CN107311015A - A kind of building hoist and its mounting platform installed downwards - Google Patents

A kind of building hoist and its mounting platform installed downwards Download PDF

Info

Publication number
CN107311015A
CN107311015A CN201710694696.6A CN201710694696A CN107311015A CN 107311015 A CN107311015 A CN 107311015A CN 201710694696 A CN201710694696 A CN 201710694696A CN 107311015 A CN107311015 A CN 107311015A
Authority
CN
China
Prior art keywords
standard knot
cage
platform
mounting platform
guide rail
Prior art date
Application number
CN201710694696.6A
Other languages
Chinese (zh)
Other versions
CN107311015B (en
Inventor
姜渭
罗涛
刘杰海
尹义民
庞科文
龙绪登
蓝王建
黄俊鸣
黄蕾
覃彤
林天德
文强
Original Assignee
广西建工集团建筑机械制造有限责任公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 广西建工集团建筑机械制造有限责任公司 filed Critical 广西建工集团建筑机械制造有限责任公司
Priority to CN201710694696.6A priority Critical patent/CN107311015B/en
Publication of CN107311015A publication Critical patent/CN107311015A/en
Application granted granted Critical
Publication of CN107311015B publication Critical patent/CN107311015B/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • B66B11/02Cages, i.e. cars
    • B66B11/0226Constructional features, e.g. walls assembly, decorative panels, comfort equipment, thermal or sound insulation
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators

Abstract

The invention provides a kind of building hoist and its mounting platform installed downwards, including mounting bracket, suspension rod, standard knot, cage, wall-attached frame and mounting platform.It is characterized in that:Mounting bracket is fixed on the ground, and first segment standard knot is fixed on mounting bracket, and each section standard knot installed backward often installs some section standard knots, wall-attached frame together is installed between standard knot and melt pit under previous section standard knot.Cage is arranged on the side of standard knot, it can be moved up and down along standard knot, hanger erection is on cage top, and mounting platform is arranged on cage and can rotated relative to cage, mounting platform is used to depositing and transferring standard knot temporarily, realizes the function that the downward supernumerary segment of building hoist is installed.Underground construction engineering is significantly facilitated, operating efficiency is improved.

Description

A kind of building hoist and its mounting platform installed downwards

Technical field

Building hoist of the present invention is a kind of construction machine, more particularly a kind of construction installed downwards Lift and its mounting platform.

Background technology

With the development of urbanization, the supply of urban land area is further tightened, an inch of land is an inch of gold, and the Ground Developing in city is The current demand for development through can not meet, the developing of the underground space turns into a general orientation of current construction industry.At present, one is built Solitary building, underground construction quantities account for 1/3rd even half quantities, particularly market place builet below the ground, get off Stand, to be related to underground construction quantities in the building course of pipe gallery and Large Underground community installations bigger.Therefore underground construction Aided Machine is indispensable.Existing building hoist is a kind of building machinery up increased from ground, typically to be waited until Underground Construction terminates that building hoist can be installed and used from bottom, it is impossible to participate in Underground Construction process, reason It is that existing building hoist can only be installed up supernumerary segment, but can not installs supernumerary segment downwards.

The content of the invention

Present disclosure is mainly to provide a kind of building hoist and its mounting platform installed downwards, and we design one Individual mounting bracket is fixed on ground, the standard knot for installing and hanging building hoist, each design one at the top and bottom of cage Window, hangs out standard knot for suspension rod and a mounting platform is designed with cage, cage, mounting platform can relative to cage To rotate, mounting platform is used to install additional interim storage and transfer standard knot during standard knot.Building hoist is fixed by mounting bracket Standard knot, mounting platform deposits and transfers standard knot temporarily, realizes the function that the downward supernumerary segment of building hoist is installed.

The technical solution used in the present invention is as follows:

A kind of building hoist and its mounting platform installed downwards, including mounting bracket, suspension rod, standard knot, cage, wall-attached frame with And mounting platform, it is characterized in that:Mounting bracket is fixed on the ground, and standard knot is made up of some sections, and first segment standard knot is fixed On mounting bracket, each section standard knot down installed often installs some section standard knots below previous section standard knot, Wall-attached frame together is installed between standard knot and melt pit;Cage is arranged on the side of standard knot and transported along above and below standard knot It is dynamic, window is designed with cage top, lower window is designed with below;Hanger erection is on cage top, and mounting platform is arranged on and hung Under cage bottom, mounting platform is rotated relative to cage.

Described mounting bracket is a kind of truss structure, is made up of column, crossbeam, longeron and intermediate beam.It is characterized in that horizontal Beam, longeron constitute a rectangle structure, and intermediate beam is located in the middle of crossbeam and parallel with longeron, column and beam vertical arrangement. Standard knot is fixedly mounted on below intermediate beam.

Described mounting platform is by bearing block, bearing, rotary shaft, otic placode, support beam, bearing pin, pull bar, web member, guide rail Beam, roller system, platform and base composition, it is characterized in that bearing block is fixedly mounted on cage, bearing is mounted in inside bearing block, Bearing connection in one end and bearing block of rotary shaft, the other end is connected with otic placode.Otic placode is connected by bearing pin with support beam.Draw One end of bar is fixed on support beam two ends, and the other end is vertically fixed on guide rail beam.Roller system is arranged in platform edges, platform dress On guide rail beam, platform is slided along guide rail beam.Web member diagonal brace is between guide rail beam and pull bar, and two guide rail beams are arranged on base Face, and two guide rail beam parallel arrangements.

Beneficial effects of the present invention are:

Compared with traditional building hoist, a kind of building hoist and its mounting platform installed downwards that the present invention is provided, Mounting bracket and mounting platform are designed with, the standard knot of building hoist is fixed by mounting bracket, mounting platform is arranged on cage And it can be rotated relative to cage, mounting platform is used to depositing and transferring standard knot temporarily, realizes that building hoist adds downwards Save the function of installing.Underground construction engineering is significantly facilitated, operating efficiency is improved.

Brief description of the drawings

Fig. 1 is the structural representation of the present invention,

Fig. 2 be Fig. 1 A to schematic diagram,

Fig. 3 is the mounting platform structural representation of the present invention,

Fig. 4 is Fig. 3 left view,

Fig. 5 is Fig. 4 partial view a enlarged diagram,

Fig. 6 is Fig. 4 partial view b enlarged diagram.

In figure:1:Mounting bracket, 1-1:Crossbeam, 1-2:Longeron, 1-3:Intermediate beam, 1-4:Column, 2:Suspension rod, 3:Ground, 4: Standard knot, 5- cages, 5-1:Upper window, 5-2:Lower window, 6:Wall-attached frame, 7:Mounting platform, 7-1:Bearing block, 7-2:Rotate Axle, 7-3:Otic placode, 7-4:Support frame, 7-5:Bearing pin, 7-6:Pull bar, 7-7:Web member, 7-8:Guide rail beam, 7-9:Roller, 7-10:It is flat Platform, 7-11:Base.

Embodiment

Below in conjunction with the accompanying drawings and case study on implementation, the present invention will be further described.

As shown in figure 1, a kind of building hoist and its mounting platform installed downwards, including mounting bracket 1, suspension rod 2, standard Section 4, cage 5, wall-attached frame 6 and mounting platform 7.It is characterized in:Mounting bracket 1 is fixed on ground 3, and standard knot 4 is that have some Section composition, first segment standard knot 4 is fixed on mounting bracket 1, and each section standard knot 4 down installed is immediately in previous section standard knot Below 4, several sections of standard knots 4 are often installed, one of wall-attached frame 6 is installed.Cage 5 is arranged on the side of standard knot 4 and can be along Standard knot 4 moves up and down, and cage 5 is designed with window 5-1 on top, and lower window 5-2 is designed with below.Suspension rod 2 is arranged on cage 5 On top, mounting platform 7 is arranged under cage 5, and mounting platform 7 can be rotated relative to cage 5.

As shown in Fig. 2 described mounting bracket 1 is a kind of truss structure, be by crossbeam 1-1, longeron 1-2, intermediate beam 1-3 and Column 1-4 is constituted.It is characterized in that crossbeam 1-1, longeron 1-2 constitute a rectangle structure, intermediate beam 1-3 is located in crossbeam 1-1 Between and it is parallel with longeron 1-2, column 1-4 is arranged vertically with crossbeam 1-1.Standard knot 4 is fixedly mounted on below intermediate beam 1-3.It is attached Wall stand 6 is arranged between standard knot 4 and melt pit.

Described cage 5, it is similar with the common cage structure in industry, unlike, cage of the present invention is except opening on top There is upper window 5-1, have lower window 5-2 in bottom design.

As seen in figures 3-6, described mounting platform 7 be by bearing block 7-1, bearing 7-12, rotary shaft 7-2, otic placode 7-3, Support beam 7-4, bearing pin 7-5, pull bar 7-6, web member 7-7, guide rail beam 7-8, roller system 7-9, platform 7-10 and base 7-11 groups Into.It is characterized in that bearing block 7-1 is fixedly mounted on cage 5, bearing 7-12 is inside bearing block 7-1, the one of rotary shaft 7-2 End is connected with bearing 7-12, and the other end is connected with otic placode 7-3.Otic placode 7-3 is connected by bearing pin 7-5 with support beam 7-4.Pull bar 7- 6 one end is fixed on support beam 7-4 two ends, and the other end is vertically fixed on guide rail beam 7-8.Roller system 7-9 is arranged on platform 7- On 10 sides, platform 7-10 is on guide rail beam 7-8, and platform 7-10 can be slided along guide rail beam 7-8.Web member 7-7 diagonal braces are in guide rail Between beam 7-8 and pull bar 7-6, two guide rail beam 7-8 are arranged on above base 7-11 and two guide rail beam 7-8 are parallel cloth Put.

Described wall-attached frame 6 and described suspension rod 2, it is structurally and functionally known components in industry, no longer detailed herein State.

A kind of downward building hoist and its mounting platform that the present invention is provided, when needing to install standard knot 4 additional downwards, Standard knot 4 mounted in the inside of cage 5 on ground 3, when standard knot 4 is transported to position to be installed by cage 5, suspension rod 2 is slinger Tool puts the inside of cage 5 into from upper window 5-1, and lifting device bundlees standard knot 4 and lift, is put into by lower window 5-2 Mounting platform 7, takes off after lifting device, rotates 180 ° of mounting platforms 7, by micro-shifting platform 7-10, standard knot 4 is directed at upper one Save below standard knot 4, the two section dockings of standard knot 4 are got up, so as to realize the function of installing standard knot 4 additional downwards.

Claims (3)

1. a kind of building hoist and its mounting platform installed downwards, including mounting bracket(1), suspension rod(2), standard knot(4), hang Cage(5), wall-attached frame(6)And mounting platform(7), it is characterized in that:Mounting bracket(1)It is fixed on ground(3)On, standard knot(4)It is It is made up of some sections, first segment standard knot(4)It is fixed on mounting bracket(1)On, each section standard knot down installed(4)Immediately in Previous section standard knot(4)Below, some section standard knots are often installed, in standard knot(4)Wall-attached frame together is installed between melt pit (6);Cage(5)Installed in standard knot(4)Side and along standard knot(4)Move up and down, cage(5)It is designed with top Window(5-1), lower window is designed with below(5-2);Suspension rod(2)Installed in cage(5)On top, mounting platform(7)Installed in hanging Cage(5)It is beneath, mounting platform(7)Relative to cage(5)Rotate.
2. the building hoist and its mounting platform according to claim 1 installed downwards, it is characterized in that:Described installation Frame(1)It is a kind of truss structure, is by crossbeam(1-1), longeron(1-2), intermediate beam(1-3)And column(1-4)Composition;Crossbeam (1-1), longeron(1-2)Constitute a rectangle structure, intermediate beam(1-3)Positioned at crossbeam(1-1)Middle and and longeron(1-2)It is flat OK, column(1-4)With crossbeam(1-1)It is arranged vertically;Standard knot(4)It is fixedly mounted on intermediate beam(1-3)Below.
3. the building hoist and its mounting platform according to claim 1 installed downwards, it is characterized in that:Described installation Platform(7)It is by bearing block(7-1), bearing(7-12), rotary shaft(7-2), otic placode(7-3), support beam(7-4), bearing pin(7- 5), pull bar(7-6), web member(7-7), guide rail beam(7-8), roller system(7-9), platform(7-10)And base(7-11)Composition; Bearing block(7-1)It is fixedly mounted on cage(5)On, bearing(7-12)Mounted in bearing block(7-1)The inside, rotary shaft(7-2)One End and bearing(7-12)Connection, the other end and otic placode(7-3)Connection, otic placode(7-3)Pass through bearing pin (7-5) and support beam (7-4) Connection, one end of pull bar (7-6) is fixed on support beam (7-4) two ends, and the other end is vertically fixed on guide rail beam (7-8), roller It is that (7-9) is arranged on platform (7-10) side, platform (7-10) is on the guide rail beam (7-8), and platform (7-10) is along guide rail beam (7- 8) slide, web member (7-7) diagonal brace is between guide rail beam (7-8) and pull bar (7-6), and two guide rail beams (7-8) are arranged on base (7- 11) above and two guide rail beams (7-8) be parallel arrangement.
CN201710694696.6A 2017-08-15 2017-08-15 Construction elevator installed downwards and installation platform thereof CN107311015B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710694696.6A CN107311015B (en) 2017-08-15 2017-08-15 Construction elevator installed downwards and installation platform thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710694696.6A CN107311015B (en) 2017-08-15 2017-08-15 Construction elevator installed downwards and installation platform thereof

Publications (2)

Publication Number Publication Date
CN107311015A true CN107311015A (en) 2017-11-03
CN107311015B CN107311015B (en) 2020-05-19

Family

ID=60176778

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710694696.6A CN107311015B (en) 2017-08-15 2017-08-15 Construction elevator installed downwards and installation platform thereof

Country Status (1)

Country Link
CN (1) CN107311015B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040240622A1 (en) * 2003-05-30 2004-12-02 Eastman Kodak Company Radiographic imaging assembly for mammography
CN201080399Y (en) * 2007-05-30 2008-07-02 广州市京龙工程机械有限公司 Inverse type mounting construction hoist
CN201826525U (en) * 2010-07-27 2011-05-11 南京道广建筑模板有限公司 Climbing shuttering system device for buildings
CN205709343U (en) * 2016-06-24 2016-11-23 山西省工程机械厂 The inverse dress special building hoist of moldeed depth foundation ditch
CN106348133A (en) * 2016-11-18 2017-01-25 天津京龙工程机械有限公司 Underground elevator with slidable standard knots

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040240622A1 (en) * 2003-05-30 2004-12-02 Eastman Kodak Company Radiographic imaging assembly for mammography
CN201080399Y (en) * 2007-05-30 2008-07-02 广州市京龙工程机械有限公司 Inverse type mounting construction hoist
CN201826525U (en) * 2010-07-27 2011-05-11 南京道广建筑模板有限公司 Climbing shuttering system device for buildings
CN205709343U (en) * 2016-06-24 2016-11-23 山西省工程机械厂 The inverse dress special building hoist of moldeed depth foundation ditch
CN106348133A (en) * 2016-11-18 2017-01-25 天津京龙工程机械有限公司 Underground elevator with slidable standard knots

Also Published As

Publication number Publication date
CN107311015B (en) 2020-05-19

Similar Documents

Publication Publication Date Title
CN101284628B (en) Hoisting method for framework of large tonnage pressing machine
CN105604334A (en) Rapid-construction method used for overall installation of large-span steel truss
CN203373664U (en) Foldable rear supporting leg of tunnel-through bridge girder erection machine
CN103072900B (en) Loading frame dual-purpose vehicle under coal mine
CN102587645A (en) Climbing supporting mechanism having expansion and automatic meshing functions, and construction method thereof
CN104499417A (en) Gravity self-balance type emergency rehabilitation rapid self-erection bridge
CN103669211B (en) Hydraulic multi-function cantilever lifting beam machine and steel box girder assembling method
CN103510864B (en) One kind three saves hydraulically extensible suit derrick
CN103422662B (en) The integral movable type operation platform cast-in-place for elevator shaft and using method thereof
CN206341631U (en) One kind suspension vertical greening device
CN103276907B (en) Hoisting method for large-span hinged type herringbone steel arch
CN202544854U (en) Lining trolley for subway station
CN205892579U (en) Fast set up tower crane's counter weight mechanism
CN205777428U (en) Elevator is from climbing platforms
CN103556627B (en) A kind of hanging cage structure for large diameter bored pile reinforcing bar cage hoisting
CN203625889U (en) Hanging cage structure for large-diameter hole drilling cast pile reinforcement cage hanging
CN103306371B (en) Assembled-type house PC prefabricated units fabrication and installation structure
CN105433855B (en) Frame-type multifunctional stretches window cleaning equipment
CN203237956U (en) Tower crane with trailer pump
CN201793330U (en) Gantry hanger frame device
CN104674665A (en) Installation method for corridor bridge of large space steel structure
CN204675726U (en) Purlin lifting auxiliary device
CN204877118U (en) Fire exit door's mounting structure
CN204689646U (en) A kind of submersible water impeller system
CN105672641A (en) Double-guide-frame multi-stage synchronous lifting working platform and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant