CN107692849A - A kind of pot cover lid making apparatus combines line - Google Patents

A kind of pot cover lid making apparatus combines line Download PDF

Info

Publication number
CN107692849A
CN107692849A CN201710718031.4A CN201710718031A CN107692849A CN 107692849 A CN107692849 A CN 107692849A CN 201710718031 A CN201710718031 A CN 201710718031A CN 107692849 A CN107692849 A CN 107692849A
Authority
CN
China
Prior art keywords
component
fixed
rotating shaft
operating desk
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710718031.4A
Other languages
Chinese (zh)
Inventor
张华�
仇如成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710718031.4A priority Critical patent/CN107692849A/en
Publication of CN107692849A publication Critical patent/CN107692849A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A47FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
    • A47JKITCHEN EQUIPMENT; COFFEE MILLS; SPICE MILLS; APPARATUS FOR MAKING BEVERAGES
    • A47J36/00Parts, details or accessories of cooking-vessels
    • A47J36/06Lids or covers for cooking-vessels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B08CLEANING
    • B08BCLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
    • B08B11/00Cleaning flexible or delicate articles by methods or apparatus specially adapted thereto
    • B08B11/04Cleaning flexible or delicate articles by methods or apparatus specially adapted thereto specially adapted for plate glass, e.g. prior to manufacture of windshields
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B24GRINDING; POLISHING
    • B24BMACHINES, DEVICES, OR PROCESSES FOR GRINDING OR POLISHING; DRESSING OR CONDITIONING OF ABRADING SURFACES; FEEDING OF GRINDING, POLISHING, OR LAPPING AGENTS
    • B24B19/00Single-purpose machines or devices for particular grinding operations not covered by any other main group
    • B24B19/22Single-purpose machines or devices for particular grinding operations not covered by any other main group characterised by a special design with respect to properties of the material of non-metallic articles to be ground
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B23/00Re-forming shaped glass
    • C03B23/02Re-forming glass sheets
    • C03B23/023Re-forming glass sheets by bending
    • C03B23/03Re-forming glass sheets by bending by press-bending between shaping moulds
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B33/00Severing cooled glass
    • C03B33/02Cutting or splitting sheet glass or ribbons; Apparatus or machines therefor
    • C03B33/04Cutting or splitting in curves, especially for making spectacle lenses

Abstract

The present invention relates to a kind of pot cover lid making apparatus to combine line, and it includes:Disk cutting equipment;Grinding apparatus;Cleaning equipment;Heat material feeding system;Cooling component;Gas button assembles equipment;Shroud ring equipment;Discharge component;Blanking bench is circulated, the circulation blanking bench is arranged on the lower section of the discharge component.Reinforced glass pot lid can so be realized(Not comprising mobile division)Making and instead of artificial, production efficiency and quality greatly improved.

Description

A kind of pot cover lid making apparatus combines line
Technical field
The present invention relates to a kind of production line, and in particular to a kind of pot cover lid making apparatus combines line.
Background technology
Pot cover is generally circular in cross section, and centre carries knob;Main function is to maintain the temperature of material in pot, and plays and prevent in pot Material liquid splash, effect that steam escapes caused by the factor such as heated.Existing conventional pot cover is generally such as Application No. Shown in 201530107997.6 Chinese appearance patent, including arc armoured glass body, be wrapped in it is stainless at body edges Ladle side and the venthole being opened on body, body middle part are provided with mobile division, cladding button are provided with venthole, with Edge is prevented at stomata to have glass chip to drop in pot.Current reinforced glass pot lid generally use is manually made, raw Inefficient is produced, quality is difficult to ensure that.
The content of the invention
A kind of pot cover lid making apparatus combination line is provided the invention aims to overcome the deficiencies in the prior art.
To reach above-mentioned purpose, the technical solution adopted in the present invention is:A kind of pot cover lid making apparatus combines line, it Including:
Disk cutting equipment, the disk cutting equipment include the cutting assembly and conveying component being engaged;The cutting assembly The first bearing platform including the first supporting table, at the top of first supporting table and liftably it is arranged on described first Cutter group above bearing platform;The cutter group includes being arranged in first supporting table and extending to described first holding Material platform above L-type support bar, installed in the L-type support bar side and extend to above first bearing platform sleeve, It is installed in rotation on the first rotary shaft in the sleeve, the first contiguous block installed in the first rotary shaft lower end, peace Cutter head on first contiguous block and it is connected installed in the L-type support bar top and with first rotary shaft The first cylinder;The conveying component is arranged at the both sides of the cutting assembly, for inputting and exporting to the cutting assembly Safety glass;
Grinding apparatus, the grinding apparatus are arranged at the downstream of the disk cutting equipment, and it includes the first operating desk, charging group Part, sanding component and shifting material component;The feeding assembly includes being arranged on first of two side edges at the top of first operating desk Transmission case, it is installed in rotation between two first transmission cases and spaced more first power transmission shafts and installation At the top of first operating desk and positioned at the more gag lever posts in the first power transmission shaft downstream;The material component that moves is positioned at described The downstream of feeding assembly, it includes being arranged on support pedestal at the top of first operating desk, is fixed on the support pedestal top The clamping jaw slide rail in portion, be slidably mounted on the clamping jaw slide rail and spaced multiple clamping jaws, installed in the clamping jaw Slide rail bottom and the second cylinder above the gag lever post, the first pinboard installed in the second cylinder lower end, peace Rotary cylinder on first pinboard, second for being connected and being rotated under its drive with the rotary cylinder Pinboard and the first vacuum cup on second pinboard;The sanding component includes being installed in rotation on The support pedestal side and be engaged with the clamping jaw material folding head group, at the top of first operating desk and be located at institute The polishing stated the second motor of support pedestal side and be engaged on second motor and with the material folding head group Emery wheel;The blanking sucker is arranged on the downstream of the support pedestal and is engaged with the clamping jaw;
Cleaning equipment, the cleaning equipment include being arranged at the 5th support frame in the first operating desk downstream, installed in described The second operating desk at the top of 5th support frame, the second transmission case installed in the side edge of the second operating desk two, rotationally Between two second transmission cases and spaced more second driving shafts, spray assemblies and it is arranged at described The air-dried component in spray assemblies downstream, the spray assemblies include being arranged on second transmission case and passed positioned at described second Spraying box above moving axis, the storage liquid case on the 5th support frame and below the spraying box, installed in institute State second driving shaft and it is described storage liquid case between and the water conservancy diversion enclosing corresponding with the spraying box, installed in it is described storage liquid case in Water pump and one end is connected with the water pump and the other end is connected with the spraying box an at least woven hose;
Material feeding system is heated, the heating material feeding system is arranged at the downstream of the cleaning equipment, and it includes pan feeding component, transmission Component, baking oven, component, bearing material component and blanking component are bent, the pan feeding component includes supporting box, installed in the support Casing top and spaced two the second cover bodies, it is installed in rotation between two second cover bodies and is mutually hung down with it Straight first rotating shaft and on the supporting box and with first rotating shaft end is connected every described at least one set It is driven chain group;The baking oven is arranged on the downstream of the pan feeding component, is mounted therein with and is in same height with the first rotating shaft More second rotating shafts that degree and both ends are extended to outside the baking oven;Between at least one end of every second rotating shaft offers Every multiple annular grooves of setting;The transmission component includes being fixed on multiple first fixed seats on the baking oven lateral wall, can The 3rd power transmission shaft that is rotationally located in multiple first fixed seats, be fixed on the 3rd power transmission shaft side face and with institute The corresponding multiple groove rings of the second rotating shaft are stated, is set in the annular groove of adjacent two second rotating shafts and is correspondingly set in More first rubber ropes in second rotating shaft and the groove ring, positioned at the supporting box side and with the driving-chain The 4th motor and the first driving-chain of connection the 4th motor and the 3rd power transmission shaft that group is connected;It is described to bend group Part includes the first supporting frame installed in the baking oven downstream, at the top of first supporting frame and spaced Two piece of second fixed plate, it is installed in rotation on the second fixed plate medial surface middle part described in any block and more perpendicular with it First short rotating shaft, be installed in rotation on it is in the middle part of another piece of the second fixed plate medial surface and relative with the described first short rotating shaft More second short rotating shafts answering, it is installed in rotation on two piece of second fixed plate medial surface and is located at the described first short rotating shaft and institute State the 3rd rotating shaft of the second short rotating shaft both sides, be liftably arranged on below the described first short rotating shaft and the second short rotating shaft Die holder, liftably it is arranged on the pressing being engaged above the described first short rotating shaft and the second short rotating shaft and with the die holder Head and it is connected respectively with the described first short rotating shaft, the second short rotating shaft and the 3rd rotating shaft for driving its synchronous turn The first dynamic drive mechanism;The bearing material component is arranged on the downstream for bending component, and it includes the first support body, rotationally Installed in first support body top and more piece fourth rotating shafts parallel with the 3rd rotating shaft and installed in described first It is connected on support body and with more 4th rotating shafts for the second drive mechanism for driving its synchronous axial system, the 4th rotating shaft It is short in the 3rd rotating shaft;The blanking component includes being arranged on the pedestal of the bearing material assemblies downstream, is installed in rotation on The rotating disk of the pedestal upper surface and in the rotating disk and the splicing that is movable to above the 4th rotating shaft Plate;Support base is installed, the transmission chain group includes being located in the in the support base on the lateral wall of the supporting box Five rotating shafts, it is meshed with the 5th roller end and the second driving-chain being engaged with the more first rotating shafts and installation It is used to adjusting at least dance roller of the second driving-chain tension force on the supporting box madial wall, the described 5th The other end of rotating shaft is also meshed with the 4th motor;The bottom of the supporting box is provided with multiple 3rd rollers;It is described First drive mechanism includes the 3rd fixed plate installed in the first supporting frame side, in the 3rd fixed plate Multiple tension adjustment wheels, be meshed with more 3rd roller ends and be engaged with multiple tension adjustment wheels Three driving-chains and the 6th motor being engaged on first supporting frame and with the 3rd driving-chain;It is described curved Component processed also includes the 3rd cylinder that on first supporting frame and upper end is connected with the die holder, installed in institute State the framework in the second fixed plate and the 4th cylinder that installation is connected on said frame and with the press head;Described Two drive mechanisms include being fixed on multiple second fixed seats of the first body side surface, are rotationally located in multiple described the Drive link in two fixed seats, more second rubber strips being set in the 4th rotating shaft and the drive link, installed in institute State the 5th motor and the driving belt of the connection transmission boom end and the 5th motor of first body side surface;
Cooling component, the cooling component include being arranged at the blanking assemblies downstream and the second support frame being matched therewith Body, two group of the 3rd fixed seat for being fixed on the second supporting frame both ends, be located in described in every group in the 3rd fixed seat two The rotating shaft of root the 6th, the conveyer belt in two the 6th rotating shafts and in second supporting frame and any institute The 6th rotating shaft is stated to be connected for driving the 7th motor that it rotates, on second supporting frame and be located at the biography Send the bearing material frid with top, at the top of second supporting frame and positioned at the bearing material frid downstream fixed mount with And on the fixed mount and towards multiple blower fans of the conveyer belt;
Gas button assembles equipment, and gas button assembling equipment is arranged at the downstream of the cooling component, and it includes the 6th support frame, the Three operating desks, electric cabinet, pressing assembly, lower mould pan feeding component, button assembling grove group and upper mould pan feeding component, the 3rd operation Platform is arranged on the top of the 6th support frame;The electric cabinet is fixed on the side of the 6th support frame, for carrying out electricity Gas control system;The lower mould pan feeding component includes being arranged at the top of the electric cabinet and higher than the second bottom of the 3rd operating desk Seat, the vibrating disk installed in the second base upper surface, one end are connected with the vibrating disk and the other end extend to it is described The first discharging cell body above 3rd operating desk, it is adjustably inserted into the limit that the first discharging cell body is used to prevent the discharging of lower mould Bit location and the rod for stiring materials for caning turn to insertion the first discharging cell body;The button assembling grove group is described including being fixed on 3rd operating desk upper surface and with the described first assembling cell body for being connected of the discharging cell body other end and being movably plugged in Push pedal in the assembling grove body;The pressing assembly include be fixed on the 3rd operating desk upper surface the first carriage, The 5th cylinder, one end at the top of first carriage connect with the 5th cylinders and the other end extend to it is described The second connecting rod in first carriage, the pendulous mass installed in the second connecting rod lower end and it is fixed on the pendulous mass Bottom surface and the extruding syringe needle above the assembling cell body;The upper mould pan feeding component includes being fixed on first carriage Second support body of side, the material storage dish on second support body and one end is connected with the material storage dish and the other end Extend to and the second discharging cell body above the assembling cell body;The lower mould pan feeding component also includes being fixed on the 3rd behaviour Make platform upper surface and be supported on the hopper support of the first discharging cell body bottom;The button assembling grove group also includes pivot and connected It is connected to two pieces of briquettings of the external end of the assembling grove, elastic component and liftable installed in two pieces of briquetting sides Ground is arranged on residing for the assembling cell body adapting table being engaged on extended line and with the briquetting;The button assembling grove group Also include the second carriage for being fixed on the 3rd operating desk bottom surface and the installed in the described second support frame bottom the 6th Cylinder, the cylinder axis of the 6th cylinder are connected through second carriage and the 3rd operating desk and with the adapting table Connect;More 3rd connecting rods perpendicular with its and in second carriage, the knob are fixed with the cylinder axis Button assembling grove group is also connected including one end with the 3rd connecting rod and the other end is connected with the second carriage inwall Spring;
Shroud ring equipment, the shroud ring equipment are arranged at the downstream of the gas button assembling equipment, and it includes the 4th operating desk, is fixed on 3rd base of the 4th operating desk upper surface, the positive stop lug boss for being installed in rotation on the 3rd base upper surface, card Pot cover on the positive stop lug boss places plate, the briquetting being liftably arranged above the positive stop lug boss and shroud ring group Part, the shroud ring component include installed in the 4th operating desk upper surface and positioned at the 3rd base side bottom plate, can It is slidably mounted on the slide plate of the plate upper surface, the 4th fixed plate installed in the bottom panel side, is located in described The adjusting screw rod that is connected in four fixed plates and with the slide plate, it is fixed on the substrate of the slide plate upper surface, installed in described Depression bar that 4th fixed seat of upper surface of base plate, one end are connected with the 4th fixed seat phase pivot, it is erected on the substrate The vertical rod on surface, the second elastic component that one end is connected with depression bar middle part and the other end is connected with the vertical rod, fixation Cross bar in the depression bar side and the pinch roller installed in the crossbar end;
Discharge component, the discharge component is including being arranged at the 7th support frame of the 4th operating desk side, one end is fixed on The supporting cantilever that extends on 7th support frame and horizontally outward, it is fixed on the supporting cantilever side and horizontally disposed second slides Rail, the connecting plate being slidably mounted on second slide rail, the L-shaped pinboard for being fixed on the connecting plate free end, peace The 9th cylinder mounted in the L-shaped pinboard end, it is arranged on the installing plate of the 9th cylinder lower end and is fixed on described Multiple second vacuum cups on installing plate;
Blanking bench is circulated, the circulation blanking bench is arranged on the lower section of the discharge component.
Because above-mentioned technical proposal is used, the present invention has following advantages compared with prior art:Pot cover lid of the present invention Making apparatus combines line, by using disk cutting equipment, grinding apparatus, cleaning equipment, heating material feeding system and cooling component Etc. being coordinated, reinforced glass pot lid can be realized(Not comprising mobile division)Making and instead of artificial, life greatly improved Produce efficiency and quality.
Brief description of the drawings
Fig. 1 is the structural representation that pot cover lid making apparatus of the present invention combines line raw material support body;
Fig. 2 is the structural representation that pot cover lid making apparatus of the present invention combines line disk cutting equipment;
Fig. 3 is the structural representation that pot cover lid making apparatus of the present invention combines line grinding apparatus;
Fig. 4 is the structural representation that pot cover lid making apparatus of the present invention combines line cleaning equipment;
Fig. 5 is that pot cover lid making apparatus of the present invention combines the part-structure schematic diagram that line heats material feeding system;
Fig. 6 is that pot cover lid making apparatus of the present invention combines the structural representation that line heats transmission component in material feeding system;
Fig. 7 is that pot cover lid making apparatus of the present invention combines the other part structural representation that line heats material feeding system;
Fig. 8 is the structural representation that pot cover lid making apparatus of the present invention combines line cooling component;
Fig. 9 is that pot cover lid making apparatus of the present invention combines the structural representation that line gas knob assembles equipment;
Figure 10 is the structural representation that pot cover lid making apparatus of the present invention combines line shroud ring equipment;
Figure 11 is the structural representation that pot cover lid making apparatus of the present invention combines line discharge component.
Embodiment
The preferred embodiment of the invention is described in detail below in conjunction with accompanying drawing:
Definition of the invention about direction is defined according to the direction of reinforced glass pot lid conveying.
Pot cover lid making apparatus of the present invention combines line, main raw material support body 1, the disk cutting equipment for including setting gradually 2nd, grinding apparatus 3, cleaning equipment 4, the heating equipment such as material feeding system 5 and cooling component 6.
Raw material support body 1 as shown in Figure 1 is used for placing toughened glass piece;Mainly include the first underframe 101, put bin 102 With the first roller 103.Wherein, the first underframe 101 is horizontally disposed, and its bottom is provided with multiple first rollers 103.Put bin 102 have two groups, and they are arranged on the upper surface of the first underframe 101 and are symmetrical arranged, and putting bin 102 for every group includes being erected at first First support frame 1022 of the upper surface of underframe 101, installed in the upper surface of the first underframe 101 and with the first support frame 1022 interval set The second support frame 1021 for putting, side(That is one article of long side of the 3rd support frame 1023)Installed in the top of the first support frame 1022 And opposite side(That is another article of long side of the 3rd support frame 1023)The 3rd support frame installed in the middle part of the second support frame 1021 1023 and in the second support frame 1021 and more head rods that one end is connected with the 3rd support frame 1023 1024, play a part of increase using head rod 1024 and entirely put the intensity of bin 102.When in use, the tempering glass of full wafer Glass rests on the second support frame 1021 and it is placed on the 3rd support frame 1023 below, according to the width of the 3rd support frame 1023 Degree can place the safety glass of varying number.In the present embodiment, the second support frame 1021 faces away from the first support frame 1022 direction is obliquely installed so that two groups of two second support frames 1021 for putting bin 102 at their top intersect and Form the angle that the number of degrees are 30 ~ 90 °.The side that 3rd support frame 1023 is connected with the second support frame 1021 is short in itself and first The side that support frame 1022 is connected, be so advantageous to avoid the safety glass in transfer of raw material support body 1 to topple over.
Disk cutting equipment 2 as shown in Figure 2, it is arranged on the downstream of raw material support body 1(It is i.e. defeated according to reinforced glass pot lid The direction determination sent, similarly hereinafter)And it is matched therewith(I.e. raw material support body 1 is arranged on the upstream of disk cutting equipment 2), mainly include Cutting assembly 21 and conveying component 22;Conveying component 22 has two groups, and they are arranged on the both sides of cutting assembly 21 and are in same On straight line, for inputting safety glass to cutting assembly 21 and exporting the safety glass after cutting.Wherein, cutting assembly 21 wraps Include the first supporting table 211, the first bearing platform 212 installed in the top of the first supporting table 211 and liftably installed in first The cutter group 213 of the top of bearing platform 212;Cutter group 213 then includes being arranged in the first supporting table 211 and extending to first The L-type support bar 2131 of the top of bearing platform 212, installed in the side of L-type support bar 2131 and extend to above the first bearing platform 212 Sleeve 2132, be installed in rotation in sleeve 2132 the first rotary shaft 2133, installed in the lower end of the first rotary shaft 2133 The first contiguous block 2134, the cutter head 2135 on the first contiguous block 2134 and installed in the top of L-type support bar 2131 And the first cylinder 2139 being connected with the first rotary shaft 2133;The lower end of first cylinder 2139 is upper with the first rotary shaft 2133 End is flexibly connected, and such first rotary shaft 2133 will not be influenceed when rotating by the first cylinder 2139.In the present embodiment, Cross bar is equipped with one contiguous block 2134 for installing cutter head 2135.When in use, the is driven first with the first cylinder 2139 One rotary shaft 2133 carries out fine setting up and down in vertical direction, and the first rotary shaft 2133 is then caused under the drive of other parts Rotate and rotated with dynamic cutter head 2135 using it as rotary shaft, so as to which the circular tempering sheet glass for making pot cover be made. In the present embodiment, conveying component 22 includes the 4th support frame 221, the second supporting table installed in the top of the 4th support frame 221 222 and multigroup roller group 223;Every group of roller group 223 includes the first base installed in the upper surface of the second supporting table 222 2231st, the sliding seat 2232 being installed in rotation in first base 2231 and the second roller in sliding seat 2232 2233.Cutter group 213 also includes being set in outer the first rotary shaft 2133 and meshed runner 2136, installed in L-type First motor 2138 of the side of support bar 2131 and the first belt 2137 on the first motor 2138 and runner 2136, So the work of the first motor 2138 can be utilized to drive the rotation of the first rotary shaft 2133.Cutting assembly 21 is also included by more Root bolt 215 is adjustably mounted at the limiting plate 214 on the first bearing platform 212(The side of limiting plate 214, which is provided with, opens up peace First fixed plate of tankage, bolt 215 are just located in the mounting groove and inserted in the first bearing platform 212;Adjusted using bolt 215 Save the tightness of the installation of limiting plate 214 and the position of limiting plate 214), it is spacing for being carried out to safety glass sheet material, it is ensured that To circular glass piece.
Grinding apparatus 3 as shown in Figure 3 is arranged on the downstream of disk cutting equipment 2, mainly includes the first operating desk 31, enters Expect component 32, sanding component 33, move material component 34 and blanking sucker 35 etc..Wherein, feeding assembly 32 includes being arranged on the first behaviour Make platform 31(First operating desk 31 is engaged with second supporting table 222 in the downstream of cutting assembly 21)The first of the side edge of top two passes Dynamic case 321, it is installed in rotation between two the first transmission cases 321 and spaced more first power transmission shafts 322(More First power transmission shaft 322 is parallel to each other and perpendicular to the first transmission case 321)And installed in the top of the first operating desk 31 and positioned at the The more gag lever posts 323 in the downstream of one power transmission shaft 322;More first power transmission shafts 322 are driven using the first transmission case 321 while are turned It is dynamic, so as to downstream transport reinforced glass pot lid disk.The downstream that material component 34 is located at feeding assembly 32 is moved, it includes being arranged on The support pedestal 341 at the top of the first operating desk 31, the clamping jaw slide rail 342 for being fixed on the top of support pedestal 341, it is slidably mounted On clamping jaw slide rail 342 and spaced multiple clamping jaws 348, installed in the bottom of clamping jaw slide rail 342 and on the gag lever post 323 Side the second cylinder 343, the first pinboard 344 installed in the lower end of the second cylinder 343, on the first pinboard 344 Rotary cylinder 345, the second pinboard 346 for being connected with rotary cylinder 345 and being rotated under its drive and it is arranged on The first vacuum cup 347 on second pinboard 346.First vacuum cup 347 is by the safety glass pot on the first power transmission shaft 322 After lid disk is drawn, it is rotated by 90 ° and is at vertical state;First clamping jaw 348 is moved to it at the first vacuum cup 347 Gripping, is downstream moved at sanding component 33 on clamping jaw slide rail 342 and is polished, subsequent second 348 is moved to herein Reinforced glass pot lid disk after gripping polishing, continuation are downstream moved.Sanding component 33 includes being installed in rotation on support The side of pedestal 341 and the material folding head group 335 being engaged with clamping jaw 348(Material folding head group 335 includes being installed in rotation on branch support group First material folding disk of 341 sides of seat and the second material folding disk for being adjustably mounted at the first material folding disk side, regulation Mode is carried out using cylinder, to realize the clamping to reinforced glass pot lid disk), installed in the top of the first operating desk 31 and be located at Support the second motor 333 of the side of pedestal 341 and beaten on the second motor 333 and with what material folding head group 335 was engaged Grinding abrasive disk 334.Blanking sucker 35 is arranged on the downstream of support pedestal 341, and it is engaged with clamping jaw 348, for drawing last The reinforced glass pot lid disk that individual clamping jaw 348 is clamped.In the present embodiment, moving material component 34 also includes being arranged on support pedestal 341 sides and the buffering clamping jaw 349 being engaged with clamping jaw 348, sanding component 33 also include being arranged on the top of the first operating desk 31 The first slide rail of multiple tracks 331 and the first sliding block 332 for being adjustably mounted on the first slide rail 331, the second motor 333 install On the first sliding block 332, polishing the distance between emery wheel 334 and material folding head group 335 can be so adjusted.
Cleaning equipment 4 as shown in Figure 4 mainly includes the 5th support frame 40, the second operating desk 41, the second transmission case 42, the Two power transmission shafts 43, spray assemblies 44 and air-dried component 45.Wherein, the second operating desk 41 is arranged on the top of the 5th support frame 40 (5th support frame 40 is arranged on the downstream of the first operating desk 31);Second transmission case 42 is arranged on two sides of the second operating desk 41 Place;For second driving shaft 43 to be parallel to each other and spaced more, they are installed in rotation on two the second transmission cases 42 Between and it is perpendicular with it;The reinforced glass pot lid disk of absorption can be transferred to the second transmission downstream by blanking sucker 35 On axle 43.Spray assemblies 44 are used to carry out water spray cleaning to the reinforced glass pot lid disk conveyed on second driving shaft 43, and it is wrapped Include on the second transmission case 42 and be located at the spraying box 441 of the top of second driving shaft 43, on the 5th support frame 40 And storage liquid case 442 positioned at the lower section of spraying box 441, installed in second driving shaft 43 and store between liquid case 442 and with spraying box 441 Corresponding water conservancy diversion enclosing 443, installed in the water pump 444 stored in liquid case 442 and one end is connected with water pump 444 and the other end At least woven hose 445 being connected with spraying box 441.Air-dry the downstream that component 45 is arranged on spray assemblies 44(Air-dry group Part 45 is arranged on the side of spray assemblies 44), for being air-dried to the reinforced glass pot lid disk after cleaning;It includes being arranged on the The two power transmission shafts guide duct 454 that first cover body 451 of both sides, one end are connected with the first cover body 451 about 43, installed in the 5th The air blower 452 that is connected on support frame 40 and with the other end of guide duct 454 and it is connected with air blower 452 for driving it 3rd motor 453 of work.
Heating material feeding system 5 as shown in Figures 5 to 7 is arranged on the downstream of cleaning equipment 4, and it mainly includes pan feeding component 51st, transmission component 52, baking oven 53, bend component 54, bearing material component 55 and blanking component 56 etc..Wherein, pan feeding component 51 includes Supporting box 511, installed in the top of supporting box 511 and spaced two the second cover bodies 512(Two the second cover bodies 512 Side edge installed in the top of supporting box 511, its bearing of trend are consistent with the conveying direction of reinforced glass pot lid disk), can It is rotatably mounted between two the second cover bodies 512 and the first rotating shaft 513 perpendicular with the second cover body 512 and installed in branch At least one set of transmission chain group 515 being connected on support casing 511 and with the every end of first rotating shaft 513;So utilize driving-chain Group 515 can drive whole synchronous axial systems of first rotating shaft 513.Baking oven 53 is arranged on the downstream of pan feeding component 51, installation in it Have and be in sustained height with first rotating shaft 513 and more second rotating shafts 531 that both ends are extended to outside baking oven 53(More second rotating shafts 531 are set at equal intervals, and the both ends of baking oven 53 offer the charging aperture and discharging opening that are engaged with the second rotating shaft 531);Every second At least one end of rotating shaft 531(I.e. on the side face of end)Offer spaced multiple annular grooves 532.Transmission component 52 Including be fixed on the lateral wall of baking oven 53 multiple first fixed seats 520, be rotationally located in multiple first fixed seats 520 The 3rd power transmission shaft 521(The bearing of trend of 3rd power transmission shaft 521 is parallel with the side wall of baking oven 53), be fixed on the 3rd power transmission shaft On 521 side faces and the multiple groove rings 522 corresponding with the second rotating shaft 531(The quantity of groove ring 522 and the second rotating shaft 531 Quantity is consistent), be set on the annular groove 532 of adjacent two second rotating shafts 531 and be correspondingly set in the second rotating shaft 531 and groove More first rubber ropes 523 on ring 522(Part in first rubber rope 523 is set in the ring of adjacent two second rotating shafts 531 On shape groove 532, and it is remaining, it is set in the second rotating shaft 531 and corresponding groove ring 522), positioned at the side of supporting box 511 And with the 4th motor 525 that is connected of transmission chain group 515 and be connected the first biography of the 4th motor 525 and the 3rd power transmission shaft 521 Dynamic chain 524.Such 4th motor 525 is capable of the rotation of the rotating shaft 531 of synchronous drive first rotating shaft 513 and second so that tempering glass Glass pot cover disk can steadily advance in course of conveying.Bend the first support frame that component 54 includes being arranged on the downstream of baking oven 53 Body 541, installed in the top of the first supporting frame 541 and spaced two piece of second fixed plate 542(Second fixed plate 542 Bearing of trend is consistent with the conveying direction of reinforced glass pot lid disk), be installed in rotation in the second fixed plate of any block 542 In the middle part of side and the more piece first short rotating shafts 546 perpendicular with it, it is installed in rotation on another piece of inner side of the second fixed plate 542 Middle face and the more piece second short rotating shafts 545 corresponding with the first short rotating shaft 546(More first short rotating shafts 546 and Duo Gen second Short rotating shaft 545 it is different in size, so as to form space for limiting reinforced glass pot lid disk in-between), rotationally Installed in two piece of second medial surface of fixed plate 542 and it is located at the first short 546 and second short rotating shaft 545 of rotating shaft)The 3rd turn of both sides Axle 543(The end of 3rd rotating shaft 543 is fixed with gear ring), be liftably arranged on the first short 546 and second short rotating shaft 545 of rotating shaft The die holder 548 of lower section, liftably it is arranged on above the first short short rotating shaft 545 of rotating shaft 546 and second and is engaged with die holder 548 Press head 544 and be connected respectively with the first short rotating shaft 546, the second short rotating shaft 543 of rotating shaft 545 and the 3rd for driving it First drive mechanism 540 of synchronous axial system;When in use, press head 544, which pushes, causes the safety glass in the top of die holder 548 Recessed and consistent with the formation radian of die holder 548 shape of pot cover disk, for press head 544 during pushing, die holder 548 is also synchronous Decline.Bearing material component 55 is arranged on the downstream for bending component 54, and it includes the first support body 551, is installed in rotation on first The top of body 551 and more piece fourth rotating shafts 552 parallel with the 3rd rotating shaft 543 and on the first support body 551 and with it is more The rotating shaft 552 of root the 4th is connected slightly short in the 3rd for the second drive mechanism 553 for driving its synchronous axial system, the 4th rotating shaft 552 Rotating shaft 543.Blanking component 56 includes being arranged on the pedestal 561 in the downstream of bearing material component 55, is installed in rotation on the upper table of pedestal 561 The rotating disk 562 in face and in rotating disk 562 and the splicing plate 563 that is movable to above the 4th rotating shaft 552 so that connect The rotating shaft 543 of flitch 563 and the 3rd is on sustained height.In the present embodiment, branch is installed on the lateral wall of supporting box 511 Seat 516 is supportted, the 5th rotating shaft 5151 that transmission chain group 515 includes being located in support base 516, is mutually nibbled with the end of the 5th rotating shaft 5151 Close and the second driving-chain 5152 for being engaged with more first rotating shafts 513 and be used on the madial wall of supporting box 511 An at least dance roller 5153 for the tension force of the second driving-chain 5152 is adjusted, the other end of the 5th rotating shaft 5151 is also electric with the 4th Machine 525 is meshed.The bottom of supporting box 511 is provided with multiple 3rd rollers 510.First drive mechanism 540 includes being arranged on 3rd fixed plate 5404 of the side of the first supporting frame 541, multiple tension adjustment wheels in the 3rd fixed plate 5404 5402nd, the 3rd driving-chain 5401 for being meshed and being engaged with multiple tension adjustment wheels 5402 with the more ends of 3rd rotating shaft 543 And on the first supporting frame 541 and the 6th motor 5403 that is engaged with the 3rd driving-chain 5401.Bend component 54 Also include be arranged on the first supporting frame 541 on and upper end be connected with die holder 548 the 3rd cylinder 547, installed in second consolidate Framework 549 on fixed board 542 and the 4th cylinder 5491 being connected on framework 549 and with press head 544.Second drives Motivation structure 553 includes being fixed on multiple second fixed seats 5531 of the side of the first support body 551, is rotationally located in multiple second Drive link 5532 in fixed seat 5531, more second rubber strips 5535 being set in the 4th rotating shaft 552 and drive link 5532, Installed in the transmission of the 5th motor 5534 and the connection end of drive link 5532 and the 5th motor 5534 of the side of the first support body 551 Belt 5533.
Cooling component 6 as shown in Figure 8 includes the second support frame for being arranged on the downstream of blanking component 56 and being matched therewith Body 61, two group of the 3rd fixed seat 62 for being fixed on the both ends of the second supporting frame 61(Two group of the 3rd fixed seat 62 is separately mounted to The both ends of two supporting frames 61), be located in every group of the 3rd fixed seat 62 two the 6th rotating shafts 67, installed in two the 6th turn Conveyer belt 63 on axle 67 and in the second supporting frame 61(When the 6th rotating shaft 67 rotates, the also synchronous circulating of conveyer belt 63 Rotate;Conveyer belt 63 is the hollow out band of metal material, avoids influence of the high temperature to it and is advantageous to radiate)And any 6th Rotating shaft 67 is connected for the 7th motor 68 for driving it to rotate(The rotation of the 6th rotating shaft 67 is driven using the 7th motor 68, is entered And drive the cycle rotation of conveyer belt 63), bearing material frid on the second supporting frame 61 and above the conveyer belt 63 64(The angle formed between bearing material frid 64 and conveyer belt 63 is 30 ~ 60 °, for accepting the safety glass of the transfer of splicing plate 563 Disk), fixed mount 65 installed in the top of the second supporting frame 61 and positioned at the downstream of bearing material frid 64 and installed in fixed mount On 65 and towards multiple blower fans 66 of conveyer belt 63.Multiple blower fans 66 are on the same straight line parallel with conveyer belt 63.
Gas knob assembling equipment 7 as shown in Figure 9 is arranged on the downstream of cooling component 6, including the 6th support frame the 71, the 3rd behaviour Make platform 72, electric cabinet 73, pressing assembly 74, lower mould pan feeding component 75, button assembling grove group 76 and upper mould pan feeding component 77 etc., use Mould is assembled and complete gas knob is formed at pot cover venthole on the gentle button of mould under to gas knob;On the device to tempering Lid of glass pot, which used when installing the operation of gas knob, manually places or removes material.Wherein, the 3rd operating desk 72 is arranged on the 6th The top of support frame 71, available for installing or fixed other related all parts.Electric cabinet 73 is fixed on the 6th support frame 71 Side, it generally respectively with pressing assembly 74, lower mould pan feeding component 75, button assembling grove group 76 and the upper phase of mould pan feeding component 77 Connection, for carrying out electric automatization control to them.Lower mould pan feeding component 75 includes second base 750, vibrating disk 751, the One discharging cell body 753, rod for stiring materials 754 and position-limiting unit 755 etc.;Second base 750 is arranged on the top of electric cabinet 73, and it is located at The side of 6th support frame 71 and it is higher than the 3rd operating desk 72, can be so matched somebody with somebody with electric cabinet 73, the 3rd operating desk 72 Close, reduce the floor space of the 3rd operating desk 72, improve the space utilization of whole reinforced glass pot lid venthole gas knob assembling equipment 7 Rate;For vibrating disk 751 using conventional, it is arranged on the upper surface of second base 750, under the gas knob that will be stored in it Mould shakes.One end of first discharging cell body 753 is connected with vibrating disk 751 and the other end extends downwardly(And non-rectilinear prolongs downwards Stretch, but seamlessly transit, be so advantageous to the discharging control of follow-up position-limiting unit 755)To the top of the 3rd operating desk 72;First Discharge cell body 753(First discharging cell body 753 can be spliced by more short cell bodies)Inside offer what mould under supply knob passed through Slotted eye and the groove extended in its longitudinal direction is at least offered at its upper surface center so that the groove and slotted eye It is connected.Position-limiting unit 755 is adjustably inserted into the first discharging cell body 753, for preventing lower mould from discharging;It includes being arranged on the One discharging cell body 753 on double end cylinder, installed in double end cylinder cylinder shaft end two pieces of pinboards and installed in turn On fishplate bar and point to first discharging cell body 753 groove two position-limited needles(Two position-limited needles are in the side of the first discharging cell body 753 Upward stagger setting), can so utilize the work synchronous drive position-limited needle of double end cylinder to be operated so that wherein one limit Under gas knob in groove insertion slotted eye of the position pin through the first discharging cell body 753 in mould so that mould temporarily can not be downstream under gas knob Conveying, now another position-limited needle is then not inserted under gas knob to be blocked in mould;Double end cylinder operation conversion direction so that another Under a piece position-limited needle insertion gas knob in mould, in the transfer process, it is to block mould under gas knob that two position-limited needles, which have the of short duration time, Realize sequentially discharging one by one for mould under gas knob.Rod for stiring materials 754 can turn to the discharging cell body 753 of insertion first, and it is also to be used for Mould under gas knob is set to discharge one by one;It is L-shaped and on the installing plate of the first discharging cell body 753 side, its one end and rotation Rotaring cylinder is connected and the other end is engaged with the groove and slotted eye of the first discharging cell body 753.In the present embodiment, lower mould pan feeding Component 75 also includes being fixed on the upper surface of the 3rd operating desk 72 and is supported on the hopper support 752 of the bottom of the first discharging cell body 753, So be advantageous to improve the support strength of the first discharging cell body 753.Button assembling grove group 76 includes being fixed on the 3rd operating desk 72 Upper surface and with the first assembling cell body 761 for being connected of the discharging other end of cell body 753 and being movably plugged in assembling cell body Push pedal 764 in 761(One end insertion assembling cell body 761 of push pedal 764 is interior and the other end generally connects with cylinders);So when When mould is inputted in assembling cell body 761 through lower mould pan feeding component 75 under gas knob, push pedal 764 forward pushes assembling cell body 761 Outer end.Button assembling grove group 76 also includes being pivotally connected to two pieces of briquettings 762 of assembling cell body 761 outer end, is arranged on First elastic component 763 of two pieces of sides of briquetting 762(Usually extension spring, for ensuring to be two pieces of briquettings without external force effect 762 can contact with each other)And liftably it is arranged on residing for assembling cell body 761 on extended line and is engaged with briquetting 762 Adapting table 760(Accept mould under the gas knob pushed by push pedal 764), be fixed on the second carriage of the bottom surface of the 3rd operating desk 72 765 and the 6th cylinder 766 installed in the bottom of the second carriage 765, the cylinder axis 7661 of the 6th cylinder 766 pass through second The operating desk 72 of support frame 765 and the 3rd and it is connected with adapting table 760;It is fixed with cylinder axis 7661 perpendicular with its and positioned at the More 3rd connecting rods 767 in two carriages 765, button assembling grove group 76 are also connected including one end with the 3rd connecting rod 767 Connect and spring 768 that the other end is connected with the inwall of the second carriage 765.So driven and held using the work of the 6th cylinder 766 The rising of platform 760 is connect, so as to which two pieces of briquettings 762 are softened and expose mould under gas knob, now spring 768 is stretched;When the 6th After cylinder 766 is removed source of the gas, the cylinder shaft 7661 that can be taken offence using the shrinkage band of spring 768 is moved down so that briquetting 762 Reset, so may insure that mould accurately can be caught in the venthole of reinforced glass pot lid under gas knob.Pressing assembly 74 includes solid It is scheduled on the first carriage 740 of the upper surface of the 3rd operating desk 72, the 5th cylinder 744, one installed in the top of the first carriage 740 End is connected with the 5th cylinder 744 and the second connecting rod 745 that the other end is extended in first carriage 740, is arranged on The pendulous mass 743 of the lower end of second connecting rod 745 and it is fixed on the bottom surface of pendulous mass 743 and positioned at assembling cell body 761 top Extruding syringe needle 741(Extruding syringe needle 741 is usually located at the top of adapting table 760).Upper mould pan feeding component 77 includes being fixed on the Second support body 771 of the side of one carriage 740, material storage dish 772 and one end and material storage dish on the second support body 771 772 be connected and the other end extend to assembling cell body 761(Generally extend to the top of adapting table 760)Second discharging of top Cell body 773;When in use, reinforced glass pot lid is arranged between the discharging cell body 773 of briquetting 762 and second.
Shroud ring equipment 8 is as shown in Figure 10, and it is arranged on the downstream of gas button assembling equipment 7, including the 4th operating desk 81, fixation The 3rd base 83 in the upper surface of the 4th operating desk 81, the positive stop lug boss 84 for being installed in rotation on base upper surface(Limit convex Platform 84 can be rotated using the axial line of itself as rotary shaft), the pot cover that is fastened on positive stop lug boss 84 place plate 86(Pot cover Place and offer the through hole being engaged with positive stop lug boss 84 at the center of plate 86;Its upper surface offers multiple tracks and is arranged concentrically simultaneously Spacing circular groove 861, for install reinforced glass pot lid), be liftably arranged on the briquetting 87 of the top of positive stop lug boss 84(Pressure Block 87 is engaged with placing the positive stop lug boss 84 of plate 86 through pot cover, when briquetting 87, which drops to, to be in contact with positive stop lug boss 84, Pot cover is placed plate 86 and is fixed)And shroud ring component 89.The shroud ring component 89 includes being arranged on the upper surface of the 4th operating desk 81 And it is located at the bottom plate 891 of the side of the 3rd base 83, is slidably mounted in the slide plate 892 of the upper surface of bottom plate 891, installed in bottom plate 4th fixed plate 890 of 891 sides, the adjusting screw rod 893 for being located in the 4th fixed plate 890 and being connected with slide plate 892, consolidate It is scheduled on substrate 894, the 4th fixed seat 895 installed in the upper surface of substrate 894, one end and the 4th fixation of the upper surface of slide plate 892 The depression bar 898 of seat 895 phase pivots connection, the vertical rod 899 for being erected in the upper surface of substrate 894, one end are connected with the middle part of depression bar 898 And the other end be connected with vertical rod 899 the second elastic component 8991, be fixed on the cross bar 897 of the side of depression bar 898 and be arranged on The pinch roller 896 of the end of cross bar 897;So when the free end to depression bar 898 applies active force, pinch roller 896 can be driven downward The product for moving and being placed to pot cover on plate 86 is extruded and is compressed the bonding jumper at its edge.In the present embodiment, shroud ring Equipment 8 also includes being fixed on the upper surface of the 4th operating desk 81 and the second support frame 82 positioned at the side of the 3rd base 83 and installation The tenth cylinder 88 being connected on the second support frame 82 and with briquetting 87, realizes the oscilaltion of briquetting 87.
And blanking component 9 is as shown in figure 11, including to be arranged on the 7th support frame 90 of the side of the 4th operating desk 81, one end solid It is scheduled on the supporting cantilever 91 extended on the 7th support frame 90 and horizontally outward(Supporting cantilever 91 and the 7th support frame 90 are perpendicular)、 The connecting plate 93 for be fixed on the side of supporting cantilever 91 and horizontally disposed slide rail 92, being slidably mounted on slide rail 92(Can be with The cylinder being connected with connecting plate 93 is installed in supporting cantilever 91, for driving connecting plate 93 to be moved on slide rail 92), it is fixed L-shaped pinboard 94 in the free end of connecting plate 93, the cylinder 95 installed in the end of L-shaped pinboard 94(Cylinder 95 is vertically arranged, and is used In the part in the vertical direction lifting of driving its underpart installation), be arranged on the installing plate 96 of the lower end of cylinder 95 and be fixed on Multiple vacuum cups 97 on installing plate 96;So using the work of cylinder 95 vacuum cup 97 can be driven rise up and down Drop.The lower section that blanking bench 10 is arranged on discharge component 9 is circulated, for accepting ready-made pot cover.
Although depicting the application by embodiment, it will be appreciated by the skilled addressee that the application have it is many deformation and Change is without departing from spirit herein, it is desirable to which appended claim includes these deformations and changed without departing from the application's Spirit.

Claims (1)

1. a kind of pot cover lid making apparatus combines line, it is characterised in that it includes:
Disk cutting equipment(2), the disk cutting equipment(2)Including the cutting assembly being engaged(21)With conveying component (22);The cutting assembly(21)Including the first supporting table(211), installed in first supporting table(211)The first of top Bearing platform(212)And liftably it is arranged on first bearing platform(212)The cutter group of top(213);The cutting Knife group(213)Including installed in first supporting table(211)Go up and extend to first bearing platform(212)The L-type of top Support bar(2131), installed in the L-type support bar(2131)Side and extend to first bearing platform(212)The set of top Cylinder(2132), be installed in rotation on the sleeve(2132)The first interior rotary shaft(2133), installed in described first rotation Axle(2133)First contiguous block of lower end(2134), installed in first contiguous block(2134)On cutter head(2135)And peace Mounted in the L-type support bar(2131)Top and with first rotary shaft(2133)The first cylinder being connected(2139);Institute State conveying component(22)It is arranged at the cutting assembly(21)Both sides, for the cutting assembly(21)Input and output steel Change glass;
Grinding apparatus(3), the grinding apparatus(3)It is arranged at the disk cutting equipment(2)Downstream, it include first operation Platform(31), feeding assembly(32), sanding component(33)Expect component with moving(34);The feeding assembly(32)Including installed in described First operating desk(31)First transmission case of the side edge of top two(321), be installed in rotation on two first transmission cases (321)Between and spaced more first power transmission shafts(322)And installed in first operating desk(31)Top and position In first power transmission shaft(322)The more gag lever posts in downstream(323);It is described to move material component(34)Positioned at the feeding assembly (32)Downstream, it include be arranged on first operating desk(31)The support pedestal at top(341), be fixed on the branch support group Seat(341)The clamping jaw slide rail at top(342), be slidably mounted in the clamping jaw slide rail(342)It is upper and spaced multiple Clamping jaw(348), installed in the clamping jaw slide rail(342)Bottom and it is located at the gag lever post(323)Second cylinder of top (343), installed in second cylinder(343)First pinboard of lower end(344), installed in first pinboard(344) On rotary cylinder(345)And the rotary cylinder(345)The second pinboard for being connected and being rotated under its drive (346)And installed in second pinboard(346)On the first vacuum cup(347);The sanding component(33)Including It is installed in rotation on the support pedestal(341)Side and with the clamping jaw(348)The material folding head group being engaged(335), peace Mounted in first operating desk(31)Top and it is located at the support pedestal(341)Second motor of side(333)And installation In second motor(333)It is upper and with the material folding head group(335)The polishing emery wheel being engaged(334);The blanking sucker (35)Installed in the support pedestal(341)Downstream and with the clamping jaw(348)It is engaged;
Cleaning equipment(4), the cleaning equipment(4)Including being arranged at first operating desk(31)5th support frame in downstream (40), installed in the 5th support frame(40)Second operating desk at top(41), installed in second operating desk(41)Two Second transmission case of side edge(42), be installed in rotation on two second transmission cases(42)Between and it is spaced more Root second driving shaft(43), spray assemblies(44)And it is arranged at the spray assemblies(44)The air-dried component in downstream(45), institute State spray assemblies(44)Including installed in second transmission case(42)Go up and be located at the second driving shaft(43)The spray of top Drench case(441), installed in the 5th support frame(40)Go up and be located at the spraying box(441)The storage liquid case of lower section(442), peace Mounted in the second driving shaft(43)With the storage liquid case(442)Between and with the spraying box(441)Corresponding water conservancy diversion encloses Gear(443), installed in the storage liquid case(442)Interior water pump(444)And one end and the water pump(444)It is connected and another End and the spraying box(441)At least woven hose being connected(445);
Heat material feeding system(5), the heating material feeding system(5)It is arranged at the cleaning equipment(4)Downstream, it includes pan feeding Component(51), transmission component(52), baking oven(53), bend component(54), bearing material component(55)With blanking component(56), it is described enter Expect component(51)Including supporting box(511), installed in the supporting box(511)Top and spaced two second covers Body(512), be installed in rotation on two second cover bodies(512)Between and the first rotating shaft perpendicular with it(513)With And installed in the supporting box(511)It is upper and with first rotating shaft every described(513)At least one set of transmission that end is connected Chain group(515);The baking oven(53)It is arranged on the pan feeding component(51)Downstream, be mounted therein with and the first rotating shaft (513)The baking oven is extended in sustained height and both ends(53)More outer second rotating shafts(531);Every described second turn Axle(531)At least one end offer spaced multiple annular grooves(532);The transmission component(52)Including fixation In the baking oven(53)Multiple first fixed seats on lateral wall(520), be rotationally located in multiple first fixed seats (520)In the 3rd power transmission shaft(521), be fixed on the 3rd power transmission shaft(521)On side face and with second rotating shaft(531) Corresponding multiple groove rings(522), be set in adjacent two second rotating shafts(531)Annular groove(532)It is interior and correspondingly It is set in second rotating shaft(531)With the groove ring(522)On more first rubber ropes(523), positioned at the support Casing(511)Side and with the transmission chain group(515)The 4th motor being connected(525)And connection the 4th motor (525)With the 3rd power transmission shaft(521)The first driving-chain(524);It is described to bend component(54)Including installed in the baking Case(53)First supporting frame in downstream(541), installed in first supporting frame(541)Top and spaced two pieces Second fixed plate(542), be installed in rotation on the second fixed plate described in any block(542)It is in the middle part of medial surface and perpendicular with it More first short rotating shafts(546), be installed in rotation on another piece of second fixed plate(542)In the middle part of medial surface and with institute State the first short rotating shaft(546)More corresponding second short rotating shafts(545), be installed in rotation on two piece of second fixed plate (542)Medial surface and it is located at the described first short rotating shaft(546)With the described second short rotating shaft(545)3rd rotating shaft of both sides(543)、 Liftably it is arranged on the described first short rotating shaft(546)With the described second short rotating shaft(545)The die holder of lower section(548), liftable Ground is arranged on the described first short rotating shaft(546)With the described second short rotating shaft(545)Top and with the die holder(548)It is engaged Press head(544)And respectively with the described first short rotating shaft(546), the second short rotating shaft(545)With the 3rd rotating shaft (543)It is connected for the first drive mechanism for driving its synchronous axial system(540);The bearing material component(55)It is arranged on described curved Component processed(54)Downstream, it includes the first support body(551), be installed in rotation on first support body(551)Top and with 3rd rotating shaft(543)More parallel 4th rotating shafts(552)And installed in first support body(551)It is upper and with it is more 4th rotating shaft described in root(552)It is connected for the second drive mechanism for driving its synchronous axial system(553), the 4th rotating shaft (552)It is short in the 3rd rotating shaft(543);The blanking component(56)Including being arranged on the bearing material component(55)The base in downstream Seat(561), be installed in rotation on the pedestal(561)The rotating disk of upper surface(562)And installed in the rotating disk (562)Go up and be movable to the 4th rotating shaft(552)The splicing plate of top(563);The supporting box(511)Lateral wall On support base is installed(516), the transmission chain group(515)Including being located in the support base(516)In the 5th rotating shaft (5151)And the 5th rotating shaft(5151)End be meshed and with the more first rotating shafts(513)Second be engaged passes Dynamic chain(5152)And installed in the supporting box(511)It is used to adjust second driving-chain on madial wall(5152)Tension force An at least dance roller(5153), the 5th rotating shaft(5151)The other end also with the 4th motor(525)Phase Engagement;The supporting box(511)Bottom multiple 3rd rollers are installed(510);First drive mechanism(540)Including Installed in first supporting frame(541)3rd fixed plate of side(5404), installed in the 3rd fixed plate(5404) On multiple tension adjustment wheels(5402)And more 3rd rotating shafts(543)End is meshed and adjusted with multiple tension force Section wheel(5402)The 3rd driving-chain being engaged(5401)And installed in first supporting frame(541)It is upper and with described the Three driving-chains(5401)The 6th motor being engaged(5403);It is described to bend component(54)Also include being arranged on the described first support Support body(541)Upper and upper end and the die holder(548)The 3rd cylinder being connected(547), installed in second fixed plate (542)On framework(549)And installed in the framework(549)It is upper and with the press head(544)The 4th gas being connected Cylinder(5491);Second drive mechanism(553)Including being fixed on first support body(551)Multiple second fixed seats of side (5531), be rotationally located in multiple second fixed seats(5531)In drive link(5532), be set in the described 4th Rotating shaft(552)With the drive link(5532)On more second rubber strips(5535), installed in first support body(551)Side 5th motor in face(5534)And the connection drive link(5532)End and the 5th motor(5534)Driving belt (5533);
Cooling component(6), the cooling component(6)Including being arranged at the blanking component(56)Downstream and be matched therewith Two supporting frames(61), be fixed on second supporting frame(61)Two group of the 3rd fixed seat at both ends(62), be located in every group 3rd fixed seat(62)Two interior the 6th rotating shafts(67), installed in two the 6th rotating shafts(67)Above and positioned at described Second supporting frame(61)Interior conveyer belt(63)And any 6th rotating shaft(67)Be connected for drive that it rotates the Seven motors(68), installed in second supporting frame(61)Go up and be located at the conveyer belt(63)The bearing material frid of top (64), installed in second supporting frame(61)Top and it is located at the bearing material frid(64)The fixed mount in downstream(65)And Installed in the fixed mount(65)It is upper and towards the conveyer belt(63)Multiple blower fans(66);
Gas button assembles equipment(7), the gas button assembling equipment(7)It is arranged at the cooling component(6)Downstream, it include the 6th Support frame(71), the 3rd operating desk(72), electric cabinet(73), pressing assembly(74), lower mould pan feeding component(75), button assembling grove Group(76)With upper mould pan feeding component(77), the 3rd operating desk(72)Installed in the 6th support frame(71)Top;Institute State electric cabinet(73)It is fixed on the 6th support frame(71)Side, for carrying out electrical control;The lower mould pan feeding component (75)Including installed in the electric cabinet(73)Top and it is higher than the 3rd operating desk(72)Second base(750), installation In the second base(750)The vibrating disk of upper surface(751), one end and the vibrating disk(751)It is connected and the other end prolongs Extend the 3rd operating desk(72)First discharging cell body of top(753), be adjustably inserted into it is described first discharging cell body (753)For preventing the position-limiting unit of lower mould discharging(755)And it can turn to insertion the first discharging cell body(753)Dial Expect bar(754);The button assembling grove group(76)Including being fixed on the 3rd operating desk(72)Upper surface and with described first Discharge cell body(753)The assembling cell body that the other end is connected(761)And movably it is plugged in the assembling cell body(761)It is interior Push pedal(764);The pressing assembly(74)Including being fixed on the 3rd operating desk(72)First carriage of upper surface (740), installed in first carriage(740)5th cylinder at top(744), one end and the 5th cylinder(744)Phase Connect and the other end extends to first carriage(740)The second interior connecting rod(745), installed in second connecting rod (745)The pendulous mass of lower end(743)And it is fixed on the pendulous mass(743)Bottom surface and it is located at the assembling cell body(761)On The extruding syringe needle of side(741);The upper mould pan feeding component(77)Including being fixed on first carriage(740)The second of side Support body(771), installed in second support body(771)On material storage dish(772)And one end and the material storage dish(772)It is connected Connect and the other end extends to and the assembling cell body(761)Second discharging cell body of top(773);The lower mould pan feeding component (75)Also include being fixed on the 3rd operating desk(72)Upper surface and be supported on it is described first discharging cell body(753)The material of bottom Groove support(752);The button assembling grove group(76)Also include being pivotally connected to the assembling cell body(761)Two pieces of outer end Briquetting(762), installed in two pieces of briquettings(762)First elastic component of side(763)And liftably it is arranged on The assembling cell body(761)On residing extended line and with the briquetting(762)The adapting table being engaged(760);The button Assembling grove group(76)Also include being fixed on the 3rd operating desk(72)Second carriage of bottom surface(765)And installed in described Second carriage(765)6th cylinder of bottom(766), the 6th cylinder(766)Cylinder axis(7661)Through described Two carriages(765)With the 3rd operating desk(72)And with the adapting table(760)It is connected;The cylinder axis(7661)On It is fixed with perpendicular with its and is located at second carriage(765)More interior 3rd connecting rods(767), the button assembling Groove group(76)Also include one end and the 3rd connecting rod(767)It is connected and the other end and second carriage(765)It is interior The spring that wall is connected(768);
Shroud ring equipment(8), the shroud ring equipment(8)It is arranged at the gas button assembling equipment(7)Downstream, it include the 4th operation Platform(81), be fixed on the 4th operating desk(81)3rd base of upper surface(83), be installed in rotation on the 3rd bottom Seat(83)The positive stop lug boss of upper surface(84), be arranged in the positive stop lug boss(84)On pot cover place plate(86), liftably It is arranged at the positive stop lug boss(84)The briquetting of top(87)And shroud ring component(89), the shroud ring component(89)Including installation In the 4th operating desk(81)Upper surface and it is located at the 3rd base(83)The bottom plate of side(891), be slidably mounted In the bottom plate(891)The slide plate of upper surface(892), installed in the bottom plate(891)4th fixed plate of side(890), wear It is located at the 4th fixed plate(890)It is upper and with the slide plate(892)The adjusting screw rod being connected(893), be fixed on the cunning Plate(892)The substrate of upper surface(894), installed in the substrate(894)4th fixed seat of upper surface(895), one end and institute State the 4th fixed seat(895)The depression bar of phase pivot connection(898), be erected in the substrate(894)The vertical rod of upper surface(899)、 One end and the depression bar(898)Middle part is connected and the other end and the vertical rod(899)The second elastic component being connected(8991)、 It is fixed on the depression bar(898)The cross bar of side(897)And installed in the cross bar(897)The pinch roller of end(896);
Discharge component(9), the discharge component(9)Including being arranged at the 4th operating desk(81)7th support frame of side (90), one end be fixed on the 7th support frame(90)Supporting cantilever that is upper and horizontally outward extending(91), to be fixed on the support outstanding Arm(91)Side and horizontally disposed second slide rail(92), be slidably mounted in second slide rail(92)On connecting plate (93), be fixed on the connecting plate(93)The L-shaped pinboard of free end(94), installed in the L-shaped pinboard(94)End 9th cylinder(95), be arranged on the 9th cylinder(95)The installing plate of lower end(96)And it is fixed on the installing plate(96)On Multiple second vacuum cups(97);
Circulate blanking bench(10), the circulation blanking bench(10)Installed in the discharge component(9)Lower section.
CN201710718031.4A 2017-08-21 2017-08-21 A kind of pot cover lid making apparatus combines line Withdrawn CN107692849A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710718031.4A CN107692849A (en) 2017-08-21 2017-08-21 A kind of pot cover lid making apparatus combines line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710718031.4A CN107692849A (en) 2017-08-21 2017-08-21 A kind of pot cover lid making apparatus combines line

Publications (1)

Publication Number Publication Date
CN107692849A true CN107692849A (en) 2018-02-16

Family

ID=61171082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710718031.4A Withdrawn CN107692849A (en) 2017-08-21 2017-08-21 A kind of pot cover lid making apparatus combines line

Country Status (1)

Country Link
CN (1) CN107692849A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114473794A (en) * 2022-01-20 2022-05-13 李莹莹 Clean safety platform device for chemical machinery

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114473794A (en) * 2022-01-20 2022-05-13 李莹莹 Clean safety platform device for chemical machinery

Similar Documents

Publication Publication Date Title
CN106587664B (en) Continuous laminated glass production line
CN107571411A (en) A kind of manual shroud ring lid production line of pot cover
CN107510376A (en) A kind of high automaticity Lid of glass pot production line
CN107584285A (en) A kind of high efficiency Lid of glass pot producing line
CN107571412A (en) One kind automation reinforced glass pot lid process units
CN107569109A (en) A kind of whole reinforced glass pot lid production line
CN107595144A (en) A kind of high automaticity reinforced glass pot lid production line
CN107473577A (en) A kind of reinforced glass pot lid production line
CN107468074A (en) A kind of pot cover automates shroud ring lid production line
CN107692849A (en) A kind of pot cover lid making apparatus combines line
CN107595141A (en) A kind of high efficiency pot cover production line
CN107495847A (en) A kind of high efficiency reinforced glass pot lid production line
CN107746174A (en) A kind of pot cover production line based on safety glass
CN208593090U (en) A kind of automatic composite production line of wood-plastic board
CN107695695A (en) A kind of pot cover overall process producing line
CN107584284A (en) A kind of reinforced glass pot lid overall process producing line
CN107595142A (en) A kind of frying pan cover overall process makes combination line
CN107601835A (en) A kind of high automaticity reinforced glass pot lid combination production line
CN107555773A (en) A kind of pot cover lid production line
CN107500516A (en) A kind of reinforced glass pot lid combines production line
CN107595139A (en) A kind of high-precision pot cover producing line
CN107470924A (en) A kind of pot cover producing line
CN107500517A (en) A kind of high efficiency reinforced glass pot lid production line
CN107595140A (en) A kind of integrated pot cover production line
CN208761659U (en) A kind of plate carrying gantry plane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180216