CN107630715A - A kind of constructing tunnel dust falling device - Google Patents

A kind of constructing tunnel dust falling device Download PDF

Info

Publication number
CN107630715A
CN107630715A CN201710780039.3A CN201710780039A CN107630715A CN 107630715 A CN107630715 A CN 107630715A CN 201710780039 A CN201710780039 A CN 201710780039A CN 107630715 A CN107630715 A CN 107630715A
Authority
CN
China
Prior art keywords
bottom plate
water
constructing tunnel
dust falling
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710780039.3A
Other languages
Chinese (zh)
Inventor
彭斌明
曹秀叶
刘艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710780039.3A priority Critical patent/CN107630715A/en
Publication of CN107630715A publication Critical patent/CN107630715A/en
Pending legal-status Critical Current

Links

Landscapes

  • Nozzles (AREA)

Abstract

The present invention relates to a kind of dust falling device, more particularly to a kind of constructing tunnel dust falling device.The technical problem to be solved in the present invention is to provide the constructing tunnel dust falling device that a kind of cost is low, time saving and energy saving, dust-laying effect is good, labor intensity is small.In order to solve the above-mentioned technical problem, the invention provides such a constructing tunnel dust falling device, bottom plate etc. is included;Bottom base plate is symmetrical to be connected with montant by bolted connection, montant bottom is provided with wheel, bottom plate top left side is provided with water injector, and bottom plate top right side is provided with and moves up and down device, and the sprinkler part of water injector is connected with moving up and down the moving parts of device.The present invention can carry out depositing dust work to job site spray water, be moved up and down by shower nozzle by starting pump working, can carry out large area watering work, reach the effect that cost is low, time saving and energy saving, dust-laying effect is good, labor intensity is small.

Description

A kind of constructing tunnel dust falling device
Technical field
The present invention relates to a kind of dust falling device, more particularly to a kind of constructing tunnel dust falling device.
Background technology
Constructing tunnel, it is the abbreviation of new Austrian method for tunnel construction, it is that Austrian scholar applies in long campaigns tunnel A kind of rational construction method of proposition from the viewpoint of rock mechanics, it is using spray anchor technology, monitoring parameter in work practice Survey etc. and with a system that rock mechanics theory is formed and a kind of new engineering construction method for being formed.
Tunnel building site generally causes and stirred up a cloud of dust in work progress, and the pollution to environment is very serious.Use at present Sprinkler, so need to expend higher cost, water consumption is also big;Artificial watering wastes time and energy, dust-laying effect is poor, work Intensity is big, therefore needs the constructing tunnel depositing dust for researching and developing that a kind of cost is low, time saving and energy saving, dust-laying effect is good, labor intensity is small badly Equipment.
The content of the invention
(1) technical problems to be solved
The present invention uses sprinkler at present in order to overcome, and so needs to expend higher cost, water consumption is also big;People Work watering is wasted time and energy, the shortcomings that dust-laying effect is poor, labor intensity is big, the technical problem to be solved in the present invention is to provide one kind into The constructing tunnel dust falling device that this is low, time saving and energy saving, dust-laying effect is good, labor intensity is small.
(2) technical scheme
In order to solve the above-mentioned technical problem, the invention provides such a constructing tunnel dust falling device, bottom is included Plate, montant, wheel, water injector and device is moved up and down, bottom base plate is symmetrical to be connected with by bolted connection Montant, montant bottom are provided with wheel, and bottom plate top left side is provided with water injector, and bottom plate top right side is provided with and moves up and down dress Put, the sprinkler part of water injector is connected with moving up and down the moving parts of device.
Preferably, water injector includes water tank, water inlet pipe, water pump, outlet pipe and shower nozzle, and spiral shell is passed on left at the top of bottom plate Tether the mode connect and water tank be installed, water tank inner bottom part is provided with water pump, is connected with water inlet pipe on the left of tank top, water inlet pipe with Connected in water tank, outlet pipe is connected with water pump, for water outlet pipe end on the right side of tank top, water outlet pipe end is provided with spray Head, shower nozzle are connected with moving up and down the moving parts of device.
Preferably, move up and down device and include slide rail, Electric Motor Wheel, driven pulley, sliding block, bracing wire and cross bar, bottom plate top Right side is vertically-mounted by bolted connection slide rail, and slide rail top is provided with Electric Motor Wheel, and slide rail bottom is provided with driven Wheel, bracing wire is slidably provided with slide rail, be connected with bracing wire between Electric Motor Wheel and driven pulley, the end of pulling top with sliding block respectively Portion connects with bottom, and sliding block right flank is connected with cross bar by bolted connection, and shower nozzle is arranged on cross bar right-hand member.
Preferably, rotating device is also included, rotating device includes rack, bearing block and gear, and sliding block right flank leads to Cross bolted mode and bearing block is installed, cross bar left end is located in the bearing in bearing block, passes through key connection in the middle part of cross bar Mode be connected with gear, right end vertical is welded with rack at the top of bottom plate, and rack be located on rear side of gear, and wheel and rack engages.
Preferably, fixing device is also included, bottom plate top is symmetrical to be provided with fixing device, and fixing device includes spiral shell Bar, knob, fixed plate and clutch shaft bearing, the left and right sides is provided with screwed hole at the top of bottom plate, is provided with screw rod in screwed hole, screw rod and Screwed hole is coordinated by screw thread, and screw tip is welded with knob, and screw rod lower horizontal is provided with fixed plate, and fixed plate crown center leads to Cross bolted mode and clutch shaft bearing is installed, screw rod bottom is located in clutch shaft bearing, and screw rod passes through interference with clutch shaft bearing Mode is connected.
Preferably, also include sleeve and spring, bottom base plate is symmetrical be bolted mode is connected with set Cylinder, sleeve is in being vertically arranged, and montant is located in sleeve, and montant is slidably matched with sleeve, between montant top and sleeve inner top It is connected with spring.
Preferably, pole and handle are also included, bottom plate top left is provided with pole, and pole is in be vertically arranged, pole bottom By bolted connection with being connected at the top of bottom plate, pole is located on the left of water tank at end, is connected at the top of pole left surface by bolt The mode horizontal connection connect has handle.
Preferably, in addition to rubber sleeve, rubber sleeve is arranged with handle, rubber sleeve is fully wrapped around by handle, rubber sleeve Thickness is at least 0.5cm.
Preferably, rubber slab is also included, the bottom of fixed plate is provided with rubber slab, and rubber slab is in horizontally disposed, rubber slab The mode being connected by screw is connected with fixed plate.
Operation principle:In use, easily the present invention can be pushed at constructing tunnel by wheel.Sprayed water by starting Device, water injector can carry out depositing dust work to construction site spray water.At the same time, start and move up and down device, up and down Mobile device drives the sprinkler part of water injector to move up and down, and so as to carry out large area water spray work, dust-laying effect is good, work Efficiency high.When need not use of the invention, close water injector and move up and down device.
Because water injector includes water tank, water inlet pipe, water pump, outlet pipe and shower nozzle, bolt is passed on left at the top of bottom plate The mode of connection is provided with water tank, and water tank inner bottom part is provided with water pump, water inlet pipe, water inlet pipe and water are connected with the left of tank top Being connected in case, outlet pipe is connected with water pump, for water outlet pipe end on the right side of tank top, water outlet pipe end is provided with shower nozzle, Shower nozzle is connected with moving up and down the moving parts of device, so operating personnel add in right amount first by water inlet pipe into water tank Clear water, then start pump working, water pump sprays the water in water tank by outlet pipe from shower nozzle, and the water of ejection is to constructing tunnel Scene carries out depositing dust work.When need not use of the invention, switch off the pump.
Because moving up and down device includes slide rail, Electric Motor Wheel, driven pulley, sliding block, bracing wire and cross bar, bottom plate top right side Vertically-mounted by bolted connection to have slide rail, slide rail top is provided with Electric Motor Wheel, and slide rail bottom is provided with driven pulley, sliding Bracing wire is slidably provided with rail, is connected with bracing wire between Electric Motor Wheel and driven pulley, end of pulling respectively with the top of sliding block and Bottom connects, and sliding block right flank is connected with cross bar by bolted connection, and shower nozzle is arranged on cross bar right-hand member, so starting electricity Driving wheel positive and negative alternate rotates, and Electric Motor Wheel pulls sliding block to move up and down by bracing wire, and sliding block, which moves up and down, drives cross bar to move up and down, Shower nozzle moves up and down therewith carries out large area water spray work.When need not use of the invention, Electric Motor Wheel is closed.
Because also including rotating device, rotating device includes rack, bearing block and gear, and sliding block right flank passes through spiral shell Tether the mode connect and bearing block is installed, cross bar left end is located in the bearing in bearing block, passes through the side of key connection in the middle part of cross bar Formula is connected with gear, and right end vertical is welded with rack at the top of bottom plate, and rack is located on rear side of gear, wheel and rack engagement, so Band moving gear moves up and down during cross bar moves up and down, because wheel and rack engages, so positive and negative alternate turns gear simultaneously It is dynamic, and then drive cross bar positive and negative alternate to rotate.I.e. cross bar is moved up and down while positive and negative alternate rotates, so as to drive shower nozzle one Rotated while moving up and down one side positive and negative alternate, into make it that the water that shower nozzle sprays is more uniform.Further improve depositing dust Effect.
It is symmetrical at the top of bottom plate to be provided with fixing device because also including fixing device, fixing device include screw rod, Knob, fixed plate and clutch shaft bearing, the bottom plate top left and right sides are provided with screwed hole, screw rod, screw rod and spiral shell are provided with screwed hole Pit is coordinated by screw thread, and screw tip is welded with knob, and screw rod lower horizontal is provided with fixed plate, and fixed plate crown center passes through Bolted mode is provided with clutch shaft bearing, and screw rod bottom is located in clutch shaft bearing, and screw rod passes through interference side with clutch shaft bearing Formula is connected, so when needing to fix the present invention, operating personnel turn screw rod clockwise by knob, and then drive and fix Plate is moved down, and in the presence of clutch shaft bearing, fixed plate will not be rotated clockwise and rotated with screw rod.When fixed plate and ground It is in close contact, continues to turn screw rod, when wheel departs from ground, stopping turns screw rod, and now the present invention is fixed.It need not consolidate When fixed of the invention, operating personnel turn screw rod counterclockwise by knob, and then drive fixed plate to move up, when wheel again with After the contact of ground, stopping turns screw rod.
Because also including sleeve and spring, bottom base plate is symmetrical be bolted mode is connected with sleeve, In being vertically arranged, montant is located in sleeve sleeve, and montant is slidably matched with sleeve, is connected between montant top and sleeve inner top There is spring, so during the mobile present invention, under the action of the spring, montant can slide up and down in sleeve, so as to Play cushioning effect so that the present invention is not easy to jolt, and extends the service life of the present invention.
Because also including pole and handle, bottom plate top left is provided with pole, and in being vertically arranged, pole bottom leads to pole Bolted mode is crossed with being connected at the top of bottom plate, pole is located on the left of water tank, is bolted at the top of pole left surface Mode horizontal connection has handle, so operating personnel hold handle, handle coordinates with wheel, can more easily move the present invention Position.
Because also including rubber sleeve, rubber sleeve is arranged with handle, rubber sleeve is fully wrapped around by handle, rubber sleeve thickness At least 0.5cm, so operating personnel contact when holding handle with rubber sleeve, rubber sleeve soft texture so that operating personnel feel Feel more comfortable.
Because also including rubber slab, the bottom of fixed plate is provided with rubber slab, and in being horizontally disposed with, rubber slab passes through rubber slab The mode of mode connects for screw is connected with fixed plate, so the present invention, by after fixation, rubber slab contacts with ground, rubber slab coefficient of friction Greatly so that the present invention is fixed to be consolidated very much.
(3) beneficial effect
The present invention can carry out depositing dust work, by shower nozzle by starting pump working to job site spray water Lower movement, large area watering work can be carried out, wheel coordinates with handle, while can easily move the position of the present invention, reaches Cost is low, time saving and energy saving, dust-laying effect is good, labor intensity is small effect.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the present invention.
Fig. 2 is second of main structure diagram of the present invention.
Fig. 3 is the third main structure diagram of the present invention.
Fig. 4 is the first enlarged diagram of fixing device of the present invention.
Fig. 5 is the 4th kind of main structure diagram of the present invention.
Fig. 6 is the 5th kind of main structure diagram of the present invention.
Fig. 7 is second of enlarged diagram of fixing device of the present invention.
Mark in accompanying drawing for:1- bottom plates, 2- montants, 3- wheels, 4- water injectors, 5- move up and down device, 41- water Case, 42- water inlet pipes, 43- water pumps, 44- outlet pipes, 45- shower nozzles, 51- slide rails, 52- Electric Motor Wheels, 53- driven pulleys, 54- sliding blocks, 55- bracing wires, 56- cross bars, 6- rotating devices, 61- racks, 62- bearing blocks, 63- gears, 7- fixing devices, 71- screwed holes, 72- Screw rod, 73- knobs, 74- fixed plates, 75- clutch shaft bearings, 8- sleeves, 9- springs, 10- poles, 11- handles, 12- rubber sleeves, 76- rubber slabs.
Embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
A kind of constructing tunnel dust falling device, as shown in figs. 1-7, include bottom plate 1, montant 2, wheel 3, water injector 4 With move up and down device 5, the bottom of bottom plate 1 is symmetrical to be connected with montant 2, the installation of the bottom of montant 2 by bolted connection There is wheel 3, the top left side of bottom plate 1 is provided with water injector 4, and the top right side of bottom plate 1 is provided with and moves up and down device 5, water injector 4 Sprinkler part is connected with moving up and down the moving parts of device 5.
Embodiment 2
A kind of constructing tunnel dust falling device, as shown in figs. 1-7, include bottom plate 1, montant 2, wheel 3, water injector 4 With move up and down device 5, the bottom of bottom plate 1 is symmetrical to be connected with montant 2, the installation of the bottom of montant 2 by bolted connection There is wheel 3, the top left side of bottom plate 1 is provided with water injector 4, and the top right side of bottom plate 1 is provided with and moves up and down device 5, water injector 4 Sprinkler part is connected with moving up and down the moving parts of device 5.
Water injector 4 includes water tank 41, water inlet pipe 42, water pump 43, outlet pipe 44 and shower nozzle 45, the top left side of bottom plate 1 Water tank 41 is installed by bolted connection, the inner bottom part of water tank 41 is provided with water pump 43, and the top left side of water tank 41 is connected with Water inlet pipe 42, water inlet pipe 42 are connected with outlet pipe 44, water tank 41 is run through in the end of outlet pipe 44 with being connected in water tank 41 on water pump 43 Top right side, the end of outlet pipe 44 are provided with shower nozzle 45, and shower nozzle 45 is connected with moving up and down the moving parts of device 5.
Embodiment 3
A kind of constructing tunnel dust falling device, as shown in figs. 1-7, include bottom plate 1, montant 2, wheel 3, water injector 4 With move up and down device 5, the bottom of bottom plate 1 is symmetrical to be connected with montant 2, the installation of the bottom of montant 2 by bolted connection There is wheel 3, the top left side of bottom plate 1 is provided with water injector 4, and the top right side of bottom plate 1 is provided with and moves up and down device 5, water injector 4 Sprinkler part is connected with moving up and down the moving parts of device 5.
Water injector 4 includes water tank 41, water inlet pipe 42, water pump 43, outlet pipe 44 and shower nozzle 45, the top left side of bottom plate 1 Water tank 41 is installed by bolted connection, the inner bottom part of water tank 41 is provided with water pump 43, and the top left side of water tank 41 is connected with Water inlet pipe 42, water inlet pipe 42 are connected with outlet pipe 44, water tank 41 is run through in the end of outlet pipe 44 with being connected in water tank 41 on water pump 43 Top right side, the end of outlet pipe 44 are provided with shower nozzle 45, and shower nozzle 45 is connected with moving up and down the moving parts of device 5.
Move up and down device 5 and include slide rail 51, Electric Motor Wheel 52, driven pulley 53, sliding block 54, bracing wire 55 and cross bar 56, bottom The top right side of plate 1 is vertically-mounted by bolted connection slide rail 51, and the top of slide rail 51 is provided with Electric Motor Wheel 52, slide rail 51 Bottom is provided with driven pulley 53, is slidably provided with bracing wire 55 on slide rail 51, drawing is connected between Electric Motor Wheel 52 and driven pulley 53 Line 55, top and bottom of the end of bracing wire 55 respectively with sliding block 54 are connected, and the right flank of sliding block 54 connects by bolted connection Cross bar 56 is connected to, shower nozzle 45 is arranged on the right-hand member of cross bar 56.
Embodiment 4
A kind of constructing tunnel dust falling device, as shown in figs. 1-7, include bottom plate 1, montant 2, wheel 3, water injector 4 With move up and down device 5, the bottom of bottom plate 1 is symmetrical to be connected with montant 2, the installation of the bottom of montant 2 by bolted connection There is wheel 3, the top left side of bottom plate 1 is provided with water injector 4, and the top right side of bottom plate 1 is provided with and moves up and down device 5, water injector 4 Sprinkler part is connected with moving up and down the moving parts of device 5.
Water injector 4 includes water tank 41, water inlet pipe 42, water pump 43, outlet pipe 44 and shower nozzle 45, the top left side of bottom plate 1 Water tank 41 is installed by bolted connection, the inner bottom part of water tank 41 is provided with water pump 43, and the top left side of water tank 41 is connected with Water inlet pipe 42, water inlet pipe 42 are connected with outlet pipe 44, water tank 41 is run through in the end of outlet pipe 44 with being connected in water tank 41 on water pump 43 Top right side, the end of outlet pipe 44 are provided with shower nozzle 45, and shower nozzle 45 is connected with moving up and down the moving parts of device 5.
Move up and down device 5 and include slide rail 51, Electric Motor Wheel 52, driven pulley 53, sliding block 54, bracing wire 55 and cross bar 56, bottom The top right side of plate 1 is vertically-mounted by bolted connection slide rail 51, and the top of slide rail 51 is provided with Electric Motor Wheel 52, slide rail 51 Bottom is provided with driven pulley 53, is slidably provided with bracing wire 55 on slide rail 51, drawing is connected between Electric Motor Wheel 52 and driven pulley 53 Line 55, top and bottom of the end of bracing wire 55 respectively with sliding block 54 are connected, and the right flank of sliding block 54 connects by bolted connection Cross bar 56 is connected to, shower nozzle 45 is arranged on the right-hand member of cross bar 56.
Also include rotating device 6, rotating device 6 includes rack 61, bearing block 62 and gear 63, the right flank of sliding block 54 Bearing block 62 is installed by bolted connection, the left end of cross bar 56 is located in the bearing in bearing block 62, the middle part of cross bar 56 Gear 63 is connected with by way of key connection, the top right end vertical of bottom plate 1 is welded with rack 61, after rack 61 is located at gear 63 Side, gear 63 engage with rack 61.
Also include fixing device 7, the top of bottom plate 1 left and right is arranged with fixing device 7, and fixing device 7 includes screw rod 72nd, knob 73, fixed plate 74 and clutch shaft bearing 75, the top of bottom plate 1 left and right sides are provided with screwed hole 71, are provided with screwed hole 71 Screw rod 72, screw rod 72 are coordinated with screwed hole 71 by screw thread, and the top of screw rod 72 is welded with knob 73, and the lower horizontal of screw rod 72 is provided with Fixed plate 74, the crown center of fixed plate 74 are provided with clutch shaft bearing 75 by bolted connection, and the bottom of screw rod 72 is positioned at the In one bearing 75, screw rod 72 is connected with clutch shaft bearing 75 by interference mode.
Also include sleeve 8 and spring 9, the bottom of bottom plate 1 is symmetrical be bolted mode is connected with sleeve 8, Sleeve 8 is in being vertically arranged, and montant 2 is located in sleeve 8, and montant 2 is slidably matched with sleeve 8, the top of montant 2 and the inner top of sleeve 8 Between be connected with spring 9.
Also include pole 10 and handle 11, the top left of bottom plate 1 is provided with pole 10, and pole 10 is in be vertically arranged, pole 10 bottoms are connected with the top of bottom plate 1 by bolted connection, and pole 10 is located at the left side of water tank 41, the left surface of pole 10 top Horizontal connection has handle 11 by bolted connection.
Also include rubber sleeve 12, be arranged rubber sleeve 12 on handle 11, rubber sleeve 12 is fully wrapped around by handle 11, rubber Cover 12 thickness and be at least 0.5cm.
Also include rubber slab 76, the bottom of fixed plate 74 is provided with rubber slab 76, and rubber slab 76 is in horizontally disposed, rubber slab 76 modes being connected by screw are connected with fixed plate 74.
Operation principle:In use, easily the present invention can be pushed at constructing tunnel by wheel 3.Sprayed by starting Water installations 4, water injector 4 can carry out depositing dust work to construction site spray water.At the same time, start and move up and down device 5, Moving up and down device 5 drives the sprinkler part of water injector 4 to move up and down, so as to carry out large area water spray work, dust-laying effect Good, operating efficiency is high.When need not use of the invention, close water injector 4 and move up and down device 5.
Because water injector 4 includes water tank 41, water inlet pipe 42, water pump 43, outlet pipe 44 and shower nozzle 45, the top of bottom plate 1 Pass on left bolted mode and water tank 41 is installed, the inner bottom part of water tank 41 is provided with water pump 43, and the top left side of water tank 41 connects Water inlet pipe 42 is connected to, water inlet pipe 42 is connected with outlet pipe 44, water is run through in the end of outlet pipe 44 with being connected in water tank 41 on water pump 43 The top right side of case 41, the end of outlet pipe 44 are provided with shower nozzle 45, and shower nozzle 45 is connected with moving up and down the moving parts of device 5, institute Appropriate clear water is added into water tank 41 by water inlet pipe 42 first with operating personnel, then starts water pump 43 and works, water pump 43 Water in water tank 41 is sprayed by outlet pipe 44 from shower nozzle 45, the water of ejection carries out depositing dust work to tunnel construction site.No When needing to use the present invention, 43 are switched off the pump.
Because moving up and down device 5 includes slide rail 51, Electric Motor Wheel 52, driven pulley 53, sliding block 54, bracing wire 55 and cross bar 56, the top right side of bottom plate 1 is vertically-mounted by bolted connection slide rail 51, and the top of slide rail 51 is provided with Electric Motor Wheel 52, The bottom of slide rail 51 is provided with driven pulley 53, is slidably provided with bracing wire 55 on slide rail 51, connects between Electric Motor Wheel 52 and driven pulley 53 Bracing wire 55 is connected to, top and bottom of the end of bracing wire 55 respectively with sliding block 54 are connected, and the right flank of sliding block 54 is bolted Mode is connected with cross bar 56, and shower nozzle 45 is arranged on the right-hand member of cross bar 56, is rotated so starting the positive and negative alternate of Electric Motor Wheel 52, Electric Motor Wheel 52 Sliding block 54 is pulled to move up and down by bracing wire 55, sliding block 54, which moves up and down, drives cross bar 56 to move up and down, and shower nozzle 45 is upper and lower therewith It is mobile to carry out large area water spray work.When need not use of the invention, Electric Motor Wheel 52 is closed.
Because also including rotating device 6, rotating device 6 includes rack 61, bearing block 62 and gear 63, and sliding block 54 is right Side is provided with bearing block 62 by bolted connection, and the left end of cross bar 56 is located in the bearing in bearing block 62, cross bar 56 Middle part is connected with gear 63 by way of key connection, and the top right end vertical of bottom plate 1 is welded with rack 61, and rack 61 is located at gear 63 rear sides, gear 63 engage with rack 61, so band moving gear 63 moves up and down during cross bar 56 moves up and down, because of gear 63 engage with rack 61, so positive and negative alternate rotates gear 63 simultaneously, and then drive the positive and negative alternate of cross bar 56 to rotate.That is cross bar 56 Move up and down while positive and negative alternate rotates, so as to drive shower nozzle 45 to move up and down while positive and negative alternate rotation, enters So that the water that shower nozzle 45 sprays is more uniform.Further improve dust-laying effect.
Because also including fixing device 7, the top of bottom plate 1 left and right is arranged with fixing device 7, and fixing device 7 includes Screw rod 72, knob 73, fixed plate 74 and clutch shaft bearing 75, the top of bottom plate 1 left and right sides are provided with screwed hole 71, in screwed hole 71 Provided with screw rod 72, screw rod 72 is coordinated with screwed hole 71 by screw thread, and the top of screw rod 72 is welded with knob 73, the lower horizontal of screw rod 72 Provided with fixed plate 74, the crown center of fixed plate 74 is provided with clutch shaft bearing 75, the bottom position of screw rod 72 by bolted connection In in clutch shaft bearing 75, screw rod 72 is connected with clutch shaft bearing 75 by interference mode, so when needing to fix the present invention, Operating personnel turn screw rod 72 clockwise by knob 73, and then drive fixed plate 74 to move down, in the work of clutch shaft bearing 75 Under, fixed plate 74 will not be rotated clockwise and rotated with screw rod 72.When fixed plate 74 and ground close contact, continue to turn spiral shell Bar 72, when wheel 3 departs from ground, stopping turns screw rod 72, and now the present invention is fixed.When need not fix the present invention, behaviour Make personnel and screw rod 72 is turned by knob 73 counterclockwise, and then drive fixed plate 74 to move up, when wheel 3 connects with ground again After touch, stop turning screw rod 72.
Because also including sleeve 8 and spring 9, the bottom of bottom plate 1 is symmetrical be bolted mode is connected with set Cylinder 8, sleeve 8 is in being vertically arranged, and montant 2 is located in sleeve 8, and montant 2 is slidably matched with sleeve 8, in the top of montant 2 and sleeve 8 Spring 9 is connected between top, so during the mobile present invention, in the presence of spring 9, montant 2 can be in sleeve 8 Inside slide up and down, so as to play cushioning effect so that the present invention is not easy to jolt, and extends the service life of the present invention.
Because also including pole 10 and handle 11, the top left of bottom plate 1 is provided with pole 10, and pole 10 is in be vertically arranged, The bottom of pole 10 is connected with the top of bottom plate 1 by bolted connection, and pole 10 is located at the left side of water tank 41, the left surface of pole 10 Horizontal connection has handle 11 by bolted connection at top, so operating personnel hold handle 11, handle 11 is matched somebody with somebody with wheel 3 Close, can more easily move the position of the present invention.
Because also including rubber sleeve 12, rubber sleeve 12 is arranged on handle 11, rubber sleeve 12 is fully wrapped around by handle 11, The thickness of rubber sleeve 12 is at least 0.5cm, so operating personnel contact when holding handle 11 with rubber sleeve 12, the quality of rubber sleeve 12 is soft It is soft so that operating personnel feel more comfortable.
Because also including rubber slab 76, the bottom of fixed plate 74 is provided with rubber slab 76, and rubber slab 76 is in horizontally disposed, rubber The mode that offset plate 76 is connected by screw is connected with fixed plate 74, so the present invention, by after fixation, rubber slab 76 contacts with ground, The coefficient of friction of rubber slab 76 is big so that the present invention is fixed to be consolidated very much.
Embodiment described above only expresses the preferred embodiment of the present invention, and its description is more specific and detailed, but simultaneously Therefore the limitation to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for one of ordinary skill in the art For, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these belong to this hair Bright protection domain.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (9)

1. a kind of constructing tunnel dust falling device, it is characterised in that include bottom plate (1), montant (2), wheel (3), water spray dress Put (4) and move up and down device (5), bottom plate (1) bottom is symmetrical to be connected with montant (2) by bolted connection, erects Bar (2) bottom is provided with wheel (3), and bottom plate (1) top left side is provided with water injector (4), and bottom plate (1) top right side is provided with up and down Mobile device (5), the sprinkler part of water injector (4) are connected with moving up and down the moving parts of device (5).
2. a kind of constructing tunnel dust falling device according to claim 1, it is characterised in that water injector (4) includes Water tank (41), water inlet pipe (42), water pump (43), outlet pipe (44) and shower nozzle (45), bottom plate (1) top left side are bolted Mode water tank (41) is installed, water tank (41) inner bottom part is provided with water pump (43), and water tank (41) top left side is connected with into water Manage (42), water inlet pipe (42) is connected with outlet pipe (44), outlet pipe (44) end is passed through with being connected in water tank (41) on water pump (43) Water tank (41) top right side is worn, outlet pipe (44) end is provided with shower nozzle (45), shower nozzle (45) and the shifting for moving up and down device (5) Dynamic component connects.
3. a kind of constructing tunnel dust falling device according to claim 2, it is characterised in that move up and down device (5) bag Slide rail (51), Electric Motor Wheel (52), driven pulley (53), sliding block (54), bracing wire (55) and cross bar (56), bottom plate (1) top right are included Side is vertically-mounted by bolted connection slide rail (51), and slide rail (51) top is provided with Electric Motor Wheel (52), slide rail (51) Bottom is provided with driven pulley (53), is slidably provided with bracing wire (55) on slide rail (51), Electric Motor Wheel (52) and driven pulley (53) it Between be connected with bracing wire (55), top and bottom of bracing wire (55) end respectively with sliding block (54) are connected, and sliding block (54) right flank leads to Cross bolted mode and be connected with cross bar (56), shower nozzle (45) is arranged on cross bar (56) right-hand member.
4. a kind of constructing tunnel dust falling device according to claim 3, it is characterised in that also include rotating device (6), rotating device (6) includes rack (61), bearing block (62) and gear (63), and sliding block (54) right flank is bolted Mode bearing block (62) is installed, cross bar (56) left end is located in the bearing in bearing block (62), passes through in the middle part of cross bar (56) The mode of key connection is connected with gear (63), and right end vertical is welded with rack (61) at the top of bottom plate (1), and rack (61) is located at gear (63) rear side, gear (63) engage with rack (61).
5. a kind of constructing tunnel dust falling device according to claim 4, it is characterised in that also include fixing device (7), left and right is arranged with fixing device (7) at the top of bottom plate (1), and fixing device (7) includes screw rod (72), knob (73), consolidated Fixed board (74) and clutch shaft bearing (75), bottom plate (1) the top left and right sides are provided with screwed hole (71), spiral shell are provided with screwed hole (71) Bar (72), screw rod (72) are coordinated with screwed hole (71) by screw thread, and screw rod (72) top is welded with knob (73), under screw rod (72) Fang Shuiping is provided with fixed plate (74), and fixed plate (74) crown center is provided with clutch shaft bearing (75) by bolted connection, Screw rod (72) bottom is located in clutch shaft bearing (75), and screw rod (72) is connected with clutch shaft bearing (75) by interference mode.
A kind of 6. constructing tunnel dust falling device according to claim 5, it is characterised in that also include sleeve (8) and Spring (9), bottom plate (1) bottom is symmetrical be bolted mode is connected with sleeve (8), sleeve (8) in being vertically arranged, Montant (2) is located in sleeve (8), and montant (2) is slidably matched with sleeve (8), between montant (2) top and sleeve (8) inner top It is connected with spring (9).
A kind of 7. constructing tunnel dust falling device according to claim 6, it is characterised in that also include pole (10) and Handle (11), bottom plate (1) top left are provided with pole (10), and for pole (10) in being vertically arranged, pole (10) bottom passes through bolt With being connected at the top of bottom plate (1), pole (10) is located on the left of water tank (41) mode of connection, passes through spiral shell at the top of pole (10) left surface Tethering the mode horizontal connection connect has handle (11).
8. a kind of constructing tunnel dust falling device according to claim 7, it is characterised in that also including rubber sleeve (12) rubber sleeve (12), is arranged on handle (11), rubber sleeve (12) is fully wrapped around by handle (11), and rubber sleeve (12) thickness is extremely It is 0.5cm less.
9. a kind of constructing tunnel dust falling device according to claim 8, it is characterised in that also include rubber slab (76), the bottom of fixed plate (74) is provided with rubber slab (76), and in being horizontally disposed with, rubber slab (76) is connected rubber slab (76) by screw The mode connect is connected with fixed plate (74).
CN201710780039.3A 2017-09-01 2017-09-01 A kind of constructing tunnel dust falling device Pending CN107630715A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710780039.3A CN107630715A (en) 2017-09-01 2017-09-01 A kind of constructing tunnel dust falling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710780039.3A CN107630715A (en) 2017-09-01 2017-09-01 A kind of constructing tunnel dust falling device

Publications (1)

Publication Number Publication Date
CN107630715A true CN107630715A (en) 2018-01-26

Family

ID=61100351

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710780039.3A Pending CN107630715A (en) 2017-09-01 2017-09-01 A kind of constructing tunnel dust falling device

Country Status (1)

Country Link
CN (1) CN107630715A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108300417A (en) * 2018-01-31 2018-07-20 庄玉琼 A kind of constructing tunnel dust-proofing agent draft machine
CN108361058A (en) * 2018-02-07 2018-08-03 曾福宁 A kind of constructing tunnel watering and lowering dust equipment
CN108379973A (en) * 2018-03-12 2018-08-10 赣州牛研科技有限公司 Use depositing dust machine to a kind of construction of hydro project
CN108532524A (en) * 2018-03-21 2018-09-14 南昌华学科技有限公司 A kind of road construction water sprayer
CN108722705A (en) * 2018-05-29 2018-11-02 张罗悦 A kind of movable tunnel construction atomizing de-dusting apparatus
CN108952792A (en) * 2018-07-09 2018-12-07 朱绍雄 A kind of energy-saving watering and lowering dust equipment of constructing tunnel
CN109653786A (en) * 2019-03-05 2019-04-19 华北理工大学 A kind of pit mining dust suppression equipment
CN110195569A (en) * 2019-05-06 2019-09-03 黄天楚 A kind of oil exploitation rotary drilling equipment
CN110237623A (en) * 2019-06-24 2019-09-17 陈莹 A kind of construction environmental protection device for reducing dust
CN111963977A (en) * 2020-07-29 2020-11-20 湖南一肯照明有限公司 Wisdom street lamp with dust fall function
CN112282831A (en) * 2020-11-28 2021-01-29 湖南煤矿机械有限公司 Spraying dust-settling device of electric traction coal mining machine
CN115554792A (en) * 2022-05-23 2023-01-03 陈益锋 Dust suppressing vehicle for bridge and tunnel construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001219422A (en) * 2000-02-10 2001-08-14 Nakayama Tekko Kk Waste compactly treating concrete cutting machine
CN106833712A (en) * 2017-03-21 2017-06-13 郭钦 A kind of oil high efficiente callback device
CN106862126A (en) * 2017-02-14 2017-06-20 刘荣春 A kind of municipal road billboard wiping device
CN107029371A (en) * 2017-04-25 2017-08-11 刘燕 A kind of lane residential building fire-extinguishing truck
CN107049200A (en) * 2017-05-09 2017-08-18 李长财 A kind of shoes processing vamp high-efficiency cleaning device
CN107059747A (en) * 2017-06-21 2017-08-18 惠安普科优利网络科技有限公司 A kind of quick dust falling device of construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001219422A (en) * 2000-02-10 2001-08-14 Nakayama Tekko Kk Waste compactly treating concrete cutting machine
CN106862126A (en) * 2017-02-14 2017-06-20 刘荣春 A kind of municipal road billboard wiping device
CN106833712A (en) * 2017-03-21 2017-06-13 郭钦 A kind of oil high efficiente callback device
CN107029371A (en) * 2017-04-25 2017-08-11 刘燕 A kind of lane residential building fire-extinguishing truck
CN107049200A (en) * 2017-05-09 2017-08-18 李长财 A kind of shoes processing vamp high-efficiency cleaning device
CN107059747A (en) * 2017-06-21 2017-08-18 惠安普科优利网络科技有限公司 A kind of quick dust falling device of construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
朱成璞: "《卫生杀虫药械应用指南》", 30 November 1988, 上海交通大学出版社 *
莫海军: "《机械设计基础:少学时》", 31 August 2014, 华南理工大学出版社 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108300417A (en) * 2018-01-31 2018-07-20 庄玉琼 A kind of constructing tunnel dust-proofing agent draft machine
CN108361058A (en) * 2018-02-07 2018-08-03 曾福宁 A kind of constructing tunnel watering and lowering dust equipment
CN108379973A (en) * 2018-03-12 2018-08-10 赣州牛研科技有限公司 Use depositing dust machine to a kind of construction of hydro project
CN108532524A (en) * 2018-03-21 2018-09-14 南昌华学科技有限公司 A kind of road construction water sprayer
CN108722705A (en) * 2018-05-29 2018-11-02 张罗悦 A kind of movable tunnel construction atomizing de-dusting apparatus
CN108952792A (en) * 2018-07-09 2018-12-07 朱绍雄 A kind of energy-saving watering and lowering dust equipment of constructing tunnel
CN109653786A (en) * 2019-03-05 2019-04-19 华北理工大学 A kind of pit mining dust suppression equipment
CN110195569A (en) * 2019-05-06 2019-09-03 黄天楚 A kind of oil exploitation rotary drilling equipment
CN110237623A (en) * 2019-06-24 2019-09-17 陈莹 A kind of construction environmental protection device for reducing dust
CN111963977A (en) * 2020-07-29 2020-11-20 湖南一肯照明有限公司 Wisdom street lamp with dust fall function
CN112282831A (en) * 2020-11-28 2021-01-29 湖南煤矿机械有限公司 Spraying dust-settling device of electric traction coal mining machine
CN115554792A (en) * 2022-05-23 2023-01-03 陈益锋 Dust suppressing vehicle for bridge and tunnel construction

Similar Documents

Publication Publication Date Title
CN107630715A (en) A kind of constructing tunnel dust falling device
CN206233219U (en) A kind of construction site ground multi-stag roller-compactor
CN206503129U (en) A kind of construction site quick roller-compactor in ground
CN107059747A (en) A kind of quick dust falling device of construction
CN107503682A (en) A kind of monitor installation perforating device
CN107127171A (en) A kind of traffic bridge roadblock device for high-efficiency cleaning
CN106272927A (en) Concrete prefabricated beam automatic spray health-preservation device
CN107252787A (en) A kind of efficient cleaning equipment of building implement
CN108057298A (en) A kind of construction environmental protection device
CN205636607U (en) Bridge is with water spray heat sink
CN107100080A (en) Sprinkler is used after a kind of bridge is good
CN205477360U (en) Quick digging device in ground for building
CN106859516A (en) A kind of family removes grease and uses high pressure washer
CN217028781U (en) Anchor rod drilling machine for digging and improving high slope
CN107376550A (en) Movable spraying system and its spraying method
CN109277218A (en) A kind of mine ionic liquid inhibitor spraying device and spraying method
CN115749154A (en) Green building roof
CN206752327U (en) Sprinkler is used after a kind of bridge is good
CN212663039U (en) Portable dust device that sprays of building site
CN220226459U (en) Construction guardrail
CN207071557U (en) A kind of traffic bridge roadblock device for high-efficiency cleaning
CN211537041U (en) Building engineering construction is with portable dust device
CN207295596U (en) A kind of quick dust falling device of construction
CN214460348U (en) Powder spraying pile machine with portable dust suppression system
CN210841002U (en) Spraying structure for building garden green belt

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180126