CN107558487A - A kind of goaf transmission line foundation bracing means and reinforcement means - Google Patents
A kind of goaf transmission line foundation bracing means and reinforcement means Download PDFInfo
- Publication number
- CN107558487A CN107558487A CN201710757987.5A CN201710757987A CN107558487A CN 107558487 A CN107558487 A CN 107558487A CN 201710757987 A CN201710757987 A CN 201710757987A CN 107558487 A CN107558487 A CN 107558487A
- Authority
- CN
- China
- Prior art keywords
- foundation
- basis
- transmission line
- goaf
- fixed steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Foundations (AREA)
Abstract
Description
技术领域technical field
本发明一种采空区输电线路基础加固装置及加固方法,属于输电线路基础防护技术领域。The invention relates to a goaf transmission line foundation reinforcement device and a reinforcement method, which belong to the technical field of transmission line foundation protection.
背景技术Background technique
采空塌陷造成的塌陷和地表盆地移动,会造成输电杆塔基础不均匀沉降,基础不均匀沉降时产生的非荷载应力将极有可能导致杆塔构件破坏、断裂、变形等事故发生,情况严重者将导致倒塔断线,对输电线路的安全运行构成严重威胁。The subsidence caused by goaf subsidence and the movement of the surface basin will cause uneven settlement of the foundation of the transmission tower. The non-load stress generated during the uneven settlement of the foundation will most likely lead to accidents such as damage, fracture, and deformation of the tower components. Leading to tower collapse and disconnection, it poses a serious threat to the safe operation of transmission lines.
为保证基础不均匀沉降时,输电杆塔仍能安全稳定运行,目前常用的方法是采用大板基础和加长地脚螺栓。In order to ensure that the transmission tower can still operate safely and stably when the foundation is unevenly settled, the current common method is to use a large slab foundation and lengthen the anchor bolts.
实际工作中,有大部分输电线路设计投运年限早,当年设计时未采用大板基础设计,而是采用的普通基础,普通基础抗塌陷和不均匀沉降能力差,调正基础和保证安全运行非常困难。In actual work, most of the transmission lines are designed to be put into operation early. The design of the large slab foundation was not adopted in the design of that year, but the ordinary foundation was adopted. The ordinary foundation has poor resistance to subsidence and uneven settlement. It is necessary to adjust the foundation and ensure safe operation. very difficult.
发明内容Contents of the invention
本发明克服了现有技术存在的不足,提供了一种采空区输电线路中可以将普通基础联合成为整体大板基础的基础加固装置。The invention overcomes the deficiencies in the prior art and provides a foundation reinforcement device for combining ordinary foundations into an integral large slab foundation in a power transmission line in a goaf.
为了解决上述技术问题,本发明采用的技术方案为:一种采空区输电线路基础加固装置,包括四个呈矩形分布的直柱式基础,基础上表面设置有地脚螺栓,基础立柱四周设置有固定钢,基础之间设置有支架。In order to solve the above-mentioned technical problems, the technical solution adopted in the present invention is: a goaf power transmission line foundation reinforcement device, including four straight column foundations distributed in a rectangular shape, anchor bolts are arranged on the upper surface of the foundation, and foundation columns are arranged around There are fixed steel, and brackets are set between the foundations.
所述固定钢两端设置有第一连接孔和第二连接孔,所述的第一连接孔设置固定钢内侧,所述的第二连接孔设置在固定钢外侧,所述固定钢在基础立柱上呈井字型排列,相对的第一连接孔之间设置有螺柱,第二连接孔与支架连接。The two ends of the fixed steel are provided with a first connecting hole and a second connecting hole, the first connecting hole is set on the inner side of the fixed steel, the second connecting hole is set on the outer side of the fixed steel, and the fixed steel is set on the foundation column The top is arranged in a well shape, studs are arranged between the opposite first connecting holes, and the second connecting holes are connected with the bracket.
所述的螺柱为双头螺柱,所述螺柱配套设置有螺母,所述螺母为加厚螺母。The studs are double-ended studs, and the studs are matched with nuts, and the nuts are thickened nuts.
所述支架包括钢筋和箍筋。The bracket includes steel bars and stirrups.
所述的固定钢可以是槽钢,也可以为其他型钢。The fixing steel can be channel steel or other shaped steel.
一种采空区基础加固方法,包括如下步骤:A foundation reinforcement method for a goaf, comprising the steps of:
一、对采空区已发生不均匀沉降的输电铁塔采取安全补强措施;1. Take safety reinforcement measures for the transmission towers that have undergone uneven settlement in the goaf;
二、沿原有基础四周向下开挖1米,在基础的立柱四周设置固定钢;2. Excavate 1 meter downward along the original foundation, and install fixed steel around the foundation column;
三、按照设计载荷和附加载荷要求,通过固定钢外侧的第二连接孔设置钢筋和箍筋组成的支架,将多个基础连接起来。3. According to the design load and additional load requirements, set a support composed of steel bars and stirrups through the second connection hole on the outside of the fixed steel to connect multiple foundations.
四、浇筑混凝土,将连接起来的基础联合成为整体大板基础,达到混凝土强度要求后,拆除临时安全补强措施。4. Concrete is poured, and the connected foundations are combined into an overall large slab foundation. After the concrete strength requirements are met, the temporary safety reinforcement measures are removed.
本发明与现有技术相比具有以下有益效果:在普通直柱式基础之间设置连梁,将直柱式基础通过连梁连接为一个整体基础,增加了基础的稳定性,可以有效的避免倒塔断线等恶劣事故,有效保证线路安全运行,提高了供电的可靠性,减少了调整铁塔基础造成的人力、物力浪费,安全环保,绿色低碳。Compared with the prior art, the present invention has the following beneficial effects: connecting beams are arranged between ordinary straight-column foundations, and the straight-column foundations are connected into a whole foundation through connecting beams, which increases the stability of the foundation and can effectively avoid Severe accidents such as tower collapse and disconnection effectively ensure the safe operation of the line, improve the reliability of power supply, reduce the waste of manpower and material resources caused by adjusting the foundation of the tower, and are safe and environmentally friendly, green and low-carbon.
附图说明Description of drawings
下面结合附图对本发明做进一步的说明。The present invention will be further described below in conjunction with the accompanying drawings.
图1为本发明的结构示意图。Fig. 1 is a structural schematic diagram of the present invention.
图2为图1的侧视图。FIG. 2 is a side view of FIG. 1 .
图中1为基础、2为地脚螺栓、3为固定钢、4为钢筋骨架、5为螺柱、6为螺母、31为第一连接孔、32为第二连接孔。In the figure, 1 is the foundation, 2 is the anchor bolt, 3 is the fixing steel, 4 is the reinforcement frame, 5 is the stud, 6 is the nut, 31 is the first connection hole, and 32 is the second connection hole.
具体实施方式detailed description
如图1、图2所示,本发明一种采空区输电线路基础加固装置,包括四个呈矩形分布的直柱式基础1,基础1上表面设置有地脚螺栓2,基础1立柱四周设置有固定钢3,基础1之间设置有支架4;所述固定钢3两端设置有第一连接孔31和第二连接孔32,所述的第一连接孔31设置固定钢3内侧,所述的第二连接孔32设置在固定钢3外侧,所述固定钢3在基础1立柱上呈井字型排列,相对的第一连接孔31之间设置有螺柱5,第二连接孔32与支架4连接;所述的螺柱5为双头螺柱,所述螺柱5配套设置有螺母6,所述螺母6为加厚螺母;所述支架4包括钢筋和箍筋;所述的固定钢3可以是槽钢,也可以为其他型钢。As shown in Fig. 1 and Fig. 2, a kind of goaf transmission line foundation strengthening device of the present invention includes four straight column foundations 1 distributed in a rectangle, the upper surface of the foundation 1 is provided with anchor bolts 2, and the foundation 1 is surrounded by uprights. A fixed steel 3 is provided, and a bracket 4 is provided between the foundations 1; a first connection hole 31 and a second connection hole 32 are provided at both ends of the fixed steel 3, and the first connection hole 31 is provided inside the fixed steel 3, The second connecting hole 32 is arranged on the outside of the fixed steel 3, and the fixed steel 3 is arranged in a square shape on the foundation 1 column, and studs 5 are arranged between the first connecting holes 31 opposite, and the second connecting hole 32 is connected with the bracket 4; the stud 5 is a double-ended stud, and the stud 5 is provided with a nut 6, and the nut 6 is a thickened nut; the bracket 4 includes a steel bar and a stirrup; The fixed steel 3 can be a channel steel or other shaped steel.
本发明在使用时,首先按照采空区基础的设计载荷和附加载荷设计钢筋骨架的配筋与混凝土强度等级,将需要加固的铁塔基础采取安全补强措施后,沿着基础1主柱四周向下开挖用于安装支架4的沟槽,在基础1主柱四周通过螺栓5和螺母6安装固定钢3,然后在固定钢3的第二连接孔32处绑扎混凝土配筋,然后浇筑混凝土,使多个基础1连接为一个整体大板基础,在混凝土强度达到95%及以上时,回填沟槽,在混凝土强度达到100%时,拆除临时安全补强措施,恢复线路正常运行。When the present invention is in use, first design the reinforcement and concrete strength grades of the steel skeleton according to the design load and additional load of the foundation of the goaf, and after taking safety reinforcement measures for the iron tower foundation that needs to be strengthened, the reinforcement along the four sides of the foundation 1 main column Excavate the groove for installing the bracket 4, install the fixed steel 3 around the main column of the foundation 1 through bolts 5 and nuts 6, then bind concrete reinforcement at the second connection hole 32 of the fixed steel 3, and then pour concrete, Connect multiple foundations 1 into an overall large slab foundation. When the concrete strength reaches 95% and above, the grooves are backfilled. When the concrete strength reaches 100%, the temporary safety reinforcement measures are removed to restore the normal operation of the line.
上面结合附图对本发明的实施例作了详细说明,但是本发明并不限于上述实施例,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化。The embodiments of the present invention have been described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Within the scope of knowledge of those of ordinary skill in the art, various modifications can be made without departing from the gist of the present invention. kind of change.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710757987.5A CN107558487A (en) | 2017-08-29 | 2017-08-29 | A kind of goaf transmission line foundation bracing means and reinforcement means |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710757987.5A CN107558487A (en) | 2017-08-29 | 2017-08-29 | A kind of goaf transmission line foundation bracing means and reinforcement means |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN107558487A true CN107558487A (en) | 2018-01-09 |
Family
ID=60976219
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710757987.5A Pending CN107558487A (en) | 2017-08-29 | 2017-08-29 | A kind of goaf transmission line foundation bracing means and reinforcement means |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107558487A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667277A (en) * | 2018-12-25 | 2019-04-23 | 中国能源建设集团广东省电力设计研究院有限公司 | Cantilevered coupling beam cable termination field |
| CN110644522A (en) * | 2019-09-06 | 2020-01-03 | 内蒙古农业大学 | A method for tower foundation settlement of coal mining subsidence transmission line in wind-blown sand area |
| CN113914701A (en) * | 2021-11-01 | 2022-01-11 | 峻江建设有限公司 | Anti-toppling iron tower capable of being applied to soft soil |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5505033A (en) * | 1988-12-06 | 1996-04-09 | 501 Hitachi Metals Ltd. | Column base structure and connection arrangement |
| CN2723551Y (en) * | 2004-07-13 | 2005-09-07 | 建研科技股份有限公司 | Frame beam and pole node reinforcing device |
| JP2012172295A (en) * | 2011-02-17 | 2012-09-10 | Tokyo Electric Power Co Inc:The | Reinforcement method of steel tower for power transmission |
| CN203284818U (en) * | 2013-03-29 | 2013-11-13 | 国家电网公司 | Transmission tower foot reinforcing device |
| CN105672473A (en) * | 2016-03-30 | 2016-06-15 | 福州大学 | Reinforced concrete frame structure with shock resistance |
| CN206346216U (en) * | 2016-12-29 | 2017-07-21 | 榆林市长江送变电工程有限责任公司 | A kind of ruggedized construction of power transmission line iron tower foundation |
| CN207109843U (en) * | 2017-08-29 | 2018-03-16 | 国网山西省电力公司晋城供电公司 | A kind of goaf transmission line foundation bracing means |
-
2017
- 2017-08-29 CN CN201710757987.5A patent/CN107558487A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5505033A (en) * | 1988-12-06 | 1996-04-09 | 501 Hitachi Metals Ltd. | Column base structure and connection arrangement |
| CN2723551Y (en) * | 2004-07-13 | 2005-09-07 | 建研科技股份有限公司 | Frame beam and pole node reinforcing device |
| JP2012172295A (en) * | 2011-02-17 | 2012-09-10 | Tokyo Electric Power Co Inc:The | Reinforcement method of steel tower for power transmission |
| CN203284818U (en) * | 2013-03-29 | 2013-11-13 | 国家电网公司 | Transmission tower foot reinforcing device |
| CN105672473A (en) * | 2016-03-30 | 2016-06-15 | 福州大学 | Reinforced concrete frame structure with shock resistance |
| CN206346216U (en) * | 2016-12-29 | 2017-07-21 | 榆林市长江送变电工程有限责任公司 | A kind of ruggedized construction of power transmission line iron tower foundation |
| CN207109843U (en) * | 2017-08-29 | 2018-03-16 | 国网山西省电力公司晋城供电公司 | A kind of goaf transmission line foundation bracing means |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667277A (en) * | 2018-12-25 | 2019-04-23 | 中国能源建设集团广东省电力设计研究院有限公司 | Cantilevered coupling beam cable termination field |
| CN110644522A (en) * | 2019-09-06 | 2020-01-03 | 内蒙古农业大学 | A method for tower foundation settlement of coal mining subsidence transmission line in wind-blown sand area |
| CN113914701A (en) * | 2021-11-01 | 2022-01-11 | 峻江建设有限公司 | Anti-toppling iron tower capable of being applied to soft soil |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN115369748A (en) | Construction method of template system for integrally pouring pier and tie beam | |
| CN103452126B (en) | Light combined hanging box with recyclable baseplate steels and construction technology thereof | |
| CN203808484U (en) | Integrated cantilevered and attached external scaffolding | |
| CN104929148B (en) | The upside-down mounting hardened system of generation power foundation of wind power ring group plinth and reinforcement means thereof | |
| CN110878522B (en) | Construction system and construction method of beam under main tower | |
| CN208055880U (en) | A kind of crane's major girder hoisting frame | |
| CN103469735B (en) | The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation | |
| CN110306774B (en) | Method and device for installing socket type cantilever scaffold | |
| CN202672766U (en) | Concrete pole repair strengthening hoop | |
| CN206607506U (en) | A kind of through type adds the capping construction support of passive stress trapezoid block | |
| CN107558487A (en) | A kind of goaf transmission line foundation bracing means and reinforcement means | |
| CN206486819U (en) | A kind of stable support body system for ensureing continuous beam cantilever casting construction | |
| CN107012795A (en) | A kind of continuous bridge pre-pressing bracket device and its construction method | |
| CN101881029A (en) | Detachable tower foundation | |
| CN206360399U (en) | The existing reinforced concrete coupling beam bracing means of one species " doubly-linked beam " | |
| CN210439163U (en) | Diagonal joist supporting structure applicable to assembly and disassembly of continuous beam | |
| CN207109843U (en) | A kind of goaf transmission line foundation bracing means | |
| CN106088379B (en) | A kind of shear-deformable nodal point connecting of BRB lockings and its installation method | |
| CN204343642U (en) | Builder's jack corner support frame | |
| CN101476330B (en) | Thick and large-volume concrete elastic base and construction method thereof | |
| CN205712733U (en) | Super-section strengthening concrete conversion beam formwork system | |
| CN108240113A (en) | Detachably across the support device at hole and method | |
| CN109441118B (en) | Distributing machine pouring system and method for assembled building construction concrete | |
| CN111519931A (en) | Support construction method and structure for transformation of existing building structure column | |
| CN214884864U (en) | Mounting structure of strength nature structure steel column |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180109 |
|
| RJ01 | Rejection of invention patent application after publication |