CN107491619A - A kind of old project steel construction that changes based on BIM technology positions construction method for hanging - Google Patents

A kind of old project steel construction that changes based on BIM technology positions construction method for hanging Download PDF

Info

Publication number
CN107491619A
CN107491619A CN201710765623.1A CN201710765623A CN107491619A CN 107491619 A CN107491619 A CN 107491619A CN 201710765623 A CN201710765623 A CN 201710765623A CN 107491619 A CN107491619 A CN 107491619A
Authority
CN
China
Prior art keywords
construction
steel
bim
old
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710765623.1A
Other languages
Chinese (zh)
Inventor
聂国强
李松晏
梁森
杨忠源
蔡泽民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd, China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201710765623.1A priority Critical patent/CN107491619A/en
Publication of CN107491619A publication Critical patent/CN107491619A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Architecture (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • General Physics & Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention provides a kind of old project steel construction that changes based on BIM technology and positions construction method for hanging, BIM threedimensional models are established according to newly-built steel construction drawing, the old construction pedestals in review scene position and by data inputting established model, the optimization to steel structure support seat positioning is completed using BIM means and component model is deepened, it is set very to agree with live reality, steel structural rod piece is instructed to process, installation, simultaneously steel structure hoisting scheme comparison is carried out using BIM technology, real-time buildability simulation is carried out to the emphasis in project and difficult point part, ensure the feasibility of arrangement and method for construction, reasonability, optimality, determine steel member unit factorial praluction, burst construction method of installation, realize rapid construction.Construction of Steel Structure overall process is simulated, realizes rapid construction.The invention belongs to the steel pipe truss structures system technical field of construction of public building and civil buildings.

Description

A kind of old project steel construction that changes based on BIM technology positions construction method for hanging
Technical field
The present invention relates to it is a kind of it is old change project steel construction positioning construction method for hanging, belong to public building and civil buildings Steel pipe truss structures system technical field of construction.
Background technology
At present, in practice of construction, due to reasons such as constructions, original structure pedestal is sung with old drawing can be present necessarily partially Difference, such as:Former stadiums concrete structure is molded, due to reasons such as constructions, the positioning of its construction pedestals and old structure chart Paper has deviation, and drawing adjustment amount is big, and in general Construction of Steel Structure is using component Site Welding, assembly, causes that welding capacity is big, applies The shortcomings of work cycle is long, quality safety risk is big.
The content of the invention
It is an object of the invention to:A kind of old project steel construction that changes based on BIM technology is provided and positions construction method for hanging, Construction of Steel Structure overall process is simulated, realizes rapid construction.
To solve the above problems, intend positioning lifting construction using such a old project steel construction that changes based on BIM technology Method, it is specific as follows:
BIM threedimensional models are established according to newly-built steel construction drawing, the old construction pedestals positioning in review scene and by data inputting In established model, complete the optimization to steel structure support seat positioning using BIM means and component model is deepened, make itself and live actual hundred Divide hundred to agree with, instruct steel structural rod piece processing, installation, while steel structure hoisting scheme comparison is carried out using BIM technology, to project In emphasis and difficult point part carry out real-time buildability simulation, it is ensured that feasibility, reasonability, the optimality of arrangement and method for construction, it is determined that Steel member unit factorial praluction, burst construction method of installation, realize rapid construction.
Utilize the maximum of BIM finite element analyses element displacement in whole hoisting process, in allowed band, most final position It is reasonable to move in design offset deviation 0.3%.
Compared with prior art, advantage of the present invention is as follows:
1st, secondary in-depth is carried out to base stand location and rod size using BIM means, effectively helps workmen to find sky early Between conflict, successfully solve to add using old structure as bearing and build positioning difficulty during steel structure truss;
2nd, using BIM technology construction simulation process, steel member unit factorial praluction, burst installation is realized, realizes rapid construction, And work progress difficulty reduces, construction quality is controllable, and the construction period shortens, and saves construction cost.
Embodiment
In order that the object of the invention, technical scheme and advantage are clearer, the present invention is made into one with reference to embodiment The detailed description of step.
Embodiment:
The present embodiment provides a kind of old project steel construction that changes based on BIM technology and positions construction method for hanging
1st, BIM threedimensional models are established according to steel construction drawing, review is measured to scene old construction pedestals positioning and by again In the built BIM models of Nuclear Data typing, secondary in-depth is carried out to steel construction base stand location in model and scantling;
2nd, using BIM optimization designs, steel structural roof segmentation position and interface shape are determined.According to specific constructive form and lifting Unit form is in suitable installation unit node arranged beneath strong point position;
3rd, simulated by construction speed(4D), carry out real-time buildability simulation, find Steric clashes early, it is determined that lifting subregion and Construction;
4th, installation on ground improves the installation accuracy of steel construction into lifting elements;
5th, " sharding unit " lifts, and realizes rapid construction, it is ensured that the close design displacement of hoisting process final mean annual increment movement.

Claims (2)

1. a kind of old project steel construction that changes based on BIM technology positions construction method for hanging, it is characterised in that specific method is such as Under:BIM threedimensional models are established according to newly-built steel construction drawing, the old construction pedestals positioning in review scene is simultaneously built by data inputting In model, complete the optimization to steel structure support seat positioning using BIM means and component model is deepened, make itself and the actual percentage in scene Hundred agree with, and instruct steel structural rod piece processing, installation, while carry out steel structure hoisting scheme comparison using BIM technology, in project Emphasis and difficult point part carry out real-time buildability simulation, determine steel member unit factorial praluction, burst construction method of installation, Realize rapid construction.
2. a kind of old project steel construction that changes based on BIM technology positions construction method for hanging, its feature according to claim 1 It is:Utilize the maximum of BIM finite element analyses element displacement in whole hoisting process, in allowed band, final mean annual increment movement It is reasonable in design offset deviation 0.3%.
CN201710765623.1A 2017-08-30 2017-08-30 A kind of old project steel construction that changes based on BIM technology positions construction method for hanging Pending CN107491619A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710765623.1A CN107491619A (en) 2017-08-30 2017-08-30 A kind of old project steel construction that changes based on BIM technology positions construction method for hanging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710765623.1A CN107491619A (en) 2017-08-30 2017-08-30 A kind of old project steel construction that changes based on BIM technology positions construction method for hanging

Publications (1)

Publication Number Publication Date
CN107491619A true CN107491619A (en) 2017-12-19

Family

ID=60651181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710765623.1A Pending CN107491619A (en) 2017-08-30 2017-08-30 A kind of old project steel construction that changes based on BIM technology positions construction method for hanging

Country Status (1)

Country Link
CN (1) CN107491619A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108197356A (en) * 2017-12-20 2018-06-22 中国铁路总公司 A kind of four electric facility location optimization method and devices based on BIM technology
CN108959708A (en) * 2018-06-01 2018-12-07 中国十七冶集团有限公司 A kind of steel construction integral hoisting construction optimization method
CN109002670A (en) * 2018-09-29 2018-12-14 国际竹藤中心 A kind of composite bamboo-timber structure optimum design method based on BIM
CN109255145A (en) * 2018-07-21 2019-01-22 中铁十八局集团有限公司 A kind of steel girder bridge simulative construction method of the three-dimensional scenic based on BIM
CN110069882A (en) * 2019-04-30 2019-07-30 中国十七冶集团有限公司 A kind of poly-machine lifting crane lifting optimization method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012860A (en) * 2017-06-02 2017-08-04 中国十七冶集团有限公司 A kind of construction method of the post Single Pile joint bar positioner based on BIM technology

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012860A (en) * 2017-06-02 2017-08-04 中国十七冶集团有限公司 A kind of construction method of the post Single Pile joint bar positioner based on BIM technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李凯 等: ""BIM 技术在钢结构施工方案优选中的应用"", 《施工技术》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108197356A (en) * 2017-12-20 2018-06-22 中国铁路总公司 A kind of four electric facility location optimization method and devices based on BIM technology
CN108959708A (en) * 2018-06-01 2018-12-07 中国十七冶集团有限公司 A kind of steel construction integral hoisting construction optimization method
CN109255145A (en) * 2018-07-21 2019-01-22 中铁十八局集团有限公司 A kind of steel girder bridge simulative construction method of the three-dimensional scenic based on BIM
CN109255145B (en) * 2018-07-21 2023-04-18 中铁十八局集团有限公司 BIM-based three-dimensional scene steel truss bridge simulation construction method
CN109002670A (en) * 2018-09-29 2018-12-14 国际竹藤中心 A kind of composite bamboo-timber structure optimum design method based on BIM
CN109002670B (en) * 2018-09-29 2023-08-25 国际竹藤中心 BIM-based bamboo-wood composite structure optimization design method
CN110069882A (en) * 2019-04-30 2019-07-30 中国十七冶集团有限公司 A kind of poly-machine lifting crane lifting optimization method

Similar Documents

Publication Publication Date Title
CN107491619A (en) A kind of old project steel construction that changes based on BIM technology positions construction method for hanging
CN111364615B (en) Mounting method of special-shaped and curved surface suspension type steel structure system
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN114086669B (en) Modularized rapid construction method for large-scale space special-shaped curved surface steel net rack
CN104631684A (en) Single-layer latticed shell steel structure roof system based on concrete building and assembling method of single-layer latticed shell steel structure roof system based on concrete building
CN104674665B (en) Large-spatial structures vestibule bridge installation method
CN107299762B (en) Concrete pouring method based on BIM
CN207079729U (en) Steel structure net rack jacking apparatus
CN104652827A (en) Three-stage-relay hoisting construction method for large-span arc-shaped truss
CN204899948U (en) Cable groove formworking jumbo
CN107460889A (en) Integral movable support formwork in underground comprehensive pipe gallery construction and construction method thereof
CN114718365A (en) BIM-based three-dimensional curved surface space grid structure modular construction method
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN106760559B (en) The installation method of hemispherical spherical crown reticulated shell
CN204356970U (en) Based on the single-layer lattice shell steel house plane system of concrete construction
CN110565856B (en) Quick installation method for double-curved-surface metal plate curtain wall
CN100570757C (en) The modular construction method that is used for nuclear island of nuclear power station
CN106544959A (en) The construction method of the lifting sections of the king-tower containing saddle and bridge main tower saddle
CN110172922A (en) A kind of environmentally friendly downlink Self-propelled steel trestle work structure construction method
CN101736925B (en) Modular construction method for nuclear island of nuclear power station
CN101752017B (en) Modularization construction method for nuclear power station nuclear island
CN113323153A (en) Bending-twisting aluminum alloy structure in existing complex space and construction method
CN105089276B (en) A kind of construction method of the large area concrete plate of application floor elevation control instrument
CN114941433B (en) Construction method of high-weight ship type daylighting roof steel structure
CN115637809A (en) Assembly type construction method for indoor high and large space modeling aluminum plate ceiling of pseudo-classic building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171219

RJ01 Rejection of invention patent application after publication