CN107322254A - 一种连铸机大包回转台回转轴承的快速更换方法 - Google Patents

一种连铸机大包回转台回转轴承的快速更换方法 Download PDF

Info

Publication number
CN107322254A
CN107322254A CN201710521140.7A CN201710521140A CN107322254A CN 107322254 A CN107322254 A CN 107322254A CN 201710521140 A CN201710521140 A CN 201710521140A CN 107322254 A CN107322254 A CN 107322254A
Authority
CN
China
Prior art keywords
floating bearing
continuous casting
revolving
inter
connecting bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710521140.7A
Other languages
English (en)
Inventor
裴青峰
宋文智
高健
陈棋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201710521140.7A priority Critical patent/CN107322254A/zh
Publication of CN107322254A publication Critical patent/CN107322254A/zh
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

本发明涉及工程机械的安装维护领域,具体是一种连铸机大包回转台回转轴承的快速更换方法;其特征是,包括大包回转台自身旋转,将新回转轴承放置在事故溜槽上;用连铸跨行车将预制好的临时支架,吊至回转台驱动侧;大包回转台回转轴承与底座及回转体连接螺栓拆卸,仅保留部分固定螺栓;采用连铸跨行车和钢水接受跨行车将回转体吊起,拆卸底座连接螺栓并吊离;用手拉葫芦将旧回转轴承放在临时支架上,再用手拉葫芦将新回转轴承安装在回转体上,并安装连接螺栓。本更换方法从起吊开始计算到更换完成,只需约3h,与常规更换方案相比可节省大量时间,为恢复正常生产提供有力保障。同时,与常规更换方案相比,不需使用汽车吊,可大幅度降低施工成本。

Description

一种连铸机大包回转台回转轴承的快速更换方法
技术领域
本发明涉及工程机械的安装维护领域,具体是一种连铸机大包回转台回转轴承的快速更换方法。
背景技术
连铸机大包回转台设备在连续使用5~7年后,回转轴承往往会发生磨损,表现为表面脱落,产生铁屑。回转轴承磨损后,当回转台满负荷运转时,可能导致回转台卡阻,无法继续使用。转炉炼钢车间的生产节奏很快,按照常规更换方案无法满足生产车间的需求。目前连铸机大包回转台回转轴承快速的更换技术尚不完善。
发明内容
本发明的目的在于克服现有技术的不足,提供一种连铸机大包回转台回转轴承快速更换方法;其在保证安装质量的前提下,可大幅度节省作业时间并降低施工成本。
为了达到上述目的,本发明是这样实现的:
一种连铸机大包回转台回转轴承的快速更换方法;包括
步骤1、大包回转台自身旋转,将新回转轴承放置在事故溜槽上;
步骤2、用连铸跨行车将预制好的临时支架,吊至回转台驱动侧;
步骤3、大包回转台回转轴承与底座及回转体连接螺栓拆卸,仅保留部分固定螺栓;
步骤4、采用连铸跨行车和钢水接受跨行车将回转体吊起,拆卸底座连接螺栓并吊离;
步骤5、用手拉葫芦将旧回转轴承放在临时支架上,再用手拉葫芦将新回转轴承安装在回转体上,并安装连接螺栓。
所述的连铸机大包回转台回转轴承的快速更换方法,步骤1中大包回转台旋转前,新回转轴承的“S”点,应当在纵向铸流方向侧;通过大包回转台的自身旋转,将其调整为空载回转横向中心线上。
本更换方法从起吊开始计算到更换完成,只需约3h,与常规更换方案相比可节省大量时间,为恢复正常生产提供有力保障。同时,与常规更换方案相比,不需使用汽车吊,可大幅度降低施工成本。
附图说明
图1是本发明回转轴承快速更换的示意图。
图2是本发明钢水接受跨和连铸跨行车抬吊安装的示意图。
图中:1、钢包臂、2、扁担、3、新回转轴承(旋转后位置)、4、大包回转台、5、新回转轴承(旋转前位置)、6、旧回转轴承、7、临时支架、8、事故溜槽、9、连铸跨行车、10、钢水接受跨行车、11、底座、12、回转体、13、大包回转台回转轴承、14、手拉葫芦、15、“S”点、16、铸流方向。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1、图2所示,一种连铸机大包回转台回转轴承的快速更换方法;包括
1)大包回转台4自身旋转,将新回转轴承(旋转后位置)3,放置在事故溜槽8上;
2)用连铸跨行车9,将预制好的临时支架7,吊至回转台驱动侧;
3)大包回转台回转轴承13,与底座11及回转体12连接螺栓拆卸,仅保留部分固定螺栓;
4)采用连铸跨行车9和钢水接受跨行车10,将回转体12吊起,拆卸底座连接螺栓并吊离;
5)用手拉葫芦14将旧回转轴承6放在临时支架7上,再用手拉葫芦14,将新回转轴承(旋转前位置)5,安装在回转体12上,并安装连接螺栓。
上述的施工过程中,步骤1大包回转台旋转前,新回转轴承“S”点15,应当在纵向铸流方向侧;通过大包回转台的自身旋转,将其调整为空载回转横向中心线上。
本更换方法从起吊开始计算到更换完成,只需约3h,与常规更换方案相比可节省大量时间,为恢复正常生产提供有力保障。同时,与常规更换方案相比,不需使用汽车吊,可大幅度降低施工成本。

Claims (2)

1.一种连铸机大包回转台回转轴承的快速更换方法;其特征是,包括
步骤1、大包回转台自身旋转,将新回转轴承放置在事故溜槽上;
步骤2、用连铸跨行车将预制好的临时支架,吊至回转台驱动侧;
步骤3、大包回转台回转轴承与底座及回转体连接螺栓拆卸,仅保留部分固定螺栓;
步骤4、采用连铸跨行车和钢水接受跨行车将回转体吊起,拆卸底座连接螺栓并吊离;
步骤5、用手拉葫芦将旧回转轴承放在临时支架上,再用手拉葫芦将新回转轴承安装在回转体上,并安装连接螺栓。
2.根据权利要求1所述的连铸机大包回转台回转轴承的快速更换方法,其特征是:步骤1中大包回转台旋转前,新回转轴承的“S”点,应当在纵向铸流方向侧;通过大包回转台的自身旋转,将其调整为空载回转横向中心线上。
CN201710521140.7A 2017-06-30 2017-06-30 一种连铸机大包回转台回转轴承的快速更换方法 Pending CN107322254A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710521140.7A CN107322254A (zh) 2017-06-30 2017-06-30 一种连铸机大包回转台回转轴承的快速更换方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710521140.7A CN107322254A (zh) 2017-06-30 2017-06-30 一种连铸机大包回转台回转轴承的快速更换方法

Publications (1)

Publication Number Publication Date
CN107322254A true CN107322254A (zh) 2017-11-07

Family

ID=60198521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710521140.7A Pending CN107322254A (zh) 2017-06-30 2017-06-30 一种连铸机大包回转台回转轴承的快速更换方法

Country Status (1)

Country Link
CN (1) CN107322254A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108500251A (zh) * 2018-06-28 2018-09-07 五冶集团上海有限公司 更换连铸机大包回转台称重臂支撑轴上滑动轴承的方法
CN109622933A (zh) * 2019-01-30 2019-04-16 上海二十冶建设有限公司 连铸机大包回转台上部设备整体抬吊更换回转轴承的方法
CN113458750A (zh) * 2020-03-30 2021-10-01 上海梅山钢铁股份有限公司 一种大包回转台回转轴承的更换方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101269462A (zh) * 2008-05-09 2008-09-24 中国第二冶金建设有限责任公司 大包回转台回转轴承快速更换方法
CN101486090A (zh) * 2009-02-20 2009-07-22 中冶实久建设有限公司南京分公司 大包回转台回转轴承拆除和更换方法
CN101486091A (zh) * 2009-02-20 2009-07-22 中冶实久建设有限公司南京分公司 上方吊装空间有限的大包回转台整体更换方法
US8464413B1 (en) * 2009-11-06 2013-06-18 Honda Motor Co., Ltd. Robot gear reducer replacing apparatus and method
CN103464737A (zh) * 2013-09-26 2013-12-25 湖北中钢联冶金工程有限公司 十字臂钢包回转台
CN104440019A (zh) * 2014-11-28 2015-03-25 东北大学 一种门机回转轴承的更换方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101269462A (zh) * 2008-05-09 2008-09-24 中国第二冶金建设有限责任公司 大包回转台回转轴承快速更换方法
CN101486090A (zh) * 2009-02-20 2009-07-22 中冶实久建设有限公司南京分公司 大包回转台回转轴承拆除和更换方法
CN101486091A (zh) * 2009-02-20 2009-07-22 中冶实久建设有限公司南京分公司 上方吊装空间有限的大包回转台整体更换方法
US8464413B1 (en) * 2009-11-06 2013-06-18 Honda Motor Co., Ltd. Robot gear reducer replacing apparatus and method
CN103464737A (zh) * 2013-09-26 2013-12-25 湖北中钢联冶金工程有限公司 十字臂钢包回转台
CN104440019A (zh) * 2014-11-28 2015-03-25 东北大学 一种门机回转轴承的更换方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108500251A (zh) * 2018-06-28 2018-09-07 五冶集团上海有限公司 更换连铸机大包回转台称重臂支撑轴上滑动轴承的方法
CN109622933A (zh) * 2019-01-30 2019-04-16 上海二十冶建设有限公司 连铸机大包回转台上部设备整体抬吊更换回转轴承的方法
CN109622933B (zh) * 2019-01-30 2021-01-19 上海二十冶建设有限公司 连铸机大包回转台上部设备整体抬吊更换回转轴承的方法
CN113458750A (zh) * 2020-03-30 2021-10-01 上海梅山钢铁股份有限公司 一种大包回转台回转轴承的更换方法

Similar Documents

Publication Publication Date Title
CN107322254A (zh) 一种连铸机大包回转台回转轴承的快速更换方法
CN102909361A (zh) 一种带称重的铁水罐倾翻装置
CN110257592A (zh) 一种两台钢水车轨道交叉的单工位rh工艺布置方法
CN110255376A (zh) 一种更换冶金桥式起重机钢丝绳的方法
CN204747073U (zh) 一种板带轧机agc液压缸更换运送装置
CN201713214U (zh) 一种钢水罐、铁水罐耳轴挡板
CN201358122Y (zh) 一种磨屑收集桶吊运装置
CN202779760U (zh) 一种铸铁机的铁水包倾翻装置
CN204737380U (zh) 可活动鞍座
CN109622932B (zh) 大型连铸钢包回转台回转轴承的快速更换方法
CN202805397U (zh) 新型悬空式脱模翻转吊具
CN211414194U (zh) 一种炉辊加工用辅助装置
CN207313637U (zh) 一种高炉炉顶布料溜槽的更换装置
CN209206877U (zh) 一种碳钢板坯连铸机大包回转台轴承更换装置
CN206011353U (zh) 耐火材料旋转浇注装置
CN206172869U (zh) 一种板坯辊道电机的更换装置
CN204724844U (zh) 一种新型倾翻车
CN206578287U (zh) 一种摆动叉指式加揭盖机
CN201866483U (zh) 一种旋转工作平台
CN205056647U (zh) 一种用于冷轧生产线的换辊装置
CN205216764U (zh) 一种混合机粘料清理装置
CN101259525A (zh) 新型大型铁水罐
CN204549893U (zh) 一种辅助起重机臂架铰支座轴承更换的起重系统
CN205347455U (zh) 一种可以快速更换渣处理转鼓分配器的专用工具
CN204018662U (zh) 用于铸铁机溅铁收集的弧形轨道渣车

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171107