CN107489214A - 核心筒竖向与水平结构的平层施工方法 - Google Patents

核心筒竖向与水平结构的平层施工方法 Download PDF

Info

Publication number
CN107489214A
CN107489214A CN201710513814.9A CN201710513814A CN107489214A CN 107489214 A CN107489214 A CN 107489214A CN 201710513814 A CN201710513814 A CN 201710513814A CN 107489214 A CN107489214 A CN 107489214A
Authority
CN
China
Prior art keywords
core walls
inner cylinder
walls structure
vertical
outer barrel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710513814.9A
Other languages
English (en)
Inventor
边文栋
尹永亮
张喜平
王海波
吴先淑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Qianhai Techen Technology Co Ltd
Shenzhen Techen Technology Co Ltd
Original Assignee
Shenzhen Qianhai Techen Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Qianhai Techen Technology Co Ltd filed Critical Shenzhen Qianhai Techen Technology Co Ltd
Priority to CN201710513814.9A priority Critical patent/CN107489214A/zh
Publication of CN107489214A publication Critical patent/CN107489214A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种核心筒竖向与水平结构的平层施工方法,包括:步骤1、绑扎竖向墙柱钢筋,预埋竖向构件;步骤2、提升内筒爬模架体;步骤3、安装核心筒的内筒铝模,穿对拉螺杆;步骤4、安装板水平模板;步骤5、提升外筒爬模架体,通过对拉螺杆将内筒铝模和外筒铝模拉紧固定;步骤6、绑扎梁钢筋和板钢筋;步骤7、拼装梁竖向模板,调平梁竖向模板的水平高度并加固;步骤8、浇筑混凝土。本发明具有成本低、工期短及质量高等优点。

Description

核心筒竖向与水平结构的平层施工方法
技术领域
本发明涉及核心筒施工方法技术领域,尤其涉及一种核心筒竖向与水平结构的平层施工方法。
背景技术
目前,随着商业用地越来越少,人们开始向地上索取空间,从而导致商业建筑越来越高。由于超高层结构高度的不断增加,现有的结构核心筒施工基本采用顶模施工、爬模施工、滑膜施工等施工工艺,这几种施工工艺都是采用液压油缸提供动力顶升架体,工艺特点是水平结构与竖向结构分开施工,这种施工方式一方面会导致结构施工的费用增加、工期拉长,另一方面由于施工工作面比较多,从而导致安全风险高。
发明内容
为了解决现有技术中存在的上述缺陷,本发明提出一种核心筒竖向与水平结构的平层施工方法,该平层施工方法不仅能实现快速施工、缩短施工时间,还能提高施工质量。
本发明采用的技术方案是,设计一种核心筒竖向与水平结构的平层施工方法,包括:
步骤1、绑扎核心筒的竖向墙柱钢筋,将竖向构件预埋在核心筒的墙体内;
步骤2、提升核心筒的内筒爬模架体;
步骤3、安装核心筒的内筒铝模,内筒铝模安装好后穿设对拉螺杆;
步骤4、安装板水平模板;
步骤5、提升核心筒的外筒爬模架体,安装核心筒的外筒铝模,通过对拉螺杆将内筒铝模和外筒铝模拉紧固定;
步骤6、绑扎核心筒的梁钢筋和板钢筋;
步骤7、拼装梁竖向模板,调平梁竖向模板的水平高度并加固;
步骤8、浇筑混凝土。
其中,步骤1中竖向构件包含水电、塔吊、爬模与钢结构等的预埋件。
与现有技术相比,本发明对核心筒的水平结构与竖向结构进行一次施工,不仅能够节省一定量的预埋、植筋、剔凿、防护成本,还能减少植筋、施工缝处理等因素引起的质量隐患,大大提供施工效率。
附图说明
下面结合实施例和附图对本发明进行详细说明,其中:
图1是本发明中核心筒整体的结构示意图;
图2是本发明中内筒爬模的结构示意图;
图3是图1中内筒爬模向上提升一层后的状态示意图;
图4是本发明中本发明中外筒爬模的结构示意图;
图5是本发明中图2中A处的放大示意图。
具体实施方式
如图1所示,实施本发明提出的平层施工方法之前,需在核心筒1内部架设内筒爬模2、在核心筒1外部架设外筒爬模3。
如图2、3所示,内筒爬模2包含:内筒爬模架体21、设于内筒爬模架体21上的内筒施工平台22、水平并排设于内筒施工平台22下方的至少两个内筒挂模组件23、用于提升内筒爬模架体21的内筒提升系统24,内筒爬模架体21的顶部两层平台为内筒施工平台22,内筒挂模组件23安装在位于第二层内筒施工平台的下方。内筒爬模架体21上靠近核心筒1墙体内侧的一面竖向间隔设有附墙滑轮25,内筒提升系统24向上拉动内筒爬模架体21时,附墙滑轮25沿核心筒1墙体滚动,内筒爬模架体21上远离核心筒1墙体的一面竖向设有梁侧滑轨26,该面还竖向间隔设有附梁支腿27。
如图4所示,外筒爬模3包含:外筒爬模架体31、设于外筒爬模架体31上的外筒施工平台32、水平并排安装于外筒施工平台32下方的至少两个外筒挂模组件33、用于提升外筒爬模架体31的外筒提升系统34,外筒爬模架体31的顶部两层平台为外筒施工平台32,外筒挂模组件33安装在位于第二层内筒施工平台的下方,外筒爬模架体31上靠近核心筒1墙体外侧的一面竖向间隔设有附墙支腿35。
其中,内筒挂模组件23和外筒挂模组件33的结构相同,分别用来悬挂安装内筒铝模4和外筒铝模5。以内筒挂模组件为例,如图5所示,其由移动小车231、手拉葫芦232及滑轨233组成,滑轨233与核心筒1墙体呈相互垂直的状态,移动小车231可沿滑轨233前后移动,内筒铝模4和外筒铝模5上均设有吊钩,手拉葫芦232的一端固定在移动小车231上、另一端钩在吊钩上。在使用过程中通过移动小车231的前后移动达到合模和退模的使用要求,同时可通过手拉葫芦232来调整铝模的高度。
本发明提出的平层施工方法包括:
步骤1、人工绑扎核心筒的竖向墙柱钢筋11,将竖向构件预埋在核心筒1的墙体内,竖向构件包含水电、塔吊及爬模的预埋件等;
步骤2、利用内筒提升系统24提升核心筒的内筒爬模架体21;
步骤3、利用内筒挂模组件23将内筒铝模4移动到指定位置,将内筒铝模4固定在该指定位置,内筒铝模4安装好后穿设对拉螺杆;
步骤4、安装板水平模板;
步骤5、利用外筒提升系统34提升核心筒的外筒爬模架体31,利用外筒挂模组件33将外筒铝模5移动到指定位置,通过对拉螺杆将内筒铝模4和外筒铝模5拉紧固定;
步骤6、人工绑扎核心筒1的梁钢筋和板钢筋,在实际操作中,梁钢筋也可以放在步骤1中进行绑扎,可根据实际施工需要灵活选择;
步骤7、拼装梁竖向模板,调平梁竖向模板的水平高度并加固;
步骤8、浇筑混凝土,混凝土凝固后形成浇筑层12。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。

Claims (2)

1.一种核心筒竖向与水平结构的平层施工方法,其特征在于,包括:
步骤1、绑扎核心筒的竖向墙柱钢筋,将竖向构件预埋在核心筒的墙体内;
步骤2、提升核心筒的内筒爬模架体;
步骤3、安装核心筒的内筒铝模,内筒铝模安装好后穿设对拉螺杆;
步骤4、安装板水平模板;
步骤5、提升核心筒的外筒爬模架体,安装核心筒的外筒铝模,通过对拉螺杆将内筒铝模和外筒铝模拉紧固定;
步骤6、绑扎核心筒的梁钢筋和板钢筋;
步骤7、拼装梁竖向模板,调平梁竖向模板的水平高度并加固;
步骤8、浇筑混凝土。
2.如权利要求1所述的平层施工方法,其特征在于,所述步骤1中竖向构件包含水电、塔吊及爬模的预埋件。
CN201710513814.9A 2017-06-29 2017-06-29 核心筒竖向与水平结构的平层施工方法 Pending CN107489214A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710513814.9A CN107489214A (zh) 2017-06-29 2017-06-29 核心筒竖向与水平结构的平层施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710513814.9A CN107489214A (zh) 2017-06-29 2017-06-29 核心筒竖向与水平结构的平层施工方法

Publications (1)

Publication Number Publication Date
CN107489214A true CN107489214A (zh) 2017-12-19

Family

ID=60643452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710513814.9A Pending CN107489214A (zh) 2017-06-29 2017-06-29 核心筒竖向与水平结构的平层施工方法

Country Status (1)

Country Link
CN (1) CN107489214A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593128A (zh) * 2019-10-14 2019-12-20 中交第二航务工程局有限公司 一种混凝土桥塔筑塔方法
CN113235913A (zh) * 2021-05-13 2021-08-10 中建三局第三建设工程有限责任公司 建筑竖向模板悬挂整拼整提的施工设备及方法
CN115288407A (zh) * 2022-07-25 2022-11-04 上海建工集团股份有限公司 一种超高层核心筒水平结构紧跟竖向结构的施工方法
CN116163523A (zh) * 2022-12-15 2023-05-26 中国建筑第八工程局有限公司 爬模拼装与核心筒同步施工方法

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2275615Y (zh) * 1996-01-25 1998-03-04 张良杰 液压爬升模板装置
CN1904291A (zh) * 2005-07-27 2007-01-31 深圳市特辰升降架工程有限公司 一种整体爬模平台系统
CN201762974U (zh) * 2010-07-29 2011-03-16 中建三局建设工程股份有限公司 核心筒内上下水平结构同时施工体系
CN103806645A (zh) * 2014-02-18 2014-05-21 广东信海建筑有限公司 一种具有良好抗风防火性能的轻型智能液压爬模装置
CN104314304A (zh) * 2014-10-23 2015-01-28 中建三局第一建设工程有限责任公司 一种外钢内铝外爬内翻的综合模架体系
CN205134939U (zh) * 2015-11-06 2016-04-06 中建三局第三建设工程有限责任公司 一种适用于核心筒内侧空间狭小区域的液压爬模系统
CN106400951A (zh) * 2016-10-10 2017-02-15 中国建筑第八工程局有限公司 一种超高层建筑的水平与竖向结构同步施工方法
CN106437130A (zh) * 2016-10-10 2017-02-22 中国建筑第八工程局有限公司 一种用于超高层建筑施工的内顶外爬式模架施工平台
CN106869489A (zh) * 2017-03-21 2017-06-20 中建三局第建设工程有限责任公司 超高层核心筒水平与竖向同步施工顶模系统及施工方法

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2275615Y (zh) * 1996-01-25 1998-03-04 张良杰 液压爬升模板装置
CN1904291A (zh) * 2005-07-27 2007-01-31 深圳市特辰升降架工程有限公司 一种整体爬模平台系统
CN201762974U (zh) * 2010-07-29 2011-03-16 中建三局建设工程股份有限公司 核心筒内上下水平结构同时施工体系
CN103806645A (zh) * 2014-02-18 2014-05-21 广东信海建筑有限公司 一种具有良好抗风防火性能的轻型智能液压爬模装置
CN104314304A (zh) * 2014-10-23 2015-01-28 中建三局第一建设工程有限责任公司 一种外钢内铝外爬内翻的综合模架体系
CN205134939U (zh) * 2015-11-06 2016-04-06 中建三局第三建设工程有限责任公司 一种适用于核心筒内侧空间狭小区域的液压爬模系统
CN106400951A (zh) * 2016-10-10 2017-02-15 中国建筑第八工程局有限公司 一种超高层建筑的水平与竖向结构同步施工方法
CN106437130A (zh) * 2016-10-10 2017-02-22 中国建筑第八工程局有限公司 一种用于超高层建筑施工的内顶外爬式模架施工平台
CN106869489A (zh) * 2017-03-21 2017-06-20 中建三局第建设工程有限责任公司 超高层核心筒水平与竖向同步施工顶模系统及施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
何昌杰等: "铝合金模板内支外爬体系在超高层建筑核心筒结构施工中的应用", 《建筑施工》 *
北京土木建筑学会: "《钢结构工程施工组织设计实例》", 31 August 2006, 中国计划出版社 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593128A (zh) * 2019-10-14 2019-12-20 中交第二航务工程局有限公司 一种混凝土桥塔筑塔方法
CN110593128B (zh) * 2019-10-14 2021-12-17 中交第二航务工程局有限公司 一种混凝土桥塔筑塔方法
CN113235913A (zh) * 2021-05-13 2021-08-10 中建三局第三建设工程有限责任公司 建筑竖向模板悬挂整拼整提的施工设备及方法
CN115288407A (zh) * 2022-07-25 2022-11-04 上海建工集团股份有限公司 一种超高层核心筒水平结构紧跟竖向结构的施工方法
CN115288407B (zh) * 2022-07-25 2023-08-22 上海建工集团股份有限公司 一种超高层核心筒水平结构紧跟竖向结构的施工方法
CN116163523A (zh) * 2022-12-15 2023-05-26 中国建筑第八工程局有限公司 爬模拼装与核心筒同步施工方法

Similar Documents

Publication Publication Date Title
CN106812120B (zh) 液压自升桁架式悬臂重型拱坝模板系统
EP3851618A1 (en) Device for alternately jacking added storey of building with high-strength concrete columns and steel slideways and construction method therefor
CN108033367B (zh) 一种钢柱筒架交替支撑式钢平台与塔吊同步提升装置及其提升方法
CN110396941B (zh) 一种桥梁墩柱施工系统及施工方法
CN102677889A (zh) 钢柱筒架交替支撑整体爬升钢平台模架体系及施工方法
CN205134939U (zh) 一种适用于核心筒内侧空间狭小区域的液压爬模系统
CN104878766A (zh) 一种长边坡护坡混凝土连续快速浇筑拉模体系及施工方法
CN108560992B (zh) 高耸构筑物的施工设备及砼浇筑施工方法
CN113235472A (zh) 一种盖板涵混凝土浇筑台车
CN206110656U (zh) 电梯井可伸缩折叠式整体提升筒模
CN107489214A (zh) 核心筒竖向与水平结构的平层施工方法
CN109184259B (zh) 建筑物的滑移施工技术
CN102733608B (zh) 一种造粒塔喷头层施工方法
CN108118620B (zh) 用于桥塔施工的整体自爬式集成平台及其施工方法
CN102286932B (zh) 移动模架桥台后方拼装自行上桥施工方法
CN109403622A (zh) 一种轨道自提升式悬挂可调平吊模系统及其施工方法
CN103774841A (zh) 轨道式滑模装置
CN109184190A (zh) 爬升与承载一体化的梁式液压爬升平台及其安装方法
CN214993219U (zh) 一种盖板涵混凝土浇筑台车
CN110847113A (zh) 基于滑移式模架的现浇深圆弧型防浪墙施工方法
CN202227365U (zh) 地下连续墙导墙移动模架
CN116537071B (zh) 一种液压顶升整体式钢架平台及其翻模施工方法
CN202064281U (zh) 一种滑模模架
CN105887884A (zh) 一种单侧式岩锚梁混凝土浇筑台车
CN202830889U (zh) 轨道式滑模装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171219