悬挑脚手架的u型锚固环施工方法 Download PDFInfo
- Publication number
- CN107524288A CN107524288A CN201610440731.7A CN201610440731A CN107524288A CN 107524288 A CN107524288 A CN 107524288A CN 201610440731 A CN201610440731 A CN 201610440731A CN 107524288 A CN107524288 A CN 107524288A
- Authority
- CN
- China
- Prior art keywords
- anchoring ring
- concrete slab
- anchoring
- shaped
- ring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/041—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffolds on roof frameworks or on roofs
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种悬挑脚手架的U型锚固环。一种悬挑脚手架的U型锚固环施工方法包括:在U型锚固环上安装塑料垫片和塑料管;在塑料垫片和塑料管接口处用胶带缠绕封堵;在混凝土板底层钢筋铺设完成后,将加工好的锚固环放置在底层钢筋以下锚固环锚固的位置;待混凝土板上层铺设完成后,调整好锚固环的位置,并将锚固环绑扎在上层钢筋上;浇筑混凝土时,随时纠正锚固环位置;拆除悬挑型钢后,左右敲击锚固环上部两个端头,使绑扎扎丝断开,锚固环从混凝土板底部掉下;将混凝土板上锚固环留下的孔洞吹扫干净,并浇筑高一等级微膨胀细石混凝土,振捣密实,待细石混凝土强度达到约50%时,拆除吊模。本发明的U型钢锚固环重复使用,降低施工成本。
Description
技术领域
本发明涉及悬挑脚手架, 尤其涉及一种悬挑脚手架的U型锚固环。
背景技术
传统的悬挑脚手架锚固环被锚固预埋在混凝土楼板中,拆除锚固环时,因锚固环与混凝土直接接触,要将预埋在混凝土中的锚固环完整地拆除下来十分困难,而且容易损伤浇筑好的结构,故只能将锚固环在楼板面处割断,因此,锚固环都是一次性的,浪费严重。
发明内容
本发明旨在解决上述缺陷,提供一种悬挑脚手架的U型锚固环施工方法。本发明使悬挑脚手架型钢锚固环重复使用,又可保证混凝土楼板原设计的完整性,节约钢材,降低施工成本。
为解决上述问题,一种悬挑脚手架的U型锚固环施工方法,它包括:
步骤一,在定型加工好的U型锚固环上安装加工好的塑料垫片和塑料管,塑料管套装在U型锚固环的两侧,塑料垫片设置在U型锚固环的底部;步骤二,在塑料垫片和塑料管接口处用胶带缠绕封堵;
步骤三,在混凝土板底层钢筋铺设完成后,将以上加工好的锚固环放置在底层钢筋以下,并放置在锚固环锚固的位置;
步骤四,待混凝土板上层铺设完成后,调整好锚固环的位置,并将锚固环绑扎在上层钢筋上,保证稳固;
步骤五,浇筑混凝土时,随时纠正锚固环位置,保证位置正确,不偏不斜;
步骤六,拆除悬挑型钢后,左右轻轻且均匀敲击锚固环上部两个端头,使绑扎扎丝断开,继续轻轻且均匀敲击锚固环两个端头,使锚固环从混凝土板底部掉下;
步骤七,将混凝土板上锚固环留下的孔洞吹扫干净,用水冲洗干净,固定吊模,再次用水冲洗,并浇筑高一等级微膨胀细石混凝土,并用细钢筋头振捣密实,待细石混凝土强度达到约50%时,拆除吊模。
本发明是在锚固环底部和中部加设塑料包裹,浇筑混凝土时将锚固环与混凝土隔离开,在拆除时,可将锚固环完整的拆除下来,以便重复利用,既节约了钢材,、又降低了施工成本,锚固环在混凝土板上留下的孔洞需及时修补,最大限度保证混凝土板完整。
具体实施方式
本发明一种悬挑脚手架的U型锚固环施工方法,它包括:
步骤一,在定型加工好的U型锚固环上安装加工好的塑料垫片和塑料管,塑料管套装在U型锚固环的两侧,塑料垫片设置在U型锚固环的底部;步骤二,在塑料垫片和塑料管接口处用胶带缠绕封堵;
步骤三,在混凝土板底层钢筋铺设完成后,将以上加工好的锚固环放置在底层钢筋以下,并放置在锚固环锚固的位置;
步骤四,待混凝土板上层铺设完成后,调整好锚固环的位置,并将锚固环绑扎在上层钢筋上,保证稳固;
步骤五,浇筑混凝土时,随时纠正锚固环位置,保证位置正确,不偏不斜;
步骤六,拆除悬挑型钢后,左右轻轻且均匀敲击锚固环上部两个端头,使绑扎扎丝断开,继续轻轻且均匀敲击锚固环两个端头,使锚固环从混凝土板底部掉下;
步骤七,将混凝土板上锚固环留下的孔洞吹扫干净,用水冲洗干净,固定吊模,再次用水冲洗,并浇筑高一等级微膨胀细石混凝土,并用细钢筋头振捣密实,待细石混凝土强度达到约50%时,拆除吊模。
Claims (1)
1.一种悬挑脚手架的U型锚固环施工方法,其特征在于,它包括:
步骤一,在定型加工好的U型锚固环上安装加工好的塑料垫片和塑料管,塑料管套装在U型锚固环的两侧,塑料垫片设置在U型锚固环的底部;步骤二,在塑料垫片和塑料管接口处用胶带缠绕封堵;
步骤三,在混凝土板底层钢筋铺设完成后,将以上加工好的锚固环放置在底层钢筋以下,并放置在锚固环锚固的位置;
步骤四,待混凝土板上层铺设完成后,调整好锚固环的位置,并将锚固环绑扎在上层钢筋上,保证稳固;
步骤五,浇筑混凝土时,随时纠正锚固环位置,保证位置正确,不偏不斜;
步骤六,拆除悬挑型钢后,左右轻轻且均匀敲击锚固环上部两个端头,使绑扎扎丝断开,继续轻轻且均匀敲击锚固环两个端头,使锚固环从混凝土板底部掉下;
步骤七,将混凝土板上锚固环留下的孔洞吹扫干净,用水冲洗干净,固定吊模,再次用水冲洗,并浇筑高一等级微膨胀细石混凝土,并用细钢筋头振捣密实,待细石混凝土强度达到约50%时,拆除吊模。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610440731.7A CN107524288A (zh) | 2016-06-20 | 2016-06-20 | 悬挑脚手架的u型锚固环施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610440731.7A CN107524288A (zh) | 2016-06-20 | 2016-06-20 | 悬挑脚手架的u型锚固环施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107524288A true CN107524288A (zh) | 2017-12-29 |
Family
ID=60734337
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610440731.7A Pending CN107524288A (zh) | 2016-06-20 | 2016-06-20 | 悬挑脚手架的u型锚固环施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107524288A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577636A (zh) * | 2018-11-29 | 2019-04-05 | 成都建工第二建筑工程有限公司 | 锚固组件、悬挑脚手架型钢锚固结构及施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203701565U (zh) * | 2014-02-08 | 2014-07-09 | 江苏中南建筑产业集团有限责任公司 | 一种可拆卸式悬挑脚手架锚环 |
CN203905511U (zh) * | 2014-06-20 | 2014-10-29 | 中建五局第三建设有限公司 | 一种可拆周转式悬挑型钢尾端固定装置 |
CN204225471U (zh) * | 2014-11-05 | 2015-03-25 | 五矿二十三冶建设集团第二工程有限公司 | 一种悬挑钢梁穿墙结构 |
CN105672645A (zh) * | 2016-03-29 | 2016-06-15 | 台州建筑安装工程公司 | 悬挑式脚手架中悬挑梁锚固结构和悬挑梁锚固施工方法 |
-
2016
- 2016-06-20 CN CN201610440731.7A patent/CN107524288A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203701565U (zh) * | 2014-02-08 | 2014-07-09 | 江苏中南建筑产业集团有限责任公司 | 一种可拆卸式悬挑脚手架锚环 |
CN203905511U (zh) * | 2014-06-20 | 2014-10-29 | 中建五局第三建设有限公司 | 一种可拆周转式悬挑型钢尾端固定装置 |
CN204225471U (zh) * | 2014-11-05 | 2015-03-25 | 五矿二十三冶建设集团第二工程有限公司 | 一种悬挑钢梁穿墙结构 |
CN105672645A (zh) * | 2016-03-29 | 2016-06-15 | 台州建筑安装工程公司 | 悬挑式脚手架中悬挑梁锚固结构和悬挑梁锚固施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577636A (zh) * | 2018-11-29 | 2019-04-05 | 成都建工第二建筑工程有限公司 | 锚固组件、悬挑脚手架型钢锚固结构及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104989102B (zh) | 一种改进的混凝土墙、柱施工方法 | |
CN103669655B (zh) | 变形缝两侧墙体混凝土浇筑施工工艺 | |
CN104727223B (zh) | 一种用于桥梁墩柱施工的环向平台及施工方法 | |
CN105239775B (zh) | 一种用于筒仓滑模施工的钢筋安装质量动态控制方法 | |
CN102134910B (zh) | 一种筒状混凝土结构倒模施工方法 | |
CN105275097A (zh) | 一种后浇带止水钢板和快易收口网安装方法 | |
CN106337391A (zh) | 高桩码头面板底部大面积破损维修施工方法 | |
CN107524288A (zh) | 悬挑脚手架的u型锚固环施工方法 | |
CN208167540U (zh) | 斜拉桥主塔与斜拉索同步施工系统 | |
KR20160119317A (ko) | 배수로 시공설비 및 배수로 시공방법 | |
CN106760004A (zh) | 一种导流槽结构表面均布插筋的施工方法 | |
CN107988918A (zh) | 混凝土卷模施工装置 | |
CN102002953A (zh) | 一种基坑围护肋板换撑的方法 | |
CN106284428A (zh) | 一种建筑结构后浇带的混凝土立柱支撑方法 | |
CN113006377B (zh) | 构造柱钢筋施工方法 | |
CN106284982A (zh) | 一种钢筋混凝土楼板后浇带模板支撑方法 | |
CN103291000A (zh) | 工具式钢筋支架及其悬挂楼板负弯矩钢筋的施工方法 | |
CN107461209A (zh) | 一种隧道工程内中隔墙顶部预留钢筋的施工方法 | |
CN107297811B (zh) | 一种用拱形构件预应力施加装置制混凝土的方法 | |
CN207597882U (zh) | 一种适用于深窄混凝土结构部位施工的振捣器 | |
KR100966639B1 (ko) | 맨홀보수공법 | |
CN108035342A (zh) | 灌注桩桩头施工方法 | |
CN108896371A (zh) | 一种新旧混凝土结合面斜剪试验件制作工装及制作方法 | |
CN209703837U (zh) | 一种筒仓钢筋保护层限位装置 | |
CN203080429U (zh) | 一种桥梁断柱顶升用墩柱续接施工结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171229 |
|
RJ01 | Rejection of invention patent application after publication |