CN107558567A - A kind of separate sewage system and control method of sewage and rainwater - Google Patents

A kind of separate sewage system and control method of sewage and rainwater Download PDF

Info

Publication number
CN107558567A
CN107558567A CN201710916624.1A CN201710916624A CN107558567A CN 107558567 A CN107558567 A CN 107558567A CN 201710916624 A CN201710916624 A CN 201710916624A CN 107558567 A CN107558567 A CN 107558567A
Authority
CN
China
Prior art keywords
water
shunting
sewer
sewage
shunting well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710916624.1A
Other languages
Chinese (zh)
Inventor
周超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Shengyu Drainage Systems Co Ltd
Original Assignee
Wuhan Shengyu Drainage Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Shengyu Drainage Systems Co Ltd filed Critical Wuhan Shengyu Drainage Systems Co Ltd
Priority to CN201710916624.1A priority Critical patent/CN107558567A/en
Publication of CN107558567A publication Critical patent/CN107558567A/en
Withdrawn legal-status Critical Current

Links

Abstract

The present invention provides a kind of separate sewage system of sewage and rainwater, including the trunk sewer on town road, the outlet of trunk sewer are provided with sewage treatment plant;Storm-water sewer on town road, the end of Storm-water sewer are connected with natural water;Storm sewer and sewage conduct in unit area, sewage conduct are connected with trunk sewer;The outlet of storm sewer sets rain processing system, and rain processing system includes shunting device and online treatment facility;The water inlet of storm sewer and shunting device is connected, and the first delivery port of shunting device is connected with trunk sewer, and the second delivery port is connected with online treatment facility, and the 3rd delivery port is connected with Storm-water sewer.The system architecture of the present invention is simple, it is convenient to build, and it is that the efficient process to the combined sewage in cell area can be achieved that shunting device and online treatment facility need to be only built in the limited region of cell.

Description

A kind of separate sewage system and control method of sewage and rainwater
Technical field
The present invention relates to a kind of combined flow system pipe network system, and in particular to a kind of combined flow system system of sewage and rainwater System and control method.
Background technology
Municipal drainage system is broadly divided into combined drainage system and separate sewage system.The interflow occurred earliest Drainage system processed is that sewage, industrial wastewater and rainwater are blended in same pipe duct, is just directly arranged nearby without any processing Enter water body, be stained significantly receiving water body, lot of domestic and international mature city is nearly all in this way.Now frequently with It is interceptive combined system drainage system.
Interceptive combined system drainage system and traditional combined drainage system are essentially identical in structure, and distinctive points are Interceptive combined system drainage system is provided with Vatch basin between municipal administration interflow main and sewage treatment plant.Interceptive combined system is arranged When water system works, the rainwater that the sewage and inlet for stom water of resident's discharge are collected all enters municipal administration interflow main by collaborating house steward, The rainwater that inlet for stom water along town road is collected also all enters municipal administration interflow main, and Vatch basin is set in main end.Fine day When, all sewage are all delivered to sewage plant, and natural water is discharged into after processing.During rainfall, the rainwater at sewage and rainfall initial stage Also sewage plant can be transported to, natural water is discharged into after processing.But with the increase of rainfall, rainfall runoff also increases, After the flow of combined sewage exceedes the conveyance power of water for the main that dams, just have part combined sewage overflow and be directly entered nature Water body.
For this combined drainage system, its problem is mainly:1. during rainfall, it can be produced on residential area and town road Pollution of area source, although existing combined drainage system is dammed in end provided with Vatch basin, the interception ratio of design Not enough so that Vatch basin could not intercept to area source pollutants, and area source pollutants are directly entered natural water, to natural water Pollute.2. to be controlled to pollution of area source, it is necessary to increase the size of Vatch basin, increase the size for the main that dams, Increase the capacity of sewage plant.3. Vatch basin dams for the control of extensive style, it is impossible to accurately early-stage rainwater is dammed.
Separate sewage system is divided into complete separate system and incomplete separate system two again according to the difference for excluding rainwater mode Kind drainage system.Complete separate sewage system is completely to separate rainwater and sanitary sewage, trade effluent, by different pipelines Conveyed.The sewage of resident's discharge enters trunk sewer by sewage conduct, is discharged after being then sent to sewage plant processing, rain The rainwater that the mouth of a river is collected enters Storm-water sewer by storm sewer, is directly discharged to natural water.Rainwater along town road The rainwater that mouth is collected also all enters Storm-water sewer, is directly discharged to natural water.In this separate sewage system, there is Many problems:1. the part of contaminated water in residential area mistakenly enters the sewage that washing machine is discharged on storm sewer, such as balcony Natural water can be directly discharged to.2. the part of contaminated water on town road mistakenly enters storm sewer, such as road cleaning Caused sewage can be directly discharged to natural water.3. during rainfall, pollution of area source, face can be produced on residential area and town road Source pollutants can be directly entered natural water.
Incomplete separate system is primarily directed on the rainwater and town road that in the collection processing of rainwater, residential block is collected The rainwater being collected into is separated.The rainwater that the sewage and inlet for stom water of resident's discharge are collected all is discharged by collaborating house steward, is being entered Vatch basin is set to be dammed before entering municipal drainage pipeline.The rainwater that inlet for stom water along town road is collected is done into rainwater Pipe, is directly discharged to natural water.During fine day, the sewage of residential area discharge is trapped to trunk sewer, is then sent to sewage Factory, natural water is discharged into after processing, but part of contaminated water is had on town road and is directly discharged to certainly into Storm-water sewer Right water body.During rainfall, the sewage and the rainwater at rainfall initial stage of residential area discharge can be also trapped to trunk sewer, be then sent to Sewage plant, natural water is discharged into after processing, but as the increase of rainfall, rainfall runoff also increase, when combined sewage After flow exceedes the conveyance power of water for the pipeline that dams, just have part combined sewage overflow and be directly entered Storm-water sewer, while city The early-stage rainwater of a large amount of pollutants is carried on political affairs road can also be directly entered Storm-water sewer, be then discharged to natural water.This The problem of kind of drainage system is mainly:1. whole system can not effectively be intercepted to area source pollutants, intercepting efficiency is low.② The sewage for entering storm sewer can not be controlled.3. during rainfall, sewage is easily carried along into natural water by rainwater.4. dam The control of well is extensive, on the one hand more early-stage rainwaters may not be sent into sewage plant processing so that area source pollutants discharge Natural water has been arrived, on the other hand substantial amounts of later stage rainwater sewage plant may be sent into, add the load of sewage plant, reduce The treatment effeciency of sewage plant.
All things considered, there is problems with for current run-off system:First, it is impossible to which pollution of area source is controlled;The Two, control is extensive, it is impossible to which sewage and early-stage rainwater are accurately controlled;3rd, pipeline hybrid junction, sewage has been directly discharged to certainly Right water body;4th, for the area that land used is nervous, end treatment can not effectively be implemented.
Meanwhile the present inventors have additionally discovered that, first rain dirt design of pipe networks it is not perfect enough, a large amount of original storm sewers and The rainwater that Storm-water sewer is not collected to it is discharged into sanitary sewage therein with misconnection hybrid junction and separated, and makes sewage and rainwater straight Run in and be put into the natural water of distal end, cause water pollution serious.
The content of the invention
The defects of in order to overcome prior art, the present invention provides a kind of separate sewage system of sewage and rainwater, described System includes:
Trunk sewer on town road, the outlet of the trunk sewer are provided with sewage treatment plant;
Storm-water sewer on town road, the end of the Storm-water sewer are connected with natural water;
Storm sewer and sewage conduct in unit area, the sewage conduct are connected with the trunk sewer;
Wherein, the outlet of the storm sewer sets rain processing system, and the rain processing system includes shunting device With online treatment facility;The shunting device have four opening, be respectively water inlet, the first delivery port, the second delivery port and 3rd delivery port;
The water inlet connection of the storm sewer and shunting device, the first delivery port and the trunk sewer of shunting device connect Connect, the second delivery port of shunting device is connected with the water inlet of online treatment facility, the delivery port and rainwater of online treatment facility Main is connected, and the 3rd delivery port of shunting device is connected with Storm-water sewer.
According to the present invention, the unit area is to include building and structure in urban area with function and usage Attribute transposition Build the soil region of thing.
According to the present invention, the area of the unit area is 0.01-0.6 square kilometres, preferably 0.01-0.3 squares of public affairs In.
According to the present invention, the Storm-water sewer is original Storm-water sewer on town road;Or when on the town road When not having Storm-water sewer, a Storm-water sewer is laid on town road.
According to the present invention, the shunting device is selected from shunting well, abandoned stream well or Vatch basin.
According to the present invention, water conservancy is set to switch on the delivery port of shunting device.Preferably, it is all provided with each delivery port Put water conservancy switch.Set water conservancy to switch 1 in the first delivery port of shunting device, water conservancy is set in the second delivery port of shunting device Switch 2, water conservancy is set to switch 3 in the 3rd delivery port of shunting device.
According to the present invention, the system also includes control system, and the control system includes being used to monitor shunting device First monitoring device and the control unit being connected with the first monitoring device signal;Described control unit and water conservancy switch 1, water Profit switch 2 switchs 3 signals with water conservancy and connected;First monitoring device is used for monitoring signals and the signal of monitoring is conveyed into control Unit processed, control unit control the aperture of water conservancy switch 1, water conservancy switch 2 and water conservancy switch 3 according to the signal of reception.
Preferably, the device that first monitoring device includes monitoring water body liquid level (such as can be liquid level sensor, liquid Position meter, liquid-level switch etc.), the device for monitoring water quality (such as can be Water quality detector, online COD monitors, online TSS monitors, online BOD monitors, online TN monitors, online TP monitors, online NH3-N monitors, online ammonia nitrogen prison Survey instrument, electrode, conductivity meter etc.), the device for monitoring water body total amount (such as can be the electronic headstock gear with function of measuring Deng), the device (such as rainfall gauge) of rainfall is monitored, monitors at least one of device (such as timer) of time.
Preferably, first monitoring device may be provided in shunting device well body or shunting device well according to type demand In vitro.For example, the device of monitoring water body liquid level and the device of monitoring water quality are arranged in shunting device well body, rainfall is monitored Device be arranged on outside shunting device well body, monitoring water body total amount device be arranged in shunting device well body water conservancy switch On, the device for monitoring the time is arranged in shunting device well body or outside well body.
Preferably, the shunting device can be slot type, weir Shi Huocao weirs formula shunting device.
According to the present invention, the water conservancy switch 1, water conservancy switch 2 and water conservancy switch 3 are identical or different;Select independently of one another From valve, gate, flap valve or weir gate;Preferably upper open type gate, bottom-open type gate, bottom-open type weir gate, rotation weir gate, floating drum Cut-off equipment, gate valve, butterfly valve, ball valve, lift rubber clack dam check-valves or the flap valve that dams.
According to the present invention, the online treatment facility is selected from online processing pond, inclined-plate clarifying basin, tube settler, flocculation Pond, efficient settling pit, artificial swamp, pass through any of pond and integrated equipment for wastewater treatment or two or more combinations.
According to the present invention, the shunting device can be one or more.
According to the present invention, the system also includes rainwater pretreatment system;It can be incorporated on the Storm-water sewer, or By the Storm-water sewer.
According to the present invention, the rainwater pretreatment system includes shunting well, rain water filtering device, particle separator, cylinder mistake One in filter, rainwater separator, hydrocyclone, osmotic cell, magnetic separating device, medium filter, online processing pond Kind is a variety of.
Preferably, the rainwater pretreatment system also includes regulate and store facility and/or cut-off equipment and/or flow control dress Put.
According to the present invention, the rainwater pretreatment system includes shunting well, cut-off equipment, volume control device, rainwater mistake Filter, facility of regulating and storing, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is slot type When, it is not provided with cut-off equipment;
For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;
The water inlet of the shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, described First delivery port of shunting well connects with the Storm-water sewer on the town road on rear side of the shunting well, the cut-off equipment It is arranged on the first water outlet of the shunting well;Second water outlet of the shunting well sets volume control device, described The other end of volume control device is sequentially connected with rain water filtering device, facility of regulating and storing, the delivery port and sewage of the facility of regulating and storing Pipeline communication.
According to the present invention, the rainwater pretreatment system includes shunting well, cut-off equipment, particle separator, cylinder filtering Device, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is slot type, are not provided with damming Device;
For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;
The water inlet of the shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, described First delivery port of shunting well connects with the Storm-water sewer on the town road on rear side of the shunting well, the cut-off equipment It is arranged on the first water outlet of the shunting well;Second delivery port of the shunting well and particle separator, cylinder filter It is sequentially connected, the delivery port of the cylinder filter connects with the Storm-water sewer on the town road on rear side of the shunting well It is logical.
According to the present invention, the rainwater pretreatment system includes shunting well, cut-off equipment, hydrocyclone, infiltration Pond and volume control device, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is groove During formula, cut-off equipment is not provided with;
For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;
The water inlet of the shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, described First delivery port of shunting well connects with the Storm-water sewer on the town road on rear side of the shunting well, the cut-off equipment It is arranged on the first water outlet of the shunting well;Second water outlet of the shunting well sets volume control device, described The other end of volume control device is sequentially connected with hydrocyclone, osmotic cell, the water penetration in the osmotic cell To underground.
According to the present invention, the rainwater pretreatment system includes shunting well, cut-off equipment, magnetic separating device, osmotic cell, Jie Mass filter, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is slot type, are not set Put cut-off equipment;
For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;
The water inlet of the shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, described First delivery port of shunting well connects with the Storm-water sewer on the town road on rear side of the shunting well, the cut-off equipment It is arranged on the first water outlet of the shunting well;Second delivery port of the shunting well and magnetic separating device, osmotic cell, medium Filter is sequentially connected, and the delivery port of the medium filter is done with the rainwater on the town road on rear side of the shunting well Pipe connects.
According to the present invention, the rainwater pretreatment system includes the first shunting well, the second shunting well, cut-off equipment, online Processing pond and volume control device, first shunting well are arranged on the Storm-water sewer on the town road, when described When one shunting well is slot type, cut-off equipment is not provided with;
For on front side of shunting well, first the first delivery port of shunting well opening position is shunting well at first shunting well water inlet position Rear side;
The water inlet of first shunting well and the Storm-water sewer on the town road on front side of first shunting well Connection, the first delivery port of first shunting well and the Storm-water sewer on the town road on rear side of first shunting well Connection, the cut-off equipment are arranged on the first water outlet of first shunting well;Second water outlet of first shunting well Mouth is connected with the water inlet of second shunting well, and the first delivery port of second shunting well and one end of sewage conduct connect Connect, the other end of sewage conduct is connected with sewage treatment plant;Second delivery port of second shunting well and online processing pond Water inlet connects, and the delivery port of online processing pond connects with the Storm-water sewer on the town road on rear side of first shunting well It is logical;
The volume control device is arranged on the second water outlet of the first shunting well or is separately positioned on the second shunting well The first water outlet and the second shunting well the second water outlet.
According to the present invention, the cut-off equipment is fixed weir;Or water conservancy switch.
One or more rainwater pretreatment systems, or multiple rainwater can be set according to the present invention, on the Storm-water sewer The combination of pretreatment system.
According to the present invention, when the group that multiple rainwater pretreatment systems or multiple rainwater pretreatment systems are set on Storm-water sewer During conjunction, the distance between combination of adjacent two rainwater pretreatment systems or two rainwater pretreatment systems is 0.2-1 kilometers.
According to the present invention, the outlet pipe of the sewage treatment plant is connected with natural water.
According to the present invention, the system also includes biofilter, and it can be arranged on the outlet pipe of sewage treatment plant.
According to the present invention, the biofilter can be one or more.
The present invention also provides a kind of control method of the separate sewage system of above-mentioned sewage and rainwater, methods described bag Include:
During fine day, the sewage of sewage conduct flows into sewage treatment plant by trunk sewer and handled;Shunting device is by rain The sanitary sewage of waterpipe misconnection hybrid junction branches to trunk sewer and handled into sewage treatment plant;
During initial rainfall, the sewage of sewage conduct flows into sewage treatment plant by trunk sewer and handled;Shunting device The sanitary sewage of storm sewer misconnection hybrid junction is branched to entering the combined sewage that the rainwater of the storm sewer in cell is formed Trunk sewer is handled into sewage treatment plant;
During middle and later periods rainfall, when water exceedes towards the maximum inflow-rate of water turbine for cutting dirty pipe of sewage treatment plant, shunting device Combined sewage is branched in online treatment facility, the combined sewage after being handled through online treatment facility is directly discharged to rain again Water conduit tube;
During flood discharge, when water exceedes the maximum processing capability of online treatment facility, shunting device is directly by combined sewage Branch to Storm-water sewer.
Preferably, method of the invention also includes:
During fine day, water conservancy switch 1 is opened, and water conservancy switch 2, water conservancy switch 3 are closed, and the sewage of sewage conduct is done by sewage Pipe flows into sewage treatment plant and handled;The sanitary sewage of storm sewer misconnection hybrid junction enters by water conservancy switch 1 and trunk sewer Enter sewage treatment plant's processing;
During initial rainfall, water conservancy switch 1 is opened, and water conservancy switch 2, water conservancy switch 3 are closed, and the sewage of sewage conduct passes through dirt Water conduit tube flows into sewage treatment plant and handled;The sanitary sewage of storm sewer misconnection hybrid junction is with entering the storm sewer in cell Rainwater formed combined sewage by water conservancy switch 1 and trunk sewer enter sewage treatment plant processing;
During middle and later periods rainfall, when water exceedes towards the maximum inflow-rate of water turbine for cutting dirty pipe of sewage treatment plant, water conservancy is opened Switch 2, combined sewage enter in online treatment facility, and the combined sewage after being handled through online treatment facility is directly discharged to again Storm-water sewer;
During flood discharge, when water exceedes the maximum processing capability of online treatment facility, water conservancy switch 3, combined sewage are opened Flow into Storm-water sewer.
Beneficial effects of the present invention
(1) system architecture of the invention is simple, it is convenient to build, need to only be built in the limited region of cell shunting device with Online treatment facility is that the efficient process to the combined sewage in cell area can be achieved.
(2) for the present invention by the way that shunting device and online treatment facility are arranged in cell area, floor space is small, can set Underground is placed in, is effectively prevented from the reconstruction significantly to cell area interior conduit, solves the problems, such as cell land used anxiety.
(3) the shunting processing in source of the present invention, excessively stream time of the first rain from ground to shunting device greatly shortens, so as to subtract Few this source region probability that for example cell later stage rainwater mixes with early-stage rainwater, retention or the early-stage rainwater concentration collected will be more Height, it is very high to cut dirty efficiency.
(4) when end cuts dirty, the deposition of duct bottom can influence the characteristic of first rain, the unobvious for allowing the characteristic of first rain to become, But source wastewater interception pipe is shorter, the influence of deposition can be ignored substantially, and first rain feature becomes apparent from.
(5) when end cuts dirty, pipeline distance is longer, and the breakage of pipeline can cause pipeline Groundwater infiltration on the way, can dilute The concentration of first rain, just rain a certain amount of to the interception of first rain will contain a certain proportion of secondary water;But dirt is cut in source, due to pipe Road is shorter, can be ignored substantially the problem of pipe network, the first rain concentration of interception will also greatly improve.
Brief description of the drawings
Fig. 1 is the separate sewage system of the community wastewater of the embodiment of the present invention 1 and rainwater;
Each reference implication is as follows:A-cell, A-1-sewage conduct, A-2-storm sewer, B-1-trunk sewer, B-2-Storm-water sewer, 1-natural water, 2-sewage treatment plant, 3-shunting well, 4-bottom-open type weir gate, 5-bottom-open type lock Door, 6-biofilter, 7-waterpower particle separator, 8-cylinder filter, 9-rotation weir gate, 10-online processing pond.
Embodiment
Further detailed description is done to present system below in conjunction with specific embodiment.It should be appreciated that following reality Apply example and be merely illustrative the ground description and interpretation present invention, and be not necessarily to be construed as limiting the scope of the invention.It is all to be based on In the range of the technology that the above of the present invention is realized is encompassed by it is contemplated that protecting.
Embodiment 1
Community wastewater as shown in Figure 1 and the separate sewage system of rainwater, the system include:Dirt on town road Water conduit tube B-1, the trunk sewer B-1 outlet are provided with sewage treatment plant 2, and the outlet pipe of the sewage treatment plant 2 passes through Biofilter 6 is connected with natural water 1;
Storm-water sewer B-2 on town road, the end of the Storm-water sewer B-2 is connected with natural water 1;
Sewage conduct A-1 in cell A is connected with trunk sewer B-1;
Storm sewer A-2 in cell A is connected with the water inlet of shunting well 3, and the first delivery port and the sewage of shunting well 3 are done Pipe connects, and the second delivery port of shunting well 3 is connected with the water inlet of online processing pond 10, the delivery port and rain of online processing pond 10 Water conduit tube B-2 is connected, and the 3rd delivery port of shunting well 3 is connected with Storm-water sewer B-2, also, in the first delivery port of shunting well 3 Bottom-open type weir gate 4 is set, bottom-open type gate 5 is set in the second delivery port of shunting well 3, set in the 3rd delivery port of shunting well 3 Put rotation weir gate 9.
Wherein, the system also includes control system, and the control system includes being used for the level sensing for monitoring shunting well 3 Device and the control unit being connected with the liquid level sensor signal;Described control unit and bottom-open type weir gate 4, bottom-open type gate 5 Connected with the rotation signal of weir gate 9;The liquid level sensor is used for monitoring signals and the signal of monitoring is conveyed into control unit, controls Unit processed controls bottom-open type weir gate 4, bottom-open type gate 5 and the aperture for rotating weir gate 9 according to the signal of reception.
Wherein, the liquid level sensor may be provided in the well body of shunting well 3.
Wherein, multiple rainwater pretreatment systems are set on the Storm-water sewer B-2, and the rainwater pretreatment system includes Shunting well, cut-off equipment, particle separator, cylinder filter, the rainwater that the shunting well is arranged on the town road are done Guan Shang, when the shunting well is slot type, it is not provided with cut-off equipment;
For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;
The water inlet of the shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, described First delivery port of shunting well connects with the Storm-water sewer on the town road on rear side of the shunting well, the cut-off equipment It is arranged on the first water outlet of the shunting well;Second delivery port of the shunting well and particle separator, cylinder filter It is sequentially connected, the delivery port of the cylinder filter connects with the Storm-water sewer on the town road on rear side of the shunting well It is logical.The distance between each two rainwater pretreatment system is 0.3 kilometer.
Embodiment 2
It is using the community wastewater of embodiment 1 and the control method of separate sewage system of rainwater:
During fine day, bottom-open type weir gate 4 is opened, and bottom-open type gate 5, rotation weir gate 9 are closed, and the sewage of sewage conduct passes through dirt Water conduit tube flows into sewage treatment plant and handled;The sanitary sewage of storm sewer misconnection hybrid junction passes through bottom-open type weir gate 4 and sewage Main is handled into sewage treatment plant;
During initial rainfall, bottom-open type weir gate 4 is opened, and bottom-open type gate 5, rotation weir gate 9 are closed, and the sewage of sewage conduct leads to Trunk sewer inflow sewage treatment plant is crossed to be handled;The sanitary sewage of storm sewer misconnection hybrid junction is with entering the rainwater in cell The combined sewage that the rainwater of pipeline is formed is handled by bottom-open type weir gate 4 and trunk sewer into sewage treatment plant;
During middle and later periods rainfall, when water exceedes towards the maximum inflow-rate of water turbine for cutting dirty pipe of sewage treatment plant, opened under unlatching Formula gate 5, combined sewage enter in online processing pond, and the combined sewage after being handled through online processing pond is directly discharged to rain again Water conduit tube;
During flood discharge, when water exceedes the maximum processing capability of online processing pond, rotation weir gate 9, combined sewage stream are opened Enter Storm-water sewer.
Specifically, when the system includes control system, the liquid level sensor in the control system is mainly used in monitoring Water body liquid level, normal water level H1, the warning line H2 of shunting well of shunting well are set in the control unit of the system;The side Method comprises the following steps:
1a) water body enters shunting well from water inlet, monitors the liquid of water body in shunting well well body in real time by liquid level sensor Position height H;
2a) work as H<During H1, bottom-open type weir gate 4 is in opening, and bottom-open type gate 5 and rotation weir gate 9 are in and close shape State;
3a) as H1≤H<During H2, bottom-open type weir gate 4 and bottom-open type gate 5 are in opening, and rotation weir gate 9, which is in, to close Closed state;
4a) as H >=H2, bottom-open type weir gate 4, bottom-open type gate 5 and rotation weir gate 9 are in opening.
The above described is only a preferred embodiment of the present invention, not the structure of the present invention is done any formal Limitation.Any simple modification, equivalent change and modification that every technical spirit according to the present invention is made to above example, In the range of still falling within technical scheme.

Claims (10)

1. the separate sewage system of a kind of sewage and rainwater, the system includes:
Trunk sewer on town road, the outlet of the trunk sewer are provided with sewage treatment plant;
Storm-water sewer on town road, the end of the Storm-water sewer are connected with natural water;
Storm sewer and sewage conduct in unit area, the sewage conduct are connected with the trunk sewer;
Characterized in that, the outlet of the storm sewer sets rain processing system, the rain processing system is set including shunting Standby and online treatment facility;The shunting device has four openings, is water inlet, the first delivery port, the second delivery port respectively With the 3rd delivery port;
The water inlet connection of the storm sewer and shunting device, the first delivery port of shunting device are connected with trunk sewer, point Second delivery port of flow device is connected with the water inlet of online treatment facility, delivery port and the Storm-water sewer phase of online treatment facility Even, the 3rd delivery port of shunting device is connected with Storm-water sewer.
2. drainage system according to claim 1, it is characterised in that the unit area is to be used in urban area with function The soil region for including building and structures of way Attribute transposition;
Preferably, the area of the unit area is 0.01-0.6 square kilometres, preferably 0.01-0.3 square kilometres;
Preferably, the Storm-water sewer is original Storm-water sewer on town road;Or when there is no rainwater on the town road During main, a Storm-water sewer is laid on town road;
Preferably, the shunting device is selected from shunting well, abandoned stream well or Vatch basin.
3. drainage system according to claim 1 or 2, it is characterised in that water conservancy is set on the delivery port of shunting device Switch;
Preferably, water conservancy switch is respectively provided with each delivery port;Water conservancy is set to switch 1 in the first delivery port of shunting device, Set water conservancy to switch 2 in the second delivery port of shunting device, set water conservancy to switch 3 in the 3rd delivery port of shunting device;
Preferably, the system also includes control system, and the control system includes being used for the first monitoring for monitoring shunting device Device and the control unit being connected with the first monitoring device signal;Described control unit and water conservancy switch 1, water conservancy switch 2 3 signals are switched with water conservancy to connect;First monitoring device is used for monitoring signals and the signal of monitoring is conveyed into control unit, Control unit controls the aperture of water conservancy switch 1, water conservancy switch 2 and water conservancy switch 3 according to the signal of reception;
Preferably, the device that first monitoring device includes monitoring water body liquid level (such as can be liquid level sensor, liquid level Meter, liquid-level switch etc.), the device for monitoring water quality (such as can be Water quality detector, online COD monitors, online TSS Monitor, online BOD monitors, online TN monitors, online TP monitors, online NH3-N monitors, online NH 3 Instrument, electrode, conductivity meter etc.), the device (such as can be electronic headstock gear with function of measuring etc.) of monitoring water body total amount, The device (such as rainfall gauge) of rainfall is monitored, monitors at least one of device (such as timer) of time;
Preferably, first monitoring device may be provided in shunting device well body or shunting device well body according to type demand Outside;For example, the device of monitoring water body liquid level and the device of monitoring water quality are arranged in shunting device well body, rainfall is monitored Device is arranged on outside shunting device well body, and the device of monitoring water body total amount is arranged on the water conservancy switch in shunting device well body, The device of monitoring time is arranged in shunting device well body or outside well body;
Preferably, the shunting device can be slot type, weir Shi Huocao weirs formula shunting device;
Preferably, the water conservancy switch 1, water conservancy switch 2 and water conservancy switch 3 are identical or different;It is independently from each other valve, lock Door, flap valve or weir gate;
Preferably upper open type gate, bottom-open type gate, bottom-open type weir gate, rotation weir gate, floating drum cut-off equipment, gate valve, butterfly valve, ball Valve, lift rubber clack dam check-valves or the flap valve that dams.
4. according to the drainage system described in claim any one of 1-3, it is characterised in that the online treatment facility is selected from online Processing pond, inclined-plate clarifying basin, tube settler, flocculation basin, efficient settling pit, artificial swamp, set by pond and integrated treatment Any of standby or two or more combination;
Preferably, the shunting device can be one or more.
5. according to the drainage system described in claim any one of 1-4, it is characterised in that the system also includes rainwater and pre-processed System;It can be incorporated on the Storm-water sewer, or by the Storm-water sewer.
6. drainage system according to claim 5, it is characterised in that the rainwater pretreatment system includes shunting well, rain Water filter, particle separator, cylinder filter, rainwater separator, hydrocyclone, osmotic cell, magnetic separating device, Jie One or more in mass filter, online processing pond;
Preferably, the rainwater pretreatment system also includes regulate and store facility and/or cut-off equipment and/or volume control device;
Preferably, the rainwater pretreatment system includes shunting well, cut-off equipment, volume control device, rain water filtering device, regulated and stored Facility, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is slot type, are not provided with cutting Flow device;For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;It is described The water inlet of shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, and the first of the shunting well Delivery port connects with the Storm-water sewer on the town road on rear side of the shunting well, and the cut-off equipment is arranged on described point Flow the first water outlet of well;Second water outlet of the shunting well sets volume control device, the volume control device The other end be sequentially connected with rain water filtering device, facility of regulating and storing, the delivery port of the facility of regulating and storing connects with sewage conduct;
Preferably, the rainwater pretreatment system include shunting well, cut-off equipment, particle separator, cylinder filter, described point Stream well is arranged on the Storm-water sewer on the town road, when the shunting well is slot type, is not provided with cut-off equipment;Shunting Jing Jinshuikouweizhichu is on front side of shunting well, and the first delivery port of shunting well opening position is on rear side of shunting well;The shunting well enters The mouth of a river connects with the Storm-water sewer on the town road on front side of the shunting well, the first delivery port of the shunting well and institute The Storm-water sewer connection on the town road on rear side of shunting well is stated, the cut-off equipment is arranged on the first of the shunting well Water outlet;Second delivery port of the shunting well is sequentially connected with particle separator, cylinder filter, the cylinder filter Delivery port connected with the Storm-water sewer on the town road on rear side of the shunting well;
Preferably, the rainwater pretreatment system includes shunting well, cut-off equipment, hydrocyclone, osmotic cell and flow Control device, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is slot type, are not set Put cut-off equipment;For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position; The water inlet of the shunting well connects with the Storm-water sewer on the town road on front side of the shunting well, the shunting well First delivery port connects with the Storm-water sewer on the town road on rear side of the shunting well, and the cut-off equipment is arranged on institute State the first water outlet of shunting well;Second water outlet of the shunting well sets volume control device, the flow control The other end of device is sequentially connected with hydrocyclone, osmotic cell, the water penetration in the osmotic cell to underground;
Preferably, the rainwater pretreatment system includes shunting well, cut-off equipment, magnetic separating device, osmotic cell, media filtration Device, the shunting well are arranged on the Storm-water sewer on the town road, when the shunting well is slot type, are not provided with damming Device;For on front side of shunting well, the first delivery port of shunting well opening position is on rear side of shunting well at shunting well water inlet position;Described point The water inlet of stream well connects with the Storm-water sewer on the town road on front side of the shunting well, and the first of the shunting well goes out The mouth of a river connects with the Storm-water sewer on the town road on rear side of the shunting well, and the cut-off equipment is arranged on the shunting First water outlet of well;Second delivery port of the shunting well and magnetic separating device, osmotic cell, medium filter successively phase Even, the delivery port of the medium filter connects with the Storm-water sewer on the town road on rear side of the shunting well;
Preferably, the rainwater pretreatment system include the first shunting well, the second shunting well, cut-off equipment, online processing pond and Volume control device, first shunting well are arranged on the Storm-water sewer on the town road, when first shunting well For slot type when, be not provided with cut-off equipment;It is shunting well front side, first the first water outlet of shunting well at first shunting well water inlet position Mouth opening position is on rear side of shunting well;The water inlet of first shunting well and the town road on front side of first shunting well On Storm-water sewer connection, the town road on rear side of the first delivery port of first shunting well and first shunting well On Storm-water sewer connection, the cut-off equipment is arranged on the first water outlet of first shunting well;First shunting Second delivery port of well is connected with the water inlet of second shunting well, the first delivery port and sewage pipe of second shunting well One end connection in road, the other end of sewage conduct are connected with sewage treatment plant;Second delivery port of second shunting well with The water inlet of line processing pond connects, on the town road on rear side of the delivery port of online processing pond and first shunting well Storm-water sewer connects;The volume control device is arranged on the second water outlet of the first shunting well or is separately positioned on second point Flow the first water outlet of well and the second water outlet of the second shunting well;
Preferably, the cut-off equipment is fixed weir;Or water conservancy switch.
7. the drainage system according to claim 5 or 6, it is characterised in that set on the Storm-water sewer one or more Rainwater pretreatment system, or the combination of multiple rainwater pretreatment systems;
Preferably, when setting the combination of multiple rainwater pretreatment systems or multiple rainwater pretreatment systems on Storm-water sewer, phase The distance between adjacent combination of two rainwater pretreatment systems or two rainwater pretreatment systems is 0.2-1 kilometers.
8. according to the drainage system described in claim any one of 1-7, it is characterised in that the outlet pipe of the sewage treatment plant with Natural water is connected.
9. according to the drainage system described in claim any one of 1-8, it is characterised in that the system also includes biofilter, It is arranged on the outlet pipe of sewage treatment plant;
Preferably, the biofilter can be one or more.
10. a kind of control method of the separate sewage system of sewage and rainwater described in any one of claim 1-9, its feature It is, methods described includes:
During fine day, the sewage of sewage conduct flows into sewage treatment plant by trunk sewer and handled;Shunting device is by rain pipe The sanitary sewage of road misconnection hybrid junction branches to trunk sewer and handled into sewage treatment plant;
During initial rainfall, the sewage of sewage conduct flows into sewage treatment plant by trunk sewer and handled;Shunting device is by rain The sanitary sewage of waterpipe misconnection hybrid junction branches to sewage with entering the combined sewage that the rainwater of the storm sewer in cell is formed Main is handled into sewage treatment plant;
During middle and later periods rainfall, when water exceedes towards the maximum inflow-rate of water turbine for cutting dirty pipe of sewage treatment plant, shunting device will be mixed Sewage separation is closed into online treatment facility, the combined sewage after being handled through online treatment facility is directly discharged to rainwater and done again Pipe;
During flood discharge, when water exceedes the maximum processing capability of online treatment facility, shunting device directly shunts combined sewage To Storm-water sewer;
Preferably, method of the invention also includes:
During fine day, water conservancy switch 1 is opened, and water conservancy switch 2, water conservancy switch 3 are closed, and the sewage of sewage conduct passes through trunk sewer stream Enter sewage treatment plant to be handled;The sanitary sewage of storm sewer misconnection hybrid junction enters dirty by water conservancy switch 1 and trunk sewer Water treatment plant is handled;
During initial rainfall, water conservancy switch 1 is opened, and water conservancy switch 2, water conservancy switch 3 are closed, and the sewage of sewage conduct is done by sewage Pipe flows into sewage treatment plant and handled;The sanitary sewage of storm sewer misconnection hybrid junction and the rain for entering the storm sewer in cell The combined sewage that water is formed is handled by water conservancy switch 1 and trunk sewer into sewage treatment plant;
During middle and later periods rainfall, when water exceedes towards the maximum inflow-rate of water turbine for cutting dirty pipe of sewage treatment plant, water conservancy switch is opened 2, combined sewage enters in online treatment facility, and the combined sewage after being handled through online treatment facility is directly discharged to rainwater again Main;
During flood discharge, when water exceedes the maximum processing capability of online treatment facility, water conservancy switch 3 is opened, combined sewage flows into Storm-water sewer.
CN201710916624.1A 2017-09-30 2017-09-30 A kind of separate sewage system and control method of sewage and rainwater Withdrawn CN107558567A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710916624.1A CN107558567A (en) 2017-09-30 2017-09-30 A kind of separate sewage system and control method of sewage and rainwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710916624.1A CN107558567A (en) 2017-09-30 2017-09-30 A kind of separate sewage system and control method of sewage and rainwater

Publications (1)

Publication Number Publication Date
CN107558567A true CN107558567A (en) 2018-01-09

Family

ID=60983519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710916624.1A Withdrawn CN107558567A (en) 2017-09-30 2017-09-30 A kind of separate sewage system and control method of sewage and rainwater

Country Status (1)

Country Link
CN (1) CN107558567A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029716A (en) * 2019-04-03 2019-07-19 中国能源建设集团广东省电力设计研究院有限公司 A kind of flood control and water drain system for having both initial rainwater processing and utilizing for plant area
CN111364579A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN111364580A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN111364581A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN111364578A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN112374556A (en) * 2020-11-12 2021-02-19 联智同达(苏州)环境科技有限公司 Monitoring system and monitoring method for abnormal sewage discharge
CN113006230A (en) * 2020-12-31 2021-06-22 浙江上鑫生态建设有限公司 Diversion equipment and diversion method for rainwater and sewage in residential area
CN114592564A (en) * 2022-03-25 2022-06-07 西南林业大学 Intelligent rain and sewage collecting device

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364579A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN111364580A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN111364581A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN111364578A (en) * 2018-12-25 2020-07-03 武汉圣禹排水系统有限公司 Method for modifying sewage disposal and distribution system based on existing pipe network
CN110029716A (en) * 2019-04-03 2019-07-19 中国能源建设集团广东省电力设计研究院有限公司 A kind of flood control and water drain system for having both initial rainwater processing and utilizing for plant area
CN110029716B (en) * 2019-04-03 2020-09-11 中国能源建设集团广东省电力设计研究院有限公司 Flood control drainage system used for factory and provided with initial rainwater treatment and utilization functions
CN112374556A (en) * 2020-11-12 2021-02-19 联智同达(苏州)环境科技有限公司 Monitoring system and monitoring method for abnormal sewage discharge
CN112374556B (en) * 2020-11-12 2023-11-21 联智同达(苏州)环境科技有限公司 Sewage abnormal discharge monitoring system and monitoring method thereof
CN113006230A (en) * 2020-12-31 2021-06-22 浙江上鑫生态建设有限公司 Diversion equipment and diversion method for rainwater and sewage in residential area
CN113006230B (en) * 2020-12-31 2022-07-12 浙江上鑫生态建设有限公司 Diversion equipment and diversion method for rainwater and sewage in residential area
CN114592564A (en) * 2022-03-25 2022-06-07 西南林业大学 Intelligent rain and sewage collecting device

Similar Documents

Publication Publication Date Title
CN107558567A (en) A kind of separate sewage system and control method of sewage and rainwater
CN107806159A (en) A kind of combined drainage system and control method of sewage and rainwater
CN107806156A (en) A kind of combined drainage system and control method of sewage and rainwater
CN107806160A (en) A kind of combined drainage system and control method of sewage and rainwater
CN207436200U (en) A kind of shunting well with downflow weir and the drainage system including the shunting well
CN107761900A (en) It is a kind of to carry the double shunting wells of flap gate including the drainage system of the shunting well and water discharge control method
CN107605006A (en) A kind of drainage system and water discharge control method
CN107747345A (en) A kind of face pollution control system and its control method for drainage system pipe network system
CN107558566A (en) A kind of separate sewage system and control method of sewage and rainwater
CN107806155A (en) A kind of combined drainage system and control method of sewage and rainwater
CN207959445U (en) A kind of drainage system with regulate and store facility and online processing facility
CN107842088A (en) A kind of drainage system and water discharge control method with regulate and store facility and online treatment facility
CN207760988U (en) A kind of combined drainage system of sewage and rainwater
CN107605005A (en) A kind of drainage system and water discharge control method arranged with waterpower non-return weir gate and pump
CN107558569A (en) A kind of separate sewage system and control method of sewage and rainwater
CN107558568A (en) A kind of separate sewage system and control method of sewage and rainwater
CN207436169U (en) A kind of combined flow system pipe network system for controlling sewage and initial rainwater pollution
CN207760983U (en) A kind of drainage system with facility of regulating and storing
CN207436192U (en) A kind of separate sewage system of sewage and rainwater
CN207436183U (en) A kind of carry cuts dirty pipe, a drainage system for regulate and store facility and online treatment facility
CN208280260U (en) A kind of combined drainage system of sewage and rainwater
CN207760987U (en) A kind of combined drainage system of sewage and rainwater
CN207761004U (en) A kind of shunting well with downflow weir and the drainage system including the shunting well
CN207760984U (en) A kind of drainage system managed with section dirt with online processing facility
CN207761003U (en) A kind of drainage system with regulate and store facility and integrated treatment facility

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180109

WW01 Invention patent application withdrawn after publication