CN107552936B - 60kg/m U75V+U75VG钢轨移动闪光焊接工艺 - Google Patents

60kg/m U75V+U75VG钢轨移动闪光焊接工艺 Download PDF

Info

Publication number
CN107552936B
CN107552936B CN201710801712.7A CN201710801712A CN107552936B CN 107552936 B CN107552936 B CN 107552936B CN 201710801712 A CN201710801712 A CN 201710801712A CN 107552936 B CN107552936 B CN 107552936B
Authority
CN
China
Prior art keywords
rail
stage
welding
u75vg
duration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710801712.7A
Other languages
English (en)
Other versions
CN107552936A (zh
Inventor
王若愚
李大东
白威
邓健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Advanced Metal Materials Industry Technology Research Institute Co Ltd
Original Assignee
Pangang Group Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Research Institute Co Ltd filed Critical Pangang Group Research Institute Co Ltd
Priority to CN201710801712.7A priority Critical patent/CN107552936B/zh
Publication of CN107552936A publication Critical patent/CN107552936A/zh
Application granted granted Critical
Publication of CN107552936B publication Critical patent/CN107552936B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pressure Welding/Diffusion-Bonding (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

本发明公开了一种60kg/m U75V+U75VG钢轨移动闪光焊接工艺,特别是一种涉及钢轨焊接技术领域的60kg/m U75V+U75VG钢轨移动闪光焊接工艺。本发明的60kg/m U75V+U75VG钢轨移动闪光焊接工艺,包括闪平阶段、脉动阶段、加速烧化阶段、顶锻阶段和保压阶段,焊接过程中焊接的总热输入量为8.2MJ~8.7MJ,焊接的总持续时间为111s~121s,焊接顶锻量为16.0mm~16.6mm。采用本发明的方法能够成功将60kg/m U75V+U75VG钢轨进行移动闪光焊接,钢轨接头的内部缺陷少,焊接质量稳定,可以通过疲劳试验、拉伸试验以及静弯试验的等各项力学性能试验;并且钢轨接头能够连续通过15支闪光焊接头落锤检验,具有较好的稳定性。

Description

60kg/m U75V+U75VG钢轨移动闪光焊接工艺
技术领域
本发明涉及一种60kg/m U75V+U75VG钢轨移动闪光焊接工艺,特别是一种涉及钢轨焊接技术领域的60kg/m U75V+U75VG钢轨移动闪光焊接工艺。
背景技术
随着各国对铁路重载要求的日益严格,铁路轴重不断提高,要求钢轨具有更强的耐磨性,也就是更高的硬度要求。在现有技术中60kg/m U75V+U75VG钢轨焊接主要包括闪平阶段、脉动阶段、加速烧化阶段、顶锻阶段和保压阶段,由于60kg/m U75V+U75VG钢轨焊接过程中各个因素相互影响,因此如何选取焊接控制的参数,如何选择并协调各个参数的控制范围是60kg/m U75V+U75VG钢轨的关键问题。其中,U75V+U75VG是指将型号为U75V和型号为U75VG的钢轨焊接在一起。在现有技术中生产厂按TB/T3276~2011 《高速铁路用钢轨》标准生产的60kg/m U75VG高速铁路百米钢轨,在生产过程中因短尺、轧疤、夹杂物或平直度控制不满足TB/T3276~2011高速钢轨标准。并且现有技术中焊接U75V+U75VG钢轨焊接时因轨底灰斑尺寸超标等原因导致接头落锤检验总是不合格。
发明内容
本发明提供了一种可以有效避免钢轨接头的内部缺陷少,显著提高焊接质量稳定性的60kg/m U75V+U75VG钢轨移动闪光焊接工艺。
本发明的60kg/m U75V+U75VG钢轨移动闪光焊接工艺,包括闪平阶段、脉动阶段、加速烧化阶段、顶锻阶段和保压阶段,焊接过程中焊接的总热输入量为8.2MJ~8.7MJ,焊接的总持续时间为111s~121s,焊接顶锻量为16.0mm~16.6mm。
进一步的是,闪平阶段的焊接热输入量为1.5MJ~1.8MJ,持续时间为19s~20s;脉动阶段的焊接热输入量为5.8MJ~6.2MJ,钢轨消耗量为6.0mm~8.5mm,持续时间为 64s~66s;加速烧化阶段的焊接热输入量为0MJ~0.3MJ,钢轨消耗量为7.5mm~8.8mm,持续时间为19s~21s;顶锻阶段的焊接热输入量为0MJ~0.1MJ,钢轨消耗量为16.5mm~ 16.8mm,带电顶锻时间0.4s~0.5s;保压阶段的持续时间为10s~14s。
进一步的是,保压阶段的保压压力为26t~28t。
进一步的是,焊接完成后对钢轨焊接接头进行热处理。
进一步的是,热处理时将接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温达到900℃~920℃,然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面40mm~45mm,喷风风压0.2MPa~0.25MPa,终冷温度≥430℃。
本发明的有益效果是:本申请的方法通过控制焊接热总输入量,闪平、脉动、加速烧化、顶锻四个阶段的焊接热输入量和每个阶段的持续时间,来改善钢轨焊接的质量。采用本发明的方法,能够成功实现60kg/m U75V+U75VG钢轨移动闪光焊接,钢轨接头的内部缺陷少,焊接质量稳定,可以通过疲劳试验、拉伸试验以及静弯试验的测试满足要求;钢轨接头能够连续通过15支闪光焊接头落锤检验,具有较好的稳定性。
附图说明
图1是本申请U75V+U75VG钢轨移动闪光焊焊接曲线图。
图2是本申请U75V+U75VG钢轨闪光焊接头焊后热处理轨腰低倍样图。
图3是本申请U75V+U75VG钢轨轨顶面硬度曲线图。
图4是本申请U75V+U75VG钢轨纵断面硬度曲线图。
图5是本申请U75V+U75VG钢轨闪光焊接头第一次静弯力曲线图。
图6是本申请本申请U75V+U75VG钢轨闪光焊接头第二次静弯力曲线图。
具体实施方式
本申请的60kg/m U75V+U75VG钢轨移动闪光焊接工艺,包括闪平阶段、脉动阶段、加速烧化阶段、顶锻阶段和保压阶段,焊接过程中焊接的总热输入量为8.2MJ~8.7MJ,焊接的总持续时间为111s~121s,焊接顶锻量为16.0mm~16.6mm。本申请的方法通过控制和协调焊接热总输入量,总持续时间,焊接顶锻来改善钢轨焊接的质量,如图3、图4、图5、图6所示,采用本发明的方法能够成功将60kg/m U75V+U75VG钢轨进行移动闪光焊接,钢轨接头的内部缺陷少,焊接质量稳定,可以通过疲劳试验、拉伸试验以及静弯试验的等各项力学性能试验;并且钢轨接头能够连续通过15支闪光焊接头落锤检验,具有较好的稳定性。其中,顶锻量为顶锻阶段的钢轨消耗量。
为了进一步提高焊接质量,本申请还对各个阶段的参数进行选择性控制与协调,闪平阶段的焊接热输入量为1.5MJ~1.8MJ,持续时间为19s~20s;脉动阶段的焊接热输入量为5.8MJ~6.2MJ,钢轨消耗量为6.0mm~8.5mm,持续时间为64s~66s;加速烧化阶段的焊接热输入量为0MJ~0.3MJ,钢轨消耗量为7.5mm~8.8mm,持续时间为19s~ 21s;顶锻阶段的焊接热输入量为0MJ~0.1MJ,钢轨消耗量为16.5mm~16.8mm,带电顶锻时间0.4s~0.5s;保压阶段的持续时间为10s~14s。本申请的方法通过控制,闪平、脉动、加速烧化、顶锻四个阶段的焊接热输入量和每个阶段的持续时间使钢轨焊接的得到进一步的改善。其焊接曲线如图1所示。
保压阶段的保压压力为26t~28t。对保压阶段的保压压力进行控制,使其位于26t~ 28t的范围内,可以进一步提高焊接质量的稳定性。
焊接完成后对钢轨焊接接头进行热处理。对焊接接头进行热处理,可以避免钢轨出现高淬硬性的马氏体组织。
热处理时将接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温达到900℃~920℃,然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面40mm~45mm,喷风风压0.2MPa~0.25MPa,终冷温度≥430℃。如图2所示、按照前述方法进行热处理可以增加焊接区母材硬度,增加焊接部分的冲击韧性,并短软化区宽度从而提高钢轨焊接接头的质量。
按照本申请进行的U75V+U75VG钢轨移动闪光焊焊接曲线图如图1所示。
实施例:以下为采用本申请的方法60kg/m U75V+U75VG钢轨移动闪光焊接的实施例。
实施例1:
U75V+U75VG钢轨采用移动钢轨闪光焊机焊接时,闪平第一阶段的焊接热输入1.7MJ,钢轨消耗量0.4mm,持续时间19.9s。脉动第二阶段的焊接热输入6.0MJ,钢轨消耗量3.8mm,持续时间63.9s。加速烧化第三阶段焊接热输入0.4MJ,钢轨消耗量7.4mm,持续时间17.1s。顶锻第四阶段的焊接热输入0.10MJ,顶锻量16.2mm,带电顶锻时间0.4s,持续时间8.8s。保压第五阶段的保压压力27.9t,持续时间13.2s。控制焊接总热输入量8.2MJ、钢轨消耗总量27.8mm和总焊接持续时间122.9s,达到控制焊接质量的目的。
当顶锻和推凸完成后的接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温900℃,加热时间145s,红外测温仪自动采集踏面温度到温后的信号并立即自动关闭加热电源。然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面40mm,喷风风压0.20MPa,喷风时间137s,当焊缝踏面温度风冷降至430℃时,自动关闭风冷装置,接头进行自然冷却至室温。
实施例2:
U75V+U75VG钢轨采用移动钢轨闪光焊机焊接时,闪平第一阶段的焊接热输入1.6MJ,钢轨消耗量1.5mm,持续时间19.9s。脉动第二阶段的焊接热输入6.2MJ,钢轨消耗量6.2mm,持续时间64s。加速烧化第三阶段焊接热输入0.3MJ,钢轨消耗量8.0mm,持续时间17.1s。顶锻第四阶段的焊接热输入0.10MJ,顶锻量16.4mm,带电顶锻时间0.4s,持续时间6.8s。保压第五阶段的保压压力27.9t,持续时间13.2s。控制焊接总热输入量8.2MJ、钢轨消耗总量32.1mm和总焊接持续时间121s,达到控制焊接质量的目的。
当顶锻和推凸完成后的接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温900℃,加热时间160s,红外测温仪自动采集踏面温度到温后的信号并立即自动关闭加热电源。然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面40mm,喷风风压0.20MPa,喷风时间137s,当焊缝踏面温度风冷降至430℃时,自动关闭风冷装置,接头进行自然冷却至室温。
实施例3:
U75V+U75VG钢轨采用移动钢轨闪光焊机焊接时,闪平第一阶段的焊接热输入1.6MJ,钢轨消耗量0.6mm,持续时间19.9s。脉动第二阶段的焊接热输入6.0MJ,钢轨消耗量6.8mm,持续时间63.9s。加速烧化第三阶段焊接热输入0.3MJ,钢轨消耗量7.6mm,持续时间16.3s。顶锻第四阶段的焊接热输入0.10MJ,顶锻量16.4mm,带电顶锻时间0.4s,持续时间7.4s。保压第五阶段的保压压力27.0t,持续时间13.2s。控制焊接总热输入量8MJ、钢轨消耗总量31.4mm和总焊接持续时间120.7s,达到控制焊接质量的目的。
当顶锻和推凸完成后的接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温920℃,加热时间156s,红外测温仪自动采集踏面温度到温后的信号并立即自动关闭加热电源。然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面45mm,喷风风压0.25MPa,喷风时间125s,当焊缝踏面温度风冷降至430℃时,自动关闭风冷装置,接头进行自然冷却至室温。
实施例4:
U75V+U75VG钢轨采用移动钢轨闪光焊机焊接时,闪平第一阶段的焊接热输入1.6MJ,钢轨消耗量0.4mm,持续时间19.9s。脉动第二阶段的焊接热输入6.1MJ,钢轨消耗量2.7mm,持续时间64s。加速烧化第三阶段焊接热输入0.7MJ,钢轨消耗量6.8mm,持续时间19.2s。顶锻第四阶段的焊接热输入0.10MJ,顶锻量16.1mm,带电顶锻时间0.4s,持续时间9.3s。保压第五阶段的保压压力28.1t,持续时间13.2s。控制焊接总热输入量8.5MJ、钢轨消耗总量26mm和总焊接持续时间125.6s,达到控制焊接质量的目的。
当顶锻和推凸完成后的接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温920℃,加热时间156s,红外测温仪自动采集踏面温度到温后的信号并立即自动关闭加热电源。然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面45mm,喷风风压0.25MPa,喷风时间128s,当焊缝踏面温度风冷降至430℃时,自动关闭风冷装置,接头进行自然冷却至室温。

Claims (4)

1.60kg/m U75V+U75VG钢轨移动闪光焊接工艺,其特征在于:包括闪平阶段、脉动阶段、加速烧化阶段、顶锻阶段和保压阶段,焊接过程中焊接的总热输入量为8.2MJ,焊接的总持续时间为121s,钢轨消耗总量为32.1mm;其中闪平阶段的焊接热输入量为1.5MJ~1.8MJ,钢轨消耗量为1.5mm,持续时间为19s~20s;脉动阶段的焊接热输入量为5.8MJ~6.2MJ,钢轨消耗量为6.2mm,持续时间为64s;加速烧化阶段的焊接热输入量为0.3MJ,钢轨消耗量为8.0mm,持续时间为17.1s;顶锻阶段的焊接热输入量为0.1MJ,钢轨消耗量为16.4mm,带电顶锻时间0.4s~0.5s,持续时间为6.8s;保压阶段的持续时间为10s~14s。
2.如权利要求1所述的60kg/m U75V+U75VG钢轨移动闪光焊接工艺,其特征在于:保压阶段的保压压力为27.9t。
3.如权利要求1所述的60kg/m U75V+U75VG钢轨移动闪光焊接工艺,其特征在于:焊接完成后对钢轨焊接接头进行热处理。
4.如权利要求3所述的60kg/m U75V+U75VG钢轨移动闪光焊接工艺,其特征在于:热处理时将接头温度自然冷却到300℃后,采用中频电源全断面加热闪光焊接头至轨头焊缝踏面峰温达到900℃~920℃,然后采用喷风装置加速风冷闪光焊接头踏面加热区域,喷风口距离踏面40mm~45mm,喷风风压0.2MPa~0.25MPa,终冷温度≥430℃。
CN201710801712.7A 2017-09-07 2017-09-07 60kg/m U75V+U75VG钢轨移动闪光焊接工艺 Active CN107552936B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710801712.7A CN107552936B (zh) 2017-09-07 2017-09-07 60kg/m U75V+U75VG钢轨移动闪光焊接工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710801712.7A CN107552936B (zh) 2017-09-07 2017-09-07 60kg/m U75V+U75VG钢轨移动闪光焊接工艺

Publications (2)

Publication Number Publication Date
CN107552936A CN107552936A (zh) 2018-01-09
CN107552936B true CN107552936B (zh) 2019-09-17

Family

ID=60979799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710801712.7A Active CN107552936B (zh) 2017-09-07 2017-09-07 60kg/m U75V+U75VG钢轨移动闪光焊接工艺

Country Status (1)

Country Link
CN (1) CN107552936B (zh)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108890106B (zh) * 2018-07-26 2020-10-30 攀钢集团攀枝花钢铁研究院有限公司 60kg/m R260热轧钢轨移动闪光焊接的方法
CN109079302B (zh) * 2018-08-29 2020-10-27 攀钢集团攀枝花钢铁研究院有限公司 60kg/mR260热轧钢轨移动闪光焊接的方法
CN109355481A (zh) * 2018-10-26 2019-02-19 攀钢集团攀枝花钢铁研究院有限公司 槽型钢轨闪光焊接头焊后热处理方法
CN110102864B (zh) * 2019-04-28 2021-06-01 铁科(北京)轨道装备技术有限公司 一种合金钢与槽型钢轨的焊接工艺
CN110480139B (zh) * 2019-08-26 2022-08-05 攀钢集团攀枝花钢铁研究院有限公司 控制下限Mn含量R350HT钢轨闪光焊接接头组织的工艺
CN113305407A (zh) * 2021-06-15 2021-08-27 中国铁道科学研究院集团有限公司金属及化学研究所 一种75kg/m、1380MPa级贝氏体钢轨的闪光焊接工艺
CN113414480B (zh) * 2021-07-23 2022-10-11 攀钢集团攀枝花钢铁研究院有限公司 消除75kg/m过共析钢轨移动闪光焊接头过烧缺陷的方法
CN113427109B (zh) * 2021-08-09 2022-11-29 攀钢集团攀枝花钢铁研究院有限公司 一种含铜耐腐蚀钢轨的焊接方法
CN114054915B (zh) * 2021-11-29 2023-04-28 攀钢集团攀枝花钢铁研究院有限公司 一种短路预热的闪光焊接方法
CN115488483B (zh) * 2022-11-03 2024-04-09 攀钢集团攀枝花钢铁研究院有限公司 一种提升钢轨闪光对焊接头的结合强度的方法
CN115488481B (zh) * 2022-11-03 2024-03-08 攀钢集团攀枝花钢铁研究院有限公司 减小过共析钢轨接头球化退火区宽度的方法
CN115488482B (zh) * 2022-11-03 2023-12-22 攀钢集团攀枝花钢铁研究院有限公司 减小高强珠光体钢轨闪光焊接头热影响区宽度的方法
CN115673505A (zh) * 2022-11-24 2023-02-03 攀钢集团攀枝花钢铁研究院有限公司 提升中碳低合金钢轨闪光焊接头质量的方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105382391A (zh) * 2015-12-14 2016-03-09 中国铁道科学研究院金属及化学研究所 一种钢轨焊接方法
CN106334863A (zh) * 2016-10-19 2017-01-18 攀钢集团攀枝花钢铁研究院有限公司 一种对75kg/m过共析钢轨与珠光体钢轨进行移动闪光焊接的方法和钢轨

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105382391A (zh) * 2015-12-14 2016-03-09 中国铁道科学研究院金属及化学研究所 一种钢轨焊接方法
CN106334863A (zh) * 2016-10-19 2017-01-18 攀钢集团攀枝花钢铁研究院有限公司 一种对75kg/m过共析钢轨与珠光体钢轨进行移动闪光焊接的方法和钢轨

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
U75V钢轨闪光焊工艺研究;丁韦;《热加工工艺》;20100531;第39卷(第9期);第135-137页
现场钢轨焊接接头热处理设备研制及工艺研究;丁韦;《热加工工艺》;20130131;第42卷(第1期);第166-168,170页

Also Published As

Publication number Publication date
CN107552936A (zh) 2018-01-09

Similar Documents

Publication Publication Date Title
CN107552936B (zh) 60kg/m U75V+U75VG钢轨移动闪光焊接工艺
CN107520529B (zh) 136re+ss热处理钢轨移动闪光焊接的方法
CN104862466B (zh) 过共析钢轨焊接接头焊后热处理的方法
CN106544933B (zh) 一种对钢轨焊接接头进行焊后热处理的方法
CN106334863B (zh) 一种对75kg/m过共析钢轨与珠光体钢轨进行移动闪光焊接的方法和钢轨
CN103898310B (zh) 一种贝氏体钢轨焊接接头的焊后热处理方法
US8075714B2 (en) Localized induction heating for residual stress optimization
US20140345753A1 (en) System and method for hot-forming blanks
CN108570550B (zh) 热处理型贝氏体钢轨焊接接头焊后热处理方法
CN107502730A (zh) 136re+ss热处理钢轨焊接接头的焊后热处理方法
MX2019008749A (es) Metodo para unir rieles de acero con entrada controlada del calor de la soldadura.
CN107385188A (zh) 贝氏体钢轨焊接接头的焊后热处理方法
EA200500282A1 (ru) Усовершенствованный способ кузнечной сварки и полученный этим способом продукт
CN112226609B (zh) 用于异种钢轨焊后接头热处理的施工方法
CN107322159A (zh) 金属双激光束冲击锻打低应力焊接装置与方法
CN102618713A (zh) 超超临界火电机组焊接sa335-p91/p92钢的热处理方法
CN103205551A (zh) 支重轮的热处理加工方法
CN110331275A (zh) 贝氏体钢轨焊后热处理方法
JP2013128945A (ja) 抵抗スポット溶接方法
CN104096972B (zh) 降低冷硬态含磷if钢激光焊缝断带率的方法
Xiong et al. Thermal cycle and microstructure of backing weld in double-sided TIG arc horizontal welding of high-strength steel thick plate
CN113618194B (zh) 60kg/m过共析钢轨气压焊接方法及装置
CN104561508A (zh) 钢轨气压焊焊后正火处理方法
CN105562893B (zh) 用于大规格超高强度钢板的co2气体保护焊的焊接方法
CN105710542A (zh) 一种避免中高碳钢复合焊接裂纹生成的方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201109

Address after: 610306, Chengdu, Sichuan, China (Sichuan) free trade test area, Chengdu Town, Qingbaijiang District, Chengxiang Island, No. 1509, xiangdao Avenue, 13 (A1301-1311, 1319) of A District, railway tower.

Patentee after: CHENGDU ADVANCED METAL MATERIALS INDUSTRY TECHNOLOGY RESEARCH INSTITUTE Co.,Ltd.

Address before: 610000 Chengdu Sichuan hi tech Zone West Park Innovation Group Panzhihua Iron & Steel Group Research Institute Co., Ltd.

Patentee before: Pangang Group Research Institute Co.,Ltd.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 610306 Chengdu City, Chengdu, Sichuan, China (Sichuan) free trade test zone, Chengdu City, Qingbaijiang District, xiangdao Boulevard, Chengxiang Town, No. 1509 (room 13, A District, railway port mansion), room 1319

Patentee after: Chengdu advanced metal material industry technology Research Institute Co.,Ltd.

Address before: 610306 Chengdu City, Chengdu, Sichuan, China (Sichuan) free trade test zone, Chengdu City, Qingbaijiang District, xiangdao Boulevard, Chengxiang Town, No. 1509 (room 13, A District, railway port mansion), room 1319

Patentee before: CHENGDU ADVANCED METAL MATERIAL INDUSTRIAL TECHNOLOGY RESEARCH INSTITUTE Co.,Ltd.

CP01 Change in the name or title of a patent holder