CN107342551A - For spool to be fixed on to the positioner and its localization method of line box - Google Patents

For spool to be fixed on to the positioner and its localization method of line box Download PDF

Info

Publication number
CN107342551A
CN107342551A CN201710562052.1A CN201710562052A CN107342551A CN 107342551 A CN107342551 A CN 107342551A CN 201710562052 A CN201710562052 A CN 201710562052A CN 107342551 A CN107342551 A CN 107342551A
Authority
CN
China
Prior art keywords
spool
line box
fixed
sleeve pipe
positioner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710562052.1A
Other languages
Chinese (zh)
Other versions
CN107342551B (en
Inventor
陈�胜
牛红梅
张禄平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201710562052.1A priority Critical patent/CN107342551B/en
Publication of CN107342551A publication Critical patent/CN107342551A/en
Application granted granted Critical
Publication of CN107342551B publication Critical patent/CN107342551B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling

Abstract

The present invention relates to a kind of positioner and its localization method for being used to for spool to be fixed on line box, wherein positioner includes:Sleeve pipe that is vertically arranged and being adapted with line box;At least one limiting plate, it is vertical to be located in sleeve pipe and be correspondingly arranged at the side in line box with spool hole, it is installed with gap between limiting plate and the side wall of corresponding sleeve pipe;And at least one spool location structure for being perpendicularly fixed at cannula tip, formed with the support groove for placing spool on spool location structure;Line box when in use, is sheathed on limiting plate and is partially disposed in gap by positioner, and the spool in support groove is inserted in corresponding spool hole and fixed, it is achieved thereby that spool is perpendicularly fixed at line box.The line box and the qualification rate of the perpendicularity of spool that present invention positioning is completed are high, and quality is good, and efficiency of construction is high, strong applicability, and boundary of works area is wide.

Description

For spool to be fixed on to the positioner and its localization method of line box
Technical field
The present invention relates to the realm of building construction, espespecially a kind of positioner and its positioning for being used to for spool to be fixed on line box Method.
Background technology
In architectural electricity installing area, pre-buried electric pipeline has been an indispensable part in architectural engineering, and The most widely used tubing of set aside pre-embedded pipeline is more than wall thickness 2.8mm welded still pipe in electromechanical installation, pre- to make It is reliable to bury electric steel pipe ground connection, code requirement connects reliable bridging ground wire between spool.Cable laying operation on the spot at the construction field (site) When, it is necessary to spool is fixedly welded on into line box, so as to which electric pipeline wears connection from spool and line box.But constructing , it is necessary to which pre-buried line box is very more in journey, spool is fixedly welded in line box in the way of measurement size or range estimation, meeting There is out of plumb between spool and line box, the skimble-scamble problem in position of the spool in each line box, spool is difficult to accurate positioning, Welding is wasted time and energy, it is difficult to ensures construction quality and progress, efficiency of construction is low.
The content of the invention
A kind of the defects of it is an object of the invention to overcome prior art, there is provided positioning for being used to for spool to be fixed on line box Device and its localization method, solution is difficult to ensure that in the prior art is fixed on spool vertical welding at the uniform location in line box The problem of.
Realizing the technical scheme of above-mentioned purpose is:
The present invention provides a kind of positioner for being used to for spool to be fixed on line box, including:
Sleeve pipe that is vertically arranged and being adapted with line box;
At least one limiting plate, it is vertical to be located in described sleeve pipe and be correspondingly arranged in the line box one with spool hole Gap is installed between the side wall of side, the limiting plate and corresponding described sleeve pipe;And
At least one spool location structure being perpendicularly fixed at the top of described sleeve pipe, on the spool location structure formed with Support groove for placing spool;
Line box when in use, is sheathed on the limiting plate and is partially disposed in the gap by the positioner, by institute State the spool in support groove to be inserted in corresponding spool hole and fix, it is achieved thereby that the spool is perpendicularly fixed at the line Box.
The present invention be used to spool being fixed on the positioner of line box further improvement is that, the top sides of described sleeve pipe Edge opens up jagged, and the end of the spool location structure is fixed in the breach and perpendicular to described sleeve pipe.
The present invention be used to spool being fixed on the positioner of line box further improvement is that, the spool location structure For L-type plate, the breach is right-angle notch.
The present invention be used to spool being fixed on the positioner of line box further improvement is that, the spool location structure For arc plate, the breach is arc notch.
The present invention be used to spool being fixed on the positioner of line box further improvement is that, in addition to be located at the set The bedplate of bottom of the tube, the limiting plate, which erects, is fixed on the bedplate.
The present invention be used to spool being fixed on the positioner of line box further improvement is that, the spool location structure Close described sleeve pipe end height be less than away from described sleeve pipe end height.
Present invention also offers a kind of localization method that spool is perpendicularly fixed to line box using above-mentioned positioner, including Following steps:
Spool is placed in the support groove of spool location structure;
Line box is sheathed on the limiting plate and is partially disposed in the gap;And
Spool in the support groove is inserted in corresponding spool hole and fixed.
The present invention it is localization method further improvement is that, in addition to:
Earthing jumper is provided, the earthing jumper is fixed on to two spools in the line box and adjacent On.
The present invention it is localization method further improvement is that, in addition to:
Locknut is provided, the fixed spool and the line box are connected by the locknut.
The present invention localization method further improvement is that, line box is sheathed on limiting plate and be partially disposed in it is described between When in gap, by plugging line box described in the spool support in corresponding spool hole, and coordinate the fitting of the limiting plate spacing so that The spool is vertical with the line box to be fixedly connected.
The present invention is used to for spool to be fixed on the positioner of line box and its beneficial effect of localization method:
Positioner and its localization method of the invention for spool to be fixed on to line box is by using limiting plate and sleeve pipe Side wall between be installed with gap, so as to line box is sheathed on into limiting plate and be partially disposed in gap, gap pair in positioning Line box carry out it is spacing, the problem of so as to prevent line box from offseting.At least one spool location structure is perpendicularly fixed at Sleeve pipe, formed with the support groove for placing spool on spool location structure, so as in positioning by being inserted in corresponding spool Spool support line box in hole, and coordinate the fitting of limiting plate spacing so that spool is vertical with line box to be fixedly connected.The present invention is fixed The line box and the qualification rate of the perpendicularity of spool that position is completed are high, and quality is good, and efficiency of construction is high.In electrical installation project, spool Generally there are three kinds of straight-through, threeway, four-way connected modes with line box, the present invention can be according to the connection of spool in practice of construction and line box Mode, and select the spool location structure of corresponding number, strong applicability, boundary of works area are wide.
Brief description of the drawings
Fig. 1 is the structural representation that the present invention is used to for spool to be fixed on the positioner of line box.
Fig. 2 is the localization method view that the present invention is used to for spool to be fixed on the positioner of line box.
Fig. 3 is Fig. 1 top view.
Fig. 4 is Fig. 1 front view.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, it is shown that the present invention is used for the structural representation that spool is fixed on to the positioner of line box.Refering to figure 2, it is shown that the present invention is used for the localization method view that spool is fixed on to the positioner of line box.With reference to Fig. 1 and Fig. 2 Shown, the positioner that the present invention is used to spool being fixed on line box includes:Sleeve pipe 11, at least one limiting plate 12, Yi Jizhi A few spool location structure 20, wherein, sleeve pipe 11 is vertically arranged and is adapted with line box 30;Limiting plate 12 is vertically located at set In pipe 11 and the side in line box 30 with spool hole 300 is correspondingly arranged at, limiting plate 12 staggers with corresponding spool hole 300 to be set Put, avoid blocking spool hole 300 and causing spool 40 not plug, stay and set between the side wall of limiting plate 12 and corresponding sleeve pipe 11 There is gap;Spool location structure 20 is perpendicularly fixed at the top of sleeve pipe 11, and spool location structure 20 is formed with for placing spool Support groove, line box 30 when in use, is sheathed on limiting plate 12 and is partially disposed in gap by positioner, by the line in support groove Pipe 40 is inserted in corresponding spool hole 300 and fixed, it is achieved thereby that spool 40 is perpendicularly fixed at line box 30.Present invention positioning The qualification rate of the line box of completion and the perpendicularity of spool is high, and quality is good, and efficiency of construction is high.In electrical installation project, spool with Line box generally has three kinds of straight-through, threeway, four-way connected modes, and the present invention can be according to spool in practice of construction and the connection side of line box Formula, and select the spool location structure of corresponding number, strong applicability, boundary of works area are wide.
Refering to Fig. 3, it is shown that Fig. 1 top view.Refering to Fig. 4, it is shown that Fig. 1 front view.With reference to shown in Fig. 1 to Fig. 4, In the present embodiment, the top of sleeve pipe 11 offers opening, and the shape and line box 30 of sleeve pipe 11 are consistent, the size ratio of sleeve pipe 11 The size of line box 30 is slightly larger, so as to which line box 30 is positioned in sleeve pipe 11 from the opening part above sleeve pipe 11.
As shown in figure 3, in the present embodiment, line box 30 and sleeve pipe 11 are rectangular-shape.Limiting plate 12 has four, respectively Vertically it is erected on inside sleeve pipe 11 corresponding to four sides of sleeve pipe 11.Limiting plate 12, which is correspondingly arranged in line box 30, has spool hole 300 side, limiting plate 12 and the corresponding stagger setting of spool hole 300, avoid blocking spool hole 300 and causing spool 40 can not Plug, it is preferable that the lateral cross-sectional area of sleeve pipe 11 is slightly larger than the lateral cross-sectional area of line box 30.Between limiting plate 12 and sleeve pipe 11 Thickness of the distance slightly larger than the side wall of line box 30.If the lateral cross-sectional area of sleeve pipe 11 is far longer than the lateral cross section of line box 30 Product, the distance between limiting plate 12 and sleeve pipe 11 are far longer than the thickness of the side wall of line box 30, then are plugged when by line box 30 After in sleeve pipe 11, there is larger space and can be moved for line box 30 in line box 30 and sleeve pipe 11, so as to be arranged on by spool 40 During line box 30,30 easy stress of line box and offset, and then may cause spool 40 fix position produce skew, spool 40 are not orthogonal to line box 30, influence the construction quality being arranged on spool 40 in line box 30, position inaccurate, reduce construction effect Rate.
In the present embodiment, the top of limiting plate 12 protrudes out sleeve pipe 11, so as to be plugged in by line box 30 in sleeve pipe 11 When, limiting plate 12 can abut against line box 30 and line box 30 be carried out spacing.But the height of limiting plate 12 is not limited thereto, limit Position plate 12 can abut against the madial wall of line box 30.The number and size of limiting plate 12 are not limited thereto.
As the better embodiment of the present invention, as shown in figure 4, the top edge of sleeve pipe 11 opens up jagged 110, line The end of tube positioning structure 20 is fixed in breach 110 and perpendicular to sleeve pipe 11, so as to which spool 40 is being positioned over into spool positioning When in the support groove of structure 20, spool 40 is also perpendicularly to line box 30, facilitates follow-up be welded and fixed.Simultaneously by the end of spool 40 It is arranged in the spool hole 300 of line box 30, so, spool 40 can also play a part of support limit line box 30, prevent line box 30 glide in gap, it is ensured that the stabilization of the position of line box 30, so as to ensure subsequently by spool 40 and line box 30 is connected vertically applies Working medium amount.
In the present embodiment, breach 110 needs to be located at the top edge of sleeve pipe 11, if breach 110 is opened in the side of sleeve pipe 11 The middle part of wall, then spool location structure 20 is worn after breach 110 is fixed on limiting plate 12, spool 40 is being placed on spool After on location structure 20, the side wall of sleeve pipe 11 will keep off the top for setting spool 40, so as to carry out spool 40 and line box 30 Connection.
In the present embodiment, spool location structure 20 is L-type plate, corresponds ground, breach 110 is right-angle notch.L-type Plate is made of angle steel, and upward, the upper surface of L-type plate forms support groove to angle, so as to which spool 40 is positioned on L-type plate In support groove, so as to realize to the spacing of spool 40.In another embodiment, spool location structure is arc plate, and breach is Arc notch, the upper surface of arc plate forms support groove, so as to spool 40 is positioned in the support groove on arc plate, so as to Realize to the spacing of spool 40.
As another better embodiment of the present invention, present invention additionally comprises the bedplate 13 located at the bottom of sleeve pipe 11, limit Position plate 12, which erects, is fixed on bedplate 13, so as to be fixedly connected with sleeve pipe 11 with limiting plate 12 using bedplate 13, is formed overall So as to easily move.
As another better embodiment of the present invention, as shown in Fig. 2 the end of the close sleeve pipe 11 of spool location structure 20 The height in portion is less than the height of the end away from sleeve pipe 11, so that after spool 40 is positioned on spool location structure 20, The end of the close sleeve pipe 11 of spool 40 can reveal, so as to which earthing jumper 50 is fixed in line box into 30 and adjacent Between two spools 40.Otherwise, if the end of the close sleeve pipe 11 of spool 40 is also embedded in spool location structure 20 completely, It can not then facilitate and earthing jumper 50 is welded on spool 40.Certainly, the size of spool location structure 20 can also accordingly all It is smaller so that the overall all high part of outlet-pipe location structure 20 of spool 40.
As shown in Fig. 2 by taking threeway connected mode as an example, the present invention is entered specifically using the localization method of positioner below Illustrate, comprise the following steps:
Spool 40 is placed in the support groove of spool location structure 20;
Line box 30 is sheathed on limiting plate 12 and is partially disposed in gap;And
Spool 40 in support groove is inserted in corresponding spool hole 300 and fixed.
Specifically, line box 30 is placed downwards at the upper shed at the top of sleeve pipe 11 so that the side wall and set of line box 30 The side wall of pipe 11, the angle of the angle of line box 30 and sleeve pipe 11 correspond, and the side wall corresponding inserted of line box 30 is in sleeve pipe 11 In gap.Untill line box 30 is continued to move down until into the spool hole 300 of line box 30 corresponds to spool location structure 20, with Ensure that sleeve pipe 11 and limiting plate 12 fix the position limitation of line box 30, line box 30 is not easy that off normal phenomenon is occurred by external force, protects The stability of the position of line box 30 is demonstrate,proved, subsequently spool 40 is arranged in line box 30 with facilitating.
As the present invention another better embodiment, as shown in Fig. 2 present invention additionally comprises provide earthing jumper 50, By earthing jumper 50 be fixed in line box 30 and two adjacent spools 40 on.Earthing jumper is between two metallic objects Grounded metal connector.
Specifically, simmering and bending are carried out to round steel according to the radian between line box 30 and two neighboring spool 40, formation has phase The earthing jumper 50 for the radian answered, it is easy to follow-up be welded and fixed.The earthing jumper 50 made will then have been simmered by specification It is required that it is welded in line box 30 between two neighboring spool 40.
As another better embodiment of the present invention, line box 30 is being sheathed on limiting plate 12 and is being partially disposed in gap When, by plugging the support line box 30 of spool 40 in corresponding spool hole 300, and coordinate the fitting of limiting plate 12 spacing so that line Pipe 40 is vertical with line box 30 to be fixedly connected.
Specifically, spool 40 is positioned in the support groove of spool location structure 20, and by the end of spool 40 to line box 30 movements, spool 40 and line box 30 are consolidated until the end of spool 40 is worn in the spool hole 300 of line box 30, and using locknut Get up calmly, spool 40 is vertically mounted in line box 30 so as to realize.
The present invention is used to spool being fixed on the positioner of line box and its having the beneficial effect that for localization method:
Positioner and its localization method of the invention for spool to be fixed on to line box is by using limiting plate and sleeve pipe Side wall between be installed with gap, so as to line box is sheathed on into limiting plate and be partially disposed in gap, gap pair in positioning Line box carry out it is spacing, the problem of so as to prevent line box from offseting.At least one spool location structure is perpendicularly fixed at Sleeve pipe, formed with the support groove for placing spool on spool location structure, so as in positioning by being inserted in corresponding spool Spool support line box in hole, and coordinate the fitting of limiting plate spacing so that spool is vertical with line box to be fixedly connected.The present invention is fixed The line box and the qualification rate of the perpendicularity of spool that position is completed are high, and quality is good, and efficiency of construction is high.In electrical installation project, spool Generally there are three kinds of straight-through, threeway, four-way connected modes with line box, the present invention can be according to the connection of spool in practice of construction and line box Mode, and select the spool location structure of corresponding number, strong applicability, boundary of works area are wide.
The present invention is described in detail above in association with accompanying drawing embodiment, those skilled in the art can be according to upper State and bright many variations example is made to the present invention.Thus, some details in embodiment should not form limitation of the invention, this Invention will be used as protection scope of the present invention using the scope that appended claims define.

Claims (10)

  1. A kind of 1. positioner for being used to for spool to be fixed on line box, it is characterised in that including:
    Sleeve pipe that is vertically arranged and being adapted with line box;
    At least one limiting plate, it is vertical to be located in described sleeve pipe and be correspondingly arranged at the side in the line box with spool hole, institute State and be installed with gap between the side wall of limiting plate and corresponding described sleeve pipe;And
    At least one spool location structure being perpendicularly fixed at the top of described sleeve pipe, formed with for putting on the spool location structure Put the support groove of spool;
    Line box when in use, is sheathed on the limiting plate and is partially disposed in the gap, held described by the positioner Spool in bracket is inserted in corresponding spool hole and fixed, it is achieved thereby that the spool is perpendicularly fixed at the line box.
  2. 2. the positioner as claimed in claim 1 for being used to for spool to be fixed on line box, it is characterised in that the top of described sleeve pipe Portion's edge is jagged, and the end of the spool location structure is fixed in the breach and perpendicular to described sleeve pipe.
  3. 3. the positioner as claimed in claim 2 for being used to for spool to be fixed on line box, it is characterised in that the spool positioning Structure is L-type plate, and the breach is right-angle notch.
  4. 4. the positioner as claimed in claim 2 for being used to for spool to be fixed on line box, it is characterised in that the spool positioning Structure is arc plate, and the breach is arc notch.
  5. 5. the positioner as claimed in claim 1 for being used to for spool to be fixed on line box, it is characterised in that also include being located at institute The bedplate of sleeve bottom is stated, the limiting plate, which erects, is fixed on the bedplate.
  6. 6. the positioner as claimed in claim 1 for being used to for spool to be fixed on line box, it is characterised in that the spool positioning The height of the end of the close described sleeve pipe of structure is less than the height of the end away from described sleeve pipe.
  7. 7. a kind of localization method that spool is perpendicularly fixed to line box using positioner as claimed in claim 1, its feature It is, comprises the following steps:
    Spool is placed in the support groove of spool location structure;
    Line box is sheathed on the limiting plate and is partially disposed in the gap;And
    Spool in the support groove is inserted in corresponding spool hole and fixed.
  8. 8. localization method as claimed in claim 7, it is characterised in that also include:
    There is provided earthing jumper, by the earthing jumper be fixed in the line box and two adjacent spools on.
  9. 9. localization method as claimed in claim 7, it is characterised in that also include:
    Locknut is provided, the fixed spool and the line box are connected by the locknut.
  10. 10. localization method as claimed in claim 7, it is characterised in that line box is being sheathed on limiting plate and is being partially disposed in institute When stating in gap, by plugging line box described in the spool support in corresponding spool hole, and coordinate the fitting of the limiting plate spacing, It is fixedly connected so that the spool is vertical with the line box.
CN201710562052.1A 2017-07-11 2017-07-11 For spool to be fixed on to the positioning device and its localization method of wire box Active CN107342551B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710562052.1A CN107342551B (en) 2017-07-11 2017-07-11 For spool to be fixed on to the positioning device and its localization method of wire box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710562052.1A CN107342551B (en) 2017-07-11 2017-07-11 For spool to be fixed on to the positioning device and its localization method of wire box

Publications (2)

Publication Number Publication Date
CN107342551A true CN107342551A (en) 2017-11-10
CN107342551B CN107342551B (en) 2019-03-29

Family

ID=60218664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710562052.1A Active CN107342551B (en) 2017-07-11 2017-07-11 For spool to be fixed on to the positioning device and its localization method of wire box

Country Status (1)

Country Link
CN (1) CN107342551B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110581331A (en) * 2019-08-26 2019-12-17 北京无线电测量研究所 Waveguide junction type ferrite switch
CN110970846A (en) * 2019-12-19 2020-04-07 龙游亿莱达电器有限公司 Multi-dimensional adjustable junction box

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001119828A (en) * 1999-10-19 2001-04-27 Sumitomo Electric Ind Ltd Cable pressure supply auxiliary system, cable pressure supply pipe line and pressure supply method of cable
CN202271136U (en) * 2011-08-02 2012-06-13 中国一冶集团有限公司 Quick aligning and positioning device for pipeline
CN203649759U (en) * 2014-01-10 2014-06-18 杭州萧山众汇工业电炉厂 Anti-deformation welding fixture for inner tank of electric furnace
CN204262641U (en) * 2014-11-24 2015-04-15 苏州市福迈精密机械有限公司 A kind of weld jig
CN105666016A (en) * 2016-04-19 2016-06-15 中建七局建筑装饰工程有限公司 Electric wire tube welding operation platform
CN205960574U (en) * 2016-08-23 2017-02-15 中建八局第二建设有限公司 Electrical piping terminal box standard component
CN106914725A (en) * 2017-04-01 2017-07-04 青岛圣族激光机械有限公司 A kind of motor vehicle seat backrest specific welding assambly

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001119828A (en) * 1999-10-19 2001-04-27 Sumitomo Electric Ind Ltd Cable pressure supply auxiliary system, cable pressure supply pipe line and pressure supply method of cable
CN202271136U (en) * 2011-08-02 2012-06-13 中国一冶集团有限公司 Quick aligning and positioning device for pipeline
CN203649759U (en) * 2014-01-10 2014-06-18 杭州萧山众汇工业电炉厂 Anti-deformation welding fixture for inner tank of electric furnace
CN204262641U (en) * 2014-11-24 2015-04-15 苏州市福迈精密机械有限公司 A kind of weld jig
CN105666016A (en) * 2016-04-19 2016-06-15 中建七局建筑装饰工程有限公司 Electric wire tube welding operation platform
CN205960574U (en) * 2016-08-23 2017-02-15 中建八局第二建设有限公司 Electrical piping terminal box standard component
CN106914725A (en) * 2017-04-01 2017-07-04 青岛圣族激光机械有限公司 A kind of motor vehicle seat backrest specific welding assambly

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110581331A (en) * 2019-08-26 2019-12-17 北京无线电测量研究所 Waveguide junction type ferrite switch
CN110970846A (en) * 2019-12-19 2020-04-07 龙游亿莱达电器有限公司 Multi-dimensional adjustable junction box

Also Published As

Publication number Publication date
CN107342551B (en) 2019-03-29

Similar Documents

Publication Publication Date Title
CN107342551A (en) For spool to be fixed on to the positioner and its localization method of line box
CN106049870B (en) It is a kind of to be used to secretly bury the pre-buried construction method of babinet in construction shear wall
CN105762728A (en) Method for pre-burying of strong and weak electricity box and electrical tubing
CN104294828A (en) Supporting structure of foundation pit
CN102995905A (en) Cast-in-place concrete board elevation control device and construction method
CN105666016A (en) Electric wire tube welding operation platform
CN204676925U (en) A kind of support
CN204703186U (en) A kind of pre-embedded bolt positioning installation apparatus
CN211830140U (en) Cable trench cable laying device
CN202712778U (en) Novel wire box
JP2010146938A (en) Ground electrode and method for constructing the same
CN103464539B (en) The special apparatus for bending of corner ground connection band iron
CN105071302A (en) Junction box concealed burying accurate positioning method
CN208862508U (en) A kind of connecting node of power transformation station cable poling turning position
CN203387076U (en) Embedded box installing assembly with upper adjustment mechanism and positioning adjustment device thereof
CN203383199U (en) Wellhead frame mounting guiding device
KR102074328B1 (en) Hanger for danger sign board of high voltage
CN204681026U (en) The cable fixture of cable shaft and junction, cable tunnel
CN205587881U (en) Electric spool welding operation platform
CN104278681B (en) A kind of supporting component of foundation ditch backplate
KR101293682B1 (en) Suspention method for buried structures
CN215645686U (en) Power distribution cabinet base
CN206625599U (en) A kind of roofing edge protection device
CN105019473B (en) The rear anchoring processing method of sole plate reinforcing bar and diaphram wall
CN209853508U (en) Welding machine secondary line centralized connecting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210107

Address after: No. 14701, 47 / F, unit 1, green space center, block a, northeast corner of cross between Jinye road and zhangbaer Road, Zhangba Street office, high tech Zone, Xi'an City, Shaanxi Province, 710076

Patentee after: Northwest Construction Co.,Ltd. of China Construction Eighth Engineering Bureau

Address before: 200122 Pudong New Area, Shanghai, China (Shanghai) free trade trial area 1568 Century Avenue 27

Patentee before: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION Co.,Ltd.