CN107611939A - A kind of block supply ring network fault quickly isolates and load transfer method - Google Patents

A kind of block supply ring network fault quickly isolates and load transfer method Download PDF

Info

Publication number
CN107611939A
CN107611939A CN201710610727.5A CN201710610727A CN107611939A CN 107611939 A CN107611939 A CN 107611939A CN 201710610727 A CN201710610727 A CN 201710610727A CN 107611939 A CN107611939 A CN 107611939A
Authority
CN
China
Prior art keywords
node
power supply
fault
switch
ring network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710610727.5A
Other languages
Chinese (zh)
Other versions
CN107611939B (en
Inventor
王虎森
马运亮
冉茂兵
吴战伟
杨云鹏
程中普
闫玲玲
陈春宇
束芳芳
季国瑞
陈新
王盛开
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XJ Electric Co Ltd
Original Assignee
XJ Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XJ Electric Co Ltd filed Critical XJ Electric Co Ltd
Priority to CN201710610727.5A priority Critical patent/CN107611939B/en
Publication of CN107611939A publication Critical patent/CN107611939A/en
Application granted granted Critical
Publication of CN107611939B publication Critical patent/CN107611939B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Small-Scale Networks (AREA)

Abstract

本发明公开了一种区域供电环网故障快速隔离和负荷转移方法,包含以下步骤:A、智能终端实时采集本间隔节点的电流电压数据,各开关的开关状态以及供电网络的拓扑信息;B、通过高速通信网络,发送本节点的电流采样值,开关状态,远方控制信息给相邻的供电节点,同时接受相邻节点发送的电流采样值,开关状态,远方控制信息,本发明可用于区域供电网,不依赖主站系统,能够自动完成故障隔离和非故障区域的供电恢复,最小化故障停电范围,非故障区域停电时间短,提高了供电可靠性。

The invention discloses a method for rapid fault isolation and load transfer of a regional power supply ring network. Through the high-speed communication network, the current sampling value, switch state, and remote control information of the node are sent to the adjacent power supply node, and the current sampling value, switch state, and remote control information sent by the adjacent node are accepted at the same time. The present invention can be used for regional power supply Network, independent of the main station system, can automatically complete fault isolation and power supply restoration in non-faulty areas, minimize the scope of fault power outages, shorten the power outage time in non-faulty areas, and improve power supply reliability.

Description

一种区域供电环网故障快速隔离和负荷转移方法A fast fault isolation and load transfer method for regional power supply ring network

技术领域technical field

本发明涉及电力系统自动化领域,具体是一种区域供电环网故障快速隔离和负荷转移方法。The invention relates to the field of electric power system automation, in particular to a method for rapid fault isolation and load transfer of a regional power supply ring network.

背景技术Background technique

为提高区域供电的可靠性,现在配电网络开始推广环网供电方式,由于配网中线路距离短,常规的过流保护存在定值、时限难于整定,无法满足继电保护的基本要求。目前国内配电自动化多采用重合器/分段器方式、基于通信的馈线自动化方式等。重合器/分段器方式这种控制方式采用断路器作为跳闸开关,通过多次重合断路器和负荷开关来确定故障区域,需要多次跳合开关,开关损耗大,停电时间较长。基于通信的馈线自动化方式保护功能完全依赖主站端进行,故障定位时间较长,故障后整条线路都会短时停电。以上方式已经不符合用户特别是重要负荷对供电高可靠性的要求。In order to improve the reliability of regional power supply, the power distribution network is now promoting the ring network power supply mode. Due to the short distance of the lines in the distribution network, the conventional overcurrent protection has a fixed value and a time limit that is difficult to set, and cannot meet the basic requirements of relay protection. At present, the domestic power distribution automation mostly adopts the recloser/sectioner method, the communication-based feeder automation method, etc. The recloser/sectioner method uses the circuit breaker as the trip switch, and determines the fault area by reclosing the circuit breaker and load switch multiple times, which requires multiple trip switches, resulting in large switching losses and long power outages. The protection function of the communication-based feeder automation mode is completely dependent on the master station, and the fault location takes a long time. After the fault, the entire line will be cut off for a short time. The above methods no longer meet the requirements of users, especially important loads, for high reliability of power supply.

发明内容Contents of the invention

本发明要解决的技术问题是提供一种区域供电环网故障快速隔离和负荷转移方法,以解决背景技术中提到的问题。The technical problem to be solved by the present invention is to provide a method for rapid fault isolation and load transfer of a regional power supply ring network, so as to solve the problems mentioned in the background technology.

为实现上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:

一种区域供电环网故障快速隔离和负荷转移方法,包含以下步骤:A method for rapid fault isolation and load transfer of a regional power supply ring network, comprising the following steps:

A、智能终端实时采集本间隔节点的电流电压数据,各开关的开关状态以及供电网络的拓扑信息;A. The smart terminal collects the current and voltage data of the nodes in this interval in real time, the switching status of each switch and the topology information of the power supply network;

B、通过高速通信网络,发送本节点的电流采样值,开关状态,远方控制信息给相邻的供电节点,同时接受相邻节点发送的电流采样值,开关状态,远方控制信息;B. Through the high-speed communication network, send the current sampling value, switch status, and remote control information of the node to the adjacent power supply node, and at the same time accept the current sampling value, switch status, and remote control information sent by the adjacent node;

C、根据系统设置的保护逻辑结合各节点的实时数据,在故障情况下,依据系统配置的保护逻辑,快速判断故障类型和故障区域;C. According to the protection logic set by the system combined with the real-time data of each node, in the event of a fault, according to the protection logic configured by the system, the fault type and fault area can be quickly judged;

D、根据故障区域启动跳闸程序,跳开相应的开关,隔离故障;D. Start the trip program according to the fault area, trip the corresponding switch, and isolate the fault;

E、故障隔离后,所在区域节点开关断开后发送远方合闸命令到通信网络,供电环网常开节点收到远合命令后启动合闸程序,合上常开开关,完成负荷转移,恢复非故障区域的供电。E. After the fault is isolated, the node switch in the area is disconnected and sends a remote closing command to the communication network. After receiving the remote closing command, the normally open node of the power supply ring network starts the closing procedure, closes the normally open switch, completes load transfer, and restores Power supply for non-faulty areas.

作为本发明的优选方案:所述步骤2具体方法:各节点的智能终端通过光缆或双绞线进行手拉手式连接;每个节点只与上下游的相邻节点进行数据交换,传输模拟量数据,开关状态,远方控制信息;数据按照固定时间间隔发送,以全双工方式工作,数据传输进行校验和应答,连续多次校验出错或无应答,启动告警程序。As a preferred solution of the present invention: the specific method of step 2: the intelligent terminals of each node are connected hand in hand through optical cables or twisted pairs; each node only exchanges data with upstream and downstream adjacent nodes, and transmits analog data , switch status, remote control information; data is sent at fixed time intervals, works in full-duplex mode, data transmission is verified and responded, and the alarm program is started for multiple consecutive verification errors or no response.

作为本发明的优选方案:所述步骤3的具体方法是:各节点依据自身采样值和接收相邻节点的采样值计算故障电流,以差动速断为主保护,过流方向保护为后备保护,判断故障类型和故障区域。As a preferred solution of the present invention: the specific method of the step 3 is: each node calculates the fault current according to its own sampling value and receiving the sampling value of the adjacent node, with the differential quick-break as the main protection, and the overcurrent direction protection as the backup protection, Determine the fault type and fault area.

作为本发明的优选方案:所述步骤4的具体方法是:供电环网故障后,对应区域节点的智能终端会启动跳闸程序,驱动断路器跳闸,同时发送对侧跳闸命令,让故障区域另一侧的智能终端启动跳闸程序跳开相应对侧断路器,隔离故障。As a preferred solution of the present invention: the specific method of step 4 is: after the power supply ring network fails, the intelligent terminal of the corresponding regional node will start the trip program, drive the circuit breaker to trip, and send the opposite side trip command at the same time, so that the other side of the faulty region The intelligent terminal on the side starts the trip program to trip the corresponding circuit breaker on the opposite side to isolate the fault.

作为本发明的优选方案:所述步骤4的具体方法是:故障隔离后,由所在故障区域节点的智能终端检测断路器位置,当开关在分位后向通信网络发送远方合闸命令,通信网络各节点根据供电环网的拓扑结构结合节点中的常开开关位置,启动对应节点开关的合闸程序,合上常开开关,完成负荷的转移,恢复非故障区域的供电。As a preferred solution of the present invention: the specific method of the step 4 is: after the fault isolation, the intelligent terminal of the node in the fault area detects the position of the circuit breaker, and when the switch sends a remote closing command to the communication network after the switch is divided, the communication network According to the topological structure of the power supply ring network and the position of the normally open switch in the node, each node starts the closing procedure of the corresponding node switch, closes the normally open switch, completes the load transfer, and restores the power supply in the non-faulty area.

作为本发明的优选方案:所述智能终端包含模拟量采集模块和开关量采集模块,出口驱动模块,通信模块和数据处理模块;所述智能终端实时采集本节点进出环网的电流电压模拟量数据,开关的跳合位状态。As a preferred solution of the present invention: the intelligent terminal includes an analog quantity acquisition module and a switch quantity acquisition module, an export drive module, a communication module and a data processing module; the intelligent terminal collects the current and voltage analog quantity data of the node entering and leaving the ring network in real time , The switch's tripping state.

与现有技术相比,本发明的有益效果是:本发明可用于区域供电网,不依赖主站系统,能够自动完成故障隔离和非故障区域的供电恢复,最小化故障停电范围,非故障区域停电时间短,提高了供电可靠性。Compared with the prior art, the beneficial effects of the present invention are: the present invention can be used in regional power supply networks without relying on the main station system, can automatically complete fault isolation and power supply recovery in non-faulty areas, minimize the scope of fault power outages, and non-faulty areas Short power outage time improves power supply reliability.

附图说明Description of drawings

图1是本发明区域供电环网故障快速隔离和负荷转移的系统结构图;Fig. 1 is the system structural diagram of fast fault isolation and load transfer of regional power supply ring network of the present invention;

图2是本发明例供电故障及处理示意图。Fig. 2 is a schematic diagram of a power supply failure and its processing according to an example of the present invention.

具体实施方式detailed description

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

请参阅图1-2,一种区域供电环网故障快速隔离和负荷转移方法,包含以下步骤:Please refer to Figure 1-2, a method for rapid fault isolation and load transfer of a regional power supply ring network, including the following steps:

A、智能终端实时采集本间隔节点的电流电压数据,各开关的开关状态以及供电网络的拓扑信息;A. The smart terminal collects the current and voltage data of the nodes in this interval in real time, the switching status of each switch and the topology information of the power supply network;

B、通过高速通信网络,发送本节点的电流采样值,开关状态,远方控制信息给相邻的供电节点,同时接受相邻节点发送的电流采样值,开关状态,远方控制信息;B. Through the high-speed communication network, send the current sampling value, switch status, and remote control information of the node to the adjacent power supply node, and at the same time accept the current sampling value, switch status, and remote control information sent by the adjacent node;

C、根据系统设置的保护逻辑结合各节点的实时数据,在故障情况下,依据系统配置的保护逻辑,快速判断故障类型和故障区域;C. According to the protection logic set by the system combined with the real-time data of each node, in the event of a fault, according to the protection logic configured by the system, the fault type and fault area can be quickly judged;

D、根据故障区域启动跳闸程序,跳开相应的开关,隔离故障;D. Start the trip program according to the fault area, trip the corresponding switch, and isolate the fault;

E、故障隔离后,所在区域节点开关断开后发送远方合闸命令到通信网络,供电环网常开节点收到远合命令后启动合闸程序,合上常开开关,完成负荷转移,恢复非故障区域的供电。E. After the fault is isolated, the node switch in the area is disconnected and sends a remote closing command to the communication network. After receiving the remote closing command, the normally open node of the power supply ring network starts the closing procedure, closes the normally open switch, completes load transfer, and restores Power supply for non-faulty areas.

步骤2具体方法:各节点的智能终端通过光缆或双绞线进行手拉手式连接;每个节点只与上下游的相邻节点进行数据交换,传输模拟量数据,开关状态,远方控制信息;数据按照固定时间间隔发送,以全双工方式工作,数据传输进行校验和应答,连续多次校验出错或无应答,启动告警程序。Step 2 Specific method: The intelligent terminals of each node are connected hand in hand through optical cables or twisted pairs; each node only exchanges data with upstream and downstream adjacent nodes, and transmits analog data, switch status, and remote control information; data Send at fixed time intervals, work in full-duplex mode, check and respond to data transmission, and start the alarm program if there are multiple consecutive check errors or no response.

步骤3的具体方法是:各节点依据自身采样值和接收相邻节点的采样值计算故障电流,以差动速断为主保护,过流方向保护为后备保护,判断故障类型和故障区域。The specific method of step 3 is: each node calculates the fault current according to its own sampling value and the sampling value received from adjacent nodes, the differential quick-break is the main protection, the overcurrent direction protection is the backup protection, and the fault type and fault area are judged.

步骤4的具体方法是:供电环网故障后,对应区域节点的智能终端会启动跳闸程序,驱动断路器跳闸,同时发送对侧跳闸命令,让故障区域另一侧的智能终端启动跳闸程序跳开相应对侧断路器,隔离故障。The specific method of step 4 is: after the power supply ring network fails, the intelligent terminal of the corresponding area node will start the trip program, drive the circuit breaker to trip, and send the opposite side trip command at the same time, let the intelligent terminal on the other side of the fault area start the trip program to trip Corresponding opposite side circuit breaker, isolate the fault.

步骤4的具体方法是:故障隔离后,由所在故障区域节点的智能终端检测断路器位置,当开关在分位后向通信网络发送远方合闸命令,通信网络各节点根据供电环网的拓扑结构结合节点中的常开开关位置,启动对应节点开关的合闸程序,合上常开开关,完成负荷的转移,恢复非故障区域的供电。The specific method of step 4 is: after the fault is isolated, the intelligent terminal of the node in the fault area detects the position of the circuit breaker. Combined with the position of the normally open switch in the node, start the closing procedure of the corresponding node switch, close the normally open switch, complete the load transfer, and restore the power supply in the non-faulty area.

智能终端包含模拟量采集模块和开关量采集模块,出口驱动模块,通信模块和数据处理模块;所述智能终端实时采集本节点进出环网的电流电压模拟量数据,开关的跳合位状态。The intelligent terminal includes an analog quantity acquisition module and a switch quantity acquisition module, an export drive module, a communication module and a data processing module; the intelligent terminal collects the current and voltage analog quantity data of the node entering and leaving the ring network in real time, and the switching state of the switch.

本发明的工作原理是:图2是本发明保护系统故障隔离及负荷转移的示意图,首先各节点实时采集本间隔节点的电流电压数据,各开关的开关状态以及供电网络的拓扑信息;The working principle of the present invention is: FIG. 2 is a schematic diagram of fault isolation and load transfer of the protection system of the present invention. First, each node collects the current and voltage data of the interval node in real time, the switch state of each switch and the topology information of the power supply network;

然后通过高速通信网络,发送本节点的电流采样值,开关状态,远方控制信息给相邻的供电节点,同时接受相邻节点发送的电流采样值,开关状态,远方控制信息;Then through the high-speed communication network, send the current sampling value, switch status, and remote control information of the node to the adjacent power supply node, and at the same time accept the current sampling value, switch status, and remote control information sent by the adjacent node;

根据系统设置的保护逻辑结合各节点的实时数据,图2中D段线路发生故障时,系统根据#N节点和#(N-1)节点的电流值做差|I1-I2|>差动定值时启动跳闸,#N节点断路器QF2跳闸,同时#N节点向#(N-1)节点发送对侧跳闸命令和远方合闸命令,经过多次确认后#(N-1)节点断路器QF1跳闸,隔离D段线路,当检测到#(N-1)节点断路器QF1跳开后,执行远方合闸命令,合上#(N-1)节点常开断路器QF2,由进线2给#(N-1)节点出线负荷供电。电流差动保护动作时间小于40ms,故障隔离时间小于90ms(包含断路器开断时间50ms);系统启动合闸动作时间小于90ms(包含断路器合闸时间80ms),故障隔离+负荷转移的总体时间小于180ms。According to the protection logic set by the system combined with the real-time data of each node, when a fault occurs on the line D in Figure 2, the system makes a differential |I1-I2|> differential determination based on the current values of #N nodes and #(N-1) nodes When the value is set to start tripping, #N node circuit breaker QF2 trips, and #N node sends the opposite side trip command and remote closing command to #(N-1) node at the same time, after multiple confirmations #(N-1) node circuit breaker QF1 trips and isolates the D-section line. When it is detected that the #(N-1) node circuit breaker QF1 is tripped, execute the remote closing command, close the #(N-1) node normally open circuit breaker QF2, and the incoming line 2 Supply power to #(N-1) node outgoing loads. The current differential protection action time is less than 40ms, the fault isolation time is less than 90ms (including the circuit breaker opening time of 50ms); the system startup closing action time is less than 90ms (including the circuit breaker closing time of 80ms), the overall time of fault isolation + load transfer Less than 180ms.

图2中故障B发生在#2节点母线时,过流方向保护启动,判断故障发生在母线侧,启动跳闸程序同时跳开#2节点断路器QF1,QF2,隔离#2节点母线,系统检测到断路器分闸位置后,向相邻的#1节点和#3节点发送远方合闸命令,各节点接收到远方合闸命令后经过多次确认并根据环网拓扑结构判断常开断路器位置,如图2中#(N-1)节点断路器QF2,由#(N-1)节点智能保护终端启动合闸程序,合上断路器QF2,进线2对#2节点后边的负荷进行供电。电流方向保护动作时间小于40ms,故障隔离时间小于90ms(包含断路器开断时间50ms);系统启动合闸动作时间小于90ms(包含断路器合闸时间80ms),故障隔离+负荷转移的总体时间小于180ms。In Figure 2, when the fault B occurred on the #2 node bus, the overcurrent direction protection was activated, and it was judged that the fault occurred on the bus side, and the tripping program was started to trip the #2 node circuit breaker QF1, QF2 at the same time, isolating the #2 node bus, and the system detected After the circuit breaker opens the position, send the remote closing command to the adjacent #1 node and #3 node. After receiving the remote closing command, each node will confirm the position of the normally open circuit breaker according to the topology of the ring network after multiple confirmations. As shown in the #(N-1) node circuit breaker QF2 in Figure 2, the #(N-1) node intelligent protection terminal starts the closing procedure, closes the circuit breaker QF2, and the incoming line 2 supplies power to the load behind the #2 node. The current direction protection action time is less than 40ms, the fault isolation time is less than 90ms (including the circuit breaker opening time of 50ms); the system startup closing action time is less than 90ms (including the circuit breaker closing time of 80ms), and the overall time of fault isolation + load transfer is less than 180ms.

故障发生后,所述系可以通过无线、双绞线或光缆多种通信方式向主站系统发送故障信息,辅助值班人员对供电网络的监控以及故障的检修。After a fault occurs, the system can send fault information to the main station system through multiple communication methods such as wireless, twisted pair or optical cable, and assist the on-duty personnel in monitoring the power supply network and troubleshooting the fault.

上述实施例不以任何形式限定本发明,凡采取等同替换或等效变换的形式所获得的技术方案,均落在本发明的保护范围之内。The above-mentioned embodiments do not limit the present invention in any form, and all technical solutions obtained in the form of equivalent replacement or equivalent transformation fall within the protection scope of the present invention.

Claims (6)

1.一种区域供电环网故障快速隔离和负荷转移方法,其特征在于,包含以下步骤:1. A method for rapid isolation and load transfer of a regional power supply ring network failure, characterized in that it comprises the following steps: A、智能终端实时采集本间隔节点的电流电压数据,各开关的开关状态以及供电网络的拓扑信息;A. The smart terminal collects the current and voltage data of the nodes in this interval in real time, the switching status of each switch and the topology information of the power supply network; B、通过高速通信网络,发送本节点的电流采样值,开关状态,远方控制信息给相邻的供电节点,同时接受相邻节点发送的电流采样值,开关状态,远方控制信息;B. Through the high-speed communication network, send the current sampling value, switch status, and remote control information of the node to the adjacent power supply node, and at the same time accept the current sampling value, switch status, and remote control information sent by the adjacent node; C、根据系统设置的保护逻辑结合各节点的实时数据,在故障情况下,依据系统配置的保护逻辑,快速判断故障类型和故障区域;C. According to the protection logic set by the system combined with the real-time data of each node, in the event of a fault, according to the protection logic configured by the system, the fault type and fault area can be quickly judged; D、根据故障区域启动跳闸程序,跳开相应的开关,隔离故障;D. Start the trip program according to the fault area, trip the corresponding switch, and isolate the fault; E、故障隔离后,所在区域节点开关断开后发送远方合闸命令到通信网络,供电环网常开节点收到远合命令后启动合闸程序,合上常开开关,完成负荷转移,恢复非故障区域的供电。E. After the fault is isolated, the node switch in the area is disconnected and sends a remote closing command to the communication network. After receiving the remote closing command, the normally open node of the power supply ring network starts the closing procedure, closes the normally open switch, completes load transfer, and restores Power supply for non-faulty areas. 2.根据权利要求1所述的一种区域供电环网故障快速隔离和负荷转移方法,其特征在于,所述步骤2具体方法:各节点的智能终端通过光缆或双绞线进行手拉手式连接;每个节点只与上下游的相邻节点进行数据交换,传输模拟量数据,开关状态,远方控制信息;数据按照固定时间间隔发送,以全双工方式工作,数据传输进行校验和应答,连续多次校验出错或无应答,启动告警程序。2. A method for rapid fault isolation and load transfer of a regional power supply ring network according to claim 1, characterized in that, the specific method of step 2: the intelligent terminals of each node are connected hand in hand through optical cables or twisted pairs ;Each node only exchanges data with upstream and downstream adjacent nodes, transmitting analog data, switch status, and remote control information; data is sent at fixed time intervals, works in full-duplex mode, and checks and responds to data transmission. If there are multiple consecutive verification errors or no response, start the alarm program. 3.根据权利要求2所述的一种区域供电环网故障快速隔离和负荷转移方法,其特征在于,所述步骤3的具体方法是:各节点依据自身采样值和接收相邻节点的采样值计算故障电流,以差动速断为主保护,过流方向保护为后备保护,判断故障类型和故障区域。3. A method for fast isolation and load transfer of regional power supply ring network faults according to claim 2, characterized in that, the specific method of step 3 is: each node receives the sampled value of the adjacent node according to its own sampled value Calculate the fault current, take the differential quick-break as the main protection, and the over-current direction protection as the backup protection, and judge the fault type and fault area. 4.根据权利要求1所述的一种区域供电环网故障快速隔离和负荷转移方法,其特征在于,所述步骤4的具体方法是:供电环网故障后,对应区域节点的智能终端会启动跳闸程序,驱动断路器跳闸,同时发送对侧跳闸命令,让故障区域另一侧的智能终端启动跳闸程序跳开相应对侧断路器,隔离故障。4. A method for fast isolation and load transfer of regional power supply ring network faults according to claim 1, characterized in that the specific method of step 4 is: after the power supply ring network fails, the intelligent terminal corresponding to the regional node will start The trip program drives the circuit breaker to trip, and at the same time sends the opposite side trip command, so that the smart terminal on the other side of the fault area starts the trip program to trip the corresponding opposite side circuit breaker to isolate the fault. 5.根据权利要求1所述的一种区域供电环网故障快速隔离和负荷转移方法,其特征在于,所述步骤4的具体方法是:故障隔离后,由所在故障区域节点的智能终端检测断路器位置,当开关在分位后向通信网络发送远方合闸命令,通信网络各节点根据供电环网的拓扑结构结合节点中的常开开关位置,启动对应节点开关的合闸程序,合上常开开关,完成负荷的转移,恢复非故障区域的供电。5. A method for rapid fault isolation and load transfer of a regional power supply ring network according to claim 1, characterized in that the specific method of step 4 is: after the fault is isolated, the intelligent terminal of the node in the fault area detects the disconnection When the switch is in position, it sends a remote closing command to the communication network, and each node of the communication network starts the closing procedure of the corresponding node switch according to the topological structure of the power supply ring network and the position of the normally open switch in the node, and closes the normally open switch. Turn on the switch to complete the load transfer and restore the power supply in the non-faulty area. 6.根据权利要求1所述的一种区域供电环网故障快速隔离和负荷转移系统,其特征在于,所述智能终端包含模拟量采集模块和开关量采集模块,出口驱动模块,通信模块和数据处理模块;所述智能终端实时采集本节点进出环网的电流电压模拟量数据,开关的跳合位状态。6. A kind of regional power supply ring network fault quick isolation and load transfer system according to claim 1, is characterized in that, described intelligent terminal comprises analog quantity acquisition module and switch quantity acquisition module, export drive module, communication module and data Processing module: the intelligent terminal collects the current and voltage analog data of the node entering and exiting the ring network in real time, and the switching state of the switch.
CN201710610727.5A 2017-07-25 2017-07-25 Regional power supply looped network fault quick isolation and load transfer method Active CN107611939B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710610727.5A CN107611939B (en) 2017-07-25 2017-07-25 Regional power supply looped network fault quick isolation and load transfer method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710610727.5A CN107611939B (en) 2017-07-25 2017-07-25 Regional power supply looped network fault quick isolation and load transfer method

Publications (2)

Publication Number Publication Date
CN107611939A true CN107611939A (en) 2018-01-19
CN107611939B CN107611939B (en) 2024-02-06

Family

ID=61059493

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710610727.5A Active CN107611939B (en) 2017-07-25 2017-07-25 Regional power supply looped network fault quick isolation and load transfer method

Country Status (1)

Country Link
CN (1) CN107611939B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110687391A (en) * 2019-08-26 2020-01-14 常州轻工职业技术学院 An intelligent judgment system for distribution network faults
CN111884186A (en) * 2020-08-10 2020-11-03 谭世克 Power distribution network node network management method
CN113690876A (en) * 2021-07-28 2021-11-23 国电南瑞科技股份有限公司 Distributed load transfer method and system for regional power grid

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611086A (en) * 2012-03-27 2012-07-25 许继集团有限公司 Centralized protection system and method for region distribution network
CN104113141A (en) * 2014-07-30 2014-10-22 国网电力科学研究院 Intelligent lengthways interconnected feeder line automatic control method
CN204179552U (en) * 2014-06-19 2015-02-25 王永法 Intelligent ring main unit
CN106058831A (en) * 2016-08-05 2016-10-26 江苏方天电力技术有限公司 Intelligent distributed rapid protection and fault isolation method of self-adaptive power distribution network
CN106230121A (en) * 2016-09-21 2016-12-14 湖南大学 A kind of self-adaptive healing guard method being applied to containing hybrid switch power distribution network

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611086A (en) * 2012-03-27 2012-07-25 许继集团有限公司 Centralized protection system and method for region distribution network
US20130262922A1 (en) * 2012-03-27 2013-10-03 State Grid Corporation Of China Centralized and networked protection system and method of a regional distribution network
CN204179552U (en) * 2014-06-19 2015-02-25 王永法 Intelligent ring main unit
CN104113141A (en) * 2014-07-30 2014-10-22 国网电力科学研究院 Intelligent lengthways interconnected feeder line automatic control method
CN106058831A (en) * 2016-08-05 2016-10-26 江苏方天电力技术有限公司 Intelligent distributed rapid protection and fault isolation method of self-adaptive power distribution network
CN106230121A (en) * 2016-09-21 2016-12-14 湖南大学 A kind of self-adaptive healing guard method being applied to containing hybrid switch power distribution network

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110687391A (en) * 2019-08-26 2020-01-14 常州轻工职业技术学院 An intelligent judgment system for distribution network faults
CN111884186A (en) * 2020-08-10 2020-11-03 谭世克 Power distribution network node network management method
CN111884186B (en) * 2020-08-10 2022-05-31 哈尔滨光宇电气自动化有限公司 Power distribution network node network management method
CN113690876A (en) * 2021-07-28 2021-11-23 国电南瑞科技股份有限公司 Distributed load transfer method and system for regional power grid

Also Published As

Publication number Publication date
CN107611939B (en) 2024-02-06

Similar Documents

Publication Publication Date Title
US11355961B2 (en) Method and system for fast reconfiguration of power supply network in tens of milliseconos after power grid failure
CN105281435B (en) Distributed fault detection and shielding system and method for work towards intelligent distribution network
CN106058831B (en) A kind of intelligent distributed quick protection of adaptive power distribution network and failure separation method
CN103354390B (en) Distributed intelligence feeder automation control method
CN109713794B (en) Distributed intelligent self-recovery system and method
CN105375635B (en) Power distribution network cascades switching station's intelligent management and system
CN103022993B (en) Adaptive cascade direction interlocking relaying method based on GOOSE (Generic Object Oriented Substation Event)
CN107069676A (en) Power distribution network fault positioning and rapid isolation recovery control method
CN102611082B (en) Adaptive Neighborhood Interactive Fault-Tolerant Relay Protection Method for Distribution Network Feeder
CN104113141B (en) A kind of intelligence longitudinally interconnects feeder automation control method
CN109149575B (en) A ring network unit and double ring network type distribution network
CN112821560B (en) Distributed self-healing protection method for overhead line distribution network
CN205753377U (en) Ring network closure system based on distribution automation terminal
CN103490392B (en) Fault handling method of power distribution network comprising distributed power supplies and microgrids
CN103606910A (en) Wide area information based fault self-healing method for dead zone of feeder outlet of distribution network
CN104701825B (en) A kind of fast protection method suitable for intelligent distribution network
CN109510192B (en) Power distribution network and self-healing method thereof
CN104485736A (en) Intelligent protection center-based wide-area backup protection system and method
CN116260135A (en) Rapid self-healing method for faults of power distribution network main line
CN204068430U (en) An Intelligent Vertical Interconnection Feeder Automatic Control System
CN113013851B (en) Distributed intelligent power distribution automation system
CN114243658A (en) A feeder automation processing method using 5G network slice communication technology
CN107611939A (en) A kind of block supply ring network fault quickly isolates and load transfer method
CN204497849U (en) A kind ofly take into account measure and control device that is centralized, formula feeder automation on the spot
CN208862570U (en) Ring unit and double-ring distribution network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant