CN107558729A - The rear pouring tape construction method that girder is built by the big area roof of post-cast strip - Google Patents

The rear pouring tape construction method that girder is built by the big area roof of post-cast strip Download PDF

Info

Publication number
CN107558729A
CN107558729A CN201710812277.8A CN201710812277A CN107558729A CN 107558729 A CN107558729 A CN 107558729A CN 201710812277 A CN201710812277 A CN 201710812277A CN 107558729 A CN107558729 A CN 107558729A
Authority
CN
China
Prior art keywords
post
girder
cast strip
suspension ring
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710812277.8A
Other languages
Chinese (zh)
Other versions
CN107558729B (en
Inventor
梁锋
裘珍妮
唐文周
刘书
孙炎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Group Co Ltd filed Critical Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority to CN201710812277.8A priority Critical patent/CN107558729B/en
Publication of CN107558729A publication Critical patent/CN107558729A/en
Application granted granted Critical
Publication of CN107558729B publication Critical patent/CN107558729B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses the rear pouring tape construction method that girder is built by the big area roof of post-cast strip, step are as follows:It is located at the pre-buried suspension ring in position of post-cast strip (5) in girder (3);Casting concrete, it is located in the girder (3) on the position of the post-cast strip and exposes the pre-buried suspension ring;The both sides for pouring band (5) in the rear set temporary support (1);Interim section steel beam (2) is set up on two temporary supports (1);It is fixed in the interim setting cable wire (4) between section steel beam (2) and the pre-buried suspension ring when girder (3) intensity of the post-cast strip (5) both sides reaches design requirement.The present invention can be achieved to wait and (be provided in this section of cycle of post-cast strip cast according to specification, it is general to be no less than 28 days), the lower section construction space of girder 3 can not be influenceed by the scaffold originally set up, can deploy more to process simultaneously, efficiency of construction is improved, reduces construction cost.

Description

The rear pouring tape construction method that girder is built by the big area roof of post-cast strip
Technical field
The present invention relates to house building technology field, and more particularly to girder is after the big area roof building of post-cast strip Pour belt construction method.
Background technology
It is to prevent monolithic reinforced concrete structure because autogenous shrinkage is uneven or settles not in construction that post-cast strip, which is, Issuable harmful cracks, according to design or job specfication requirement, stay what is set to face in sole plate, wall, beam relevant position When construction joint.
In the prior art, post empiricism mode is that post-cast strip both sides concrete is supported from the bottom to top, is treated Post empiricism completion and concrete reach the support system of the dismountable bottom in design strength rear.
This lower space for resulting in building can not utilize during post empiricism, cause construction costs height, construction The problems such as cycle is long.
Therefore, it is necessary to be improved to existing rear pouring tape construction method, the defects of overcoming prior art, can ensure In the case of post empiricism quality, efficiency of construction is improved, reduces construction cost.
The content of the invention
In view of the drawbacks described above of prior art, the present invention provides girder after the big area roof building of post-cast strip Belt construction method is poured, the first purpose of realization is the defects of overcoming prior art, can ensure the feelings of post empiricism quality Under condition, efficiency of construction is improved, reduces construction cost.
To achieve the above object, the invention discloses the post empiricism that girder is built by the big area roof of post-cast strip Method, step are as follows:
A. it is located at the pre-buried suspension ring in position of post-cast strip in girder;
B. casting concrete, it is located in the girder on the position of the post-cast strip and exposes the pre-buried suspension ring;
C. the both sides for pouring band in the rear set temporary support;
D. interim section steel beam is set up in two temporary supports;
E. when the girder intensity of the post-cast strip both sides reaches design requirement, the interim section steel beam with it is described Cable wire is set to fix between pre-buried suspension ring.
Preferably, the temporary support height 500mm to 1500mm.
Preferably, the interim section steel beam is I-steel or H profile steel.
Beneficial effects of the present invention:
1st, other multiple working procedures of synchronization implementation in the post empiricism cycle are realized.
2nd, can it is greatly cost-effective and shorten construction period, realize good social value and economic value.
Design, concrete structure and the caused technique effect of the present invention are described further below with reference to accompanying drawing, with It is fully understood from the purpose of the present invention, feature and effect.
Brief description of the drawings
Fig. 1 shows the structural representation of the Construction State of one embodiment of the invention.
Embodiment
Embodiment
As shown in figure 1, the rear pouring tape construction method that girder is built by the big area roof of post-cast strip, step are as follows:
A. it is located at the pre-buried suspension ring in position of post-cast strip 5 in girder 3;
B. casting concrete, it is located in girder 3 on the position of post-cast strip and exposes pre-buried suspension ring;
C. temporary support 1 is set in the both sides of post-cast strip 5;
D. interim section steel beam 2 is set up in two temporary supports 1;
E. when the intensity of girder 3 of the both sides of post-cast strip 5 reaches design requirement, between interim section steel beam 2 and pre-buried suspension ring Cable wire 4 is set to fix.
Nationality of the present invention is poured by the mode in concrete girder 3 by the pre-buried suspension ring of position setting of post-cast strip 5 after dismounting Before the lower support system of band 5, by being embedded in the suspension ring and cable wire of girder 3, the load of girder 3 is transferred on section steel beam 2, The support system that the lower section of girder 3 is set up can be removed.
The present invention can be achieved to wait in this section of cycle of post-cast strip cast and (being provided according to specification, general to be no less than 28 days), The lower section construction space of girder 3 can not be influenceed by the scaffold originally set up, can deploy more to process simultaneously, improve efficiency of construction, Reduce construction cost.
In certain embodiments, the height 500mm to 1500mm of temporary support 1.
In certain embodiments, interim section steel beam 2 is I-steel or H profile steel.
Preferred embodiment of the invention described in detail above.It should be appreciated that one of ordinary skill in the art without Creative work can is needed to make many modifications and variations according to the design of the present invention.Therefore, all technologies in the art Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Technical scheme, all should be in the protection domain being defined in the patent claims.

Claims (3)

1. the rear pouring tape construction method that girder is built by the big area roof of post-cast strip, step are as follows:
A. it is located at the pre-buried suspension ring in position of post-cast strip (5) in girder (3);
B. casting concrete, it is located in the girder (3) on the position of the post-cast strip and exposes the pre-buried suspension ring;
C. the both sides for pouring band (5) in the rear set temporary support (1);
D. interim section steel beam (2) is set up on two temporary supports (1);
E. when the girder (3) intensity of the post-cast strip (5) both sides reaches design requirement, in the interim section steel beam (2) Set cable wire (4) fixed between the pre-buried suspension ring.
2. the rear pouring tape construction method that girder according to claim 1 is built by the big area roof of post-cast strip, it is special Sign is:Temporary support (1) the height 500mm to 1500mm.
3. the rear pouring tape construction method that girder according to claim 1 is built by the big area roof of post-cast strip, it is special Sign is:The interim section steel beam (2) is I-steel or H profile steel.
CN201710812277.8A 2017-09-11 2017-09-11 The rear pouring tape construction method that girder is built by the big area roof of post-cast strip Active CN107558729B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710812277.8A CN107558729B (en) 2017-09-11 2017-09-11 The rear pouring tape construction method that girder is built by the big area roof of post-cast strip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710812277.8A CN107558729B (en) 2017-09-11 2017-09-11 The rear pouring tape construction method that girder is built by the big area roof of post-cast strip

Publications (2)

Publication Number Publication Date
CN107558729A true CN107558729A (en) 2018-01-09
CN107558729B CN107558729B (en) 2019-07-23

Family

ID=60979929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710812277.8A Active CN107558729B (en) 2017-09-11 2017-09-11 The rear pouring tape construction method that girder is built by the big area roof of post-cast strip

Country Status (1)

Country Link
CN (1) CN107558729B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070092460A (en) * 2006-03-10 2007-09-13 주식회사 퍼스폼 System form and construction method using the same
CN101575911A (en) * 2009-05-27 2009-11-11 上海市第一建筑有限公司 Top-down decreasing-formwork formwork system and construction method
CN103225395A (en) * 2013-04-17 2013-07-31 中国十七冶集团有限公司 Floor post-cast strip template structure and use method
CN103758347A (en) * 2014-01-20 2014-04-30 常州第一建筑集团有限公司 Support underpinning method of large-span reinforced concrete beam-slab structure post-cast strips
CN204163115U (en) * 2014-10-17 2015-02-18 江西中联建设集团有限公司 Template construction device is hung in a kind of ater-casting
CN204899204U (en) * 2015-07-28 2015-12-23 上海建工二建集团有限公司 Mouthful structure concrete structure's of department a template system fetches earth among reverse construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070092460A (en) * 2006-03-10 2007-09-13 주식회사 퍼스폼 System form and construction method using the same
CN101575911A (en) * 2009-05-27 2009-11-11 上海市第一建筑有限公司 Top-down decreasing-formwork formwork system and construction method
CN103225395A (en) * 2013-04-17 2013-07-31 中国十七冶集团有限公司 Floor post-cast strip template structure and use method
CN103758347A (en) * 2014-01-20 2014-04-30 常州第一建筑集团有限公司 Support underpinning method of large-span reinforced concrete beam-slab structure post-cast strips
CN204163115U (en) * 2014-10-17 2015-02-18 江西中联建设集团有限公司 Template construction device is hung in a kind of ater-casting
CN204899204U (en) * 2015-07-28 2015-12-23 上海建工二建集团有限公司 Mouthful structure concrete structure's of department a template system fetches earth among reverse construction method

Also Published As

Publication number Publication date
CN107558729B (en) 2019-07-23

Similar Documents

Publication Publication Date Title
CN108019076B (en) Construction method of large-diameter reinforced concrete silo and device for conical shell construction
JP5047680B2 (en) Construction method of continuous viaduct
CN107313589A (en) Outer wall of basement one side steel form support system and its construction method
CN104109999A (en) Construction method for bridge tower transverse beams
CN108589535B (en) Reinforced concrete box type arch bridge construction method
CN111535579A (en) Construction method for support-free mold hanging tool for horizontal post-pouring belt
CN102192368A (en) Large-span overhead pipeline sliding installation method
CN108755984A (en) Late poured band support construction method based on concrete square column
CN106193588B (en) A kind of method pouring building post-cast strip and pour mould
CN107044090A (en) A kind of construction method of dual deck bridge
CN105464216B (en) Construction method based on integral lifting formwork-strengthening system superelevation super-section batter post
CN104099871A (en) Arching structure of high large-span bridge bailey beams and construction method thereof
CN108360380A (en) A kind of bridge pier column construction operation platform and its construction method
CN106049289B (en) Bailey beam make-shift bridge transform the construction method of steel reinforced concrete combination permanent bridge as
CN105401679A (en) Large-gradient cast-in-place concrete inclined roof construction method
CN107269085B (en) A kind of construction method of large-diameter concrete silo top conical shell structure
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN106320373A (en) Supporting system at position of post-pouring belt of underground garage roof and construction method
CN103061568B (en) Tapered hanging bracket high-position in-situ casting construction method of water tank of reverse taper shell heat-preservation water tower
CN107558729A (en) The rear pouring tape construction method that girder is built by the big area roof of post-cast strip
CN109184193A (en) A kind of early-dismantling formwork system and its construction method
CN105442453A (en) Construction method for suspension bridge tower crossbeam combination support
CN205976472U (en) Pour mould of building post -cast strip
CN105625202B (en) The construction method of the cast-in-place box culvert of the porous overlength of big cross section
CN104847090B (en) A kind of small cross-sectional size ventilation shaft construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant