CN107700355B - 一种大桥钢模板底模制作工艺 - Google Patents
一种大桥钢模板底模制作工艺 Download PDFInfo
- Publication number
- CN107700355B CN107700355B CN201710600674.9A CN201710600674A CN107700355B CN 107700355 B CN107700355 B CN 107700355B CN 201710600674 A CN201710600674 A CN 201710600674A CN 107700355 B CN107700355 B CN 107700355B
- Authority
- CN
- China
- Prior art keywords
- segmentation
- bed die
- side mode
- prefabricated
- splicing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Abstract
本发明公开了一种大桥钢模板底模制作工艺,依次经过分段组件制作、分段组件螺栓孔加工、分段支撑梁组件预制、分段底模制作、中间底模分段预拼及标记、边模折弯组件预制、边模组件预制、边模分段制作、边模与中间底模预拼及标记完成整个工艺。其优点在于:本发明耗材低、成本较低、拼接简易,而且拼接安装质量显著提升,节省大量的人力物力,提高工作效率。
Description
技术领域
本发明涉及桥梁钢模板底模技术领域,特别是一种大桥钢模板底模制作工艺。
背景技术
传统的桥梁钢模板底模制作耗材大、成本较高、拼接过程中需要反复调节。
发明内容
本发明的目的克服现有技术的不足,提供一种高效的大桥钢模板底模制作工艺。
本发明解决其技术问题所采取的技术方案是:
一种大桥钢模板底模制作工艺,其创新点在于,依次经过分段组件制作、分段组件螺栓孔加工、分段支撑梁组件预制、分段底模制作、中间底模分段预拼及标记、边模折弯组件预制、边模组件预制、边模分段制作、边模与中间底模预拼及标记完成整个工艺,具体步骤包括:
1)分段组件制作:数控下料折弯后需测量钢板长度,并保证尺寸偏差在-2~0mm之间,然后进行配件的焊接,焊接完成成对配件进行打磨、做底漆,并保证尺寸偏差在-2~2mm之间;
2)分段组件螺栓孔加工:按照要求在分段组件上画出螺栓孔的定位尺寸,并配钻螺栓孔,螺栓孔配钻完成后,在分段的组件两侧装配工艺销轴,而且平均每8个螺栓孔装配2套工艺螺栓,然后再进行装焊;
3)分段支撑梁组件预制:下料拼装焊接,并将焊缝打磨后喷涂防锈底漆,再进行工艺轴的制作,进行分段支撑梁组件的装配;
4)分段底模制作:分段底模采用反置制作,先将面板平铺于整平后的胎架上,进行拼板对接,面板采用半自动火焰切割机下料,下料时应保留15mm的修割余量,拼板焊接完成后将焊缝打磨平整,并将面板用卡马固定定于胎架上,再在面板纵向上从中间向两侧画出工字钢安装线,再将工字钢对准安装线进行点焊装配,然后在修割面板横向两侧余量,最后再安装端部法兰件;
5)中间底模分段预拼及标记:首先复测面板是否有明显变形,再将分段支撑梁组件装配在分段组件上,然后将中间底模分段放置在支撑梁上,调节完成后进行焊接,并在各个分段上标记编号,编号需能明确表示分段位置及朝向;
6)边模折弯组件预制:首先画出折弯线,折弯时保证尺寸偏差在-2~2mm之间;
7)边模组件预制:边模组件安装时,应调整开档及垂直度后按照要求焊接到位;
8)边模分段制作:面板按照尺寸要求用半自动切割机下料,面板校平后,用卡马将面板固定于胎架上,卡马装配时需注意避免与工字钢干涉,然后再画出工字钢、槽钢及折弯预制件的安装线,再将工字钢、槽钢及折弯预制件进行焊接,完成后再与中间底模进行拼装焊接;
9)边模与中间底模预拼及标记:中间底模完成预拼后,各分段仍保持螺栓连接状态,将两侧的边模与中间底模进行预拼,配合千斤顶调节构件位置,使中间底模与边模面板接口贴合且处于同一水平面上,预拼完成后对各边模分段进行编号标记,然后再进行焊接固定,并涂抹防锈蜡,运往现场。
本发明的有益效果如下:
本发明耗材低、成本较低、拼接简易,而且拼接安装质量显著提升,节省大量的人力物力,提高工作效率。
附图说明
图1为本发明分段组件制作示意图;
图2为本发明分段组件螺栓孔加工示意图;
图3为本发明分段支撑梁组件预制示意图;
图4为本发明分段底模制作示意图;
图5、6为本发明中间底模分段预拼及标记示意图;
图7为本发明边模折弯组件预制示意图;
图8为本发明边模组件预制示意图;
图9为本发明边模分段制作示意图;
图10为本发明边模与中间底模预拼及标记。
具体实施方式
本发明解决其技术问题所采取的技术方案是:
一种大桥钢模板底模制作工艺,依次经过分段组件制作、分段组件螺栓孔加工、分段支撑梁组件预制、分段底模制作、中间底模分段预拼及标记、边模折弯组件预制、边模组件预制、边模分段制作、边模与中间底模预拼及标记完成整个工艺,具体步骤包括:
1)分段组件制作:数控下料折弯后需测量钢板长度,并保证尺寸偏差在-2~0mm之间,然后进行配件的焊接,焊接完成成对配件进行打磨、做底漆,并保证尺寸偏差在-2~2mm之间,如图1所示;
2)分段组件螺栓孔加工:按照要求在分段组件上画出螺栓孔的定位尺寸,并配钻螺栓孔,螺栓孔配钻完成后,在分段的组件两侧装配工艺销轴,而且平均每8个螺栓孔装配2套工艺螺栓,然后再进行装焊,如图2所示;
3)分段支撑梁组件预制:下料拼装焊接,并将焊缝打磨后喷涂防锈底漆,再进行工艺轴的制作,进行分段支撑梁组件的装配,如图3所示;
4)分段底模制作:分段底模采用反置制作,先将面板平铺于整平后的胎架上,进行拼板对接,面板采用半自动火焰切割机下料,下料时应保留15mm的修割余量,拼板焊接完成后将焊缝打磨平整,并将面板用卡马固定定于胎架上,再在面板纵向上从中间向两侧画出工字钢安装线,再将工字钢对准安装线进行点焊装配,然后在修割面板横向两侧余量,最后再安装端部法兰件,如图4所示;
5)中间底模分段预拼及标记:首先复测面板是否有明显变形,再将分段支撑梁组件装配在分段组件上,然后将中间底模分段放置在支撑梁上,调节完成后进行焊接,并在各个分段上标记编号,编号需能明确表示分段位置及朝向,如图5、6所示;
6)边模折弯组件预制:首先画出折弯线,折弯时保证尺寸偏差在-2~2mm之间,如图7所示;
7)边模组件预制:边模组件安装时,应调整开档及垂直度后按照要求焊接到位,如图8所示;
8)边模分段制作:面板按照尺寸要求用半自动切割机下料,面板校平后,用卡马将面板固定于胎架上,卡马装配时需注意避免与工字钢干涉,然后再画出工字钢、槽钢及折弯预制件的安装线,再将工字钢、槽钢及折弯预制件进行焊接,完成后再与中间底模进行拼装焊接,如图9所示;
9)边模与中间底模预拼及标记:中间底模完成预拼后,各分段仍保持螺栓连接状态,将两侧的边模与中间底模进行预拼,配合千斤顶调节构件位置,使中间底模与边模面板接口贴合且处于同一水平面上,预拼完成后对各边模分段进行编号标记,然后再进行焊接固定,并涂抹防锈蜡,运往现场,如图10所示。
以上所述是本发明的优选实施方式,不能以此来限定本发明之权利范围。应当指出,对于本技术领域的普通技术人员来说,对本发明的技术方案进行修改或者等同替换,都不脱离本发明的保护范围。
Claims (1)
1.一种大桥钢模板底模制作工艺,其特征在于,依次经过分段组件制作、分段组件螺栓孔加工、分段支撑梁组件预制、分段底模制作、中间底模分段预拼及标记、边模折弯组件预制、边模组件预制、边模分段制作、边模与中间底模预拼及标记完成整个工艺,具体步骤包括:
1)分段组件制作:数控下料折弯后需测量钢板长度,并保证尺寸偏差在-2~0mm之间,然后进行配件的焊接,焊接完成成对配件进行打磨、做底漆,并保证尺寸偏差在-2~2mm之间;
2)分段组件螺栓孔加工:按照要求在分段组件上画出螺栓孔的定位尺寸,并配钻螺栓孔,螺栓孔配钻完成后,在分段的组件两侧装配工艺销轴,而且平均每8个螺栓孔装配2套工艺螺栓,然后再进行装焊;
3)分段支撑梁组件预制:下料拼装焊接,并将焊缝打磨后喷涂防锈底漆,再进行工艺轴的制作,进行分段支撑梁组件的装配;
4)分段底模制作:分段底模采用反置制作,先将面板平铺于整平后的胎架上,进行拼板对接,面板采用半自动火焰切割机下料,下料时应保留15mm的修割余量,拼板焊接完成后将焊缝打磨平整,并将面板用卡马固定定于胎架上,再在面板纵向上从中间向两侧画出工字钢安装线,再将工字钢对准安装线进行点焊装配,然后在修割面板横向两侧余量,最后再安装端部法兰件;
5)中间底模分段预拼及标记:首先复测面板是否有明显变形,再将分段支撑梁组件装配在分段组件上,然后将分段放置在支撑梁上,调节完成后进行焊接,并在各个分段上标记编号,编号需能明确表示分段位置及朝向;
6)边模折弯组件预制:首先画出折弯线,折弯时保证尺寸偏差在-2~2mm之间;
7)边模组件预制:边模组件安装时,应调整开档及垂直度后按照要求焊接到位;
8)边模分段制作:面板按照尺寸要求用半自动切割机下料,面板校平后,用卡马将面板固定于胎架上,卡马装配时需注意避免与工字钢干涉,然后再画出工字钢、槽钢及折弯预制件的安装线,再将工字钢、槽钢及折弯预制件进行焊接,完成后再与中间底模进行拼装焊接;
9)边模与中间底模预拼及标记:中间底模完成预拼后,各分段仍保持螺栓连接状态,将两侧的边模与中间底模进行预拼,配合千斤顶调节构件位置,使中间底模与边模面板接口贴合且处于同一水平面上,预拼完成后对各边模分段进行编号标记,然后再进行焊接固定,并涂抹防锈蜡,运往现场。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710600674.9A CN107700355B (zh) | 2017-07-21 | 2017-07-21 | 一种大桥钢模板底模制作工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710600674.9A CN107700355B (zh) | 2017-07-21 | 2017-07-21 | 一种大桥钢模板底模制作工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107700355A CN107700355A (zh) | 2018-02-16 |
CN107700355B true CN107700355B (zh) | 2019-05-07 |
Family
ID=61170523
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710600674.9A Active CN107700355B (zh) | 2017-07-21 | 2017-07-21 | 一种大桥钢模板底模制作工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107700355B (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020074523A (ko) * | 2001-03-20 | 2002-10-04 | 태성판넬 주식회사 | 일체조립되는 거푸집 및 그 조립과 해체방법 |
KR20090048723A (ko) * | 2007-11-12 | 2009-05-15 | 고준석 | 유로폼과 이를 이용한 거푸집 시공방법 |
CN101781878A (zh) * | 2010-01-21 | 2010-07-21 | 中铁二十局集团有限公司 | 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法 |
CN103481022A (zh) * | 2013-08-20 | 2014-01-01 | 合肥万众交通工程有限公司 | 一种墩柱模板制造方法 |
CN104775612A (zh) * | 2015-02-16 | 2015-07-15 | 北京建工四建工程建设有限公司 | 三维扭曲旋转倾斜钢筋混凝土框架结构模板及其施工方法 |
-
2017
- 2017-07-21 CN CN201710600674.9A patent/CN107700355B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020074523A (ko) * | 2001-03-20 | 2002-10-04 | 태성판넬 주식회사 | 일체조립되는 거푸집 및 그 조립과 해체방법 |
KR20090048723A (ko) * | 2007-11-12 | 2009-05-15 | 고준석 | 유로폼과 이를 이용한 거푸집 시공방법 |
CN101781878A (zh) * | 2010-01-21 | 2010-07-21 | 中铁二十局集团有限公司 | 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法 |
CN103481022A (zh) * | 2013-08-20 | 2014-01-01 | 合肥万众交通工程有限公司 | 一种墩柱模板制造方法 |
CN104775612A (zh) * | 2015-02-16 | 2015-07-15 | 北京建工四建工程建设有限公司 | 三维扭曲旋转倾斜钢筋混凝土框架结构模板及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN107700355A (zh) | 2018-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109518604A (zh) | 一种用于大曲率钢箱梁顶推施工方法 | |
CN102806415A (zh) | 焊接h型钢腹板与翼板免清根焊接方法及焊接平台 | |
CN105755915A (zh) | Crtsⅲ型板式无砟轨道底座板施工方法 | |
EP2951117B1 (en) | Method to form a rail joint, and a rail joint | |
CN204640562U (zh) | 一种符合绿色施工的墙体砌块立杆剪切机 | |
CN107700355B (zh) | 一种大桥钢模板底模制作工艺 | |
CN102059513B (zh) | 铁路客车整体式底架牵引梁制造工艺 | |
CN110406829B (zh) | 罐式运输车罐体总成及其制造方法 | |
CN101812856B (zh) | 绞吸式挖泥船钢桩结构制作工艺 | |
CN108465962B (zh) | 勾臂上装总成拼焊工装及其生产工艺 | |
CN112658524A (zh) | 一种大型液压缸分段缸体全焊透结构的设计方法 | |
CN202894163U (zh) | 用于双曲线流线型墩帽面板压型的设备 | |
CN108080896B (zh) | 一种破碎锤侧板的焊接装配方法 | |
CN210553142U (zh) | 一种风机叶片大梁定位工装 | |
CN202240140U (zh) | 一种滑动铜板垫焊机构 | |
CN212671202U (zh) | 一种用于大跨度顶部钢模板水平纠偏的装置 | |
CN201459605U (zh) | 钢箱梁的u肋组装用装置 | |
CN211058811U (zh) | 一种隧道中心水沟二次填充模板台车 | |
CN218203902U (zh) | 一种用于大型钢桥梁段长距离同步位移的滑靴装置 | |
CN109778602A (zh) | 一种有轨电车槽型辙叉及无缝化制造方法 | |
CN220550866U (zh) | 一种造楼机的顶部平台拼装用h型转接件 | |
CN218205223U (zh) | 应用于冬季钢结构工程的钢梁防裂纹焊接结构 | |
CN103862210B (zh) | 铁路车辆用车顶大弯梁组对工装 | |
CN105834552A (zh) | 管件两半部分对接点焊合缝机 | |
CN218145482U (zh) | 一种水利水电管道固定装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |