating platform |
CN206289944U (en) * | 2016-12-02 | 2017-06-30 | 中建四局第六建筑工程有限公司 | For the tool-type protective platform of Super High exterior frame column |
-
2017
- 2017-10-31 CN CN201711050010.6A patent/CN107740570B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2523293C (en) * | 2003-05-16 | 2011-09-13 | Denis Paquette | Safety restraint system |
CN203271096U (en) * | 2013-04-16 | 2013-11-06 | 中建钢构有限公司 | Operating platform |
CN206289944U (en) * | 2016-12-02 | 2017-06-30 | 中建四局第六建筑工程有限公司 | For the tool-type protective platform of Super High exterior frame column |
Also Published As
Publication number | Publication date |
---|---|
CN107740570B (en) | 2020-10-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102383588B (en) | Lifting platform for protecting safety of high-level construction | |
CN101736893B (en) | Overhanging type scaffold supporting system | |
CN106088637B (en) | Construction assembled high-altitude protection canopy and its assembly method | |
CN204163364U (en) | A kind of elevator shaft formwork and operation steel platform | |
CN102168484B (en) | External hanging scaffold and application method thereof | |
CN105298107B (en) | A kind of high carriage of High Large Cantilever structure | |
CN211173007U (en) | Novel tripod of encorbelmenting | |
CN107587711A (en) | A kind of regularization assembled overhanging protection canopy and its assembly method | |
CN209011528U (en) | A kind of all steel attachment type raise scaffold | |
CN107740570A (en) | The huge post protective platform system of Super High housing and its installation method | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN107059641A (en) | Goods-shelf type pier shaft external scaffolding | |
CN211447690U (en) | Latticed construction platform with material storage space | |
CN209161337U (en) | A kind of boom-type tower crane support system auxiliary circulation transporting device | |
CN105152034B (en) | For the cableway Lift-on/Lift-off System of pitched roof curtain wall | |
CN207553635U (en) | Elevator shaft safety protection device and elevator | |
CN211622551U (en) | Scaffold protection shed and scaffold protection shed mounting structure | |
CN208777750U (en) | A kind of safety protection guard convenient for construction | |
CN219100689U (en) | Attachment structure suitable for super high floor attached lifting scaffold | |
CN205046861U (en) | Discharging platform | |
CN219652563U (en) | Elevator well protection and material lifting device | |
CN109914774A (en) | A kind of building bearing device | |
CN211622525U (en) | Can have enough to meet need elevartor shaft construction operation platform | |
CN206625523U (en) | Builder's jack rotation angle position regularization component | |
CN210419022U (en) | Tower crane standard knot with safety performance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province Patentee after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau Address before: 230000 21 / F and 22 / F, Zhongjian building, northeast corner, intersection of Tongling Road and Heping Road, Yaohai District, Hefei City, Anhui Province Patentee before: CHINA CONSTRUCTION 4TH ENGINEERING BUREAU, 6TH Co.,Ltd. |
|
CP03 | Change of name, title or address |