CN107605159A - Secondary structure vertical member concrete construction pours device and construction method - Google Patents

Secondary structure vertical member concrete construction pours device and construction method Download PDF

Info

Publication number
CN107605159A
CN107605159A CN201711012592.9A CN201711012592A CN107605159A CN 107605159 A CN107605159 A CN 107605159A CN 201711012592 A CN201711012592 A CN 201711012592A CN 107605159 A CN107605159 A CN 107605159A
Authority
CN
China
Prior art keywords
vertical
push pedal
concrete
screw
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711012592.9A
Other languages
Chinese (zh)
Inventor
王俊增
龚飞
杨树泉
胡涛
贾令博
于洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG SANJIAN CONSTRUCTION ENGINEERING Co Ltd
SHANDONG SANJIAN CONSTRUCTION ENGINEERING MANAGEMENT Co Ltd
Original Assignee
SHANDONG SANJIAN CONSTRUCTION ENGINEERING Co Ltd
SHANDONG SANJIAN CONSTRUCTION ENGINEERING MANAGEMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG SANJIAN CONSTRUCTION ENGINEERING Co Ltd, SHANDONG SANJIAN CONSTRUCTION ENGINEERING MANAGEMENT Co Ltd filed Critical SHANDONG SANJIAN CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201711012592.9A priority Critical patent/CN107605159A/en
Publication of CN107605159A publication Critical patent/CN107605159A/en
Pending legal-status Critical Current

Links

Abstract

Device is poured the invention discloses a kind of secondary structure vertical member concrete construction.It includes support and push pedal, support includes two vertical supportings being oppositely arranged, two bearing diagonals being fixedly connected on vertical supporting, three connecting screws, it is removably joined together to form rectangular frame by a connecting screw respectively between lower end between the upper end of two vertical supportings, two bearing diagonals are located in rectangular frame, it is removably joined together on the outside of the upper end of two bearing diagonals by the 3rd connecting screw, the push handle of a steel is rotatably coupled on the connecting screw of vertical supporting lower end is connected to, the upper end of push handle is located at the inner side for the connecting screw being connected between two bearing diagonals and is higher than the connecting screw, the push pedal is movably arranged between two bearing diagonals, two vertical supportings, two bearing diagonals, formed between push pedal and dustpan-shaped pour bucket.Using the present invention it is easy for construction, vertical member can one-shot forming, set up operation support body without secondary.

Description

Secondary structure vertical member concrete construction pours device and construction method
Technical field
Device is poured the present invention relates to a kind of secondary structure vertical member concrete construction, belongs to building construction technology Field.The invention further relates to utilize the above-mentioned construction method for pouring device and carrying out secondary structure vertical member concrete construction.
Background technology
At present, the concrete construction of secondary structure vertical member mainly uses two categories below conventional construction method:First, loudspeaker is utilized Mouth pours bucket:(1) when installing vertical member template, by side formwork erection to top, another side template top is reserved " to winnow with a dustpan Dustpan " shape pours mouth, " dustpan " slightly above vertical member top suitable for reading;(2) casting concrete is to top, and is full of " dustpan ", base Originally it can ensure that whole vertical member end is closely knit;(3) form removal, and " dustpan " shape coagulation earthen platform of prominent metope is carried out Pick chisel.2nd, end template is reserved, at twice pouring molding:(1) when installing vertical member template, by side formwork erection extremely 10-15cm spaces are reserved in vertical member top, another side template top apart from vertical member top;(2) " dustpan " shape is utilized to pour It is suitable for reading to template to build mouthful casting concrete;(3) 4-6 hours are spaced, it is dry without stone with same match ratio after concrete initial set Rigid mortar carries out secondary filling, the former reserved charging 10-15cm spaces in vertical member top is full of, vibration compacting simultaneously uses template Blocked.Using the first construction method, it is necessary to which the later stage sets up operation support body again, " dustpan " platform of prominent metope is carried out Pick chisel, and repeat to set up crosshead to know from experience and cause largely to waste, waste substantial amounts of concrete and artificial, and low construction efficiency, And vertical member end face uneven, perception are poor;And second of construction method is used, also need to set up operation support body again, apply Work work efficiency is low, and rear plug mortar forms cold seam with concrete surface, influences overall structure stress.
The content of the invention
For drawbacks described above present in prior art, the invention provides a kind of simple in construction, it can effectively improve and apply Work efficiency rate, operation can be poured and once arrive top, without secondary teeming, can with Reliable guarantee construction quality, ensure vertical member by The secondary structure vertical member concrete construction of power performance pours device.
The present invention is achieved by the following technical solution:A kind of secondary structure vertical member concrete construction is poured Device is built, it is characterized in that:Including support and push pedal, the support is consolidated respectively including two vertical supportings being oppositely arranged, two Surely it is connected on the vertical supporting and to the inclined bearing diagonal in the same side, the screwed connecting screw in three both ends, two Shape is removably joined together by the connecting screw described in one respectively between lower end between the upper end of individual vertical supporting Rectangular framework, and the distance between two vertical supportings are adjustable, two bearing diagonals are located in the rectangular frame, two oblique branch It is removably joined together on the outside of the upper end of support by the connecting screw described in the 3rd, is being connected to vertical supporting lower end The push handle of a steel is rotatably coupled on connecting screw, the upper end of the push handle, which is located at, is connected to two bearing diagonals Between connecting screw inner side and be higher than the connecting screw, the push pedal is movably arranged between two bearing diagonals and is located at institute State the inner side of push handle, two vertical supportings, two the dustpan-shaped bucket that pours, two vertical branch are formed between bearing diagonal, push pedal The mounting hole of at least two installations is respectively arranged with support.
Further, the push pedal is plank sheathing.
Further, for ease of being adjusted and fixing to the distance between two vertical supportings, two are connected at two Four nuts are respectively equipped with connecting screw between individual vertical supporting, two nuts therein are located at the inner side of vertical supporting, Two other nut is located at the outside of vertical supporting.Nut on the inside of vertical supporting is used to position vertical supporting, with limit The distance between fixed two vertical supportings, the fixation that the nut on the outside of vertical supporting is used between connecting screw and vertical supporting.
Further, the vertical supporting is angle steel.
Present invention also offers using the above-mentioned method for pouring device and carrying out secondary structure vertical member concrete construction, It comprises the following steps:
(1) when installing secondary structure vertical member template, by side formwork erection therein to vertical structure to be onstructed The top of part, opposite side formwork erection to template top reserve 15cm spaces apart from the top of vertical member to be onstructed;
(2) installation pours device:Two of device are poured according to the regulation of the horizontal width size of vertical member to be onstructed The distance between vertical supporting is simultaneously fixed, will pour the reserved gap on the template top that device is correspondingly arranged in step 1, And the both ends for the support for pouring device are fixed on both sides and built by laying bricks or stones on the secondary structure metope of completion, according to pouring device The push pedal of space height interception corresponding size is reserved in the distance between on the inside of two vertical supportings and vertical member end, and will push away Plate, which is placed on, forms the dustpan-shaped mouth that pours, the lower end of the push pedal and the template of reserved gap in the support for pouring device Alignment suitable for reading;
(3) casting concrete:By pouring mouth casting concrete into template, vibrated when pouring, when pouring to end, It is to pour 2/3 height of bucket height to control the amount of concrete poured in bucket;
(4) push up the push pedal using push handle, by the push pedal will pour bucket in concrete extrusion enter it is perpendicular Into component ends space, unnecessary concrete is discharged from the side of push pedal, after push pedal is pushed into metope, will pour the support of device Remove, push pedal and bottom form bracing system are fixed together using flitch, rivet, that is, complete construction.
Further, it is pre- on the secondary structure metope for built by laying bricks or stones completion for ease of pouring the installation of device and fixation The split bolt with PVC sleeve pipes is left, the device that pours is fixed on the secondary knot for having built completion by laying bricks or stones by split bolt On structure metope.
Further, it is the compactness that ensures end concrete, ensures construction quality, in step 4, push up push pedal When, push pedal is tapped when pushing away, makes concrete compaction.
The beneficial effects of the invention are as follows:Device is poured in the present invention, its is simple in construction, easy to use, utilizes its progress Secondary structure vertical member concrete construction, it can both ensure that pouring operation once arrives top, again can be reliable without secondary teeming Ensure the compactness of end concrete, it is ensured that vertical member stress performance.Meanwhile of the invention pour device and can dismount circulation Use, lot of materials can be saved, and the present invention can pour the size of bucket according to the width adjustment of vertical member, can Enough it is applied to various sizes of vertical member, there is high adaptivity.The present invention carries out secondary structure using device is poured Vertical member concrete construction, its construction is simple, has the following advantages that:Operation support body can be set up without secondary with one-shot forming, Construction is simple;Without be rejected to the position on protruding member surface, save a large amount of artificial, while avoid and follow-up pick chisel and make Into concrete waste, substantial amounts of concrete can be saved, reduction effect is notable;Speed of application is very fast, and efficiency of construction is high, can be significantly Man-hour is saved, at the same it is simple to operate, and a worker can complete to pour the dismounting operation of device;Can be with Reliable guarantee vertical member The compactness of end concrete, it is ensured that vertical member stress performance, construction quality are high.The present invention's pours device and construction method Current secondary structure vertical member concrete construction is can be widely applied to, alternative traditional construction method, is had very high Practicality and good social and economic benefit.
Brief description of the drawings
Fig. 1 is the structural representation (push pedal not shown in figure) for pouring device in the present invention;
Fig. 2 is the schematic side view for pouring device in the present invention;
Fig. 3 is the connection diagram of the push handle poured in device and connecting screw in the present invention;
Fig. 4 is the schematic diagram of the push pedal in the present invention;
In figure, 1, bearing diagonal, 2, vertical supporting, 3, mounting hole, 4, connecting screw A, 5, nut, 6, connecting screw C, 7, even Meet screw rod B, 8, push handle, 9, nut, 10, push pedal.
Embodiment
Below by non-limiting embodiment and with reference to accompanying drawing, the present invention is further illustrated:
As shown in drawings, a kind of secondary structure vertical member concrete construction pours device, and it includes support and pushed away Plate 10, the support include two screwed connections in the both ends of bearing diagonal 1, three of the vertical supporting being oppositely arranged 2, two Screw rod.Three connecting screws are respectively:Connecting screw A4, connecting screw B7, connecting screw C6.Two vertical supportings 2 use angle Steel makes, and is linked together by connecting screw A4 between the upper end of two vertical supportings 2, the lower ends of two vertical supportings 2 it Between linked together by connecting screw B7, two vertical supportings 2, connecting screw A4, connecting screw B7 formed rectangular frame, and The distance between two vertical supportings 2 are adjustable.Two bearing diagonals 1 are respectively fixedly connected with the vertical supporting 2 and to same Roll oblique, two bearing diagonals 1 be located in the rectangular frame, and the upper end outsides of two bearing diagonals 1 is respectively arranged with nut 5, and two The upper end of individual bearing diagonal 1 is removably joined together by connecting screw C6.It has been rotatably coupled on connecting screw B7 The push handle 8 of one steel, the upper end of the push handle 8 are located at connecting screw C6 inner side and are higher than connecting screw C6.It is described Push pedal 10 is movably arranged between two bearing diagonals 1 and positioned at the inner side of the push handle 8.Two vertical supportings 2, two tiltedly prop up Support 1, formed between push pedal 10 and dustpan-shaped to pour bucket.At least two installations are respectively arranged with two vertical supportings 2 Mounting hole 3.
Push pedal 10 in the present embodiment can use various applicable materials of the prior art to make, it is preferred to use plank sheathing, It is easy to make and is removed after being easy to construction.
For ease of being adjusted and fixing to the distance between two vertical supportings 2, in connecting screw A4 and connecting screw Four nuts 9 are respectively provided with B7, two nuts 9 therein are located at the inner side of vertical supporting 2, and two other nut 9 is positioned at vertical The outside of support 2, wherein, the nut of the inner side of vertical supporting 2 is used to position vertical supporting 2, to limit two vertical branch Support the distance between 2, the nut in the outside of vertical supporting 2 is for the fixation between connecting screw and vertical supporting 2.
Secondary structure vertical member concrete construction is carried out using the above-mentioned device that pours, it comprises the following steps:
(1) when installing secondary structure vertical member template, by side formwork erection therein to vertical structure to be onstructed The top of part, opposite side formwork erection to template top reserve 15cm spaces apart from the top of vertical member to be onstructed;
(2) installation pours device:According to the horizontal width size of vertical member to be onstructed, by adjusting connecting screw A4 With the nut 9 on connecting screw B7, regulation pours the distance between two vertical supportings 2 of device, passes through nut after adjusting It is fixed, the reserved gap on the template top that device is correspondingly arranged in step 1 will be poured, and make to pour pouring for device Upper surface of the bucket higher than the vertical member for intending pouring is built, the both ends for the support for pouring device are fixed on both sides and have built completion by laying bricks or stones Secondary structure metope on, left blank in advance according to the distance between on the inside of the two of apparatus for pouring vertical supportings and vertical member end Gap highly intercepts the plank sheathing of corresponding size as push pedal 10, and push pedal 10 is placed in the support for pour device and forms dustpan Shape pours mouth, and the lower end of the push pedal 10 is alignd with the suitable for reading of the template of reserved gap;
(3) casting concrete:By pouring mouth casting concrete into template, vibrated when pouring, when pouring to end, It is to pour 2/3 height of bucket height to control the amount of concrete poured in bucket;
(4) push pedal 10 is pushed up using push handle 8, the concrete extrusion that will be poured by the push pedal 10 in bucket Enter in vertical member end space, unnecessary concrete is discharged from the side of push pedal 10, after push pedal 10 is pushed into metope, is buttressed on the other hand Push pedal 10, the support removing of device will be poured on the other hand, finally using the flitch intercepted in advance, rivet is by push pedal 10 and bottom template Support system is fixed together, that is, completes construction.It is best to tap push pedal when pushing away when pushing up push pedal 10, so that concrete It is closely knit.The device that pours pulled down is carried out after simply clearing up, both can be recycled.
For ease of being fixed to pouring device, preferably it is reserved with and carries on the secondary structure metope for having built completion by laying bricks or stones The split bolt of PVC sleeve pipes, the device that pours are fixed on by split bolt on the secondary structure metope for having built completion by laying bricks or stones.
Other parts in the present embodiment are prior art, be will not be repeated here.

Claims (7)

1. a kind of secondary structure vertical member concrete construction pours device, it is characterized in that:Including support and push pedal (10), The support include two vertical supportings (2) being oppositely arranged, two be respectively fixedly connected with the vertical supporting (2) and to The inclined bearing diagonal in the same side (1), the screwed connecting screw in three both ends, between the upper end of two vertical supportings (2) It is removably joined together to form rectangular frame by the connecting screw described in one respectively between lower end, and two vertical The distance between support (2) is adjustable, and two bearing diagonals (1) are located in the rectangular frame, on the outside of the upper end of two bearing diagonals (1) It is removably joined together by the connecting screw described in the 3rd, is being connected to the connecting screw of vertical supporting (2) lower end On be rotatably coupled the push handle (8) of a steel, the upper end of the push handle (8) is positioned at being connected to two bearing diagonals (1) inner side of the connecting screw between is simultaneously higher than the connecting screw, the push pedal (10) be movably arranged on two bearing diagonals (1) it Between and positioned at the push handle (8) inner side, formed and winnowed with a dustpan between two vertical supportings (2), two bearing diagonals (1), push pedal (10) The mounting hole (3) for pouring bucket, at least two installations being respectively arranged with two vertical supportings (2) of dustpan shape.
2. secondary structure vertical member concrete construction according to claim 1 pours device, it is characterized in that:It is described Push pedal (10) is plank sheathing.
3. secondary structure vertical member concrete construction according to claim 1 or 2 pours device, it is characterized in that: Four nuts, two nut positions therein are respectively equipped with the connecting screw that two are connected between two vertical supportings (2) In the inner side of vertical supporting (2), two other nut is located at the outside of vertical supporting (2).
4. secondary structure vertical member concrete construction according to claim 1 or 2 pours device, it is characterized in that: The vertical supporting (2) is angle steel.
5. a kind of carry out secondary structure vertical member concrete construction side using any described devices that pour of claim 1-4 Method, it is characterized in that:Comprise the following steps:
(1) when installing secondary structure vertical member template, by side formwork erection therein to vertical member to be onstructed Top, opposite side formwork erection to template top reserve 15cm spaces apart from the top of vertical member to be onstructed;
(2) installation pours device:According to the regulation of the horizontal width size of vertical member to be onstructed pour two of device it is vertical Support the distance between (2) and fix, the reserved gap on the template top that device is correspondingly arranged in step 1 will be poured, and The both ends for the support for pouring device are fixed on into both sides to have built by laying bricks or stones on the secondary structure metope of completion, according to the two of apparatus for pouring The push pedal (10) of space height interception corresponding size is reserved in the distance between individual vertical supporting inner side and vertical member end, and will Push pedal (10) be placed on pour formed in the support of device it is dustpan-shaped pour mouth, the lower end of the push pedal (10) with interspacing in advance The alignment suitable for reading of the template at place;
(3) casting concrete:By pouring mouth casting concrete into template, vibrated when pouring, when pouring to end, control It is to pour 2/3 height of bucket height to pour the amount of concrete in bucket;
(4) push pedal (10) is pushed up using push handle (8), is squeezed the concrete poured in bucket by the push pedal (10) It is pressed into vertical member end space, unnecessary concrete is discharged from the side of push pedal (10), will after push pedal (10) is pushed into metope The support removing of device is poured, push pedal (10) is fixed together with bottom form bracing system using flitch, rivet, that is, completed Construction.
6. secondary structure vertical member concrete construction method according to claim 5, it is characterized in that:Building by laying bricks or stones Into secondary structure metope on be reserved with the split bolt with PVC sleeve pipes, the device that pours is fixed on by split bolt Build by laying bricks or stones on the secondary structure metope of completion.
7. the secondary structure vertical member concrete construction method according to claim 5 or 6, it is characterized in that:In step 4, When pushing up push pedal, push pedal is tapped when pushing away, makes concrete compaction.
CN201711012592.9A 2017-10-26 2017-10-26 Secondary structure vertical member concrete construction pours device and construction method Pending CN107605159A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711012592.9A CN107605159A (en) 2017-10-26 2017-10-26 Secondary structure vertical member concrete construction pours device and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711012592.9A CN107605159A (en) 2017-10-26 2017-10-26 Secondary structure vertical member concrete construction pours device and construction method

Publications (1)

Publication Number Publication Date
CN107605159A true CN107605159A (en) 2018-01-19

Family

ID=61080371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711012592.9A Pending CN107605159A (en) 2017-10-26 2017-10-26 Secondary structure vertical member concrete construction pours device and construction method

Country Status (1)

Country Link
CN (1) CN107605159A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111472567A (en) * 2020-04-14 2020-07-31 中国一冶集团有限公司 Vertical hole plugging mechanism and plugging mechanism construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111472567A (en) * 2020-04-14 2020-07-31 中国一冶集团有限公司 Vertical hole plugging mechanism and plugging mechanism construction method

Similar Documents

Publication Publication Date Title
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN105952154B (en) A kind of concrete-pouring template stent
CN207063522U (en) A kind of frame column high-supported formwork
CN104631232A (en) Integrated pouring device for installation of rail column type inspection pit fastening system
CN109024987A (en) Construction method is poured after a kind of toilet shear wall
CN207063515U (en) A kind of scalable aluminium frame template
CN206616862U (en) Formwork root bracing means
CN107605159A (en) Secondary structure vertical member concrete construction pours device and construction method
CN208267362U (en) A kind of constructing device of deformation joint concrete wall formwork
CN207484981U (en) Secondary structure vertical member concrete construction pours device
CN209163138U (en) A kind of reservation device of the floor reserved steel bar for climbing formwork for construction
CN204551173U (en) Pull bar locating support
CN105696796A (en) Cantilever scaffold steel girder anchoring method
CN207260593U (en) Floor concrete casting operation platform is built in a kind of room
CN202744907U (en) Concrete leveling, paste lifting and elevation control integrated device for bed plates
CN206448272U (en) Roadbed side slope arched framework one-time-shaped mould
CN207296408U (en) Portable concrete constructional column irrigation device
CN205314542U (en) Construction liquid die plate device that climbs
CN202097815U (en) Horizontal signal foundation prefabrication mold
CN201915635U (en) Form erecting device free of bar planting for brickwork construction
CN201610510U (en) Stepless fine-tuning template of plate-type ballastless track base concrete
CN108457190A (en) Anchor ceiling board construction method before anchorage
CN206050367U (en) A kind of job site raw material of reinforcement rebar piles up skeleton
CN210658959U (en) Constructional column concrete placement construction structures of smashing
CN208702139U (en) A kind of construction template structure of toilet wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination